Upload
maddysggs
View
215
Download
0
Embed Size (px)
Citation preview
8/8/2019 Rwps Downloads
1/54
Rylstone WS R iver Pumping Station
Concept Design Report
Prepared for Mid-Western Regional Council
Report No. WSR 09022A (Final Draft)September 2009
8/8/2019 Rwps Downloads
2/54
Forward
This document has been prepared by the NSW Public Works for Mid-Western Regional
Council. Public Works acknowledges the assistance provided by the staff of Mid-WesternRegional Council. Especially, the assistance of Brett Corven, Carrie Hooper, Steve Hanthorn,Scott Jackson and Peter Dunn in providing information pertinent to the preparation of thisreport is greatly appreciated.
NSW Water Solutions Project Team members involved in this investigation were:
Dayan Gunasekera
Ken Kay
Vu Dao
Abdur Razzak
George Fuller
Sisitha Pathirana
Nicholas Kaparos
Document History
Version Date Issued
Draft 11th September 2009
Final Draft 20th September 2009
Final To be issued
Contact: Kamal FernandoT 02 9372 7869F 02 9372 7877E [email protected]
8/8/2019 Rwps Downloads
3/54
8/8/2019 Rwps Downloads
4/54
Pumping Station Building
The pumpwell would be enclosed in a building (13m x 7m) which would consist of two rooms,i.e. Switch Room and PAC Room. The Switch Room would be directly above the pumpwelland would accommodate the electrical and telemetry switch gear assembly. The Switch Roomalso provides the access to the pumpwell and supports the monorail. The existing PAC plant
at the WTP site would be relocated in the PAC room. The Switch Room would have two doors(1.2m and 2-3m wide) while the PAC room would have a GI mesh front with a door made ofsimilar material. The building would be a brick building on reinforced concrete floor supportedon concrete piers founded on the bedrock.
System Hydraulics and Operation
In order to minimise the depth of the pumpwell, the suction main and the trunnion arm(except the trunnion & the pipe through the damwall) would be DN 300. The delivery mainwould be DN250.
For efficient and flexible operation, the pump would be provided with variable speed drives. Apressure sustaining valve would also be provided at the end of the rising main near the
treatment plant.
Trunnion
The trunnion, if made of stainless steel, would last more than 70 years. If made in mild steel(epoxy coated after fabrication) it would last about 50 years. Without designing and preparingshop drawings, the price of the trunnion cannot be estimated/obtained. The supply cost ofstainless steel is generally 3-4 times higher than mild steel, however, with the labour involvedin fabrication and the epoxy coating, the overall price difference between the two is notexpected to be significant.
It is recommended to include a mild steel trunnion in the tender as a conforming bid with analterative tender price invited for a stainless steel trunnion.
The trunnion arm would be made of epoxy coated mild steel.
Pipelines
Due to the rocky condition and the high overburden (3-4m backfill), rubber ring jointedcement lined ductile iron (DICL) pipes are recommended on a well-graded bedding. For thesuction main, rock excavation is anticipated for about 70% of its excavation volume.However, a lesser quantity of rock excavation is expected for the delivery main (~25%). Bothpipelines will be buried except the first 10m length of the suction main which will besupported on concrete piers founded on the bedrock.
The pipelines would be connected to the existing lines with Tees enabling the use of the
existing system during construction and afterward.
Electrical and Telemetry
The existing transformer (100 kVA) would be sufficient for the new pumps and the PAC plant.It is proposed to provide a new 100kVA transformer on a new pole near the new pumpingstation. The existing transformer and the associated overhead powerlines would be removedonce the existing system is de-commissioned. Underground power and communication cablesshould be laid from the new pump station to the dam.
The pumps would be automatically controlled depending on the requirements of the WTP. Inaddition to pump controls, necessary monitoring, alarms and warnings signals would beprovided to the treatment plant control centre via telemetry. A lightening protection system
would also be provided.
8/8/2019 Rwps Downloads
5/54
Environmental aspects
The proposed pipeline alignment is not expected to disturb much vegetation, especiallymature trees. As such, for the purpose of the concept design there are no real constraints toconsider. It is recommended, however, that vegetation removal be kept to a minimum and nomature eucalypts be removed during the construction. The pipeline alignments have beenselected avoiding these trees.
There are no evident Aboriginal cultural heritage constraints to the project.
Cost Estimation
The estimated capital cost for the pumping station and associated works is $0.94M. Theanticipated annual O&M cost (excluding replacement cost) is $31,000/year.
Testing and commissioningThe existing raw water supply needs to be interrupted at various times for connections of thenew system to the existing infrastructure. It will be necessary to maintain the supply duringthe period of construction and installation of the new system. It is therefore considered thatthe connection and installation should be carried out in a manner which will allow for achange over before the old system is de-commissioned.
____ . ____
8/8/2019 Rwps Downloads
6/54
Rylstone Water Supply NSW Water SolutionsRiver Pumping Station Concept Design NSW Public Works
d:\rylstone\intake\final draft report\rylstone rps - concept report ( finaldraft).doc i
Table of Contents
Forward i
Executive Summ ary ii
Table of Content s i
1 Introduction 3 1.1 Project Background 31.2 Existing Raw Water Pumping Station 31.3 Proposed Pumping Station 31.4 Concept Design 41.5 Report Structure 4
2
Proposed pumping Station 5
2.1 Infrastructure components 52.2 Pumpwell 5
2.2.1 Location 52.2.2 Dimensions 52.2.3 Type of well 82.2.4 Constructability 82.2.5 Pumping Machinery 8
2.3 Pumping Station Building 112.4 Pits for valves and PAC injection 122.5 Electrical works 12
2.5.1 Electrical works 12
2.5.2
Telemetry 122.5.3 Power supply to site 13
3 Hydraulic Analysis 14 3.1 Size of trunnion and pipelines 143.2 Operational aspects 143.3 Pump duties and system characteristics 15
4 Pipelines 17 4.1 Suction Pipeline 174.2 Delivery Pipeline 184.3 Trunnion 18
5 Miscellaneous 20 5.1 Environmental assessment 20
5.1.1 Ecological Issues 205.1.2 Aboriginal Cultural Assessment 205.1.3 Consultation 20
5.2 Temporary water supply 205.2.1 Testing and commissioning of pumps 215.2.2 Access to the Pumping Station 21
6 Cost estimates 22 6.1 Capital Cost 226.2 Operation and Maintenance Costs 22
8/8/2019 Rwps Downloads
7/54
Rylstone Water Supply NSW Water SolutionsRiver Pumping Station Concept Design NSW Public Works
d:\rylstone\intake\final draft report\rylstone rps - concept report ( finaldraft).doc ii
7 Conclusion & Recommendation 24
8 Reference 25
Appendices
Appendix 1: Preliminary Geotechnical Assessment
Appendix 2: Capital and O&M Cost Estimates
Figures
Figure 1: Proposed Pumping Station and Pipelines Concept Layout 6
Figure 2: Ground Profile across Pumpwell 7
Figure 3: Proposed Pump Installation Arrangement 9
Figure 4: Pumpwell Plan & Sectional Elevation (4m well) 10
Figure 5: Pumping Station Building Layout Plan 11
Figure 6: Hydraulic Grade Lines for 67 L/s & reduced flows. 15
Figure 7: System characteristics and a typical pump curve 16
Figure 8: Connection of new suction pipeline to existing pipe 17
Figure 9: Long Section of Suction Pipeline 17
Figure 10: Long Section of Delivery Pipeline 18
Tables
Table 1: Cost estimates for the pumping station and associated works 22
Table 2: Annual Operation & Maintenance Cost for the pumping station 23
8/8/2019 Rwps Downloads
8/54
Rylstone Water Supply NSW Water SolutionsRiver Pumping Station Concept Design NSW Public Works
d:\rylstone\intake\final draft report\rylstone rps - concept report ( finaldraft).doc 3
1 Introduction
1.1 Project BackgroundThe Rylstone water supply system currently provides potable water to Rylstone, Kandos,Charbon and Clandulla villages.
