21
Risk Assessment Matrix © All rights reserved. The Managers Resource Handbook by MHX Global LLP www.ManagersResourceHandbook.com v1 An Example for Project Managers

Risk Assessment Matrix - Manager's Resource Handbook · – Sums the total potential risk for a project as a function of cost • A Risk Assessment Matrix helps Project Teams plan

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Risk Assessment Matrix - Manager's Resource Handbook · – Sums the total potential risk for a project as a function of cost • A Risk Assessment Matrix helps Project Teams plan

Risk Assessment Matrix

© All rights reserved. The Managers Resource Handbook by MHX Global LLP www.ManagersResourceHandbook.com v1

An Example for Project Managers

Page 2: Risk Assessment Matrix - Manager's Resource Handbook · – Sums the total potential risk for a project as a function of cost • A Risk Assessment Matrix helps Project Teams plan

© All rights reserved. The Managers Resource Handbook by MHX Global LLP www.ManagersResourceHandbook.com v1

What is A Risk Assessment Matrix?

• A Risk Assessment Matrix is a tool. – Helps organize concerns and risks you foresee with a given project

– Includes potential impacts to the project

– Identifies the person(s) responsible for managing each risk item

– Computes the cost associated with each risk

– States the likelihood a risk will occur

– Sums the total potential risk for a project as a function of cost

• A Risk Assessment Matrix helps Project Teams plan for problems, manage risk, prioritize action, and communicate to others.

• The potential cost of risk value you calculate can be factored into your financial model to build a stronger business case.

Page 3: Risk Assessment Matrix - Manager's Resource Handbook · – Sums the total potential risk for a project as a function of cost • A Risk Assessment Matrix helps Project Teams plan

© All rights reserved. The Managers Resource Handbook by MHX Global LLP www.ManagersResourceHandbook.com v1

Key Steps in Building a Risk Assessment Matrix

1. Identify the Risk

2. Evaluate the Impacts of Each Risk

3. Define Ways to Mitigate Each Item

4. Calculate the Total Cost of Each Risk

5. Define the Probability of Each Item

6. Sum the Total Potential Risk Value of a Project

For Step-By-Step Instructions and to Download The Template: http://www.managersresourcehandbook.com/project-risk-matrix-template/

Page 4: Risk Assessment Matrix - Manager's Resource Handbook · – Sums the total potential risk for a project as a function of cost • A Risk Assessment Matrix helps Project Teams plan

© All rights reserved. The Managers Resource Handbook by MHX Global LLP www.ManagersResourceHandbook.com v1

Watkins Smith Corporation

RF-30 Upgrade

Jessica Abrams

May 1, 2016

October 1, 2018 C Cost

August 12, 2018 S Schedule

December 3, 2017 R Resources

On Track O Other

Number Risk Description Impact of Risk C S R O Mitigation Strategy Risk OwnerTotal Risk

Value

Probability of

Occurrence

Predicted

Risk Value

1Customer delays release of end

product into market

-Delay in investment recovery

-Reduced Sales next yearX X

-Add customer-driven delays to penalties

clause of contract

-Add milestone payments for Initial Concept

and Design Acceptance to shorten time

between payments

T. Franklin $45,000 60% $27,000

2Customer seeks to renegotiate

price based on final design

-Reduction in total projected revenue

-Business case may not be as strong

-Sales contribution from project may

need to be reduced

-Cost reduction may be needed

X X

-Track detailed cost changes throughout

design evolution to show cost adjustments

-Seek funding for changes to help absorb

non-recurring costs impacts

G. DuBois $33,050 50% $16,525

3

Specialize software is needed

based on current project

requirements

-Purchase of additional software

necessary

-Employees will need training

-Efficiency loss due to learning curve

X X X

-Negotiate with customer to use 'industry

standard' software

-Charge customer for added cost of special

software under scope change clause.

R. Nelson $77,000 25% $19,250

4

Produce Validation Testing

must be performed by 3rd

party

-Need to identify potential suppliers

-Added cost of paying 3rd party

-Schedule impact due to logisticsX X X

-Setup test program to use only internal

equipment

-Work with customer to see what tests they

can perform on our behalf

C. Jenkins $113,000 20% $22,600

5

Product Parts List exceeds

estimated value by more than

10%

-Recurring Cost in excess of business

case

-Reduced profit margin if price

remains unchanged

-Potential loss on effort

X

-Negotiate component costs with suppliers

-Renegotiate contract price with customer

based on customer-driven changes.

M. Hart $8,400 30% $2,520

6

Customer IT system/formats

cannot receive project

deliverables

-Will need to convert formats

internally

-May require specialize conversion

software

-Schedule impact if formatting issues

cannot be resolved

X X

-Test software export abilities within first

90 days

-Have customer provide list of formats to

evaluate import capabilities

R. Nelson $18,500 70% $12,950

$294,950

$100,845

Risk Values

Project Financial Summary:

42%

41%

$100,845

$119,643

75%

68%

$1.595M

$2.351M

Reporting Date

Risk Category DefinitionProject

Project Manager

Current ROS:

Estimated % Complete:

Initial Risk Value:

Current Risk Value:

Total Potential Risk (Unweighted)

Total Estimated Impact (Weighted)

Estimated Completion Date

% Budget SpendPlanned Completion Date

Category

Project Status

Customer Initial ROS:

Estimated Investment:

Current Investment:Project Start Date

Project Information

Page 5: Risk Assessment Matrix - Manager's Resource Handbook · – Sums the total potential risk for a project as a function of cost • A Risk Assessment Matrix helps Project Teams plan

© All rights reserved. The Managers Resource Handbook by MHX Global LLP www.ManagersResourceHandbook.com v1

Watkins Smith Corporation

RF-30 Upgrade

Jessica Abrams

May 1, 2016

October 1, 2018 C Cost

August 12, 2018 S Schedule

December 3, 2017 R Resources

On Track O Other

Number Risk Description Impact of Risk C S R O Mitigation Strategy Risk OwnerTotal Risk

Value

Probability of

Occurrence

Predicted

Risk Value

1Customer delays release of end

product into market

-Delay in investment recovery

-Reduced Sales next yearX X

-Add customer-driven delays to penalties

clause of contract

-Add milestone payments for Initial Concept

and Design Acceptance to shorten time

between payments

T. Franklin $45,000 60% $27,000

2Customer seeks to renegotiate

price based on final design

-Reduction in total projected revenue

-Business case may not be as strong

-Sales contribution from project may

need to be reduced

-Cost reduction may be needed

X X

-Track detailed cost changes throughout

design evolution to show cost adjustments

-Seek funding for changes to help absorb

non-recurring costs impacts

G. DuBois $33,050 50% $16,525

3

Specialize software is needed

based on current project

requirements

-Purchase of additional software

necessary

-Employees will need training

-Efficiency loss due to learning curve

X X X

-Negotiate with customer to use 'industry

standard' software

-Charge customer for added cost of special

software under scope change clause.

