58
Land Acquisition and Resettlement Plan Document Stage: Updated Final Project Number: 41121 March 2011 Loan 2562-KAZ: Multitranche Financing Facility for the CAREC Transport Corridor 1 (Zhambyl Oblast Section) [Western Europe–Western People's Republic of China International Transit Corridor] Investment Program—Project 2 Km 305–Km 331 (Realigned Section) Resettlement Planning Document The land acquisition and resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. Prepared by the Committee for Roads, Ministry of Transport and Communications, Republic of Kazakhstan, for the Asian Development Bank (ADB).

RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

Land Acquisition and Resettlement Plan Document Stage: Updated Final Project Number: 41121 March 2011

Loan 2562-KAZ: Multitranche Financing Facility for the CAREC Transport Corridor 1 (Zhambyl Oblast Section) [Western Europe–Western People's Republic of China International Transit Corridor] Investment Program—Project 2 Km 305–Km 331 (Realigned Section)

Resettlement Planning Document

The land acquisition and resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

Prepared by the Committee for Roads, Ministry of Transport and Communications, Republic of Kazakhstan, for the Asian Development Bank (ADB).

Page 2: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor
Page 3: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

CURRENCY EQUIVALENTS (As of 31 December 2010)

Currency Unit – KazakhstanTenge (KZT) KZT 1.00 = $ 0.007 $1.00 = KZT 150.00

ABBREVIATIONS

ADB Asian Development Bank CAREC Central Asia Regional Economic Cooperation CoR Committee of Roads CSC Construction Supervision Consultant DP displaced person EA environmental assessment FS feasibility study GFP grievance focal point GosNPTsZem State Scientific and Production Center for Land Management HH Household IFI international financial institution JICA Japan International Cooperation Agency LAR land acquisition and resettlement LARF Land Acquisition and Resettlement Framework LARP Land Acquisition and Resettlement Plan LE legal entity MFF Multi-Tranche Financing Facility MOTC Ministry of Transportation and Communication NTP notice to proceed PFR periodic financing request PMC Project Management Consultant RD Roads Department RK Republic of Kazakhstan ROW right of way SPS Safeguard Policy Statement TPV third party validation TSA targeted social assistance

NOTE

In this report, ―$‖ refers to US dollars.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgment as to the legal or other status of any territory or area.

Page 4: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

GLOSSARY

Compensation Payment in cash or kind to which the affected people are entitled in order to replace the lost asset, resource or income.

Cut-off-date Date after which people will NOT be considered eligible for compensation i.e. they are not included in the list of DPs as defined by the census.

Displaced Person People affected by project related changes in use of land, water, natural resources, or income losses. DP may be members of affected households or legal entities

Encroachers People who move into the project area after the cut-off date and are therefore not eligible for compensation or other rehabilitation measures provided by the project or persons who have trespassed onto government land, adjacent to his/her own land or asset, to which he/she is not entitled, by deriving his/her livelihood there. Such act is called ―encroachment.‖

Entitlement Range of measures comprising compensation in cash or kind, relocation cost, income rehabilitation assistance, transfer assistance, income substitution, and business restoration which are due to PPs, depending on the type, degree and nature of their losses, to restore their social and economic base.

Household All persons living and eating together as a single-family unit and cooking from the same kitchen whether or not related to each other. The census used this definition and the data generated by the census forms as the basis for identifying the household unit.

Income restoration Re-establishing income sources and livelihood of DPs.

Involuntary Resettlement

Any resettlement, which does not involve willingness of the persons being adversely affected, but is forced through an instrument of law.

Land acquisition Land acquisition means the process whereby a person is compelled by a public agency to transfer all or part of the land s/he owns or possesses, to the ownership and possession of that agency, for public purposes in return for fair compensation.

Rehabilitation Assistance provided to DPs to supplement their income losses in order to improve, or at least achieve full restoration of their pre-project living standards and quality of life.

Legal Entity Legally registered enterprise established by two or several individuals or companies vested with its separate property, rights and liability such as a limited liability partnership (LLP), and joint stock company (JSC). It also includes former Soviet

Page 5: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

collective farms that were privatized into collective enterprises, and production cooperatives.

Vulnerable household

Households that might suffer disproportionately or face the risk of being further marginalized by the effects of resettlement and specifically households living below the poverty line (with per capita income of KZT 6,399.6 per month)

Page 6: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

TABLE OF CONTENTS

List of Abbreviations Glossary Executive Summary

Chapter 1 Introduction 1.1 General 1.2 LAR-Related Conditionalities 1.3 The Tranche 2 Project: Realigned Section (Km 305-331)

1 1 2 2

Chapter 2 Impact Assessment 2.1 Data Collection Methodology 2.2 Land Losses 2.3 Crop Losses 2.4 Tree Losses 2.5 Structure Losses 2.6 Business Losses 2.7 Employment Loss 2.8 Number of Affected Households/Legal Entities and Persons 2.9 Severely Affected DPs

3 3 3 4 5 5 5 5 5 6

Chapter 3 Socio Economic Profile 3.1 General Characteristics of the Project Area 3.2 Profile of the Affected Population 3.3 Vulnerable Households 3.4 Description of the Displaced Legal Entities

7 7 7

10 11

Chapter 4 Objectives, Policy Framework and Entitlements

4.1 Kazakhstan Legal Framework and Practice 4.2 ADB Involuntary Resettlement Safeguards 4.3 Comparison of ADB Resettlement Policy and Kazakhstan’s Legislation 4.4 Actions Made to Address the Gaps 4.5 Policy Framework and Entitlements for this Project

12 12 14

16 17 18

Chapter 5 Compensation and Livelihood Restoration Policy

5.1 Compensation for Termination of Land Leases from the State 5.2Compensation for Crop Losses 5.3Compensations for Losses Related to Plot Development and

Responsibilities to Third Parties 5.4 Cash Allowance and Agricultural Subsidies for Severe Loss of Productive Land

23 23 24

24

24

Chapter 6

Consultation and Disclosures 6.1 Consultations 6.2 Disclosure

26 26 27

Page 7: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

Chapter 7 Grievance Redress Participation 7.1 Grievance Focal Points, Complaints Reporting, Recording and Monitoring 7.2 Grievance Resolution Process 7.3 Disclosure of the Grievance Process

28

28 28 29

Chapter 8 Institutional Framework 8.1 Committee of Roads 8.2 Zhambyl Oblast Roads Department 8.3 Akimat (District Local Government) of Merke 8.4 Project Management Consultant (PMC-ADB)

30 30 30 30 31

Chapter 9 Resettlement Budget and Financing

32

Chapter 10 Implementation Schedule

33

Chapter 11 Monitoring and Evaluation 11.1 Internal Monitoring 11.2 Third Party Validation/Compliance Reporting

34 34 35

Appendices: A Census and Socioeconomic Survey Questionnaires 36 B List of Heads of Affected Households and Legal Entities 45 C List of Vulnerable Households 47

Page 8: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

i

EXECUTIVE SUMMARY

1. This updated Land Acquisition and Resettlement Plan (LARP) is prepared by the Committee of Roads (CoR) for the rehabilitation and upgrading of 26 km of road section from km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor 1 Investment Program under a Multi-Tranche Financing Facility (MFF). A LARP for the same tranche was prepared CoR and approved by the ADB in October 2009 covering Km 310.5 – km 389.4. However, the realignment of the section between Km 310.5 to Km 331 required the updating of the LARP. This document is the final version of the LARP covering the realigned section of the road from Km 305–km 331. 2. The DPs for this Project were originally identified during the preparation of the detailed design in March 2009. Information on the socio economic profile of the DPs was first obtained through the census and socio economic surveys conducted in May 2009. The revision of the road alignment in July 2010 resulted in the inclusion of new DPs and changes on the impacts to the original DPs. A revaluation of affected lands was conducted between August to September, 2010 and supplemental socioeconomic surveys in January 2011. 3. This revised LARP includes: i) updated number of affected households and cost of relative allowances; ii.) updated information on vulnerable households and costs for their compensation; iii.) results of the re-evaluation of affected assets; iv) consultations with DPs; and v) updated overall costs. 4. The initiation of civil works on the road section covered by this LARP is contingent on the following conditions:

a. approval of this LARP by ADB; b. full disclosure of this LARP to the public; and c. full implementation of the compensation program described in this LARP including

full delivery of compensation to DPs. 5. A total of 28 affected parties comprising 26 households and 2 legal entities will be affected under this part of Tranche-2 project. These parties will lose portion of their productive lands. One lessee will lose more than 10% of its productive land. None of the households will lose any residential land, commercial land or any other structure on the road alignment and none will require relocation from their present place of residence or business. The affected farms employed a total of 136 agricultural workers. However, none of these workers are expected to lose their employment as a result of the land acquisition. They will simply be assigned to the unaffected/remaining portion of the farmland. To ensure that workers in the affected farms are retained, a labor-maintenance allowance will be provided to the affected farmers proportionate to the amount of productive land and number of workers. 6. 115.5 hectares of agricultural land leased from the State will be acquired for permanent use. No land is used for commercial purposes. All the 26 households and 2 legal entities are long-term leaseholders. An additional 33.9 ha of State-reserved land will also be transferred to the Roads Department. 7. Affected households and legal entities reportedly plant a combination of crops on the affected lands. Commonly cited plants are safflower, barley, wheat, and hay. Government statistics shows that perennial grasses in Merke raion have an average yield between 25.3 – 37.9 centner/hectare. The average yield of cereal crops is between 9.9 to 12.4 centner/hectare.

Page 9: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

ii

8. A 0.075 portion of an apple orchard will be affected. However, the portion is not planted with any apple tree. No structure or any business establishment will be affected. A summary of the land acquisition and resettlement impacts is given in Table E-1 below.

Table E-1 Summary Land Acquisition and Resettlement Impacts

No. Description Number/Amount

1 Total number of permanently affected land parcels

28

2 Total area of land to be acquired permanently (in hectares) 115.5 3 Total area of permanently affected arable land,(in hectares) 115.5 4 Total area of permanently affected commercial land (in hectares) 0 5 Total number of privately-owned trees 0 6 Total number of affected households and legal entities 28 7 Total number of severely affected households and legal entities 1 8 Total number of vulnerable households 6 9 Total number of affected structure 0

10 Total number of households and legal entities losing business 0 11 Total number of affected persons 169

9 Affected households have an average household size of 6.5. However, there are also 7 households (29%) with 9 members or more. Two households are headed by women. Most households (92.7%) are Kazakhs. The remaining 2 households belong to other ethnic (Azeris) groups that migrated into the area. All these ethnic groups are mainstreamed into Kazakhstan’s culture and do not possess characteristics of an indigenous peoples population as defined under the ADB SPS. Six households can be considered vulnerable given their per capita income below the poverty line. These households will be provided additional allowance to help them cope with their displacement. 10. Heads of the affected households have a mean age of 48.1. Most of the heads of affected households (75%) are above 40 years old. However, six household heads (25%) are more than 60 years old. In terms of education, majority of the household heads (54.17%) have secondary education. About a third (33.33%) were able to obtain higher education. 11. Consultations with raion akimat and DPs in the entire road corridor were conducted by the Committee of Roads since 2007. Initial consultations were with the akim, deputy akims and Land Allocation Offices at the different raions. Consultation related to the preparation of the environmental assessment was conducted in Merke in January 2009. 12. In May 2009, a formal consultation was again held in Merke to explain the rights of affected persons, the valuation of losses, grievance redress and procedures in land acquisition. A total of 98 DPs attended. Representatives from local NGOs also participated. 13. During these consultations, DPs were informed on who they can contact or approach at the raion akimat and at the Zhambyl Roads Department in case of complaints or queries. Follow up discussions were made during the valuation activities in August-September 2010 and socioeconomic surveys in January 2011. 14. Efforts will be made to resolve/clarify issues at the level of the raion akimat and at the Zhambyl Roads Department. However, issues requiring attention or action from the MOTC-Project Management will be forwarded to the Project Management Consultant-ADB which

Page 10: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

iii

provides technical and supervision support to MOTC for the Project. If the case remains unsolved, a complaint can be lodged to the court. 15. Compensation and entitlements for this road section aims to assure that the DPs maintain or improve their standard of living and restore their livelihood after the project. The table below provides a summary of the compensation entitlements for various categories of DPs and degrees of impacts related to the project .

