Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Rochester Station Project
DH34463
DB CONTRACT DOCUMENTS
PART 3
PROJECT REQUIREMENTS
DRAFT
New York State Department of Transportation
This page is intentionally blank.
New York State Department of Transportation
SECTON 1. RAILROAD PROPERTY ACCESS REQUIREMENTS .................................................................... 1 1.1 Access Requirements onto Amtrak Property .................................................................................... 1 1.2 Access Requirements for CSX Property ............................................................................................ 1 SECTION 2 ENVIRONMENTAL COMPLIANCE ........................................................................................... 1 2.1 Scope ................................................................................................................................................. 1 2.2 Compliance with Approved NEPA Action ......................................................................................... 2 2.3 Environmental Requirements ........................................................................................................... 2 SECTION 3. COMMUNITY OUTREACH REQUIREMENTS ........................................................................... 5 SECTION 4 BASIS OF PAYMENT REQUIREMENTS .................................................................................... 6 4.1 CPM Schedule Submittals ................................................................................................................. 7 4.2 Milestones for Item 800.0600012 Design Build Construction Work ................................................ 8 4.3 Milestone Progress Payments ........................................................................................................... 8 4.4 CPM Schedule Requirements ............................................................................................................ 9 4.5 CPM Schedule Updates and Revisions ............................................................................................ 10 4.6 Extra Work ...................................................................................................................................... 11 4.7 Four Week Look Ahead Schedule ................................................................................................... 11 SECTON 5. SITE REQUIREMENTS ........................................................................................................... 12 5.1 General Site Requirements ............................................................................................................. 12 5.2 Codes and Standards ...................................................................................................................... 13 5.3 Foundation ...................................................................................................................................... 13 5.4 Structures ........................................................................................................................................ 13 5.5 Utilities ............................................................................................................................................ 14 5.6 Design Loading and Loading Combinations .................................................................................... 14 5.7 Materials ......................................................................................................................................... 14 5.8 Site Layout and Circulation ............................................................................................................. 14 5.9 Other Site Components................................................................................................................... 16 SECTION 6. GEOTECHNICAL REQUIREMENTS ........................................................................................ 16 6.1 Standards and References .............................................................................................................. 17 6.2 Design Requirements ...................................................................................................................... 18 6.3 Geotechnical Work Plan .................................................................................................................. 18 6.4 Geotechnical Subsurface Investigation Plan ................................................................................... 19 6.5 Geotechnical Data Report ............................................................................................................... 20 6.6 Subsurface Investigation Records ................................................................................................... 20 6.7 Seismic Assessment Report ............................................................................................................ 20 6.8 Geotechnical Instrumentation and Construction Monitoring Plan ................................................ 21 6.9 Foundation Design Report .............................................................................................................. 23 SECTION 7. TEMPORARY FACILITY REQUIREMENTS .............................................................................. 24 SECTION 8. TRACK AND PLATFORM REQUIREMENTS ............................................................................ 26 SECTION 9 ARCHITECTURAL REQUIREMENTS ....................................................................................... 26 9.1 Code Requirements and Design Standards ..................................................................................... 26 9.2 Description of Proposed Facility ..................................................................................................... 27 9.3 Façade Elements ............................................................................................................................. 28 9.4 Station Ground Level....................................................................................................................... 28 9.5 Station Concourse Level .................................................................................................................. 32 9.6 Space Allocation .............................................................................................................................. 32 9.7 Information Systems ....................................................................................................................... 38 9.8 Finishes and Materials .................................................................................................................... 39 9.9 Public Art Installations .................................................................................................................... 40
New York State Department of Transportation
9.10 Historic Canopy and SHPO Coordination ........................................................................................ 40 SECTION 10. VERTICAL CIRCULATION REQUIREMENTS ........................................................................... 40 10.1 Pedestrian Concourse ..................................................................................................................... 41 10.2 Baggage Ramps ............................................................................................................................... 41 SECTION 11. SUSTAINABILITY REQUIREMENTS ....................................................................................... 42 11.1 Sustainable Strategies ..................................................................................................................... 42 11.2 Energy Consumption ....................................................................................................................... 44 11.3 Life Cycle Analysis ........................................................................................................................... 44 11.4 Material Selection ........................................................................................................................... 44 11.5 Commissioning ................................................................................................................................ 45 11.6 Documentation ............................................................................................................................... 45 SECTION 12. MECHANICAL REQUIREMENTS ........................................................................................... 47 12.1 General ............................................................................................................................................ 47 12.2 Codes and Standards ...................................................................................................................... 47 12.3 Vibration Isolation / Seismic Design ............................................................................................... 48 12.4 Mechanical Identification ............................................................................................................... 48 12.5 HVAC SYSTEMS ................................................................................................................................ 48 12.6 PLUMBING SYSTEMS ....................................................................................................................... 53 12.7 Fire Protection ................................................................................................................................ 58 SECTION 13. ELECTRICAL REQUIREMENTS ............................................................................................... 60 13.1 General Requirements .................................................................................................................... 60 13.2 Codes and Standards ...................................................................................................................... 62 13.3 Area Types ....................................................................................................................................... 63 13.4 Maintenance requirements ............................................................................................................ 64 13.5 Mounting of equipment .................................................................................................................. 65 13.6 Electrical Service: ............................................................................................................................ 67 13.7 Generator Service and Power Distribution ..................................................................................... 78 13.8 Lighting ............................................................................................................................................ 80 13.9 Receptacles ..................................................................................................................................... 84 SECTION 14. COMMUNICATIONS REQUIREMENTS ................................................................................. 98 14.1 Facility Requirements ..................................................................................................................... 98 14.2 General Requirements .................................................................................................................. 111 SECTION 15 INSTRUMENTATION AND CONTROLS REQUIREMENTS ................................................... 112 15.1 Building Management System (BMS) (DfE) .................................................................................. 112 SECTION 16. FACILITY PARKING AND TRAFFIC REQUIREMENTS ............................................................... 114 16.1 Parking .............................................................................................................................. 114 16.2 Pay Stations ................................................................................................................................... 114 16.3 Bus Access ..................................................................................................................................... 114 16.4 Accommodations for Bicylists ....................................................................................................... 115
New York State Department of Transportation
Rochester Station Project Part 3‐1
Part 3 Project RequirementsJune 14, 2013
SECTON 1. RAILROAD PROPERTY ACCESS REQUIREMENTS
The Design Builder must adhere to the railroad property access requirements while working on property under the control of either Amtrak or CSX.
1.1 Access Requirements onto Amtrak Property
A. The Design Builder is required to obtain a Temporary Permit to Enter (TPE) from Amtrak. B. All field personnel must attend Amtrak contractor safety/security training
a. Available Online: http://www.amtrakcontractor.com C. The Design Builder is required to submit an overall Site Specific Work Plan and Hazard Analysis
(SSWP/Hazard) Form to Amtrak Engineering for review and approval.
