Upload
raquel
View
39
Download
2
Embed Size (px)
DESCRIPTION
Run 2B upgrades di CDF. INFN - Riunione della Commissione 1 Laboratori Nazionali di Frascati 14 Maggio 2002 Franco Bedeschi INFN-Pisa. Stato Tevatron e CDF Run IIB: CDF upgrades per il run IIB Piano finanziario per il Run IIB upgrade . SOMMARIO. TeV Luminosity. - PowerPoint PPT Presentation
Citation preview
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
Run 2B upgrades di CDF
Stato Tevatron e CDF Run IIB:
CDF upgrades per il run IIB Piano finanziario per il Run IIB upgrade
SOMMARIO
INFN - Riunione della Commissione 1
Laboratori Nazionali di Frascati
14 Maggio 2002Franco BedeschiINFN-Pisa
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
TeV Luminosity Peak luminosity still low but
improving X2 since January 2002 Best 2x1031
Delivered/on tape 40/25 pb-1
Delivered
On tape
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
Run 1 comparison Luminosity progress in Run 1
~1 yr to get x10 Steady progress after that
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
TeV Luminosity Medium range plan
Current performance ~60% of Church plan- Does not include effect
of October shutdown
0
50
100
150
200
250
300
350
Jan/1 Feb/27 Apr/26 Jun/23 Aug/20 Oct/17 Dec/14
2002 Integrated Luminosity
date
From Mike Church PMG 1/8/02 presentation
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
Luminosity Massive effort put into understanding and improving
Luminosity- Fixed Accumulator MI optics- Much work on stabilizing tunes in injection and low beta squeeze- Fight large p-bar emittances- Work on accumulator lattice to reduce beam heating
Access early June to add transverse cooling to accumulator is expected to improve L by factor 2 – 4
Max luminosity achievable without Recycler ~8x1031 (maybe by end of 2002)
Need recycler to get to 2x1031
- Major shutdown in October ’02 to finish Recycler work- Full benefits of Recycler ~Summer 2003
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
Status of CDF Detector:
All systems installed and commissioned- ISL will be fixed during the next accesses this summer/fall
DAQ and trigger: Running physics trigger table with > 100 trigger paths since
February ‘02- New SVT very successful
Typical running conditions:- L1: 3.5KHz, L2: 200 Hz, L3: 20 Hz
Data processing: Reconstruction farm keeps up with data logging Physics groups skim data:
- Observe signals from low and high pt triggers: , D, B, W, Z- Some preliminary results expected for Amsterdam this July
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
Recent problems Broken wire in COT
Wire plane removed Need additional fixtures to replace (October shutdown) Minor impact on current data quality
Lost 6 SVX II ladders, maybe due to radiation accident Silicon has been off for about a month until May 2nd Now back to normal operation, after
- Many studies were done to understand what happened Irradiation tests at booster delivering x100 – 1000 more than
suffered during accident- Several additional interlocks and protections put into place
Probability of same conditions as accident severely reduced
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
First results Much data recorded to debug detector and trigger Actual data so far used for analysis with stable and
complete detector and trigger configuration ~ 6 pb-1
Specific analysis non requiring all of the detector information can use larger data sets
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
W and Z’s
From 3.65 pb-1
Central MuonsET >12 GeV
ET >20 GeV
298 Wevents
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
W Tau’s very clean with new
detector/selection algorithms
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
CDF: J/
Clear J/signal CMU or CMX
- ~ 60,000 ’s- = 21 MeV/c2 (16
with SVX II)- J/ x-section
~9nb as expected
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
CDF: J/
First checks on physics: Inclusive B lifetime from J/
consistent with expectations- cB ~ 470 mm from unbinned fit
Systematics still out of control!
- Prompt fraction ~ 85% Consistent with lower
momentum cut relative to Run I
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
First B signals
Bd
Bu
Bs
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
So much Charm!!! Getting much more charm than expected with SVT!!!
50 pb-1 2 fb-1 E791 FOCUS (4S)/100 fb-1
500K 20M 40K 120K 1M
KD0 yields:
Large yield, but poor PID, trigger bias, prompt & secondary charm……….Need to understand how to make best use of it
6 pb-1
60K
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
CDF for Run II The current detector was
designed/built based on Run IIa specifications: Maximum instantaneous
luminosity of 2×1032cm-2s-1. Integrated luminosity of 2 fb-1. Operation with 396 ns and
132 ns bunch spacing
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
The Run IIb Specifications
We now consider the detector to have a longer, harder life. Operating conditions for Run IIb:
Maximum instantaneous luminosity of 5×1032cm-2s-1. Integrated luminosity of 15 fb-1.
