Upload
maximillian-hall
View
216
Download
0
Tags:
Embed Size (px)
Citation preview
Rookery South Resource Recovery Facility (RRF)
Community Liaison Panel
Transport Presentation – 14th December 2009
John Hopkins, Peter Brett Associates
Introduction
Today’s presentation will provide additional information on:– traffic flows from Covanta’s RRF;
– future forecast traffic flows on the highway;
– traffic impact and junction capacity assessments;
– environmental impact;
– construction traffic flows.
Obviously, although all this is work in progress, Covanta
remain committed to keeping the CLP fully informed
throughout this process.
Rookery South RRF Context
64 staff employed on site every day; RRF operation to work “24-7”; waste to be delivered into the site Monday to
Saturday only; anticipated 182 HGV deliveries per day for
Nominal throughput of 585,000tpa; a highly theoretical Maximum 318 HGV
deliveries per day also assessed for 645,000tpa throughput;
all HGV access via Green Lane.
Vehicle trip distribution
Covanta will commit to a Route Management Plan to ensure delivery contractor HGV compliance;
except for employees residing locally, employees will be contractually required to be routed via Green Lane;
different distributions for HGV movements and employees anticipated as:
Distribution HGVS Employees
East – from Stewartby 0% * 11%
North – along old / new A421
27 - 36% 70%
South – along old / new A421
64 - 73% 15%
West – via Wootton 0% * 4%
* except for council household waste collection in the local area
HGV movement times - context
unknown waste material sources - difficulty providing definitive information whilst contractual procurement negotiations ongoing;
Rookery South RRF delivery times need to respond to the clients’ requirements;
delivery times therefore set by planning parameters; informed and advised by the Acoustics Assessment,
showing additional delivery noise within acceptable standards (work still ongoing with the EHOs);
maintaining operational flexibility to respond to future changes - within agreed limits.
Proposed HGV movement times
HGV movements limited to 05:00 to 23:00; HGV movements in the first hour (05:00 - 06:00) relate
to parked bulk haulage vehicles leaving empty only – up to 15 outbound trips;
first deliveries from 06:00 to 07:00 - up to 20 HGV movements;
majority of deliveries (76% - 87%) anticipated from 08:00 to 17:00;
Covanta is seeking future operational flexibility.
Daily Arrival Patterns - Nominal
For the Nominal (585ktpa) throughput, weekday two-way flows:Time Commentary HGVs Cars / Buses0000 - 0100
0100 - 0200
0200 - 0300
0300 - 0400
0400 - 0500
0500 - 0600
0600 - 0700
0700 - 0800
0800 - 0900
0900 - 1000
1000 - 1100
1100 - 1200
1200 - 1300
1300 - 1400
1400 - 1500
1500 - 1600
1600 - 1700
1700 - 1800
1800 - 1900
1900 - 2000
2000 - 2100
2100 - 2200
2200 - 2300
2300 - 0000
TOTAL
Drivers in, bulk haulage lorries leaving
First C and I deliveries arriving
Bulk haulage lorries return, drivers off
0
0
0
0
0
7
40
40
22
23
32
50
34
24
44
42
6
0
0
0
0
0
0
0
364
0
0
0
0
0
9
13
33
17
6
2
3
3
10
2
2
23
29
10
6
0
0
0
0
168
Daily Arrival Patterns - Maximum
For the Maximum (645ktpa) throughput, weekday two-way flows:Time Commentary HGVs Cars / Buses0000 - 0100
0100 - 0200
0200 - 0300
0300 - 0400
0400 - 0500
0500 - 0600
0600 - 0700
0700 - 0800
0800 - 0900
0900 - 1000
1000 - 1100
1100 - 1200
1200 - 1300
1300 - 1400
1400 - 1500
1500 - 1600
1600 - 1700
1700 - 1800
1800 - 1900
1900 - 2000
2000 - 2100
2100 - 2200
2200 - 2300
2300 - 0000
TOTAL
Drivers in, bulk haulage lorries leaving