D. Temporary fencing and barricades of work zones is required. All fencing must be approved by Amtrak.
E. Station operations and areas must remain open for its normal operations. Temporary station operations staging shall be reviewed and approved by Amtrak.
F. Mandatory Personal Protective Equipment (PPE) for all workers worn at all times including: a. Hard Hat, High visibility Orange Safety Vest with reflective striping (vest must be break‐
away), Safety Glasses or goggles, Work boots, Hearing protection and Visible Safety Trained ID card.
G. The Design Builder shall provide to Amtrak Engineering the following: a. 2 week minimum look ahead schedule of planned work activities, updated weekly. b. Specific work plans for safe operations prior to work activities being progressed. c. The Design Builder shall create perform a written daily Job Safety Briefing with all crafts,
workers, and anyone involved on the project prior to any work beginning the briefing shall include all tasks and be updated as major changes in work occur, the briefing shall be performed by the Employee in charge who shall keep the briefing in his/her possession and presented to Amtrak or FRA officials if requested.
H. Amtrak Engineering will provide Station Operation Coordination and Inspection services as it relates to Amtrak’s interests.
1.2 Access Requirements for CSX Property
A. CSX Railroad is responsible for all flagging operations and separate coordination with CSX is required.
B. All field personnel must attend CSX contractor safety/security training, which is different from the Amtrak training.
SECTION 2 ENVIRONMENTAL COMPLIANCE
2.1 Scope
An essential component of the Project is the comprehensive integration of environmental compliance into all design and construction activities by the Design‐Builder. Except as otherwise detailed herein, the Design‐Builder shall be responsible for preparing its design, carrying out its
New York State Department of Transportation
Rochester Station Project Part 3‐2
Part 3 Project RequirementsJune 14, 2013
construction activities and undertaking other activities as needed to ensure compliance with the Project’s Environmental documentation and all applicable environmental laws and regulations. This Project Requirement identifies certain required actions by the Design‐Builder to ensure that the Environmental Requirements are complied with throughout the Project activities.
2.2 Compliance with Approved NEPA Action
NEPA environmental approval for the subject project has been granted based on analysis and documentation of potential environmental impacts of the identified preferred alternative. This analysis is summarized along with any identified environmental commitments and depicted in the May 2013 Federal Railroad Administration (FRA) Categorical Exclusion Worksheet for the subject project. If during detailed design and/or construction the Design‐Builder introduces design elements, variations, or methodologies that potentially induce environmental impacts that differ from those identified in the approved Categorical Exclusion Worksheet or is unable to comply with established environmental commitments then the NEPA process for this project will need to be re‐evaluated by the Design‐Builder and reviewed by the Department prior to proceeding with construction. This requirement also applies to proposed variations which may affect resources covered under Section 106, Section 4(f), and other applicable federal and state environmental regulations. The need to re‐evaluate the NEPA process may impact the overall project schedule.
2.3 Environmental Requirements
2.3.1 General
A) Unless otherwise indicated in the Contract Documents, the Department will be responsible for obtaining all Environmental Approvals as identified in this Section. In the event the Design‐Builder requests changes to the permits obtained by the Department, the Design‐ Builder shall be responsible for the preparation of all information including materials, investigations, testing and documentation, as necessary to support said permit modification request. Based on the Design‐Builder’s provision of said information, the Department will undertake the requested permit modification with the respective permitting agencies on the Design‐Builder’s behalf. The Department will not be responsible for any delay or additional cost associated with the Design‐Builder’s requested permit modification;
B) The Design‐Builder shall procure all Environmental Approvals as needed for all Design‐ Builder located areas, including staging, borrow and disposal sites, and any other areas used by the Design‐Builder, for its convenience, in the construction of the Project;
C) The Design‐Builder shall be responsible for obtaining all new Environmental Approvals. For any such approvals required to be obtained by the Design‐Builder that must formally be issued in the Department's name, the Department will cooperate with the Design‐Builder as reasonably requested by the Design‐Builder, including execution and delivery of appropriate applications and other documentation prepared by Design‐Builder in a format approved by the Department;
D) The Design‐Builder shall be solely responsible for violations of any Environmental Requirements;
New York State Department of Transportation
Rochester Station Project Part 3‐3
Part 3 Project RequirementsJune 14, 2013
E) The Design‐Builder shall indemnify the Department and the State of New York for any fines, violations or damages incurred by reason of failure of the Design‐Builder to comply with Environmental Approvals.
2.3.2 Environmental Plans
The Design‐Builder shall be responsible for preparing the following documents in conformity with all Environmental applicable standards, regulations, permits and requirements. For each documents listed, the Design‐Builder shall identify the frequency of submission of compliance reports to the Department.
A) Health and safety plan (HASP);
B) Soil Erosion and Sediment Control Plan complying with the New York State SPDES General Permit for Stormwater Discharges from Construction Activities (GP‐0‐10‐001) This plan is to include but is not limited construction entrance(s), construction phasing, drawings showing size and location of permanent (seeding, pavement) and temporary (silt fence, temporary seed) erosion controls, and details.
C) Stormwater pollution prevention plan (SWPPP)
D) Contaminated Soil Sampling and Analysis Plan (for areas of excavation in the railroad bed)
E) Based on the results of the Contaminated Soil Sampling and Analysis Plan the following plans may be required (see NYSDOT Standard Specification Section 205):
• Contaminated Material Handling Plan (CMHP)
• Field Organic Vapor Monitoring Plan (FOVMP)
• Disposal Plan
2.3.3 Environmental Plan Deliverables
At a minimum, the deliverables shall include the items listed in Table 2‐1 – Environmental Compliance Deliverables, for the Department’s review. Each of the deliverables listed in Table 2‐1 ‐ Environmental Compliance Deliverables, shall be provided to the Department by the earlier of: (i) 30 days after NTP; and (ii) 30 days prior to the relevant on site activity, including start of construction.
New York State Department of Transportation
Rochester Station Project Part 3‐4
Part 3 Project RequirementsJune 14, 2013
Table 2‐1 – Environmental Compliance Deliverables
Deliverable Number of Copies Reference Section
Hardcopy Electronic
Health and safety plan 1 1 10.4.2
Stormwater pollution prevention plan & NOI 1 1 10.4.2
Soil Erosion and Sediment Control Plan 1 1 10.4.2
Contaminated Soil Sampling and Analysis Plan 1 1 10.4.2
2.3.4 Soil Erosion and Sediment Control
The Design‐Builder shall provide the department with a SWPPP and Notice of Intent complying with the New York State SPDES General Permit for Stormwater Discharges from Construction Activities (GP‐0‐10‐001) 60 days prior to any ground disturbance for the Department’s signature. The Department will apply for coverage under the SPDES General Permit for Stormwater Discharges from Construction Activities. The Design‐Builder shall review final SWPPP and sign/complete Contractor/Subcontractor SPDES Permit Certification form (CONR 5). Discharges covered under the SPDES general permit shall not commence until the date authorized on the SPDES Acknowledgement Letter.
