CANBERRA REGION JOINT ORGANISATION CANBERRA REGION JOINT ORGANISATION Report prepared by Road and Bridge Register 20 December 2018

Road and Bridge Register - crjo.nsw.gov.au · to assist Councils move one step closer to being Shovel‐Ready to deliver on 140 road and bridge projects. For example, a commitment

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Road and Bridge Register - crjo.nsw.gov.au · to assist Councils move one step closer to being Shovel‐Ready to deliver on 140 road and bridge projects. For example, a commitment

CANBERRA REGION JOINT ORGANISATION 

  CANBERRA REGION JOINT ORGANISATION 

 

 

Report prepared by 

Road and Bridge Register 20 December 2018

   

Page 2: Road and Bridge Register - crjo.nsw.gov.au · to assist Councils move one step closer to being Shovel‐Ready to deliver on 140 road and bridge projects. For example, a commitment

 

 

CANBERRA REGION JOINT ORGANISATION 

Executive Summary 

 

  

  The Canberra Region Joint Organisation (CRJO) Road and Bridge Register presents a summary of priority infrastructure projects within the Canberra Region, which require funding from NSW State and Federal Governments.   A total of 102 Road and 38 Bridge Projects are included in this Register; submitted by the eleven councils who are members of the CRJO. Project information was submitted by the Engineering, Infrastructure or Operations Department within each council.    The eleven councils who are members of the CRJO include: Queanbeyan Palerang Regional Council, Snowy Monaro Regional Council, Snowy Valleys Council, Yass Valley Council, Upper Lachlan Shire Council, Wingecarribee Shire Council, Hilltops Council, Goulburn Mulwaree Council, Eurobodalla Shire Council, Bega Valley Shire Council and Wagga Wagga City Council.  A summary of the project costs is provided below, noting that the NSW Government is requested to provide funding to assist Councils move one step closer to being Shovel‐Ready to deliver on 140 road and bridge projects. For example, a commitment of $5.5M will fund 41 Options Studies and $1.7M for 20 Concept Designs on Road and Bridge Projects that have been prioritized to commence in 1‐3 years. This is high impact, immediately expendable funding.    

Framework Stages

Identify & Define

Brief Options Study

Site

Assess

Concept Design

Planning

& Approval

Design &

Spec

Const Proc’mnt

Const

Delivery

Finalise Contracts

Close Out

1-3 year projects

$0.3M [5] $5.5M [41] $1.3M [18] $1.7M [20] $2.1M [14] $7.7M [28] $0.3M [5] $327M [48] $876M [100]

Roads $0.3M [5] $4.5M [30] $0.9M [16] $1.4M [14] $2M [12] $6.5M [19] $0.3M [5] $277M [34] $810M [75]

Bridges $1.0M [11] $0.04M [2] $0.3M [6] $0.08M [2] $1.2M [9] $49.1M [14] $66M [25]

4-10 year projects

$2.4M [24] $0.9M [14] $0.33M [4] $3,1M [11] $258.1M

[26] $644M [38]

Roads $2.1 [16] $0.5M [7] $0.1M [1] $2.1M [8] $224M [21] $277M [26]

Bridges $0.3M [8] $0.33M [7] $0.23M [3] $1.0M [3] $34.1M [5] $367M [12]

10-20 year projects

$0.55M [2] $0.8M [1] $0.3M [1] $3.5M [1] $10M [1] $7.5M [2]

Roads $0.3M [1] $0.8M [1] $0.3M [1] $3.5M [1] [1]

Bridges $0.25M [1] $10M [1] $7.5M [1]

 We trust you will seriously consider the work that has been undertaken to ensure councils are shovel ready to commence road and bridge work across the region.  Cr. Rowena Abbey Chair, Canberra Region Joint Organisation [email protected]  0411 251 018   

Page 3: Road and Bridge Register - crjo.nsw.gov.au · to assist Councils move one step closer to being Shovel‐Ready to deliver on 140 road and bridge projects. For example, a commitment

 

 

CANBERRA REGION JOINT ORGANISATION 

Road & Bridge Map 

 

    

Page 4: Road and Bridge Register - crjo.nsw.gov.au · to assist Councils move one step closer to being Shovel‐Ready to deliver on 140 road and bridge projects. For example, a commitment

 

 

CANBERRA REGION JOINT ORGANISATION 

Delivery Framework 

 

    

IDENTIFY  PLAN  DEVELOP  DELIVER  CLOSE        

 

  

  

  

  

  

  

  

  

     

  Road Projects [1‐3 Year Priority]    Phase  

      

  

      

      

  

    

     

      

  

      

      

  

      

   Framework

Stages Identify &

Define Brief Options Study Site Assessment Concept Design

Planning & Approvals

Design &

Specification

Construction Procurement

Construction

Delivery

Finalise Contracts

Close Out        

 

      

  

      

      

  

     

#  Project  Council % Council 

contributes to next stage 

   [Cost ‐ Time] to Next Stage 

 [Cost ‐ Time] to Next Stage 

 [Cost ‐ Time] to Next Stage 

 [Cost ‐ Time] to Next Stage 

         [Cost ‐ Time] 

to Shovel‐Ready          

[Total Cost ‐ Total Time] 

                                                                                                

1  Port of Eden: Upgrades (R) (H)  BVSC  50%                               [$10K‐1mo]    [$3M‐1yr]        [$3.2M‐1.25yr]                                                

                                               

2  Towamba and Burragate Roads: Sealing (L) (H)  BVSC                             [$65k‐4mo]         [$10M‐2yr]         [$10.07M‐2.5yr]                                                

                                               

3  Tantawangalo Mountain Road: Sealing (L) (H)  BVSC                            [$35k‐1mo]        [$1.95M‐1.5yr]        [$1.99M‐2yr]                                                

                                               

4  Tathra Public School: Traffic Safety Upgrades (R)   BVSC                                [$10k‐2mo]     [$400k‐1yr]         [$0.42M‐1.5yr]                                                

                                               

5  Sapphire Coast Drive: Realignment (R)   BVSC            [$50k‐4mo]                        [$400k‐1yr]        [$0.45M‐2.5yr]                                                

                                               

6  Wolumla Public School: Traffic Safety Upgrades (L)   BVSC                        [$25k‐3mo]            [$405k‐1yr]        [$0.43M‐2yr]                                                

                                               

7  Doctor George Mountain Road: Sealing (L)   BVSC                            [$35k‐3mo]        [$5M‐2yr]        [$5.2M‐2.5yr]                                                

                                               

8  Market Street Merimbula CBD: Revitalisation (L)   BVSC                        [$100k‐6mo]            [$14M‐3yr]         [$14.1M‐3yr]                                                

                                               

9  Beach Road Intersections: Upgrades (R) (H)  ESC                        [$100k‐6mo]            [$4.2M‐12mo]        [$4.3M‐2yr]                                                

                                               

10  George Bass Drive: Duplication of Lanes (R) (H)  ESC                                     [$800k‐4mo]        [$0.8M‐4mo]                                                

                                               

11 George Bass Drive/Grandfathers Gully: Realignment(R)(H) 

ESC  25%                      [$100k‐3mo]            [$3.9M‐18mo]        [$4M‐3yr] 

                                               

                                               

12  Beach Road: Installation of Central Median (R) (H)  ESC                        [$100k‐3mo]            [$1.7M‐9mo]        [$1.8M‐1yr]                                                

                                               

13  George Bass Drive: Upgrades (R) (H)  ESC                        [$150k‐6mo]            [$7.85M‐18mo]        [$8M‐2yr]                                                

                                               

14  Eurobodalla Road: Upgrades (L) (H)  ESC  25%                      [$150k‐3mo]            [$750k‐6mo]        [$0.9M‐9mo]                                                

                                               

15  ESC High Priority Pathways: New Construction (R)   ESC  20%                      [$100k‐3mo]            [$5.4M‐24mo]        [$5.5M‐3yr]                                                

                                               

16  Moruya Town Centre: Pedestrian Activation (L)   ESC                                    [$800k‐12mo)         [$0.8M‐yr]                                                

                                               

17  Dunns Creek Road: Safety Improvements (L)  ESC                        [$100k‐2mo]            [$900k‐4mo]        [$1M‐6mo]                                                

                                               

18  Orient Street CBD Intersections: Upgrades (L)   ESC                        [$100k‐3mo]             [$3.4M‐9mo]        [$3.5M‐1yr]                                                

                                               

19  Gurrundah Road: Upgrades (L) (H)  GMC            [$50k‐3mo]    [$50k‐3mo]                            [$4.07M‐4yr]                                                

                                               

20  Bungonia Road: Upgrades (L) (H)  GMC  50%              [$50k‐3mo]        [$50k‐3mo]     [$50k‐3mo]                 [$1.2M‐2yr]                                                

                                               

21  Range Road: Upgrades (L) (H)  GMC                    [$100k‐6mo]                         [$3.7M‐4yr]                                                

                                               

22  Windellama Road: Upgrades (L)   GMC            [$50k‐3mo]    [$50k‐3mo]                             [$8.6M‐4yr]                                                

                                               

23  Oallen Ford Road: Upgrades (L)   GMC  50%              [$50k‐3mo]     [$100k‐6mo]                        [$4.04M‐4yr]                                                

                                               

24  Lumley Road : Upgrades (L)   GMC  50%          [$50k‐3mo]                                [$3M‐2yr]                                                

                                               

25  Cullulla Road: Upgrades (L)   GMC  50%          [$100k‐6mo]                                [$20M‐4yr]                                                

                                               

26  Sandy Point Road: Upgrades (L)   GMC  50%          [$100k‐6mo]                                [$3M‐2yr]                                                

                                               

27  Lachlan Valley Way: Upgrades (S) (H)  HC  50%          [$20k‐2mo]    [$65k‐3mo]    [$50k‐2mo]                        [$0.135]*                                                

                                               

28  Murringo Road: Upgrades (R) (H)  HC            [$20k‐2mo]    [$80k‐3mo]    [$50k‐2mo]                        [$30M‐1yr]                                                

                                               

29  Jugiong Road Bypass: Upgrades (L) (H)  HC  50%          [$20k‐2mo]    [$50k‐2mo]    [$50k‐2mo]                        [$22M‐yr]                                                