R. Nelson $77,000 25% $19,250

4

Produce Validation Testing

must be performed by 3rd

party

-Need to identify potential suppliers

-Added cost of paying 3rd party

-Schedule impact due to logisticsX X X

-Setup test program to use only internal

equipment

-Work with customer to see what tests they

can perform on our behalf

C. Jenkins $113,000 20% $22,600

5

Product Parts List exceeds

estimated value by more than

10%

-Recurring Cost in excess of business

case

-Reduced profit margin if price

remains unchanged

-Potential loss on effort

X

-Negotiate component costs with suppliers

-Renegotiate contract price with customer

based on customer-driven changes.

M. Hart $8,400 30% $2,520

6

Customer IT system/formats

cannot receive project

deliverables

-Will need to convert formats

internally

-May require specialize conversion

software

-Schedule impact if formatting issues

cannot be resolved

X X

-Test software export abilities within first

90 days

-Have customer provide list of formats to

evaluate import capabilities

R. Nelson $18,500 70% $12,950

$294,950

$100,845

Risk Values

Project Financial Summary:

42%

41%

$100,845

$119,643

75%

68%

$1.595M

$2.351M

Reporting Date

Risk Category DefinitionProject

Project Manager

Current ROS:

Estimated % Complete:

Initial Risk Value:

Current Risk Value:

Total Potential Risk (Unweighted)

Total Estimated Impact (Weighted)

Estimated Completion Date

% Budget SpendPlanned Completion Date

Category

Project Status

Customer Initial ROS:

Estimated Investment:

Current Investment:Project Start Date

Project Information

Create a Header

Since a Risk Assessment Matrix is used by a project team and as a reporting tool, create a header of key information about the project. You may want to include: • Project Name • Customer • Program Manager • Key Dates

Watkins Smith Corporation

RF-30 Upgrade

Jessica Abrams

May 1, 2016

October 1, 2018 C Cost

August 12, 2018 S Schedule

December 3, 2017 R Resources

On Track O Other

Number Risk Description Impact of Risk C S R O Mitigation Strategy Risk OwnerTotal Risk

Value

Probability of

Occurrence

Predicted

Risk Value

1Customer delays release of end

product into market

-Delay in investment recovery

-Reduced Sales next yearX X

-Add customer-driven delays to penalties

clause of contract

-Add milestone payments for Initial Concept

and Design Acceptance to shorten time

between payments

T. Franklin $45,000 60% $27,000

2Customer seeks to renegotiate

price based on final design

-Reduction in total projected revenue

-Business case may not be as strong

-Sales contribution from project may

need to be reduced

-Cost reduction may be needed

X X

-Track detailed cost changes throughout

design evolution to show cost adjustments

-Seek funding for changes to help absorb

non-recurring costs impacts

G. DuBois $33,050 50% $16,525

3

Specialize software is needed

based on current project

requirements

-Purchase of additional software

necessary

-Employees will need training

-Efficiency loss due to learning curve

X X X

-Negotiate with customer to use 'industry

standard' software

-Charge customer for added cost of special

software under scope change clause.

R. Nelson $77,000 25% $19,250

4

Produce Validation Testing

must be performed by 3rd

party

-Need to identify potential suppliers

-Added cost of paying 3rd party

-Schedule impact due to logisticsX X X

-Setup test program to use only internal

equipment

-Work with customer to see what tests they

can perform on our behalf

C. Jenkins $113,000 20% $22,600

5

Product Parts List exceeds

estimated value by more than

10%

-Recurring Cost in excess of business

case

-Reduced profit margin if price

remains unchanged

-Potential loss on effort

X

-Negotiate component costs with suppliers

-Renegotiate contract price with customer

based on customer-driven changes.

M. Hart $8,400 30% $2,520

6

Customer IT system/formats

cannot receive project

deliverables

-Will need to convert formats

internally

-May require specialize conversion

software

-Schedule impact if formatting issues

cannot be resolved

X X

-Test software export abilities within first

90 days

-Have customer provide list of formats to

evaluate import capabilities

R. Nelson $18,500 70% $12,950

$294,950

$100,845

Risk Values

Project Financial Summary:

42%

41%

$100,845

$119,643

75%

68%

$1.595M

$2.351M

Reporting Date

Risk Category DefinitionProject

Project Manager

Current ROS:

Estimated % Complete:

Initial Risk Value:

Current Risk Value:

Total Potential Risk (Unweighted)

Total Estimated Impact (Weighted)

Estimated Completion Date

% Budget SpendPlanned Completion Date

Category

Project Status

Customer Initial ROS:

Estimated Investment:

Current Investment:Project Start Date

Project Information

Page 6: Risk Assessment Matrix - Manager's Resource Handbook · – Sums the total potential risk for a project as a function of cost • A Risk Assessment Matrix helps Project Teams plan

© All rights reserved. The Managers Resource Handbook by MHX Global LLP www.ManagersResourceHandbook.com v1

Watkins Smith Corporation

RF-30 Upgrade

Jessica Abrams

May 1, 2016

October 1, 2018 C Cost

August 12, 2018 S Schedule

December 3, 2017 R Resources

On Track O Other

Number Risk Description Impact of Risk C S R O Mitigation Strategy Risk OwnerTotal Risk

Value

Probability of

Occurrence

Predicted

Risk Value

1Customer delays release of end

product into market

-Delay in investment recovery

-Reduced Sales next yearX X

-Add customer-driven delays to penalties

clause of contract

-Add milestone payments for Initial Concept

and Design Acceptance to shorten time

between payments

T. Franklin $45,000 60% $27,000

2Customer seeks to renegotiate

price based on final design

-Reduction in total projected revenue

-Business case may not be as strong

-Sales contribution from project may

need to be reduced

-Cost reduction may be needed

X X

-Track detailed cost changes throughout

design evolution to show cost adjustments

-Seek funding for changes to help absorb

non-recurring costs impacts

G. DuBois $33,050 50% $16,525

3

Specialize software is needed

based on current project

requirements

-Purchase of additional software

necessary

-Employees will need training

-Efficiency loss due to learning curve

X X X

-Negotiate with customer to use 'industry

standard' software

-Charge customer for added cost of special

software under scope change clause.