Entitlement and Compensation Framework

Asset Specifications DP Compensation Entitlements Permanent Loss Arable Land

All Land Losses irrespective of severity of impact

Owners

Cash compensation at replacement cost (without deduction of depreciation, taxes and other transaction costs) or through replacement land equal in value/productivity to the plot lost and at location acceptable to DPs where feasible.

Leaseholders of State land

Cash compensation1 for recovery of leased government land, or, renewed lease in an alternative plot

Severe Impact—>more than 10% of income/productive land lost

Owners, leaseholders of State land

Additional cash compensation equal to market value of one year crop harvest (based on a 3-year average) and agricultural subsidies for 2 crop-years

Commer-cial Lands

Owners Cash compensation at replacement cost (without deduction of depreciation, taxes and other transaction costs) or through replacement land equal in value/productivity to the plot lost and at location acceptable to DPs where feasible.

Squatters (if any)

Leased plot on State land; Self-relocation cash allowance option;.

Buildings and Structures

Owners of permanent structures

Compensation of full market value (without deduction of depreciation, taxes and other transaction costs) or, at the owner option, house for house swap

Crops Crops affected All DPs including

squatters

Crop compensation in cash at full market rate for 1 year crop harvest (based on a 3-year average)

Business and employ ment

Temporary or permanent business/ employment loss

All DPs including squatters and workers of alienable enterprises

Owner of shops/commercial establishments: if permanent loss, cash compensation equal to one year income (lost profits); if temporary, cash compensation for the period of income loss taking into account the compensation to workers for lost job (forced interruption) due to complete or temporary business cancellation – amounting up to 3-months average wages

Owner of peasant farm: allowance for labor maintenance

Resettle ment

Transport and transitional livelihood costs

All resettled DPs Allowance sufficient to cover transport expenses and livelihood expenses for one

1 Based on the base payment rates provided for under Resolution 890 (revised 7 November 2008)

Page 11: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

iv

Asset Specifications DP Compensation Entitlements month due to relocation.

Vulnerable house holds

households below the poverty line

Cash assistance. Priority in local employment for members

of vulnerable household.

Temporary Loss Land for construction sites and

burrow pits Owners (private or public)

Cash compensation at local commercial rental rates for duration of use;

Land restored to original status at the end of rental.

* HH refers to household, LE refers to legal entity, while AP refers to affected person. 16 The Zhambyl Oblast Roads Department will implement the LARP, with support from the Construction Supervision Consultants (CSC), the Zhambyl GosNPTsZem and the akimat of Merke raion. Internal resettlement monitoring will be done by the CSC. 17 An External Resettlement Monitor will be engaged by PMC-ADB to provide an independent assessment of the implementation of land acquisition and resettlement activities for the road section. 18. The Committee of Roads (CoR) is responsible for all land acquisition costs associated with the implementation of the LARP. A budget of approximately KZT 14.41million has been allocated for the implementation of this LARP. This includes the cost for compensation of losses, land re-registration, and assistance to vulnerable households. 19. Civil works for km 305 – km 331 is expected to commence on July 2011. Related to this, the LARP needs to be fully implemented and evaluated not later than June 2011.

Page 12: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

Chapter 1 Introduction

1.1 General 1. The Asian Development Bank (ADB) has agreed to provide the Republic of Kazakhstan up to $700 million for implementing the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor 1 Investment Program (the Program). The Program entails the rehabilitation, improvement or construction of several road sections along the Western Europe-Western China transit corridor and is financed through a Multi-tranche Financial Facility (MFF) divided in several tranches (Projects). Under MFF financing, fund release for each tranche is subject to the submission of a Periodic Financing Request (PFR) to be approved by ADB based on the implementation readiness of the tranche.

2. The following road sections are already funded by ADB:

Tranche/Project 1 (Loan 2503-KAZ, Km 404-443, 443-483, and Km 260-17.7km before Korday);

Tranche/Project 2 (Loan 2562-KAZ, Km 310.5-358.6, 358.6-383); Tranche/Project 3 (Loan 2697-KAZ, Km 162-260, 383-404, and the last 17.7km from

Km 260 to Korday). 3. The road sections Km 310.5 to 389.5 (Km 305-383) had been realigned/changed. As a result, the LARP for the re-aligned (Km 305-383) section requires updating.This updated Land Acquisition and Resettlement Plan (LARP)was prepared by the Committee of Roads (CR) of the Ministry of Transport and Communications (MOTC) with support from the PMC-ADB. The objective of this LARP is to assess the land acquisition-related impacts of the realigned road section and plan needed compensation/rehabilitation measures. This document fits relevant Kazakhstan laws, ADB SPS(2009) and the Program's Land Acquisition and Resettlement Framework (LARF). Its preparation involved: (i) detailed measurement surveys, (ii) valuation of affected plots, (iii) consultation with raion (district) local governments, and affected parties; and (iv) a 100% census and sample socioeconomic survey of affected households. 4. This updated LARP covering the realigned section under Tranche 2 is based on detailed design with adjustments made in the count and valuation of a number of affected lands based on additional information and valuation conducted from August to September 2010 after the approval of the road realignment and revised detailed design. An evaluation company (Daler) conducted a revaluation of the affected agricultural lands. In January 2011, PMC-ADB conducted a census, socioeconomic survey, and follow-up discussions with the DPs, in coordination with the Merke akimat and Zhambyl Oblast Roads Department. 5. This LARP includes: i) updated number of affected households and cost of relative allowances; ii.) revised count and re-evaluation of affected assets; iii) results of consultations and discussions with the DPs; and iv) overall costs.

Page 13: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

2

1.2 LAR-Related Conditionalities2

6. Based on the ADB policy and practice, signing of contract awards and civil works implementation for this Project are subject to the following conditionalities:

Contract Awards Signing and LARP implementation: i) approval of the

final/implementation-ready updated LARP by ADB and the Government; ii) conduct of third party validation.

Provision of No-Objection to initiation of civil works: i.) full implementation of the compensation program described in the LARP including the full delivery of compensation to the DPs and ii) satisfactory review by ADB and the Government of the resettlement internal monitoring/completion report and third party validation/compliance report.

1.3 The Tranche 2 Project: Realigned Section (Km 305-331) 7. Originally, the civil works for this section include the upgrading of the existing two-lane highway to a Category 1 four-lane highway. However, as a result of the border adjustments between Kyrgyz Republic and Kazakhstan, the Kazakhstan Government decided to realign the road section between Km 305-331 from 200 to 250 meters to the North of the original road. 8. All these civil works for the construction of this road section will involve permanent land acquisition. During construction, contractors may also require temporary use of land which also need to be monitored.

MAP OF THE PROJECT AREA (including the realigned section between Km 305-331)

2Based on paragraph 21, LARF CAREC Transport Corridor 1 (Zhambyl Oblast Section), MOTC, July 2008

Page 14: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

3

Chapter 2 Impact Assessment

2.1 Data Collection Methodology 9. DPs and affected assets were identified at different stages of the Project preparation. Initial assessment was made during the feasibility study in January 2008. More intensive assessments were made by the design firm (KazNIiPIDortans) during the detailed design. Information on the affected plots was derived by plotting the proposed road alignment into the land cadastre provided by the Zhambyl State Scientific and Production Center for Land Management (GosNPTsZem). The land cadastre was used in identifying the names of the registered landowners/leaseholders/DPs with permanent land use rights, land use, size of the affected plots and the proportion of affected land against the total area of the plot. For the realigned section, the DPs and their affected plots were identified in July 2010. Valuation was done from August to September 2010. PMC-ADB conducted a census and socioeconomic survey and impacts assessment of the DPs in January 2011 and incorporated in this LARP. 10. The completion date of AP identification (July 31, 2010) is the established cut-off date for these sections (Km.305-331). Persons who have occupied these acquired lands after this date will not be eligible for compensation. A total 28 parties (26 households and 2 legal entities) were found to be affected in the re-aligned road section. Of these,7 parties are new, while the remaining 21 were already included from the original list. 11. At the raion level, a committee chaired by the deputy akim was formed in Merke. From August to November 2008, the committee surveyed the affected plots and met with the owners/lessees of these plots to inform them what area of their lands would be affected. A licensed valuation company was engaged by the design firm to assess the compensation amount for the affected lands. After the road was realigned in July 2010, the design firm engaged another valuation firm (Daler) to conduct a revaluation of the affected land. An assessment of the impacts from the proposed civil works between km 305 – km 331 is presented in the following sections. 2.2 Land Losses 12. A total of 115.5 hectares of agricultural lands leased from the State will be acquired. In addition, 33.97 hectares of State reserved lands will be transferred to the Zhambyl Oblast Roads Department. None of the affected land is used for commercial or any other purpose. A total of 28 parties comprising 26 households and 2 legal entities will lose portions of their leased lands permanently. (See Table 1 and Appendix B).

Table-1 Loss of land by land category (km 331- km 389)

Land category Number of

Plots Land to be permanently

affected (in hectares) Number of affected

parties Arable land 26

2 62.98 52.52

26 households 2 legal entities

Commercial land 0 0 0 Residential land 0 0 0 Total 28 115.5 28

(An additional 33.97 hectares of land are State-reserved lands will be transferred from other State Agencies to the Zhambyl Oblast Roads Department and which will not affect any third party).

Page 15: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

4

13. All of the affected land (115.5 hectares) is leased on a long-term basis (49 years) - 62.98 hectares by 26 households and 52.52 hectares by 2 legal entities. There is no affected land that is under short term lease arrangement, privately-owned or unregistered. See table 2.

Table-2 Affected land by type of ownership/tenurial status of affected households&

legal entities Ownership/Tenurial Status Land to be acquired (in

hectares) Number of affected households

(HH) / legal entities (LE) Privately owned 0 0 Long-term lease 62.98

52.52 26(HH)

2(LE) Short-term lease 0 0 Unregistered 0 0 Total 115.5 28

2.3 Crop Losses 14. Affected households and legal entities interviewed during the census/socio economic surveys reportedly plant a combination of crops in the affected lands. Commonly cited plants include Safflower, barley, wheat, hay etc. During the census, interviewees were asked what crops they plant on the affected portions of their land. The farming households and legal entities reported that they plant crops such as safflower, barley, wheat, and hayon the affected lands. See table 3.

Table-3 Crops reportedly planted on the affected land

(n = 26 households and 2 legal entities)

LE PK ―Aspara‖ plants 3 types of crop: barley, wheat and hay, H-d Dzhumatayev Ali plants both safflower and hay, H-d AlmassovAshimhan, plants both barley and hay and H-d Alimbekov A. plants barely and hay.

15. Of the total affected agricultural land, about 31.6 ha is planted with safflower followed by barley with 30.72 ha, wheat 20.13 ha, and hay 29.7. Around 0.075.ha. of an apple orchard will also be affected. Based on regional official statistics of 2010, the average wheat yield is 15.25 centner/ha, feed crops yield 52.2 centner/ha. (1 centner = approximately 100kg). 2.4 Tree Losses 16. No tree will be affected. There is no apple tree planted on the.075 hectares of affected apple orchard. Hence, the DP was only compensated for land losses.