Mid-Western Regional Council (MWRC) engaged the NSW Public Works to carry out aninvestigation of the Rylstone water supply system. The investigation included a detailedreview of major infrastructure components of the system and an assessment of upgradesnecessary for the future demands.
Provision of a new raw water pumping station for the Rylstone water supply system is one ofthe priority augmentation works recommended in this strategy study.
1.2 Existing Raw Water Pumping StationThe existing raw water pump station draws water from the Rylstone Dam which is located onthe Cudgegong River. The pump station is located approximately 35m downstream of thedam by the side of the Cudgegong River. The suction pipeline which runs through the damwall to the pump station consists of a trunnion enabling drawing off water just below thewater surface. The dam and the pump station were constructed in the early 1950s and havebeen in operation since then.
Prevailing issues with the existing intake include: (a) an inability to draw water below RL577m level (30% unusable storage), (b) high head losses through the suction main; (c)
splash flooding of the pumping station during spilling of the dam; (d) aging of the pumps andthe pumping station; (d) poor condition of the trunnion; and (e) insufficient pumping capacityto meet the future demand.
1.3 Proposed Pumping StationThe recommended augmentation works for the Rylstone intake are as follows.
- A dry pump well accommodating pumping units (one duty/one standby);
- A building to accommodate: (a) electrical switchgear and other instrumentsassociated with pump operation and (b) the PAC plant which is currently at thetreatment plant;
- A new suction pipeline from the dam to the pumpwell;
- A new delivery pipeline from the pumpwell to the existing rising main;
- A new trunnion (replacement);
- Pits for valves and PAC injection;
- Electrical and telemetry works; and
- Associated minor works for the proper completion and operation of the system.
8/8/2019 Rwps Downloads
9/54
Rylstone Water Supply NSW Water SolutionsRiver Pumping Station Concept Design NSW Public Works
d:\rylstone\intake\final draft report\rylstone rps - concept report ( finaldraft).doc 4
1.4 Concept DesignMWRC engaged the NSW Public Works to undertake a concept and detailed designs including
tender documentation for the proposed pumping station. Specific tasks required to be carriedout at the concept stage included the following.
1. Engineering survey, geotechnical investigation and environmental assessment;
2. Concept design of the pump well (location, diameter, bottom floor level, top level)including constructability (rock excavation, stability, type of pump well material etc.);
3. Finalisation of the hydraulic analysis to determine the pump duties, sizes of trunnion armand suction/delivery pipelines, pipework configuration within the well and operationalcontrol requirements;
4. Concept design of the suction and delivery pipelines including alignment, depth, rock
excavation, constructability etc.;
5. Design methodology of the trunnion including type of material;
6. Adequacy of the power supply requirements; and
7. Identification of any environmental issues related to the above works.
1.5 Report StructureThe report structure is as follows.
Chapter Contents
1 Project background and concept design tasks
2 Concept design of the pumpwell and the building including location selection,type, size and constructability of the well and geotechnical aspects
3 Hydraulic analysis including sizing of the trunnion, suction/delivery pipelinesand pumps including operational aspects
4 Pipelines and trunnion including material types, alignments, geotechnicalaspects, connection to the existing pipes and constructability
5 Miscellaneous information such as environmental issues, temporary watersupply during construction, testing and commissioning
6 Capital and O&M cost estimates
7 Conclusion followed by References and Appendices
8/8/2019 Rwps Downloads
10/54
Rylstone Water Supply NSW Water SolutionsRiver Pumping Station Concept Design NSW Public Works
d:\rylstone\intake\final draft report\rylstone rps - concept report ( finaldraft).doc 5
2 Proposed pumping Station
2.1 Infrastructure componentsThe main civil infrastructure associated with the pumping station are:
-A dry well to accommodate pumps (pumpwell);
-A building to accommodate electrical switch gear assembly, other control units and a PACplant;
-Pits for valves and PAC injection;
The trunnion and suction/delivery pipelines are discussed in Chapter 4.
2.2 Pumpwell2.2.1 Location
An approximate location of the pumpwell was identified during a joint site inspection carriedout at the inception meeting. The final location of the well was determined taking intoconsideration the topography, slope of the bank, depth to bedrock, environmental aspects,suction main invert level, flood levels and other constraints such as an overhead power line.
It was not possible to locate the well 10m away from the powerline due the steepness of theslope. Therefore it was decided to re-locate the powerline to suit the well and the building. Anew transformer would be installed on a new pole closer to the new pumping station. Theexisting transformer including the power line would be removed after commissioning of the
new pumping station. The proposed location of the well and the new power pole are shown inFigure 1.
2.2.2 DimensionsGeotechnical investigation results show that the bedrock is of very high strength andtherefore rock excavation would be very costly. The size of the pumpwell has therefore beensized as small as possible to minimise the cost of construction.
In order to reduce the size and provide clear space as much as possible within the well, theinlet (suction) bifurcation has been made outside of the well. It is envisaged that thisarrangement would be suitable because of the method of rock excavation/removal. The
discharge isolation valves and non return valves have been arranged in a separate valve pitoutside the pump well to once again to provide clear space in the well.
The minimum size of the well which could accommodate the above pumps would be 3.6m,however a 4m diameter well is recommended considering other issues such as access,working space etc. This is further discussed in section 2.2.3 to 2.2.5.
The bottom level of the well should suit the invert level of the incoming suction pipeline andthe depth required for the pump installation. Allowing a gradient equivalent to the headlossand another 0.5m for the pump installation, the floor level of the well was selected as RL570.0 m.
The top level of the well was selected as RL 575.5m which is 2.2m above the 100 year flood
level. A cross section of the pumpwell showing the profile of the bedrock is given in Figure 2.