R. Nelson $77,000 25% $19,250

4

Produce Validation Testing

must be performed by 3rd

party

-Need to identify potential suppliers

-Added cost of paying 3rd party

-Schedule impact due to logisticsX X X

-Setup test program to use only internal

equipment

-Work with customer to see what tests they

can perform on our behalf

C. Jenkins $113,000 20% $22,600

5

Product Parts List exceeds

estimated value by more than

10%

-Recurring Cost in excess of business

case

-Reduced profit margin if price

remains unchanged

-Potential loss on effort

X

-Negotiate component costs with suppliers

-Renegotiate contract price with customer

based on customer-driven changes.

M. Hart $8,400 30% $2,520

6

Customer IT system/formats

cannot receive project

deliverables

-Will need to convert formats

internally

-May require specialize conversion

software

-Schedule impact if formatting issues

cannot be resolved

X X

-Test software export abilities within first

90 days

-Have customer provide list of formats to

evaluate import capabilities

R. Nelson $18,500 70% $12,950

$294,950

$100,845

Risk Values

Project Financial Summary:

42%

41%

$100,845

$119,643

75%

68%

$1.595M

$2.351M

Reporting Date

Risk Category DefinitionProject

Project Manager

Current ROS:

Estimated % Complete:

Initial Risk Value:

Current Risk Value:

Total Potential Risk (Unweighted)

Total Estimated Impact (Weighted)

Estimated Completion Date

% Budget SpendPlanned Completion Date

Category

Project Status

Customer Initial ROS:

Estimated Investment:

Current Investment:Project Start Date

Project Information

Create a Header (Continued)

Since a Risk Assessment Matrix is used by a project team and as a reporting tool, create a header of key information about the project. You may want to include: • Return on Sales (ROS) • Total Investment • % of Budget Spent • Risk Values

Watkins Smith Corporation

RF-30 Upgrade

Jessica Abrams

May 1, 2016

October 1, 2018 C Cost

August 12, 2018 S Schedule

December 3, 2017 R Resources

On Track O Other

Number Risk Description Impact of Risk C S R O Mitigation Strategy Risk OwnerTotal Risk

Value

Probability of

Occurrence

Predicted

Risk Value

1Customer delays release of end

product into market

-Delay in investment recovery

-Reduced Sales next yearX X

-Add customer-driven delays to penalties

clause of contract

-Add milestone payments for Initial Concept

and Design Acceptance to shorten time

between payments

T. Franklin $45,000 60% $27,000

2Customer seeks to renegotiate

price based on final design

-Reduction in total projected revenue

-Business case may not be as strong

-Sales contribution from project may

need to be reduced

-Cost reduction may be needed

X X

-Track detailed cost changes throughout

design evolution to show cost adjustments

-Seek funding for changes to help absorb

non-recurring costs impacts

G. DuBois $33,050 50% $16,525

3

Specialize software is needed

based on current project

requirements

-Purchase of additional software

necessary

-Employees will need training

-Efficiency loss due to learning curve

X X X

-Negotiate with customer to use 'industry

standard' software

-Charge customer for added cost of special

software under scope change clause.

R. Nelson $77,000 25% $19,250

4

Produce Validation Testing

must be performed by 3rd

party

-Need to identify potential suppliers

-Added cost of paying 3rd party

-Schedule impact due to logisticsX X X

-Setup test program to use only internal

equipment

-Work with customer to see what tests they

can perform on our behalf

C. Jenkins $113,000 20% $22,600

5

Product Parts List exceeds

estimated value by more than

10%

-Recurring Cost in excess of business

case

-Reduced profit margin if price

remains unchanged

-Potential loss on effort

X

-Negotiate component costs with suppliers

-Renegotiate contract price with customer

based on customer-driven changes.

M. Hart $8,400 30% $2,520

6

Customer IT system/formats

cannot receive project

deliverables

-Will need to convert formats

internally

-May require specialize conversion

software

-Schedule impact if formatting issues

cannot be resolved

X X

-Test software export abilities within first

90 days

-Have customer provide list of formats to

evaluate import capabilities

R. Nelson $18,500 70% $12,950

$294,950

$100,845

Risk Values

Project Financial Summary:

42%

41%

$100,845

$119,643

75%

68%

$1.595M

$2.351M

Reporting Date

Risk Category DefinitionProject

Project Manager

Current ROS:

Estimated % Complete:

Initial Risk Value:

Current Risk Value:

Total Potential Risk (Unweighted)

Total Estimated Impact (Weighted)

Estimated Completion Date

% Budget SpendPlanned Completion Date

Category

Project Status

Customer Initial ROS:

Estimated Investment:

Current Investment:Project Start Date

Project Information

Page 7: Risk Assessment Matrix - Manager's Resource Handbook · – Sums the total potential risk for a project as a function of cost • A Risk Assessment Matrix helps Project Teams plan

© All rights reserved. The Managers Resource Handbook by MHX Global LLP www.ManagersResourceHandbook.com v1

Watkins Smith Corporation

RF-30 Upgrade

Jessica Abrams

May 1, 2016

October 1, 2018 C Cost

August 12, 2018 S Schedule

December 3, 2017 R Resources

On Track O Other

Number Risk Description Impact of Risk C S R O Mitigation Strategy Risk OwnerTotal Risk

Value

Probability of

Occurrence

Predicted

Risk Value

1Customer delays release of end

product into market

-Delay in investment recovery

-Reduced Sales next yearX X

-Add customer-driven delays to penalties

clause of contract

-Add milestone payments for Initial Concept

and Design Acceptance to shorten time

between payments

T. Franklin $45,000 60% $27,000

2Customer seeks to renegotiate

price based on final design

-Reduction in total projected revenue

-Business case may not be as strong

-Sales contribution from project may

need to be reduced

-Cost reduction may be needed

X X

-Track detailed cost changes throughout

design evolution to show cost adjustments

-Seek funding for changes to help absorb

non-recurring costs impacts

G. DuBois $33,050 50% $16,525

3

Specialize software is needed

based on current project

requirements

-Purchase of additional software

necessary

-Employees will need training

-Efficiency loss due to learning curve

X X X

-Negotiate with customer to use 'industry

standard' software

-Charge customer for added cost of special

software under scope change clause.

