Rsrc TEL Making Substations Presentation

Embed Size (px)

Citation preview

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    1/34

    MAKING SUBSTATIONS MORE INTELLIGENT BY DESIGNA United Illuminating Case Study

    2007 WESTERN POWER DELIVERY AUTOMATION CONFERENCE

    Craig Preuss Black & Veatch Corporation

    Bob Pellegrini United Illuminating Company

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    2/34

    2

    MAKING SUBSTATIONS MORE INTELLIGENT BY DESIGN

    Safety Tip for the Day

    A Brief History of United Illuminating

    Substation Integration

    Functional Requirements

    IED Selection Security

    Architecture Selection

    Protocol Selection Performance

    Progress

    Conclusion

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    3/34

    SAFETY TIP OF THE DAY

    SAFETY TIP OF THE DAY

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    4/34

    A BRIEF HISTORY OF UIA BRIEF HISTORY OF UI

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    5/345

    A Brief History of UI

    UI doesnt generate electricity

    Purchases, transmits, distributes and sells itto residential, commercial and industrialcustomers

    Regional distribution utility 335 square miles in Connecticut

    17 towns

    320,000 customers

    26 Bulk Electric substations

    115 and 345 kV transmission

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    6/346

    115

    kV

    115

    kV

    115

    kV

    115

    kV

    115

    kV

    115 kV

    Trumbull

    Substation

    A Brief History of UI

    Trumbull Substation

    New substation

    Located in Trumbull, CT

    Purpose

    Increased distribution system capacity Improve reliability

    Two 24/32/40 MVA 115/13.8 kV LTC

    transformers Three 115 kV transmission lines with ring

    bus configuration

    Distribution switchgear for 10 distributionfeeders

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    7/34

    SUBSTATION INTEGRATIONSUBSTATION INTEGRATION

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    8/34

    8

    Substation Integration

    What to do with a blank sheet of paper

    Update to IEEE C37.1 includes substation

    integration process1. Define near term and long term system

    functionality (functional requirements)

    2. Protocol selection (both inside and outside thesubstation)

    3. IED selection

    4. Architecture selection5. Secure the system

    6. Define performance requirements

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    9/34

    9

    Step 0 Training

    Introduced UI personnel from across the enterprise

    Equipment, concepts and issues, reasons, costs,

    risks, benefits, and process of substation integration Who to invite?

    Protection and control

    SCADA

    IT

    Operations

    Metering

    Maintenance

    Substation engineering, planning, technicians,engineering management

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    10/34

    10

    Step 1 Functional Requirements

    I/O

    Analogs

    Status

    Control

    Protection Time synchronization

    Programmed logic Ancillary services

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    11/34

    11

    I/O Scheme

    Functional requirements were realized by creating anI/O scheme for the substation

    All equipment included

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    12/34

    12

    Measurements Analog

    Metering Relays accurate

    enough for distribution

    and one transmissionline Revenue meters

    already required for

    transformers and twotransmission lines Other

    LTC tap position (IED)

    Transformer windingtemperature (IED) Transformer gas (IED) Inside temperature

    (Transducer) DC battery voltage

    (IED)

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    13/34

    13

    Measurements Status

    Hard-wired status

    No RTU means distributed I/O

    ~ 270 hard-wired status points Breaker and switch status

    SCADA enable/disable

    Breaker alarms Transformer alarms

    IED status (failure contact)

    Security status More than traditional SCADA values

    Relay targets (IED)

    Communication status (IED) Breaker monitoring (IED)

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    14/34

    14

    Measurements Control

    Control

    Original scheme

    SCADA control through primary relays

    Local control through backup relays

    What happens when relay is not in service? Control through dedicated distributed I/O

    HMI local control

    Backup control switches

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    15/34

    15

    Protection

    Protective functions remain in relays

    Interest in IEC 61850

    Primary relays can support

    Data concentrator can support

    HMI can support Substation network can support

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    16/34

    16

    Time Synchronization

    Three methods to time synch in substation IRIG-B, NTP/SNTP, and DNP IEEE 1588 not implemented by IED vendors

    IRIG-B design Fiber to substation yard Overloading of satellite clock drive outputs by IEDs Relays, meters, distributed I/O, substation

    computer, and data concentrator NTP/SNTP

    Ethernet equipment from time server on substationPC

    DNP Transformer LTC controller and temperature monitor

    None Transformer gas monitor, Battery monitor

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    17/34

    17

    Programmed Logic

    Basis for substation automation

    IEC 61850

    DNP report by exception to multiple masters Differentiator

    Data concentrator

    Distributed I/O

    Supported in data concentrator but not yetimplemented

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    18/34

    18

    Ancillary Services

    Services left over:

    IED configuration

    File transfer Log and data capture

    Diagnostic observation

    Requires a high-speed network that supports morethan two simultaneous connections.

    Performance improvements

    Prioritizing these services

    Limiting bandwidth usage by lower priority tasks(given that IEDs generally do not supportprioritization).

