General Items OGR 198 – Setup work group to address comments concerning shedding firm load via SCADA Work group will address PUCT request to review load shedding procedures Wind Survey Results – still awaiting responses NERC will provide interpretation of standards
Citation preview
ROS Report to TAC
October 5, 2007
OutlineGeneral ItemsNodal Operating GuidesOGRR192Document control issuesProposed revisions to Texas Nodal
Telemetry Criteria and State Estimator Performance Stanadards
General ItemsOGR 198 – Setup work group to address
comments concerning shedding firm load via SCADA
Work group will address PUCT request to review load shedding procedures
Wind Survey Results – still awaiting responses
NERC will provide interpretation of standards
Nodal Operating Guides NOGRR001, Nodal Operating Guides – Section 1,
Overview (Vote) NOGRR002, Nodal Operating Guides – Section 2,
System Operations and Control Requirements - Remand back to ROS to address ERCOT Staff comments (Vote)
NOGRR003, Nodal Operating Guides – Section 3, Resource Testing and Qualification Procedures (Vote)
NOGRR004, Nodal Operating Guides – Section 4, Emergency Operation (Vote)
NOGRR005, Nodal Operating Guides – Section 5, Planning (Vote)
NOGRR006, Nodal Operating Guides – Section 6, Disturbance Monitoring and System Protection (Vote)
NOGRR007, Nodal Operating Guides – Section 7, Telemetry and Communication Vote)
Nodal Operating Guides NOGRR008, Nodal Operating Guides – Section 8,
Attachment A, Detailed Black Start Information (Vote) NOGRR009, Section 8, Attachment B, Relay Misoperation
Report (Vote) NOGRR010, Section 8, Attachment C, Turbine Governor
Speed Tests (Vote) NOGRR011, Section 8, Attachment D, Seasonal Unit Net
Real Power Capability Verification (Vote) NOGRR012, Section 8, Attachment E, Biennial Unit
Reactive Limits (Lead and Lag) Verification (Vote) NOGRR013, Section 8, Attachment F, Seasonal Hydro
Responsive Reserve Net Capability Verification (Vote) NOGRR014, Section 8, Attachment G, Load Resource
Tests (Vote) NOGRR015, Section 8, Attachment H, Unit Alternative
Fuel Capability (Vote)
Nodal Operating GuidesNotice of NOGRR Rejections:
– NOGRR016, Section 8, Attachment I, Security, Facilities, and Connectivity of WAN Systems
– NOGRR017, Section 8, Attachment J, ERCOT Data Sets
Request that proposed changes to NOGRRs and NPRRS that deviate from current operating practices be remanded to ROS
Operating GuideOGRR192, Combustion Turbine
Governor Performance Test Forms (Vote)
Issues With Document Control Criteria, Handbooks, Standards (Not NERC or
TRE Standards), Work Papers etc. Quasi Requirements
– Consequences for not meeting?– Who is monitoring compliance?
No defined owner for documents No control process for updating document Undefined voting structures Potential for conflicting information Duplication of effort
Document Change Timeline September 10, 2007 – ERCOT staff submitted
changes to existing Texas Nodal Telemetry Criteria and State Estimator Standards for comment
September 17, 2007 - ROS hosted workshop September 24, 2007 - NDSWG hosted
workshop October 1, 2007 - ROS hosted workshop October 4, 2007 - ROS approved Telemetry
Criteria via E-Mail
Texas Nodal Market State Estimator Standards Postponed vote due to potential
duplication or conflict with Nodal Protocols
Texas Nodal Market Telemetry CriteriaROS voted by E-Mail to approve Texas
Nodal Market Telemetry Criteria– Affirmative 13 (70% weighted)– Negative 3 (30% weighted)– Abstain – 1
Dissenting comments concerning performance metrics and response times
ROS setting up process to monitor and update metrics
Texas Nodal Market Telemetry Criteria Section B Requirements:
– R6, Minimum Telemetry Criteria (Vote)– R7, Telemetry Availability (Vote)– R9, Critically Important Telemetry
(Vote)– R10, Availability for Critically Important
Telemetry (Vote)– R13, Requests for Additional
Telemetry (Vote)
Questions?