R. Nelson $77,000 25% $19,250

4

Produce Validation Testing

must be performed by 3rd

party

-Need to identify potential suppliers

-Added cost of paying 3rd party

-Schedule impact due to logisticsX X X

-Setup test program to use only internal

equipment

-Work with customer to see what tests they

can perform on our behalf

C. Jenkins $113,000 20% $22,600

5

Product Parts List exceeds

estimated value by more than

10%

-Recurring Cost in excess of business

case

-Reduced profit margin if price

remains unchanged

-Potential loss on effort

X

-Negotiate component costs with suppliers

-Renegotiate contract price with customer

based on customer-driven changes.

M. Hart $8,400 30% $2,520

6

Customer IT system/formats

cannot receive project

deliverables

-Will need to convert formats

internally

-May require specialize conversion

software

-Schedule impact if formatting issues

cannot be resolved

X X

-Test software export abilities within first

90 days

-Have customer provide list of formats to

evaluate import capabilities

R. Nelson $18,500 70% $12,950

$294,950

$100,845

Risk Values

Project Financial Summary:

42%

41%

$100,845

$119,643

75%

68%

$1.595M

$2.351M

Reporting Date

Risk Category DefinitionProject

Project Manager

Current ROS:

Estimated % Complete:

Initial Risk Value:

Current Risk Value:

Total Potential Risk (Unweighted)

Total Estimated Impact (Weighted)

Estimated Completion Date

% Budget SpendPlanned Completion Date

Category

Project Status

Customer Initial ROS:

Estimated Investment:

Current Investment:Project Start Date

Project Information

Create a Header (Continued)

Since a Risk Assessment Matrix is used by a project team and as a reporting tool, create a header of key information about the project. You may want to include: • A Key or Legend of Definitions

Watkins Smith Corporation

RF-30 Upgrade

Jessica Abrams

May 1, 2016

October 1, 2018 C Cost

August 12, 2018 S Schedule

December 3, 2017 R Resources

On Track O Other

Number Risk Description Impact of Risk C S R O Mitigation Strategy Risk OwnerTotal Risk

Value

Probability of

Occurrence

Predicted

Risk Value

1Customer delays release of end

product into market

-Delay in investment recovery

-Reduced Sales next yearX X

-Add customer-driven delays to penalties

clause of contract

-Add milestone payments for Initial Concept

and Design Acceptance to shorten time

between payments

T. Franklin $45,000 60% $27,000

2Customer seeks to renegotiate

price based on final design

-Reduction in total projected revenue

-Business case may not be as strong

-Sales contribution from project may

need to be reduced

-Cost reduction may be needed

X X

-Track detailed cost changes throughout

design evolution to show cost adjustments

-Seek funding for changes to help absorb

non-recurring costs impacts

G. DuBois $33,050 50% $16,525

3

Specialize software is needed

based on current project

requirements

-Purchase of additional software

necessary

-Employees will need training

-Efficiency loss due to learning curve

X X X

-Negotiate with customer to use 'industry

standard' software

-Charge customer for added cost of special

software under scope change clause.

R. Nelson $77,000 25% $19,250

4

Produce Validation Testing

must be performed by 3rd

party

-Need to identify potential suppliers

-Added cost of paying 3rd party

-Schedule impact due to logisticsX X X

-Setup test program to use only internal

equipment

-Work with customer to see what tests they

can perform on our behalf

C. Jenkins $113,000 20% $22,600

5

Product Parts List exceeds

estimated value by more than

10%

-Recurring Cost in excess of business

case

-Reduced profit margin if price

remains unchanged

-Potential loss on effort

X

-Negotiate component costs with suppliers

-Renegotiate contract price with customer

based on customer-driven changes.

M. Hart $8,400 30% $2,520

6

Customer IT system/formats

cannot receive project

deliverables

-Will need to convert formats

internally

-May require specialize conversion

software

-Schedule impact if formatting issues

cannot be resolved

X X

-Test software export abilities within first

90 days

-Have customer provide list of formats to

evaluate import capabilities

R. Nelson $18,500 70% $12,950

$294,950

$100,845

Risk Values

Project Financial Summary:

42%

41%

$100,845

$119,643

75%

68%

$1.595M

$2.351M

Reporting Date

Risk Category DefinitionProject

Project Manager

Current ROS:

Estimated % Complete:

Initial Risk Value:

Current Risk Value:

Total Potential Risk (Unweighted)

Total Estimated Impact (Weighted)

Estimated Completion Date

% Budget SpendPlanned Completion Date

Category

Project Status

Customer Initial ROS:

Estimated Investment:

Current Investment:Project Start Date

Project Information

Page 8: Risk Assessment Matrix - Manager's Resource Handbook · – Sums the total potential risk for a project as a function of cost • A Risk Assessment Matrix helps Project Teams plan

© All rights reserved. The Managers Resource Handbook by MHX Global LLP www.ManagersResourceHandbook.com v1

Watkins Smith Corporation

RF-30 Upgrade

Jessica Abrams

May 1, 2016

October 1, 2018 C Cost

August 12, 2018 S Schedule

December 3, 2017 R Resources

On Track O Other

Number Risk Description Impact of Risk C S R O Mitigation Strategy Risk OwnerTotal Risk

Value

Probability of

Occurrence

Predicted

Risk Value

1Customer delays release of end

product into market

-Delay in investment recovery

-Reduced Sales next yearX X

-Add customer-driven delays to penalties

clause of contract

-Add milestone payments for Initial Concept

and Design Acceptance to shorten time

between payments

T. Franklin $45,000 60% $27,000

2Customer seeks to renegotiate

price based on final design

-Reduction in total projected revenue

-Business case may not be as strong

-Sales contribution from project may

need to be reduced

-Cost reduction may be needed

X X

-Track detailed cost changes throughout

design evolution to show cost adjustments

-Seek funding for changes to help absorb

non-recurring costs impacts

G. DuBois $33,050 50% $16,525

3

Specialize software is needed

based on current project

requirements

-Purchase of additional software

necessary

-Employees will need training

-Efficiency loss due to learning curve

X X X

-Negotiate with customer to use 'industry

standard' software

-Charge customer for added cost of special

software under scope change clause.

