Upload
jorge-herrera-b
View
223
Download
0
Embed Size (px)
Citation preview
8/8/2019 Rsrc TEL Making Substations Presentation
1/34
MAKING SUBSTATIONS MORE INTELLIGENT BY DESIGNA United Illuminating Case Study
2007 WESTERN POWER DELIVERY AUTOMATION CONFERENCE
Craig Preuss Black & Veatch Corporation
Bob Pellegrini United Illuminating Company
8/8/2019 Rsrc TEL Making Substations Presentation
2/34
2
MAKING SUBSTATIONS MORE INTELLIGENT BY DESIGN
Safety Tip for the Day
A Brief History of United Illuminating
Substation Integration
Functional Requirements
IED Selection Security
Architecture Selection
Protocol Selection Performance
Progress
Conclusion
8/8/2019 Rsrc TEL Making Substations Presentation
3/34
SAFETY TIP OF THE DAY
SAFETY TIP OF THE DAY
8/8/2019 Rsrc TEL Making Substations Presentation
4/34
A BRIEF HISTORY OF UIA BRIEF HISTORY OF UI
8/8/2019 Rsrc TEL Making Substations Presentation
5/345
A Brief History of UI
UI doesnt generate electricity
Purchases, transmits, distributes and sells itto residential, commercial and industrialcustomers
Regional distribution utility 335 square miles in Connecticut
17 towns
320,000 customers
26 Bulk Electric substations
115 and 345 kV transmission
8/8/2019 Rsrc TEL Making Substations Presentation
6/346
115
kV
115
kV
115
kV
115
kV
115
kV
115 kV
Trumbull
Substation
A Brief History of UI
Trumbull Substation
New substation
Located in Trumbull, CT
Purpose
Increased distribution system capacity Improve reliability
Two 24/32/40 MVA 115/13.8 kV LTC
transformers Three 115 kV transmission lines with ring
bus configuration
Distribution switchgear for 10 distributionfeeders
8/8/2019 Rsrc TEL Making Substations Presentation
7/34
SUBSTATION INTEGRATIONSUBSTATION INTEGRATION
8/8/2019 Rsrc TEL Making Substations Presentation
8/34
8
Substation Integration
What to do with a blank sheet of paper
Update to IEEE C37.1 includes substation
integration process1. Define near term and long term system
functionality (functional requirements)
2. Protocol selection (both inside and outside thesubstation)
3. IED selection
4. Architecture selection5. Secure the system
6. Define performance requirements
8/8/2019 Rsrc TEL Making Substations Presentation
9/34
9
Step 0 Training
Introduced UI personnel from across the enterprise
Equipment, concepts and issues, reasons, costs,
risks, benefits, and process of substation integration Who to invite?
Protection and control
SCADA
IT
Operations
Metering
Maintenance
Substation engineering, planning, technicians,engineering management
8/8/2019 Rsrc TEL Making Substations Presentation
10/34
10
Step 1 Functional Requirements
I/O
Analogs
Status
Control
Protection Time synchronization
Programmed logic Ancillary services
8/8/2019 Rsrc TEL Making Substations Presentation
11/34
11
I/O Scheme
Functional requirements were realized by creating anI/O scheme for the substation
All equipment included
8/8/2019 Rsrc TEL Making Substations Presentation
12/34
12
Measurements Analog
Metering Relays accurate
enough for distribution
and one transmissionline Revenue meters
already required for
transformers and twotransmission lines Other
LTC tap position (IED)
Transformer windingtemperature (IED) Transformer gas (IED) Inside temperature
(Transducer) DC battery voltage
(IED)
8/8/2019 Rsrc TEL Making Substations Presentation
13/34
13
Measurements Status
Hard-wired status
No RTU means distributed I/O
~ 270 hard-wired status points Breaker and switch status
SCADA enable/disable
Breaker alarms Transformer alarms
IED status (failure contact)
Security status More than traditional SCADA values
Relay targets (IED)
Communication status (IED) Breaker monitoring (IED)
8/8/2019 Rsrc TEL Making Substations Presentation
14/34
14
Measurements Control
Control
Original scheme
SCADA control through primary relays
Local control through backup relays
What happens when relay is not in service? Control through dedicated distributed I/O
HMI local control
Backup control switches
8/8/2019 Rsrc TEL Making Substations Presentation
15/34
15
Protection
Protective functions remain in relays
Interest in IEC 61850
Primary relays can support
Data concentrator can support
HMI can support Substation network can support
8/8/2019 Rsrc TEL Making Substations Presentation
16/34
16
Time Synchronization
Three methods to time synch in substation IRIG-B, NTP/SNTP, and DNP IEEE 1588 not implemented by IED vendors
IRIG-B design Fiber to substation yard Overloading of satellite clock drive outputs by IEDs Relays, meters, distributed I/O, substation
computer, and data concentrator NTP/SNTP
Ethernet equipment from time server on substationPC
DNP Transformer LTC controller and temperature monitor
None Transformer gas monitor, Battery monitor
8/8/2019 Rsrc TEL Making Substations Presentation
17/34
17
Programmed Logic
Basis for substation automation
IEC 61850
DNP report by exception to multiple masters Differentiator
Data concentrator
Distributed I/O
Supported in data concentrator but not yetimplemented
8/8/2019 Rsrc TEL Making Substations Presentation
18/34
18
Ancillary Services
Services left over:
IED configuration
File transfer Log and data capture
Diagnostic observation
Requires a high-speed network that supports morethan two simultaneous connections.