Perennial Grasses and Cereal Crops Planted on the Affected Land

Number of Affected Households/Legal Entities

Planting

Land to be acquired (in ha)

Safflower 8 HH 1 LE

28.10 3.50

Barley 8 HH 1 LE

14.38 16.34

Wheat 5 HH 1 LE

14.38 16.34

Hay 6 HH 1 LE

12.93 16.34

Orchard 1 h/h 0.75 Not indicated 3 h/h 3.03

Page 16: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

5

2.5 Structure Losses 17. No structure will be affected by the new road alignment at Km 305 to 331.

2.6 Business Losses 18. No business will be affected by the new road alignment at Km 305 to 331. 2.7 Employment Loss 19. No worker is expected to be laid off as a result of the project. About 136 agricultural workers employed by some farming households and agricultural firms/collectives (legal entities) for crop production or livestock raising will continue to be employed by the owners of the affected farms despite of the reduction in the area of their farmland. To ensure that workers in the affected farms are retained despite the reduced area of the affected farms, a labor-maintenance allowance will be provided to the affected farmers proportionate to the amount of productive land and number of workers. However, to provide an alternative or additional source of employment for these workers, information on available jobs from the project will be disseminated in the project area. 2.8 Number of Affected Households/Legal Entities and Persons 20. A total of 26 households with a population of 169, (average 6.5 per household) are likely to experience various losses/impacts from the implementation of the project. These households will lose access to their agricultural leased lands and the income they derive from it. Two legal entities will also lose marginal portions of their land plots. See table 4- below.

Table-4 Details of affected households, legal entities and APs by category

DP Category Number of Affected

Households (HH)/ Legal Entities (LE)

Number of DPs

Remarks

(x impact type)

Absolute (Without double counting)

A. Agricultural Land -owned/leased by households -owned/leased by legal entities

26 HH 2 LE

26HH 2 LE

169 population for 24 hh

Sub-total (A) 28 28 B. Crops and Trees

Titled owners/leaseholders/permanent land users -owners/leaseholders (households) -owners/leaseholders (legal entities)

0/26 HH 0/2 LE

Same as A1

Sub-total (crops and Trees) 28 28 C. Total (A+B) 56 28 169

2.9 Severely Affected DPs 21. It was revealed from the survey that only one household will lose more than 10% of its productive land. Mr. Almassov Ashimkhan’s household will lose 2.01 hectares of land which is

Page 17: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

6

equivalent to about 10.6% of his total productive land. See Table 5. There are four other leaseholders who will lose more than 10% of their affected plots, but have other leased plots which make the impact on their total productive land marginal (less than 10%). All five leaseholders were compensated for an additional one year crop harvest.

Table-5 Severely affected Households

№ Land use right Acquired area

(ha) Percentage from

affected land area Percentage from total land holding

1 Long-term leaseholder 2.01 10.06 10.6 2 Long-term leaseholder 13.2 26.4 4.6 3 Long-term leaseholder 1.58 18.8 8.2 4 Long-term leaseholder 1.41 10.1 6.7 5 Long-term leaseholder 0.78 13.2 5.7 Total 5 Households 18.98

Page 18: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

7

CHAPTER 3

SOCIO ECONOMIC PROFILE

3.1 General Characteristics of the Project Area 22. The project is situated within Zhambyl Oblast, which is one of the four oblasts (provinces) in the Southern Region of Kazakhstan. Zhambyl is subdivided into 10 raions (districts), 12 urban settlements and 367 villages. The realigned section from Km 305 to 331will passes through the raion of Merke only. 23. Zhambyl Oblast covers 144,300 sq. km. The oblast center is Taraz, once a main stop on the Silk Road. The population of Taraz is 336,100 (34 percent of the total oblast population). Most of the villages and urban settlements were constructed as part of the state and collective farm structure. Population in the Oblast in 2007 was a little over 1 million people. Population density is 6.9 persons per sq. km. Almost half of population lives in towns. The urban population is 451,200 (45.1%), while the rural population is 549,900 (54.5%).The Merke raion has a combined population of 75,100, with a population density of about 10.6 persons per km2.The population in the oblast is mostly Kazakhs (65%). Russians account to about 18.1%. There are also Uzbeks, Tatars, Ukrainians and other ethnic groups in the area.

24. In a report prepared in June 2010, Zhambyl Oblast’s economic development is estimated to be below that of the average Kazakhstani oblast.3 The oblast’s primary industries are crop agriculture, livestock and poultry raising. Government provides agricultural subsidies, but only to a limited extent. It has 1,485 small and medium-sized enterprises operating. Another 2,659 enterprises are inactive for various reasons. 1,919 were liquidated and 102 are being liquidated, according to the Statistics Department. for a major reason cited why many farms in the oblast are inactive is the lack of working capital and an unwillingness by banks to lend. In recent years the only source of credit for farmers has been the State Fund for Agricultural Support which has very limited loan potential.

25. The Zhambyl Oblast Statistics Department indicates the region’s average monthly pay is US $331. The income below the subsistence minimum is estimated at4.8 percent. Zhambyl oblast now ranks 3rd among the oblasts in Kazakhstan in terms of the percentage of people with incomes below the subsistence minimum.4 As of January 2011, unemployment rate in Zhambyl Oblast is estimated at around 5.6%5 Half of those with income sources are self-employed, with majority relying on agriculture particularly livestock raising.

3.2 Profile of the Affected Population 3.2.1 Number and Membership of Affected Households 26. A total of 26 households will be affected. The average household size is 6.5. However, there are also 7 households (26.9%) with 9 or more members. 24households or 92.3% are headed by male, while 2households or 7.7% by female.

3 Source: CentralAsiaOnline.com, July 2010 4 Source: www.eng.stat.kz/population standard of living 5 State Statistical Agency, January 2011

Page 19: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

8

Table-6

Size of affected households

Household Size Number Percent 1 – 4 3 11.5 5 – 8 12 46.1 9 and above 7 26.9 No data 4 15.4 Total 26 100.0 3.2.2 Residence and Ethnic Composition 27. All the affected HHs reside in villages within the Merke raion. In terms of ethnic composition, almost all of the affected households (92.7%) are Kazakhs. The 2 other households are Azeris. 28. The Kazakhs constitute majority of the native local population. The 2 Azeri households are migrants who settled in the area over the past years. None of the ethnic groups in the project area maintain cultural and social identifies separate from the mainstream Kazakhstan’s society fitting the ADB definition of Indigenous Peoples. They have full and equal access to institutions and economic opportunities as the rest of the population. Because of this, the project will not trigger the ADB policy on indigenous peoples. 3.2.3 Age and Education Level of Household Head 29. Heads of the affected households have a mean age of 48.1. Most of the heads of affected households (69.2%) are above 40 years old. Six household heads (23.1%) are more than 60 years of age, while four households are between the age of 31-40 years. The two women household heads are above 50 years. In terms of education, half of the household heads have secondary education. Those who were able to obtain higher education comprise 30.8%. See tables 7 and 8.

Table-7 Age of surveyed household heads disaggregated by gender

Age Range Male Female Total Percent

31 – 40 4 0 4 15.4 41 – 50 5 0 5 19.2 51 – 60 6 1 7 26.9

61 and above 5 1 6 23.1 No data 4 0 4 15.4

Total 24 2 26 100.0

Table-8 Education profile of surveyed household heads

Education Men Women Total Number Number Number Percent Higher 6 2 8 30.8 Secondary 13 0 13 50.0 No data 5 0 5 19.2 Total 24 2 26 100.0

Page 20: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

9

3.2.4 Size of Landholding 30 Lands owned/leased by the affected households vary greatly in size. Two affected households (7.1%) lease between 1-10 hectares, while another 57% lease between 11-70 hectares. There are also 8 households and two legal entities (35.7%) who lease more than 100 hectares of land. Hence, for most leaseholders impact of land acquisition from the project is marginal considering the total land holding of the affected HHs. See table 9 and Appendix B.

Table-9

Total landholding of displaced households and legal entities Total land holding (in ha) HH LE Total Percent

10 and below 2 0 2 7.1 11 – 40 12 0 12 42.9 41 – 70 4 0 4 14.3 More than 100 8 2 10 35.7 Total 26 2 28 100.0

3.2.5 Household Income and Expenditures 31. Agriculture is the primary income source of the affected farming households. Commonly planted crops are wheat, barley, safflower and hay. Hence, they are concerned about the possible disruption that the proposed road construction may have on their livelihood to some extent. 32. As shown in Table 10 below, the incomes and expenditures of different households vary greatly. All of the affected households earn and spend more than 16,000 KZT monthly. Out of 26 HHs, 14 HHs (53.8%) earn 60,000 KZT or more per month. Majority of the households(78%) spend 60,000 KZT & more per month. The average monthly income of households amounts approximately to 86, 266 KZT, while average expenditure is102,333 KZT. Hence, the overall trend is that household expenditure exceeds income, and especially in the highest income bracket (above KZT 90,000). It is possible that they either have understated their monthly income, or possibly are borrowing to cover the deficit.

Table-10 Distribution of monthly income and expenditure of surveyed HHs

Value (KZT) Number of HH Number of HH 16,001-30,000 1 0 30,001-45,000 2 1 45,001-60,000 7 3 60,001-75,000 6 7 75,001-90,000 4 8 Above 90,000 4 5

No Data 2 2 TOTAL 26 26

Average: 86,266 KZT 102,333 KZT

Page 21: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

10

3.2.6 Living Conditions 33. Majority of the interviewed households have houses made of bricks or saman (clay with straw) which were built between 1948 and 2009. An average house has one floor with about 5 rooms and all has access to electricity. Majority of the HHs (62%) have landline telephones. However, only 42% have access to potable water while about 38% have gas for fuel. See table-11 below.

Table-11 Living conditions of surveyed affected households

Criterion Number % a. Type of house Brick 9 35 Saman 12 46 Concrete 3 12 No data 2 8 b. When built Pre-1950 5 19 1951-1980 10 38 1981-present 5 19 No data 6 23 c. No. Rooms 3-4 7 27 5-7 16 62 7 or more 1 4 No data 2 8 d. Source of drinking water Piped 11 42 Well 10 38 No data 5 19 e. Fuel for Cooking Gas 10 38 Coal 9 35 No data 7 27 f. Electricity 26 100 g. Telephone 16 62

3.3 Vulnerable Households 34. In Kazakhstan, households with an average per capita income below the poverty line (defined as 40% of the subsistence minimum) are considered vulnerable and are entitled to the Targeted Social Assistance (TSA) program of the government. As of January 1 2010, the official subsistence minimum in Kazakhstan is 15,999 KZT per capita. The poverty line therefore is

Page 22: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

11

6,399,6 KZT per capita. TSA for each household is computed as follows: Household income – (poverty line x number of family members). In addition, there are State social benefits, financed from the central budget, that provide monetary transfers to citizens in need due to disability, loss of the family breadwinner, or old age. The socioeconomic survey conducted in January 2011 identified a total of 6 households with average reported per capita income below the poverty line (see Appendix C). 3.4 Description of the Displaced Legal Entities 35. Two legal entities will be affected under the realigned section of Tranche 2 (km305-331) Project. These legal entities (GP ―Mukashev and Company‖ and PK ―Aspara‖) are agricultural firms/collectives producing crops primarily for raising livestock (sheep, cows etc.). Crops cultivated by these firms include barley, wheat, safflower and hay. Average annual income varies greatly depending on the size of land holding and nature of activities. These legal entities usually have both permanent and seasonal laborers. PK ―Aspara‖ hires both male and female laborers/workers (27males and 79 females.). Total owned land is 8224 ha. Also they raise livestock (4240 sheep and 260 horses). They own 13 tractors, 1 lorry, 12 cars and 7 wells. The operations of these legal entities will continue on their remaining plot. None of their workers are expected to be laid-off as a result of the land acquisition.

