RTF Work PlanMid-Year Re-Programming

July 15, 2014

Page 2: RTF Work Plan Mid-Year Re-Programming July 15, 2014

Current Status of 2014 Work Plan

• Not-yet-committed tasks soon to be underway:• Task Order for Small/Rural Work plan items• Task Order for HVAC Interaction Factors (once CBSA data is available)• Task Order for End-Use updates from RBSA metering• Task Order for Cost-effectiveness volume of Guidelines

$0 $100,000 $200,000 $300,000 $400,000 $500,000 $600,000

Contract Budget Snapshot (through May, 2014)Allocated through WorkPlan 2014 Committed to Contracts 2014 Spent in 2014

2014

Bud

get

Dol

lars

Page 3: RTF Work Plan Mid-Year Re-Programming July 15, 2014

Existing Measure Reviews

• 14 measure updates remaining for 2014– Workplan budgeted for 24; so far 10 are done• 3 more might be done today!• After this year, all UES measures will have gone through

Guidelines compliance*

• Current budget allocation seems sufficient– Standard Protocols continue to move slowly• Budgeted for 5 Protocols per year; so far 0 done

– SIS effort has been large, but has not yet resulted in a protocol– CVR & VO slow to start due to SEEM calibration work

*Except MF weatherization due to sunset in 8/2015

Page 4: RTF Work Plan Mid-Year Re-Programming July 15, 2014

New Measure Reviews

• Upcoming measures requiring RTF Staff support– DHP for Forced Air Furnaces for Single Family and

Manufactured Homes– Duct Insulation for SF & MH– Prescriptive Duct Sealing– RTU Provisional Protocol for Heat Pumps

• Current allocation seems sufficient at this time– Assumed proposers did most development work– If no new measures submitted by fall, should

reallocate budget dollars elsewhere

Page 5: RTF Work Plan Mid-Year Re-Programming July 15, 2014

Small/Rural Work

• Light on work this year after large effort in 2013– Scoping a small task order for MH Decommissioning– Other small efforts likely to arise

• Allocation seems sufficient, but excess funds may be available from this category

• As a reminder, SRR used general RTF funds last year to accomplish some work

Page 6: RTF Work Plan Mid-Year Re-Programming July 15, 2014

Items Shifting to Staff Work

• ProCost Engine Updates & QC– Contract staff has in-depth VBA knowledge– Doing QC of ProCost model including new elements

added in past few years– Some components may still require external contract

depending on timeframe & workload• SEEM updates– Staff has already made several updates (template)

however some items may still require external contract• Annual Report done mostly in-house

Page 7: RTF Work Plan Mid-Year Re-Programming July 15, 2014

Items Added, Changed or Removed

• Likely to add small task order for QC of Grocersmart results

• Increase QC budget to AEG (formerly EnerNOC) to handle remaining UES updates

• Small contract to Abt for follow-up work on Wood Smoke analysis

Page 8: RTF Work Plan Mid-Year Re-Programming July 15, 2014

Remaining 2014 funds to allocate

Approved 2014 Allocated in Contracts$0

$200,000

$400,000

$600,000

$800,000

$1,000,000

$1,200,000

$1,400,000

$1,600,000

$51,600

Remaining to AllocateExisting Measure Review & UpdatesNew Measure Development & Review of Unsolicited ProposalsStandardization of Technical AnalysisTool DevelopmentResearch Projects & Data Devel-opmentRegional CoordinationRTF Member Support & Administra-tionRTF Management

Page 9: RTF Work Plan Mid-Year Re-Programming July 15, 2014

July – December Requests

• Inform RTF staff about any upcoming:– New UES measures– New Standard Protocols & calculators– Research projects within RTF scope to perform

• Ops Committee will be informed of how funds get re-allocated if not used for specified work plan items