119
Rochester Station Project DH34463 DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS DRAFT

Rochester Station Project DH34463 DB CONTRACT DOCUMENTS ... · 6/14/2013  · Rochester Station Project Part 3‐2 Part 3 Project Requirements June 14, 2013 construction activities

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

  •  

     

     

     

     

     

     

     

    Rochester Station Project 

     

    DH34463 

    DB CONTRACT DOCUMENTS 

    PART 3 

     

    PROJECT REQUIREMENTS 

     

    DRAFT 

     

  • New York State Department of Transportation 

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

    This page is intentionally blank.

  • New York State Department of Transportation 

     

     

    SECTON 1.  RAILROAD PROPERTY ACCESS REQUIREMENTS .................................................................... 1 1.1  Access Requirements onto Amtrak Property .................................................................................... 1 1.2  Access Requirements for CSX Property ............................................................................................ 1 SECTION 2  ENVIRONMENTAL COMPLIANCE ........................................................................................... 1 2.1   Scope ................................................................................................................................................. 1 2.2   Compliance with Approved NEPA Action ......................................................................................... 2 2.3   Environmental Requirements ........................................................................................................... 2 SECTION 3.  COMMUNITY OUTREACH REQUIREMENTS ........................................................................... 5 SECTION 4  BASIS OF PAYMENT REQUIREMENTS .................................................................................... 6 4.1  CPM Schedule Submittals ................................................................................................................. 7 4.2  Milestones for Item 800.0600012 Design Build Construction Work ................................................ 8 4.3  Milestone Progress Payments ........................................................................................................... 8 4.4  CPM Schedule Requirements ............................................................................................................ 9 4.5  CPM Schedule Updates and Revisions ............................................................................................ 10 4.6  Extra Work ...................................................................................................................................... 11 4.7  Four Week Look Ahead Schedule ................................................................................................... 11 SECTON 5.  SITE REQUIREMENTS ........................................................................................................... 12 5.1  General Site Requirements ............................................................................................................. 12 5.2  Codes and Standards ...................................................................................................................... 13 5.3  Foundation ...................................................................................................................................... 13 5.4  Structures ........................................................................................................................................ 13 5.5  Utilities ............................................................................................................................................ 14 5.6  Design Loading and Loading Combinations .................................................................................... 14 5.7  Materials ......................................................................................................................................... 14 5.8  Site Layout and Circulation ............................................................................................................. 14 5.9  Other Site Components................................................................................................................... 16 SECTION 6.  GEOTECHNICAL REQUIREMENTS ........................................................................................ 16 6.1  Standards and References .............................................................................................................. 17 6.2  Design Requirements ...................................................................................................................... 18 6.3  Geotechnical Work Plan .................................................................................................................. 18 6.4  Geotechnical Subsurface Investigation Plan ................................................................................... 19 6.5  Geotechnical Data Report ............................................................................................................... 20 6.6  Subsurface Investigation Records ................................................................................................... 20 6.7  Seismic Assessment Report ............................................................................................................ 20 6.8  Geotechnical Instrumentation and Construction Monitoring Plan ................................................ 21 6.9  Foundation Design Report .............................................................................................................. 23 SECTION 7.  TEMPORARY FACILITY REQUIREMENTS .............................................................................. 24 SECTION 8.   TRACK AND PLATFORM REQUIREMENTS ............................................................................ 26 SECTION 9  ARCHITECTURAL REQUIREMENTS ....................................................................................... 26 9.1  Code Requirements and Design Standards ..................................................................................... 26 9.2  Description of Proposed Facility ..................................................................................................... 27 9.3  Façade Elements ............................................................................................................................. 28 9.4  Station Ground Level....................................................................................................................... 28 9.5  Station Concourse Level .................................................................................................................. 32 9.6  Space Allocation .............................................................................................................................. 32 9.7  Information Systems ....................................................................................................................... 38 9.8  Finishes and Materials .................................................................................................................... 39 9.9  Public Art Installations .................................................................................................................... 40 

  • New York State Department of Transportation 

     

     

    9.10  Historic Canopy and SHPO Coordination ........................................................................................ 40 SECTION 10.  VERTICAL CIRCULATION REQUIREMENTS ........................................................................... 40 10.1  Pedestrian Concourse ..................................................................................................................... 41 10.2  Baggage Ramps ............................................................................................................................... 41 SECTION 11.   SUSTAINABILITY REQUIREMENTS ....................................................................................... 42 11.1  Sustainable Strategies ..................................................................................................................... 42 11.2  Energy Consumption ....................................................................................................................... 44 11.3  Life Cycle Analysis ........................................................................................................................... 44 11.4  Material Selection ........................................................................................................................... 44 11.5  Commissioning ................................................................................................................................ 45 11.6  Documentation ............................................................................................................................... 45 SECTION 12.  MECHANICAL REQUIREMENTS ........................................................................................... 47 12.1  General ............................................................................................................................................ 47 12.2  Codes and Standards ...................................................................................................................... 47 12.3  Vibration Isolation / Seismic Design ............................................................................................... 48 12.4  Mechanical Identification ............................................................................................................... 48 12.5  HVAC SYSTEMS ................................................................................................................................ 48 12.6  PLUMBING SYSTEMS ....................................................................................................................... 53 12.7  Fire Protection ................................................................................................................................ 58 SECTION 13.  ELECTRICAL REQUIREMENTS ............................................................................................... 60 13.1  General Requirements .................................................................................................................... 60 13.2   Codes and Standards ...................................................................................................................... 62 13.3  Area Types ....................................................................................................................................... 63 13.4  Maintenance requirements ............................................................................................................ 64 13.5  Mounting of equipment .................................................................................................................. 65 13.6  Electrical Service: ............................................................................................................................ 67 13.7  Generator Service and Power Distribution ..................................................................................... 78 13.8  Lighting ............................................................................................................................................ 80 13.9  Receptacles ..................................................................................................................................... 84 SECTION 14.  COMMUNICATIONS REQUIREMENTS ................................................................................. 98 14.1  Facility Requirements ..................................................................................................................... 98 14.2  General Requirements .................................................................................................................. 111 SECTION 15   INSTRUMENTATION AND CONTROLS REQUIREMENTS ................................................... 112 15.1  Building Management System (BMS) (DfE) .................................................................................. 112 SECTION 16. FACILITY PARKING AND TRAFFIC REQUIREMENTS ............................................................... 114 16.1  Parking .............................................................................................................................. 114 16.2  Pay Stations ................................................................................................................................... 114 16.3  Bus Access ..................................................................................................................................... 114 16.4  Accommodations for Bicylists ....................................................................................................... 115   

  • New York State Department of Transportation 

    Rochester Station Project Part 3‐1 

    Part 3 Project RequirementsJune 14, 2013

     

     

    SECTON 1. RAILROAD PROPERTY ACCESS REQUIREMENTS 

    The Design Builder must adhere to the railroad property access requirements while working on property under the control of either Amtrak or CSX. 

    1.1  Access Requirements onto Amtrak Property 

    A. The Design Builder is required to obtain a Temporary Permit to Enter (TPE) from Amtrak.  B. All field personnel must attend Amtrak contractor safety/security training 

    a. Available Online: http://www.amtrakcontractor.com  C. The Design Builder  is  required  to  submit  an overall  Site  Specific Work Plan and Hazard Analysis 

    (SSWP/Hazard) Form to Amtrak Engineering for review and approval.  

    D. Temporary  fencing  and  barricades  of work  zones  is  required.    All  fencing must  be  approved  by Amtrak. 

    E. Station  operations  and  areas must  remain  open  for  its  normal  operations.    Temporary  station operations staging shall be reviewed and approved by Amtrak. 

    F. Mandatory Personal Protective Equipment (PPE) for all workers worn at all times including:  a. Hard Hat, High  visibility Orange  Safety  Vest with  reflective  striping  (vest must  be  break‐

    away), Safety Glasses or goggles, Work boots, Hearing protection and Visible Safety Trained ID card.   