                                               

30  Chews Lane Bypass: Upgrades (L) (H)  HC  50%          [$20k‐2mo]    [$50k‐3mo]    [$50k‐2mo]                        [$24M‐1yr]                                                

                                               

31  Henry Lawson Way: Upgrades (L)   HC            [$20k‐2mo]    [$80k‐3mo]    [$50k‐2mo]                        [$24M‐1yr]                                                

                                               

32  Bribbaree Road: Upgrades (L)   HC  50%          [$20k‐2mo]    [$50k‐3mo]    [$50k‐2mo]                        [$24M‐1yr]                                                

                                               

33  Mahons Reef Road: Upgrades (L)   HC  50%          [$20k‐2mo]    [$50k‐3mo]    [$50k‐2mo]                        [$24M‐1yr]                                                

                                               

34  Nerriga Road (R) (H)  QPRC                            [$350k‐12mo]        [$28M‐4yr]        [$28M‐4yr]                                                

                                               

35  Captains Flat: Road Realignment and upgrade (R) (H)  QPRC                                            [$36M‐6yr]                                                

                                               

36  Bungendore Bypass (L) (H)  QPRC            [$1M‐24mo]                                [$1M‐2yr]*                                                

                                               

37  Braidwood Bypass (L) (H)  QPRC            [$1M‐24mo]                                [$1M‐2yr]*                                                

                                               

Page 5: Road and Bridge Register - crjo.nsw.gov.au · to assist Councils move one step closer to being Shovel‐Ready to deliver on 140 road and bridge projects. For example, a commitment

 

 

CANBERRA REGION JOINT ORGANISATION 

Delivery Framework 

 

    

IDENTIFY  PLAN  DEVELOP  DELIVER  CLOSE        

 

  

  

  

  

  

  

  

  

     

  Road Projects [1‐3 Year Priority]    Phase  

      

  

      

      

  

    

     

      

  

      

      

  

      

   Framework

Stages Identify &

Define Brief Options Study Site Assessment Concept Design

Planning & Approvals

Design &

Specification

Construction Procurement

Construction

Delivery

Finalise Contracts

Close Out        

 

      

  

      

      

  

     

#  Project  Council % Council 

contributes to next stage 

   [Cost ‐ Time] to Next Stage 

 [Cost ‐ Time] to Next Stage 

 [Cost ‐ Time] to Next Stage 

 [Cost ‐ Time] to Next Stage 

         [Cost ‐ Time] 

to Shovel‐Ready          

[Total Cost ‐ Total Time] 

                                                 

38  Braidwood Mainstreet: Upgrade (S)   QPRC            [$150k‐18mo]        [$300k‐24mo]                [$16M‐1.5yr]        [$16M‐5yr]                                                

                                               

39  Williamsdale Road (L)   QPRC                    [$250k‐12mo]                 [$25M‐4yr]        [$25M‐4yr]                                                

                                               

40  Burra Bends extension (L)   QPRC  50%                           [$150‐12mo]         [$3.4M‐3yr]        [$3.4M‐3yr]                                                

                                               

41  Black Lake Road: Upgrades (R) (H)  SMRC  35%          [$43k‐6mo]                [$212k‐12mo]        [$3.9M‐12mo]        [$4.3M‐2.5yr]                                                

                                               

42  Middlingbank Road: Upgrades (R) (H)  SMRC  10%          [$139k‐6mo]                [$695k‐12mo]        [$13.1M‐2.5yr]        [$13.9M‐4yr]                                                

                                               

43  The Snowy River Way: Upgrades (R) (H)  SMRC  10%          [$66k‐6mo]                [$330k‐12mo]        [$6.2M‐1.5yr]        [$6.6M‐3yr]                                                

                                               

44  Polo Flat Road: Upgrades (R) (H)  SMRC  10%          [$18k‐6mo]                [$90k‐12mo]        [$1.7M‐1.5yr]        [$1.8M‐3yr]                                                

                                               

45  Cathcart Road: Upgrades (R) (H)  SMRC  10%          [$49.5k‐6mo]                [$248k‐6mo]        [$4.7M‐24mo]        [$5M‐3yr]                                                

                                               

46  Barry Way: Upgrades (R) (H)  SMRC  10%          [$288k‐6mo]                [$1.4M‐6mo]        [$27M‐3yr]        [$28.8M‐4yr]                                                

                                               

47  Jerangle Road: Upgrades (L)   SMRC  10%          [$238k‐6mo]                [$1.2M‐2yr]        [$22.4M‐3yr]        [$23.8M‐4yr]                                                

                                               

48  Snowy Mountains Highway: Overtaking Lanes (S) (H)  SVC            [$20k‐6mo]                                [$45M‐4yr]                                                

                                               

49  Tumbarumba: Heavy Vehicle Bypass (S) (H)  SVC        [$75k‐5mo]                                    [$0.85M]*                                                

                                               

50  Batlow Road: Climbing Lanes (S) (H)  SVC            [$20k‐6mo]                                [$0.20M]*                                                

                                               

51  Snowy Mountains Highway: Upgrades (S) (H)  SVC        [$10k‐2mo]                                    [$0.01M]*                                                

                                               

52  Tooma Road: Upgrades (R) (H)  SVC        [$75k‐6mo]                                    [$22M‐3yr]                                                

                                               

53  Yellowin Access Road: Upgrades (L) (H)  SVC        [$40k‐4mo]                                     [$15M‐4yr]                                                

                                               

54  Brungle Road: Upgrades (L)   SVC  50%              [$40k‐3mo]     [$10k‐2mo]                         [$0.8‐2yr]                                                

                                               

55  Courabyra Road: Upgrades (L)   SVC  50%      [$75k‐7mo]                                    [$6M‐3yr]                                                

                                               

56  Rye Park Road (R) (H)  ULSC    

Rye Park Road (R) (H)  ULSC                                    [$18.5‐3.5yr]         [$18.5‐3.5yr]                                                

                                               

57  Tablelands Way Various Sections (R) (H)  ULSC                    [$100k‐9mo]         [250k‐6mo]         [$6.15M‐2.5yr]         [$6.5M3.75]                                                

                                               

58  Wombeyan Caves Road: Upgrades (R)   ULSC                                    [$11.05M‐5yr]         [$11.05M‐5yr]                                                

                                               

59  Grabine Road: Upgrades (L)   ULSC                                    [$4.25M‐2yr]         [$4.25M‐2yr]                                                

                                               

60  Moss Vale Bypass: Stages 1‐3 (R) (H)  WSC                        [$850k‐18mo]                     [$50M‐10yr]                                                

                                               

61  Exeter/Bundanoon Road: Upgrades (R) (H)  WSC            [$100k‐12mo]                        [$20M‐8yr]        [$20M‐8yr]                                                

                                               

62  Old South Road: Upgrades (L)   WSC  15%          [$250k‐12mo]                        [$25M‐6yr]        [$25M‐6yr]                                                

                                               

63  Holbrook Road: Reconstruction (R) (H)  WWCC                     [$150k‐2yr]                        [$37.3M‐6yr]                                                

                                               

64  Tumbarumba Road: Upgrades (R) (H)  WWCC                            [$450k‐2yr]                 [$16.6M‐4yr]                                                

                                               

65  Byrnes Road: Upgrades (L) (H)  WWCC                            [$300k‐2yr]                 [$8M‐3yr]                                                

                                               

66  Inglewood Road: Upgrades (L) (H)  WWCC                [$50k‐1yr]                            [$5.2M‐3yr]                                              

                                               

67  Glenfield Road: Upgrades (L) (H)  WWCC                            [$500k‐2yr]                 [$20.2M‐3yr]                                              

                                               

68  Farrar Road: Upgrades (L)   WWCC                                [$75k‐1yr]             [$7.9M‐3yr]                                              

                                               

69  Lake Albert Road: Reconstruction (L)   WWCC                             [$50k‐2yr]                 [$18.2M‐3yr]                                              

                                               

                                               

70  Gregadoo Road: Reconstruction (L)   WWCC                                [$200k‐1yr]             [$6.04M‐4yr]                                              

                                               

71  Ivan Jack Drive: Reconstruction (L)   WWCC                                 [$20k‐1yr]             [$6.4M‐4yr]                                                

                                               

72  Macleay Street: Reconstruction (L) ()  WWCC                             [$75k‐1yr]                 [$3.4M‐2yr]                                                

                                               

73  Mulligans Flat Road: Upgrades (R) (H)  YVC  25%          [$250k‐6mo]    [$25k‐3mo]                             [$0.275M]*                                                

                                               

74  Namima Road: Upgrades (L) H  YVC  25%          [$50k‐6mo]    [$25k‐3mo]                            [$0.75]*                                                

                                               

 

Page 6: Road and Bridge Register - crjo.nsw.gov.au · to assist Councils move one step closer to being Shovel‐Ready to deliver on 140 road and bridge projects. For example, a commitment

 

 

CANBERRA REGION JOINT ORGANISATION 

Delivery Framework 

 

    

IDENTIFY  PLAN  DEVELOP  DELIVER  CLOSE        

 

  

  

  

  

  

  

  

  

     

  Road Projects [1‐3 Year Priority]    Phase  

      

  

      

      

  

    

     

      

  

      

      

  

      

   Framework

Stages Identify &

Define Brief Options Study Site Assessment Concept Design

Planning & Approvals

Design &

Specification

Construction Procurement

Construction

Delivery

Finalise Contracts

Close Out        

 

      

  

      

      

  

     

#  Project  Council % Council 

contributes to next stage 

   [Cost ‐ Time] to Next Stage 

 [Cost ‐ Time] to Next Stage 

 [Cost ‐ Time] to Next Stage 

 [Cost ‐ Time] to Next Stage 

         [Cost ‐ Time] 

to Shovel‐Ready          

[Total Cost ‐ Total Time] 

                                                 

75  Yass Valley Way: Upgrades (R)   YVC  25%          [$200k‐12mo]    [$75k‐3mo]                             [$0.275M]*                                                

                                               

 Road Projects [4‐10 Yr Priority] 76  Guardrail: Replacement (R)   BVSC                [$50k‐6mo]                     [$2M‐10yr]        [$2M‐10yr] 

