ROAD SAFETY AUDIT PRACTICE IN MALAYSIA by Ir. RICHARD WONG CHAIRMAN HIGHWAY & TRANSPORTTION ENGINEERING TECHNICAL DIVISION (HTETD) INSTITUTION OF ENGINEERS, MALAYSIA (IEM) RW Consultancy Understanding Road Safety Audit (RSA) 1

ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

ROAD SAFETY AUDIT

PRACTICE IN MALAYSIA

by

Ir. RICHARD WONG

CHAIRMAN

HIGHWAY & TRANSPORTTION ENGINEERING TECHNICAL DIVISION (HTETD)

INSTITUTION OF ENGINEERS, MALAYSIA (IEM)

RW Consultancy Understanding Road Safety Audit (RSA) 1

Page 2: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

ROAD DEATHS IN MALAYSIA

RW Consultancy 2

5600

5800

6000

6200

6400

6600

6800

7000

7200

7400

2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

DEATH

DEATH

Source: Dato Ir Foong Choy Chye

Page 3: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

RW Consultancy 3Source: Dato Ir Foong Choy Chye

Page 4: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

Consequences of Overloading

RW Consultancy 4Source: Dato Ir Foong Choy Chye

Page 5: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

Interaction of road, vehicle and driver in road crash

ROAD

VEHICLE

DRIVER

EXTERNAL

FACTORS

EXTERNAL

FACTORS

EXTERNAL

FACTORS

External Factors are :

1. institutional policy

2. organisational

administrative factors

relating to safety

management issue

PROBABLE CRASH

PROBABLE SEVERE CRASH

RW Consultancy 5Source: Dato Ir Foong Choy Chye

Page 6: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

RW Consultancy 6Source: Dato Ir Foong Choy Chye

Page 7: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

RW Consultancy 7Source: Dato Ir Foong Choy Chye

Page 8: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

Brief History of Road Safety Audit

• 1994 – JKR or PWD Malaysia introduced Road Safety Audit in Road Project implementation

• Later was mandatory for all new road projects implemented under the Seventh Malaysia Plan (1996 - 2000)

• 1997 – Road Safety Audit Section was set up in JKR

RW Consultancy 8

Page 9: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

There are 5 stages in the development of a road project when it ismost appropriate to carry out a road safety audit (RSA).

They are as follows:

➢ Stage 1 – Feasibility and Planning Stage

➢ Stage 2 – Draft (Preliminary) Design Stage

➢ Stage 3 – Detail Design Stage

➢ Stage 4 – TMP/During Construction/Pre-Opening Stage

➢ Stage 5 – After Construction/Operational Stage

RW Consultancy Understanding Road Safety Audit (RSA) 9

Page 10: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

OBJECTIVE

1) To determine whether the consulting engineer’s design from theplanning to operational stage of the proposed road project is inaccordance with the “Guidelines for the Safety Audit of Roads inMalaysia” published by the Jabatan Kerja Raya (JKR) Malaysia;the “Arahan Teknik Jalan” publications by JKR Malaysia; and alsoany other recognized publications such as Road EngineeringAssociation of Malaysia (REAM), Austroads and IHT.

2) To identify road safety deficiencies at various stages in thedevelopment of the proposed road project.

3) Eliminate deficiencies at the most opportune time to reducecosts and minimize disruption to design and constructionprogress.

RW Consultancy Understanding Road Safety Audit (RSA) 10

Page 11: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

TECHNICAL GUIDELINE REFERENCES

▪ Guidelines for the Safety Audit of Roads in Malaysia by JKR

▪ ATJ 1/85 – Manual on Design Guidelines of Longitudinal Traffic Barrier

▪ REAM GL 9/2006 – Guidelines on Design and Selection of Longitudinal Traffic Safety Barrier

▪ ATJ 2A/85 – Manual on Traffic Control Devices, Standard Traffic Signs

▪ ATJ 2B/85 – Manual on Traffic Control Devices, Traffic Sign Applications

▪ ATJ 2C/85 (Pindaan 2017) – Manual on Traffic Control Devices, Temporary Signs and Work Zones Control

▪ Nota Teknik Jalan 23/03 - Guidelines for Traffic Management During Construction

▪ ATJ 2E/87 (2011) – Guide Signs Design and Application

RW Consultancy Understanding Road Safety Audit (RSA) 11

Page 12: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

TECHNICAL GUIDELINE REFERENCES (cont’d)