2.3.5 Performance
The Design‐Builder shall perform of all activities required under each of the foregoing plans until final acceptance of the Project, except to the extent that the plans provide for activities to be undertaken by the Department or third parties. Provisions in said plans for activities to be undertaken by the Department or third parties are subject to prior written approval by the Department.
2.3.6 Environmental Approvals and Identified Permits
All environmental design approvals for this project shall be acquired prior to construction. The following is an initial list of permits that have been identified as necessary for this project:
A) SPDES General Permit for Stormwater Discharges from Construction Activities
B) NYSDEC Waste transporter permit.
The Design Builder is responsible for identifying and acquiring all necessary permits required to complete the proposed Work.
New York State Department of Transportation
Rochester Station Project Part 3‐5
Part 3 Project RequirementsJune 14, 2013
2.3.7 Asbestos Containing Materials (ACMs)
Based on laboratory analyses of bulk samples collected, ACMs are present in the existing Station.
2.3.8 Inaccessible/Assumed ACMs
Inaccessible/Assumed ACMs were found within the former passenger tunnel as ceiling plaster, 9” x 9” floor tile and mastic and thermal pipe insulation. Refer to ”Hazardous Materials Investigations” found on the project website: https://www.dot.ny.gov/main/business‐center/designbuildproject for a list of inspections and samplings performed to determine the presence of asbestos‐containing materials (ACM). The Design‐Builder shall be responsible for the identification, removal and disposal of all asbestos containing materials (ACMs) encountered in the inaccessible areas if such areas will be disturbed during the performance of the Work. The removal and disposal of ACMs shall be performed in accordance with the Contract Documents and the applicable safety and health codes.
The Design‐Builder shall be responsible for providing any necessary asbestos inspection, project design and abatement project/air monitoring services as part of this contract in accordance with 12 NYCRR 56. NYSDOL asbestos licensure and applicable staff certification(s) are required for structure rehabilitation work where confirmed or presumed asbestos‐containing materials are impacted. All necessary asbestos inspection, project design and project/air monitoring work shall be conducted in conformance with policy and guidance provided in NYSDOT TEM Section 4.4.19 ‐ Asbestos Management.
2.3.9 Hazardous Waste/Contaminated Soils
A Contaminated Soil Sampling and Analysis plan shall be completed for all proposed excavation areas within the railroad bed. The Design‐Builder shall be responsible for the identification, removal and disposal of all hazardous waste or contaminated soil encountered. The removal and disposal of Hazardous Waste or Contaminated soils shall be performed in accordance with the Contract Documents and the applicable regulations.
A Contaminated Soil Sampling and Analysis plan for the station area has been completed. Refer to ”Hazardous Materials Investigations” found on the project website:
https://www.dot.ny.gov/main/business‐center/DesignBuildProject
SECTION 3. COMMUNITY OUTREACH REQUIREMENTS
Outreach has been and will be critical to obtain the full support of all project stakeholders and the community. The Design‐Builder shall provide support to the Department inclusive of, but not limited to, the following groups.
A. Rochester Station Executive Steering Committee
New York State Department of Transportation
Rochester Station Project Part 3‐6
Part 3 Project RequirementsJune 14, 2013
NYSDOT has formed an Executive Steering Committee to guide the design of Rochester Station as it progresses. Mayor Tom Richards of the City of Rochester, United States Congresswoman Louise Slaughter, and Commissioner Joan McDonald of the New York State Department of Transportation comprise the Committee, along with technical advisory from representatives of Amtrak, Trailways of New York, and Parsons Brinckerhoff. The Design‐Builder shall aide NYSDOT to keep the Committee up to date on the development of the design by making presentations to the Committee. The Design‐Builder shall respond to comments and incorporate input and guidance from Committee members.
B. Council for Persons with Disabilities The Council for Persons with Disabilities is an advisory council to the County Executive of Monroe County and to the Mayor of the City of Rochester. The Council has provided input and guidance developing a preliminary design that fulfills the needs of persons with disabilities in Rochester and Monroe County as they utilize Rochester Station. The Design‐Builder shall be required to meet with and present to the Council as the design progresses.
C. Rochester Cycling Alliance The Rochester Cycling Alliance is a cycling advocacy group focused on promoting cycling in Rochester, development of cycling roads and trails, and distributing information about safety and cycling in general. The Design‐Builder shall assist the Department as needed in presenting the final design to the Rochester Cycling Alliance for their input.
D. Reconnect Rochester Reconnect Rochester is a transit advocacy group focused on promoting mobility and physical connections between downtown Rochester and the surrounding neighborhoods. The Design‐Builder shall assist the Department as needed in presenting the final design to Reconnect Rochester for their input.
E. Other Groups The Design‐Builder shall provide support to the Department and the Executive Steering Committee to meet with community groups such as:
a. Area universities, b. RGRTA, c. High Falls Business Improvement District, d. Rochester Downtown Development Corporation e. Monroe County Department of Transportation f. Empire State Passenger Association
SECTION 4 BASIS OF PAYMENT REQUIREMENTS
New York State Department of Transportation
Rochester Station Project Part 3‐7
Part 3 Project RequirementsJune 14, 2013
The scheduling of submittals, procurement and construction is the responsibility of the Design Builder. Progress payments shall be subject to the requirements of DB §109‐2. All Work, including Phase II, if included in the contract, shall be monitored by a detailed Critical Path Method Schedule "CPM Schedule". The Design Builder shall submit the CPM Schedule to NYSDOT’s Project Manager for approval. The CPM Schedule shall meet the requirements of DB §108 and Part 2‐ Appendix 1. The approved CPM Schedule is used to assist NYSDOT in appraising the reasonableness of the proposed schedule, as well as, its compliance with Contract requirements. This approved CPM Schedule shall be the basis for the evaluation of Design Builder performance and approval of Progress Payments for Item 800.0600012 Design Build Construction Work. Progress Payments will be made according to the approved CPM schedule as each Milestone is completed to the satisfaction of NYSDOT’s Project Manager.
The CPM Schedule is the Design Builder's committed plan to complete all Work (including punch list items) within the allotted time. The CPM Schedule shall be based on and derived from detailed schedules used to monitor all Contract activities.
4.1 CPM Schedule Submittals A. Preliminary Schedule: No later than 14 calendar days after Notice to Proceed, the
Design Builder shall submit the Preliminary Schedule for NYSDOT review and approval of the Design Builder's planned activities during the first 90 calendar days. The Preliminary Schedule shall indicate the cost of activities and milestones expected to be completed or partially completed before submission and approval of the complete CPM Schedule.
