48
Risktec Solutions risk management and assessment for business © 2018 Risktec Solutions Limited Meeting the challenges of a safety-driven organisation Safety Engineering Conference Feb 9 th 2016 Steve Lewis & Gareth Ellor - Directors

Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

Risktec Solutionsrisk management and assessment for business

© 2018 Risktec Solutions Limited

Meeting the challenges of a safety-driven organisation

Safety Engineering Conference – Feb 9th 2016

Steve Lewis & Gareth Ellor - Directors

Page 2: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

1. Introduction to Risktec

2. Key challenges for a safety driven organisation

3. Case Studies – a few ideas & solutions

4. Q&A

Agenda

Page 3: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

1. Introduction to Risktec

2. Key challenges for a safety driven organisation

3. Case Studies – a few ideas & solutions

4. Q&A

Agenda

Page 4: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

Risktec Solutions

Independent and specialist risk management consulting and training provider

Part of the TÜV Rheinland Group

We focus on:

Safety & risk assessment (what are the risks?)

Management systems (how are they managed?)

Culture & behaviour (what really happens!)

Training & education (knowledge transfer)

Resource solutions (specialist, flexible support)

260+ employees across 16 offices worldwide

100 associates embedded in client organisations

…working in 7 diverse market sectors

…delivered over 4,200 projects to over 1,000 clients in over 50 countries

…providing solutions (no two assignments are the same!)

Page 5: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

Other Training Courses

Leadership

BowTieXP Software

(Basic and Advanced)

Investigator 3 Software

HSSE Leadership for

Managers

HSSE Risk Management

for Managers

HSSE Leadership for

Supervisors

Training & Educationin partnership with

Nuclear Foundation Modules

Radiological Protection

Radioactive Waste

Management

Implementing a

Regulatory Regime

Nuclear Reactor Safety

Principles

Principles of Regulatory

Systems

Nuclear Reactor Basics

Introduction to

Risk Management

Core Module

HAZOP Study

Risk Assessment and Treatment

Bowtie Risk

Management

Functional Safety

(including SIL)

Availability, Reliability &

Maintainability (ARM)

Fault Tree & Event

Tree Analysis

Human Factors in

Design & Operations

Oil & Gas & Process

Industry Risk Studies

Nuclear PSA

Rail Safety Analysis

Hazard Identification

Risk Analysis

Risk Reduction & ALARP

Research Methods in

Risk & Safety Mgmt

Research Methods

Project

MSc Project

Postgraduate Modules in Risk & Safety Management

Engineered Risk Control

Systems & Perf (Oil & Gas)

Engineered Risk Control

Systems & Perf (Nuclear)

Physical Effects

Modelling

Environmental Risk

Assessment

Rail Risk Management

Project Risk

Management

For details of our accredited maritime safety and security

officer modules please visit www.intmarsec.co.uk

Software

Offshore Wind Farm Safety

Assurance & Justification

Oil & Gas & Process Nuclear

Rail

Module key:

Marine

Cross-industry

Renewables

Process Hazard Analysis

Asset Integrity

Risk Management

Oil and Gas Lifecycle

Hazards & RisksNuclear Lifecycle

Hazards & Risks

Rail Industry

Hazards & Risks

Process Safety Mgmt in

Design & Operations

Maritime Risk

Management

Oil & Gas & Process

Industry QRA

Safety/HSE Cases

Management

Systems and Culture

Incident Investigation &

Analysis

Emergency Response

and Crisis Management

Workplace Safety

Performance Monitoring,

Auditing & Mgmt Review

Culture, Behaviour &

Competency Mgmt

Business Continuity

Management

Health, Safety & Environ-

ment (HSE) Mgmt Systems

Root Cause Analysis

Page 6: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

Ris

k

Time

Risk Reduction

Page 7: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

Thales

Safety and Assurance for Jubilee and Northern Line Upgrade Project (JNUP)