▪ ATJ 2D/85 – Manual on Traffic Control Devices, Road Marking andDelineation

• REAM GL 8/2004 – Guidelines on Traffic Control and Management Devices Part 4 – Pavement Marking and Delineation

• ATJ 8/86 (2015) – A Guide on Geometric Design of Roads by JKR

• REAM GL 2/2002 – A Guide on Geometric Design of Roads

• ATJ 11/87 – A Guide to the Design of At-Grade Intersections by JKR

• ATJ 12/87 – A Guide to the Design of Interchanges by JKR

• ATJ 13/87 – A Guide to the Design of Traffic Signals by JKR

• Nota Teknik Jalan 18/97 – Guidelines on Pedestrian Facilities

• References are also made to other nationally and internationally accepted engineering practices such as LLM, AASHTO and AUSTROADS.

RW Consultancy Understanding Road Safety Audit (RSA) 12

Page 13: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

RW Consultancy 13

Page 14: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

RW Consultancy 14

Page 15: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

RW Consultancy 15

Page 16: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

RW Consultancy 16

Page 17: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

Understanding Road Safety Audit (RSA)

Stage 1 Audit – Feasibility and Planning Stage

1) Identifies safety problems associated with the overallconcept of the project.

2) Covers the road network, geometric standards,provision for other users such as motorcyclists &pedestrians, access control, environmentalconsiderations such as high winds & scenic vistas androute options/alternatives.

RW Consultancy Understanding Road Safety Audit (RSA) 17

Page 18: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

Understanding Road Safety Audit (RSA)

Stage 2 Audit – Draft (Preliminary) Design Stage

At this stage, many of the traffic engineering features of the projectshould be established.

1. Identify the safety aspects and design requirements as per bestinternational practice and the guidelines of the JKR “ArahanTeknik Jalan” and REAM publications.

2. We audit the design criteria, cross section, alignments,interchanges/junctions, access control, major land usedevelopments (their implications such as entry and exits) andstage development of major projects

RW Consultancy Understanding Road Safety Audit (RSA) 18

Page 19: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

Understanding Road Safety Audit (RSA)

Stage 2 Audit – Draft (Preliminary) Design Stage (cont’d)

3. Also includes interchange layouts, lane and carriagewaylayouts, sight distances, ‘Right-of-Way’ requirements andprovisions for other users such as motorcyclists andpedestrians.

4. The project development shall not proceed into the detaildesign stage before resolution of each of the road safetyitems identified in the Stage 2 Audit.

RW Consultancy Understanding Road Safety Audit (RSA) 19

Page 20: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

Understanding Road Safety Audit (RSA)

Stage 3 Audit – Detail Design Stage

1) Examine the design decisions made against road safetyobjectives and will identify aspects in which safety hasnot been given high enough weighting compared toother competing factors.

2) For areas where the design features can not be altered,for whatever reason, and road safety is beingcompromised, mitigating factors shall be recommendedby the designer and agreed upon by the auditor.

RW Consultancy Understanding Road Safety Audit (RSA) 20

Page 21: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

Understanding Road Safety Audit (RSA)

Stage 3 Audit – Detail Design Stage (cont’d)

3) Audit features shall include sight distance, adversecombinations of vertical and horizontal alignment, gradients,interchanges/intersections, road markings, drainage,roadside safety, traffic signings and controls, street lighting,landscaping features and provisions for special road users.

4) The project shall not proceed to the construction stage untileach of the road safety items identified in the Stage 3 Audithas been resolved.

RW Consultancy Understanding Road Safety Audit (RSA) 21

Page 22: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

Understanding Road Safety Audit (RSA)

Stage 4 Audit - During Construction/Pre-Opening Stage

1) Includes the Verfication Audit and traffic managementin and around the site during construction.

2) Viewed in three dimensions for both day and night. Theactual placement of guardrails, traffic signs and poles,street lights and landscaping shall be looked at in detail.

3) Emphasis will be given to all road user groups to ensurethat desirable road safety standards are met.

4) Auditing shall be done as early as possible duringconstruction (about 50% completion), to cover anychanges or modifications made during constructionuntil its completion or pre-opening to traffic.