B. CPM Baseline Schedule: No later than 30 calendar days after Award of Contract, the Design Builder shall submit CPM Schedule depicting the Design Builder's Work plan for the entire Contract. The Design Builder shall submit to the NYSDOT’s Project Manager for review and approval the following:
1. Logic Diagram: A detailed CPM Time‐Scaled Network Logic Diagram.
2. Cost Loaded CPM for Item 800.0600012 Design Build Construction Work. The Design Builder will create a proposed list of Milestones including Manadatory Milestones and the percentage of the total price bid for Item 800.0600012 Design Build Construction Work associated with each Milestone. The Design Builder may propose to include Milestones in addition to the mandatory Milestones. The Department will review the Design Builder’s proposed Milestones and Associated Progress Payments for reasonableness prior to approval. These approved Milestones and Associated Progress Payments for Item 800.0600012 Design Build Construction Work are the basis for the Design Builder’s Cost Loaded CPM Schedule. Any revisions and modifications to the approved CPM Schedule must be approved by NYSDOT’s Project Manager in writing.
3. Cost Report: A Cost Report generated from the cost loaded CPM Schedule is to be submitted 14 calendar days after approval of the Line Item Breakdown, in accordance with Paragraph F.(3).
New York State Department of Transportation
Rochester Station Project Part 3‐8
Part 3 Project RequirementsJune 14, 2013
4. Narrative: A written narrative explaining the schedule and the Design Builder's general approach for meeting interim and completion milestone dates.
4.2 Milestones for Item 800.0600012 Design Build Construction Work A. The Design Builder shall include the following mandatory Milestone and required
Completions in the CPM Schedule:
Activity ID
Activity Description Follows
Logic Tie Duration
Responsible Party
Progress Payment Structure
P0010 Submission of
Health and Safety Plan
FS 2 months from the Notice To
Proceed
Design Builder
Proposed by Design
Builder/Approved by NYSDOT
P0020
Temporary Facility, Site
Work, Demolition of the existing Building and
appurtenances.
P0001 FS Proposed by
Design Builder/Approved
by NYSDOT
P0030 Station Building P0002 FSP0040 Tunnel P0003 FSP0050 Station Platform P0004 FSP0060 Platform Tracks P0005 FS
P0070 Substantial Completion P0006 FS
32 months from Notice To Proceed
P0080
Project Completion, in accordance with DB 109‐11.3
P0007 FS
36 months from the Notice To
Proceed
B. The Design Builder’s Preliminary, Baseline, and Monthly Update schedules shall incorporate the mandatory Milestone Completion Dates. The Department’s approval of the Design Builder’s schedule(s), in part, will be subject to the Design Builder’s compliance with the Milestone Schedule.
C. Failure of the Design Builder to submit the CPM Preliminary, Baseline, Update Schedules and any required revisions thereto within the time limits stated, shall be sufficient cause to withhold approval of the Design Builder's invoices for progress payment(s) until such delinquent submittal is made and accepted by NYSDOT’s Project Manager.
4.3 Milestone Progress Payments
The Design Builder shall furnish a breakdown of the total price bid for Item 800.0600012 Design Build Construction Work by assigning dollar values to each milestone, which
New York State Department of Transportation
Rochester Station Project Part 3‐9
Part 3 Project RequirementsJune 14, 2013
cumulatively equals the total amount. Upon approval by the NYSDOT’s Project Manager, the percentages associated with each milestone shall be used in the Cost Report as a basis for determining progress payments. The Design Builder's overhead and profit shall be prorated through all activities.
4.4 CPM Schedule Requirements
A. The CPM Schedule shall include all of the Design Builder's submittals, procurement and construction work activities with sufficient detail such that all interfaces with all direct and related parties to the Work are shown.
1. The Work of the Design Builder, Subcontractors, Suppliers, CSX, Amtrak and all others that affect progress shall be shown and identified on the schedule by using Activity Codes.
2. Procurement activities shall be shown, including submittal and approval of shop drawings, fabrication and delivery of the material.
3. Interruption of service, delivery of NYSDOT/Amtrak/CSX‐furnished equipment, project phasing and any other Technical Provision requirements shall be shown.
B. The CPM Schedule shall contain sufficient construction activities to represent the Work, subject to the approval of the NYSDOT’s Project Manager.
C. The CPM Schedule shall be of the precedence type. Activity precedence relationships consistent with proper logic shall be shown with lag codes.
D. Logic and activity time durations shall be established by the Design Builder consistent with Contract requirements and reflective of proper coordination between trades. Logic shall show how the start of a given activity is dependent on the completion of preceding activities and its completion restricts the start of following activities. No activity shall have a duration greater than 30 calendar days.
E. The start date of the CPM Schedule shall be the Notice to Proceed. The completion date of the CPM Schedule shall be the Contract completion date as specified in Part 1 Design Build Agreement, which shall be input as the "Project Must Finish No Later Than" date. All intermediate milestones required in the Contract shall be shown in proper logical sequence and input as "Start‐No‐ Earlier‐Than" or "Finish‐No‐Later‐Than" dates. The Design Builder may add milestones with the approval of NYSDOT’s Project Manager.
F. Activities shall be described such that the Work is readily identifiable for assessment of start and completion, as well as intermediate status. Descriptions shall utilize Activity Codes for physical locations such as column lines, stations and elevations where possible to define the Work. Activity description of "start", "continue", "completion", "X%", "Y%", "Z%" or similar non‐specific descriptions will not be allowed.
G. The CPM Schedule shall be calculated in working days. The working day to calendar date correlation shall be based upon the Design Builder's proposed work week with adequate allowance for weekends, legal holidays and any special requirements of the Contract.
New York State Department of Transportation
Rochester Station Project Part 3‐10
Part 3 Project RequirementsJune 14, 2013
Durations for activities shall not be less than one work day. Multiple shifts per day should be shown using multiple resources.
H. Seasonal weather conditions shall be considered in the planning and scheduling of all Work influenced by high or low ambient temperatures for the completion of all Work within the allotted Contract time. Appropriate allowances shall be made for anticipated time losses, due to normal rain and snow conditions by statistically expanding the estimated time durations for weather sensitive activities. Additionally, allowance for lower productivity during bad weather periods shall be made by increasing activity durations by an appropriate amount. All allowances for anticipated time losses shall be stated in the baseline narrative.
I. The review period shown in the Schedule for submittals shall conform with review periods stated in the Approved Project Quality Control Plan.
J. Constraint dates are permitted only on Milestone activities, unless otherwise approved by NYSDOT’s Project Manager.
K. All activities with the exception of Work start and end nodes shall have predecessors and successors. The start of an activity shall have a start‐to‐ start or finish‐to‐start relationship with preceding activities. The completion of an activity shall have a finish‐to‐start or finish‐to‐finish relationship with a succeeding activity. Start‐to‐finish relationships are not acceptable.
L. CPM Schedules which have been resource leveled are permissible provided the effects of leveling are incorporated in the schedule using "Start‐no‐Earlier Than" date constraint.
4.5 CPM Schedule Updates and Revisions
A. The Design Builder shall update the CPM Schedule monthly, whether or not the NYSDOT’s Project Manager has accepted the schedule, to reflect actual construction progress. The update shall include the historical record of actual start and finish dates for activities in progress, or completed, percent complete based on a unit of measure and remaining duration based on the amount of work days required to complete the activity.