    G. The Design Builder shall provide to Amtrak Engineering the following: a. 2 week minimum look ahead schedule of planned work activities, updated weekly. b. Specific work plans for safe operations prior to work activities being progressed.  c. The Design Builder  shall  create perform a written daily  Job Safety Briefing with all  crafts, 

    workers, and anyone  involved on the project prior to any work beginning the briefing shall include  all  tasks  and  be  updated  as major  changes  in work  occur,  the  briefing  shall  be performed by the Employee in charge who shall keep the briefing in his/her possession and presented to Amtrak or FRA officials if requested. 

    H. Amtrak Engineering will provide Station Operation Coordination and Inspection services as it relates to Amtrak’s interests.  

    1.2  Access Requirements for CSX Property 

    A. CSX  Railroad  is  responsible  for  all  flagging  operations  and  separate  coordination  with  CSX  is required.  

    B. All field personnel must attend CSX contractor safety/security training, which  is different from the Amtrak training.  

    SECTION 2  ENVIRONMENTAL COMPLIANCE 

    2.1   Scope 

    An  essential  component  of  the  Project  is  the  comprehensive  integration  of  environmental compliance into all design and construction activities by the Design‐Builder. Except as otherwise detailed herein, the Design‐Builder shall be responsible for preparing its design, carrying out its 

  • New York State Department of Transportation 

    Rochester Station Project Part 3‐2 

    Part 3 Project RequirementsJune 14, 2013

     

     

    construction activities and undertaking other activities as needed  to ensure  compliance with the  Project’s  Environmental  documentation  and  all  applicable  environmental  laws  and regulations.  This Project Requirement identifies certain required actions by the Design‐Builder to  ensure  that  the  Environmental  Requirements  are  complied with  throughout  the  Project activities. 

    2.2   Compliance with Approved NEPA Action 

    NEPA environmental approval for the subject project has been granted based on analysis and documentation of potential environmental impacts of the identified preferred alternative. This analysis  is summarized along with any  identified environmental commitments and depicted  in the May 2013 Federal Railroad Administration  (FRA) Categorical Exclusion Worksheet  for  the subject  project.  If  during  detailed  design  and/or  construction  the  Design‐Builder  introduces design elements, variations, or methodologies  that potentially  induce environmental  impacts that differ from those  identified  in the approved Categorical Exclusion Worksheet or  is unable to comply with established environmental commitments then the NEPA process for this project will need  to be  re‐evaluated by  the Design‐Builder and  reviewed by  the Department prior  to proceeding with construction. This requirement also applies to proposed variations which may affect resources covered under Section 106, Section 4(f), and other applicable federal and state environmental regulations. The need to re‐evaluate the NEPA process may  impact the overall project schedule. 

    2.3   Environmental Requirements 

    2.3.1   General 

    A)  Unless  otherwise  indicated  in  the  Contract  Documents,  the  Department  will  be  responsible  for obtaining  all  Environmental  Approvals  as  identified  in  this  Section.  In  the  event  the  Design‐Builder requests changes to the permits obtained by the Department, the Design‐ Builder shall be responsible for the preparation of all information including materials, investigations, testing and documentation, as necessary to support said permit modification request. Based on the Design‐Builder’s provision of said information,  the  Department will  undertake  the  requested  permit modification with  the  respective permitting  agencies  on  the Design‐Builder’s  behalf.  The Department will  not  be  responsible  for  any delay or additional cost associated with the Design‐Builder’s requested permit modification; 

    B) The Design‐Builder shall procure all Environmental Approvals as needed for all Design‐ Builder located areas, including staging, borrow and disposal sites, and any other areas used by the Design‐Builder, for its convenience, in the construction of the Project; 

    C) The Design‐Builder shall be responsible for obtaining all new Environmental Approvals. For any such approvals  required  to  be  obtained  by  the  Design‐Builder  that  must  formally  be  issued  in  the Department's name, the Department will cooperate with the Design‐Builder as reasonably requested by the  Design‐Builder,  including  execution  and  delivery  of  appropriate  applications  and  other documentation prepared by Design‐Builder in a format approved by the Department; 

    D) The Design‐Builder shall be solely responsible for violations of any Environmental Requirements; 

  • New York State Department of Transportation 

    Rochester Station Project Part 3‐3 

    Part 3 Project RequirementsJune 14, 2013

     

     

    E) The Design‐Builder shall indemnify the Department and the State of New York for any fines, violations or damages incurred by reason of failure of the Design‐Builder to comply with Environmental Approvals. 

    2.3.2   Environmental Plans 

    The Design‐Builder  shall be  responsible  for preparing  the  following documents  in  conformity with all Environmental applicable standards, regulations, permits and requirements.   For each documents  listed, the Design‐Builder shall  identify the frequency of submission of compliance reports to the Department. 

    A) Health and safety plan (HASP); 

    B) Soil Erosion and Sediment Control Plan complying with the New York State SPDES General Permit for Stormwater Discharges from Construction Activities (GP‐0‐10‐001) This plan is to include but is not limited construction entrance(s), construction phasing, drawings showing size and  location of permanent  (seeding, pavement) and temporary  (silt  fence, temporary seed) erosion controls, and details. 

    C) Stormwater pollution prevention plan (SWPPP) 

    D) Contaminated Soil Sampling and Analysis Plan (for areas of excavation in the railroad bed) 

    E) Based  on  the  results  of  the  Contaminated  Soil  Sampling  and Analysis  Plan  the  following plans may be required (see NYSDOT Standard Specification  Section 205): 

    • Contaminated Material Handling Plan (CMHP) 

    • Field Organic Vapor Monitoring Plan (FOVMP) 

    • Disposal Plan 

    2.3.3   Environmental Plan Deliverables 

    At  a minimum,  the  deliverables  shall  include  the  items  listed  in  Table  2‐1  –  Environmental Compliance Deliverables, for the Department’s review. Each of the deliverables  listed  in Table 2‐1  ‐  Environmental  Compliance  Deliverables,  shall  be  provided  to  the  Department  by  the earlier of: (i) 30 days after NTP; and (ii) 30 days prior to the relevant on site activity,  including start of construction. 

  • New York State Department of Transportation 

    Rochester Station Project Part 3‐4 

    Part 3 Project RequirementsJune 14, 2013

     

     

     

    Table 2‐1 – Environmental Compliance Deliverables 

    Deliverable  Number of Copies  Reference Section

    Hardcopy  Electronic 

    Health and safety plan  1  1  10.4.2 

    Stormwater pollution prevention plan & NOI  1  1  10.4.2 

    Soil Erosion and Sediment Control Plan  1  1  10.4.2 

    Contaminated Soil Sampling and Analysis Plan  1  1  10.4.2 

    2.3.4   Soil Erosion and Sediment Control 

    The Design‐Builder shall provide the department with a SWPPP and Notice of Intent complying with  the New York State SPDES General Permit  for Stormwater Discharges  from Construction Activities  (GP‐0‐10‐001)  60  days  prior  to  any  ground  disturbance  for  the  Department’s signature.    The  Department  will  apply  for  coverage  under  the  SPDES  General  Permit  for Stormwater  Discharges  from  Construction  Activities.  The  Design‐Builder  shall  review  final SWPPP and sign/complete Contractor/Subcontractor SPDES Permit Certification form (CONR 5). Discharges  covered  under  the  SPDES  general  permit  shall  not  commence  until  the  date authorized on the SPDES Acknowledgement Letter. 

    2.3.5   Performance 

    The Design‐Builder  shall perform of  all  activities  required under each of  the  foregoing plans until final acceptance of the Project, except to the extent that the plans provide for activities to be undertaken by the Department or third parties. Provisions  in said plans for activities to be undertaken by  the Department  or  third  parties  are  subject  to  prior written  approval  by  the Department. 

    2.3.6   Environmental Approvals and Identified Permits 

    All environmental design approvals for this project shall be acquired prior to construction.  The following is an initial list of permits that have been identified as necessary for this project: 

    A) SPDES General Permit for Stormwater Discharges from Construction Activities 

    B) NYSDEC Waste transporter permit. 

    The Design Builder is responsible for identifying and acquiring all necessary permits required to complete the proposed Work. 