                                               

                                               

77  Bermagui‐Tathra Road: Upgrades (R)   BVSC                [$150k‐3mo]                     [$2.5M‐2yr]        [$3M‐4yr]                                                

                                               

78  Lamont St Bermagui: Revitalisation Project (R)   BVSC            [$100k‐18mo]                        [$10M‐5yr]        [$10M‐5yr]                                              

                                               

79  Carp St Bega: Revitalisation Project (R)   BVSC            [$100k‐24mo]                        [$2M7yr]        [$5M‐7yr]                                                

                                               

80  Mountain Ash Road: Upgrades (L) ()  GMC  50%              [$100k‐6mo]     [$100k‐6mo]                        [$7.33M‐4yr]                                                

                                               

81  Bungendore Road (R) H  QPRC            [$200k‐15mo]                                [$26M‐5yr]                                              

                                               

82  Cooma Street Queanbeyan (R) ()  QPRC            [$200k‐15mo]                                [$21M‐5yr]                                                

                                               

83  Badja Road: Upgrades (R) (H)  SMRC  15%          [$67k‐6mo]                [$334k‐12mo]        [$9.2M‐2yr]        [$10M‐3.5yr]                                                

                                               

84  Dalgety Road: Upgrades (R) (H)  SMRC  10%          [$39k‐6mo]                [$192k‐6mo]        [$3.6M‐24mo]        [$3.9M‐3yr]                                                

                                               

85  Countegany Road: Upgrades (R) H  SMRC  10%          [$50.5k‐6mo]                [$252k‐6mo]        [$4.7M‐24mo]        [$5.1M‐3yr]                                                

                                               

86  Numeralla Road: Upgrades (L)   SMRC  10%                          [$423k‐6mo]        [$7.95M‐24mo]         [$8.5M‐3yr]                                                

                                               

87  Wheeo Road: Upgrades (L)  ULSC                                    [$4.2M‐12mo]         [$4.2M‐1yr]                                                

                                               

88  Reids Flat Road (L)   ULSC                                    [$12.75M‐2yr]         [$12.75M‐2.5yr]                                                

                                               

89  Alternate Route Collector Rd: Upgrades (L)  ULSC                                     [$15.39‐4.5yr]         [$15.39M‐4.5yr]                                                

                                               

90  Peelwood Road (L)   ULSC                            [$200k‐6mo]         [$14.8M‐5yr]        [$15M‐5.5yr]                                                

                                               

91  Breadalbane Road: Flood Damage (L) ()  ULSC                             [$200k‐6mo]         [$3.8M‐2yr]        [$4M‐2.5yr]                                              

                                               

92  Bowral Distributor Road: Stage 2 (R) (H)  WSC                                    [$15M‐4yr]         [$15M‐5yr]                                                

                                               

93  Berrima Road/Taylor Avenue: Upgrades (R) (H)  WSC            [$125k‐12mo]                        [$17.5M‐5yr]        [$17.5M‐6yr]                                                

                                               

94  Penrose Road: Upgrades (R) (H)  WSC            [$200k‐12mo]                        [$30M‐5yr]        [$30M‐6yr]                                                

                                               

95  Nowra Road: Upgrades (R) H  WSC            [$250k‐12mo]                         [$35M‐5yr]        [$35M‐6yr]                                                

                                               

96  Wilson Drive: Upgrades (L)   WSC                            [$225k‐12mo]         [$15M‐4yr]        [$15M‐5yr]                                                

                                               

97  Range Road: Upgrades (L) ()  WSC            [$100k‐12mo]                        [$16M‐4yr]        [$16M‐5yr]                                              

                                               

98 Murrumbateman Road/Shingle Hill Road: Upgrades (R) (H) 

YVC  25%          [$100k‐6mo]    [$50k‐3mo]                            [$0.15M]* 

                                               

                                                 

99  Dog Trap Road: Extension (L) H  YVC  25%          [$250k‐6mo]    [$25k‐3mo]                            [$0.275M]*                                                

                                               

100  Wee Jasper Road: Upgrades (R)   YVC  25%          [$150k‐9mo]    [$75k‐3mo]                             [$0.225M]*                                                

                                               

101  Euroka Avenue: Upgrades (L)   YVC  25%          [$50k‐6mo]    [$25k‐3mo]                             [$0.75]*                                                

 Road Projects [10‐20 Yr Priority] 102  Oallen Ford Road (L) (H)  QPRC            [$300k‐12mo]         [$800k‐18mo]    [$300k‐6mo]    [$3.5M‐12mo]                [$63M‐4yr] 

                                               

    

Page 7: Road and Bridge Register - crjo.nsw.gov.au · to assist Councils move one step closer to being Shovel‐Ready to deliver on 140 road and bridge projects. For example, a commitment

 

 

CANBERRA REGION JOINT ORGANISATION 

Delivery Framework 

 

    

IDENTIFY  PLAN  DEVELOP  DELIVER  CLOSE        

 

  

  

  

  

  

  

  

  

     

  Bridge Projects [1‐3 Yr Priority]    Phase  

      

  

      

      

  

    

     

      

  

      

      

  

      

   Framework

Stages Identify &

Define Brief Options Study Site Assessment Concept Design

Planning & Approvals

Design &

Specification

Construction Procurement

Construction

Delivery

Finalise Contracts

Close Out        

 

      

  

      

      

  

     

#  Project  Council % Council 

contributes to next stage 

   [Cost ‐ Time] to Next Stage 

 [Cost ‐ Time] to Next Stage 

 [Cost ‐ Time] to Next Stage 

 [Cost ‐ Time] to Next Stage 

         [Cost ‐ Time] 

to Shovel‐Ready          

[Total Cost ‐ Total Time] 

                                                 

103  Whipstick Creek Bridge: Replacement (R) (H)  BVSC                            [$55k‐1mo]         [$1.1m‐6mo]        [$1.2M‐9mo]                                                

                                               

104  BVSC Bridges: Replacement (1‐3yr package) (R) (H)  BVSC                            [$250k‐12mo]        [$10M‐3yr]        [$10.05M‐3yr]                                                

                                               

105  Cuttagee Bridge: Upgrades (R) (H)  BVSC            [$250k‐6mo]                        [$14M‐3yr]        [$12‐$15M‐4yr]                                                

                                                 

106  Pericoe Creek Bridge: Replacement (L)   BVSC                            [$15k‐1mo]        [$115k‐3mo]        [$0.13M‐3mo]                                              

                                               

107  Slaters Lane Bridge: Replacement (L)   BVSC                        [$25k‐3mo]             [$290k‐1yr]        [$0.3M‐1.5yr]                                                

                                               

108  Garlandtown Bridge: Upgrades (R)   ESC  35%                          [$150k‐6mo]        [$950k‐10mo]        [$1.1M‐2yr]                                                

                                                 

109  May Street Bridge: Replacement (L)   GMC                                     [$1.6M‐1yr]         [$1.7M‐1yr]                                                

                                               

110  Towrang Bridge: Replacement (L)   GMC                            [$150k‐4mo]                [$4.2M‐2yr]                                                

                                               

111  Resch's Crossing (L)   QPRC                                    [$1.8M‐2yr]        [$1.8M‐2yr]                                                

                                                 

112  Peak Creek Bridge: Replacement (R) (H)  SMRC  50%          [$50k‐3mo]        [$25k‐3mo]        [$100k‐6mo]        [$700k‐12mo]        [$0.9M‐2yr]                                              

                                               

113  Delegate River Bridge: Replacement (R) (H)  SMRC  25%          [$50k‐3mo]        [$50k‐3mo]        [$100k‐6mo]        [$1.8M‐12mo]        [$2M‐2.25yr]                                              

                                               

114  Numeralla River Bridge: Upgrades (L)   SMRC  15%          [$50k‐3mo]        [$50k‐6mo]        [$120k‐6mo]        [$980k‐12mo]        [$1.2M‐2yr]                                                

                                                 

115  Sherlock River Bridge: Upgrade/Replacement (L)   SMRC  15%          [$50k‐3mo]        [$50k‐6mo]        [$200k‐12mo]        [$3M‐12mo]        [$3.3M‐2.5yr]                                                

                                               

116  Jacksons Bridge: Replacement (S) (H)  SVC             [$50k‐6mo]                                [$12M‐3yr]                                                

                                               

117  Wingecarribee Street Bridge: Duplication (L) (H)  WSC            [$400k‐12mo]                        [$12M‐4yr]        [$12M‐4yr]                                              

                                                 

118  Lockhart Road: Culvert Replacement (R) (H)  WWCC                    [$25k‐6mo]                        [$1.05M‐1yr]                                                

                                               

119  Burkes Creek Bridge: Upgrades (R) (H)  WWCC                [$20k‐6mo]                            [$0.45M‐3yr]                                                

                                               

120  Umbango Creek Bridge: Upgrades (L) (H)  WWCC                        [$50k‐6mo]                     [$0.75M‐1yr]                                                

                                                 

121  Tooles Creek Bridge: Upgrades (L) (H)  WWCC                    [$30k‐6mo]                        [$0.75M‐2yr]                                                

                                               

122  Beavers Creek Bridge: Upgrades (R)   WWCC                [$20k‐12mo]                            [$0.75M‐3yr]                                                

                                               

123  Brooklynn Lane Bridge: Replacement (L)   WWCC            [$25k‐12mo]                                [$0.45M‐3yr]                                              

                                               

124  Mona Vale Road Bridge: Replacement (L)   WWCC            [$25k‐12mo]                                [$0.45M‐3yr]                                              

                                                 

125  Wollundry Lagoon Bridge: Upgrades (L)   WWCC                                    [$750k‐12mo]         [$0.75M‐2yr]                                                

                                               

126  Big Springs Road: Culvert Replacement (L)   WWCC            [$25k‐18mo]                                [$0.75M‐2yr]                                              

                                                 

127  Bulloc Hills Road Bridge: Replacement (L)   WWCC            [$25k‐12mo]                                [$0.45M‐3yr]                                                

Page 8: Road and Bridge Register - crjo.nsw.gov.au · to assist Councils move one step closer to being Shovel‐Ready to deliver on 140 road and bridge projects. For example, a commitment