B. A monthly progress meeting shall be held. At this meeting, attended by the NYSDOT’s Project Manager, all progress during the calendar month shall be addressed and reviewed for incorporation into the schedule by the Design Builder. Within a period of 10 calendar days from the date of this progress meeting, the Design Builder shall submit the schedule update to the NYSDOT’s Project Manager with the agreed upon changes for approval. The approved updated CPM schedule shall be the basis for the progress payment.
C. A CPM Progress Narrative Report shall be submitted as part of the update analysis shall include, but not be limited to:
1. Description of cost and schedule status.
New York State Department of Transportation
Rochester Station Project Part 3‐11
Part 3 Project RequirementsJune 14, 2013
2. Discussion of current and anticipated delaying problem areas and their estimated impact.
3. Schedule slippage and/or progress along the critical path in terms of days ahead or behind the allowable dates, and if the Work is behind schedule, progress along other paths with negative float.
4. Logic changes and an explanation of the revisions. Revisions to activities not worked on during the period, including changes in duration, or revisions to activity relationships are to be considered logic revisions. Out‐of‐sequence activities are not acceptable and shall be corrected in logic revisions prior to submission to NYSDOT.
D. When, in the NYSDOT’s Project Manager's opinion, the CPM Schedule fails to reflect the Design Builder's actual plan and method of operation, or the Design Builder's completion date as indicated by the CPM is more than 1 month behind the Contract completion date, NYSDOT’s Project Manager may require the Design Builder to submit for review within 2 weeks, a revised CPM Schedule for completion of the remaining Work within the Contract completion date.
E. Bar Chart: The length of the bar shall equal the Baseline Schedule. Status shown should be based on the Update Schedules.
F. When it becomes apparent activities must be added to the CPM Schedule, they must be added in a method that completion dates of any succeeding baseline activities are not affected. All revisions must be submitted to NYSDOT’s Project Manager for approval before incorporation into the CPM Schedule.
4.6 Extra Work
To insure that the CPM Schedule shall continue to accurately reflect the Design Builder's plan for the Work and that it incorporates the impact of all Extra Work as soon as the Work scope can be defined, the following procedure shall be followed to incorporate Extra Work (including deletions of Work) in the Schedule.
When an Extra Work proposal is submitted by the Design Builder, the Design Builder must identify in a CPM‐type sketch, additional work required as a result of the proposal and its interrelationship to the CPM Schedule. This sketch shall show all activities, logic revisions, duration changes, and associated cost changes for performing the Work in question. Upon NYSDOT’s Project Manager's approval of the sketch, the Design Builder shall incorporate the revisions into the Baseline Schedule and the Monthly Cost Report at the next Schedule update. No additional compensation will be paid the Design Builder for preparing these revisions. Any request for Extension of Time must be verified by CPM Analysis and be in accordance with DB 108‐6 “EXTENSIONS OF CONTRACT TIME”.
4.7 Four Week Look Ahead Schedule
The Design Builder shall provide with the monthly schedule update, or more frequently if required by NYSDOT, a Four Week Look Ahead Schedule to be used for coordination of the
New York State Department of Transportation
Rochester Station Project Part 3‐12
Part 3 Project RequirementsJune 14, 2013
Design Builder’s work with Railroad operation, other work groups and at regular Progress Review Meetings.
This Four Week Look Ahead Schedule shall contain early start and early finish dates for all activities scheduled or planned for start and/or completion in the upcoming 4 week period. It shall include design, submittal, procurement and construction activities, as applicable.
SECTON 5. SITE REQUIREMENTS
5.1 General Site Requirements
A. Prior to construction activities, the Design Builder and Department representative shall identify existing site features to remain such as trees, landscape, walks, etc; and establish protection measures to for duration of project.
B. Develop phased erosion and sediment control plan meeting the guidelines of the New York Standards and Specifications for Erosion and Sediment Controls; maintain erosion and sediment controls through duration of construction. Provide stabilized entrances to prevent mud from leaving the site, regularly sweep and sprinkle water to avoid mud and dust concerns on local streets and neighboring properties.
C. Provide a Storm Water Pollution Prevention Plan (SWPPP) in accordance with NYSDEC Standards and Design Guidelines. SWPPP shall include temporary and permanent measures and will require review and approval by local MS4 officer and NYSDEC prior to construction. Install stormwater measures in accordance with approved SWPPP and Notice of Intent and Notice of Termination.
D. Existing features in the work area including buildings, walks, pavements, curbs, lighting and other site amenities should be demolished and disposed in accordance with City ordinances, obtain needed demolition permits. Coordinate utility disconnects with each utility provider. Clear site of trash, debris, vegetation, trees (other than those which can remain), and any materials not incorporated in the project design; dispose of in accordance with City ordinances.
E. Provide site security with a fence and lockable gates for all phases of construction. F. Provide safe, reliable ingress/egress, traffic circulation and pedestrian circulation for all
public use areas including temporary and permanent station and amenities through all phases of construction.
G. Provide parking lots and site roadways in accordance with Amtrak Standard Program and Planning Standards and Guidelines. Based on geotechnical report, provide a pavement design for parking areas in accordance with NYSDOT pavement design guidelines. For all pavements that will accommodate bus traffic upon completion of any phase, provide a heavy duty pavement design to accommodate the largest vehicles anticipated for use by the local and regional transportation providers.
New York State Department of Transportation
Rochester Station Project Part 3‐13
Part 3 Project RequirementsJune 14, 2013
H. Provide shelters and amenities to accommodate taxi, shuttle bus, local bus and regional transportation service in accordance with Amtrak Standard Program and Planning Standards and Guidelines.
I. Provide concrete walks and curbing in accordance with ADA Standards for Accessible design and Amtrak Standard Program and Planning Standards and Guidelines.
J. Provide bicycle parking Amtrak Standard Program and Planning Standards and Guidelines and City of Rochester Bicycle Master Plan.
K. Provide a detailed Landscaping Plan prepared by a professional landscape designer in accordance with Amtrak Standard Program and Planning Standards and Guidelines; install landscaping components in accordance with approved plan.
5.2 Codes and Standards
A. New York State Building Code 2010 B. ACI 318‐08 “Building Code Requirements for Structural Concrete and Commentary” C. ACI 530 Building Code Requirements for Buildings D. AISC Manual of Steel Construction E. ASCE 7‐10 Minimum Design Loads for Buildings and Other Structures
5.3 Foundation
A. Geotechnical report and available soil data will be given in an addendum as it becomes available.
B. Building foundation recommendation will be provided in the Geotechnical Report. The Design‐Builder may design the foundations using the existing building’s caissons. Information about the caissons will be available in the Geotechnical Report.
C. Tunnel and platform foundation and fill recommendations will be available in the Geotechnical Report.
5.4 Structures
A. Building structure shall be determined and designed by a NYS licensed Professional Engineer. Building structural system shall comply with all applicable codes and regulations even if not explicitly listed in this document.
B. Building structural system shall be designed to accommodate the architectural aesthetic as presented in these documents and optimize the space as described in the Amtrak Station Program and Planning – Standards and Guidelines.