  • New York State Department of Transportation 

    Rochester Station Project Part 3‐5 

    Part 3 Project RequirementsJune 14, 2013

     

     

    2.3.7   Asbestos Containing Materials (ACMs) 

    Based  on  laboratory  analyses  of  bulk  samples  collected,  ACMs  are  present  in  the  existing Station. 

    2.3.8   Inaccessible/Assumed ACMs 

    Inaccessible/Assumed ACMs were found within the former passenger tunnel as ceiling plaster, 9”  x  9”  floor  tile  and mastic  and  thermal  pipe  insulation.    Refer  to  ”Hazardous Materials Investigations”  found  on  the  project    website:  https://www.dot.ny.gov/main/business‐center/designbuildproject  for a  list of  inspections and samplings performed  to determine  the presence of asbestos‐containing materials  (ACM). The Design‐Builder  shall be  responsible  for the  identification,  removal  and  disposal  of  all  asbestos  containing  materials  (ACMs) encountered in the inaccessible areas if such areas will be disturbed during the performance of the Work.  The  removal  and  disposal  of  ACMs  shall  be  performed  in  accordance  with  the Contract Documents and the applicable safety and health codes. 

    The Design‐Builder shall be responsible for providing any necessary asbestos inspection, project design  and  abatement project/air monitoring  services  as part  of  this  contract  in  accordance with 12 NYCRR 56. NYSDOL asbestos licensure and applicable staff certification(s) are required for structure rehabilitation work where confirmed or presumed asbestos‐containing materials are  impacted.    All  necessary  asbestos  inspection,  project  design  and  project/air monitoring work  shall be  conducted  in  conformance with policy and guidance provided  in NYSDOT TEM Section 4.4.19 ‐ Asbestos Management. 

    2.3.9   Hazardous Waste/Contaminated Soils 

    A Contaminated Soil Sampling and Analysis plan shall be completed for all proposed excavation areas within  the  railroad bed.   The Design‐Builder  shall be  responsible  for  the  identification, removal and disposal of all hazardous waste or contaminated  soil encountered. The  removal and disposal of Hazardous Waste or Contaminated soils shall be performed in accordance with the Contract Documents and the applicable regulations.   

    A Contaminated Soil Sampling and Analysis plan for the station area has been completed. Refer to ”Hazardous Materials Investigations” found on the project  website: 

    https://www.dot.ny.gov/main/business‐center/DesignBuildProject 

    SECTION 3.  COMMUNITY OUTREACH REQUIREMENTS 

    Outreach has been and will be critical to obtain the full support of all project stakeholders and the community.   The Design‐Builder shall provide support to the Department  inclusive of, but not limited to, the following groups. 

    A. Rochester Station Executive Steering Committee 

  • New York State Department of Transportation 

    Rochester Station Project Part 3‐6 

    Part 3 Project RequirementsJune 14, 2013

     

     

    NYSDOT  has  formed  an  Executive  Steering  Committee  to  guide  the  design  of  Rochester Station  as  it  progresses.   Mayor  Tom  Richards  of  the  City  of  Rochester,  United  States Congresswoman Louise Slaughter, and Commissioner Joan McDonald of the New York State Department of Transportation comprise the Committee, along with technical advisory from representatives of Amtrak, Trailways of New York, and Parsons Brinckerhoff. The  Design‐Builder  shall  aide  NYSDOT  to  keep  the  Committee  up  to  date  on  the development of the design by making presentations to the Committee.  The Design‐Builder shall respond to comments and incorporate input and guidance from Committee members. 

    B. Council for Persons with Disabilities The Council  for Persons with Disabilities  is an advisory council  to  the County Executive of Monroe County and to the Mayor of the City of Rochester.  The Council has provided input and  guidance  developing  a  preliminary  design  that  fulfills  the  needs  of  persons  with disabilities in Rochester and Monroe County as they utilize Rochester Station.  The Design‐Builder shall be required to meet with and present to the Council as the design progresses. 

    C. Rochester Cycling Alliance The Rochester Cycling Alliance is a cycling advocacy group focused on promoting cycling in Rochester,  development  of  cycling  roads  and  trails,  and  distributing  information  about safety and cycling in general. The Design‐Builder shall assist the Department as needed  in presenting the final design to the Rochester Cycling Alliance for their input. 

    D. Reconnect Rochester Reconnect  Rochester  is  a  transit  advocacy  group  focused  on  promoting  mobility  and physical connections between downtown Rochester and the surrounding neighborhoods. The Design‐Builder shall assist the Department as needed  in presenting the final design to Reconnect Rochester for their input. 

    E. Other Groups The  Design‐Builder  shall  provide  support  to  the  Department  and  the  Executive  Steering Committee to meet with community groups such as: 

    a. Area universities,  b. RGRTA,  c. High Falls Business Improvement District,  d. Rochester Downtown Development Corporation e. Monroe County Department of Transportation f. Empire State Passenger Association 

    SECTION 4  BASIS OF PAYMENT REQUIREMENTS 

  • New York State Department of Transportation 

    Rochester Station Project Part 3‐7 

    Part 3 Project RequirementsJune 14, 2013

     

     

    The scheduling    of    submittals,    procurement    and    construction    is   the responsibility of the Design Builder.  Progress payments shall be subject to the requirements of DB §109‐2.  All Work, including Phase II, if included in the contract,  shall  be  monitored  by  a  detailed  Critical  Path  Method  Schedule "CPM  Schedule".   The Design Builder shall submit the CPM Schedule to NYSDOT’s Project Manager for approval.  The CPM Schedule shall meet the requirements of DB §108 and Part 2‐ Appendix 1.     The approved CPM Schedule  is used  to assist NYSDOT    in  appraising  the  reasonableness  of  the  proposed  schedule,  as  well  as,  its  compliance  with  Contract    requirements.        This    approved  CPM    Schedule    shall    be    the    basis    for    the  evaluation    of   Design  Builder    performance    and    approval  of  Progress  Payments  for  Item 800.0600012 Design Build Construction Work.     Progress Payments will be made according to the approved CPM  schedule as each Milestone  is  completed  to  the  satisfaction of NYSDOT’s Project Manager.   

    The    CPM    Schedule    is    the    Design  Builder's    committed    plan    to    complete    all   Work  (including  punch  list  items)  within  the  allotted  time.  The  CPM  Schedule  shall  be  based  on  and  derived  from  detailed  schedules  used  to  monitor all Contract activities.  

    4.1 CPM Schedule Submittals A. Preliminary   Schedule:       No    later   than   14   calendar   days   after   Notice to Proceed,   the  

    Design Builder  shall  submit  the Preliminary Schedule for NYSDOT review and approval of the  Design Builder's  planned  activities  during the first 90 calendar days.  The Preliminary Schedule shall  indicate  the cost of activities and milestones expected  to be completed or partially completed before submission and approval of the complete CPM Schedule.  

    B. CPM Baseline Schedule:  No later than 30 calendar days after Award of Contract, the Design Builder shall submit CPM Schedule depicting the Design Builder's Work plan for the entire Contract.  The Design Builder shall submit to the NYSDOT’s Project Manager for review and approval the following: 

    1. Logic Diagram:   A detailed CPM Time‐Scaled Network Logic Diagram. 

    2. Cost Loaded CPM  for  Item 800.0600012 Design Build Construction Work.     The Design Builder will create a proposed  list of Milestones  including Manadatory Milestones and the percentage of  the  total price bid  for  Item 800.0600012 Design Build Construction Work  associated with  each Milestone.      The  Design  Builder may  propose  to  include Milestones  in addition  to  the mandatory Milestones.   The Department will  review  the Design  Builder’s  proposed  Milestones  and  Associated  Progress  Payments  for reasonableness prior to approval.  These approved Milestones and Associated Progress Payments  for  Item 800.0600012 Design Build Construction Work are  the basis  for  the Design Builder’s Cost  Loaded CPM Schedule.     Any  revisions and modifications  to  the approved CPM Schedule must be approved by NYSDOT’s Project Manager in writing. 

    3. Cost  Report:   A  Cost  Report  generated  from  the  cost  loaded  CPM  Schedule  is  to  be submitted 14 calendar days after approval of the   Line Item Breakdown,  in accordance with Paragraph F.(3).  