R. Nelson $77,000 25% $19,250

4

Produce Validation Testing

must be performed by 3rd

party

-Need to identify potential suppliers

-Added cost of paying 3rd party

-Schedule impact due to logisticsX X X

-Setup test program to use only internal

equipment

-Work with customer to see what tests they

can perform on our behalf

C. Jenkins $113,000 20% $22,600

5

Product Parts List exceeds

estimated value by more than

10%

-Recurring Cost in excess of business

case

-Reduced profit margin if price

remains unchanged

-Potential loss on effort

X

-Negotiate component costs with suppliers

-Renegotiate contract price with customer

based on customer-driven changes.

M. Hart $8,400 30% $2,520

6

Customer IT system/formats

cannot receive project

deliverables

-Will need to convert formats

internally

-May require specialize conversion

software

-Schedule impact if formatting issues

cannot be resolved

X X

-Test software export abilities within first

90 days

-Have customer provide list of formats to

evaluate import capabilities

R. Nelson $18,500 70% $12,950

$294,950

$100,845

Risk Values

Project Financial Summary:

42%

41%

$100,845

$119,643

75%

68%

$1.595M

$2.351M

Reporting Date

Risk Category DefinitionProject

Project Manager

Current ROS:

Estimated % Complete:

Initial Risk Value:

Current Risk Value:

Total Potential Risk (Unweighted)

Total Estimated Impact (Weighted)

Estimated Completion Date

% Budget SpendPlanned Completion Date

Category

Project Status

Customer Initial ROS:

Estimated Investment:

Current Investment:Project Start Date

Project Information

Step 1: Identify The Risk

• Meet with Project Team • Brainstorm all possible issues and concerns • Group them into main buckets

• NOTE: Be thorough… but realistic!

Watkins Smith Corporation

RF-30 Upgrade

Jessica Abrams

May 1, 2016

October 1, 2018 C Cost

August 12, 2018 S Schedule

December 3, 2017 R Resources

On Track O Other

Number Risk Description Impact of Risk C S R O Mitigation Strategy Risk OwnerTotal Risk

Value

Probability of

Occurrence

Predicted

Risk Value

1Customer delays release of end

product into market

-Delay in investment recovery

-Reduced Sales next yearX X

-Add customer-driven delays to penalties

clause of contract

-Add milestone payments for Initial Concept

and Design Acceptance to shorten time

between payments

T. Franklin $45,000 60% $27,000

2Customer seeks to renegotiate

price based on final design

-Reduction in total projected revenue

-Business case may not be as strong

-Sales contribution from project may

need to be reduced

-Cost reduction may be needed

X X

-Track detailed cost changes throughout

design evolution to show cost adjustments

-Seek funding for changes to help absorb

non-recurring costs impacts

G. DuBois $33,050 50% $16,525

3

Specialize software is needed

based on current project

requirements

-Purchase of additional software

necessary

-Employees will need training

-Efficiency loss due to learning curve

X X X

-Negotiate with customer to use 'industry

standard' software

-Charge customer for added cost of special

software under scope change clause.

R. Nelson $77,000 25% $19,250

4

Produce Validation Testing

must be performed by 3rd

party

-Need to identify potential suppliers

-Added cost of paying 3rd party

-Schedule impact due to logisticsX X X

-Setup test program to use only internal

equipment

-Work with customer to see what tests they

can perform on our behalf

C. Jenkins $113,000 20% $22,600

5

Product Parts List exceeds

estimated value by more than

10%

-Recurring Cost in excess of business

case

-Reduced profit margin if price

remains unchanged

-Potential loss on effort

X

-Negotiate component costs with suppliers

-Renegotiate contract price with customer

based on customer-driven changes.

M. Hart $8,400 30% $2,520

6

Customer IT system/formats

cannot receive project

deliverables

-Will need to convert formats

internally

-May require specialize conversion

software

-Schedule impact if formatting issues

cannot be resolved

X X

-Test software export abilities within first

90 days

-Have customer provide list of formats to

evaluate import capabilities

R. Nelson $18,500 70% $12,950

$294,950

$100,845

Risk Values

Project Financial Summary:

42%

41%

$100,845

$119,643

75%

68%

$1.595M

$2.351M

Reporting Date

Risk Category DefinitionProject

Project Manager

Current ROS:

Estimated % Complete:

Initial Risk Value:

Current Risk Value:

Total Potential Risk (Unweighted)

Total Estimated Impact (Weighted)

Estimated Completion Date

% Budget SpendPlanned Completion Date

Category

Project Status

Customer Initial ROS:

Estimated Investment:

Current Investment:Project Start Date

Project Information

Page 9: Risk Assessment Matrix - Manager's Resource Handbook · – Sums the total potential risk for a project as a function of cost • A Risk Assessment Matrix helps Project Teams plan

© All rights reserved. The Managers Resource Handbook by MHX Global LLP www.ManagersResourceHandbook.com v1

Watkins Smith Corporation

RF-30 Upgrade

Jessica Abrams

May 1, 2016

October 1, 2018 C Cost

August 12, 2018 S Schedule

December 3, 2017 R Resources

On Track O Other

Number Risk Description Impact of Risk C S R O Mitigation Strategy Risk OwnerTotal Risk

Value

Probability of

Occurrence

Predicted

Risk Value

1Customer delays release of end

product into market

-Delay in investment recovery

-Reduced Sales next yearX X

-Add customer-driven delays to penalties

clause of contract

-Add milestone payments for Initial Concept

and Design Acceptance to shorten time

between payments

T. Franklin $45,000 60% $27,000

2Customer seeks to renegotiate

price based on final design

-Reduction in total projected revenue

-Business case may not be as strong

-Sales contribution from project may

need to be reduced

-Cost reduction may be needed

X X

-Track detailed cost changes throughout

design evolution to show cost adjustments

-Seek funding for changes to help absorb

non-recurring costs impacts

G. DuBois $33,050 50% $16,525

3

Specialize software is needed

based on current project

requirements

-Purchase of additional software

necessary

-Employees will need training

-Efficiency loss due to learning curve

X X X

-Negotiate with customer to use 'industry

standard' software

-Charge customer for added cost of special

software under scope change clause.