New York State Department of Transportation
Rochester Station Project Part 3‐14
Part 3 Project RequirementsJune 14, 2013
5.5 Utilities
A. Provide utility service for temporary station. Facility to utilize electric heat. Temporary station to utilize overhead wiring, electric and communication service to permanent station to be underground.
B. Design Builder to provide the services of an underground utility locating service to find and map potential obstructions over entire site prior to construction.
C. Water service – Provide new water mains appropriately sized for: D. projected domestic use, E. Sprinklers in accordance with mechanical section, F. Site hydrants to provide protection in accordance with NYS Building Code. G. Fire protection main, domestic service main, backflow prevention and related facilities shall
meet Ten States Standards, City Water Department regulations and Monroe County/NYS Health Department regulations.
H. Provide and install new sanitary collection piping sized to accommodate all proposed facilities. Sanitary facilities shall meet Ten States Standards, City Sanitary Department regulations and Monroe County/NYS Health Department regulations.
I. Stormwater collection shall meet the SWPPP requirements identified in Site Design section. J. Coordinate and install private utilities (including but not limited to electric, gas, communications) in
accordance with the standards and guidelines of the utility provider and the City. K. Coordinate with Amtrak IT for power and conduit sizing/location for the temporary station and new
station. L. Coordinate with Trailway’s IT for power and conduit sizing/location for the new station.
5.6 Design Loading and Loading Combinations
A. All loads and load combinations shall be compliant and adhere to the New York State Building Code 2010 and ASCE 7‐10.
5.7 Materials
Refer to Part 8 – Project Specifications.
5.8 Site Layout and Circulation
The Rochester Station Project shall promote ease of transfer between transportation modes and circulation throughout its exterior site, but must also segregate different uses for safety reasons. Intercity and potential future city bus operations cannot share access or space with cars and shuttles. Drop off/pickup for passengers must be separated from general parking and shall share access with both short term parking and taxi/shuttle bus movements. The Design‐Builder shall ensure pedestrians are protected and separated from vehicular movements wherever possible.
New York State Department of Transportation
Rochester Station Project Part 3‐15
Part 3 Project RequirementsJune 14, 2013
It is desirable to promote a visual presence of the new station along the North Clinton frontage in order to create a visual connection with downtown Rochester along that street to the south. To ensure the shortest possible passenger travel distance, the station building should be sited as close as possible to the center line of tracks, while adhering to the twenty‐five foot minimum clearance from the centerline of the nearest track bed. The goal of a ‘seamless journey’ through the station building to the boarding area shall be achieved with this configuration. There are other mandates that shall impact the location of the station building and other site features including, but not limited to:
A. Replacement of the existing low‐level platform with an ADA compliant high level center island platform for passenger access to Amtrak service to Empire, Maple Leaf, and Lake Shore Corridors.
B. Minimize customer travel distance between station functions and the platform. C. Consolidation of traffic movements’ onto the Central Avenue frontage in Phase One to
eliminate sight distance conflicts at Joseph Avenue and North Clinton Avenue. D. Segregation of baggage and passenger traffic. E. Provision of ramps to accommodate baggage movements in lieu of elevators. F. The new station building must maintain a minimum of twenty‐five feet clear envelope
from the centerline of the southernmost track with additional 10’ setback recommended wherever possible to minimize flagging and lower construction costs for the building.
G. Provide ADA accessible path connecting all site and program elements. H. Provide a covered path to transport baggage from the Baggage Work Area to the exterior
baggage ramp and into the Concourse without exposing baggage to weather. I. Provide a covered path to transport baggage from the Concourse to the Platform without
exposing baggage to weather. J. Provide a covered area for passengers to board Trailways buses. Since wheelchair
boarding is at the very rear of the bus, the bus canopy extends to cover the entire length of the buses.
K. Install large skylight units in both the baggage and bus boarding canopies to allow natural light into these large shaded areas.
L. Allow for the installation of bicycle share facilities. M. Widen North Clinton and Joseph Avenues to provide street side bus stops for RGRTA bus
routes. Provide bus shelters at these layovers for waiting passengers. N. Provide queue space for taxis, university shuttle vans, and other paratransit services O. Allow for passenger drop off and pick up at the Station entry, and provide short‐term
parking near the Station entry.
The site layout shall incorporate softscape wherever possible, eliminating any unnecessary paving in accordance with the City of Rochester’s Project Green policy, especially at the North Clinton Avenue frontage. North Clinton has been identified by the City as one of the proposed “Green Corridors” that shall feature integrated bicycle and pedestrian circulation. The landscape shall include trees along the street line and along pedestrian paths to create an urban environment that is pleasant and friendly for bicyclists and pedestrians. The Design‐Builder shall balance the requirements of both the City of Rochester and Amtrak security
New York State Department of Transportation
Rochester Station Project Part 3‐16
Part 3 Project RequirementsJune 14, 2013
concerns, including small trees compatible with an urban setting that do not allow for hiding places. Landscaped islands shall be incorporated in the parking areas to soften the hardscape. LED site lighting shall be supplemented with additional pedestrian level lighting along major circulation routes. The Design‐Builder shall provide life‐cycle cost analysis for LED site lighting or other proposed substitute. Loading dock and trash and recycling storage shall be screened from public view.
Exterior to the station building, a Kiss and Ride Drop‐Off location, taxi stand, and short‐term parking are sited along the Central Avenue frontage. For ease of arrival and departure, the pick‐up and drop‐off lanes are designed at a minimum of twelve feet wide. Similarly, the taxi berths are minimally twenty feet in length with an additional five feet for maneuvering. Sidewalks throughout the site shall be a minimum of 8 feet wide, and crosswalks shall receive a thermoplastic decorative treatment. The Design‐Builder shall provide speed tables at major pedestrian crossings for both traffic calming and for ease of accessible travel with bollards for pedestrian safety.
5.9 Other Site Components
A place for garbage storage and retrieval shall be provided onsite concealed and screened from public view. Additional station maintenance items, such as snow plow, ice melt, and additional baggage floats and carts shall be accommodated with a minimum of three hundred square feet of covered exterior Amtrak storage space per Amtrak Functional Space Requirements, issued on 12/30/2012.
In order to further sustainable initiatives, a Construction and Building Site Waste Management Plan shall be in place to ensure 50% recycling and/or salvaging of existing material. Throughout the site, low maintenance landscaping shall be integrated to minimize impervious surfaces. The Design‐Builder shall grade areas away from structures to prevent ponding, while mitigating the flow of runoff over impervious surfaces.
SECTION 6. GEOTECHNICAL REQUIREMENTS
The Design‐Builder shall be responsible for geotechnical design and construction of all permanent and temporary structures, including assessing available information, geotechnical analysis and reporting, geotechnical instrumentation and monitoring, and protection of existing infrastructure, structures and utilities in accordance with the requirements of the Contract Documents. These requirements are considered as a minimum and do not include all possible conditions that may be encountered in the Design‐Builder’s final design.
