Runway Environmental Impact Assessment Mike Matthews Senior Vice President Aviation and Airport Planning Inter VISTAS Consulting Inc.

Runway Environmental Impact Assessment · 2013-03-20 · Environmental Assessment Typical Process Environmental Assessment Typical Process • Initial Assessment • Screening •

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Runway Environmental Impact Assessment · 2013-03-20 · Environmental Assessment Typical Process Environmental Assessment Typical Process • Initial Assessment • Screening •

Runway Environmental Impact Assessment

Mike Matthews

Senior Vice President

Aviation and Airport Planning

InterVISTAS Consulting Inc.

Page 2: Runway Environmental Impact Assessment · 2013-03-20 · Environmental Assessment Typical Process Environmental Assessment Typical Process • Initial Assessment • Screening •

Tower CartoonTower Cartoon

Page 3: Runway Environmental Impact Assessment · 2013-03-20 · Environmental Assessment Typical Process Environmental Assessment Typical Process • Initial Assessment • Screening •

Aircraft Lineup

Page 4: Runway Environmental Impact Assessment · 2013-03-20 · Environmental Assessment Typical Process Environmental Assessment Typical Process • Initial Assessment • Screening •

Environmental Assessment Typical Process

Environmental Assessment Typical Process

• Initial Assessment • Screening

• Scoping

• Impact Statement• Comprehensive assessment provided by the project

sponsor of the anticipated effects on the environment. Includes

• Project need

• Alternatives

• Impacts

• Review• Public hearings

• Responsible agency

Page 5: Runway Environmental Impact Assessment · 2013-03-20 · Environmental Assessment Typical Process Environmental Assessment Typical Process • Initial Assessment • Screening •

Vancouver International Airport Runway ProjectVancouver International Airport Runway Project

Characteristics

• Controversial

• Strong, well organized opposition to project dating back to the Sixties

• Located adjacent to residential areas

• Environmentally Sensitive Area• Salmon

• Waterfowl wintering and staging area

• Raptor, passerine, heron habitat

Page 6: Runway Environmental Impact Assessment · 2013-03-20 · Environmental Assessment Typical Process Environmental Assessment Typical Process • Initial Assessment • Screening •

Vancouver International Airport Runway ProjectVancouver International Airport Runway Project

The Project

Page 7: Runway Environmental Impact Assessment · 2013-03-20 · Environmental Assessment Typical Process Environmental Assessment Typical Process • Initial Assessment • Screening •

Environmental Impact Statement

Environmental Impact Statement

Approach:

• Justify Technical Solution• Capacity Requirement

• Alternative solutions

• Demonstrate Economic Viability• Benefit/Cost

• Economic impact

• Manage Environmental Impacts• Mitigate all impacts to acceptable levels

• Proactive solutions with agency advice

Page 8: Runway Environmental Impact Assessment · 2013-03-20 · Environmental Assessment Typical Process Environmental Assessment Typical Process • Initial Assessment • Screening •

Project JustificationProject Justification

Objective: To present a technically correct solution supported by comprehensive data.

• Demonstrate practical capacity has been reached

• Operations analysis

• Delay data

• Cost of delays

• Forecast aircraft operations

• Test alternative solutions

• Demand management/diversion to other airports

• Runway locations and lengths

Page 9: Runway Environmental Impact Assessment · 2013-03-20 · Environmental Assessment Typical Process Environmental Assessment Typical Process • Initial Assessment • Screening •

Project JustificationProject Justification

Aircraft delay data applications• Confirms capacity analysis results

• Provides base for cost calculations

• Motivates carrier support

• Supports air quality studies

Page 10: Runway Environmental Impact Assessment · 2013-03-20 · Environmental Assessment Typical Process Environmental Assessment Typical Process • Initial Assessment • Screening •

Economic AnalysisEconomic Analysis

Compared benefits and costs of alternate strategies.