Safety Cases for Neasden Depot

Safety Cases for Train Protect & Warning System (TPWS) for Network Rail

Safety Assessment for the Manchester Metrolink Project

Safety Case for the Train Management System (TMS) Project for Network Rail

Safety and Assurance for London Underground Four Lines (Signalling) Modification Project (4LM)

Submarine Periscope System Safety Support Thales Optronics Glasgow

Page 8: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

1. Introduction to Risktec

2. Key challenges for a safety driven organisation

3. Case Studies – a few ideas & solutions

4. Q&A

Agenda

Page 9: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

Déjà vu

How do we effectively integrate safety in design?

How can we give our safety

engineers practical tools

to do this?

How do we bring our

Safety Case to life?

How do we capture

knowledge of ageing

workforce?

How do we implement

training effectively across our

organisation?

How do we make learning

stick?Ris

k

Time

Mange tout Rodney

Page 10: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

1. Introduction to Risktec

2. Key challenges for a safety driven organisation

3. Case Studies – a few ideas & solutions

4. Q&A

Agenda

Page 11: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

Déjà vu

How do we effectively integrate safety in design?

How can we give our safety

engineers practical tools

to do this?

How do we bring our

Safety Case to life?

How do we capture

knowledge of ageing

workforce?

How do we implement

training effectively across our

organisation?

How do we make learning

stick?

A few ideas & solutions

Page 12: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

What the Customer

wanted

How the Customer

explained it

How the Project

Manager understood it

How the Engineer

designed it

What the Site Team

installed

How Management

explained it

What the Safety Case

had to justify

How the Project was

documented

A shared goal?

Page 13: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

1. To get things right.

2. To reduce risks ALARP

De

cre

asin

g e

ffe

cti

ve

ne

ss

Remove the hazard all together or substitute for a less hazardous alternative

Eliminate

Reduce

Isolate

Control

PPE

Discipline

Volume, inventory, concentration, speed, voltage, etc.

Move further away, enclose, circuit breakers, guards, isolation valves, lock-out-tag-out, etc.

Work procedures, safety systems, alarms, trips, interlocks, limit switches, permit to work

Personal Protection Equipment

Training, supervision, instruction, information, awareness of incidents, safety meetings, disciplinary process

Always try to

think beyond this

most obvious,

but least effective

level of control

Why integrate safety in design

Page 14: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

1. To get things right.

2. To reduce risks ALARP.

3. To reduce costs!

Potential to reduce risk

TimeDesign &

Construction

Commissioning, Operations & Maintenance

Life Extension/Decommissioning

PlanningLicensing

Time

Concepts & options

Layouts

Design

Specifications

Management Systems-QHSSE-Asset management-O&M-Competency

Location

Project schedule

O&M philosophies

Contractor selection Managing residual risk

Changes are also cheaper

and easier early on

Why integrate safety in design

Page 15: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

HSE

Functional

Requirements

Plant

Operations

Site Operations

Project Operations Boundary

Assu

mptio

ns

Design v Ops v Safety Case Study: Nuclear Defence

Page 16: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

1. It’s a juggling act! “Negotiate” between the three elements to find the optimum overall compromise!

2. Ensure all three elements remain in in harmony at all times.

Plant Operations Plant Operations

Success Factors

Page 17: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

1. It’s a juggling act! “Negotiate” between the three elements to find the optimum overall compromise!

2. Ensure all three elements remain in in harmony at all times.

3. Start early! A truly ALARP solution can only be reached if integration starts from concept design.

Success Factors

Page 18: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

Déjà vu

How do we effectively integrate safety in design?

How can we give our safety

engineers practical tools

to do this?

How do we bring our

Safety Case to life?

How do we capture

knowledge of ageing

workforce?

How do we implement

training effectively across our

organisation?

How do we make learning

stick?