NYSDOT has performed subsurface investigations in the vicinity of the proposed station building. Boring logs and laboratory test data from these previous subsurface investigations are provided in Part 7 – Project Data. The soil and rock samples obtained during these previous subsurface investigations are available for inspection by the Design‐Builder at request. The Design‐Builder shall be responsible for making any arrangements to view the samples from the previous subsurface investigations, by first seeking the prior consent of the NYSDOT’s Project Manager. Information from these previous subsurface investigations shall be considered part
New York State Department of Transportation
Rochester Station Project Part 3‐17
Part 3 Project RequirementsJune 14, 2013
of the Contract Documents only to the extent that they are used to represent soil conditions at the depths indicated within the respective borings drilled at the approximate locations shown. Presentation of this information in no way implies that subsurface conditions are the same at other locations and different times. The Design‐Builder shall form its own interpretation of the existing geotechnical data and satisfy itself as to the nature and behavior of the ground and sub‐soil, the form and nature of the Site, and nature of the Work that may affect its detailed design, construction method, and tools.
6.1 Standards and References
The Design‐Builder shall perform geotechnical activities in accordance with the Contract Requirements, the applicable Standards, Codes and Manuals.
AMTRAK
AMTRAK Station Program and Planning, Standards and Guidelines, Station Manual 2.2
AREMA – American Railway Engineering and Maintenance of Way Association
AREMA Manual for Railway Engineering
NYSDOT
A. Access Management Requirements B. Annual Report titled "Axle Factor Update" C. Approved Materials List D. Highway Design Manual – Chapters 20 and 21 (CADD Standards and Procedures) E. Comprehensive Pavement Design Manual F. Consultant Instructions G. Design Consultant Manual H. Engineering Bulletins I. Engineering Instructions and Directives J. Environmental Procedures Manual (EPM) / The Environmental Manual (TEM) K. General Design and Construction Requirements for Occupancies L. Geotechnical Engineering Bureau Manuals and Publications M. GCP‐17, Procedure for the Control of Granular Materials N. Land Surveying Standards and Procedures Manual O. Manual for Uniform Record Keeping P. Materials Bureau ‐ Applicable Sampling and Testing Manuals, Inspection Manuals, and
Materials Methods. Q. New York State Supplement to the Manual on Uniform Traffic Control Devices R. Prestressed Concrete Construction Manual S. Project Development Manual T. Reference Marker Manual U. Rules and Regulations Governing the Accommodation of Utilities within the State
Highway Right of Way V. Special Specifications
New York State Department of Transportation
Rochester Station Project Part 3‐18
Part 3 Project RequirementsJune 14, 2013
W. Standard Sheets X. Standard Specifications for Construction and Materials Y. Steel Construction Manual (SCM) Z. U.S. Customary Standard Sheets AA. Work Zone Traffic Control Manual
The above is a partial listing of applicable NYSDOT Engineering Manuals and Guidelines. The Design Builder shall perform the Work in conformance with all current NYSDOT Engineering Manuals and Guidelines.
6.2 Design Requirements
The Design‐Builder shall at a minimum provide the following:
A. Geotechnical Work Plan B. Geotechnical investigation plan C. Geotechnical data report D. Subsurface investigation records E. Seismic assessment report F. Geotechnical instrumentation and construction monitoring plans G. Foundation design reports
6.3 Geotechnical Work Plan
The Design‐Builder shall prepare a geotechnical work plan for the project. The plan shall identify the required geotechnical scope of work that the Design‐Builder plans to complete for the design and construction of the Project. The geotechnical work plan shall include the following:
A. Design‐Builder’s knowledge and understanding of the geotechnical, geologic, hydrogeology and seismic settings of the Project Site and how the nature and behavior of the soil, rock, groundwater and subsurface conditions will affect the investigation, design and methods of construction;
B. Anticipated methods of analysis and design for the foundation of the station building, high‐level platform and cut‐and‐cover tunnel and a discussion of the foundation optimization process and rationale for selection of the foundation types;
C. Identify key Project constraints and describe how the geotechnical activities will be designed and constructed to meet these constraints;
D. Identification of all principal geotechnical deliverables and activities;
E. A narrative describing the approach to quality control during design and construction of the geotechnical Works;
F. A risk register identifying all major design and construction risks of the geotechnical activities, and describe how these risks are managed and mitigated;
New York State Department of Transportation
Rochester Station Project Part 3‐19
Part 3 Project RequirementsJune 14, 2013
G. Resumes of the Foundations Lead Designer, Geotechnical Instrumentation Engineer, and Seismic Specialist;
H. Minimum numbers, depths, types of subsurface investigations to be carried out for the station building, high‐level platform and the tunnel design, including a narrative of the in‐situ tests and laboratory tests to be carried out;
I. Minimum numbers, and types of axial load tests for each foundation type, size and subsurface condition;
J. Minimum numbers, and types of lateral load tests for each foundation type and subsurface condition;
K. Minimum percentage and/or numbers of driven piles as tested piles to be dynamically tested;
L. Crosshole sonic logging shall be done on all drilled shafts according to NYSDOT specifications. Thermal integrity profiling shall be done on all demonstration shafts, in addition to the first three production shaft of each diameter size. Thermal integrity data shall be collected continuously and remotely through embedded sensors. Location of embedded sensors arrays shall be assumed similar to Crosshole sonic locations.
6.4 Geotechnical Subsurface Investigation Plan
The Design‐Builder shall prepare a geotechnical investigation plan, including specifications for performing the Work. The geotechnical investigation plan shall include the criteria or rationale used in developing the plan, and shall identify the locations of all field investigation sites, and borings, together with their depths, sampling intervals, and a description of both the field and laboratory testing programs utilized. The geotechnical investigation plan shall be prepared and signed and sealed by the Design‐Builder’s Lead Designer. The geotechnical investigation plan shall include details of borehole abandonment procedures and a list of all permits required to perform the geotechnical investigation.
The Design‐Builder shall plan and conduct subsurface investigations in accordance with the NYSDOT’s Standards for subsurface exploration programs, and as deemed necessary by the Design‐Builder’s Lead Designer to establish the geotechnical conditions and to perform all geotechnical and foundation design and analysis.
The Design‐Builder shall determine the coordinate location and ground surface elevation for each boring and field investigation position, and shall show the coordinates, station and offset, and elevation for each individual boring log or investigation record. Coordinates and station and offsets for the borings shall be referenced to Amtrak Mile Post 371.0 stationing. Elevations shall be referenced to the Project datum and horizontal control system. Boring horizontal coordinates shall be accurate to +/‐ 1.0 foot; vertical coordinates shall be accurate to +/‐ 0.5 foot.