8/8/2019 Rwps Downloads
11/54
Suction Main
Connection to
the existing pipe
35m
New power pole
& transformer
Pumpwell
NRV Pit
0 5m 10m
Figure 1
Dam Wall
Existing Pumping StationExisting Suction Pipeline
Pumping
station building
Proposed Works are
shown in red
Indicative alignment for the
access road is shown in green
8/8/2019 Rwps Downloads
12/54
8/8/2019 Rwps Downloads
13/54
Rylstone Water Supply NSW Water SolutionsRiver Pumping Station Concept Design NSW Public Works
d:\rylstone\intake\final draft report\rylstone rps - concept report ( finaldraft).doc 8
2.2.3 Type of wellThe well could be constructed either in-situ or with pre-cast concrete cylinders. Pre-castmethod is generally cheaper in excavatable materials, if sunk as a caisson, than cast-in-situ
construction especially for smaller diameters. Because of the anticipated rock, an open cutexcavation would be required which lends itself to cast-in-situ construction. The otheradvantage of a cast-in-situ well is that it would be a monolithic construction unlike the pre-cast concrete wells which have joints between each cylinder (i.e. at 1.22m spacing). On theother hand, the available largest pre-cast concrete cylinder size is 3.6m.
It is recommended to design a 4m diameter cast-in-situ well, however, an alternative tenderprice for a pre-cast concrete well of 3.6m diameter should also be invited. If the alternativetender price (3.6m pre-cast well) is significantly less than the conforming tender (4m cast in-situ well), it would be worth re-considering a 3.6m well.
2.2.4 ConstructabilityThe major constraint in the construction of the well would be the excavation of rock whichwould be encountered at a depth of around 0.5m. The rock has a yield strength of 110 -130MPa requiring blasting. Because the site is on close proximity to the dam blasting would notbe allowed except pre-splitting which is a slow process. Excavation works, if carried out bypre-splitting the rock, would take 3-4 weeks as it has to be done stage by stage.
It may be possible to excavate vertically without shoring, however, it should be carried outafter a thorough examination of rock characteristics and on advice from geotechnical experts.
Vertical excavation would enable construction of the well either in-situ or with pre-cast units.
The access to the well during construction may be from the trench excavated for the suctionmain. Accordingly, the excavation near the suction main entry point to the well would be
larger than the normal pipeline trench enabling installation of the bifurcation pipework outsidethe well.
2.2.5 Pumping MachineryVertically mounted axially split centrifugal pumps (one duty/one standby) each with a duty of67 L/s at 23 m are recommended for the Rylstone river pumping station. These pumps havean efficiency around 80-83%.
The pump installation arrangement is shown in Figure 3. As shown in the figure, the pumpswould be installed with thrust bearing dismantling joints on the discharge side, to assist pumpremoval.
By using standard joints for pumping machinery to deliver 67 L/s larger pumps can beinstalled for 85 L/s by substituting these with short bodied thrust bearing dismantling joints, ifrequired, in the future.
The plinth height to 67 L/s pumps and pipework centre height will also allow for theinstallation of larger pumps for flow rates up to 85 L/s.
As discussed before, the non return valves would be installed outside the pumpwell tomaximise the space within the well. The two delivery pipes from the pumps would come upthrough the wall and then under the building. Each pipeline will have a non return valve andan isolation valve on either side prior joining together. The PAC injection point would be onthe common main.
8/8/2019 Rwps Downloads
14/54
Rylstone Water Supply NSW Water SolutionsRiver Pumping Station Concept Design NSW Public Works
d:\rylstone\intake\final draft report\rylstone rps - concept report ( finaldraft).doc 9
The pump motors are air cooled and do not require mechanical ventilation. However, forOH&S reasons, an air ventilation system (a duct consisting of a blower or fan) would be
provided.
Figure 3: Proposed Pump Installation Arrangement
A sump will be provided within the well with a submersible dewatering pump. A level censor
will also be provided in the sump to give warning if flooding occurs inside the well. In case ofemergency, the isolation valve on the suction main near the dam could be closed if theisolation valves in the pump well cannot be reached.
The operational aspects of the pumps are discussed in Section 3.2. A typical cross section ofthe pumpwell is shown in Figure 4.
8/8/2019 Rwps Downloads
15/54
Rylstone Water Supply NSW Water SolutionsRiver Pumping Station Concept Design NSW Public Works
d:\rylstone\intake\final draft report\rylstone rps - concept report ( finaldraft).doc 10
Figure 4: Pumpw ell Plan & Sectional Elevation (4m well)
8/8/2019 Rwps Downloads
16/54
Rylstone Water Supply NSW Water SolutionsRiver Pumping Station Concept Design NSW Public Works
d:\rylstone\intake\final draft report\rylstone rps - concept report ( finaldraft).doc 11
2.3 Pumping Station BuildingThe pumping station building would be above the pumpwell enclosing the well within the
building. The building would consist of two rooms. The room directly above the pumpwell(Switch Room) would accommodate the electrical switchgear for the pumps, telemetrycontrol, monorail etc.. The other room (PAC Room) would accommodate the PAC plantwhich is currently at the treatment plant. The layout plan of the building is shown in Figure 5.
Figure 5: Pumping Station Building Layout Plan
The building would be a brick building with a steel portal framed structure on a reinforcedconcrete foundation. The walls would be single brick. The foundation would be a concreteslab and beam arrangement supported on concrete piers founded on bedrock. The pier heightwould vary from 0.5m to 2m and would be anchored to the bedrock using dowel bars. Thefoundation (slab, beams and piers) would be a monolithic structure including the pumpwell.The building would have a single pitched roof made of metal sheet cladding.
The switch room would have two exits i.e. a 1.2m wide door on the southern side (facing theexisting access to the dam) and a 2-3m wide door on the eastern side (facing the dam).
Vehicular access would be provided to both these sides as shown in Figure 1. The PACbuilding would consist of brick walls except the front (southern side) which would be a 25mmgalvanised steelmesh and a door of similar material.
A monorail would be provided for the pumps. The monorail would be extended outside thebuilding through the 3m wide door for about 2m length. The monorail would be hung to across girder which is fixed to the portal frame.
Other necessary features in the building would include handrails around the pumpwell, accessladder to the well with removable ladder entry rail, a davit, ventilation system, switchgearassembly and PLC.
70005500
7000
PAC ROOM
SWITCH
ROOM
SCA
PUMPWELL
Retaining wall
for access road
Davit
Mono Rail
Door
Door
25mm GI mesh & sliding door
Access towell
Service
lines
1200
1200
12001200
8/8/2019 Rwps Downloads
17/54
Rylstone Water Supply NSW Water SolutionsRiver Pumping Station Concept Design NSW Public Works
d:\rylstone\intake\final draft report\rylstone rps - concept report ( finaldraft).doc 12
2.4 Pits for valves and PAC injectionNon return valves and isolation valves would be on individual delivery mains from each pump
whereas the PAC injection would be on the common line.