 

 

CANBERRA REGION JOINT ORGANISATION 

Delivery Framework 

 

    

IDENTIFY  PLAN  DEVELOP  DELIVER  CLOSE        

 

  

  

  

  

  

  

  

  

     

  Bridge Projects [4‐10 Yr Priority]    Phase  

      

  

      

      

  

    

     

      

  

      

      

  

      

   Framework

Stages Identify &

Define Brief Options Study Site Assessment Concept Design

Planning & Approvals

Design &

Specification

Construction Procurement

Construction

Delivery

Finalise Contracts

Close Out        

 

      

  

      

      

  

     

#  Project  Council % Council 

contributes to next stage 

   [Cost ‐ Time] to Next Stage 

 [Cost ‐ Time] to Next Stage 

 [Cost ‐ Time] to Next Stage 

 [Cost ‐ Time] to Next Stage 

         [Cost ‐ Time] 

to Shovel‐Ready          

[Total Cost ‐ Total Time] 

                                                                                                

128  Tathra Wharf: Renewal (State Owned) (State)   BVSC                    [$150k‐6mo]                [$10M‐1yr]        [$10M‐10yr]                                                

                                               

129  BVSC Bridges: Replacement (4‐10yr package) (R)   BVSC                [$125k‐12mo]                     [$10m‐10yr]        [$10.2M‐10yr]                                                

                                               

130  Thornford Bridge: Replacement (L)   GMC            [$50k‐3mo]    [$50k‐3mo]                            [$0.7M‐3yr]                                                

                                               

131  Carrick Road Bridge: Replacement (L)  GMC            [$50k‐3mo]    [$50k‐3mo]                            [$0.9M‐3yr]                                                

                                                 

132  Foxlow Bridge (L)   QPRC                                            [$3.6M‐2yr]                                              

                                               

133  Badja River Bridge: Upgrade (R) (H)  SMRC  15%          [$50k‐3mo]        [$50k‐6mo]        [$200k‐12mo]        [$3M‐12mo]        [$3.3M‐2.5yr]                                                

                                               

134  Queanbeyan River Bridge: Upgrades (L)   SMRC  50%          [$50k‐3mo]        [$30k‐3mo]        [$100k‐6mo]        [$800k‐12mo]        [$0.97M‐1.75yr]                                                

                                               

135  ULSC Bridges: Replacement (4‐10yr package) (L)   ULSC                            [$700k‐12mo]         [$10.3M‐10yr]        [$11M‐11yr]                                                

                                               

136  Burrinjuck Road Bridge: Replacement (R) (H)  YVC  50%          [$20k‐6mo]    [$25k‐3mo]                            [$0.045]*                                                

                                                 

137 Burrinjuck Road Bridge: Replacement (Childowa Trail) (R) (H) 

YVC  50%          [$20k‐6mo]    [$25k‐3mo]                            [$0.045]* 

                                               

                                               

138  Bango Lane Bridge: Replacement (L)   YVC  50%          [$20k‐6mo]    [$25k‐3mo]                             [$0.045]*                                              

                                               

139  Garryowen Road Bridge: Replacement (L)   YVC  50%          [$20k‐6mo]    [$25k‐3mo]                             [$0.045]*                                                

 

 Bridge Projects [10‐20 Year Priority] 140  BVSC Bridges: Replacement (10‐20yr package) (R)   BVSC            [$250k‐12mo]                        [$10M‐20yr]        [$10.3M‐20yr] 

                                               

  * refers to a project that does not have a total close out cost or cost to commission (L) Local Road (R) Regional Road (S) State Road (H) Heavy Vehicles Road    

     

KEY – PROJECT STATUS  

 Under preparation  

Funding Required, Submitted, Awaiting Funding 

Completed 

Declined Funding*  

Page 9: Road and Bridge Register - crjo.nsw.gov.au · to assist Councils move one step closer to being Shovel‐Ready to deliver on 140 road and bridge projects. For example, a commitment

 

 

CANBERRA REGION JOINT ORGANISATION 

Project Data 

 

    

   

Project  Council Road 

Number(s)   Road Name(s)  Project Description  Electorate 

State / Federal 

AADT 

Vehicles / Heavy Vehicles 

                     

1  Port of Eden: Upgrades  BVSC      Mitchell St, Calle Calle St, Chandos St, Albert Terrace, 

Weecoon St 

  Upgrade of the intersection of Imlay Street/Albert Terrace including bus drop off for two buses on Imlay Street, upgrade of the intersection of Albert Terrace/Museum Street, upgrade of Albert Terrace between Imlay Street and Weecoon Street including; Construction of a 1.5M auxiliary lane for prospective cycleway of tourist ‘road trains’. Construction of four new pedestrian platforms for an interactive walk along Albert Terrace. Installation of stairs leading from Albert Terrace to Eden Whale Museum. Replacement of rock retaining wall at Albert Street, south of Imlay Street/Albert Street intersection. 3m shared pathway on the eastern side of Albert Street. Upgrade of inlet to stormwater pits along Albert Street. Upgrade of Chandos Street, Calle Calle Street and Mitchell Street for a Heavy Vehicle Route bypassing Eden town centre. Landscaping works. Development of an historic interpretive walk. 

  Bega / Eden Monaro   1917 (2017) / 167 (2017) 

2  Towamba and Burragate Roads: Sealing  BVSC      Towamba Rd, Burragate Rd 

  Seal the remaining 25km of gravel road on Towamba and Burragate Roads.    Bega / Eden Monaro    140 (2017) / 11 (2017) 

3  Tantawangalo Mountain Road: Sealing  BVSC      Tantawangalo Mountain Rd 

  Seal 1.6km of gravel road between the two sealed sections on Tantawangalo Mountain Road.    Bega / Eden Monaro    177 (2018) / 24 (2018) 

4  Tathra Public School: Traffic Safety Upgrades  BVSC      Bega St    Reform entrance to Tathra Public School, to include parking formalisation, signage, bus stop, and pathways (which are to link to the Tathra to Kalaru Bike Track). 

  Bega / Eden Monaro   5391 (2018) / 412 (2018) 

5  Sapphire Coast Drive: Realignment  BVSC      Sapphire Coast Drive, Berrambool 

Drive 

  Sapphire Coast Drive/Berrambool Drive realignment forms the northern approach to Merimbula. It is one of three access points into the key activity centre of Merimbula. It is currently a T‐intersection with the priority to Berrambool Drive. Project is to re‐align intersection so that Sapphire Coast Drive has right of way over Berrambool Drive. 

  Bega / Eden Monaro    9453 (2007) /  

6  Wolumla Public School: Traffic Safety Upgrades  BVSC      Bega St    Concrete footpath from the school main entrance on top of the bank to Bellbird Court. Concrete footpath Bellbird Court. Pedestrian fence full length of Bega Street where new footpath goes in. Footpath from main entrance 50m to the north east to the bus set down facility. Edgelines full length of school frontage on Bega Street. Two speed control devices on Bega Street. VAS signs both ends. 

  Bega / Eden Monaro    635 (2018) / 72 (2018) 

7  Doctor George Mountain Road: Sealing  BVSC      Doctor George Mountain Rd 

  Seal 11.1km of gravel road.    Bega / Eden Monaro    165 (2017) / 20 (2017) 

8  Market Street Merimbula CBD: Revitalisation  BVSC          Refer to the recent submission. The upgrade requirements have identified with a landscape master plan to address the tired infrastructure. The works include active transport improvements and safe crossing facilities improving traffic flows specially the commercial vehicles. 

  Bega / Eden Monaro       

9  Beach Road Intersections: Upgrades  ESC  MR560    Beach Rd, Pacific St and Herarde St 

  Install CHR intersections including pedestrian activated traffic signals at Pacific Street, central median/traffic islands, services relocation, land acquisition, stormwater, pavement and bitumen seal. 

  Bega / Gilmore    15330 (2017) / 613 (2017) 

10  George Bass Drive: Duplication of Lanes  ESC  MR7630    George Bass Drive    Construct 1000m of additional lane to create two lanes in both directions including earthworks, kerb and gutter, stormwater, pavement construction and new bitumen seal. 

  Bega / Gilmore   5598 (2013) / 391 (2013) 

11  George Bass Drive/Grandfathers Gully: Realignment  ESC  MR7630    George Bass Drive    Realign 1100m of road including clearing, earthworks, land acquisition, services relocation, stormwater, pavement construction and new bitumen seal. 

  Bega / Gilmore   4981 (2017) / 349 (2017) 

12  Beach Road: Installation of Central Median  ESC  MR560    Beach Rd    Install central median 630m of road including services relocation, widening of pavement, stormwater, new kerb and gutter and bitumen seal. 

  Bega / Gilmore    17995 (2017) / 720 (2017) 

13  George Bass Drive: Upgrades  ESC  MR7630    George Bass Drive    Widen, strengthen and improve safety to 1000m of road including service relocation, roundabouts, restricted right turns, shared pathway, 600m median, new pavement and bitumen seal. 

  Bega / Gilmore   4039 (2012) / 282 (2012) 

14  Eurobodalla Road: Upgrades  ESC      Eurobodalla Rd    Widen and strengthen 800m of road including kerb and gutter, footpath, stormwater and new bitumen seal.    Bega / Eden Monaro    497 (2013) / 94 (2013) 

15  ESC High Priority Pathways: New Construction  ESC      Various    High priority pathways identified from the Eurobodalla Pathways Strategy 2017. Footpaths and shared pathways providing strategic connectivity to commercial, recreational, cultural and education centres and to integrate with public and school transport. The pathways selected are limited to those with a significant road safety benefit, separating pedestrians and young cyclists from vehicular traffic on the busiest roads in the Shire. 

  Bega / Gilmore/Eden Monaro   2000 (2018) / 140 (2018) 

16  Moruya Town Centre: Pedestrian Activation  ESC      Ford St, Queen St, Church St and 

Shore St 

  Design and install speed controls and pedestrian crossing points.    Bega / Gilmore   7737 (2018) / 387 (2018) 

17  Dunns Creek Road: Safety Improvements  ESC      Dunns Creek Rd    Safety improvements to 4350m of road including linemarking, CAMS's, signage, provision of sealed shoulder, improving clear zones and guardrail. 