New York State Department of Transportation
Rochester Station Project Part 3‐20
Part 3 Project RequirementsJune 14, 2013
6.5 Geotechnical Data Report
The Design‐Builder shall prepare a geotechnical data report, signed and sealed by the Foundations Lead Designer. The geotechnical data report shall serve as a factual depiction of the subsurface conditions and at a minimum it shall include:
a. A detailed description of the investigation methods; b. Complete records (typed logs using NYSDOT log format) with summary tables of
investigation;
c. Complete records with summary tables of laboratory test results; d. Exploratory hole location plan, showing locations of any existing (pre‐award)
exploratory holes for which data was used by the Design‐Builder plus locations of post‐award exploratory hole locations undertaken by the Design‐Builder; and Plots of laboratory test results versus elevations for separate areas and soil types.
6.6 Subsurface Investigation Records
The Design‐Builder shall be responsible for keeping a continuous and accurate log of the materials encountered and a complete record of the operation of progressing the casing. Where driving is used, a record of the number of blows required to advance the sampling barrel, each 6 inches in the soil where each sample is taken, shall be kept. Records shall be kept using the NYSDOT Subsurface Exploration Log Form (US Units).
The Design‐Builder shall use Bentley gINT® or similar commercial software to develop and maintain an electronic database of subsurface information including in‐situ test and laboratory test results, and to produce boring records.
6.7 Seismic Assessment Report
Prior to issue to the NYSDOT, the Design‐Builder shall ensure that the seismic assessment report is peer‐reviewed by a suitably qualified specialist in this field, and the findings and conclusions of the peer review shall be included in an appendix to the Seismic Assessment Report. The seismic specialist who will perform the review of this report shall meet the minimum requirements specified in General Instructions to Proposers.
A. Seismic Site Response Analyses ‐ Site‐specific seismic response analysis shall be performed to develop design free‐field response spectra in accordance with AREMA and Amtrak Guidelines. The Design‐Builder shall develop dynamic soil/rock properties for use in the seismic analysis based on PS‐Logging data as well as widely‐used empirical correlations. Spatial variation of ground motions shall be accounted for, as applicable.
B. Soil Structure Interaction ‐ Seismic soil structure interaction evaluation of deep foundations shall include determination of the maximum imposed curvatures and bending from earthquake ground motions and structure response, including free‐field soil strains modified for soil‐foundation‐structure interaction coupled with deep foundation
New York State Department of Transportation
Rochester Station Project Part 3‐21
Part 3 Project RequirementsJune 14, 2013
deformations associated with earthquake loads imparted to the foundation by the structure (i.e. inertial response).
C. Liquefaction ‐ Evaluation of liquefaction potential shall be performed. Should this show that liquefaction is a potential hazard at the Site, the risk potential on the station building, high‐level platform and the tunnel shall be evaluated by the Design Builder, and any remediation solutions proposed by the Design‐Builder shall be demonstrated by analytical and field methods.
6.8 Geotechnical Instrumentation and Construction Monitoring Plan
A. Monitoring of Existing Structures and Utilities ‐ The Design‐Builder shall develop, implement, and maintain a geotechnical instrumentation and construction monitoring plan to monitor vibrations, accelerations, vertical settlement, and lateral movement of temporary support structures and adjacent ground, and existing infrastructure during construction including the existing station building, utilities and other infrastructures within the zone of influence of construction.
B. Wherever vibration‐producing activities could affect a structure, building, or utility, the Design‐Builder shall prepare a Vibration Monitoring and Control Plan to address the potential impacts to nearby receptors due to construction or demolition activities associated with this Project. The term “receptor” includes buildings, structures, utilities, and sensitive operations/processes for which construction impacts or Work above recommended limits may be detrimental. The plan shall include ground and air‐blast vibration threshold limits. The monitoring plan shall address how the Design‐Builder intends to complete vibration‐related activities and meet the following minimum requirements:
1. Develop a list of all anticipated vibration producing activities and where they are expected to occur;
2. Develop a list of all potentially impacted receptors from these activities;
3. Provide a vibration susceptibility analysis for each identified receptor, and establish a vibration control limit to preclude damage, including threshold damage, to each of the identified receptors.
4. Provide a plan for notifying the public of potential vibration impacts, responsible Project personnel, receptors requiring precondition surveys, and vibration monitoring activities;
5. Monitor construction related vibrations at the nearest and most critical receptor(s), and notify appropriate project personnel immediately if established vibration limits are exceeded;
6. Provide instrumentation locations, monitoring procedures, and a description of the monitoring devices and/or manufacturers’ brochures in the submitted plan;
7. Assess any sensitive community or business operations that may be affected by vibrations;
New York State Department of Transportation
Rochester Station Project Part 3‐22
Part 3 Project RequirementsJune 14, 2013
8. Provide recommendations for vibration‐limiting methods to meet the established maximum safe vibration levels.
9. List of receptors shall include, but not limited to:
• Utilities
• Nearby bridges
• Buildings
• Newly constructed elements
• Existing structures within zone of influence of vibration producing activities
C. Construction Monitoring ‐ The Design‐Builder’s construction monitoring plan shall include details of the proposed program of instrumentation and monitoring, monitoring frequency, assesses the impacts to existing structures and utilities, establishes threshold values of the monitored parameters, and describes the response plan that will be implemented when threshold parameters are exceeded. A system of construction monitoring shall be established to include the following:
1. Measurement of ground water levels and ground water pressure.
2. Monitoring of settlement of the permanent structures and surrounding area both during and after construction. In all cases, monitoring shall be initiated well in advance of construction to establish baseline readings.
3. Measurement of lateral movement of permanent structures.
4. Measurement of vibration levels of the permanent structures and surrounding area both during and after construction. Ambient vibration monitoring shall be conducted well in advance of construction to establish baseline readings.
D. The extent of the monitoring program will depend on the size and type of the affected structures. A detailed monitoring program shall be prepared for each structure affected by the work, subject to review by NYSDOT.
E. Where adjacent properties may be affected by the works, the monitoring program shall allow for readings on fixed points on the structures and buildings, to allow both total and differential settlements to be assessed and lateral movements to be determined. The monitoring program shall also allow for access to conduct vibration monitoring on adjacent properties.
F. Potential Instrumentation
The instrumentation and monitoring program shall include appropriate types and quantities of monitoring instruments capable of measuring horizontal and vertical movements, tilt of adjacent structures, soil pore pressures, vibrations, and noise, as applicable. Instrumentation to be used in the monitoring programs to control and assist design and construction could include:
New York State Department of Transportation
Rochester Station Project Part 3‐23
Part 3 Project RequirementsJune 14, 2013
1. Piezometers and observation wells 2. Inclinometers 3. Survey stations on structures and at ground level locations 4. Tiltmeters 5. Deep settlement points and extensometers 6. Strain and load‐measuring devices 7. Seismographs, geophones, and others.
The types and numbers of instruments will depend on factors including the size, type and location of proposed work. The design and distribution of instrumentation shall demonstrate an understanding of the need, purpose and advantages of using each proposed type. Responsibilities for design, procurement, installation, recording, maintenance and protection, and monitoring plan, criteria and performance requirements shall be clearly stated in the specifications and Contract Documents. These shall also contain the