Reinforced concrete pits will be provided for the non return valves (NRV) and PAC injectionpit. The pits will be covered with aluminium gratings. The pit for the NRVs would be commonto both pipelines.
Installation of a new magflow meter near the pumping station is not considered as there is anexisting magflow meter on the rising main near the treatment plant. It is envisaged that lowPAC dosages would not affect the magflow metering performance.
2.5 Electrical works2.5.1 Electrical work s
Main components of the electrical works would include:
- New consumers main from the proposed pole-mounted transformer to the newswitchboard in the pump station building.
- Metering Enclosure (Meter Box);
- Main Switchboard indoor type, Form 3b. This Switchboard will contain a mainswitch, motor starters, feeder for PAC Switchboard, Telemetry compartment, feederfor supplying power to existing Dam equipment, and other essential components;
- Cables and cable supports;
- A lightening protection system; and
- Building services lighting and general purpose power outlets.
A performance based technical specification (clauses) will be prepared for design, supply,installation, testing, demonstration and commissioning of all electrical components. Severalstandard (typical) drawings will be included as part of the specification, however, detaileddesign drawings and related documents would be prepared by the Contractor.
It is assumed that the Council will relocate the existing PAC system including the electrical
switchboard from its present location to the new pump station site. Necessary clauses forprovision of power supply to the PAC electrical switchboard/control panel from the mainswitchboard will be included in the technical specification.
2.5.2 TelemetryIt is understood that the existing ROMTECK telemetry system will be replaced with SERCKControl Telemetry system.
Main telemetry components would include:
- Telemetry RTU;
- Antenna;
- Modification of existing SCADA, if required.
8/8/2019 Rwps Downloads
18/54
Rylstone Water Supply NSW Water SolutionsRiver Pumping Station Concept Design NSW Public Works
d:\rylstone\intake\final draft report\rylstone rps - concept report ( finaldraft).doc 13
The Serck Telemetry RTU will be used for automatic control and remote monitoring of pumpstation.
A list of input and output signals will included in the technical specification for automaticcontrol and remote monitoring via existing telemetry system.
A performance based technical specification (clauses) will be prepared for a Design andConstruct (D&C) type contract for design, supply, installation, testing, demonstration andcommissioning of the telemetry system at the pump station.
2.5.3 Pow er supply to siteIntegral Energy advise that the existing pole-mounted transformer is 100kVA rated. Thiscapacity would be sufficient for the power supply to the new pumping station, to the PACsystem (relocated) and to the existing equipment at the Dam.
It is understood that MWRC would liaise with Integral Energy and provide a new transformeron a new pole located closer to the new pumping station (refer to Figure 1 for the proposedlocation for the transformer).
8/8/2019 Rwps Downloads
19/54
Rylstone Water Supply NSW Water SolutionsRiver Pumping Station Concept Design NSW Public Works
d:\rylstone\intake\final draft report\rylstone rps - concept report ( finaldraft).doc 14
3 Hydraulic Analysis
Hydraulic analyses were carried out to determine the size of the trunnion, trunnion arm,suction and delivery pipelines, pump duties and the operational control of the pump.
3.1 Size of trunnion and pipelinesThe required flow rate in the year 2031 would be 67 L/s. However, considering the demandbeyond 2031, it was agreed with MWRC that the pipeline and the trunnion be designed for afurther 25% increase in flow i.e. 85 L/s.
The head loss for a flow 85 L/s through a DN250 pipeline would be about 15m/km (includinglosses through specials). This would be equivalent to a loss of 1.5m through the suction
pipeline, requiring the pump well floor to be at RL 569m. If a DN300 pipeline is selected, thepumpwell could be raised by about 1 metre (headloss is 5m/km). Velocity through the DN300pipe for 67 L/s is 0.9 m/s and would not cause any siltation.
Additional cost of increasing the diameter would be approximately $8,500 whereas theincrease in the cost of the pumpwell due to additional rock excavation and the height wouldbe over $20,000. Therefore DN300 is recommended for the suction pipeline.
Additional 1m headloss is not critical for the rising main and therefore DN250 pipeline isrecommended for the delivery line (note that the existing rising main is also DN250).
The size of the trunnion cannot be increased due to installation problems, however, thetrunnion arm may be increased to DN300 which would reduce the headloss further.
Final design data:
Trunnion arm - DN300
Trunnion - DN250
Suction pipeline - DN300
Delivery pipeline - DN250
3.2 Operational aspectsWith the pumping station sited at the recommended location the characteristics for thepumping machinery have been determined with a detailed hydraulic analysis. This will berevised, if necessary, during the design phase to take into account any changes which mayfound necessary.
The dam level varies between RL 572m to RL 580m. In order to deliver a constant flow rate of67 L/s it is proposed that the pumping machinery is controlled by variable speed drives. Thisis the most efficient means of delivering the flow required.
This form of control will also allow for a reduced flow delivery and therefore longer plant runtimes in non-peak periods, which is desirable for stable operation.
The rising main delivers water to the WTP at a level of RL 576.6m. However the rising main
route is over a hill of RL 588m and a further rise at RL 585m.
8/8/2019 Rwps Downloads
20/54
Rylstone Water Supply NSW Water SolutionsRiver Pumping Station Concept Design NSW Public Works
d:\rylstone\intake\final draft report\rylstone rps - concept report ( finaldraft).doc 15
HGL - Reservoir @ MOL
586.49
576.6
571
583
585
571.6
580.7
588.3
581.6
576.6
588.7
572.31572.6
589.18589.48
590.01590.42590.9
590.72
587.79588.59
590.04
591.14592.45
591.98
572.6
571.82
570
575
580
585
590
595
0 100 200 300 400 500 600 700 800 900 1000
Distance (m)
Hight/Head(m)
Ground Profile HGL @ 39 l/s HGL @ 65 l/s
Because of the pipe size and flowrate the water will flow under gravity from the RL 588mlevel. The gravity flow under these conditions may cause some sections to not run full and todrain when the pump stops. This can cause some turbulence because of air and water mixing,producing a form of hydraulic obstruction and random intermittent variations in flow.
Maintaining a full pipeline is the best hydraulic operation.
In order to overcome these possible problems it is considered that an artificial head should beinduced at the end of the pipeline with a pressure sustaining valve (PSV). This will maintain afull pipe and provide the optimum hydraulic conditions. It is proposed to install the PSV u/s ofthe existing magflow near the WTP. This is mainly considering any possible modification tothe inlet pipework which may be required as part of the proposed improvements to the WTP.
The pressure sustaining valve could be fitted with two control pilots which would be set to suitthe flow rates with either manual or automatic selection. The hydraulic gradelines are shownin Figure 6.
Figure 6: Hydraulic Grade Lines for 67 L/ s & reduced flows.