R. Nelson $77,000 25% $19,250

4

Produce Validation Testing

must be performed by 3rd

party

-Need to identify potential suppliers

-Added cost of paying 3rd party

-Schedule impact due to logisticsX X X

-Setup test program to use only internal

equipment

-Work with customer to see what tests they

can perform on our behalf

C. Jenkins $113,000 20% $22,600

5

Product Parts List exceeds

estimated value by more than

10%

-Recurring Cost in excess of business

case

-Reduced profit margin if price

remains unchanged

-Potential loss on effort

X

-Negotiate component costs with suppliers

-Renegotiate contract price with customer

based on customer-driven changes.

M. Hart $8,400 30% $2,520

6

Customer IT system/formats

cannot receive project

deliverables

-Will need to convert formats

internally

-May require specialize conversion

software

-Schedule impact if formatting issues

cannot be resolved

X X

-Test software export abilities within first

90 days

-Have customer provide list of formats to

evaluate import capabilities

R. Nelson $18,500 70% $12,950

$294,950

$100,845

Risk Values

Project Financial Summary:

42%

41%

$100,845

$119,643

75%

68%

$1.595M

$2.351M

Reporting Date

Risk Category DefinitionProject

Project Manager

Current ROS:

Estimated % Complete:

Initial Risk Value:

Current Risk Value:

Total Potential Risk (Unweighted)

Total Estimated Impact (Weighted)

Estimated Completion Date

% Budget SpendPlanned Completion Date

Category

Project Status

Customer Initial ROS:

Estimated Investment:

Current Investment:Project Start Date

Project Information

Step 2: Define the Impact

If the risk became ‘real,’ how would it affect the project? • More Time? • Added Cost? • Require More Resources? • Change Pricing Strategy?

Watkins Smith Corporation

RF-30 Upgrade

Jessica Abrams

May 1, 2016

October 1, 2018 C Cost

August 12, 2018 S Schedule

December 3, 2017 R Resources

On Track O Other

Number Risk Description Impact of Risk C S R O Mitigation Strategy Risk OwnerTotal Risk

Value

Probability of

Occurrence

Predicted

Risk Value

1Customer delays release of end

product into market

-Delay in investment recovery

-Reduced Sales next yearX X

-Add customer-driven delays to penalties

clause of contract

-Add milestone payments for Initial Concept

and Design Acceptance to shorten time

between payments

T. Franklin $45,000 60% $27,000

2Customer seeks to renegotiate

price based on final design

-Reduction in total projected revenue

-Business case may not be as strong

-Sales contribution from project may

need to be reduced

-Cost reduction may be needed

X X

-Track detailed cost changes throughout

design evolution to show cost adjustments

-Seek funding for changes to help absorb

non-recurring costs impacts

G. DuBois $33,050 50% $16,525

3

Specialize software is needed

based on current project

requirements

-Purchase of additional software

necessary

-Employees will need training

-Efficiency loss due to learning curve

X X X

-Negotiate with customer to use 'industry

standard' software

-Charge customer for added cost of special

software under scope change clause.

R. Nelson $77,000 25% $19,250

4

Produce Validation Testing

must be performed by 3rd

party

-Need to identify potential suppliers

-Added cost of paying 3rd party

-Schedule impact due to logisticsX X X

-Setup test program to use only internal

equipment

-Work with customer to see what tests they

can perform on our behalf

C. Jenkins $113,000 20% $22,600

5

Product Parts List exceeds

estimated value by more than

10%

-Recurring Cost in excess of business

case

-Reduced profit margin if price

remains unchanged

-Potential loss on effort

X

-Negotiate component costs with suppliers

-Renegotiate contract price with customer

based on customer-driven changes.

M. Hart $8,400 30% $2,520

6

Customer IT system/formats

cannot receive project

deliverables

-Will need to convert formats

internally

-May require specialize conversion

software

-Schedule impact if formatting issues

cannot be resolved

X X

-Test software export abilities within first

90 days

-Have customer provide list of formats to

evaluate import capabilities

R. Nelson $18,500 70% $12,950

$294,950

$100,845

Risk Values

Project Financial Summary:

42%

41%

$100,845

$119,643

75%

68%

$1.595M

$2.351M

Reporting Date

Risk Category DefinitionProject

Project Manager

Current ROS:

Estimated % Complete:

Initial Risk Value:

Current Risk Value:

Total Potential Risk (Unweighted)

Total Estimated Impact (Weighted)

Estimated Completion Date

% Budget SpendPlanned Completion Date

Category

Project Status

Customer Initial ROS:

Estimated Investment:

Current Investment:Project Start Date

Project Information

Page 10: Risk Assessment Matrix - Manager's Resource Handbook · – Sums the total potential risk for a project as a function of cost • A Risk Assessment Matrix helps Project Teams plan

© All rights reserved. The Managers Resource Handbook by MHX Global LLP www.ManagersResourceHandbook.com v1

Watkins Smith Corporation

RF-30 Upgrade

Jessica Abrams

May 1, 2016

October 1, 2018 C Cost

August 12, 2018 S Schedule

December 3, 2017 R Resources

On Track O Other

Number Risk Description Impact of Risk C S R O Mitigation Strategy Risk OwnerTotal Risk

Value

Probability of

Occurrence

Predicted

Risk Value

1Customer delays release of end

product into market

-Delay in investment recovery

-Reduced Sales next yearX X

-Add customer-driven delays to penalties

clause of contract

-Add milestone payments for Initial Concept

and Design Acceptance to shorten time

between payments

T. Franklin $45,000 60% $27,000

2Customer seeks to renegotiate

price based on final design

-Reduction in total projected revenue

-Business case may not be as strong

-Sales contribution from project may

need to be reduced

-Cost reduction may be needed

X X

-Track detailed cost changes throughout

design evolution to show cost adjustments

-Seek funding for changes to help absorb

non-recurring costs impacts

G. DuBois $33,050 50% $16,525

3

Specialize software is needed

based on current project

requirements

-Purchase of additional software

necessary

-Employees will need training

-Efficiency loss due to learning curve

X X X

-Negotiate with customer to use 'industry

standard' software

-Charge customer for added cost of special

software under scope change clause.