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    19/34

    19

    Step 2 Protocol Selection

    DNP3

    Previously used between RTUs and SCADA

    master

    IEC 61850

    Discussed Decided to support it

    Too much of a paradigm shift at this point

    Integration level does not decrease becausetoo many substation IEDs do not support it

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    20/34

    20

    Step 3 IED Selection

    Protection

    Primary

    UI had piloted and tested relays thatsupport Modbus, DNP, and IEC 61850

    Ethernet Backup

    UI had no interest in connecting to backup

    relays

    Keep integration simple

    Lower cost backup relays

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    21/34

    21

    Step 3 IED Selection

    Breaker monitor

    Previous monitor did not support integration

    Primary relays are used

    Transformer temperature monitor

    Previously used IED supports DNP but notEthernet

    Serial device server

    Transformer gas monitor

    Previous monitor did not support integration

    Another monitor selected that supports DNP Serial device server

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    22/34

    22

    Step 3 IED Selection

    RTU

    Existing RTU could not meet several requirements

    Evaluated data concentrators and RTUs No RTUs made final cut

    Hard to differentiate data concentrators

    Surprising details that made the difference

    No support for analog deadbands

    Interpreted protocol analyzer

    Support for IEC 61850

    Polling support over Ethernet

    NERC CIP compliance for remote access

    Requires use of distributed I/O

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    23/34

    23

    Step 3 IED Selection

    Distributed I/O

    Ubiquitous in industrial environment.

    Industrial devices have temperature, powersupply, and surge protection issues

    Not many available for substation environments

    Limited form factor for two of them (combinationof I/O)

    No support for fiber optic Ethernet

    Capability to trip and close breakers directly

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    24/34

    24

    Step 3 IED Selection

    HMI

    Original approach

    Use SCADA master software for substation HMI Not possible due to technical limitations of system

    architecture

    Revised approach Evaluate competing HMI products

    Substation products may be simpler but not

    flexible enough to support customization Major vendor selected for HMI

    Used by other utilities and vendors

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    25/34

    25

    Step 3 IED Selection

    Networking Equipment

    Meets IEEE 1613

    Fiber optics used to improve performance and makeIEC 61850 possible

    Switches, router, serial device servers from samevendor

    Revenue meters

    Meter already being used supports DNP3, Ethernet,and IRIG-B.

    Battery chargers Charger already being used supports DNP3 and

    Ethernet.

    Battery monitor Not connected only hard-wired contact

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    26/34

    26

    Step 3 IED Selection

    Substation Computer

    Meets IEEE 1613 (mostly)

    Major contribution for why SCADA mastersoftware could not be used in substation

    Operating system was workable SCADA HMI RAM requirements were

    greater than available for operating

    system

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    27/34

    27

    Step 4 Security

    NERC CIP requirements are an enterprise issue

    Requires an enterprise solution standardized across

    substations Design system to promote NERC CIP compliance

    Physical security perimeter monitored

    Electronic security perimeter established at router SCADA network separated from corporate network

    Critical cyber assets are locked in a cabinet

    Future project to add in remote access

    S A hi S l i

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    28/34

    28

    Step 5 Architecture Selection

    Why based upon Ethernet

    Corporate WAN and SCADA WAN to

    substations

    Experience with relays that support Ethernet

    More than SCADA data requires more thantwo serial connections

    Eventual migration to IEC 61850

    Application of IEEE 1615 prior to publishing asa recommended practice

    St 6 P f

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    29/34

    29

    Step 6 Performance

    Substation hardened All Ethernet networking equipment meets IEEE

    1613 except Fiber optic cables used inside and outside the

    control house Exceptions

    Monitor for substation converter required DC-DCconverter designed to meet IEEE C37.90 Some ports on some IEDs

    Changeability

    Distributed I/O is key Ease of expansion Provision for spare capacity

    Ease of replacement Ease of maintenance

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    30/34

    PROGRESSPROGRESS

    P

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    31/34

    31

    Progress

    September 2005

    Training completed

    April 2006

    Conceptual design begins

    February 2007 Conceptual design completed

    March 2007

    Control house awarded

    December 2007

    Project completion

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    32/34

    CONCLUSIONSCONCLUSIONS

    Conclusions

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    33/34

    33

    Conclusions

    Making substations intelligent by design requires

    Use of techniques being included in the newupcoming revision to IEEE C37.1

    Not part of IEC 61850

    Other standards/recommended practices can help

    IEEE 1615

    IEEE 1613

    Many IED vendors do not support

    Ethernet

    Fiber optic ports

    DNP3

    IEC 61850

    Selecting IEDs can be difficult

  • 8/8/2019 Rsrc TEL Making Substations Presentation

    34/34

    MAKING SUBSTATIONS MORE INTELLIGENT BY DESIGN

    A United Illuminating Case Study

    QUESTIONS?Craig Preuss [email protected] (913)-458-7781