  Bega / Gilmore    1957 (2013) / 78 (2013) 

18  Orient Street CBD Intersections: Upgrades  ESC      Orient St, Camp St and Museum Place 

  Signalise and realign intersection including islands, service relocation, earthworks, land acquisition, kerb and gutter, signals, pavement and asphalt surface. 

  Bega / Gilmore   3863 (2013) / 154 (2013) 

19  Gurrundah Road: Upgrades  GMC  0041    Gurrundah Rd    Rehabilitate damaged pavement and widen the road to achieve a 9m formation with 8m seal for the 17.4km length.    Goulburn / Hume    651 (2017) / 78 (2017) 

20  Bungonia Road: Upgrades  GMC  0451    Bungonia Rd    Road widening and overlay of 595m length road section between Lansdown Bridge and Braidwood Road intersection, including footpath, kerb and gutter, culvert extension and elevated road level to cater for 1 in 5 flood event. 

  Goulburn / Hume   2131 (2016) / 130 (2016) 

21  Range Road: Upgrades  GMC  0128    Range Rd    Widening and rehabilitation of entire length from 0.212km to 20.278km which is about 19.8km of haulage route.    Goulburn / Hume    607 (2017) / 65 (2018) 

22  Windellama Road: Upgrades  GMC  0042    Windellama Rd    Rehabilitate damaged pavement and widen the road to achieve a 9m formation with 8m seal for the 37km length.    Goulburn / Hume   1658 (2017) / 162 (2017) 

23  Oallen Ford Road: Upgrades  GMC  0024    Oallen Ford Rd    Road widening and rehabilitation work, starting from Windellama Road intersection up to Sandy Point Road intersection length of 4.77km including replacement of bridge size culvert/causeway at 24.4km from Windellama Road intersection. 

  Goulburn / Hume    1282 (2017) / 86 (2017) 

Page 10: Road and Bridge Register - crjo.nsw.gov.au · to assist Councils move one step closer to being Shovel‐Ready to deliver on 140 road and bridge projects. For example, a commitment

 

 

CANBERRA REGION JOINT ORGANISATION 

Project Data 

 

    

10 

 Project  Council 

Road Number(s) 

  Road Name(s)  Project Description  Electorate 

State / Federal 

AADT 

Vehicles / Heavy Vehicles 

                     

24  Lumley Road : Upgrades  GMC  RD112    Lumley Rd    Widening and rehabilitation of entire length from 33km to 37.771km which is about 5km of haulage route.    Goulburn / Hume    770 (2017) / 45 (2017) 

25  Cullulla Road: Upgrades  GMC  RD33    Cullulla Rd    Widening and rehabilitation of entire length from 0km to 37.771km which is about 37.77km of haulage route.    From Lumley / Hume    818 (2017) / 100(2017) 

26  Sandy Point Road: Upgrades  GMC  RD95    Sandy Point Rd    Widening and rehabilitation of entire length from 10.86km to 16.5km which is about 5.64km of haulage route.    Goulburn / Hume    794 (2017) / 60 (2017) 

27  Lachlan Valley Way: Upgrades  HC  MR56    Lachlan Valley Way    Improve the road alignment and road width, provide heavy vehicle passing bays, traffic safety improvements and pavement strengthening, project length 44km. 

  Cootamundra & Goulburn / Riverina/Hume 

 3000 (2017) / 390 (2017) 

28  Murringo Road: Upgrades  HC  RR241    Murringo Rd: Shoulder 

  Widen the road shoulders and seal 1m shoulders each lane, pavement strengthening 22km, five bridge replacements to HML vehicle capacity, project length 49km. 

  Cootamundra & Goulburn / Riverina/Hume 

 1221 (2016) / 232 (2016) 

29  Jugiong Road Bypass: Upgrades  HC  RR381    Jugiong Rd    Widen the road shoulders and seal 1m shoulders each lane 20km, pavement strengthening 20km, guardrail install at curves and drop‐offs. Two bridge replacements to HML vehicle capacity, project length 20km. Hume Highway acceleration lane off Riverside Drive (south). 

  Cootamundra & Goulburn / Riverina/Hume 

  387 (2016) / 34 (2016) 

30  Chews Lane Bypass: Upgrades  HC  66    Chews Lane, part    Widen the road shoulders and seal 1m shoulders each lane 14km, pavement strengthening 14km, guardrail install at curves and drop‐offs, one bridge replacement to HML vehicle capacity, project length 14km. 

  Cootamundra & Goulburn / Riverina/Hume 

  173 (2015) / 17 (2015) 

31  Henry Lawson Way: Upgrades  HC  RR3239    Henry Lawson Way    Shoulder widening, 26km of pavement strengthening, four bridge replacements and major culverts to HML vehicle capacity, traffic safety improvements, project length 26km. 

  Cootamundra & Goulburn / Riverina/Hume 

     

32  Bribbaree Road: Upgrades  HC  70    Bribbaree Rd    Widen the road shoulders and seal 1m shoulders each lane 42km, pavement strengthening 42km, 3 x bridge replacement to HML vehicle capacity, project length 42km. 

  Cootamundra & Goulburn / Riverina/Hume 

  251 (2014) / 36 (2014) 

33  Mahons Reef Road: Upgrades  HC      McMahons Reef Rd    Widen the road shoulders and seal 1m shoulders each lane 35km, bitumen seal full length 35km, pavement strengthening 35km, guardrail install at curves and drop‐offs and bridge replacement to HML vehicle capacity, project length 35km. 

  Cootamundra & Goulburn / Riverina/Hume 

  112 (2017) / 35 (2017) 

34  Nerriga Road  QPRC  MR92        Pavement rehabilitation from Nerriga‐Corang River, widening and rehabilitation from Oallen Road to Nerriga Widening and rehabilitation from MR51‐Halls Lane. 

  Monaro / Eden Monaro    1210(2018) / 108(208) 

35  Captains Flat: Road Realignment and upgrade  QPRC  MR72        Realign and widen road to allow for 100km/h alignment. Replace bridges to allow for 11m wide road and shoulder.    Monaro / Eden Monaro   1070 (2018) / 401 (2018) 

36  Bungendore Bypass  QPRC          Bypass.    Monaro / Eden Monaro       

37  Braidwood Bypass  QPRC          Bypass.    Monaro / Eden Monaro       

38  Braidwood Mainstreet: Upgrade  QPRC  HW51    Kings Hwy    Mainstreet upgrade and construction of a car park to accommodate approximately 180 (TBC) vehicles to increase parking capacity of the town, relocate Councils depot to locate the carpark. Redevelop some of the land to assist with funding the project. 

  Monaro / Eden Monaro    5072 (2017) / 598 (2017 

39  Williamsdale Road  QPRC          Seal Williamsdale Road and realign vertical and horizontal curves to allow a 100km/h speed limit. Replace the low level crossing at the Burra end of Williamsdale Road to reduce flood impacts on the road. 

  Monaro / Eden Monaro    356 (2018) / 36 (2018) 

40  Burra Bends extension  QPRC          Widen and realign road to allow 100km/h vertical and horizontal alignment and install safety barriers as required.    Monaro / Eden Monaro    1072 (2018) / 49 (2018) 

41  Black Lake Road: Upgrades  SMRC  MR563    Black Lake Rd    Widen and realign formation for 9.5km to regional road standards, improve drainage as required, overlay 200mm DGB20 road base, primer seal 9.5km x 10mm primer and final seal 9.5km x 14mm C240. 

  Monaro / Eden Monaro    Currently collecting data  

42  Middlingbank Road: Upgrades  SMRC  MR585    Middlingbank Rd    Widen and realign formation for 30.86km to regional road standards, improve drainage as required, overlay 200mm DGB20 road base, primer seal 30.86km x 10mm, final seal 30.86km x 14mm C240. 

  Monaro / Eden Monaro    156 (2016) / 6 (2016) 

43  The Snowy River Way: Upgrades  SMRC  MR7626/394    Snowy River Way    Widen and realign formation for 14km to regional road standards, overlay 150mm DGB 20 road base, primer seal 14km x 10mm primer, final seal with 14mm C240. 

  Monaro / Eden Monaro    267 (2015) / 39 (2015) 

44  Polo Flat Road: Upgrades  SMRC  MR7624    Polo Flat Rd    Overlay Road 150mm DGB20 for 4km, stabilise road with 60/40 slag lime, place 7mm primer for 4km and place AC50mm for 4km. 

  Monaro / Eden Monaro    Currently collecting data  

45  Cathcart Road: Upgrades  SMRC  MR91    Cathcart Rd    Widen and realign formation to meet regional road standards 11km, overlay 200mm DGB 20 road base, primer seal 11km x 10mm, final seal with 14mm C241. 

  Monaro / Eden Monaro    Currently collecting data  

46  Barry Way: Upgrades  SMRC  MR4056    Barry Way    Realign road to meet Collector road standards for 29km, improved drainage, overlay 100mm DGB 20 road base, primer seal 29km x 10mm, final seal with 14mm C240. 

  Monaro / Eden Monaro    1230 (2014) / 33 (2014) 

47  Jerangle Road: Upgrades  SMRC      Jerangle Rd    Widen and realign formation to meet Collector road standards 53km, overlay 200mm DGB 20 road base, primer seal 53km x 10mm, final seal with 14mm C240. 

  Monaro / Eden Monaro    159 (2017) / 19 (2017) 

48  Snowy Mountains Highway: Overtaking Lanes  SVC      Snowy Mountains Hwy 

  Widen road and seal 1m shoulders, new seal across the entire length. 28km of new seal and 150km shoulder widening.    Wagga Wagga / Eden Monaro      

49  Tumbarumba: Heavy Vehicle Bypass  SVC      Tumbarumba Township 

  Heavy Vehicle bypass route feasibility study, investigation, costing and implementation to remove heavy vehicles (including HML) from the Main Street of the town. 

  Albury / Eden Monaro       

50  Batlow Road: Climbing Lanes  SVC      Batlow‐Tumbarumba Rd 

  Creation of climbing lanes on the Batlow Road (MR85) to allow safe opportunity for traffic to negotiate timber haulage traffic. 

