DNV-GL Database Ontario

DNV-GL Database Eastern Ontario

Bio-energy Contractshttp://www.powerauthority.on.ca/current-electricity-contracts/bio-energy

Q3 2014 UpdateBy the end of the reporting period, the OPA was managing 508 MW of combined capacity from bio-energy projects, 333 MW in commercial operation and 175 MW under development. All of the capacity from projects that are currently under development is scheduled to be in-service at or before the end of 2016.Facilities in commercial operation (120 MW)Eastview Landfill Gas Energy Plant (1.7 MW) - Guelph Hamilton (Digester Gas) Cogen Plant (1.6 MW) - HamiltonTrail Road Landfill Gen Facility (6 MW) - Ottawa Thunder Bay Condensing Turbine (40 MW) - Thunder BayBecker Cogen Plant (8 MW) - HornepayneFeed-in Tariff (23.1 MW) Renewable Energy Standard Offer (39.7 MW) Projects under development (248 MW)Atikokan Generating Station (205 MW) AtikokanFeed-in Tariff (38.8 MW)Renewable Energy Standard Offer (4 MW)

Solar Photovoltaic (PV) - Contractshttp://www.powerauthority.on.ca/current-electricity-contracts/solar

Q3 2014 Update By the end of the reporting period, the OPA was managing 2,171 MW of combined capacity from solar PV projects, 1,396 MW in commercial operation and 775 MW under development. All of the capacity from projects that are under development is scheduled to be in-service at or before the end of 2017.Facilities in commercial operation (1,235 MW)FIT (594.8 MW) microFIT (166.8 MW) (19,215 contracts)RESOP (473.7 MW) Projects under development (939 MW) Grand Renewable Energy Park (100.0 MW) - Haldimand CountyKingston North (100.0 MW) - Kingston & Loyalist TownshipFeed-in Tariff (738.5 MW)

Wind Contractshttp://www.powerauthority.on.ca/current-electricity-contracts/wind

Q3 2014 UpdateBy the end of the reporting period, the OPA was managing 5,697 MW of combined capacity from wind projects, 3,066 MW in commercial operation and 2,631 MW under development. All of the capacity from projects that are currently under development is scheduled to be in-service at or before the end of 2018.

Facilities in commercial operation (2,853 MW)RES Contracts (see list)South Kent Wind Project (270 MW) - Chatham-KentFeed-in Tariff (797.7 MW) Renewable Energy Standard Offer (275.4 MW) Projects under development (2,862 MW) Armow Wind Project (180 MW) - Kincardine Grand Renewable Energy Park (wind) (148.6 MW) - Haldimand County K2 (270 MW)- Ashfield-Colborne-Wawanosh Feed-in Tariff (2,253.7 MW) Renewable Energy Standard Offer (9.5 MW)Enbridge Ontario Wind Farm (181.5 MW) - Bruce CountyErie Shores Wind Farm (99.0 MW) - Port BurwellGosfield Wind Project (50.6 MW) - Essex CountyGreenwich Wind Farm (98.9 MW) - District of Thunder BayKingsbridge I Wind Power Project (39.6 MW) GoderichKruger Energy Chatham Wind Project (99.4 MW) - Municipality of Chatham-KentKruger Energy Port Alma Wind Power Project (101.2 MW) - Port AlmaMelancthon I Wind Plant (67.5 MW) - Melancthon TWPMelancthon II Wind Plant (132.0 MW) - Amaranth/Melancthon TWPPrince I Wind Power Project (99.0 MW) - Aweres/Dennis/Pennefather/Prince TWPPrince II Wind Power Project (90.0 MW) - Dennis/Pennefather TWPRaleigh Wind Energy Centre (78.0 MW) - Chatham-KentRipley Wind Power Project (76.0 MW) - Huron/Kinloss TWPTalbot Windfarm (98.9 MW) - Howard / Oxford TWPWolfe Island Wind Project (197.8 MW) - Wolfe Island

Hydroelectricity Contractshttp://www.powerauthority.on.ca/hydroelectricity-contracts

Facilities in commercial operation (1,847 MW)Feed-in Tariff (22 MW)Renewable Energy Standard Offer (28.2 MW)Projects under development (591 MW)Harmon GS (17.6 MW) Runner Upgrade- Kapuskasing: Mattagami RiverKipling GS (78 MW) - Kapuskasing: Mattagami RiverSmoky Falls GS (267.9 MW) - Timmins: Mattagami RiverYellow Falls (16 MW) - Smooth Rock Falls: Mattagami RiverFeed-in Tariff (163.4 MW)HESOP (35.3 MW) (Hydroelectric Energy Standard Offer Program)HCI (12.4 MW) - Expansion Projects (Hydroelectric Contract Initiative)

High Level Estimate: Economic Benefit

Source: IESO/OPA, A Progress Report on Contracted Electricity Supply, Third Quarter 2014, Appendix I

Contract Capacity as of Sept. 30, 2014

Thank You