Page 23: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

12

Chapter 4 Objectives, Policy Framework, and Entitlements

36. The Land Acquisition and Resettlement Policy Framework (LARF) 6 for the Project agreed between RK and ADB defines the eligibility for compensation and rehabilitation assistance, and details the entitlements for each impact type, as well as procedures for valuation, compensation, complaints consideration, consultations and disclosure and monitoring/evaluation. It combines existing legal framework and procedures for land acquisition in Kazakhstan and international good practice as embodied in the policies of ADB. 4.1 Kazakhstan Legal Framework and Practice 37. In Kazakhstan, land is owned by the State but can be transferred, sold or leased to individuals or legal entities. Most leases are on a long-term basis (generally for 49 years). A few others lease for the short-term (between 1 to 5 years). The State can reclaim private lands and lands leased from the State only for specific uses, including road construction, and only after compensating the owner for the asset and other losses. 4.1.1 Kazakhstan Constitution 38. Kazakhstan laws and regulations regarding land and land ownership are derived from the Constitution, which states that land (surface and underground) is owned by the State, but can also be privately-owned (Article 6.3). Article 26.3 also states that no one may be deprived of property unless stipulated by a court decision. Forcible expropriation of property for public use in extraordinary cases stipulated by law may be exercised after payment of equivalent compensation. 4.1.2 The Land Code of 2003 39. The Land Code (RK Code No. 442-II of 20 June 2003, amended on 6 July 2007) which covers the acquisition of land for State needs stipulates that a plot may be reserved for State needs by way of purchase or by granting an equivalent plot with the consent of the owner or land user (Article 84.1). Road construction is one of several grounds for purchasing private land or terminating long-term leases (Article 84.2.4). In the case of land under lease, the land user is compensated for the full amount of losses and, if the land user wishes, may be granted an alternative plot to lease under the same terms and conditions (Article 84.4). However, the availability of suitable land to swap varies from one location to another. 40. Land owners/users must be notified of the decision to purchase 1 year in advance, unless the owner/user agrees to release the land more quickly (Article 85.2). If part of a plot is acquired and the remaining area cannot be used as before, the whole plot must be purchased (Article 86 para 2). 41. The price of a plot purchased for State needs is determined by agreement with the owner/land user (Article 87.1). The payment price includes the market value of a plot or rights to it and of real estate situated on it, as well as all losses caused to the owner/land user due to land loss, including losses due to the premature termination of obligations to third parties (Article 87.2). If the owner or land user agrees, another plot of equal value can be substituted instead of cash compensation (Article 87.3). 6 Land Acquisition and Resettlement Framework, Central Asia Regional Economic Cooperation (CAREC) Transport Corridor 1 (Zhambyl Oblast Section) Project, Ministry of Transport and Communications, Republic of Kazakhstan, July 2008

Page 24: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

13

42. Under the Land Code, basic rates of payment for land plots were established for determining the value of land. Cadastral value of the land plots which are granted by the state for agricultural production is determined using adjustment coefficients based on the quality/condition of a given land plot, its location, water supply, remoteness from service centers and the condition of a land plot by type of land and type of soil.7 43. If an owner disagrees with the decision to purchase (acquisition), the price offered or other purchase conditions, the authority issuing the decision to purchase can file an expropriation case in court (Article 88 paragraph 1) after the year of notification has passed (Article 88 paragraph 2). In disputed cases, the land cannot be taken until the court adjudicates a settlement specifying compensation levels and losses (Article 166.7). Compensation must be paid to the owner or user before the reservation is processed by the regional level office of the Land Resources Management Committee and registered at the Registration Service Committee. Only then can work be allowed to begin on the land. 44. The Land Code of RK does not entitle encroachers to compensation for the loss of access to lands they use informally (squatters) or those who have not registered their claims to land. Moreover, no additional provisions are made for those who are losing a significant portion (10% or more) of their productive assets. 4.1.3 Law on Housing Relations 45. When residences are affected, the Law on Housing Relations also applies. If a house is demolished for State needs, the owners can choose either to receive a new residence or receive compensation equal to the market value of the house. An owner who chooses the replacement option can select a home from a list of available homes. If the value of the selected house is higher than the market value of the building to be demolished, the exchange is completed. If the cost of the selected building is lower than the market value of the one to be demolished, the owner is compensated in cash for the difference. Disagreements over the evaluation are settled in court. 4.1.4 Labor Code 46. Registered workers from affected business establishments/enterprises who lose their work as a result of discontinuation of the operations of the establishment are entitled to compensation equivalent to their one-month salary as per the Labor Code of RK. 4.1.5 Standard Land Acquisition Practices and Process 47. Land acquisition for public needs in Kazakhstan generally follows the following procedures:

Proposed alignment and estimates of the amount of land to be acquired permanently or temporarily, as well as estimated cost of acquisition, rental and restoration of affected lands are included in the feasibility study (FS).

The FS is sent to the oblast and raion akimat for review and comments. In the case of republican roads, the FS is sent to the Committee of Roads in Astana for review.

Based on the tentative alignment, registered owners/leaseholders are notified initially that their land will be acquired.

7In accordance with the Land Code, the RK issued Resolution No. 890 in 2 September 2003 (revised in November 2008) establishing the base payment rates for land plots in providing for private ownership, leasing by the State and payment for selling the right to lease land.

Page 25: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

14

The detailed design (DD) is prepared to firm up the alignment and assessment of land acquisition requirements. The DD includes detailed maps and individual landholdings to be affected, ownership data from the cadastre and estimated compensation for acquisition and losses.

Once the final alignment is agreed with local officials, the agency that requires the land requests the raion akimat to call owners and leaseholders together to discuss the LAR process.

The akimat issues a resolution on the land acquisition and registers the resolution with the oblast Department of Justice. Owners are officially notified of the extent of land acquisition of their properties.

The raion akimat establishes an evaluation commission that includes officials and land owners. Inputs are sought from licensed valuators in establishing official compensation amounts. For this project, greater reliance is placed on the valuation report of the licensed valuators.

Once the official compensation amounts have been established, negotiation between government and the affected persons starts. Signed agreements are registered with the oblast Department of Justice. Based on the agreements, compensation amounts are processed and delivered to the affected person.

If agreement cannot be reached, the government agency requiring the land will initiate a court appeal for expropriation after the one-year notification period ends.

Once the court renders a decision, the compensation amount will be transferred to the account of the displaced land user. Land cannot be accessed until compensation is completed and the title is transferred.

4.2 ADB Involuntary Resettlement Safeguards 8

48. ADB Safeguard Requirements 2: Involuntary Resettlement aims to avoid involuntary resettlement wherever possible; to minimize involuntary resettlement by exploring project and design alternatives; to enhance, or at least restore, the livelihoods of all displaced persons in real terms relative to pre-project levels; and to improve the standards of living of the displaced poor and other vulnerable groups. 49. ADB SPS (2009) has the following requirements related to involuntary resettlement:

a. Compensation, Assistance and Benefits for Displaced Persons (DPs) – Compensate/assist those with formal legal rights to the land lost and those who have

claims to lands that are recognized or recognizable under national laws. DPs who have neither formal legal rights nor recognized or recognizable claims to such land are entitled only to compensation for non-land assets.

- Compensate for affected lands, structures and other assets and put in place a comprehensive income and livelihood rehabilitation program prior to displacement

- Give preference to land-based resettlement strategies for displaced persons whose livelihoods are land-based. Provide physically displaced persons with relocation assistance, secured tenure to relocation land, better housing at resettlement sites with comparable access to employment and production opportunities, and civic infrastructure and community services.

- Promptly compensate economically displaced persons for the loss of income or livelihood sources at full replacement cost, and provide other assistance (i.e. access to credit, training, and employment opportunities) to help them improve, or at least restore, their income-earning capacity, production levels, and standards of living to pre-displacement levels.

8ADB. Safeguards Policy Statement, June 2009. Manila

Page 26: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

15

- Provide displaced persons with opportunities to share project benefits in addition to compensation and resettlement assistance.

b. Social Impact Assessment

- Conduct socioeconomic survey(s) and a census, with appropriate socioeconomic baseline data to identify all persons who will be displaced by the project and to assess the project’s socioeconomic impacts on them.

- As part of the social impact assessment, identify individuals and groups who may be differentially or disproportionately affected by the project because of their disadvantaged or vulnerable status.

c. Resettlement Planning

- Prepare a resettlement plan based on the social impact assessment and through meaningful consultation with the affected persons if the proposed project will have involuntary resettlement impacts

- Include in the resettlement plan measures to ensure that the displaced persons are (i) informed about their options and entitlements pertaining to compensation, relocation, and rehabilitation; (ii) consulted on resettlement options and choices; and (iii) provided with resettlement alternatives.

- Pay adequate attention to gender concerns to ensure that both men and women receive adequate and appropriate compensation for their lost property and resettlement assistance, if required, as well as assistance to restore and improve their incomes and living standards.

- Analyze and summarize national laws and regulations pertaining to land acquisition, compensation payment, and relocation of affected persons in the resettlement plan; and compare such laws and regulations with ADB’s involuntary resettlement policy principles and requirements. If a gap between the two exists, propose a suitable gap-filling strategy in the resettlement plan in consultation with ADB.

- Consider all costs of compensation, relocation, and livelihood rehabilitation as project costs.

- Include detailed measures for income restoration and livelihood improvement of displaced persons in the resettlement plan. For vulnerable persons and households, include measures to provide extra assistance so that they can improve their incomes in comparison with pre-project levels.

- Finalize the resettlement plan soon after the completion of engineering design Ensure that the final resettlement plan (i) adequately addresses all involuntary resettlement issues pertaining to the project, (ii) describes specific mitigation measures that will be taken to address the issues, and (iii) ensures the availability of sufficient resources to address the issues satisfactorily.

- Consult with displaced persons identified after the formulation of the final resettlement plan and inform them of their entitlements and relocation options. A supplementary resettlement plan or a revised resettlement plan should be submitted to ADB for review before any contracts are awarded.

- Use qualified and experienced experts to prepare the social impact assessment and the resettlement plan.

d. Information Disclosure

- submit the following documents to ADB for disclosure on ADB’s website: (i) a draft resettlement plan and/or resettlement framework endorsed by the borrower/client before project appraisal; (ii) the final resettlement plan endorsed by the borrower/client; (iii) a new resettlement plan or an updated resettlement plan, and a corrective action plan prepared during project implementation, if any; and (iv) the resettlement monitoring reports.

Page 27: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

16

- Provide relevant resettlement information in a timely manner, in an accessible place and in a form and language(s) understandable to affected persons and other stakeholders. For illiterate people, use other suitable communication methods.

e. Consultation and Participation

- Conduct meaningful consultation with DPs, their host communities, and civil society for every project and subproject identified as having involuntary resettlement impacts.

- Pay particular attention to the need of disadvantaged or vulnerable groups, especially those below the poverty line, the landless, the elderly, female-headed households, women and children, Indigenous Peoples, and those without legal rights to land.

f. Grievance Redress Mechanism

- establish a responsive, readily accessible and culturally appropriate mechanism to receive and facilitate the resolution of affected persons’ concerns and grievances about physical and economic displacement and other project impacts, paying particular attention to the impacts on vulnerable groups.

g. Monitoring and Reporting

- monitor and measure the progress of implementation of the resettlement plan. For projects/subprojects with significant LAR impacts, qualified and experienced external experts are retained to verify internal resettlement monitoring information. If any significant involuntary resettlement issues are identified, prepare a corrective action plan to address such issues. Do not proceed with implementing the Project until such planning documents are formulated, disclosed and approved.

h. Unanticipated Impacts

- If unanticipated involuntary resettlement impacts are found during project implementation, conduct a social impact assessment, update the resettlement plan or formulate a new resettlement plan

i. Special Considerations for Indigenous Peoples

- avoid physical relocation of Indigenous Peoples that will result in adverse impacts on their identity, culture, and customary livelihoods. If adverse impacts cannot be avoided, formulate a combined Indigenous Peoples plan and resettlement to meet all relevant requirements specified under ADB Safeguard Requirements 3: Indigenous People.

j. Negotiated Settlement

- acquisition of land and other assets through a negotiated settlement whenever possible is encouraged.

- Negotiated settlements that would result in expropriation are subject to third-party validation to ensure that the compensation is based on fair price (replacement cost) of land and/or other assets, and is based on meaningful consultation with DPs.

4.3 Comparison of ADB Resettlement Safeguards and Kazakhstan’s Legislation 50. There is congruence between Kazakhstan’s laws and ADB’s Resettlement Safeguards with regard to compensating at replacement value for affected privately-owned assets. However, ADB’s Resettlement Safeguards does not consider the absence of land rights of DPs as an impediment to receiving compensation for non-land assets. Likewise, ADB Policy

Page 28: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

17

stipulates the improvement of livelihood for vulnerable DPs. Key differences between ADB Resettlement Safeguards and Kazakhstan’s Legislation are outlined in Table-12 below.