Performance improvements
Prioritizing these services
Limiting bandwidth usage by lower priority tasks(given that IEDs generally do not supportprioritization).
8/8/2019 Rsrc TEL Making Substations Presentation
19/34
19
Step 2 Protocol Selection
DNP3
Previously used between RTUs and SCADA
master
IEC 61850
Discussed Decided to support it
Too much of a paradigm shift at this point
Integration level does not decrease becausetoo many substation IEDs do not support it
8/8/2019 Rsrc TEL Making Substations Presentation
20/34
20
Step 3 IED Selection
Protection
Primary
UI had piloted and tested relays thatsupport Modbus, DNP, and IEC 61850
Ethernet Backup
UI had no interest in connecting to backup
relays
Keep integration simple
Lower cost backup relays
8/8/2019 Rsrc TEL Making Substations Presentation
21/34
21
Step 3 IED Selection
Breaker monitor
Previous monitor did not support integration
Primary relays are used
Transformer temperature monitor
Previously used IED supports DNP but notEthernet
Serial device server
Transformer gas monitor
Previous monitor did not support integration
Another monitor selected that supports DNP Serial device server
8/8/2019 Rsrc TEL Making Substations Presentation
22/34
22
Step 3 IED Selection
RTU
Existing RTU could not meet several requirements
Evaluated data concentrators and RTUs No RTUs made final cut
Hard to differentiate data concentrators
Surprising details that made the difference
No support for analog deadbands
Interpreted protocol analyzer
Support for IEC 61850
Polling support over Ethernet
NERC CIP compliance for remote access
Requires use of distributed I/O
8/8/2019 Rsrc TEL Making Substations Presentation
23/34
23
Step 3 IED Selection
Distributed I/O
Ubiquitous in industrial environment.
Industrial devices have temperature, powersupply, and surge protection issues
Not many available for substation environments
Limited form factor for two of them (combinationof I/O)
No support for fiber optic Ethernet
Capability to trip and close breakers directly
8/8/2019 Rsrc TEL Making Substations Presentation
24/34
24
Step 3 IED Selection
HMI
Original approach
Use SCADA master software for substation HMI Not possible due to technical limitations of system
architecture
Revised approach Evaluate competing HMI products
Substation products may be simpler but not
flexible enough to support customization Major vendor selected for HMI
Used by other utilities and vendors
8/8/2019 Rsrc TEL Making Substations Presentation
25/34
25
Step 3 IED Selection
Networking Equipment
Meets IEEE 1613
Fiber optics used to improve performance and makeIEC 61850 possible
Switches, router, serial device servers from samevendor
Revenue meters
Meter already being used supports DNP3, Ethernet,and IRIG-B.
Battery chargers Charger already being used supports DNP3 and
Ethernet.
Battery monitor Not connected only hard-wired contact
8/8/2019 Rsrc TEL Making Substations Presentation
26/34
26
Step 3 IED Selection
Substation Computer
Meets IEEE 1613 (mostly)
Major contribution for why SCADA mastersoftware could not be used in substation
Operating system was workable SCADA HMI RAM requirements were
greater than available for operating
system
8/8/2019 Rsrc TEL Making Substations Presentation
27/34
27
Step 4 Security
NERC CIP requirements are an enterprise issue
Requires an enterprise solution standardized across
substations Design system to promote NERC CIP compliance
Physical security perimeter monitored
Electronic security perimeter established at router SCADA network separated from corporate network
Critical cyber assets are locked in a cabinet
Future project to add in remote access
S A hi S l i
8/8/2019 Rsrc TEL Making Substations Presentation
28/34
28
Step 5 Architecture Selection
Why based upon Ethernet
Corporate WAN and SCADA WAN to
substations
Experience with relays that support Ethernet
More than SCADA data requires more thantwo serial connections
Eventual migration to IEC 61850
Application of IEEE 1615 prior to publishing asa recommended practice
St 6 P f
8/8/2019 Rsrc TEL Making Substations Presentation
29/34
29
Step 6 Performance
Substation hardened All Ethernet networking equipment meets IEEE
1613 except Fiber optic cables used inside and outside the
control house Exceptions
Monitor for substation converter required DC-DCconverter designed to meet IEEE C37.90 Some ports on some IEDs
Changeability
Distributed I/O is key Ease of expansion Provision for spare capacity
Ease of replacement Ease of maintenance
8/8/2019 Rsrc TEL Making Substations Presentation
30/34
PROGRESSPROGRESS
P
8/8/2019 Rsrc TEL Making Substations Presentation
31/34
31
Progress
September 2005
Training completed
April 2006
Conceptual design begins
February 2007 Conceptual design completed
March 2007
Control house awarded
December 2007
Project completion
8/8/2019 Rsrc TEL Making Substations Presentation
32/34
CONCLUSIONSCONCLUSIONS
Conclusions
8/8/2019 Rsrc TEL Making Substations Presentation
33/34
33
Conclusions
Making substations intelligent by design requires
Use of techniques being included in the newupcoming revision to IEEE C37.1
Not part of IEC 61850
Other standards/recommended practices can help
IEEE 1615
IEEE 1613
Many IED vendors do not support
Ethernet
Fiber optic ports
DNP3
IEC 61850
Selecting IEDs can be difficult
8/8/2019 Rsrc TEL Making Substations Presentation
34/34
MAKING SUBSTATIONS MORE INTELLIGENT BY DESIGN
A United Illuminating Case Study
QUESTIONS?Craig Preuss [email protected] (913)-458-7781