  • New York State Department of Transportation 

    Rochester Station Project Part 3‐8 

    Part 3 Project RequirementsJune 14, 2013

     

     

    4. Narrative:  A written narrative explaining the schedule and the Design Builder's general approach for meeting interim and completion milestone dates.  

    4.2 Milestones for Item 800.0600012 Design Build Construction Work A. The  Design  Builder  shall  include  the  following  mandatory  Milestone  and  required 

    Completions in the CPM Schedule: 

    Activity ID 

    Activity Description  Follows

    Logic Tie  Duration 

    Responsible Party 

    Progress Payment Structure

    P0010 Submission of 

    Health and Safety Plan 

      FS 2 months from the Notice To 

    Proceed 

    Design Builder 

     

    Proposed by Design 

    Builder/Approved by NYSDOT 

     

    P0020 

    Temporary Facility, Site 

    Work, Demolition of the existing Building and 

    appurtenances. 

    P0001  FS Proposed by 

    Design Builder/Approved 

    by NYSDOT 

     

    P0030  Station Building  P0002  FSP0040  Tunnel  P0003  FSP0050  Station Platform  P0004  FSP0060  Platform Tracks  P0005  FS 

    P0070  Substantial Completion  P0006  FS 

    32 months from Notice To Proceed 

    P0080 

    Project Completion, in accordance with DB 109‐11.3 

    P0007  FS 

    36 months from the Notice To 

    Proceed  

    B. The Design Builder’s Preliminary, Baseline, and Monthly Update schedules shall incorporate the mandatory Milestone  Completion  Dates.    The  Department’s  approval  of  the  Design Builder’s  schedule(s),  in part, will be  subject  to  the Design Builder’s  compliance with  the Milestone Schedule.   

    C. Failure    of    the    Design  Builder    to    submit    the    CPM    Preliminary,    Baseline, Update Schedules  and  any  required  revisions  thereto within  the  time  limits    stated,    shall    be  sufficient    cause    to   withhold    approval   of    the   Design Builder's    invoices  for progress payment(s)  until  such  delinquent  submittal  is made    and  accepted  by NYSDOT’s  Project Manager. 

    4.3  Milestone Progress Payments 

    The  Design Builder  shall  furnish  a  breakdown  of  the  total  price  bid for Item 800.0600012 Design  Build  Construction Work  by    assigning    dollar    values    to    each   milestone,   which  

  • New York State Department of Transportation 

    Rochester Station Project Part 3‐9 

    Part 3 Project RequirementsJune 14, 2013

     

     

    cumulatively  equals  the  total   amount.    Upon  approval  by  the  NYSDOT’s Project Manager,  the   percentages associated with each   milestone shall   be   used    in   the   Cost   Report   as   a  basis  for  determining  progress  payments.    The  Design Builder's  overhead  and  profit  shall  be  prorated  through  all  activities.   

    4.4  CPM Schedule Requirements  

    A. The   CPM   Schedule   shall    include   all   of   the   Design Builder's   submittals,   procurement  and   construction   work   activities   with   sufficient   detail   such   that all  interfaces with all direct and related parties to the Work are shown.  

    1. The   Work   of    the   Design Builder,   Subcontractors,   Suppliers,   CSX, Amtrak   and   all  others  that  affect  progress  shall  be  shown  and  identified on the schedule by using Activity Codes.  

    2. Procurement  activities  shall  be  shown,  including  submittal  and  approval      of      shop   drawings,   fabrication   and   delivery   of   the material.  

    3. Interruption    of    service,    delivery    of    NYSDOT/Amtrak/CSX‐furnished equipment, project phasing and any other Technical Provision requirements shall be shown.  

    B. The  CPM  Schedule  shall  contain  sufficient  construction  activities  to  represent  the Work, subject to the approval of the NYSDOT’s Project Manager.  

    C. The  CPM  Schedule  shall  be  of  the  precedence  type.    Activity  precedence  relationships consistent with proper logic shall be shown with lag codes.  

    D. Logic  and  activity  time  durations  shall  be  established  by  the  Design Builder  consistent    with       Contract       requirements       and       reflective       of       proper   coordination   between  trades.       Logic   shall   show   how   the   start   of   a   given   activity    is   dependent   on   the  completion   of   preceding   activities   and    its    completion  restricts  the  start of  following activities.  No activity shall have a duration greater than 30 calendar days.     

    E. The start date of the CPM Schedule shall be the Notice to Proceed.  The completion  date  of  the  CPM  Schedule  shall  be  the  Contract  completion  date as specified in Part 1 Design Build Agreement, which shall be input as the "Project Must Finish No Later Than" date.  All intermediate milestones required in the Contract shall be shown in proper logical sequence and  input as "Start‐No‐ Earlier‐Than" or "Finish‐No‐Later‐Than" dates.   The Design Builder may add milestones with the approval of NYSDOT’s Project Manager.  

    F. Activities shall be described such that the Work is readily identifiable for assessment of start and completion, as well as  intermediate status. Descriptions   shall   utilize   Activity   Codes  for   physical    locations    such   as   column  lines,  stations and elevations where possible  to define the Work.     Activity description of "start", "continue",   "completion",   "X%",   "Y%",  "Z%" or similar non‐specific descriptions will not be allowed.  

    G. The CPM Schedule shall be calculated  in working days.   The working day to calendar date correlation  shall be based upon  the Design Builder's proposed work week with adequate allowance  for  weekends,  legal  holidays  and  any  special  requirements  of  the  Contract.  

  • New York State Department of Transportation 

    Rochester Station Project Part 3‐10 

    Part 3 Project RequirementsJune 14, 2013

     

     

    Durations for activities shall not be less than one work day.    Multiple shifts per day should be shown using multiple resources.  

    H. Seasonal  weather  conditions  shall  be  considered  in  the  planning  and  scheduling  of  all  Work    influenced   by   high   or    low   ambient    temperatures    for    the   completion   of   all  Work   within    the    allotted   Contract    time.     Appropriate  allowances  shall be made  for anticipated time  losses, due to normal rain and snow conditions by statistically expanding the estimated  time durations  for weather  sensitive activities.   Additionally, allowance  for lower  productivity  during  bad  weather  periods  shall  be  made  by  increasing  activity   durations   by   an   appropriate   amount.      All   allowances   for anticipated time losses shall be stated in the baseline narrative.  

    I. The review period shown in the Schedule for submittals shall conform with review periods stated in the Approved Project Quality Control Plan. 

    J. Constraint     dates     are     permitted     only     on     Milestone     activities,     unless otherwise approved by NYSDOT’s Project Manager.  

    K. All  activities  with the  exception  of  Work  start  and  end  nodes  shall  have  predecessors and  successors.    The  start  of  an  activity  shall  have  a  start‐to‐  start      or      finish‐to‐start   relationship   with   preceding   activities.      The  completion  of  an  activity  shall  have  a  finish‐to‐start  or  finish‐to‐finish  relationship  with  a  succeeding  activity.    Start‐to‐finish relationships are not acceptable.  

    L. CPM   Schedules   which   have   been   resource   leveled   are   permissible  provided  the  effects  of  leveling  are  incorporated  in  the  schedule  using  "Start‐no‐Earlier Than" date constraint. 

    4.5  CPM Schedule Updates and Revisions 

    A. The   Design Builder    shall   update    the   CPM   Schedule   monthly,   whether   or   not    the  NYSDOT’s Project Manager   has   accepted   the   schedule,   to   reflect   actual   construction  progress.  The update shall include the historical record of actual start and  finish  dates  for  activities  in  progress,  or  completed,  percent  complete  based on a unit of measure and remaining duration based on the amount of  work days required to complete the activity.  

    B. A monthly progress meeting  shall be held.   At  this meeting, attended by    the   NYSDOT’s Project Manager,   all   progress   during    the    calendar   month    shall   be   addressed   and  reviewed  for  incorporation  into  the  schedule  by  the  Design Builder.   Within  a  period  of  10  calendar  days  from  the  date  of  this  progress  meeting, the Design Builder shall submit  the  schedule update  to  the NYSDOT’s Project Manager   with    the    agreed   upon  changes  for approval.       The approved updated CPM schedule shall be    the   basis  for  the progress payment.  