First C and I deliveries arriving
Bulk haulage lorries return, drivers off
0
0
0
0
0
7
36
50
46
65
52
68
58
62
76
74
42
0
0
0
0
0
0
0
636
0
0
0
0
0
9
13
33
17
6
2
3
3
10
2
2
23
29
10
6
0
0
0
0
168
Questions and Answers
A421 Traffic Model - included development
Forecast Traffic Flows –
Nominal Throughput - All Vehicle Daily flows
Additional RRF Flows
Green Lane– West – 517 vehicles– East – 15 cars
Stewartby Way– 15 cars
Old A421– North – 216 vehicles– South – 301 vehicles
Forecast Traffic Flows – Nominal Throughput – All Vehicle AM Peak Hour flows
Additional RRF Flows
Green Lane– West – 75 vehicles– East – 6 cars
Stewartby Way– 6 cars
Old A421– North – 48 vehicles– South – 28 vehicles
Forecast Traffic Flows – Nominal Throughput - Heavy Goods Vehicle Daily flows
Additional RRF Flows
Green Lane– West – 364 HGVs(Landfill – 320 – until Dec 2014)
– East – 0 HGVs
Stewartby Way– 0 HGVs
Old A421– North – 101 HGVs– South – 263 HGVs
(Excluding the local waste collections)
Forecast Traffic Flows – Nominal Throughput - Heavy Goods Vehicle AM Peak Hour flows
Additional RRF Flows
Green Lane– West – 22 HGVs– East – 0 HGVs
Stewartby Way– 0 HGVs
Old A421– North – 6 HGVs– South – 16 HGVs
(Excluding the local waste collections)
Forecast Traffic Flows – Maximum Throughput - All Vehicle Daily flows
Additional RRF Flows
Green Lane– West – 804 vehs– East – 15 cars
Stewartby Way– 15 cars
Old A421– North – 376 vehs– South – 428 vehs
Forecast Traffic Flows – Maximum Throughput - All Vehicle AM Peak Hour flows
Additional RRF Flows
Green Lane– West – 99 vehs– East – 6 cars
Stewartby Way– 6 cars
Old A421– North – 65 vehs– South – 34 vehs
Forecast Traffic Flows – Maximum Throughput - Heavy Goods Vehicle Daily flows
Additional RRF Flows
Green Lane– West – 636 HGVs(Landfill – 320 – until Dec 2014)
– East – 0 HGVs
Stewartby Way– 0 HGVs
Old A421– North – 261 HGVs– South – 375 HGVs
(Excluding the local waste collections)
Forecast Traffic Flows – Maximum Throughput - Heavy Goods Vehicle AM Peak Hour flows
Additional RRF Flows
Green Lane– West – 46 HGVs– East – 0 HGVs
Stewartby Way– 0 HGVs
Old A421– North – 23 HGVs– South – 23 HGVs
(Excluding the local waste collections)
Traffic Impact Summary - 2014
(all impacts relate to the Nominal throughput)
Green Lane (East of Site Access)– Daily - 0.4% All Vehicle, 0% HGV;– AM Peak - 1% All Vehicle, 0% HGV;
Green Lane (West of Site Access)– Daily - 23% All Vehicle, 448% HGV;– AM Peak - 20% All Vehicle, 230% HGV;
Stewartby Way– Daily - 0.4% All Vehicle, 0% HGV;– AM Peak - 1% All Vehicle, 0% HGV;
Traffic Impact Summary
(all impacts relate to the Maximum throughput)
Old A421 (North)– Daily - 6% All Vehicle, 33% HGV;– AM Peak - 10% All Vehicle, 24% HGV;
Old A421 (South)– Daily - 5% All Vehicle, 22% HGV;– AM Peak - 3% All Vehicle, 13% HGV;
Questions and Answers
Junction Capacity Summaries
PARAMICS runs to follow– Nominal throughput
– Maximum throughput
Site Access / Green Lane Junction
Junction Capacity Summaries - AM
2014 - Without RRF– RFC = 0.547– Queue = 2 vehicles
2014 - With RRF– RFC = 0.598– Queue = 2 vehicles
Green Lane / A421 Priority Junction
Source - Google Maps
Junction Capacity Summaries
A421 / Marston Moretaine Junction
Plan supplied by Jacobs Consultancy Marston Northern Roundabout– 2014 - Without RRF
RFC = 1.15 (Beancroft Rd (N) Queue = 55 vehicles
– 2014 - With RRF RFC = 1.18 (Beancroft Rd (N) Queue = 64 vehicles
Junction Capacity Summaries
A421 / Marston Moretaine Junction
Plan supplied by Jacobs Consultancy Marston Middle Roundabout– 2014 - Without RRF
RFC = 0.84 Queue = 5 vehicles
