Road Map To Development
Data Submission
WEQ 008 Assessment
CO 283 Report
GTL CO’s Draft
CO’s Development
Key Assumptions:-WEQ 008 is approved by December 2013-Agreement for funding of the Change Order required is in place by June 2014-IDCWG SC support of the CO’s development by March 2014
Road Map To Trial Period12-18 Month Test
TestingTesting Result
Report
Implement CO’s Start of Trial Period
Key Assumptions:-WEQ 008 is approved by December 2013-Agreement for funding of the Change Order required is in place by June 2014-IDCWG SC support of the CO’s development by March 2014
3 Free Template from www.brainybetty.com 3
BPS Approval
EC Approval
BPS Approval
EC Approval
Q1 Q2 Q3 Q4
2017
Parallel Flow Visualization Development (Full Staffing)2014 2015
Q1 Q2 Q3 Q2 Q3 Q4
2016Q1 Q2 Q3 Q4Q4 Q1
Scen
ario
1Sc
enar
io 2
IDC Development/Testing
12 Month Field Test
IDC Development/Testing
18 Month Field Test
Timeline Scenarios
Activities after Completion of Field Test/Full Staffing
•Standards ratified after successful field test•Standards submitted to FERC•Notice of Proposed Rulemaking/Order•Incorporated into Code of Federal Regulations with effective date