Upload
moraru-gabriel
View
225
Download
0
Embed Size (px)
Citation preview
7/27/2019 Risk Management Student Moraru Gabriel Second Year of Master ISE
1/16
Risk Management
Student: Moraru GabrielGroup: I.S.E. 2nd year of master
Professor: Diego Varela
Risk Management for Design and ConstructionOvidiu Cretu,Robert Stewart,Terry Berends
7/27/2019 Risk Management Student Moraru Gabriel Second Year of Master ISE
2/16
7/27/2019 Risk Management Student Moraru Gabriel Second Year of Master ISE
3/16
7/27/2019 Risk Management Student Moraru Gabriel Second Year of Master ISE
4/16
A project manager responsible for thedelivery of a new office building identifies aperrmitting concern that could delay theapproval of her project.
A structural engineer is assessing thequality of the data of a technical report thatwas performed and fears that the abutmentsof the bridge he is designing could
experience differential settlement.A general contractor fears that the
recent volatility in the price of steel could turn
a profitable project into a money loser.
7/27/2019 Risk Management Student Moraru Gabriel Second Year of Master ISE
5/16
Risk Management includes theprocesses conducting riskmanagementplanning, identification, analysis, responses,
and monitoring and control on a project.
The objectives of project risk managementare to increase the probability and impact of
positive events and decrease the probabilityand impact of negative events in the project.
7/27/2019 Risk Management Student Moraru Gabriel Second Year of Master ISE
6/16
Risk management should:
create value
be an integral part of organizationalprocesses
be part of decision making
explieitiv address uncertainty be systematic and structured
be based on the best availableinformation
Why and what is Risk Management?
1.2 What Is Risk Management?
7/27/2019 Risk Management Student Moraru Gabriel Second Year of Master ISE
7/16
Research has shown that historically themajority of construction projects experience
cost and/or schedule overruns.
A study focused on analyzing the costs of
public works projects in Europe and North
America found that the incidence and severity
of cost overruns was significantly higher thanindicated by the previous source. This same
study found that cost overruns were found in 86
percent of the 258 projects that were sampled.
Why and what is Risk Management?
1.3 Why Risk Management?
7/27/2019 Risk Management Student Moraru Gabriel Second Year of Master ISE
8/16
Further, actual costs were, on average, 2.8percent higher than estimated costs. The
authors of the study concluded that the
following factors were the primary culprits in
cost overruns: Lack of proper risk analysis in developing
estimates
Poorly defined scope at the time initial projectbudgets were developed
Larger public projects are prone to intentional
underestimation due to political
Why and what is Risk Management?
1.3 Why Risk Management?
7/27/2019 Risk Management Student Moraru Gabriel Second Year of Master ISE
9/16
Why and what is Risk Management?
1.4 The Limitations of Risk Management
How can you manage the future?The use of probability distributions, which werefirst developed by the Germanmathematician Carl Freidrich Gauss (1777-
1855), were never designed for the purposesmodeling complex future events, they are stilluseful, provided we acknowledge these
limitations and ensurethat those who make decisions based onthem are made aware of them.
7/27/2019 Risk Management Student Moraru Gabriel Second Year of Master ISE
10/16
The dangers of modeling risks usingstatistical methods are abundane.g.:stockmarket crash of 2008.
Risk analysis will always be limited by theassumptions onwhich the calculations arebased, Financial markets are far too complexto include all data, and any quantitativemodel is therefore only as good as the
information and algorithms used, which cannever match the real world.
Why and what is Risk Management?
1.4 The Limitations of Risk Management
2 P j t t d h d l E ti t
7/27/2019 Risk Management Student Moraru Gabriel Second Year of Master ISE
11/16
Cost estimate- aprediction of quantities,cost,and/
or price of resources required by the scope of an
asset investment option ,activity,or project.As aprediction, an estimate must adress risks and
uncertainties.
Schedule estimate-identifies a plan of work to beperformed showing the order in which tasks are
to be carried out and the amount of time
allocated to each of them.
Base cost estimate-the cost which can resonablebe expected if the project materializes as
planned. The base cost estimate must be
unbiased and neutral- it should not be optimistic
or conservative.
2. Project cost and schedule Estimates
2.1 Introduction
7/27/2019 Risk Management Student Moraru Gabriel Second Year of Master ISE
12/16
2. Project cost and schedule Estimates
2.2 Cost estimate process
7/27/2019 Risk Management Student Moraru Gabriel Second Year of Master ISE
13/16
2. Project cost and schedule Estimates
2.2 Cost estimate process
The cost estimating process includes the
following steps:
-determine the bias estimate-prepare the estimate
-review estimate
-determine risks and set contingency
-determine estimate communication approach-conduct independent review and obtain
management endorsement
7/27/2019 Risk Management Student Moraru Gabriel Second Year of Master ISE
14/16
3.1 RBE-The process
The risk-based estimate (RBE),known as
cost risk analysis is an important part of projectmanagement as well as the project cost andschedule estimating.
The advantages of using RBE approachincludes:-It minimizes the number of suprises during
project development and delivery by providingfor the identification and quantification of riskevents
7/27/2019 Risk Management Student Moraru Gabriel Second Year of Master ISE
15/16
3.1 RBE-The process
-it creates opportunities to study what-ifscenarios using a rigorousand statisticalapproach
-it allows reasonable control over the projectsestimate through project risk management-it is a collaborative effort that improvesproject communication and transfer ofinformation amoung the project teammembers, stakeholders, and the public.
7/27/2019 Risk Management Student Moraru Gabriel Second Year of Master ISE
16/16
3.1 RBE-The process
The diagram illustrates the situation when theanalysis assumes that changes may occur only
for the cost, and the schedule is fixed .