    C. A   CPM   Progress   Narrative   Report   shall be submitted   as  part   of   the   update   analysis shall include, but not be limited to:  

    1. Description of cost and schedule status.  

  • New York State Department of Transportation 

    Rochester Station Project Part 3‐11 

    Part 3 Project RequirementsJune 14, 2013

     

     

    2. Discussion  of  current  and  anticipated  delaying  problem  areas  and  their  estimated impact.  

    3. Schedule slippage and/or progress along the critical path  in terms   of   days   ahead   or  behind   the   allowable   dates,   and    if   the   Work    is   behind schedule, progress along other paths with negative float.  

    4. Logic changes and an explanation of the  revisions.    Revisions  to  activities  not  worked  on    during    the    period,    including    changes    in    duration,  or  revisions  to  activity relationships are  to be considered    logic  revisions.   Out‐of‐sequence activities are not acceptable and shall be corrected in logic revisions prior to submission to NYSDOT.  

    D. When,  in  the  NYSDOT’s Project Manager's  opinion,  the  CPM  Schedule  fails  to  reflect  the   Design Builder's   actual   plan   and   method   of   operation,   or    the   Design Builder's  completion  date  as  indicated  by  the  CPM  is  more  than  1  month  behind  the  Contract  completion  date, NYSDOT’s Project Manager  may  require  the  Design Builder  to  submit for review within 2 weeks, a revised CPM Schedule for completion of the remaining Work within the Contract completion date.  

    E. Bar Chart:  The length of the bar shall equal the Baseline Schedule.  Status shown should be based on the Update Schedules.  

    F. When  it becomes apparent activities must be added  to  the CPM Schedule,  they must be added  in  a method  that  completion  dates  of  any  succeeding  baseline  activities  are  not affected.  All revisions must be submitted to NYSDOT’s Project Manager for approval before incorporation into the CPM Schedule.  

    4.6  Extra Work   

    To  insure  that  the  CPM  Schedule  shall  continue  to  accurately  reflect  the  Design Builder's  plan  for  the  Work  and  that  it  incorporates  the  impact  of  all  Extra  Work as soon as the Work scope can be defined, the following procedure shall be   followed   to    incorporate   Extra  Work  (including  deletions  of  Work)  in  the  Schedule.  

    When   an   Extra   Work   proposal    is   submitted   by   the   Design Builder,   the   Design Builder  must  identify  in  a  CPM‐type  sketch,  additional  work  required  as  a  result  of  the  proposal and  its  interrelationship  to  the  CPM  Schedule.    This  sketch  shall  show  all    activities,    logic  revisions,   duration    changes,    and    associated    cost    changes    for   performing  the Work  in question.  Upon  NYSDOT’s Project Manager's approval of the sketch, the  Design Builder  shall  incorporate  the  revisions  into  the  Baseline  Schedule  and  the  Monthly Cost Report at the next  Schedule  update.    No  additional  compensation  will  be  paid  the  Design  Builder  for preparing these revisions.    Any request for Extension of Time must be verified by CPM Analysis and be in accordance with DB 108‐6 “EXTENSIONS OF CONTRACT TIME”.   

    4.7  Four Week Look Ahead Schedule  

    The  Design Builder  shall  provide  with  the  monthly  schedule  update,  or  more  frequently if required by NYSDOT, a Four Week Look Ahead Schedule to be used   for   coordination   of   the  

  • New York State Department of Transportation 

    Rochester Station Project Part 3‐12 

    Part 3 Project RequirementsJune 14, 2013

     

     

    Design Builder’s  work  with  Railroad  operation,  other  work  groups and at regular Progress Review Meetings.  

    This  Four Week  Look  Ahead  Schedule  shall  contain  early  start  and  early  finish  dates  for  all activities scheduled or planned for start and/or completion in the upcoming 4 week period.  It shall include design, submittal, procurement and construction activities, as applicable. 

    SECTON 5. SITE REQUIREMENTS 

    5.1  General Site Requirements 

    A. Prior  to  construction  activities,  the  Design  Builder  and  Department  representative  shall identify existing site  features to remain such as trees,  landscape, walks, etc; and establish protection measures to for duration of project. 

    B. Develop phased erosion and sediment control plan meeting the guidelines of the New York Standards  and  Specifications  for  Erosion  and  Sediment  Controls;  maintain  erosion  and sediment  controls  through  duration  of  construction.    Provide  stabilized  entrances  to prevent mud  from  leaving  the site,  regularly sweep and sprinkle water  to avoid mud and dust concerns on local streets and neighboring properties. 

    C. Provide  a  Storm Water  Pollution  Prevention  Plan  (SWPPP)  in  accordance  with  NYSDEC Standards and Design Guidelines.  SWPPP shall include temporary and permanent measures and will require review and approval by local MS4 officer and NYSDEC prior to construction.  Install stormwater measures in accordance with approved SWPPP and Notice of Intent and Notice of Termination. 

    D. Existing features in the work area including buildings, walks, pavements, curbs, lighting and other  site  amenities  should  be  demolished  and  disposed  in  accordance  with  City ordinances,  obtain  needed  demolition  permits.  Coordinate  utility  disconnects with  each utility provider.   Clear site of  trash, debris, vegetation,  trees  (other  than  those which can remain), and any materials not incorporated in the project design; dispose of in accordance with City ordinances. 

    E. Provide site security with a fence and lockable gates for all phases of construction.   F. Provide  safe,  reliable  ingress/egress,  traffic  circulation  and  pedestrian  circulation  for  all 

    public  use  areas  including  temporary  and  permanent  station  and  amenities  through  all phases of construction. 

    G. Provide parking  lots and site  roadways  in accordance with Amtrak Standard Program and Planning  Standards  and  Guidelines.    Based  on  geotechnical  report,  provide  a  pavement design  for parking areas  in accordance with NYSDOT pavement design guidelines.   For all pavements  that will  accommodate  bus  traffic  upon  completion  of  any  phase,  provide  a heavy duty pavement design to accommodate the largest vehicles anticipated for use by the local and regional transportation providers. 

  • New York State Department of Transportation 

    Rochester Station Project Part 3‐13 

    Part 3 Project RequirementsJune 14, 2013

     

     

    H. Provide  shelters  and  amenities  to  accommodate  taxi,  shuttle bus,  local bus  and  regional transportation service in accordance with Amtrak Standard Program and Planning Standards and Guidelines.   

    I. Provide concrete walks and curbing in accordance with ADA Standards for Accessible design and Amtrak Standard Program and Planning Standards and Guidelines.   

    J. Provide bicycle parking Amtrak Standard Program and Planning Standards and Guidelines and City of Rochester Bicycle Master Plan. 

    K. Provide a detailed Landscaping Plan prepared by a professional  landscape designer  in accordance with  Amtrak  Standard  Program  and  Planning  Standards  and  Guidelines;  install  landscaping components in accordance with approved plan.   

    5.2  Codes and Standards 

    A. New York State Building Code 2010 B. ACI 318‐08 “Building Code Requirements for Structural Concrete and Commentary” C. ACI 530 Building Code Requirements for Buildings D. AISC Manual of Steel Construction E. ASCE 7‐10 Minimum Design Loads for Buildings and Other Structures 

    5.3  Foundation 

    A. Geotechnical  report  and  available  soil  data will  be  given  in  an  addendum  as  it  becomes available. 

    B. Building  foundation  recommendation  will  be  provided  in  the  Geotechnical  Report.  The Design‐Builder  may  design  the  foundations  using  the  existing  building’s  caissons. Information about the caissons will be available in the Geotechnical Report. 

    C. Tunnel  and  platform  foundation  and  fill  recommendations  will  be  available  in  the Geotechnical Report. 

    5.4  Structures 

    A. Building  structure  shall  be  determined  and  designed  by  a  NYS  licensed  Professional Engineer.  Building structural system shall comply with all applicable codes and regulations even if not explicitly listed in this document. 

