Risk management
Berliner Energieagentur GmbH
Risks of EPC
Equipment transfered into the property of building owner at the moment of installation and/or hand-over
Ownership
by contractor for the total investment into ESC schemes
economic risk
by contractor;
guarantee of performance, technical condition & availability
technical risk
by building owner;
rising prices => protection of contractor
decreasing prices => benefit for building owner
energy price risk
by building owner; change of use => modification of guaranteed savings
risk of use
Berliner Energieagentur GmbH
Risk Management Instruments
• Careful analysis of the savings potential
• Good, complete data basis
• Complete and meaningful tender documents with clear and detailled specifications of services required
• Careful selection of the service provider
• Integration of additional external know-how where needed
• Use of standard documents, e.g. model contract and checklists
• Well balanced contract
Berliner Energieagentur GmbH
by building owner; change of use => modification of guaranteed savings
risk of use
Risk of use
is a risk that cannot be influenced by the contractor. This risk is born by the building owner/client only. Good contracts foresee procedures for cases like this.
It can be done via a baseline adaptation in case of changes in use; the calculation basis for such cases should be available.
Berliner Energieagentur GmbH
by building owner; energy price risk
Risk of changing energy prices
are to be born by the client/ building owner in any case, with or without a contracting project.
• Rising prices => protection of contractor
• Decreasing prices => benefit for building owner
For the sake of calculating the proper savings, the baseline is calculated with fixed reference prices of the base year.
Berliner Energieagentur GmbH
Technical Risks
exist with regard to the adequacy and design, construction, operability and availability during operation, as well as maintenance periods of the technical equipment. The contractor fully bears this risk
The Economic Risk
is related to the need that the invested capital depreciates in the course of a project. In the case of EPC the contractor bears this risk that the capital depreciates through the achieved savings.
by contractor for the total investment into ESC schemes
economic risk
by contractor;
guarantee of performance, technical condition & availability
technical risk
Berliner Energieagentur GmbH
• Under German law, the ownership of equipment installed passes to the building owner when the equipment is installed and accepted. There are parts that can also pass into the ownership at the end of a contract
• Ownership with Building Owner: Security in case of problems on side of ESCO (worst case: bankruptcy)
• Ownership with ESCO: Asset Security for credits
Tax or credit issues can have both negative and positive factors for both sides
Equipment transfered into the property of building owner at the moment of installation and/or hand-over
Ownership