Table-12 Comparison of Kazakhstan's Land Acquisition/Resettlement Practice/Policy

and ADB Resettlement Policy

Kazakhstan’s Land Acquisition Practice ADB Involuntary Resettlement Policy Compensation for land and non-land assets is only for titled landowners or leaseholders who purchased the right to land leasing from the State.

DPs without formal legal rights and claims are entitled to compensation for non-land assets

Compensation of private agricultural land plot (with no account for losses) purchased by the land owner from the State and subject to acquisition for public needs shall be determined as equal to the amount paid to the State.

Compensation of private agricultural land is based on current market value.

Crop, tree and structure losses compensated only to registered DPs

DPs without formal legal rights and claims are entitled to compensation for crop, tree and structure losses (non-land assets)

Objective is more on compensation for affected privately-owned assets, not restoration of livelihood and standards of living

Considers as a key objective, the restoration of livelihood and standards of living displaced persons, regardless of tenure or legal status

No provision for additional assistance to vulnerable groups, relocation costs or transition period.

Stipulates enhancement of livelihood if possible and improvement of livelihood for vulnerable DPs

Uses negotiated settlement as an initial approach to acquiring land without the requirement for third party validation. If agreement cannot be reached, initiates expropriation procedures,

Encourages acquisition through a negotiated settlement subject to third party validation, to ensure compensation at replacement costs and conduct of meaningful consultations with DPs

51. Differences in the national legislation and practice and ADB Policy was reconciled through the adoption of a Land Acquisition and Resettlement Framework for the MFF. The LARF ensures: (a) that compensation is provided at replacement cost of all items, (b) DPs without legal rights to land are compensated for non-land assets, (c) that DPs are assisted in restoring their livelihood, and (c) the provision of allowances for DPs who may experience severe losses of productive assets and DPs who are vulnerable. 4.4 Actions Made to Address the Gaps 52. In 2008, the Government of Kazakhstan (through the Ministry of Transport and Communication) agreed to adopt a Land Acquisition and Resettlement Framework (LARF) for the Project that incorporates both Kazakhstan’s laws and procedures and the Resettlement Policies of its partner-International Financial Institutions (IFIs) for the Project, including ADB. Specific to ADB, a modified LARF was prepared in July 2008 that reflects the ADB Processing Requirements related to involuntary resettlement. The Framework applies to all persons whose private land status is affected permanently or temporarily due to the Project, including purchase and temporary use during construction. It also applies to people whose use of state land, sanctioned or not, changes as a result of the investment. The Framework does not apply to State land that is transferred from one authority to another, or used for the reconstruction, unless third parties are adversely affected by the transfer or use. 53. The LARF ensures that: (a) compensation is provided at replacement cost of all items, (b) DPs are given livelihood rehabilitation, and (c) DPs who may experience severe losses of productive assets or are vulnerable are provided with subsidies or allowances.

Page 29: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

18

4.5 Policy Framework and Entitlements for this Project 4.5.1 Entitlements to Compensation 54. The following groups of DPs are included in the LARF and will be addressed in the LARP for this road section:

All DPs losing land either with legal title, lease holding land rights or without legal status;

Tenants and sharecroppers whether registered or not; Owners of buildings, crops, plants, or other objects attached to the land; and, DPs losing business, income, and salaries temporarily or permanently.

55. To enable the project to compensate unregistered land users under Kazakhstan’s laws, representatives from the Zhambyl Land State Scientific and Production Center for Land Management (GosNPTsZem) advised displaced land users to register or update the registration of their lands. In the previous tranche, 5 unregistered land users identified during the surveys were assisted in having their land claims registered. This entitled them to be compensated according to standard Kazakh legal framework. The assets/structures on the affected plots of land users without titles have been evaluated by exactly the same criteria as those with titles. For this project (Tranche/Project 2), there are no unregistered land users. In case unregistered land users are identified later, similar assistance for registering their lands will be provided. 56. Compensation and entitlements must ensure that the DPs are able to restore their livelihood and maintain or improve their standard of living after the project. For purposes of eligibility, the cut-off date in this realigned road section is the completion date of DP identification (31 July 2010). The owners and leaseholders of the affected lands received new notifications in July 2010. Official notifications were sent by the Merke raion akimat after the issuance of the akimat resolution on land acquisition. Table 13below provides the entitlements for various categories of DPs and degrees of impacts related to the Project.

Page 30: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

19

Table- 13 Entitlement and Compensation Framework

Asset Specifications DP Compensation Entitlements

Permanent Loss Arable Land All Land

Losses irrespective of severity of impact

Owners

Cash compensation at replacement cost (without deduction of depreciation, taxes and other transaction costs) or through replacement land equal in value/productivity to the plot lost and at locations acceptable to DPs where feasible.

Leaseholders of State land

Cash compensation for recovery of leased government land9, or, renewed lease in an alternative plot

Severe Impact—>more than 10% of income/ productive land lost

Owners, leaseholders of State land

Additional cash compensation equal to market value of one year crop harvest (based on a 3-year average) and agricultural subsidies for two crop-years.

Commercial Plots

Owners Cash compensation at replacement cost (without deduction of depreciation, taxes and other transaction costs) or through replacement land equal in value/productivity to the plot lost and at locations acceptable to DPs where feasible.

Squatters (if any)

Leased plot on State land; Self-relocation cash allowance option;

Buildings and Structures

Owners of permanent structures

Compensation of full market value (without deduction of depreciation, taxes and other transaction costs) or, at the owner option, house for house swap

Crops Crops All DPs including squatters

Crop compensation in cash at full market rate for 1 year crop harvest (based on a 3-year average)

Business and employ ment

Temporary or permanent business/ employment loss

All DP including squatters and workers of alienable enterprises

Owner of shops/commercial establishments: if permanent loss, cash compensation equal to one year income (lost profits); if temporary, cash compensation for the period of income loss taking into account the compensation to workers for lost job (forced interruption) due to complete or temporary business cancellation – amounting up to 3-months average wages

Owner of peasant farm: allowance for labor maintenance Resettle ment

Transport and transitional livelihood costs

All resettled DPs

Allowance sufficient to cover transport expenses and livelihood expenses for one month due to relocation.

Vulnerable house holds

Households below the poverty line

Cash assistance equivalent to 1-month minimum wage. Priority in local employment for members of vulnerable

household.

Temporary Loss Lands for construction sites and burrow pits

Owners (private or public)

Cash compensation at local commercial rental rates for duration of use;

Land restored to original status at the end of rental.

9 Based on the base payment rates provided for under Resolution 890 (revised 7 November 2008)

Page 31: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

20

57. The entitlements provided in the matrix are further elaborated below:

a. Arable land impacts. The households with private ownership will be given cash compensation at replacement cost or through replacement land equal in value/productivity to the plot lost and at location acceptable to DPs where feasible and also cash compensation for crop losses at current market rates. Actual transaction taxes/fees will be paid by the Committee of Roads (CoR) or waived by the concerned agency. Compensation will also include costs incurred by the owner related to land plot development, maintenance, protective measures and soil fertility improvement, taking into account the inflation, as well as the losses, that the owner incurred related to early termination of obligations to third parties.

Leaseholders will be paid cash compensation for losing their right-to-lease the affected land following the established base rates as per Resolution No. 890 (revised on 7 November 2008). They will also be given compensation for works related to land plot development, maintenance, protective measures etc. To facilitate livelihood restoration of leaseholders, leaseholders may be granted an alternative plot to lease depending on the plot availability.

If the permanent or temporary acquisition results in partial or complete damage to irrigation, drainage and erosion-preventive structures (systems), losses will be determined based on the cost for constructing of new facilities or rehabilitation of existing structures (systems), including the cost of design and survey works.

b. Residual agricultural land impacts. Residual portions of the acquired lands which

are rendered unusable will be included in the affected land and compensated as indicated above subject to the preference of the DP.10 Alternatively, the DP has the option of seeking an alternative plot or of changing the intended use of the remaining plot i.e. from agricultural to commercial. DPs may also explore the reorganization and swapping of plots with adjacent owners to improve the economic viability of the remaining agricultural lands.

c. Severe impact losses. When >10% of an DP income or agricultural land is affected, DP (owners, leaseholders, sharecroppers, and squatters) will receive an additional allowance for severe impacts equal to one year’s harvest from the acquired land. The amount of the harvest is determined based on the average yield in the past three years. Assistance will also be provided (i.e. agricultural subsidies and micro-credit support under the current agricultural programs of the Government), to help them restore their livelihoods.

d. Agricultural sharecroppers and agricultural workers. Sharecroppers will receive cash compensation equivalent to their share of harvest at market rates, including cost incurred by the sharecropper in improving the land. Cost incurred by the sharecropper on the plot will be determined under the procedure stipulated by constituent documents of economic partnerships, producers' co-operatives or by the agreement between parties. Agricultural workers who will lose employment due to

10 The main criterion to determine whether the residual part (plough land or pasture) is or is not suitable for its earlier purpose is its economic impracticability based on the following: a) small area of the remaining part; b) difficulty of access (driving of agricultural machinery or cattle via highway); c) incomparable cost for plot processing and insignificant profits that can be obtained from its further use. The owner or long-term leaseholder has the right to determine practicability of further use of the land. This will be determined via negotiation. (Article 86, RK Land Code)

Page 32: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

21

land acquisition for the Project will be paid cash compensation equivalent to their salary for the remaining part of the agricultural year.

e. Commercial land. Households and legal entities who own commercial plots that will be affected by the Project will be compensated at replacement rate either (i) in the form of land for land or (ii) in cash at current market rates free of transaction costs and depreciation.

f. Buildings and structures will be compensated in cash at replacement cost without deduction for depreciation, salvaged materials, and transaction costs irrespective of the registration status of the affected item. The cost of lost water and electricity connections will be included in the compensation.

g. Crops. Standing crops on the acquired lands will be compensated at market rates for their gross value of 1 year’s harvest losses. Crop compensation will be paid both to landowners and tenants.

h. Businesses. If business is lost permanently, it will be compensated in cash equal to

1-year net income (loss of profit). If disruption is temporary, the DP will be paid cash compensation for the period of business interruption period based on tax declaration or, if unavailable, official monthly minimum salary. Cash compensation is also provided in cases where there is already an approved business plan and the DP has already incurred cost in the business preparation, subject to review of supporting documents. For those involved in agricultural production and who employ workers, a one-time labor maintenance allowance will be provided to supplement cost of maintaining labor. Labor maintenance allowance is computed based on the following formula: number of workers X average wages for 3 years X percentage of acquired land.

i. Employees. Workers, whose employment will be disrupted, will be provided with

indemnity for lost wages for the period of business interruption up to a maximum of 3 months, based on their registered monthly wages/salaries.

k. Self resettlement allowance. DP households/owners of structures forced to move

will receive a self-relocation allowance to help them transport their structures, goods and personal items.

l. Community structures and public utilities will be fully replaced or rehabilitated to maintain their pre-project functions.

m. Socially vulnerable people (Displaced households with per capita income below the poverty line) will be provided an additional assistance equivalent to one-month official minimum wage and will be enlisted in existing special programs and other initiatives for socially vulnerable people (i.e. Targeted Social Assistance and State social benefits). Able-bodied (and qualified, after training if necessary) members of vulnerable households will be given priority in project-related jobs.

n. Temporary impacts. In case of temporary land acquisition, compensation will be

based at local commercial rental rates for the duration of use, taking into account the lost income from the land. The Project will ensure that the land is restored to its original status at the end of the rental period. The contractor will be responsible for all temporary impacts. However, CoR and its CSC will monitor contractors’ compliance with the LARF provisions.

Page 33: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

22

58. For unexpected adverse effects during the project implementation, the Raion Akimats and the Zhambyl Oblast Roads Department will undertake measures in accordance with the objectives of the LARF of restoring the socio-economic and living conditions of the DPs. 59. In case of cash compensation, payment will be made through the banks or ―KazPost‖ JSC, by checks or other means based on the preference of the DPs, free from fees or processing charges. Expenses related to transfer of funds, and documentation requirements will be borne by the Zhambyl Oblast Roads Department.