    B. Building structural system shall be designed to accommodate the architectural aesthetic as presented  in these documents and optimize the space as described  in the Amtrak Station Program and Planning – Standards and Guidelines.  

  • New York State Department of Transportation 

    Rochester Station Project Part 3‐14 

    Part 3 Project RequirementsJune 14, 2013

     

     

    5.5  Utilities 

    A. Provide  utility  service  for  temporary  station.    Facility  to  utilize  electric  heat.    Temporary station to utilize overhead wiring, electric and communication service to permanent station to be underground. 

    B. Design Builder to provide the services of an underground utility locating service to find and map potential obstructions over entire site prior to construction. 

    C. Water service – Provide new water mains appropriately sized for:  D. projected domestic use,  E. Sprinklers in accordance with mechanical section, F. Site hydrants to provide protection in accordance with NYS Building Code. G. Fire protection main, domestic service main, backflow prevention and related facilities shall 

    meet  Ten  States  Standards, City Water Department  regulations  and Monroe County/NYS Health Department regulations. 

    H. Provide  and  install  new  sanitary  collection  piping  sized  to  accommodate  all  proposed  facilities.  Sanitary facilities shall meet Ten States Standards, City Sanitary Department regulations and Monroe County/NYS Health Department regulations. 

    I. Stormwater collection shall meet the SWPPP requirements identified in Site Design section. J. Coordinate and install private utilities (including but not limited to electric, gas, communications) in 

    accordance with the standards and guidelines of the utility provider and the City. K. Coordinate with Amtrak IT for power and conduit sizing/location for the temporary station and new 

    station. L. Coordinate with Trailway’s IT for power and conduit sizing/location for the new station.  

    5.6  Design Loading and Loading Combinations 

    A. All loads and load combinations shall be compliant and adhere to the New York State Building Code 2010 and ASCE 7‐10. 

    5.7  Materials 

    Refer to Part 8 – Project Specifications. 

    5.8  Site Layout and Circulation   

    The Rochester  Station Project  shall promote ease of  transfer between  transportation modes and  circulation  throughout  its exterior  site, but must also  segregate different uses  for  safety reasons.  Intercity and potential  future city bus operations cannot  share access or  space with cars and shuttles. Drop off/pickup for passengers must be separated from general parking and shall share access with both short term parking and taxi/shuttle bus movements.   The Design‐Builder  shall  ensure  pedestrians  are  protected  and  separated  from  vehicular  movements wherever possible. 

  • New York State Department of Transportation 

    Rochester Station Project Part 3‐15 

    Part 3 Project RequirementsJune 14, 2013

     

     

    It is desirable to promote a visual presence of the new station along the North Clinton frontage in order to create a visual connection with downtown Rochester along that street to the south. To ensure the shortest possible passenger travel distance, the station building should be sited as close as possible to the center line of tracks, while adhering to the twenty‐five foot minimum clearance  from  the  centerline  of  the  nearest  track  bed.    The  goal  of  a  ‘seamless  journey’ through  the  station  building  to  the  boarding  area  shall  be  achieved with  this  configuration.  There are other mandates that shall  impact the  location of the station building and other site features including, but not limited to: 

    A. Replacement of the existing  low‐level platform with an ADA compliant high  level center island platform  for passenger access  to Amtrak service  to Empire, Maple Leaf, and Lake Shore Corridors. 

    B. Minimize customer travel distance between station functions and the platform. C. Consolidation of  traffic movements’ onto  the Central Avenue  frontage  in Phase One  to 

    eliminate sight distance conflicts at Joseph Avenue and North Clinton Avenue. D. Segregation of baggage and passenger traffic. E. Provision of ramps to accommodate baggage movements in lieu of elevators. F. The new  station building must maintain  a minimum of  twenty‐five  feet  clear envelope 

    from the centerline of the southernmost track with additional 10’ setback recommended wherever possible to minimize flagging and lower construction costs for the building. 

    G. Provide ADA accessible path connecting all site and program elements. H. Provide a covered path to transport baggage from the Baggage Work Area to the exterior 

    baggage ramp and into the Concourse without exposing baggage to weather. I. Provide a covered path to transport baggage from the Concourse to the Platform without 

    exposing baggage to weather. J. Provide  a  covered  area  for  passengers  to  board  Trailways  buses.    Since  wheelchair 

    boarding is at the very rear of the bus, the bus canopy extends to cover the entire length of the buses. 

    K. Install large skylight units in both the baggage and bus boarding canopies to allow natural light into these large shaded areas. 

    L. Allow for the installation of bicycle share facilities. M. Widen North Clinton and Joseph Avenues to provide street side bus stops for RGRTA bus 

    routes.  Provide bus shelters at these layovers for waiting passengers. N. Provide queue space for taxis, university shuttle vans, and other paratransit services O. Allow  for  passenger  drop  off  and  pick  up  at  the  Station  entry,  and provide  short‐term 

    parking near the Station entry. 

    The  site  layout  shall  incorporate  softscape  wherever  possible,  eliminating  any  unnecessary paving  in accordance with the City of Rochester’s Project Green policy, especially at the North Clinton Avenue frontage.  North Clinton has been identified by the City as one of the proposed “Green  Corridors”  that  shall  feature  integrated  bicycle  and  pedestrian  circulation.    The landscape  shall  include  trees  along  the  street  line  and  along  pedestrian  paths  to  create  an urban  environment  that  is  pleasant  and  friendly  for  bicyclists  and  pedestrians.    The Design‐Builder  shall  balance  the  requirements  of  both  the  City  of  Rochester  and  Amtrak  security 

  • New York State Department of Transportation 

    Rochester Station Project Part 3‐16 

    Part 3 Project RequirementsJune 14, 2013

     

     

    concerns,  including small  trees compatible with an urban setting  that do not allow  for hiding places.  Landscaped islands shall be incorporated in the parking areas to soften the hardscape.  LED  site  lighting  shall be  supplemented with  additional pedestrian  level  lighting  along major circulation routes.   The Design‐Builder shall provide  life‐cycle cost analysis for LED site  lighting or other proposed substitute.   Loading dock and trash and recycling storage shall be screened from public view. 

    Exterior  to  the  station building, a Kiss and Ride Drop‐Off  location,  taxi  stand, and  short‐term parking are sited along the Central Avenue frontage. For ease of arrival and departure, the pick‐up and drop‐off lanes are designed at a minimum of twelve feet wide. Similarly, the taxi berths are minimally  twenty  feet  in  length with  an  additional  five  feet  for maneuvering.  Sidewalks throughout  the  site  shall  be  a  minimum  of  8  feet  wide,  and  crosswalks  shall  receive  a thermoplastic decorative  treatment.    The Design‐Builder  shall provide  speed  tables  at major pedestrian crossings for both traffic calming and for ease of accessible travel with bollards for pedestrian safety. 

    5.9  Other Site Components  

    A place for garbage storage and retrieval shall be provided onsite concealed and screened from public view.  Additional station maintenance items, such as snow plow, ice melt, and additional baggage floats and carts shall be accommodated with a minimum of three hundred square feet of covered exterior Amtrak storage space per Amtrak Functional Space Requirements, issued on 12/30/2012.  

    In order to further sustainable initiatives, a Construction and Building Site Waste Management Plan shall be in place to ensure 50% recycling and/or salvaging of existing material.  Throughout the site, low maintenance landscaping shall be integrated to minimize impervious surfaces.  The Design‐Builder shall grade areas away from structures to prevent ponding, while mitigating the flow of runoff over impervious surfaces. 

    SECTION 6.  GEOTECHNICAL REQUIREMENTS 

    The  Design‐Builder  shall  be  responsible  for  geotechnical  design  and  construction  of  all permanent  and  temporary  structures,  including  assessing  available  information,  geotechnical analysis and reporting, geotechnical instrumentation and monitoring, and protection of existing infrastructure,  structures  and  utilities  in  accordance with  the  requirements  of  the  Contract Documents.  These requirements are considered as a minimum and do not include all possible conditions that may be encountered in the Design‐Builder’s final design. 