  Wagga Wagga / Eden Monaro      

51  Snowy Mountains Highway: Upgrades  SVC          Realignment of corners to improve safety and widening to consistent width.    Wagga Wagga / Riverina       

52  Tooma Road: Upgrades  SVC      Tooma Rd: Increased 

  Widen road to 8m seal, 9m formation and overlay of pavement with 150mm gravel from Maragle Road to Alpine Way. Strengthen deteriorating B‐Double route pavement. 

  Albury / Eden Monaro       

53  Yellowin Access Road: Upgrades  SVC  MR85    Yellowin Access Rd    Pavement strengthening and sealing of the Yellow Access Road (21km) from Batlow to Talbingo.    Wagga Wagga / Eden Monaro      

54  Brungle Road: Upgrades  SVC      Brungle Rd    Improvement of alignment, site distance and road width (to minimum 7m seal) from Wee Jasper Road to Brungle.    Wagga Wagga / Riverina      

55  Courabyra Road: Upgrades  SVC      Courabyra Rd    Overlay of 150mm and widening to 8m to allow for HML vehicle access and removal of weight restriction for 22km.    Albury / Eden Monaro       

Page 11: Road and Bridge Register - crjo.nsw.gov.au · to assist Councils move one step closer to being Shovel‐Ready to deliver on 140 road and bridge projects. For example, a commitment

 

 

CANBERRA REGION JOINT ORGANISATION 

Project Data 

 

    

11 

 Project  Council 

Road Number(s) 

  Road Name(s)  Project Description  Electorate 

State / Federal 

AADT 

Vehicles / Heavy Vehicles 

                     

56  Rye Park Road  ULSC          Corridor widening to 12m (21.76km), pavement strengthening, compaction, seals line making and sings in addition to some minor rectification of horizontal and vertical curves. 

  Goulburn / Hume    126 (2017) / 13 (2017) 

57  Tablelands Way Various Sections  ULSC          Realignment of Curraweela Creek causeway with installation box culvert and elevated road pavement, corridor widening 10m and slope stabilization over decline to Abercrombie River (6.5km). 

  Goulburn / Hume    301 (2018) / 135 (2018) 

58  Wombeyan Caves Road: Upgrades  ULSC      Grabine Rd    Corridor widening to 10m on ridge (9km) and 7m over decline (4km), pavement strengthening, compaction, seals line making and sings in addition to some minor rectification of horizontal and vertical curves. 

  Goulburn / Hume    166 (2013) / 4.05 (2013) 

59  Grabine Road: Upgrades  ULSC      Various    Corridor widening to 7m (5.7km), pavement strengthening, compaction, seals, signs in addition to some minor rectification of horizontal and vertical curves, remove of gates with bypasses and fencing out road reserve. 

  Goulburn / Hume    82 (2018) / 19 (2018) 

60  Moss Vale Bypass: Stages 1‐3  WSC  MR260    Moss Vale Bypass    Construction of 3.3 km of new road, a railway overbridge and eight roundabouts.    Goulburn/Wollondilly / Whitlam/Hume 

 6320 (2015) / 700 (2015) 

61  Exeter/Bundanoon Road: Upgrades  WSC  MR569    Bundanoon and Exeter Rds 

  Pavement reconstruction, widen road and place new seal, including 1m shoulder over entire length. 10 km from Sutton Forest to Bundanoon. 

  Goulburn/Wollondilly / Whitlam/Hume 

 3453 (2016) / 350 (2016) 

62  Old South Road: Upgrades  WSC  1587    Old South Rd    Pavement reconstruction, widen road and place new seal, including 1m shoulder over entire length. 12.7 km from Merrigang Street to Old Hume Hwy. 

  Goulburn/Wollondilly / Whitlam/Hume 

 5887 (2016) / 300 (2016) 

63  Holbrook Road: reconstruction  WWCC  1154    Holbrook Rd    30km total. Construction of new pavement and increased width, formalised gravel shoulders and roadside drainage. Intersection improvements for rural freight and associated vehicles. 

  Wagga Wagga / Riverina   1021 (2018) / 201 (2018) 

64  Tumbarumba Road: Upgrades  WWCC  575    Tumbarumba Rd    11.5km total length. Complete upgrade and reconstruction of roadway within section nominated, includes new vertical and horizontal alignment as per design. Construction of heavy duty pavement to support heavy freight and significant roadside drainage provisions considering surrounding environment and terrain. 

  Wagga Wagga / Riverina    481 (2013) / 140 (2013) 

65  Byrnes Road: Upgrades  WWCC  4038    Byrnes Rd    13.2km total length. Construction of new pavement and increased width, formalised gravel shoulders and roadside drainage. Intersection improvements for surrounding industrial precinct and associated heavy plant. 

  Wagga Wagga / Riverina   2422 (2015) / 460 (2015) 

66  Inglewood Road: Upgrades  WWCC  350    Inglewood Rd    2.4km total length. Construction of new pavement and increased width, formalised gravel shoulders and roadside drainage.    Wagga Wagga / Riverina   2535 (2011) / 127 (2011) 

67  Glenfield Road: Upgrades  WWCC  305    Glenfield Rd    2.3km total length. Road widening (from 10m to 17m) to support two additional 3.5m traffic lanes. New seal over road in its entirety. Project to include formalising roadside drainage and gravel shoulders. 

  Wagga Wagga / Riverina    12466 (2017) / 1384 (2018) 

68  Farrar Road: Upgrades  WWCC  1195    Farrar Rd    1700m total length. Complete upgrade and reconstruction of roadway within section nominated. New vertical and horizontal alignment as per design. Road widening to 10m to support general residential growth within the area and linemarking improvements and bus parking areas for schools within the vicinity. 

  Wagga Wagga / Riverina   2856 (2017) / 268 (2017) 

69  Lake Albert Road: Reconstruction  WWCC  568        3.8km total length. Construction of heavy bound asphaltic pavement within section nominated and intersection improvements to support high traffic volumes and significant growth of the southern suburbs. 

  Wagga Wagga / Riverina   6841 (2018) / 711 (2018) 

70  Gregadoo Road: Reconstruction  WWCC  1016    Gregadoo Rd    3.8km total length. Construction of new pavement and increased width, formalised gravel shoulders and roadside drainage. Construction of slip lanes for adjacent developments and schools and pedestrian refuge islands. 

  Wagga Wagga / Riverina   2728 (2017) / 216 (2017) 

71  Ivan Jack Drive: Reconstruction  WWCC  2677    Ivan Jack Drive    500m total length. Construction of new pavement and kerb and gutter renewal. Two roundabout improvements with Gurwood Street and Johnson Street. Linemarking  improvements to formalise parking areas, cycleways and pedestrian areas. 

  Wagga Wagga / Riverina   8263 (2018) / 190 (2018) 

72  Macleay Street: Reconstruction  WWCC  599    Macleay Rd    800m total length. Construction of new pavement and kerb and gutter renewal. Intersection improvements with Coleman Street and linemarking to formalise parking areas, considering close proximity of schools. 

  Wagga Wagga / Riverina    1630 (2017) / 46 (2017) 

73  Mulligans Flat Road: Upgrades  YVC          New seal and install safety barriers (2.4km).    Goulburn / Eden Monaro    816 (2015) / 69 (2015) 

74  Namima Road: Upgrades  YVC          Widen existing seal, new seal entire width and install safety barriers (13.7km).    Goulburn / Eden Monaro    514 (2016) / 52 (2016) 

75  Yass Valley Way: Upgrades  YVC          Widen existing seal, new seal entire width and install safety barriers (17.3km).    Goulburn / Eden Monaro   6163 (2016) / 795 (2016) 

76  Guardrail: Replacement  BVSC          Replacement of the chain mesh guardrail that does not offer any level of protection for road users.    Bega / Eden Monaro       

77  Bermagui‐Tathra Road: Upgrades  BVSC      Tathra‐Bermagui Rd 

  Pavement lifting and protection from high water sea levels. This is primarily about protection of the north south route as an alternative to the Princes Highway. 

  Bega / Eden Monaro    578 (2013) /  

78  Lamont St Bermagui: Revitalisation Project  BVSC      Lamont St    The seasonal traffic volumes change significantly during holiday periods for both vehicles and active transport users. This revitalisation project will improve access for tourism with modified parking arrangements and locations for active users to navigate the tourist location. There are many safety issues due to the older standard of treatments in Lamont Street which are being addressed in accordance with current levels of funding. Therefore it will be many years before any form of change occurs. The works include active transport improvements and safe crossing facilities. 

  Bega / Eden Monaro   3500 (2017) / 175 (2017) 

79  Carp St Bega: Revitalisation Project  BVSC  MR560    Carp St    The upgrade to the commercial hub of Bega Valley has been identified with a landscape master plan to address the tired infrastructure. The works include active transport improvements and safe crossing facilities. 

  Bega / Eden Monaro   7200 (2017) / 650 (2017) 

80  Mountain Ash Road: Upgrades  GMC  0038    Mountain Ash Rd    Pavement widening with 9m formation (8m seal) and rehabilitation work, starting from 4.5km from Windellama Road intersection up to 22km towards Bungonia. 

  Goulburn / Hume    767 (2017) / 94 (2017) 

81  Bungendore Road  QPRC          1.35km of new road construction to connect Bungendore Road directly to the Kings Hwy via the proposed sporting complex. 8.8km of shoulder widening and developing a full width clear zone. 5.5km of overlay and shape correction plus development of a full width clear zone. Reconstruction of four bridges. 

  Monaro / Eden Monaro    5095 (2018) / 1314 (2018) 

82  Cooma Street Queanbeyan  QPRC  MR584        Cooma Street is one of Queanbeyan's busiest roads however the roadside environment isn't suitable for the traffic demand due to the approx. 144 houses, 2 childcare centres, a primary school, and 19 intersections along it's 1.6km length. The proposed solution for the intersections is to restrictmost intersections to left in left out and install traffic signals at key 

  Monaro / Eden Monaro    15,987 (2017) / 623 (2017) 

Page 12: Road and Bridge Register - crjo.nsw.gov.au · to assist Councils move one step closer to being Shovel‐Ready to deliver on 140 road and bridge projects. For example, a commitment

 

 

CANBERRA REGION JOINT ORGANISATION 

Project Data 

 

    

12 

 Project  Council 

Road Number(s) 

  Road Name(s)  Project Description  Electorate 

State / Federal 

AADT 

Vehicles / Heavy Vehicles 

                     

locations. For the road, full pavement reconstruction is required to create a single lane in each direction separated by a central median, bike lanes and on‐street car parking. 