Page 34: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

23

Chapter 5 Compensation and Livelihood Restoration Strategy

60. Almost all DPs will have marginal income losses because they will lose less than 10% of their productive lands and could continue with their livelihood activities in the remaining portion of their lands or in their other plots. For all the DPs, the cash compensation provided for losses would be sufficient to help them re-establish and continue with their livelihood. No DP will lose commercial or other lands.. No household will be displaced from housing nor need to relocate to another location. No worker from the affected peasant farms and agricultural enterprises will lose his or her job despite the reduction in the land area of these farms. This chapter presents a more detailed explanation of the compensation strategy of this project. 5.1 Compensation for Termination of Land Leases from the State 61. Long-term lease holders will be compensated for their permanently recovered leased government land through cash compensation following the base rates provided for under RK Resolution No. 890 (revised 7 November 2008). The same base rate is used for valuating land for mortgage purposes, contribution to economic partnerships, share to production cooperatives, and for selling rights to lease. Table-14shows the basic rates used for compensating for the permanent recovery of leased government agricultural land, regardless of duration of lease.

Table-14

Basic Rates for Computing Compensation for permanent recovery of leased government agricultural land

Thousands of tenge per hectare Region Types of

leased agricultural

land

Soil types and subtypes Grey-brown

Sands Light and

ordinary sierozem

Light-brown foothill

and upland

soil

Chestnut foothill

and upland

chernozem

Sub-alpine and

alpine

Zhambyl Non-irrigated plough land

15.6 24.4 26,9

Irrigated plough land

40.2 74,5 114,1

Hay field 5.6 2.0 10.6 10.6 11,9 9.4 Pasture

land 2.0 1.9 5.6 6.9 8.6 6.9

Source: RK Government Resolution #890 on Establishment of Base Payment Rates for Land Plots in Providing them for Private Ownership, as well as in providing for lease by the State or State land users and also fees to be paid for selling the right to Lease land plots dated September 2, 2003 (revised 7 November 2008)

5.2 Compensation for Crop Losses 62. All the affected leaseholders except one have been compensated in October, 2010 for crop losses. Compensation for crop losses was equivalent to the market value of gross crop forone year (based on the average three-year indicator). Information on crop losses was based primarily from the DP’s statements/application. Data from the Zhambyl Department of Agriculture and other documents/data (pledge agreements, statistics data and tax information regarding farms, etc.) were also used in the valuation.

Page 35: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

24

63. Each plot was individually valuated by a licensed valuator engaged by the Zhambyl Oblast Roads Department based primarily on the DPs application provided that these were reasonably within the recorded average volume of harvest/productivity in the region for similar land and crop category. If the application was found unreasonable, the valuator could request the DP to submit a revised application for another review. Moreover, the valuator provided free consultation to DPs on filling up the application. The DP could also request a re-evaluation in case the DP is not satisfied with the earlier valuation. Table-15shows, per hectare average crop value in the project area based on the actual valuation in 2010.

Table-15

Average Value of Crops (KZT) per Hectare based on actual valuations, 2010

Crop Average value per ha (in KZT) Safflower 67,615 Hay 2,380 Wheat 25,586 Barley 8,108

5.3 Compensations for Losses Related to Plot Development and Responsibilities to

Third Parties 64. Losses related to plot development, encumbrance and responsibilities towards third parties were also taken into consideration for the compensation for permanent recovery of leased government agricultural land. However, none of the DP’s in the realigned section of Tranche 2 (Km 305-331) incurred this type of loss.

5.4 Cash Allowance and Agricultural Subsidy for Severe Loss of Productive Land

65. Five leased plots will lose more than 10% of its area. Households leasing these plots will be provided with additional one-year crop compensation (severe impact allowance), although four of the five affected leaseholders have other plots. The impact of the land acquisition on the total land holding of these four households is less than 10%. Only one HH leasing/renting agricultural lands will actually lose more than 10% (10.6%) of his total land. This household will be provided with additional fully-subsidized inputs (fertilizers and pesticides) and micro-finance support proportionate to the land it has lost (2.01 hectares) and the type of crops he plants. Application of such inputs is expected to double the productivity of the land which in turn will help the household to replace its lost income from the acquired land. Cost of subsidy for 2.01 ha affected area (0.38 under barely & 1.63 under hay) is estimated at around KZT 31,000. However, he may also avail micro-finance support as per government rules subject to submission of application during cropping season.

Page 36: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

25

Table-16 Cost per hectare of fertilizers and pesticides for increasing productivity of land

Crop Cost of Agricultural Input Per Hectare (in KZT)

Ammonium Nitrate

Ammophos Potassium Pesticides Fertilizer Application

Others(cultivation

processing cost)

Total

Barley 7,600 7,000 7,000 3,000 3,000 0 27,600 Hay11 0 0 0 0 0 3000 3000 Source: Estimates from the Crop Production Development Unit, Agricultural Division, Zhambyl

Oblast

11 Hay/perennial grass, Lucerne etc.need not any fertilizer & pesticides but it needs cultivation processing cost. This has been included as input cost (Source: Zhambyl Oblast Agriculture Division)

Page 37: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

26

Chapter 6 Consultation and Disclosures

6.1 Consultations 66. Consultations with the Merke raion akimat and DPs were conducted by the CoR since 2007. Initial consultations were with the akim, deputy akims and land allocation office of Merke. Further informal discussions and individual visits were made by the design firm in 2008 during the preparation of detailed design. DPs identified in the process were contacted by the valuators and the committee chaired by the deputy akim of Merke from August to November 2008 to notify them of the extent of the affected lands and seek preliminary agreements for land acquisition. 67. In January 2009, a formal consultation was held in Merke to present the scope of the project as part of the preparation of the environmental assessment (EA) for Tranche 2. Questions and concerns related to the subproject were noted. Compensation issues and crossings for animals were among the common concerns raised in the consultations. A total of 67 people attended the consultation12 68. In May 2009, a formal consultation was again held in Merke to explain the rights of DPs, as well as the valuation of losses, grievance redress and procedures in land acquisition. In order to maximize participation in the consultation, notifications were twice made in local newspapers The Akimat also mobilized the heads of rural villages to inform DPs about the event. 69. Mr. Ilyas Akhmetzhanov, raion vice akim, chaired the consultation in Merke. The Deputy Director of Zhambyl Oblast RD (Mr. Toishibai Aliakhmetov) attended the consultation. Representatives from 2 local NGOs (Alga and Taraz Information Center) also participated. Brochures (in Russian and Kazakhs) on the entitlements and other relevant aspects were distributed at the start of the consultation. 70. A total of 98 DPs attended the May consultation. DPs participated actively in the discussion. Questions and comments revolved around the following: (i) eligibilities and entitlements, (ii) factors to be considered in the valuation of agricultural and commercial lands, (iii) documentation requirements, (iv) compensation amounts, (v) schedule of project implementation and compensation payments,(vi) mode of delivery of compensation, (vii) concerns about charges and expenses related to receipt of compensation (viii) options for remaining plot areas that are no longer suitable for their former use, and (ix) treatment of people who haven’t registered their land rights. 71. Queries about the location and dimensions of underpasses for animal crossing, as well as employment opportunities for local residents were likewise raised. Participants also raised the need to improve dissemination/disclosure of information about the project. Participants requested for specific persons and contacts in case of inquiries and complaints. Related to this, the Zhambyl CoR provided the phone numbers that can be contacted concerning the project. The deputy akim also clarified the akimat’s role in receiving and forwarding complaints from the public. A summary of the dates of consultations and number of participants is shown in Table-17. A video-recording of the May 2009 proceedings is also available on file.

12 Highlights of these consultations are provided in the Summary Environmental Impact Assessment, Kazakhstan: Multitranche Financing Facility for the CAREC Transport Corridor 1 (Zhambyl Oblast Section) Investment Program-Tranche 2, prepared by MOTC for ADB, May 2009

Page 38: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

27

Table-17 Summary dates of consultations

Date Location Participants Aug–Nov 2008 Offices of the Akimat of Merke / on-

site Representatives from the Akimat, Design Firms, Zhambyl Land Resource Mgmt Agency, and individual APs met at the field

January 12, 2009 Lecture Hall, MerkeAkimat, Merke Representatives from Zhambyl Road Dept, Design Firm and 26 APs/stakeholders

May 22, 2009 Lecture Hall, Merke Akimat, Merke Representatives from Zhambyl Road Dept, Akimat and 68 APs/ stakeholders

August & September 2010

DPs’ residence during valuation by the by RD/Daler team on site

Heads or members of affected households

January 23-30,2011 DPs’ residence during conduction of Socioeconomic survey by the PMC-ADB team on site

heads or members of affected households

6.2 Disclosure 72. Consultations were followed with the conduct of census of all known affected HHs and socio-economic survey to a sample HHs, where information brochures were also distributed to ensure that all DPs are well-informed about the project and their entitlements to compensation and assistance under the project. 73. A revised summary brochure of the Land Acquisition and Resettlement Plan (LARP) to be prepared (translated in Kazakh and Russian) and distributed among the DPs to provide additional information on the implementation arrangement, payment schedule, assistance to specific groups and grievance redress options. Separate instructions to contractors regarding temporary use 74. The full-LARP document will be translated into Russian and Kazakh languages and disclosed on the MOTC-Project website, the website of the CoR and the Zhambyl Roads Department. Copies will also be distributed to the raion akimat of Merke. The LARP in English will likewise be submitted for uploading to the ADB website.

Page 39: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

28

Chapter 7 Grievance Redress Participation

75. Grievance redress procedures for the project aim to provide an effective and systematic mechanism for the Subproject in responding to queries, feedbacks and complaints from DPs, other key stakeholders and the general public. 7.1 Grievance Focal Points, Complaints Reporting, Recording and Monitoring 76. Complaints can be received through the staff of the Akimats of Merke, the Zhambyl Committee of Roads or the Project Management Consultants. Grievance Focal Points have been designated at these levels to receive, help resolve, report or forward complaints received from APs and the general public. The following are the Grievance Focal Points designated for the Subproject:

a. Mr. Aliakhmetov Toishibai Zhanadilovich, Deputy Director ZhambylCommittee of Roads, 1a Tauke Khan Street, Taraz City Telephone Nos: 8 (7262) 31-6006 / 8 (7262) 31-6004 Email: [email protected]

b. Mr. Akhmetzhanov Ilyas Bekturgaevich, Vice Akim MerkeAkimat

Telephone Nos: +7 72632 2 17 64;2 26 55 77. PMC-ADB will liaise with the above parties and will compile/maintain a central register of the details of all complaints in writing (including how, when, and by whom the complaint was resolved), and distribute periodically to all parties, if desired. Zhambyl Oblast RD and PMC-ADB will also propose who should investigate, who should attend meetings with the complainants, etc. 78. At the rayon level, the deputy akim will be supported by the Land Allocation Unit and Legal Staff of the akimat. DPs or other concerned individuals may visit, call or send a letter or fax to any of the Grievance Focal Points to register their comments or complaints related to land acquisition or other aspects of the project. 79. The raion akimat and the Zhambyl Oblast Roads Department will maintain a record-book to register the complaints, keep track of their status and report monthly to the Project Management. Reports and grievance resolution will be subject to follow-up by the external monitoring/evaluation team, and by the Project Management. Complaint forms will be distributed to the heads of local self governments, the akimat and the Zhambyl Oblast Roads Department to facilitate recording of complaints. 7.2 Grievance Resolution Process 80. Information about the land acquisition and other aspects of the project will be provided to the heads of the local self-governments/rural settlements. DPs may opt to initially course their complaints or queries through their local self-government heads. 81. In case the heads of the rural settlement cannot resolve or clarify the issue at their level within one week, they can then forward the case to the grievance focal point (GFP) at the raion

Page 40: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

29

akimat. If the issue cannot be resolve in two weeks, the akimat will pass the complaint to the GFP at the Zhambyl Oblast Roads Department. 82. Issues requiring attention or action from the MOTC-Project Management will be forwarded by the Zhambyl Oblast Roads Department to the CoR in Astana. If the case remains unsolved, a complaint can be lodged to the court. 83. Alternatively, people with concerns about the Project may contact the CSC which supervises the work of the contractors or the PMC-ADB which has a designated GFP in Taraz who is tasked to receive, follow-up and report on a weekly basis all complaints, disputes or questions received about the Project. 84. The following standards shall be used in responding to or referring complaints received by the Project (Table-18):

Table-18 Standards to be used in responding to or referring complaints received by the Project

Level/Stage Responsibility Steps in Complaint Handling

Village Head of Local Self Government

Registers the complaint and attempts to solve it. If complaint is not resolved in one week, it is passed to the raion Akimat for resolution.