3.3 Pump duties and system characteristicsThe type of pumps suitable for this type of drywell arrangement are axially split centrifugalpumps. These pumps could be expected to have an efficiency in the order of 80% plus. Tomaximise the space within the well, the pump motor could be installed in a verticalconfiguration. The duty and operating range of the pump is 67 L/s @ 23m and 39 L/s @11m.For low flow rates the pump would run at a lower speed but almost at the same efficiency.
The system characteristics and a typical pump curve are given in Figure 7.
8/8/2019 Rwps Downloads
21/54
Rylstone Water Supply NSW Water SolutionsRiver Pumping Station Concept Design NSW Public Works
d:\rylstone\intake\final draft report\rylstone rps - concept report ( finaldraft).doc 16
Figure 7: System characteristics and a typical pump curve
Rylstone Proposed Raw Water Intake
0
5
10
15
20
25
30
35
40
45
50
55
60
0 10 20 30 40 50 60 70 80 90 100
Flow (L/s)
Head(m)
-35
-15
5
25
45
65
85
Efficiency(%)
Sys Curve (FSL) Sys Curve (MOL) Eta Omega 125-290 B (288) % Curve
8/8/2019 Rwps Downloads
22/54
Rylstone Water Supply NSW Water SolutionsRiver Pumping Station Concept Design NSW Public Works
d:\rylstone\intake\final draft report\rylstone rps - concept report ( finaldraft).doc 17
Suction Pipeline - Long Section
565
570
575
580
0 20 40 60 80 100 120Chainage (m)
RL(m)
Ground Level
Likley bedrock
Pipe Invert Level
4 Pipelines
4.1 Suction PipelineThe new suction pipeline from the dam to the pumpwell is 104m long. Considering the rockycondition of the site and the 3-4m backfill over the pipe, ductile iron pipes (rubber ring jointcement lined) are recommended on a well graded bedding. The new suction will be connectedto the existing pipeline at the dam wall with an angle branch and isolation valve as shown inFigure 8.
Figure 8: Connection of new suction pipeline to existing pipe
The alignment of the suction line has been selected to minimise the impact on vegetation.The alignment is mostly through hardrock as shown in Figure 9. The amount of rockexcavation is expected to be around 70% of its total excavation volume of (189m3).
Figure 9: Long Section of Suction Pipeline
Existing pipeline
New
pipeline
New supports
Existing supports
Angle Branch Tee to be installedwith FlxSP & couplings after
cutting the existing pipe
Dam Wall
Note: All fittings to beflanged DICL except
couplings
Existing pipeline
Couplings
So x Sp pipes
8/8/2019 Rwps Downloads
23/54
Rylstone Water Supply NSW Water SolutionsRiver Pumping Station Concept Design NSW Public Works
d:\rylstone\intake\final draft report\rylstone rps - concept report ( finaldraft).doc 18
Delivery Main - Long Section
570
575
580
585
590
0 20 40 60 80
Chainage (m)
RL(m)
Ground Level
Likley bedrock
Pipe Invert Level
The excavation volume includes a trench width of 0.9m for construction access. The pipelinewould be laid underground except the first 10m which will be supported on concrete piersanchored to bedrock.
4.2 Delivery PipelineThe new delivery pipeline from the pumpwell to the existing rising main would be 72m long.Considering the rocky condition of the site and being a pumping main, rubber ring jointedcement lined ductile iron (DICL) pipes are recommended. The pipeline would consist of a PACinjection point in a concrete pit. The alignment has been selected avoiding all existing treesand also minimising the rock excavation. Two additional bores were drilled in order todetermine the route which would encounter minimum amount of rock (refer to Appendix A geotechnical results for test bore locations). The final alignment is shown in Figure 1 and thelong section is shown in Figure 10. The amount of rock anticipated for the delivery pipelinewould be about 25%.
Figure 10: Long Section of Delivery Pipeline
The new delivery main would be connected to the existing rising main using an angle branchtee similar to the suction main connection. The provision of the Tee would enable using theexisting rising main during the contract period as well as afterward.
4.3 TrunnionThe trunnion would be designed as a welded fabrication unit of steel plates with necessarybearings etc. It could be made either from stainless steel or epoxy coated mild steel. Thesupply cost of stainless steel is generally 3-4 times higher than mild steel, however, with thelabour involved in fabrication and the epoxy coating, the overall price difference between the
two is not expected to be significant.
8/8/2019 Rwps Downloads
24/54
Rylstone Water Supply NSW Water SolutionsRiver Pumping Station Concept Design NSW Public Works
d:\rylstone\intake\final draft report\rylstone rps - concept report ( finaldraft).doc 19
From a durability point of view, the epoxy coated mild steel, if manufactured strictly inaccordance with specified requirements, should last at least 50 years. The stainless trunnionshould last over 70 years.
The trunnion is not a common item fabricated for water supply use and therefore budgetprices cannot be obtained without carrying out the design and preparing shop drawings forthe trunnion.
It is recommended that the trunnion to be made of epoxy coated mild steel, however, analternative tender price should be invited for a stainless steel unit.
The trunnion arm would be made of epoxy coated mild steel.
8/8/2019 Rwps Downloads
25/54
Rylstone Water Supply NSW Water SolutionsRiver Pumping Station Concept Design NSW Public Works
d:\rylstone\intake\final draft report\rylstone rps - concept report ( finaldraft).doc 20
5 Miscellaneous
5.1 Environmental assessment5.1.1 Ecological Issues
The proposed pipeline alignment is not expected to disturb much vegetation, especiallymature trees. It is quite likely that some of the vegetation within the study area andsurrounding vegetation conforms to Box-Gum Woodland ecological community, which is listedas a critically endangered ecological community under the Environment Protection andBiodiversity Conservation Act (Commonwealth) and an endangered ecological communityunder the Threatened Species Conservation Act (NSW). While this will require an assessment,
the impact of the works is expected to be very low and will be unlikely to have a significantimpact.
As such, for the purpose of the concept design there are no real constraints to consider. It isrecommended, however, that vegetation removal be kept to a minimum and no matureeucalypts be removed. There were three main Eucalypts identified in the subject area - oneapproximately 10m west of the pump shed and the other two upslope towards the accesstrack in the south of the study area. It is not considered that these 3 trees fall within theproposed pipeline alignment; however, they may suffer some root damage as a result of theworks.
It has been suggested that the alignment be moved closer to the powerline easement so as toreduce the loss of plants and habitat. However, this is not considered to be a viable option, as
it would require excavation deeper into the bedrock in this area and would greatly increasethe cost of the project.
5.1.2 Aboriginal Cultural AssessmentA site inspection carried out by a representative of the Mudgee Local Aboriginal Land Council(LALC) did not identify any Aboriginal items or artefacts which would be impacted by theproposed works. As such, there are no evident Aboriginal cultural heritage constraints to theproject.