Not all portions of the detector can operate effectively in these conditions
The Run IIb project consists primarily of replacements for key elements needed for high luminosity running Make changes needed in a 6 month shutdown starting approximately
in Spring 2005
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
The Run 2B Specifications
Luminosity profiles from Tevatron Run 2B TDR
Peak Luminosity
0
50
100
150
200
250
300
350
400
450
FY01 FY02 FY03 FY04 FY05 FY06 FY07 FY08
x10^
30 Integrated luminosity
0
2
4
6
8
10
12
14
16
FY01 FY02 FY03 FY04 FY05 FY06 FY07 FY08
fb^-
1 Total
per year
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
Upgrades List 4 projects well established as seeking Stage 1
approval at June PAC and being part of the baseline review of late July 2002 Silicon tracker, Central pre-radiator, Event builder switch,
EM calorimeter timing CSX scintillator/L3 CPU replacements are treated as
maintenance Italian interest in all but the Event builder and L3
Additional trigger/DAQ upgrades presented to PAC in April 2002, but need more work to become part of DOE baseline (TDC, L2, 3-D track trigger) No Italian interest so far for these projects
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
DOE Baselining Update
DOE baselining dates have been slipping from May to October 2002. Current estimates: DOE review for CD 1 approval (definition of scope):
Late July, 2002 DOE review for CD 2, 3 (cost baseline, spend construction
money): October 2002
Baselining in October is well matched to our September budget meeting
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
Run IIa silicon system Radiation damage tests and
rate measurements allow us to predict the lifetime of the SVXII.
Silicon detector end view
Layer Lifetime (fb -1)00 7.40 4.31 8.52 10.73 234 14
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
Silicon Installation Silicon detector replacement
Space constraints require removal of the central detector from the collision hall
This requires 14 weeks (round trip).
Time constraints force a complete replacement of SVXII. Partial replacement would also
be very risky.
ISL and SVXII positioned for installation (Jan. 2001)
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
SVX Replacement The replacement silicon detector is being designed to
be simple, and should be relatively quick to build. Based on single sided detectors Readout chip is common with D0, manufactured in a
standard process. One structure is used for most of the detector Compatible with existing systems
- Data acquisition- Cooling
Developments since Nov. 2001 have simplified the design we propose to build.
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
Silicon Detector - Run IIb
New detector is designed for quick construction
A basic module - the “stave” will be built
This structure will populate most of the detector volume
This gives the advantage of fewer parts than the current detector
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
Silicon Detector - Run IIb
Single sided sensors will be used for Run IIb.
Axial and small angle stereo layers will be joined in a single structure – this is used for layers 1-5.
Layer 0 (innermost) will be axial only, and a different structure. Stave layout
Mini Portcard
Axial SensorsStereo Sensors
Hybrids
Chips
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
Run IIB Silicon Chip development and production
- Cost: 30 k € (R&D) {funded} + 130 k € (1/3 of chip production)- Funding year: 2002- Foreign Institutions on sub-project: LBL, FNAL- Italian Institutions on sub-project: Padova- Physicists on sub-project: Alfonsi, Bacchetta, Centro, Garbossa, Guang,
Neviani Power supplies development and production
- Cost: 25 k € (R&D) + 150 k € (1/3 of production)- Funding year: 25 k € in 2002, remaining in 2004- Foreign Institutions on sub-project: FNAL- Italian Institutions on sub-project: Padova- Physicists on project: Bacchetta, Bisello, Wang + technical personnel
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
Run IIB Silicon Mechanical work (precision fixtures):
- Cost: 17 k € - Funding year: 2002- Foreign institutions on project: FNAL + many contribute to other fixtures- Italian institutions on sub-project: Bologna- Physicists on sub-project: Zucchelli
SVT modifications:- Cost: 100 k € (12 merger boards)- Funding year: 2003-2004- Foreign Institutions on sub-project: Chicago (fitter boards)- Italian Institutions on sub-project: Trieste, Pisa- Physicists on sub-project: Ristori, Belforte, Zanetti
Simulation and reconstruction software- Italian Institutions on sub-project: Roma1, Padova- Physicists on sub-project: Giagu, Rescigno, Jeans, Sarkar, Azzi, Sidoti
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
Run IIB Silicon Detail R&D requests:
25 k € PS test system:- $10,000 crate SY1527- $ 3,100 modulo A1551 di alta tensione- $ 2,900 modulo A1518 di bassa tensione- $ 1,500 consumo per cavi connettori, load box- IVA
17 k € Gluing Fixtures (R&D and production)- Al prototype (production and measurement)- Steel Prototype (production and measurement)- Production of 10 pieces
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
Central Preradiator
100
10
1
0.11030 103310321031
Luminosity (1032cm-2s-1)
< N >
Run IIb
Run IIa396 n
s
132 n
s
Located on the front face of the central calorimeter
The current device is a gas chamber Charge must be collected over
4 beam crossings Will contain data from ~20
interactions in Run IIb The rate will seriously
compromise its usefulness.