Raion Vice Akim,

GFP akimat

Receives the complaint, registers it and attempts to resolve it. If there is no resolution in 2 weeks, it is passed to the Zhambyl Roads Department

Zhambyl Oblast Deputy Director,

Zhambyl Oblast Roads Department

Receives the complaint and attempts to resolve it. If there is no resolution within 2 weeks, it will be passed to the Grievance Focal Point at the Committee of Roads

Committee of Roads GFP Receives the complaint and coordinate with the

concerned units or agencies to find timely solution. If there is no resolution within 2 weeks, the case will be presented to a Kazakh court and resolved according to Kazakhstan legislation.

Court Oblast court Hears the case and renders decision. 7.3 Disclosure of the Grievance Process 85. The grievance resolution process for this LARP will be disseminated through information brochures and posted in the offices of the rural village heads, the raion akimats and at the Zhambyl Roads Department Office.

Page 41: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

30

Chapter 8 Institutional Framework

86. The timely and effective implementation of the LARP will require the involvement of several agencies and units. This chapter describes the roles of these units. 8.1 Committee of Roads 87. The Committee of Roads (CoR) through its Project Director has overall responsibility for LAR preparation, implementation and financing, with the assistance of PMC-ADB. 8.2 Zhambyl Oblast Roads Department 88. However, day-to-day implementation of LAR activities will be the responsibility of the Zhambyl Oblast Roads Department. The Legal, Economic Affairs and Monitoring Division – LEMD) within the Zhambyl Oblast RD will implement the LARP for this subproject. This unit shall report to the Deputy Director of Zhambyl Oblast Committee of Roads. It will be tasked to:

Finalize the list of DPs and develop/update a database of DPs based on the results of the census and new information;

Prepare documents for negotiation of compensation with the DPs; Coordinate regularly with relevant State Agencies at the Oblast (e.g. Land Resource

Agency, Justice Department), and raion akimat; Prepare documents for formalizing agreements with DPs and processing of

compensation payments; Conduct regular consultations and exchange of information with DPs on the

implementation of the LARP; Assist in receiving, recording, resolving and reporting of grievances related to land

acquisition process and other aspects of the Subproject and coordinate with the GFPs of the raion akimat, the CSC and PMC-ADB;

Assist in facilitating discussions and agreements among DPs and other adjacent land users for land swapping and land reconsolidation, including reissue of documents on land use rights;

Assist DPs who may wish to reclassify the remaining portions of their plots that are no longer viable for continued agricultural activities or the continuation of the past activity;

Facilitate the conduct of field surveys, and re-registration of the remaining portions of the DPs plots (it is assumed the government will promptly register its own ownership of land it has acquired);

Monitor/supervise the temporary land acquisitions done by contractors engaged for the Subproject;

Prepare regular reports on the progress of LARP-related activities.

8.3 Akimats (District Local Governments) of Merke Rayon 89. Although the Zhambyl Oblast RD will take the central role in implementing the LARP, the akimat of Merke raion will continue to play important roles in grievance resolution. The raion akimat will also tap leaders of village/rural settlements for information dissemination, and grievance redress.

Page 42: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

31

8.4 Project Management Consultant-ADB (PMC-ADB) 90. At the Project Management level, the PMC-ADB Unit will assist the Project Director in the overall responsibility for implementing, supervising, and evaluating LAR activities. PMC-ADB will:

Ensure complete relocation or reconstruction of affected structures/businesses before civil works start, and paying appropriate compensation before displacing DP;

Ensure that contractors take full responsibility for implementing the LARP; Implement immediate remedial for any non-compliance with the LARP; and, Facilitate the engagement of the External Monitoring Agency and supervise their

work. Figure 1

LARP Implementation Arrangement

Project Director (Committee of Roads)

Committee of Roads

Support Unit

Zhambyl Oblast Regional Director

(Roads Department)

Zhambyl Oblast RD

Deputy Director

Zhambyl Oblast RD Legal, Economic Affairs and Monitoring Division (LEMD)

Zhambyl Oblast Land Resources

Agency

Deputy Akim

(focal point for the Raion Akimat)

Land Allocation unit Legal Unit

Zhambyl Oblast Justice

Dept

Displaced Persons/Entities Heads of Rural Settlements

Project Mgmt Consultants

PMC-ADB Team Leader

Page 43: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

32

Chapter 9

Resettlement Budget and Financing

91. The Committee of Roads (CoR) is responsible for all land acquisition costs associated with the implementation of the LARP. An indicative budget regarding compensation cost of the DPs has been outlined below. This compensation cost has been calculated based on the official valuation reports conducted by the licensed evaluators engaged by the Department of Roads. The budget for the compensation and LARP implementation might be updated if there are any changes of evaluation data and will be incorporated in the final LARP. The current estimated budget is stated below in Table-19. The total cost has been estimated approximately KZT 14.41 million for all cost for implementation of LARP including contingency cost.

Table-19 Land acquisition and resettlement budget

Particulars/Items Number of HHs & Les Quantity Estimated Budget (KZT)

1 Compensation for land a. privately owned

b. leased

0

26 HHs and 2 LEs

0

115.5 ha.

0.00

2,844,300.00 2 Compensation for crops and

perennials

26 HHs and 2 Les

115.5 ha.

6,420,446.00

3 Compensation for structures 0 0 0.00 4 Cost of land plot

development 0 0 0.00

5 Severe impact cash allowance

5 HHs 20.32 ha. 1,159,236.00

6 Agricultural subsidy and micro credit for livelihood restoration for severely affected DPs

1 HH

2.01 ha 31,000.00

7 One-time cash allowance for labor maintenance

26 HHs+2 LEs that employ agriculture

workers

136 463,474.00

8 Vulnerable Persons 6 HHs 181,315.00 9 LAR Administration/

Implementation including internal monitoring by CR/PMC

1,500,000.00

10 External Monitoring 500,000.00 11 Total 13,099,771.00

12 Contingencies (10%) 1309977.1

13 Total + Contingencies 14,409,748.10

Page 44: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

33

Chapter 10 Implementation Schedule

92. Civil works for Tranche 2 Section Km 305–331 is expected to commence in August 2011. Related to this, the LARP needs to be fully implemented and evaluated not later than July 2011. Table-20 shows the activities involved in the LARP preparation, finalization and implementation and the agencies/units involved.

Table 20. Activities/Milestones and Agencies/Units Involved Milestones/Activities Agency/Unit Involved 2011

12 1 2 3 4 5 6 7 8 9 10 A. draft LARP Preparation A1.Detailed surveys/consultation Zhambyl RD/

PMC-ADB

A2. draft LARP preparation PMC-ADB A3.draft LARP Review ADB A4.draft LARP approval / Disclosure ADB/MOTC C. LARP implementation C1 Processing of remaining compensation and assistance payments

C2 Third Party Validator mobilization /Action plan preparation

C5 Monitoring C6 Preparation of compliance report C7 Review of compliance report and issuance of No-objection for civil works

Milestone 3 no objection to start of civil works from ADB

Start of civil works

* Restoration of temporarily acquired lands will be done at the end of the rental period. Cash compensation will be completed by end June 2011.

Page 45: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

34

Chapter 11 Monitoring and Evaluation

93. The LARP implementation will be subject to both internal monitoring and Third Party Validation (TPV). Results of these monitoring will be used as based for the issuance of notice-to-proceed (NTP) to the contractors. 11.1 Internal Monitoring 94. The Social Specialist of the Construction Supervision Consultant (CSC)) will undertake internal monitoring of LARP implementation. 95. The CSC will submit an internal resettlement monitoring report which will be reviewed by the third party valuator (TPV)/external monitor to be engaged by CoR, through PMC-ADB. The overall system of monitoring indicators is represented in the table below.

Table 21 LARP internal monitoring and evaluation matrix

Purpose Activities Monitoring Indicators

Identification of compensation recipients

Checking the list of compensation recipients against eligibility criteria for compensations

Number of persons in the list of compensation recipients, who do not meet eligibility criteria (mistaken inclusion)

Identification of persons, who may claim eligibility to compensation, but are not included in the lists of compensation recipients. Separate check should be performed on each type of compensation

Number of persons who meet the criteria, but are not included in the list of compensation recipients (mistaken exclusion)

Controlling types of compensation

Confirmation of temporarily or permanently affected areas against the LARP

Area of land subjected to temporary acquisition, for which compensations have been paid

Area of land subjected to permanent acquisition, to which compensations have been paid

Controlling compensation

Examination of financial documents

Number of persons who received compensation in time and in full amount, disaggregated by compensation types

Identification and analysis of reasons for compensations not being paid in full amount and in time.

Number of persons who did not receive compensation in time and in full amount, disaggregated by compensation types. Amount of funding allocated for payment of compensations.

Identification of reasons for which funds for compensations have been under/overspent

Rate of spending of funds allocated for compensations, % of amount envisaged in the LARP

Additional compensation

Monitoring time limits of temporary land acquisition

Number of persons on whose plots temporary acquisition needs to be extended Area on which construction works will be continued after the established deadline.

Page 46: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

35

Purpose Activities Monitoring Indicators Household impact (income restoration)

Follow up socio-economic survey of affected households (3 months after implementation of LARP)

Changes in household income/livelihood

Consultation and participation

Determining the level of involvement and identification of reasons of inadequate participation

Number of compensation recipients who participated in consultations and coordination meetings at each stage of land acquisition

Analysis of disputes and complaints content. Resolution of conflicts

Number of complaints Number of complaints resolved

11.2 Third Party Validation/Compliance Reporting 96. CoR, through PMC-ADB, will engage a Third Party Validator (TPV). The TPV will prepare a due diligence/compliance report once the LARP activities have been fully implemented. The TPV will determine whether (i) the provisions in the resettlement plan have been observed during its implementation, (ii) whether the sources of income of the individuals, whose interests have been affected, were restored, and (iii) whether there occurred any unplanned or unexpected consequences of the resettlement.

Page 47: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

36

APPENDIX A

CENSUS AND SOCIOECONOMIC SURVEY QUESTIONNAIRES

Page 48: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

37

Zhambyl Oblast Committee on Road Ministry for Transport and Communications

Western Europe to Western China (WE-WC) Corridor Development Project

CENSUS OF AFFECTED LAND USERS

1. Full name ___________________________ 2. Sex Male________ Female______________ 3. Address ________________________________________________________________ 4. Year of birth ___________________________ 5. Nationality ________________________ 6. Members of the household

Full name Relation to household head (husband, wife, son, daughter etc.)

Age Sex Marital status

Education Occupation Any disabilities

Yes/No

1 2 3 4 5 6 7 8 9 10 11

7. What are potential impacts on your household due to the road development project? (Mark with Х)

Description of Impact Temporary Permanent

Loss of some portion of lands (agricultural, commercial, residential)

Loss of structure (house, shop-house, secondary structures etc.)

Loss of business, livelihood or income Loss of grains, vegetable crops or trees

8. What are your rights to the land? a) Long-term lease for 49 years b) Short-term lease for ____years c) Private land ownership d) Common land ownership

9. Years you use this land? ________________________________________

10. If you lease the land from a private person, provide the following information on the

owner of the land? Owner’s full name___________________________________

Page 49: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

38

Address_______________________________________________ Phone number___________________

11. Did you have any expenditure for land improvement during the last 3 years?

Yes No a Fertilizers b Irrigation system c Bank loan d Seeds e Access roads on the land plot subject to acquisition f Fuels and lubricants

12. Do you think that after acquisition of a portion of your land you will be able to

continue with your former activities, namely:

Agricultural activities 1. Yes 2. No, but has alternative land to continue agricultural activity

3. No, and has no alternative land

Trading, Business 1. Yes 2. No, but has alternative

land to continue trading or business activity

3. No, and has no alternative land

Residential life 1. Yes 2. No, but has alternative

land to reside 3. No, and has no alternative

land

13. If you have alternative land to continue with agricultural activity, trading or to reside, where is this land situated?_______________________________________________________

14. If the remaining land is not sufficient to continue with agricultural activity or

trading, would you like to obtain alternativeland plot instead of cash compensation? Yes No

15. What would you like to get as compensation for your land?

1. Cash compensation 2. Land for land 3. Other compensation (specify)

16. (For business owners only)

Type of business Is it basic or non-operating activity?