R. Nelson $77,000 25% $19,250

4

Produce Validation Testing

must be performed by 3rd

party

-Need to identify potential suppliers

-Added cost of paying 3rd party

-Schedule impact due to logisticsX X X

-Setup test program to use only internal

equipment

-Work with customer to see what tests they

can perform on our behalf

C. Jenkins $113,000 20% $22,600

5

Product Parts List exceeds

estimated value by more than

10%

-Recurring Cost in excess of business

case

-Reduced profit margin if price

remains unchanged

-Potential loss on effort

X

-Negotiate component costs with suppliers

-Renegotiate contract price with customer

based on customer-driven changes.

M. Hart $8,400 30% $2,520

6

Customer IT system/formats

cannot receive project

deliverables

-Will need to convert formats

internally

-May require specialize conversion

software

-Schedule impact if formatting issues

cannot be resolved

X X

-Test software export abilities within first

90 days

-Have customer provide list of formats to

evaluate import capabilities

R. Nelson $18,500 70% $12,950

$294,950

$100,845

Risk Values

Project Financial Summary:

42%

41%

$100,845

$119,643

75%

68%

$1.595M

$2.351M

Reporting Date

Risk Category DefinitionProject

Project Manager

Current ROS:

Estimated % Complete:

Initial Risk Value:

Current Risk Value:

Total Potential Risk (Unweighted)

Total Estimated Impact (Weighted)

Estimated Completion Date

% Budget SpendPlanned Completion Date

Category

Project Status

Customer Initial ROS:

Estimated Investment:

Current Investment:Project Start Date

Project Information

Step 3: Categorize the Risk

For Communication purposes, and to help sort information, categorize the risk. Some ways you can categorize: • Types of Impact • Product Families • Customer • Regional Location

• NOTE: Risks may have more than one category

Watkins Smith Corporation

RF-30 Upgrade

Jessica Abrams

May 1, 2016

October 1, 2018 C Cost

August 12, 2018 S Schedule

December 3, 2017 R Resources

On Track O Other

Number Risk Description Impact of Risk C S R O Mitigation Strategy Risk OwnerTotal Risk

Value

Probability of

Occurrence

Predicted

Risk Value

1Customer delays release of end

product into market

-Delay in investment recovery

-Reduced Sales next yearX X

-Add customer-driven delays to penalties

clause of contract

-Add milestone payments for Initial Concept

and Design Acceptance to shorten time

between payments

T. Franklin $45,000 60% $27,000

2Customer seeks to renegotiate

price based on final design

-Reduction in total projected revenue

-Business case may not be as strong

-Sales contribution from project may

need to be reduced

-Cost reduction may be needed

X X

-Track detailed cost changes throughout

design evolution to show cost adjustments

-Seek funding for changes to help absorb

non-recurring costs impacts

G. DuBois $33,050 50% $16,525

3

Specialize software is needed

based on current project

requirements

-Purchase of additional software

necessary

-Employees will need training

-Efficiency loss due to learning curve

X X X

-Negotiate with customer to use 'industry

standard' software

-Charge customer for added cost of special

software under scope change clause.

R. Nelson $77,000 25% $19,250

4

Produce Validation Testing

must be performed by 3rd

party

-Need to identify potential suppliers

-Added cost of paying 3rd party

-Schedule impact due to logisticsX X X

-Setup test program to use only internal

equipment

-Work with customer to see what tests they

can perform on our behalf

C. Jenkins $113,000 20% $22,600

5

Product Parts List exceeds

estimated value by more than

10%

-Recurring Cost in excess of business

case

-Reduced profit margin if price

remains unchanged

-Potential loss on effort

X

-Negotiate component costs with suppliers

-Renegotiate contract price with customer

based on customer-driven changes.

M. Hart $8,400 30% $2,520

6

Customer IT system/formats

cannot receive project

deliverables

-Will need to convert formats

internally

-May require specialize conversion

software

-Schedule impact if formatting issues

cannot be resolved

X X

-Test software export abilities within first

90 days

-Have customer provide list of formats to

evaluate import capabilities

R. Nelson $18,500 70% $12,950

$294,950

$100,845

Risk Values

Project Financial Summary:

42%

41%

$100,845

$119,643

75%

68%

$1.595M

$2.351M

Reporting Date

Risk Category DefinitionProject

Project Manager

Current ROS:

Estimated % Complete:

Initial Risk Value:

Current Risk Value:

Total Potential Risk (Unweighted)

Total Estimated Impact (Weighted)

Estimated Completion Date

% Budget SpendPlanned Completion Date

Category

Project Status

Customer Initial ROS:

Estimated Investment:

Current Investment:Project Start Date

Project Information

Page 11: Risk Assessment Matrix - Manager's Resource Handbook · – Sums the total potential risk for a project as a function of cost • A Risk Assessment Matrix helps Project Teams plan

© All rights reserved. The Managers Resource Handbook by MHX Global LLP www.ManagersResourceHandbook.com v1

Watkins Smith Corporation

RF-30 Upgrade

Jessica Abrams

May 1, 2016

October 1, 2018 C Cost

August 12, 2018 S Schedule

December 3, 2017 R Resources

On Track O Other

Number Risk Description Impact of Risk C S R O Mitigation Strategy Risk OwnerTotal Risk

Value

Probability of

Occurrence

Predicted

Risk Value

1Customer delays release of end

product into market

-Delay in investment recovery

-Reduced Sales next yearX X

-Add customer-driven delays to penalties

clause of contract

-Add milestone payments for Initial Concept

and Design Acceptance to shorten time

between payments

T. Franklin $45,000 60% $27,000

2Customer seeks to renegotiate

price based on final design

-Reduction in total projected revenue

-Business case may not be as strong

-Sales contribution from project may

need to be reduced

-Cost reduction may be needed

X X

-Track detailed cost changes throughout

design evolution to show cost adjustments

-Seek funding for changes to help absorb

non-recurring costs impacts

G. DuBois $33,050 50% $16,525

3

Specialize software is needed

based on current project

requirements

-Purchase of additional software

necessary

-Employees will need training

-Efficiency loss due to learning curve

X X X

-Negotiate with customer to use 'industry

standard' software

-Charge customer for added cost of special

software under scope change clause.