RW Consultancy Understanding Road Safety Audit (RSA) 22

Page 23: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

Understanding Road Safety Audit (RSA)

Stage 5 Audit – After Construction/Existing Stage

1) Identify safety problems developed due to normal‘wear and tear’ from traffic operation.

2) Also identify safety hazards from the way thelandscaping has matured, such as trees and foliageobstructing traffic signs or impairing sight distances.

3) Inspections shall be carried out for both day andnight to check inadequacies in road delineation andvisibility.

RW Consultancy Understanding Road Safety Audit (RSA) 23

Page 24: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

Understanding Road Safety Audit (RSA)

Stage 5 Audit – After Construction/Existing Stage (cont’d)

4) Emphasise the way each road user group views theroad from their particular safety viewpoint. Example, amotorcyclist may view a safety hazard differently froma motorist.

5) This audit shall be carried out within 3 to 6 monthsafter the opening of the project to the public orgenerally during the defect liability period.

RW Consultancy Understanding Road Safety Audit (RSA) 24

Page 25: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

Looking from north (Solok Pandamaran) to the site on the left. Sight distance is good and alignment is straight and flat. Faded lane markings. Trees and posts near to

travelled way.

RW Consultancy RSA 1 - Planning & Feasibility Stage 25

Page 26: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

Delineator Post Provided

Without Delineator Post

Page 27: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

Rigid Delineator Post

Flexible Delineator

Post

Page 28: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate
Page 29: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

RW Consultancy 29

Page 30: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

RW Consultancy 30

Page 31: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

Proposed New Temporary Signs During Construction For All Roads Other Than Expressways

RW Consultancy RSA Stage 4 31

Page 32: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

Temporary Signs (Expressways)

RW Consultancy RSA Stage 4 32

Page 33: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

Photo 1: NJBs are not interlocked; blinkers are not regularly spaced; string delineators are not continuous;

pavement delineators are faded; directional pavement arrows are recommended.RW Consultancy 33

Page 34: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

Photo 2: At the abutment, concrete NJBs are recommended to close up the gap exposing a drop of

more than 1 m.

RW Consultancy Bukit Kuang RSA 4 Pt 2 34

Page 35: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

Photo 3: Signs with distance markers; NJBs, if not interlocked, may drop and become disorganised.

RW Consultancy 35

Page 36: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

Photo 4: Permanent delineation are mixed with temporary delineation; recommend a buffer zone;

signs behind barriers should be on high posts; and provide a U-turn sign at the U-turn.

RW Consultancy 36

Page 37: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

Photo 5: Lack of pavement delineation and road markings to guide motorists; NJBs not

interlocked and disorganised; string delineators not continuous; blinkers not regularly spaced.

RW Consultancy 37

Page 38: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

Study Approach – Stage 5 Audit

RW Consultancy RSA Stage 5 38

Page 39: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

Study Approach – Stage 5 Audit

RW Consultancy RSA Stage 5 39

Page 40: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

Study Approach – Stage 5 Audit

RW Consultancy RSA Stage 5 40

Page 41: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

RW Consultancy RSA Stage 5 41

Page 42: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

RW Consultancy RSA 5 - Existing Condition 42

Page 43: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

RW Consultancy RSA 5 - Existing Condition 43

Page 44: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

RW Consultancy RSA 5 - Existing Condition 44

Page 45: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

RW Consultancy RSA 5 - Existing Condition 45

Page 46: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

RW Consultancy RSA 5 - Existing Condition 46

Page 47: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

Parting Words

• While we Engineers, Contractors,Auditors, Authorities give our level bestto have safety in mind in carrying out ourduties, road environment and designcontributes insignificantly to roadaccidents.

• The greatest contributor to roadaccidents is human behaviour & attitude.

RW Consultancy RSA Stage 5 47

Page 48: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

SO….

1. DON’T DRINK AND DRIVE

2. DON’T PHONE, TEXT AND DRIVE

3. DON’T SPEED

RW Consultancy RSA Stage 5 48

Page 49: ROAD SAFETY AUDIT PRACTICE IN MALAYSIArsswpiarckl2019.miros.gov.my/registration/assets/slides/...There are 5 stages in the development of a road project when it is most appropriate

THANK YOU

fromIr. RICHARD WONG

ChairmanHTETD, IEM

RW Consultancy RSA 5 - Existing Condition 49