83  Badja Road: Upgrades  SMRC  MR7624    Badja Rd    Widen and realign formation for 21.2Km to regional road Standards, improve drainage as required, overlay 200mm DGB20 road base, primer seal 21.2km x 10mm primer and final seal 21.2km x 14mm C240. 

  Monaro / Eden Monaro    56 (2012) / 9 (2012) 

84  Dalgety Road: Upgrades  SMRC  MR394    Dalgety Rd    Widen and realign formation to meet regional road standards 9km, overlay 150mm DGB 20 road base, primer seal 9km x 10mm primer, final seal with 14mm C240. 

  Monaro / Eden Monaro    Currently collecting data  

85  Countegany Road: Upgrades  SMRC  MR7624    Countegany Rd    Widen and realign formation to meet regional road standards 11km, overlay 200mm DGB 20 road base, primer seal 11km x 10mm, final seal with 14mm C240. 

  Monaro / Eden Monaro    Currently collecting data  

86  Numeralla Road: Upgrades  SMRC  MR7624    Numberalla Rd    Widen and realign formation to meet regional road standards 19km, overlay 200mm DGB 20 road base, primer seal 19km x 10mm, final seal with 14mm C240. 

  Monaro / Eden Monaro    268 (2007) / 32 (2008) 

87  Wheeo Road: Upgrades  ULSC      Wheeo Rd    Corridor widening to 10m (4.9km), pavement strengthening, compaction, seals line making and sings in addition to some minor rectification of horizontal and vertical curves. 

  Goulburn / Hume    86 (2018) / 18 (2018) 

88  Reids Flat Road  ULSC      Reids Flat Rd    Corridor widening to 7m (15km), pavement strengthening, compaction, seals, signs in addition to some minor rectification of horizontal and vertical curves, remove of gates with bypasses and fencing out road reserve. 

  Goulburn / Hume    42 (2018) / 23 (2018) 

89  Alternate Route Collector Rd: Upgrades  ULSC      Wombeyan Caves Rd 

  Corridor widening to 10m (18.1km) including decline of (1km), pavement strengthening, compaction, seals line making and sings in addition to some minor rectification of horizontal and vertical curves. 

  Goulburn / Hume    112 (2016) / 1.12 (2016) 

90  Peelwood Road  ULSC      Breadalbane Rd    Corridor widening to 10m (17.65km), pavement strengthening, compaction, seals line making and sings in addition to some minor rectification of horizontal and vertical curves. 

  Goulburn / Hume    55 (2018) / 1.10 (2018) 

91  Breadalbane Road: Flood Damage  ULSC      Tablelands Way    10m carriage width two sections totalling (4km), install culvert and raise pavement out flood zone.    Goulburn / Hume    51 (2014) / 1.3 (2014) 

92  Bowral Distributor Road: Stage 2  WSC  MR639    Bowral Distributor Rd 

  1.1km of new road, 4 lane and 2 roundabouts. Land acquisition required.    Goulburn/Wollondilly / Whitlam/Hume 

  13088 (2016) / 1100 (2016) 

93  Berrima Road/Taylor Avenue: Upgrades  WSC  MR372    Berrima Rd and Taylor Avenue 

  Pavement reconstruction, shoulder widening and new asphalt surface over entire length including shoulders, roundabout. 7.5 km from Moss Vale to Old Hume Hwy. 

  Goulburn/Wollondilly / Whitlam/Hume 

 6320 (2015) / 700 (2015) 

94  Penrose Road: Upgrades  WSC  7636    Penrose Rd    Pavement reconstruction, widen road and place new seal ‐ including 1m shoulder‐over entire length. 15 km from Bundanoon to Wingello. 

  Goulburn/Wollondilly / Whitlam/Hume 

 1045 (2017) / 150 (2017) 

95  Nowra Road: Upgrades  WSC  2415    Nowra Rd    Pavement reconstruction, widen road and place new seal including 1m shoulder‐over entire length (17.6km).    Goulburn/Wollondilly / Whitlam/Hume 

 1250 (2004) / 110 (2004) 

96  Wilson Drive: Upgrades  WSC  MR365    Wilson Drive    Pavement reconstruction, widening of road and place new seal, including 1m shoulder over entire length. 11.5 km from Colo Vale to Balmoral. 

  Goulburn/Wollondilly / Whitlam/Hume 

 3925 (2012) / 250 (2015) 

97  Range Road: Upgrades  WSC  3189    Range Rd    Pavement reconstruction, widen road and place new seal, including 1m shoulder over entire length (8.1km).    Goulburn/Wollondilly / Whitlam/Hume 

  799 (2016) / 100 (2016) 

98  Murrumbateman Road/Shingle Hill Road: Upgrades  YVC          Widen existing seal, new seal entire width and install safety barriers (37.5km).    Goulburn / Eden Monaro    1461 (2017) / 100 (2017 

99  Dog Trap Road: Extension  YVC          Construct new seal from end of existing seal to Isabel Drive (5.0km).    Goulburn / Eden Monaro    205 (2015) / 25 (2015) 

100  Wee Jasper Road: Upgrades  YVC          Widen existing seal, new seal entire width and install safety barriers (75.1km).    Goulburn / Eden Monaro    1495 (2010) / 79 (2010) 

101  Euroka Avenue: Upgrades  YVC          Widen existing seal, new seal entire width and install safety barriers (4.7km).    Goulburn / Eden Monaro    325 (2017) / 33 (2017) 

102  Oallen Ford Road  QPRC          14km minor realignment, widening and pavement rehabilitation to allow heavy vehicle access.    Monaro / Eden Monaro    1120(2017) / 60 (2017) 

103  Whipstick Creek Bridge: Replacement  BVSC      Mt Darragh Rd    Refurbish timber truss bridge, like for like.    Bega / Eden Monaro   2228 (2017) / 428 (2017) 

104  BVSC Bridges: Replacement (1‐3yr package)  BVSC      Various    The bridge renewal program places significant pressure on Council given the number of bridges and their asset condition. This program does not include the Cuttagee Bridge. 

  Bega / Eden Monaro       

105  Cuttagee Bridge: Upgrades  BVSC      Tathra‐Bermagui Rd 

  113m Timber Tres bridge. This significance of this project is the protection of the north south route as an alternative to the Princes Highway. 

  Bega / Eden Monaro    578 (2013) / ‐ 

106  Pericoe Creek Bridge: Replacement  BVSC      Pericoe Rd    Refurbish timber truss bridge, like for like.    Bega / Eden Monaro       

107  Slaters Lane Bridge: Replacement  BVSC      Slaters Lane Bridge    Replace with 9.3m InQuick Bridge to remove weight restrictions.    Bega / Eden Monaro       

108  Garlandtown Bridge: Upgrades  ESC  MR7630    North Head Drive    Partial removal and reconfiguration of existing bridge, widening of bridge abutments and deck, upgrade of bridge approaches and new bitumen seal. 

  Bega / Gilmore   3882 (2014) / 233 (2014) 

109  May Street Bridge: Replacement  GMC  0623    May St    Construct a new single span 2 lane concrete bridge with pedestrian path, new approaches with footpath, kerb & gutter. New bridge deck; 18.5m long and 10.5m wide 

  Goulburn / Hume    947 (2017) / 68 (2017) 

110  Towrang Bridge: Replacement  GMC  0049    Towrang Rd    Replace the existing bridge with an new five span 2 lane concrete bridge 4.5m above the existing bridge. New bridge deck; 85.5m long and 9.5m wide. 

  Goulburn / Hume    406 (2018) / 42 (2018) 

111  Resch's Crossing  QPRC          Replace the low level crossing with a bridge which allows traffic to cross Resch's Creek in flood events.    Monaro / Eden Monaro    211 (2018) / 65 (2018) 

112  Peak Creek Bridge: Replacement  SMRC  MR394    The Snowy River Way 

  The bridge is a 10M Timber Bridge in need of significant Repairs, with a Level 3 safe Load Limit of 24T for T44 Traffic. The proposed works are to carry out a survey and investigations of replacement options, then to upgrade the bridge to meet SM1600 STD. 

  Monaro / Eden Monaro    93 (2009) / 17 (2009) 

113  Delegate River Bridge: Replacement  SMRC  MR93    Delegate Rd    Current Bridge is a single lane 4 span timber bridge 36.7min length, in need of significant repairs. The bridge has had a recent level 3 inspection recommending a 17T limit for T44 Vehicles. The proposal is to replace the bridge with a two‐lane SM1600 opening the Bonang Hwy into Victoria and removing the need for the current heavy vehicles to Bypass. 

  Monaro / Eden Monaro    68 (2008) / 09 (2008) 

Page 13: Road and Bridge Register - crjo.nsw.gov.au · to assist Councils move one step closer to being Shovel‐Ready to deliver on 140 road and bridge projects. For example, a commitment

 

 

CANBERRA REGION JOINT ORGANISATION 

Project Data 

 

    

13 

 Project  Council 

Road Number(s) 

  Road Name(s)  Project Description  Electorate 

State / Federal 

AADT 

Vehicles / Heavy Vehicles 

                     

114  Numeralla River Bridge: Upgrades  SMRC  MR7624    Cooma‐Braidwood Rd 

  The bridge is a 3 span 52m steel girder/concrete deck bridge in good repair, with a level 3 safe load limit of 28T for T44 Traffic and 51T for 25/26m B‐double traffic. Level 3 assessment indicates the deck meets load requirements but the beams fail. The proposal is to upgrade the substructure to ensure the bridge provides the required level of service. 

