Click here to load reader
Upload
duonghuong
View
212
Download
0
Embed Size (px)
Citation preview
Riverina Aquaculture Murray Cod Farm Overview
Recirculating Aquaculture Facility / Dam site
Location: 34°15'51.75" S 146°08'45.19" E
Design – Paul Van der Werf Ph: 0439 468 201
The proposed recirculating aquaculture system (RAS) is to be located at 34°15'51.75" S 146°08'45.19" E
just outside of Griffith NSW, Australia. The farm currently grows Murray Cod in net cages in a farm dam.
This facility is to provide up to three cohorts of Murray Cod of 60,000 each (a total of 180,000 x 100
gram fish for further grow out to 1200 grams each in net caged pond systems on the property.
Waste Water/ Recycle Dam
Proposed 5 additional dams
The design parameters for the proposed farm are based on the following species requirements
Water Quality Parameters UOM Design Range
Temperature Celsius 24 3-30
Elevation above Sea Level Meters 100 -
Dissolved Oxygen mg/L 5.0 >5.0
pH - 6.8 5.5-9.0
Ammonia-nitrogen mg/L 2.0 <3.0
Unionised Ammonia mg/L 0.01 <0.02
Nitrite-nitrogen mg/L 0.2 <0.5
Nitrate-nitrogen mg/L 200 <200
Total Hardness mg/L 300 <400
Alkalinity mg/L 100 <200
Carbon Dioxide mg/L 32 <40
Phosphorus mg/L 12 <13
Total Suspended Solids mg/L 10.0 <10
The draft biological plan for the recirculating aquaculture facility
The culture system draft of tank sizes and volumes
System production and consumption
Bio Plan UOM Nursery
Stage 1
Juvenile
Stage 2
Fingerling
Stage 3
Maximum culture density kg/m3 23 37 52
Size at Stocking grams 3.5 17 49
Size at Harvest grams 17.3 49 105
Maximum Feed Rate (% bw/day) 3.36% 2.05% 1.46%
Feed Protein Level % 52 50 50
Feed Phosphorous Level % 1.3 1.2 1.2
Number of Fish in System # 64,078 62,476 60,914
System Maximum Biomass at Harvest kg 1,110 3,037 6,371
Daily Maximum Feed Rate kg 37.3 63 95
Culture System Parameters UOM Nursery
Stage 1
Juvenile
Stage 2
Fingerling
Stage 3
Number of Tanks # 10.00 8.00 12.00
Tank Diameter Meters 2.38 3.45 3.45
Water Depth Meters 1.10 1.10 1.10
Tank Volume Liters 4,898 10,295 10,295
System Volume Liters 48,975 82,358 123,537
Tank Exchange for Self Cleaning Minutes 50 50 50
Oxgyen UOM Nursery
Stage 1
Juvenile
Stage 2
Fingerling
Stage 3
Oxygen Partial Pressure (at elevation) mmHg 155 155 155
System Partial Oxygen Pressure mmHg 90 90 90
Disolved Oxygen at saturation mg/L 8.3 8.3 8.3
Inlet DO mg/L 18.0 18.0 18.0
Outlet DO mg/L 4.8 4.8 4.8
DO Consumption Rate per kg of feed kg 0.50 0.50 0.50
Oxygen Demand per Day kg 18.6 31.5 47.3
Ozone Demand per Day kg 0.93 1.57 2.36
Nitrogen UOM Nursery
Stage 1
Juvenile
Stage 2
Fingerling
Stage 3
TAN Production Rate per kg of Feed kg 0.048 0.046 0.046
TAN Production Rate per Day kg 1.78 2.90 4.35
Passive Nitrification % 5.00 5.00 5.00
TAN available after Passive Nitrification kg 1.69 2.75 4.13
Passive Denitrification % 0 0 0
Draft System Design Parameters UOM Design
Flow Rate (for oxygen) lps 86
Flow Rate (for oxygen) lpm 5,138
Flow Rate (for oxygen) lph 308,278
Tank Volume Liters 254,871
Sump Volume Liters 25,487
Moving Bed Bio Reactor Media (840m2/m3) m3 24
Moving Bed Bio Reactor Volume Liters 38,535
Moving Bed Fill % 0.66
Moving Bed Depth Meters 3.00
Trickle Filter Volume (Divided by 2) m3 11
Culture System Retention time Minutes 50
Water Exchange per Day (for Solids) Liters 48,698
Water Exchange per Day (for Solids) % 19.11%
Feed per day kg 194.8
Nitrogen per Day kg 8.58
Phosphorous per Day kg 0.24
Carbon Dioxide per Day kg 134
Solids per Day kg 48.7
Design water flow rates and discharge water for irrigation
The draft system design
parameters are an estimate
based on mass balance
equations and information
at hand on intensive culture
of Murray cod. These details
may change slightly as the
final design formula is
worked up.