Monthly income from this activity, in KZT

Amount of lost income

17. Only for persons engaged in trading, commerce or service

When did you start the mentioned activity in this location? (year)

Do you have an official permit to carry out this activity? (underline)

Authority that issued a trading permit

Yes No

18. Do you employ or hire workers to help you on the land plot that would be affected

due to road improvement? 1. Yes (permanent or seasonal?) 2. No

Page 50: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

39

19. If you have permanent hired workers, please fill in the table below:

Item No.

Work being done by hired worker Age Sex Education Worker’s monthly income

1 2 3 4 5

20. Main crops and trees cultivated on the land subject to acquisition for public needs

Grains Area Area that will be acquired

Year of sowing

Total area (ha) Area subject to acquisition (ha)

Price per 1 metric centner (100 kg), in KZT

Total cost of the harvest lost

21. Structures on the land that will be affected due to road improvement Type of building, structure Area (sq. m) Cost (in KZT)

22. Information on basic premises (house, shop, building) that will be affected due to construction

Building Materials Number of storeys

Number of rooms

Has electricity? Has telephone facility?

Has pipe- borne water?

Year built

23. For persons whose structures will be affected: а) Did you obtain any credit to build this/these structure/structures? 1.Yes 2. No b) If yes, please specify your source(s) of credit for building the structure?

1. Bank 4. Money lender 2. NGO 5. Relatives/Friends 3. Cooperative Society 6. Other (specify)

24. Information from renters of affected structures:

a) Monthly rent _____________KZT b) Number of years you have been renting the affected structure__________years c) Until when do you intend to rent the structure:

1. Less than 6 months 3. More than 1 year 2. 6 to12 months 4. Indefinitely

d) Do you know of an alternative place to rent? 1. Yes

2. No

e) If no, will you need assistance in finding another place to rent?

Page 51: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

40

1. Yes 2. No

25. In case you need to relocate your business as a result of road improvement, what would you prefer?

1. Self relocate to another site 2. Relocate in a site to be identified and provided by local authority (Akimat) 3. Undecided / Don’t know

26. What opportunities and livelihood assistance do you expect from the road

improvement to help restore your livelihood? 1. Employment from road construction 2. Skill training (specify kind of training) 3. Micro-finance/soft loan (specify business) 4. Others (specify) 5. Don’t expect anything

27. Are you a member of any local/community organization?

1. Yes (Please indicate name of organization)________________________________ 2. No

28. What portion of your income (in KZT) you will lose due to land acquisition for road

construction?

29. What impact will the road improvement have on your household?

1. Positive 2. Negative 3. Neither positive, nor negative 4. Undecided / Don’t know

30. What do you think are the advantages that you and your family would get due to

construction ofthe road?

31. What are your suggestions to minimize the losses or adverse impacts due to construction ofthe road?

Thank you !

Page 52: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

41

Zhambyl Oblast Committee on Roads Ministry for Transport and Communications

Western Europe to Western China (WE-WC) Corridor Development Project

SOCIO-ECONOMIC SURVEY OF AFFECTED LAND USERS

1. Full name of household head___________________________ 2. Sex Male________ Female______________ 3. District______________________________________ 4. Address______________________________________________________ 5. Land and asset ownership

a) Total Land area, ha___________________ b) Area of cultivated land, ha_______________________ c) Area of uncultivated land, ha_________________ d) Crops being cultivated_______________________________________________ e) Yield_______________________

6. Land type

a) Irrigated arable land b) Non-irrigated arable land c) Garden d) Pasture e) Fallow land f) Commercial land g) Residential lands h) Other

7. Information on the structures that belong to the household head (including those outside the road corridor and in other locations)

Type of structure

Materials (bricks, clay, wood)

Number of storeys

Number of rooms

Has electricity? Has telephone facility?

Has pipe- borne water?

Year built

8. Other assets owned by your family

Asset Quantity Livestock Agricultural equipment Tractor Lorry Car Well Trading and Business

Page 53: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

42

9. Family members who generate income (specify all of them including pensioners) Member’s name (father, mother, son, daughter etc.) Income source (salary, pension,

profit) Monthly income, in KZT

10. Information on family expenditure (Monthly):

Item of Expenditure Amount in KZT Food Clothing Coal Gas Electricity Water Dwelling house and other accommodation Gasoline, fuel Medical/health Education Household utensils Telephone Transport expenses Payment of loan/credit Maintenance cost of household structures and equipment Smoking Alcohol Entertainment Other (if any) TOTAL

11. Information on family income (2008 average)

Source of Income Amount in KZT Agriculture Livestock Salary Allowance Pension Rent of land or real assets Trade/Business Household products Renting heavy vehicles (bus, lorry, tractor) Renting light vehicles (car, van) Interest (bank deposit, money lending) Gardening Other (specify) TOTAL

Page 54: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

43

12. Please indicate your family borrowings during 2008 S

No Name of borrowing family member

Name of source (institution or private person)

Amount taken, KZT

Amount returned, KZT

Balance, KZT

1 2 3 4 5

TOTAL 13. What illness did you and your family members experience during the last 12 months?

14. Did you and your family members apply for medical service to a hospital, out-patients' clinic or maternity hospital during the last 12 months?

Family member Illness Medical institutions you applied to

15. Are there members of your family who work in locations outside the raion (district)? 1. Yes 2. No

If “Yes”, please fill in the following:

Name Type of work (agriculture, industry, construction, trade and business, other.)

Location of work (Zhambyl Oblast, Almaty, Astana, other regions in Kazakhstan, CIS, foreign countries (specify where)

Frequency and duration of work (shift team, permanent, years?)

Monthly income of this member, in KZT

Page 55: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

44

(Question for women – heads of households or family members of the person filling the Questionnaire)

16. Do you think that women in your area have sufficient opportunities to participate in decision making in:

Yes No Limited Land use Bank credits Household development Land selling or renting Temporary workers hiring Harvest selling Household income distribution

Purchasing agricultural equipment, seeds, livestock, fertilizers Other (specify)

17. (For respondents who think that there are no or limited opportunities for women) What do you think are the possible reasons why there are limited opportunities for women to participate in decision making in their family and society?

_____________________________________________________________________ _____________________________________________________________________ 18. What can be done to improve women’s life in your region? _____________________________________________________________________ _____________________________________________________________________ 19. Should the women receive any supplemental assistance related to land acquisition for

road construction? 1. Yes (Please specify) ________________________________________________________________________ 2. No

3. Don’t know

THANK YOU

Page 56: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

45

APPENDIX-B List of Affected Persons and Information on their

Acquired Land Plots( Km. 305-331)

Sl№ Name of AP

Cadastr,

number

Area of total owned land

Area of the plot

affected (in

ha)

Acqui-red area

% of acqui-

red area

out of total

owned land

Owner ship

Use of land

Crop cultivated Ara

ble Pas ture

1 H-d Dzhumatayev Ali 055-001 290 50 13.2 4.55 49 y, 13.2 0

safflower hay

2 H-d GasanovAladin 054-107 19 8.4 1.58 8.15 49 y, 1.58 0 safflower

3 H-d MamytovSerikzhan 055-071 102 102 2.59 2.53 49 y, 2.59 0 safflower

4 H-d MyktybayevAnuarnek

055-018 6.4 6.4 0.23 3.6 49 y, 0.23 0 wheat

5 H-d TeltayevKyrgyzbek 055-019 11.4 11.4 0.4 8.77 49 y, 0.4 0 wheat

6 H-d SpankulovSeitbek 055-014 9.4 9.4 0.34 3.61 49 y, 0.34 0 barley

7 H-d BelhozhayevBaurzhan

055-020 30.2 30.2 1.08 3.6 49 y, 1.08 0 wheat

8 H-d SauranbayevGaydar - 19.4 19.4 0.69 3.56 49 y, 0.69 0 barley

9 H-d OrazkulovRyskulbek 055-023 15 10.6 0.37 2.46 49 y, 0.37 0 wheat

10 H-d SuleymanovaRoza 055-047 25 7.6 0.26 1.04 49 y, 0.26 0 barley

11 H-d OspanovKasymhan - 62 62 2.03 3.27 49 y, 2.03 0 barley

12 H-d RaushanovAsan 055-007 128 83.8 2.47 1.92 49 y, 2.47 0 barley

13 H-d DulatbekovAnday 055-007 246 93.8 5.66 2.3 49 y, 5.66 0 barley

14 H-d AlmasovAshimhan 055-047 18.87 18.87 2.01 10.6 49 y, 0.38 1.63

barley hay

15 H-d KerimkulovNurgazy 054-169 21 14 1.41 6.71 49 y, 1.41 0 wheat

16 H-d ZgayevNurlan 055-045 46.7 43.3 0.54 1.16 49 y, 0 0.54 hay

17 H-d AkbuzauovZharlapes 055-011 51 34.6 1.15 2.25 49 y, 0 1.15 hay

18 H-d BakirtovMeyrman 055-030 13.8 5.9 0.78 5.65 49 y, 0.78 0 safflower

19 H-d TatykulovaKaynarkul

055-055 130 36 3.53 2.71 49 y, 3.53 0 safflower

20 H-d KazimovNabi 055-024 271 88.6 7.79 2.87 49 y, 7.79 0 safflower

21 H-d ImashevAskar 055-046 22.8 22.8 2.12 9.29 49 y, 2.12 0 safflower

Page 57: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

46

22 H-d AlimbekovAzimhan 055-061 220 220 7.27 3.31 49 y, 1.07 6.2

barley hay

23 H-d TaskynovNurzhan 055-004 64 30 0.3 0.47 49 y, 0.3 0 safflower

24 H-d YeshetovSauytbek 055-046 154 150 4.39 2.85 49 y, 4.39 0 safflower

25 GP "Mukashev and company" - 190 90 3.5 1.84 49 y,

LE 3.5 0 safflower

26 H-d DalibayevSayat - 34 21.15 0.04 0.11 49 y, 0 0.04 hay

27 PK "Aspara", G,Miheev

085-030, 085-031

8110.87 5000 49.0

2 0.6 49 y, LE 48.98 0.04

barley hay

wheat

28 H-d SarsenbiyevaSharapathan

085-042 35.25 36 0.75 2.12 49 y, 0.75 0 apple

trees

Page 58: RP: MFF: CAREC Transport Corridor 1 (Zhambyl Oblast ... · km 305–km 331 covered under part of Tranche 2 of the Central Asia Regional Economic Cooperation (CAREC) Transport Corridor

47

APPENDIX-C

List of Vulnerable Households

No. Name of household head

Age Sex Social status

# of h/h members

Monthly Income (KZT, as advised during the socioeconomic survey (Jan. 2011)

Assistance rate (KZT)*

1 Gassanov Alladin

77 male Married 11 24000 (pension) 24000-6,399* *11 = 46389

2 Belhozhaev Baurzhan

56 Male Married 10 27000 (pension) + 10000 (agriculture)

37000-6,399* *10 =

26990 3 Sauranbayev

Gaydar 42 Male Married 7 9 (pension) + 6000 15000-

6,3999* *7 = 29793

4 Spankulov Seitbek

52 Male Married 6 18000 (agriculture) 18000-6,3999* *6 =

17961 5 Orazkulovrysk

ulbek 60 Male Married 8 20000 20000-

6399* *8= 31192

6 Akbuzauov Zharlapes

60 Male Married 10 35000 35000-6399* *8=

28990 TOTAL 181 315