• No runway (Base case)

• Runway lengths of 5000’, 7500’, 10,000’

• Alternate airport development

• Peak period fees tested in each case

Page 11: Runway Environmental Impact Assessment · 2013-03-20 · Environmental Assessment Typical Process Environmental Assessment Typical Process • Initial Assessment • Screening •

Economic AnalysisEconomic Analysis

Net Present Value of 10,000’ runway:

$C 4 Billion

Page 12: Runway Environmental Impact Assessment · 2013-03-20 · Environmental Assessment Typical Process Environmental Assessment Typical Process • Initial Assessment • Screening •

Environmental Impact IssuesEnvironmental Impact Issues

• Noise

• Fish, birds and wildlife habitat

• Air Quality

• Water Quality

• Archaeological

• Construction

Page 13: Runway Environmental Impact Assessment · 2013-03-20 · Environmental Assessment Typical Process Environmental Assessment Typical Process • Initial Assessment • Screening •

Noise Impact AnalysisNoise Impact Analysis

• Used NEF, Ldn and Single Event metrics

• Pre-Stage 3 impact required mitigation• 49% increase in residences in NEF 30-35

• Mitigation Plan • Runway to be used primarily for arrivals

• No night operations

• Reverse thrust limitations

• 12% reduction in residences in NEF 30-35 zone.

Page 14: Runway Environmental Impact Assessment · 2013-03-20 · Environmental Assessment Typical Process Environmental Assessment Typical Process • Initial Assessment • Screening •

Measured v. Modeled Ldn

Page 15: Runway Environmental Impact Assessment · 2013-03-20 · Environmental Assessment Typical Process Environmental Assessment Typical Process • Initial Assessment • Screening •

Wildlife Habitat ImpactWildlife Habitat Impact

• Baseline data on bird/animal populations essential to analysis

• Mitigation agreement with agencies

• Land acquisition offsets.

• Designed-in mitigation• Approach lighting pier

• Construction methods

Page 16: Runway Environmental Impact Assessment · 2013-03-20 · Environmental Assessment Typical Process Environmental Assessment Typical Process • Initial Assessment • Screening •

Air Quality AssessmentAir Quality Assessment

• One year baseline data collection

• Future operations impact assessed with Emissions and Dispersion Modeling System

• Demonstrated that YVR was not a major contributor to air quality problem

Page 17: Runway Environmental Impact Assessment · 2013-03-20 · Environmental Assessment Typical Process Environmental Assessment Typical Process • Initial Assessment • Screening •

Water Quality AssessmentWater Quality Assessment

• Data gap• Minimal information available on surface and ground

water

• Complicated by tidal waters surrounding airport

• EIS Proposed• Enhanced runoff water monitoring by automatic stations

• Improvements in handling of fuels and glycol

Page 18: Runway Environmental Impact Assessment · 2013-03-20 · Environmental Assessment Typical Process Environmental Assessment Typical Process • Initial Assessment • Screening •

Public Information and Stakeholder ConsultationPublic Information and

Stakeholder Consultation

• Be ready!• Consultation starts on Project Day One

• Provide clear messages• Runway analysis inherently complex

• Make it understandable

• Establish communications with opponents early in the program.

• Mobilize support• Local government

• Business community

Page 19: Runway Environmental Impact Assessment · 2013-03-20 · Environmental Assessment Typical Process Environmental Assessment Typical Process • Initial Assessment • Screening •

Public Information and Stakeholder ConsultationPublic Information and

Stakeholder Consultation

Video: (Approximately 8 minutes duration)

“YVR - A New Runway, The Environment, and You”

Page 20: Runway Environmental Impact Assessment · 2013-03-20 · Environmental Assessment Typical Process Environmental Assessment Typical Process • Initial Assessment • Screening •

Runway 08L-26R Opened 4 November, 1996

N

WE

S

Runway 08L-26R Opened 4 November 1996