Sensitivity to feed
conversion rate, daily feed
rate and survival rates.
Phosphorous UOM Nursery
Stage 1
Juvenile
Stage 2
Fingerling
Stage 3
Feed Phosphorous Level % 1.3 1.2 1.2
Phosphorous Assimilated by Fish % 0.45 0.45 0.45
Phosphorous Production per kg of Feed grams 1.296 1.196 1.196
Total Phosphorous per day kg 0.048 0.075 0.113
Phosphorous Removal Rate % 0.0 0 0
Carbon Dioxide UOM Nursery
Stage 1
Juvenile
Stage 2
Fingerling
Stage 3
CO2 Production Rate per kg Feed kg 0.69 0.69 0.69
CO2 Production per Hour kg 1.07 1.80 2.71
CO2 Production per Day kg 25.62 43.29 65.01
Solids UOM Nursery
Stage 1
Juvenile
Stage 2
Fingerling
Stage 3
TSS Production Rate per kg of Feed kg 0.25 0.25 0.25
Solids Production per Day kg 9.3 15.7 23.6
Volume per Day Liters 9,315 15,742 23,641
Solids Removal Efficiency % 90 90 90
Water Flow Rates
Flow Required based on Tank Exchange
Reuse Flow Required based on DO
Reuse Flow Required based on TAN
Reuse Flow Required based on CO2
Reuse Flow Required based on TSS
Waste Flow Required for Phosphorous
Waste Flow Required for Nitrate
Proposed Shed Site and Statement of Construction
The Proposed shed is to be of a steel construction with a 10 degree pitched web truss roof with
universal beam columns (posts) of steel construction and a concrete floor. The shed and slab will be
built in accordance with council building codes and regulations to fully engineered specifications.
Colorbond will be used on the shed walls and roof to minimize impact on the local community. The shed
will be 18m x 60m as shown on the attached site plans and will contain machinery and tanks required in
the raising of fish. The Shed will be 4m high to the eves with total shed height of 5.5m to the top of the
roof. Internal walls will be constructed of steel as well with the office and lab walls consisting of timber
and plaster stud design.
Proposed Dam Site
The site already contains one preexisting aquaculture dam growing murray cod in cages.
It is proposed to increase this to a total of 6 dams operating under the same cage systems we are
currently using.
Of these 6 production dams only 4 will be in production at any one time. This gives us two dry dams or
30% of our production volume to use for emergency water storage should they be needed.
Each dam will have a water surface area of 4390m2 or 66.25m x 66.25m and hold approximately 12
megs of water. It is assumed from figures gained from our initial dam in stage 1 of the development that
production will be around 18t of murray cod per year from each dam giving an annual production from
the whole farm of approximately 72 t.
The dams will require at least two complete water changes per year to maintain water quality and fish
health. This means we need a minimum of 96 megs of water annually at full production. This will be
supplied via our 205 meg general security irrigation license and will supplement our normal irrigation
cropping program.
Any water used in the dams will be held on farm and used for irrigation purposes growing both summer
and winter crops.
Water will be pumped from the internal supply channel into a 300mm PVC Pipe that supplies each dam
through individual valves. Similar pipe will be used to drain the dams supplying water to a raised channel
that runs back to the top of the farm and allows water to be flooded onto the paddocks for irrigation
any irrigation runoff can be caught in our 5 meg drainage/recirculation dam which can then be pumped
back for further irrigation. This drainage dam is 150m long and 20m wide and 2.5m deep. At no time will
any water be allowed back into the Murrumbidgee Irrigation drainage system.
Dams can only be emptied by gravity back to natural ground level and the remaining water can be
pumped using our pinerise pump ensuring complete drainage into a small sump constructed in one side
of the dam base.
This will be essential as it is anticipated to get around 4 years of production out of a dam before it will be
required to drain and dry it out and remove any trash fish and built up organic matter swapping
production to another dam.