5.1.3 ConsultationThe Department of Environment, Climate Change and Water (DECCW) and the Department ofIndustry and Investment (I & I NSW) have been consulted regarding the proposed works. TheNSW Office of Water (within DECCW) has identified an existing licence which authorizes thedam and two 150mm centrifugal pumps (within an extraction rate of 120L/s). As the newextraction rate will not exceed this limit and the extraction location will not be changed, areplacement licence is not required. No other issues have been raised in response to thisconsultation.
5.2 Temporary water supply Arrangement for a temporary water supply at various stages of the construction may be
required. The raw water supply needs to be interrupted during the following activities.
8/8/2019 Rwps Downloads
26/54
Rylstone Water Supply NSW Water SolutionsRiver Pumping Station Concept Design NSW Public Works
d:\rylstone\intake\final draft report\rylstone rps - concept report ( finaldraft).doc 21
- Installation of the trunnion;
- Connection of the new suction pipeline to the existing pipeline near the dam;
-
Connection of the new delivery pipeline to the existing rising main;
- Installation of a pressure sustaining valve on the rising main near the WTP;
- During on site testing of pumps (due to limited capacity of transformer)
Investigation on temporary water supply arrangements is outside the scope of work of thisengagement. However, the responsibilities of the temporary supply (i.e. Contractors orPrincipals) and consequences or losses due to delays in completion of these activities etc.should be clearly defined and agreed at the concept stage. This information is required in thepreparation of the tender document.
5.2.1 Testing and commissioning of pumpsThe new pumps would be tested at the manufacturers works prior to installation. The newsystem would be tested when completed. The testing of the new pumps cannot be done whilerunning the existing pumps (a) due to limitation of the power supply; (b) without connectingthe new pipelines to the existing pipelines; and (c) without installing the PSV.
The limitation of power supply would not be a problem if a new transformer is installedwithout removing the existing transformer.
It will be necessary to maintain the supply during the period of construction and installation ofthe new system. It is therefore considered that the connection and installation should becarried out in a manner which will allow for a change over before the old system is de-commissioned. Careful consideration and thoughtful planning is required for a smooth
transition from the existing system to the new system.
5.2.2 Access to the Pumping StationIt is understood that MWRC would construct the access road to the pump station using hiredlabour. Therefore the access road is not included in the construction contract. However, theContractor would have to construct a temporary access road for the construction work andthis access could be upgraded later as the formal access to the new pumping station. Anindicative alignment of the access to the pump station is shown in Figure 1.
8/8/2019 Rwps Downloads
27/54
Rylstone Water Supply NSW Water SolutionsRiver Pumping Station Concept Design NSW Public Works
d:\rylstone\intake\final draft report\rylstone rps - concept report ( finaldraft).doc 22
6 Cost estimates6.1 Capital Cost
The estimated capital cost of the works is given in Table 1. A detailed breakdown of costs isgiven in Appendix B.
Table 1: Cost estimates for the pumping station and associated work s
Item Description Amount
1 Trunnion (supply & install) $80,000
2 Suction pipeline (DN300-DICL) 104m long $158,000
3 Pump well (4m dia. X 5.5m deep) $151,000
4 Pumping Station building (13m x 7m) $113,000
5 Delivery pipeline (DN250-DICL) 72m long $80,000
6 Pumps & internal pipework $127,000
7 External pipework including NRV & isolation valves $27,000
9 Electrical and telemetry $120,000
Sub Total $856,000
Contingencies (10%) $86,000
Grand Total (including GST) $942,000
The estimated capital cost has increased by about 20% from the estimated cost in thestrategy study. This is mainly due the rock excavation and the building. The estimate in thestrategy study allowed for a nominal volume of rock excavation which was far exceeded afterthe geotech investigation. The original estimate was for a smaller building outside thepumpwell and did not include PAC Room.
6.2 Operation and Maintenance CostsThe annual operation and maintenance (O&M) cost of the pumping station is based on anannual supply of 500 ML/yr (Commerce, 2009-2). The O&M cost includes the power cost andother maintenance cost of the operation of pumps, other costs involved in the generalmaintenance of system infrastructure but does not include replacement costs. The power costwas assumed to be $0.15/kWh.
Details of O&M costs are given in Table 2.
8/8/2019 Rwps Downloads
28/54
Rylstone Water Supply NSW Water SolutionsRiver Pumping Station Concept Design NSW Public Works
d:\rylstone\intake\final draft report\rylstone rps - concept report ( finaldraft).doc 23
Table 2: Annual Operation & Maintenance Cost for the pumping station
Descr iption Uni t Quant ity Rate Amount
Power cost of pumps kWh 49,220 $0.15 $7,383
Maintenance of M&E works-1 Sum $9,160
Maintenance of civil works-2 Sum $6,370
Operational personnel (4hrs/week) hrs 208 $40 $8,320
Total $31,233
Production of raw water -3 ($/kL) $0.06
1). 3% of the capital cost of mechanical and electrical works;
2). 0.5% of the capital cost;
3). Based on an annual supply of 500 ML.
8/8/2019 Rwps Downloads
29/54
Rylstone Water Supply NSW Water SolutionsRiver Pumping Station Concept Design NSW Public Works
d:\rylstone\intake\final draft report\rylstone rps - concept report ( finaldraft).doc 24
7 Conclusion & Recommendation
Pumpwell
A 4m diameter cast-in-situ reinforced concrete pumpwell is recommended, however, analternative tender price should be invited for a 3.6m dia. pre-cast pumpwell. The base leveland the top level of the pumpwell are RL 570m and 575.5m respectively. Two verticallymounted axially split centrifugal pumps of duty 67 L/s @ 23m would be provided (oneduty/one standby) with variable speed drives. Non return and isolation valves would beprovided outside the well. The pump well would be equipped/provided with a sump and adewatering pumping system, a level sensor, air ventilation system, access ladder, a davit,handrails, mono rail, a removable grate cover and other necessary items.
Building
The pumpwell would be enclosed in a building which would consist of two rooms, i.e. SwitchRoom and PAC Room. The switch room would be directly above the pumpwell and wouldaccommodate the electrical and telemetry switch gear assembly. The Switch Room alsoprovides the access to the pumpwell and supports the monorail. The existing PAC plant at theWTP site would be relocated in the PAC room. The Switch Room would have two doors (1.2mand 2-3m wide) while the PAC Room would have a GI mesh front with a door made of similarmaterial. The building would be a brick building on reinforced concrete floor supported onconcrete piers founded on the bedrock.
Pipelines and trunnion
The designed pipe sizes are as follows.
Trunnion arm - DN300 Epoxy coated mild steel
Trunnion - DN250 Epoxy coated mild steel (alternative stainless steel)
Suction pipeline - DN300 - DICL
Delivery pipeline - DN250 DICL
A pressure sustaining valve should be provided in the rising main near the treatment plant.Concrete pits would be provided for the PAC injection and non return valves.
