19
GDA CONSULTATIVE GROUP – 16 TH JUNE, 2016 Ronan Doyle Grangegorman Development Agency

Ronan Doyle Grangegorman Development Agencyggda.ie/assets/160616_update_presentation.pdf · Ronan Doyle Grangegorman Development Agency. OVERVIEW • HSE Projects • DIT Projects

  • Upload
    leminh

  • View
    228

  • Download
    0

Embed Size (px)

Citation preview

GDA CONSULTATIVE GROUP – 16TH JUNE, 2016

Ronan Doyle Grangegorman Development Agency

OVERVIEW

• HSE Projects • DIT Projects

– Programme 2 – Programme 3

• Other Projects

• Grangegorman Employment Charter Compliance

• Public Art

• Communications/Community

Start Date: 13th April 2015 Completion Date: End of 2016

Contractor: L & M Keating Ltd .

Programme: Up to 20 weeks extension allowed for with Audiology

• Internal plastering – 100% on 1st and 2nd floors, painting commenced

• Landscape base works commenced.

• Plastering in Protected building commenced.

• HSE’s Furniture fit out and occupation plan

to be established. Employment Overall: 50 persons weekly (Will reduce significantly In Q3 for Audiology suite work) Local: 11 persons and 2 local businesses

HSE PRIMARY CARE CENTRE

Aerial View of CNU/PCC Site from SE

Programme 2 (PPP) Legal Case Update

Substantive Case • 9th Feb 2016 – Case heard and now being

considered by Judge Haughton • 13th April 2016 – Listed for Mention • Case listed for mention again 14th June • Discussions underway to get project

moving again apart from legal case

DIT PROGRAMME 3

NCR Temp Car Park Academic Hub / Library for DIT

West Quad for DIT

Energy Centre

Student Accommodation 1

NCR Gate Sitewide / H&S

Academic Hub • Design team selected –

O’ Donnell + Tuomey • Design work to commence

in June 2016 • Target construction works

to start October 2017 for • Occupation in September

2019

DIT PROGRAMME 3 PROGRESS

STUDENT ACCOMMODATION - PROJECT PROGRAMME

• August 2016 – Out to tender

• August 2017 - Financial Close

• Jan 2018 – Construction begins

• Sept 2019 – First phase complete

and ready for occupation

GREENWAY HUB – IN OCCUPATION

Broadstone Gate under construction

Contractor • Francis Haughey Construction

Works • Lightning Protection • Access Ramp • Internal modifications

Programme • Duration – 10 weeks • Substantial Completion – 11 July 2016

CLOCK TOWER Additional Works to GDA/DIT OFFICES

OTHER PROJECTS - PROGRESS UPDATE

Primary School

Community Nursing Unit & Car Park

Primary Care

Car Parking Strategy

PRIMARY SCHOOL D7ETNS

• Planning Scheme Amendment • 16 to 24 classrooms • DES progressing 24 classroom

school only • Traffic management

Grangegorman Upper • Part VIII by DCC

April 2016Month Ending:

22%

78%

L&M Keating

Local: 11

L&M Keating, 50

Contractor 2, 0

Contractor 3, 0

Contractor 4, 0

Total Current Employment

Total Employment: 50

22%

78%

Target: 20% of new employees

Local: 11 Current Month

18%

82%

Local Employment

Local: 9 Last Month

GRANGEGORMAN EMPLOYMENT CHARTER COMPLIANCE

PUBLIC ART UPDATE

P1: Major Visual Art Commission – ongoing P2: Two projects started; Q&A for second round – next deadline, 24th June P3: Cultural Mapping Project P4: Creative Agents – event took place on 10th June P5: International Public Art Conference P6: Policy meetings continue – see Alice Maher work on site

General PAWG: Meeting regularly, including sub-Meetings

PUBLIC ART – THE AXE (AND THE WAVING GIRL)

COMMUNICATIONS/COMMUNITY

• Ongoing Communications – Summer newsletter currently being written – Preparations underway with DIT Access and DIT Sports for info sessions

around greater area – Ongoing support for public Art Programme

• Comms issued press release on ‘The Masterplan’ • Press release for ‘Home on the Grange shortly’

– Process underway to prepare for the return of local Sports clubs to Grangegormam

COMMUNICATIONS/COMMUNITY

Meetings • Meeting with Community Gardaí, GDA and GEM took

place to discuss strategy on playground.

• Last Community Liaison Committee Wed. 18th May – DIT Sport gave presentation on Fit2go Club – General Update given

• Follow up meeting to take place with Constitution Hill Flats residents with GDA and DIT Access

THANK YOU