    NYSDOT  has  performed  subsurface  investigations  in  the  vicinity  of  the  proposed  station building. Boring logs and laboratory test data from these previous subsurface investigations are provided  in Part 7 – Project Data.   The soil and  rock samples obtained during  these previous subsurface  investigations  are  available  for  inspection  by  the Design‐Builder  at  request.    The Design‐Builder shall be responsible for making any arrangements to view the samples from the previous subsurface  investigations, by  first seeking  the prior consent of  the NYSDOT’s Project Manager.    Information from these previous subsurface  investigations shall be considered part 

  • New York State Department of Transportation 

    Rochester Station Project Part 3‐17 

    Part 3 Project RequirementsJune 14, 2013

     

     

    of the Contract Documents only to the extent that they are used to represent soil conditions at the depths indicated within the respective borings drilled at the approximate locations shown.  Presentation of this  information  in no way  implies that subsurface conditions are the same at other locations and different times.  The Design‐Builder shall form its own interpretation of the existing geotechnical data and  satisfy  itself as  to  the nature and behavior of  the ground and sub‐soil, the  form and nature of the Site, and nature of the Work that may affect  its detailed design, construction method, and tools. 

    6.1  Standards and References 

    The  Design‐Builder  shall  perform  geotechnical  activities  in  accordance  with  the  Contract Requirements, the applicable Standards, Codes and Manuals. 

    AMTRAK 

    AMTRAK Station Program and Planning, Standards and Guidelines, Station Manual 2.2 

    AREMA – American Railway Engineering and Maintenance of Way Association 

    AREMA Manual for Railway Engineering 

    NYSDOT 

    A. Access Management Requirements B. Annual Report titled "Axle Factor Update" C. Approved Materials List D. Highway Design Manual – Chapters 20 and 21 (CADD Standards and Procedures) E. Comprehensive Pavement Design Manual F. Consultant Instructions G. Design Consultant Manual H. Engineering Bulletins I. Engineering Instructions and Directives J. Environmental Procedures Manual (EPM) / The Environmental Manual (TEM) K. General Design and Construction Requirements for Occupancies L. Geotechnical Engineering Bureau Manuals and Publications  M. GCP‐17, Procedure for the Control of Granular Materials N. Land Surveying Standards and Procedures Manual O. Manual for Uniform Record Keeping P. Materials Bureau  ‐ Applicable Sampling and Testing Manuals,  Inspection Manuals, and 

    Materials Methods. Q. New York State Supplement to the Manual on Uniform Traffic Control Devices R. Prestressed Concrete Construction Manual  S. Project Development Manual T. Reference Marker Manual U. Rules  and  Regulations  Governing  the  Accommodation  of  Utilities  within  the  State 

    Highway Right of Way V. Special Specifications 

  • New York State Department of Transportation 

    Rochester Station Project Part 3‐18 

    Part 3 Project RequirementsJune 14, 2013

     

     

    W. Standard Sheets  X. Standard Specifications for Construction and Materials Y. Steel Construction Manual (SCM) Z. U.S. Customary Standard Sheets AA. Work Zone Traffic Control Manual 

    The above  is a partial  listing of applicable NYSDOT Engineering Manuals and Guidelines. The Design Builder  shall perform  the Work  in  conformance with  all  current NYSDOT  Engineering Manuals and Guidelines. 

    6.2  Design Requirements 

    The Design‐Builder shall at a minimum provide the following:  

    A. Geotechnical Work Plan   B. Geotechnical investigation plan  C. Geotechnical data report   D. Subsurface investigation records  E. Seismic assessment report  F. Geotechnical instrumentation and construction monitoring plans  G. Foundation design reports   

    6.3  Geotechnical Work Plan 

    The  Design‐Builder  shall  prepare  a  geotechnical  work  plan  for  the  project.  The  plan  shall identify the required geotechnical scope of work that the Design‐Builder plans to complete for the  design  and  construction  of  the  Project.  The  geotechnical  work  plan  shall  include  the following: 

    A. Design‐Builder’s knowledge and understanding of the geotechnical, geologic, hydrogeology and seismic settings of the Project Site and how the nature and behavior of the soil, rock, groundwater and subsurface conditions will affect the investigation, design and methods of construction;  

    B. Anticipated methods of analysis and design for the foundation of the station building, high‐level platform  and  cut‐and‐cover  tunnel  and  a discussion  of  the  foundation optimization process and rationale for selection of the foundation types;  

    C. Identify  key  Project  constraints  and  describe  how  the  geotechnical  activities  will  be designed and constructed to meet these constraints;  

    D. Identification of all principal geotechnical deliverables and activities;  

    E. A narrative describing the approach to quality control during design and construction of the geotechnical Works;  

    F. A  risk  register  identifying  all  major  design  and  construction  risks  of  the  geotechnical activities, and describe how these risks are managed and mitigated;  

  • New York State Department of Transportation 

    Rochester Station Project Part 3‐19 

    Part 3 Project RequirementsJune 14, 2013

     

     

    G. Resumes  of  the  Foundations  Lead Designer, Geotechnical  Instrumentation  Engineer,  and Seismic Specialist;  

    H. Minimum  numbers,  depths,  types  of  subsurface  investigations  to  be  carried  out  for  the station building, high‐level platform and the tunnel design,  including a narrative of the  in‐situ tests and laboratory tests to be carried out;  

    I. Minimum  numbers,  and  types  of  axial  load  tests  for  each  foundation  type,  size  and subsurface condition;  

    J. Minimum numbers, and types of lateral load tests for each foundation type and subsurface condition;  

    K. Minimum  percentage  and/or  numbers  of  driven  piles  as  tested  piles  to  be  dynamically tested;  

    L. Crosshole  sonic  logging  shall  be  done  on  all  drilled  shafts  according  to  NYSDOT specifications.    Thermal  integrity  profiling  shall  be  done  on  all  demonstration  shafts,  in addition  to  the  first  three production  shaft of each diameter  size. Thermal  integrity data shall  be  collected  continuously  and  remotely  through  embedded  sensors.    Location  of embedded sensors arrays shall be assumed similar to Crosshole sonic locations. 

    6.4  Geotechnical Subsurface Investigation Plan 

    The Design‐Builder shall prepare a geotechnical  investigation plan,  including specifications  for performing the Work. The geotechnical investigation plan shall include the criteria or rationale used  in developing the plan, and shall  identify the  locations of all field  investigation sites, and borings, together with their depths, sampling intervals, and a description of both the field and laboratory testing programs utilized. The geotechnical investigation plan shall be prepared and signed and  sealed by  the Design‐Builder’s  Lead Designer. The geotechnical  investigation plan shall  include details of borehole abandonment procedures and a  list of all permits required to perform the geotechnical investigation. 

    The Design‐Builder  shall  plan  and  conduct  subsurface  investigations  in  accordance with  the NYSDOT’s  Standards  for  subsurface  exploration  programs,  and  as  deemed  necessary  by  the Design‐Builder’s  Lead  Designer  to  establish  the  geotechnical  conditions  and  to  perform  all geotechnical and foundation design and analysis. 

    The Design‐Builder  shall determine  the  coordinate  location and ground  surface elevation  for each boring and field investigation position, and shall show the coordinates, station and offset, and elevation for each individual boring log or investigation record. Coordinates and station and offsets for the borings shall be referenced to Amtrak Mile Post 371.0 stationing. Elevations shall be  referenced  to  the  Project  datum  and  horizontal  control  system.  Boring  horizontal coordinates shall be accurate  to +/‐ 1.0  foot; vertical coordinates shall be accurate  to +/‐ 0.5 foot. 

  • New York State Department of Transportation 

    Rochester Station Project Part 3‐20 

    Part 3 Project RequirementsJune 14, 2013

     

     

    6.5  Geotechnical Data Report 

    The  Design‐Builder  shall  prepare  a  geotechnical  data  report,  signed  and  sealed  by  the Foundations Lead Designer.   The geotechnical data report shall serve as a factual depiction of the subsurface conditions and at a minimum it shall include:  

    a. A detailed description of the investigation methods;  b. Complete  records  (typed  logs  using  NYSDOT  log  format)  with  summary  tables  of 

    investigation;   

    c. Complete records with summary tables of laboratory test results;   d. Exploratory  hole  location  plan,  showing  locations  of  any  existing  (pre‐award) 

    exploratory holes for which data was used by the Design‐Builder plus locations of post‐award  exploratory  hole  locations  undertaken  by  the  Design‐Builder;  and  Plots  of laboratory test results versus elevations for separate areas and soil types. 