Costs
The estimated capital cost of the pumping station is $0.94M. The annual operation andmaintenance cost (excluding replacement cost) is $31,000 per annum.
Testing and commissioning
The existing raw water supply needs to be interrupted at various times for connection of thenew system to the existing infrastructure. It will be necessary to maintain the supply duringthe period of construction and installation of the new system.
It is therefore considered that the connection and installation should be carried out in amanner which will allow for a smooth change over before the old system is de-commissioned.
8/8/2019 Rwps Downloads
30/54
Rylstone Water Supply NSW Water SolutionsRiver Pumping Station Concept Design NSW Public Works
d:\rylstone\intake\final draft report\rylstone rps - concept report ( finaldraft).doc 25
8 Reference
Commerce, 2009 -1: Rylstone Water Supply System - Reticulation System Hydraulic
Analysis, A report prepared for Mid Western Regional Council by the Department ofCommerce, (Final Report, September, 2009).
Commerce, 2009 -2: Rylstone, Kandos and Villages Water Supplies Strategy Options Study,A report prepared for Mid Western Regional Council by the Department of Commerce, (April2009).
8/8/2019 Rwps Downloads
31/54
Rylstone Water Supply NSW Water SolutionsRiver Pumping Station Concept Design NSW Public Works
APPENDICES
8/8/2019 Rwps Downloads
32/54
Rylstone Water Supply NSW Water SolutionsRiver Pumping Station Concept Design NSW Public Works
Appendix 1
Preliminary Geotechnical Assessment
8/8/2019 Rwps Downloads
33/54
Rylstone WS River Pumping Station
Preliminary Geotechnical Assessment
1. General
The site is located within rhyolitic tuff. Bouldery outcrop is evident throughout theslopes along the mains alignment and pumping station site. Bedrock crops outs in a
series of ledges on the slope leading to the creek and is exposed in the creek bed.
Generally the soil profile is very thinly developed. There is some fill along the suction
main alignment, especially in the vicinity of the dam where boulders appear to have
been placed. Some fill associated with the construction of the existing pump station
may also be expected on the upper slope leading to a levelled area adjoining the
building.
2. Pumping Station
At the pumping station site (borelog reference PS1 & PS2), bedrock was encounteredat depths of 0.14m/0.15m. In borehole PS1, the bedrock was cored between 0.14m to
6.01m. In borehole PS2, the TC bit penetrated the bedrock to a depth of 0.5m at which
point TC bit refusal was recorded.
The bedrock, within the depths of coring, is a rhyolitic tuff. The tuff is typically very
coarse grained with occasional medium grained interbeds and commonly includes
pebble-sized clasts.
The degree of weathering varies. The bedrock is moderately weathered to an
approximate depth of 1.2m and then becomes slightly weathered with rare moderately
weathered interbeds.
The rock sub-strength is assessed as very strong. For the three samples tested uniaxial
compressive strength ranged from 120 MPa to 146 MPa. The defect spacing ranges
from closely spaced in the upper 1m/1.4m and then becomes moderately widely
spaced to widely spaced.
The proposed 3.6m diameter well may need to be constructed by sinking a shaft.
Open excavation, due to the moderately steep slope leading to the creek, may not be
practical. Excavation in bedrock will be difficult due to high rock substance strength
and unfavourable defect spacing. A large excavator (30 tonne) with a rock breaker
will be needed in combination with blasting. Blasting will be required.
3. Suction Main
One borehole (M1) was cored adjacent to the existing building. Bedrock was
encountered at 0.86m depth. The bedrock is of similar type and quality to that
encountered in pumping station borehole PS1. Difficult excavation may expected.
Rock substance strength is also very strong. For two specimans tested, UCs test
yielded strengths of 99.5 MPa and 111 MPa. Blasting will be required.
8/8/2019 Rwps Downloads
34/54
4. Rising Main
The rising main from the pump station to the connection point of the existing rising
main will traverse a moderate slope characterised by bouldery outcrop.
A total of four boreholes (M3-M6) were drilled on the slope. Generally, the soil
profile is thinly developed, ranging in thickness between 0.15m (M3) and 0.8m (M2).
The stratum is a silty sand with gravel, locally with traces of clay, organics or cobbles.
Rhyolitic tuff underlies this surficial horizon.
When first encountered the bedrock is extremely and highly weathered. This quality
bedrock extends to depths 0.6m (M3). 1,6m(M5) and 0.6m (M6). In borehole M4, the
TC bit refusal failed to penetrate the bedrock for any appreciable depth. TC bit
refusal, inferred to be in moderately weathered bedrock , was recorded at depths of
0.65m (M3) 0.7m (M4) and 0.6m (M6). Borehole M5 was terminated upon reaching
nominal target of 1.5m.
Excavation to TC bit refusal should be achieved using a large excavator. If
excavations below refusal levels are proposed then an assistance from a rock breaker
will be required. In area of outcrop, a rock breaker will be required.