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
CPR for High PT Electrons
The pre-radiator provides an estimate of pion backgrounds to electrons Can provide some rejection
Note, the shower maximum chamber is also gas, and inaccessible Pre-radiator is our only avenue
to strengthen electron ID.
Run I hi-pt electrons
MIPS
electrons
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
CPR for Soft b tagging Again, the ability of the CPR
to discriminate between pions and electrons was used for tagging in Run I. 2 GeV particles from Run I CPR data was used to reduce
background
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
CPR for Jet resolution Some jet energy algorithms
under study indicate that resolution can be improved by including CPR information.
Jet resolution impacts directly sensitivity to Higgs or any other high mass particle decaying into jets
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
Pre-radiator Replacement
The pre-radiator replacement will take the place of existing CPR. Replacement uses scintillator
- Dubna scintillator currently assumed as default option
- Minos excess is possible, used for the first prototype
- Other approaches will be studied (BICRON)
Optical fiber readout, with 16 channel phototubes- Same readout used in the
plug calorimeter shower maximum detector, same phototubes
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
Pre-radiator Installation
Installation requires the calorimeter arches to be extracted Not possible in collision hall Assembly hall installation does
not interfere with silicon
CPR location
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
Run2b Pre-shower
Non-italian institutions: ANL, FNAL, Michigan State, Tsukuba
Italian institutions: Pisa, Siena, Roma1, Pavia Italian physicists on CPR project:
- Introzzi, Iori, Lami, Menzione, Paoletti, Scribano, Turini (R&D phase)
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
Run2b Pre-shower Cost of current default solution with JINR scintillator:
- Italy contributes total of 182 k$ = 202 k€ new scintillator 80 k € (funding yr 2003/04) fibers & conn. 45 k € (funding yr 2003/04) PS and Cables 57 k € (funding yr 2003/04) Prototyping 20 k € (funding yr 2002)
Details of R&D request:- Scintillator, shipping and mechanical work 3,500 €- Fibers & glue 1,500 €- 2 PMT with bases 4,500 €- Electronics 6,000 €- Mechanics 3,000 €- Miscellaneous 1,500 €
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
EM Calorimeter Timing Cosmic background removal is essential (e.g. Z Hard to do with Need for EM calorimeter timing
Calorimeter timing currently implemented only on hadron calorimeters
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
EM Calorimeter Timing In + MET events hard
to find a good handle to remove cosmic backgrounds Figure shows comparison
of some natural discriminating variables for “in time” and “out of time” data- No big difference between
distributions
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
EM timing Physics Motivation:
Important for SUSY, LED searches which rely on photons
Important for studies of W/Z production
Important for any other study involving
Our eeET had 2 EM object missing timing information!
SM Background estimate of 10-6
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
EM timing Currently only Hadronic Calorimeters have timing instrumented
EM shower needs to leak into Hadronic section to be timed inefficiency!
Run 2
Run II +METTrigger threshold
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
EM Calorimeter Timing Examples:
EWK physics: WZ production SUSY searches: N2 G~~
Run II x30 run 1 acceptance
Run 1
Need good containment of shower to have reliable efficiency calculation
- No EM timing Higher threshold
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
EM Timing
Solution: Add TDC timing to EM calorimeters: Central and Plug
- Minimal R&D- Project risk low:
No need for PMT base modification Inductive pick sufficient and does not change charge collected by
ADC- Installation possible during 2003 well before the Run IIB shutdown!