  Monaro / Eden Monaro    286 (2008) / 32 (2008) 

115  Sherlock River Bridge: Upgrade/Replacement  SMRC      Jerangle Rd    Existing bridge is a 4‐span 47M two‐lane concrete bridge. Level 3 load limit Inspections have down graded the safe load capacity of the bridge to 33T for T44 traffic and 45T for 25/26M B‐double traffic. The required level of service by industry is for 44T for T44 traffic and 68T for 25/26M B‐doubles. The proposal is to upgrade/replace the bridge with one that meets current SM1600 STD's, opening Jerangle Road to 25/26M B‐double traffic. 

  Monaro / Eden Monaro    159 (2018) / 19 (2018) 

116  Jacksons Bridge: Replacement  SVC      Batlow‐Tumbarumba Rd 

  Replace the existing timber bridge with an new single span precast concrete bridge. 150m new bridge, dual lane.    Albury / Eden Monaro       

117  Wingecarribee Street Bridge: Duplication  WSC  1632    Wingecarribee St    Duplication of the existing Rail Over Bridge on Wingecarribee Street. 50m new bridge, dual lane.    Goulburn/Wollondilly / Whitlam/Hume 

 4641 (1998) / 450 (1998) 

118  Lockhart Road: Culvert Replacement  WWCC  636    Lockhart Rd    Replacement of damaged concrete culvert with new concrete structure.    Wagga Wagga / Riverina    771 (2011) / 162 (2011) 

119  Burkes Creek Bridge: Upgrades  WWCC  1154    Holbrook Rd    Investigation and repairs of existing concrete structure/strengthening works.    Wagga Wagga / Riverina   1021 (2018) / 201 (2018) 

120  Umbango Creek Bridge: Upgrades  WWCC  3596    Humula Rd    Investigation and shear strengthening works of bridge headstocks to strengthen structure and support heavy vehicle freight.    Wagga Wagga / Riverina    136 (2013) / 37 (2013) 

121  Tooles Creek Bridge: Upgrades  WWCC  3324    Gregadoo East Rd    Investigation and repairs of existing steel structure at abutments.    Wagga Wagga / Riverina    346 (2011) / 73 (2011) 

122  Beavers Creek Bridge: Upgrades  WWCC  1247    Mundowy Lane    Investigation and repairs of existing concrete structure and replacement of bearing pads.    Wagga Wagga / Riverina    243 (2006) / 36 (2006) 

123  Brooklynn Lane Bridge: Replacement  WWCC  369    Brooklyn Land    Replacement of timber bridge with new concrete structure.    Wagga Wagga / Riverina    50 (2018) / 5 (2018) 

124  Mona Vale Road Bridge: Replacement  WWCC  357    Mona Vale Rd    Replacement of timber bridge with new concrete structure.    Wagga Wagga / Riverina    100 (2018) / 20 (2018) 

125  Wollundry Lagoon Bridge: Upgrades  WWCC  2677    Ivan Jack Drive    Investigation and repairs of abutment walls either side of the structure.    Wagga Wagga / Riverina   8263 (2018) / 190 (2018) 

126  Big Springs Road: Culvert Replacement  WWCC  111    Big Springs Rd    Replacement of corroded steel culvert with new concrete structure.    Wagga Wagga / Riverina    148 (2005) / 15 (2005) 

127  Bulloc Hills Road Bridge: Replacement  WWCC  597    Bulloc Hills Rd    Replacement of timber bridge with new concrete structure.    Wagga Wagga / Riverina    100 (2018) / 10 (2018) 

128  Tathra Wharf: Renewal (State Owned)  BVSC      Tathra Wharf    The iconic tourist facility is an active transport destination of significance for the region. Council has allocated $80k in the current financial year to determine the full extent of the renewal requirements which are expected to be in the order of $10M over the next 10 years. 

  Bega / Eden Monaro       

129  BVSC Bridges: Replacement (4‐10yr package)  BVSC      Various    The bridge renewal program places significant pressure on Council given the number of bridges and their asset condition. This program does not include the Cuttagee Bridge. 

  Bega / Eden Monaro       

130  Thornford Bridge: Replacement  GMC  0117    Thornford Rd    Replace the existing timber bridge with an new single span 2 lane concrete bridge. New bridge deck; 8.5m long and 9.5m wide. 

  Goulburn / Hume    74 (2017) / 12 (2017) 

131  Carrick Road Bridge: Replacement  GMC  0048    Carrick Rd    Replace the existing timber bridge with an new single span 2 lane concrete bridge. New bridge deck; 12m long and 9.5m wide. 

  Goulburn / Hume    217 (2017) / 44 (2017) 

132  Foxlow Bridge  QPRC          Refurbish or replace Foxlow Bridge depending on structural engineers report. Increase weight limit on bridge to 10 tonne or more. 

  Monaro / Eden Monaro    18 (2018) / 4 (2018) 

133  Badja River Bridge: Upgrade  SMRC  MR7624    Cooma‐Braidwood Rd 

  Existing bridge is a 5‐span 77M two‐Lane concrete bridge. Level 3 load limit inspections have downgraded the safe load capacity of the bridge to 33T for T44 traffic and 59T for 25/26M B‐double traffic. The required level of service by industry is for 44T for T44 traffic and 68T for 25/26M B‐doubles. The proposal is to upgrade/replace the bridge with one that meets current SM1600 STD's, opening the Cooma Braidwood Road to 25/26M B‐double traffic. 

  Monaro / Eden Monaro    65 (1997) / N/A 

134  Queanbeyan River Bridge: Upgrades  SMRC      Jerangle Rd    Recent Level 3 inspections have set the bridges load capacity below industry requirements for 25/26M B‐Double Traffic (68T). The bridge is a 38m steel beam with concrete deck. Level 3 assessment indicates the deck meets load requirements but the beams fail. The proposal is to upgrade the substructure to ensure the bridge provides the required level of service. 

  Monaro / Eden Monaro    67 (2014) / 16 (2014) 

135  ULSC Bridges: Replacement (4‐10yr package)  ULSC      Various    Replace timber bridges with reinforced box culverts to an 8m width.    Goulburn / Hume       

136  Burrinjuck Road Bridge: Replacement  YVC          Replace the existing timber bridge with an new single span precast concrete bridge. 15m new bridge, dual lane and resealed approach road. 

  Goulburn / Eden Monaro    174(2017) / 58 (2017) 

137  Burrinjuck Road Bridge: Replacement (Childowa Trail)  YVC          Replace the existing timber bridge with an new single span precast concrete bridge. 15m new bridge, dual lane and resealed approach road. 

  Goulburn / Eden Monaro    51 (2011) / 7 (2011) 

138  Bango Lane Bridge: Replacement  YVC          Replace the existing timber bridge with an new single span precast concrete bridge. 15m new bridge, dual lane and 100m sealed approach road. 

  Goulburn / Eden Monaro       

139  Garryowen Road Bridge: Replacement  YVC          Replace the existing timber bridge with an new single span precast concrete bridge. 15m new bridge, dual lane and 100m sealed approach road. 

  Goulburn / Eden Monaro    61 (2009) / 6 (2009) 

140  BVSC Bridges: Replacement (10‐20yr package)  BVSC      Various    The bridge renewal program places significant pressure on Council given the number of bridges and their asset condition. This program does not include the Cuttagee Bridge. 

  Bega / Eden Monaro      

  

Page 14: Road and Bridge Register - crjo.nsw.gov.au · to assist Councils move one step closer to being Shovel‐Ready to deliver on 140 road and bridge projects. For example, a commitment

14 

  

 

CANBERRA REGION JOINT ORGANISATION 

Glossary/Disclaimer 

 

  

   Acronym

Description

   

QPRC  Queanbeyan Palerang Regional Council SMRC  Snowy Monaro regional Council SVC  Snowy Valleys Council YVC  Yass Valley Council ULSC  Upper Lachlan Shire Council WSC  Wingecarribee Shire Council HC  Hilltops Council GMC  Goulburn Mulwaree Council ESC  Eurobodalla Shire Council BVSC  Bega Valley Shire Council WWCC  Wagga Wagga City Council 

                        Every effort and all reasonable care has been taken to ensure the accuracy of the material contained within this Document. This document is based on information provided by the Councils who are members of the Canberra Region Joint Organisation. Project information was supplied by the Engineering, Infrastructure or Operations Department within each Council. It is written using informative terminology and should not be interpreted otherwise. This document is copyright and the intellectual property of The Infrastructure Collaborative Pty Ltd. Methodology for collection, prioritisation and processing of data similarly remains the property of The Infrastructure Collaborative Pty Ltd and permission must be sought for use of same. The Infrastructure Collaborative Pty Ltd has provided this document using a degree of skill, care and diligence as is generally exercised by project engineers performing services of a similar nature, at the time the services are provided, however, does not accept any liability or responsibility in any way whatsoever and expressly disclaims any liability or responsibility for any loss, damage or costs however incurred by any person as a result or in connection with reliance upon any part of this document. Here required, independent advice from competent professional persons should be sought on matters covered in this Document. All rates and prices provided in this document are based upon figures provided directly by Councils. The Infrastructure Collaborative Pty Ltd has not tested the accuracy or sensitivity of these budget estimates. Some Councils have used their own rates to price work. The Document shall not be reproduced, except in full. The Document has been prepared for the nominated project, and no responsibility is offered or accepted for the use of any part of the Document in any other context or for any other purpose. Where required, independent advice from competent professional persons should be sought on matters covered in this Document. 

 

NSW Regional Service Infrastructure Plan

We have used the classification system from the 2056 Plan to introduce further strategic projects to improve social connectivity and economic efficiency in the region.

All infrastructure projects in the CRJO were reviewed and those that most met the goals of the NSW Regional Service and Infrastructure Plan priorities for inclusion in this prospectus. Projects fall into three categories:

Committed initiatives (0‐10yrs)  Initiatives that either have committed funding, are committed/ contractually committed, are for immediate detailed planning, or are part of key maintenance, renewal or safety programs. Some initiatives are subject to final business case and funding.

Initiatives for investigation (0‐10, 10‐20yrs) Initiatives intended to be investigated for potential commitment or implementation within the next 20 years. Those listed in 0‐10 horizon will be prioritised for more detailed investigation to determine if they are required in the next 20 years.

Visionary initiatives (20+ years)  Longer term initiatives that may be investigated within the next 10 years, but are unlikely to require implementation within 20 years.

$