– 2014 - With RRF RFC = 0.86 Queue = 6 vehicles
Junction Capacity Summaries
A421 / Marston Moretaine Junction
Plan supplied by Jacobs Consultancy Marston Southern Roundabout– 2014 - Without RRF
RFC = 0.75 Queue = 3 vehicles
– 2014 - With RRF RFC = 0.76 Queue = 3 vehicles
Junction Capacity Summaries
Marsh Leys Roundabout – part signalised
Drawing supplied by Jacobs Consultancy Without RRF– DoS = 88% (Western Bypass arm)– Queue = 13
With RRF– DoS = 89% (Western Bypass arm)– Queue = 14
Questions and Answers
Environment impact of traffic flows
“Magnitude” of change in flow is identified as ‘large’, ‘medium’, ‘small’ or ‘negligible’ according to set criteria;
“Receptors” are identified early and categorised into ‘high’, ‘medium’, ‘low’ and ‘negligible’ sensitivities based on current guidance;
the two sets of information are compared to give the “significance of effect” of the traffic.
the minimum threshold for Fear and Intimidation is set by average hourly traffic flows in excess of 600 additional all vehicle trips per hour across an 18 hour day, and total 18 hour HGV flows in excess of 1,000.
Taken from: Institute of Environmental Assessment’s Guidelines for Environmental Assessment of Road Traffic (1993) Department of Transport Manual of Environmental Appraisal (1983)Crompton and Gilbert – “Pedestrian Delay Annoyance and Risk” (1981)
Environmental Impact of traffic flows
Significance of Effects of the Traffic
Sensitivity of Receptors
Highe.g. Schools
AccidentBlackspots
ResidentialHomes
Mediume.g. Congestedjunctions
CommunityCentres
Lowe.g. ListedBuildings
Public openspace
Churches
NegligibleReceptors ofvery lowsensitivity totraffic flows
Magnitudeof Changein trafficflow /Conditions(both in allvehicle andHGV)
Large > 90% VerySubstantial
Substantial Moderate Insignificant
Medium 60%-90% Substantial Substantial Moderate Insignificant
Small 30%-60% Moderate Moderate Slight Insignificant
Negligible < 30% Insignificant Insignificant Insignificant
Insignificant
Plan Showing Sensitivity of Receptors throughout the Area
Environmental Impact of traffic flows
Significance of Effects of the Traffic
Sensitivity of Receptors
Highe.g. Schools
AccidentBlackspots
ResidentialHomes
Mediume.g. Congestedjunctions
CommunityCentres
Lowe.g. ListedBuildings
Public openspace
Churches
NegligibleReceptors ofvery lowsensitivity totraffic flows
Magnitudeof Changein trafficflow /Conditions(both in allvehicle andHGV)
Large > 90% VerySubstantial
Substantial Moderate Insignificant
Medium 60%-90% Substantial Substantial Moderate Insignificant
Small 30%-60% Moderate Moderate Slight Insignificant
Negligible < 30% Insignificant Insignificant Insignificant
Insignificant
Plan showing Significance of Effect of Traffic on Sensitive Receptors
Environmental Impact of traffic
Summary of Impact, Maximum throughput, 2014:
Green Lane (west of Site Access)– Magnitude of change in All Vehicle flow = ‘Negligible’– Magnitude of change in HGV flow = ‘Large’;– no sensitive receptors;– Significance = ‘Insignificant’.
A421
Questions and Answers
Construction trips
details cannot be confirmed until Covanta has appointed a Contractor yet;
Covanta commits to a RMP to ensure only Green Lane used by deliveries and non-local employees;
two worst case assessments:i) assuming realistic HGV inbound movements in the AM peak;
ii) assuming workers coming in between 0700 – 0800 in the morning.
Construction trips
Site Access / Green Lane Junction
PARAMICS runs– Realistic HGV movements (AM peak)
– Maximum Workforce movements (0700 – 0800)
Questions and Answers