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
EM timing
Non-italian institutions: Texas A&M, Chicago
Italian institutions: LNF Italian physicists on EM timing project:
- Dell’Agnello, Cordelli, Happacher, Miscetti, Sansoni
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
EM timing Cost of EM Calorimeter timing
Italian contribution 130 k$ = 144 k€ :- ASD 74 k€ - Transition boards 25 k€ - ASD TDC cables 25 k€ - Prototyping 20 k€
Details of R&D: Design and build 4 ASD/TB pairs for larger scale test this
summer
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
Run 2B CMX counters CMX Scintillator Counters
Counter fabrication/installation and commissioning- Cost:
85 kEuro (scintillator/fabrication – 50% of all counters) + 75 kEuro (installation and refurbishing of current system)
- Funding year: 2002 (85 kEuro), 2003-2004 (75 kEuro)- Foreign Institutions: JINR-Dubna - Italian Institutions: Udine (with physicists from Roma), Pisa- Physicists on project: Pauletta, Menzione
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
Run IIB Summary Cost summary compared to other international funding
Total cost Dollars EuroProject M&S Cost + US M&S Japan M&S Italy M&S Italy R&D Italy M&S Italy R&D
contingency no contin. no contin. no contin. no contin. no contin. no contin.Run 2B silicon $10,870,937 $5,655,639 $1,741,264 $372,380 $49,555 € 397,000 € 55,000--> Chip eng. Run $135,880 $88,000 $0 $27,030 € 30,000--> Chip production $547,500 $425,000 $117,130 $0 € 130,000--> PS test system $22,525 $0 $22,525 € 25,000--> PS Production $672,000 $390,000 $135,150 $0 € 150,000--> SVT upgrade $382,000 $210,000 $90,100 $0 € 100,000--> Gluing Fixtures $40,000 $0 $30,000 € 17,000Pre-radiator $955,050 $425,481 $300,805 $163,982 $18,020 € 182,000 € 20,000--> Prototyping $101,254 $55,672 $27,562 $0 $18,020 € 20,000--> Scintillator (Dubna) $92,666 $0 $0 $72,080 $0 € 80,000--> Fibres & connectors $60,523 $6,590 $0 $40,545 $0 € 45,000--> PS & cables $75,800 $8,300 $0 $51,357 $0 € 57,000EM timing $248,150 $107,865 $0 $111,715 $18,020 € 123,990 € 20,000--> Prototyping ASD $18,020 $0 $0 $0 $18,020 € 20,000--> ASD Board $81,000 $0 $0 $66,899 $0 € 74,250--> Transition boards $26,460 $0 $0 $22,300 $0 € 24,750--> ASD --> TDC cables $27,019 $0 $0 $22,516 $0 € 24,990
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
Run IIB Summary Run 2B Italian requests
Project Italy M&S Italy R&D 2002 funds 2002 funds 2003 / 04 2003 / 04 Summaryno contin. no contin. Italy M&S Italy R&D Italy M&S Italy R&D new funds
Run 2B silicon € 380,000 € 55,000 € 147,000 € 25,000 € 250,000 € 0 € 422,000Pre-radiator € 182,000 € 20,000 € 0 € 20,000 € 182,000 € 0 € 202,000EM timing € 123,990 € 20,000 € 0 € 20,000 € 123,990 € 0 € 143,990Total € 685,990 € 95,000 € 147,000 € 65,000 € 555,990 € 0 € 767,990CSX replacement € 160,000 € 0 € 85,000 € 0 € 75,000 € 0 € 160,000Total with CSX € 845,990 € 95,000 € 232,000 € 65,000 € 630,990 € 0 € 927,990
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
Italian Group in Run 2B Results of poll to verify size of Italian group in Run 2B
(% of current group size by staff physicists) Bologna: 100 Frascati: 70 Roma: 55 Padova: 55 Pavia: 100 (1 person) Pisa: 75 Trieste: 75 Udine: 90
Franco Bedeschi – INFN-Pisa Gruppo1 – 14 Maggio 2002
Conclusions Concerns about Tevatron luminosity continue, but
finally see signs of improvement CDF detector working well. Few problems have been
effectively dealt with The Run IIB contributions from Italy are taking shape
Costs (R&D + M&S) are well defined Italian group interest and involvement is clear
Need to start ASAP with the R&D work Need a clear encouragement from INFN on the
overall plan