A few ideas & solutions

Page 19: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

Concept/

Development

Production/

Manufacture

Recycling/

Disposal

Pro

du

ct L

ife-C

yc

le

Design

Works Testing

Project Life-Cycle

Concept/

DevelopmentDesign

Site Construction

& Commissioning

Operation &

Maintenance

Decommissioning/

Re-Powering

Logistics

Case Study: Siemens Offshore Wind Safety Case Framework

Page 20: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

Identify Hazards

Generate

Hazard Register

Develop Risk

Scenarios

Perform detailed Risk

Assessment on

Significant Hazards

Screen Significant

Hazards

Are risks

ALARP?

Implement further

risk reduction

measures

No

Yes

Case Study: Siemens Offshore Wind Safety Case Framework

Hypothetical Wind Farm:

Project

Product

Logistics

Capture/Record

Position Apply to specific Project, Product or Logistics

Full Life-Cycle

Framework

Toolkit:

Policies

Procedures

Templates

Worked Examples

Page 21: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

Project (e.g. Specific Wind Farm)

Generates: Wind Farm Safety Case

Demonstrates that a specific Wind Farm is

designed and can be constructed, operated,

maintained and decommissioned safely and

that all risks are reduced ALARP

Logistics(e.g. Marine Operations, Aviation)

Generates:

Generic Logistics Safety Case

Demonstrates: all (or selected)

Offshore Wind Logistics risks

are reduced ALARP on a

generic basis (not location

specific)

Product(e.g. Wind Turbine, Offshore Platform)

Generates:

Generic Product Safety Case

Demonstrates: all (or selected)

Product design, construction,

operation etc. risks are reduced

ALARP on a generic basis (not

location specific)

Safety Case Framework

Safety Case Procedure

Safety Case Toolkit

Case Study: Siemens Offshore Wind Safety Case Framework

Page 22: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

1. Framework ensures and demonstrates that they are managing risk effectively internally, to customers and the regulator.

2. Ensures a complete and thorough approach – thinking done up-front (once!) involving all the right people.

3. Provides a blueprint and template for specific projects ensuring consistent approach.

4. Reduces cost; majority of work done up-front - application limited to project specific tailoring.

5. Captures experience and lessons learned centrally providing a live basis of safety.

6. Approach applicable to any replicated project.

Case Study: Siemens Offshore Wind Safety Case Framework

Page 23: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

Déjà vu

How do we effectively integrate safety in design?

How can we give our safety

engineers practical tools

to do this?

How do we bring our

Safety Case to life?

How do we capture

knowledge of ageing

workforce?

How do we implement

training effectively across our

organisation?

How do we make learning

stick?

A few ideas & solutions

Page 25: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

Prevention Mitigation

HSE Critical Activities

Responsible parties

Visually demonstrate and communicate the link

between controls and the management system

Bow-Tie Methodology

Page 26: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

Improved understanding

Greater ownership

Efficiency gains

Live “Basis of Safety”

Benefits of Bow-Tie

Page 27: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

We know what could go wrong?

We have systems in place to prevent

this from happening?

We can assure ourselves that

they are working effectively?

Identify Hazards

Generate

Hazard Register

Develop Risk

Scenarios

Generate Bowtie

Diagrams for

Significant Hazards

Screen Significant

Hazards

Are risks

ALARP?

Implement further

risk reduction

measures

No

Define Roles &

Responsibilities

Identify Safety

Critical Equipment

Yes

Inspect, Maintain,

Test etc.

Monitor, Review,

Audit etc.

Where does it fit in?

Page 28: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

Déjà vu

How do we effectively integrate safety in design?

How can we give our safety

engineers practical tools

to do this?

How do we bring our

Safety Case to life?

How do we capture

knowledge of ageing

workforce?

How do we implement

training effectively across our

organisation?

How do we make learning

stick?