    6.6  Subsurface Investigation Records 

    The  Design‐Builder  shall  be  responsible  for  keeping  a  continuous  and  accurate  log  of  the materials  encountered  and  a  complete  record  of  the  operation  of  progressing  the  casing. Where  driving  is  used,  a  record  of  the  number  of  blows  required  to  advance  the  sampling barrel, each 6 inches in the soil where each sample is taken, shall be kept. Records shall be kept using the NYSDOT Subsurface Exploration Log Form (US Units). 

    The  Design‐Builder  shall  use  Bentley  gINT®  or  similar  commercial  software  to  develop  and maintain an electronic database of subsurface information including in‐situ test and laboratory test results, and to produce boring records. 

    6.7  Seismic Assessment Report 

    Prior  to  issue  to  the  NYSDOT,  the  Design‐Builder  shall  ensure  that  the  seismic  assessment report  is  peer‐reviewed  by  a  suitably  qualified  specialist  in  this  field,  and  the  findings  and conclusions  of  the  peer  review  shall  be  included  in  an  appendix  to  the  Seismic Assessment Report.    The  seismic  specialist  who  will  perform  the  review  of  this  report  shall meet  the minimum requirements specified in General Instructions to Proposers. 

    A. Seismic Site Response Analyses ‐ Site‐specific seismic response analysis shall be performed to  develop  design  free‐field  response  spectra  in  accordance  with  AREMA  and  Amtrak Guidelines.    The Design‐Builder  shall develop dynamic  soil/rock properties  for use  in  the seismic  analysis  based  on  PS‐Logging  data  as well  as widely‐used  empirical  correlations.  Spatial variation of ground motions shall be accounted for, as applicable. 

    B. Soil Structure Interaction ‐ Seismic soil structure interaction evaluation of deep foundations shall  include  determination  of  the  maximum  imposed  curvatures  and  bending  from earthquake  ground  motions  and  structure  response,  including  free‐field  soil  strains modified  for  soil‐foundation‐structure  interaction  coupled  with  deep  foundation 

  • New York State Department of Transportation 

    Rochester Station Project Part 3‐21 

    Part 3 Project RequirementsJune 14, 2013

     

     

    deformations associated with earthquake loads imparted to the foundation by the structure (i.e. inertial response). 

    C. Liquefaction ‐ Evaluation of liquefaction potential shall be performed.  Should this show that liquefaction is a potential hazard at the Site, the risk potential on the station building, high‐level platform and the tunnel shall be evaluated by the Design Builder, and any remediation solutions  proposed  by  the  Design‐Builder  shall  be  demonstrated  by  analytical  and  field methods.  

    6.8  Geotechnical Instrumentation and Construction Monitoring Plan 

    A. Monitoring  of  Existing  Structures  and  Utilities  ‐  The  Design‐Builder  shall  develop, implement, and maintain a geotechnical instrumentation and construction monitoring plan to  monitor  vibrations,  accelerations,  vertical  settlement,  and  lateral  movement  of temporary  support  structures  and  adjacent  ground,  and  existing  infrastructure  during construction including the existing station building, utilities and other infrastructures within the zone of influence of construction.  

    B. Wherever  vibration‐producing  activities  could  affect  a  structure,  building,  or  utility,  the Design‐Builder  shall  prepare  a  Vibration  Monitoring  and  Control  Plan  to  address  the potential  impacts  to  nearby  receptors  due  to  construction  or  demolition  activities associated with  this Project.   The  term  “receptor”  includes buildings,  structures, utilities, and  sensitive  operations/processes  for  which  construction  impacts  or  Work  above recommended  limits  may  be  detrimental.    The  plan  shall  include  ground  and  air‐blast vibration threshold limits. The monitoring plan shall address how the Design‐Builder intends to complete vibration‐related activities and meet the following minimum requirements: 

    1. Develop  a  list  of  all  anticipated  vibration  producing  activities  and  where  they  are expected to occur; 

    2. Develop a list of all potentially impacted receptors from these activities; 

    3. Provide a vibration  susceptibility analysis  for each  identified  receptor, and establish a vibration control  limit to preclude damage,  including threshold damage, to each of the identified receptors.  

    4. Provide a plan for notifying the public of potential vibration impacts, responsible Project personnel, receptors requiring precondition surveys, and vibration monitoring activities; 

    5. Monitor construction related vibrations at the nearest and most critical receptor(s), and notify  appropriate  project  personnel  immediately  if  established  vibration  limits  are exceeded; 

    6. Provide  instrumentation  locations,  monitoring  procedures,  and  a  description  of  the monitoring devices and/or manufacturers’ brochures in the submitted plan; 

    7. Assess  any  sensitive  community  or  business  operations  that  may  be  affected  by vibrations; 

  • New York State Department of Transportation 

    Rochester Station Project Part 3‐22 

    Part 3 Project RequirementsJune 14, 2013

     

     

    8. Provide  recommendations  for  vibration‐limiting  methods  to  meet  the  established maximum safe vibration levels.  

    9. List of receptors shall include, but not limited to: 

    • Utilities 

    • Nearby bridges 

    • Buildings 

    • Newly constructed elements 

    • Existing  structures  within  zone  of  influence    of  vibration  producing activities 

    C. Construction Monitoring  ‐ The Design‐Builder’s construction monitoring plan  shall  include details of the proposed program of instrumentation and monitoring, monitoring frequency, assesses the impacts to existing structures and utilities, establishes threshold values of the monitored  parameters,  and  describes  the  response  plan  that will  be  implemented when threshold  parameters  are  exceeded.    A  system  of  construction  monitoring  shall  be established to include the following: 

    1. Measurement of ground water levels and ground water pressure. 

    2. Monitoring of settlement of the permanent structures and surrounding area both during and  after  construction.    In  all  cases, monitoring  shall  be  initiated well  in  advance  of construction to establish baseline readings. 

    3. Measurement of lateral movement of permanent structures. 

    4. Measurement  of  vibration  levels  of  the  permanent  structures  and  surrounding  area both during and after construction.   Ambient vibration monitoring shall be conducted well in advance of construction to establish baseline readings. 

    D. The  extent  of  the monitoring  program will  depend  on  the  size  and  type  of  the  affected structures.  A detailed monitoring program shall be prepared for each structure affected by the work, subject to review by NYSDOT. 

    E. Where  adjacent  properties may  be  affected  by  the works,  the monitoring  program  shall allow for readings on fixed points on the structures and buildings, to allow both total and differential  settlements  to  be  assessed  and  lateral movements  to  be  determined.    The monitoring program shall also allow for access to conduct vibration monitoring on adjacent properties. 

    F. Potential Instrumentation 

    The instrumentation and monitoring program shall include appropriate types and quantities of monitoring  instruments capable of measuring horizontal and vertical movements, tilt of adjacent  structures,  soil  pore  pressures,  vibrations,  and  noise,  as  applicable.  Instrumentation  to be used  in  the monitoring programs  to  control  and  assist design  and construction could include: 

  • New York State Department of Transportation 

    Rochester Station Project Part 3‐23 

    Part 3 Project RequirementsJune 14, 2013

     

     

    1. Piezometers and observation wells 2. Inclinometers 3. Survey stations on structures and at ground level locations 4. Tiltmeters 5. Deep settlement points and extensometers 6. Strain and load‐measuring devices 7. Seismographs, geophones, and others. 

    The types and numbers of  instruments will depend on factors  including the size, type and location  of  proposed  work.    The  design  and  distribution  of  instrumentation  shall demonstrate  an  understanding  of  the  need,  purpose  and  advantages  of  using  each proposed  type.  Responsibilities  for  design,  procurement,  installation,  recording, maintenance and protection, and monitoring plan, criteria and performance requirements shall  be  clearly  stated  in  the  specifications  and  Contract  Documents.    These  shall  also contain  the