Encl. Bore logs
8/8/2019 Rwps Downloads
35/54
8/8/2019 Rwps Downloads
36/54
8/8/2019 Rwps Downloads
37/54
8/8/2019 Rwps Downloads
38/54
8/8/2019 Rwps Downloads
39/54
8/8/2019 Rwps Downloads
40/54
8/8/2019 Rwps Downloads
41/54
8/8/2019 Rwps Downloads
42/54
8/8/2019 Rwps Downloads
43/54
8/8/2019 Rwps Downloads
44/54
8/8/2019 Rwps Downloads
45/54
8/8/2019 Rwps Downloads
46/54
8/8/2019 Rwps Downloads
47/54
8/8/2019 Rwps Downloads
48/54
Rylstone Water Supply NSW Water SolutionsRiver Pumping Station Concept Design NSW Public Works
Appendix 2
Capital and O&M Cost Estimates
8/8/2019 Rwps Downloads
49/54
Rylstone WS - River Pumping Station Created - 05Sep09Concept Design Cost Estimate Revised - 17Sep09
No Item Description Unit Quantity Rate Amount Total
1 Trunnion
Fabrication of trunnion & trunnion arm Item 1 $30,000 $30,000
Replace the trunnion (DN250) and arm (DN300) Item 1 $50,000 $50,000 $80,000
2 Suction Main
Supply & deliver DICLpipes (DN300 - SoxSp) m 103 $198 $20,394
Excavation and laying m 103 $137 $14,111
Extra over for rock excavation m3
131 $700 $91,700
Bedding m3
69 $85 $5,865
Backfilling m3
108 $35 $3,780
Concrete supports Nos 4 $2,500 $10,000
Connection to existing pipework near the dam Item 1 $12,535 $12,535 $158,385
3 Pumpwell
Site clearing Item 1 $5,000 $5,000
Excavation and dispose within site m3
12 $150 $1,800
Excavate in rock and dispose within site m3
91.0 $700 $63,700
R.C walls (cast-in-situ) m3
19 $2,000 $38,000
Base concrete incl.r/f & rock anchors (0.4m thick) m3
5.8 $2,000 $11,600
Cover (GI gratings) m2
4 $3,800 $15,200
Acceess platform Item 1 $12,500 $12,500
Access ladder m 9.5 $350 $3,325 $151,125
4 Pumpwell - PumpsPumping units Nos 2 $35,000 $70,000
Pipework within well (incl suction Tee) Item 1 $28,490 $28,490
GI davit Item 1 $4,500 $4,500
Allow for pump plinth, pipe brackets etc. Item 1 $5,000 $5,000
Dewatering pump and pipework Item 1 $12,000 $12,000
Ventilation system Item 1 $7,500 $7,500 $127,490
5 SCA & PAC Building (excluding PAC plant & accessories ) R/C columns (450x450) from bedrock including excavation m 26 $350 $9,100
Beams & slab for the building floor m3
27 $1,300 $35,100
Brickwork m2
102 $180 $18,360
Steel portal frame m 60 $250 $15,000
Roof m2
112 $35 $3,920
Door (1.2m wide) Nos 1 $2,400 $2,400
Door (3m wide) Nos 1 $4,200 $4,200
GI mesh for PAC room m2
$135 $0
Mono rails m 10 $450 $4,500Handrail for pumpwell m 15 $85 $1,275
Lighting Item 1 $5,000 $5,000
Rainwater down pipes m 18 $95 $1,710Retaining wall for access road next to main door exit (5m long) Item 1 $12,000 $12,000 $112,565
6 Del ivery Main
Supply & deliver DICLpipes (DN250 - SoxSp) m 71 $157 $11,147
Excavation and laying m 71 $127 $9,017
Bedding m3
43 $115 $4,945
Backfilling m3
26 $35 $910
Extra over for rock excavation m3
20 $750 $15,000
Concrete bulk heads Nos 10 $1,500 $15,000
PAC & valve pit Nos 2 $7,500 $15,000
Connection to existing rising main Item 1 $8,762 $8,762 $79,781
7 External pipework
Pump delivery pipes (DN200 double lines) Item 1 $27,314 $27,314 $27,314
8 Electrical & Telemetry
Electrical works Item 1 $85,000 $85,000
Lightening protector Item 1 $15,000 $15,000
Telemetry Item 1 $20,000 $20,000 $120,000
9 SUB TOTAL $856,659
10 Contingencies
Add 10% (of sub total) $85,666
TOTAL (INCLUDING GST) $942,325
Notes:
This estimate does not include:
1. Cost of temorary water supply arrangement
2. Access road
3. Relocation and installation of PAC plant and associated works
4. Power supply to site including new transformer and pole
5. Construction supervision cost
Costs for O&M cost calculations
M&E costs $305,400
Other costs $636,925
8/8/2019 Rwps Downloads
50/54
8/8/2019 Rwps Downloads
51/54
Rylstone WS - River Pumping Station Created - 05Sep09
Concept design - Cost Estimate for pipework within pumpwell
No Item Description Unit Quantity Rate Amount Total
1 Suction side (All DICL , supply price)
DN300 FlxSo Nos 1 $480 $480
DN300x300 Tee (all flanged) Nos 1 $950 $950
DN300 FlxFl 90 deg bends Nos 2 $500 $1,000
DN300 FlxFl pipe (0.55m long) Nos 1 $600 $600
DN300 FlxFl pipes 0.7m long Nos 2 $650 $1,300
DN300 butterfly valves Nos 2 $2,200 $4,400
DN300 FlxFl pipes 0.5m long Nos 2 $450 $900
DN300x200 Taper Nos 2 $480 $960 $10,590
2 Delivery side (All DICL - supply price)
DN150x200 Taper Nos 2 $460 $920
DN200 Thrust dismantling joint Nos 2 $2,300 $4,600
DN200 - FlxFl 90 deg bends Nos 4 $390 $1,560 DN200 - FlxFl pipe 4m Nos 2 $410 $820 $7,900
Sub Total $18,490
Delivery (10%) $1,849
Installation $10,000
Total ( for pipework within pumpwell) $28,490
8/8/2019 Rwps Downloads
52/54
Rylstone WS - River Pumping Station Created - 05Sep09
Concept design - Cost Estimate for pipework at the rising main (delivery main)
No Item Description Unit Quantity Rate Amount Total
1 Connection to the existing rising main (All DICL)
DN250 couplings Nos 3 $685 $2,055
DN250 equal tee Nos 1 $810 $810
DN250 - FlxSp (1m long) Nos 2 $375 $750
DN250 pipe (1m) Nos 1 $350 $350
Sub Total $3,965
Delivery $397
Installation $3,500
Thrust block for the tee and valve $900
Total ( for connection of delivery main) $8,762
8/8/2019 Rwps Downloads
53/54
Rylstone WS - River Pumping Station Created - 05Sep09
Revised - 17Sep09
Concept design - Cost Estimate for pipework outside the pumpwell (dual lines)
No Item Description Unit Quantity Rate Amount Total
1 DN200-DICL double lines from pumpwell wall
DN200 FlxSp pipes 1.8m long Nos 2 $350 $700
DN200 dismantling joints Nos 2 $490 $980
DN200 couplings Nos 2 $325 $650DN200 FlxFl NRV Nos 2 $3,500 $7,000
DN200 FlxSp pipes - 0.4m long Nos 2 $215 $430
DN200 - FlxFl bend (90deg) Nos 1 $380 $380
DN200 - FlxFl gate valves Nos 4 $1,800 $7,200
DN200 FlxFl pipes - 0.7m long Nos 3 $450 $1,350
DN200x200 Tee Nos 1 $475 $475
DN200 FlxFl pipes - 0.4m long Nos 4 $280 $1,120 $20,285
Sub Total $20,285
Delivery (10%) $2,028.5
Installation $5,000
Total ( for pipework outside pumpwell) $27,314
8/8/2019 Rwps Downloads
54/54
Rylstone River Pumping Station - O&M Cost Calculations
Common inputs:
System capacity 5.28 ML/d
power cost 0.15 $/kwh =(15*5*0.2+0.1*(9*5+2*24))/(24*7)
Annual supply 500 ML
Pump head 23 m
ITEM DESCRIPTION Cost
$*1000
1 CAPITAL COSTS
Civil works 631
M&E Works 305.4
TOTAL CAPITAL COST 937
2 OPERATION AND MAINTENANCE COSTS
2.1 OPERATION COSTS
Power costs (pumps+other minor) 7.38 Add 10% to pump cost
Operator (4 hrs a week) 8.32 @40/hr
2.2 MAINTENANCE COSTS
Civil works (1% of capital cost) 6.31
M&E works (3% of capital cost) 9.16
3 REPLACEMENT COSTS
Not considered 0
TOTAL OPERATION & MAINTENANCE COSTS* $31,177 $/Year
[* Does not include PAC costs]