A few ideas & solutions

Page 29: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

0% 1% 2% 3% 4% 5% 6% 7% 8%

0-4

10-14

20-24

30-34

40-44

50-54

60-64

70-74

80-84

90+

Ageing Western Workforce

United Kingdom, 2014, source www.ons.gov.uk

Typical

retirement age

1960s baby

boomers

Disproportionate number of experienced and skilled workers retiring in

next 5-10 years => specific strategies required for knowledge transfer

Page 30: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

Case study: Rolls-Royce Submarines

Problem: How to capture safety knowledge of mature safety engineers and pass on to new younger safety engineers?

Solution: Customised MSc in Risk and Safety Management

Course delivery

& assessmentCoaching support to trainees

Post-course On-the-job coaching and mentoring

Course content

Selection and review of modulesSignposts to RR standards and practices

Case studies specific to RR

Input of mature safety engineersActivity

Page 31: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

Benefits

100% success rate (2 passes, 3 merits, 11 distinctions)

Course materials captured company knowledge in structured programme

Trainees able to relate theory to practical applications of day job

Subsequent performance reviews revealed trainees outperformed peers in day job

Page 32: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

Déjà vu

How do we effectively integrate safety in design?

How can we give our safety

engineers practical tools

to do this?

How do we bring our

Safety Case to life?

How do we capture

knowledge of ageing

workforce?

How do we implement

training effectively across our

organisation?

How do we make learning

stick?

A few ideas & solutions

Page 33: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

Delivery

More classroom based

More online or CBT

Audience Assessment

Essay & dissertation

Trainer observation

Multiple choice

Tracking of

participation

Methods of Delivery & Assessment

Page 34: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

Case Study: Talisman-SINOPEC Energy UK

Problem: How to make 4,000 workers aware of importance of new Risk Assessment Matrix and how to help 250 supervisors use it correctly?

Solution: Blended learning (online + classroom)

Online 1 hour awareness

training for 4,000 workers

(client secure area on Risktec

Online)

Classroom 1 day training for

250 supervisors in groups of

20, with individual and group

activities

Testing by

multiple choice

questions

Page 35: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

Benefits

Different audiences get:

right message for them

appropriate delivery method

appropriate level of assessment to confirm

message understood

Very cost-effective

More consistent risk assessment and decision-making in workplace

Right person, right message, right way

Page 36: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

Déjà vu

How do we effectively integrate safety in design?

How can we give our safety

engineers practical tools

to do this?

How do we bring our

Safety Case to life?

How do we capture

knowledge of ageing

workforce?

How do we implement

training effectively across our

organisation?

How do we make learning

stick?

A few ideas & solutions

Page 37: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case
Page 38: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case
Page 39: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

“Operating equipment before understanding the safety critical

aspects of operation and before verifying the safety critical ‘lines of

defence’ are in place and functional”.

Example Games

THEME 1“Layers of Protection”

Page 40: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case
Page 41: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case
Page 42: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

Example games

THEME 2“Functional Safety Critical Equipment”

“Starting or operating equipment when safety critical

instrumentation is bypassed, out of calibration or out of

service”.

Page 43: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case
Page 44: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case
Page 45: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

1. A novel, engaging mechanism for learning.

2. Significantly improved knowledge retention rates.

3. Increases impact of training by linking a fun activity to a serious issue or concept – makes it enjoyable and memorable.

4. Refreshing alternative to conventional training.

5. Readily tailored to suit different issues/concepts - can easily link issue/concept to a game either literally or metaphorically.

Benefits of

Page 46: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

1. Introduction to Risktec

2. Key challenges for a safety driven organisation

3. Case Studies – a few ideas & solutions

4. Q&A

Agenda

Page 47: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

Questions

Page 48: Risktec Solutions · 2018-11-29 · Risktec Solutions risk management and assessment for business ... Root Cause Analysis. k Time Risk Reduction. Thales ... Safety Case Toolkit Case

[email protected]

risktec.tuv.com

+44 (0)1925 611200

Thank you for your attention