R. Nelson $77,000 25% $19,250

4

Produce Validation Testing

must be performed by 3rd

party

-Need to identify potential suppliers

-Added cost of paying 3rd party

-Schedule impact due to logisticsX X X

-Setup test program to use only internal

equipment

-Work with customer to see what tests they

can perform on our behalf

C. Jenkins $113,000 20% $22,600

5

Product Parts List exceeds

estimated value by more than

10%

-Recurring Cost in excess of business

case

-Reduced profit margin if price

remains unchanged

-Potential loss on effort

X

-Negotiate component costs with suppliers

-Renegotiate contract price with customer

based on customer-driven changes.

M. Hart $8,400 30% $2,520

6

Customer IT system/formats

cannot receive project

deliverables

-Will need to convert formats

internally

-May require specialize conversion

software

-Schedule impact if formatting issues

cannot be resolved

X X

-Test software export abilities within first

90 days

-Have customer provide list of formats to

evaluate import capabilities

R. Nelson $18,500 70% $12,950

$294,950

$100,845

Risk Values

Project Financial Summary:

42%

41%

$100,845

$119,643

75%

68%

$1.595M

$2.351M

Reporting Date

Risk Category DefinitionProject

Project Manager

Current ROS:

Estimated % Complete:

Initial Risk Value:

Current Risk Value:

Total Potential Risk (Unweighted)

Total Estimated Impact (Weighted)

Estimated Completion Date

% Budget SpendPlanned Completion Date

Category

Project Status

Customer Initial ROS:

Estimated Investment:

Current Investment:Project Start Date

Project Information

Step 4: Define Mitigation Strategies • What can you do to influence the outcome of the risks,

or mitigate their impact? • What can you do to protect the project?

Watkins Smith Corporation

RF-30 Upgrade

Jessica Abrams

May 1, 2016

October 1, 2018 C Cost

August 12, 2018 S Schedule

December 3, 2017 R Resources

On Track O Other

Number Risk Description Impact of Risk C S R O Mitigation Strategy Risk OwnerTotal Risk

Value

Probability of

Occurrence

Predicted

Risk Value

1Customer delays release of end

product into market

-Delay in investment recovery

-Reduced Sales next yearX X

-Add customer-driven delays to penalties

clause of contract

-Add milestone payments for Initial Concept

and Design Acceptance to shorten time

between payments

T. Franklin $45,000 60% $27,000

2Customer seeks to renegotiate

price based on final design

-Reduction in total projected revenue

-Business case may not be as strong

-Sales contribution from project may

need to be reduced

-Cost reduction may be needed

X X

-Track detailed cost changes throughout

design evolution to show cost adjustments

-Seek funding for changes to help absorb

non-recurring costs impacts

G. DuBois $33,050 50% $16,525

3

Specialize software is needed

based on current project

requirements

-Purchase of additional software

necessary

-Employees will need training

-Efficiency loss due to learning curve

X X X

-Negotiate with customer to use 'industry

standard' software

-Charge customer for added cost of special

software under scope change clause.

R. Nelson $77,000 25% $19,250

4

Produce Validation Testing

must be performed by 3rd

party

-Need to identify potential suppliers

-Added cost of paying 3rd party

-Schedule impact due to logisticsX X X

-Setup test program to use only internal

equipment

-Work with customer to see what tests they

can perform on our behalf

C. Jenkins $113,000 20% $22,600

5

Product Parts List exceeds

estimated value by more than

10%

-Recurring Cost in excess of business

case

-Reduced profit margin if price

remains unchanged

-Potential loss on effort

X

-Negotiate component costs with suppliers

-Renegotiate contract price with customer

based on customer-driven changes.

M. Hart $8,400 30% $2,520

6

Customer IT system/formats

cannot receive project

deliverables

-Will need to convert formats

internally

-May require specialize conversion

software

-Schedule impact if formatting issues

cannot be resolved

X X

-Test software export abilities within first

90 days

-Have customer provide list of formats to

evaluate import capabilities

R. Nelson $18,500 70% $12,950

$294,950

$100,845

Risk Values

Project Financial Summary:

42%

41%

$100,845

$119,643

75%

68%

$1.595M

$2.351M

Reporting Date

Risk Category DefinitionProject

Project Manager

Current ROS:

Estimated % Complete:

Initial Risk Value:

Current Risk Value:

Total Potential Risk (Unweighted)

Total Estimated Impact (Weighted)

Estimated Completion Date

% Budget SpendPlanned Completion Date

Category

Project Status

Customer Initial ROS:

Estimated Investment:

Current Investment:Project Start Date

Project Information

Page 12: Risk Assessment Matrix - Manager's Resource Handbook · – Sums the total potential risk for a project as a function of cost • A Risk Assessment Matrix helps Project Teams plan

© All rights reserved. The Managers Resource Handbook by MHX Global LLP www.ManagersResourceHandbook.com v1

Watkins Smith Corporation

RF-30 Upgrade

Jessica Abrams

May 1, 2016

October 1, 2018 C Cost

August 12, 2018 S Schedule

December 3, 2017 R Resources

On Track O Other

Number Risk Description Impact of Risk C S R O Mitigation Strategy Risk OwnerTotal Risk

Value

Probability of

Occurrence

Predicted

Risk Value

1Customer delays release of end

product into market

-Delay in investment recovery

-Reduced Sales next yearX X

-Add customer-driven delays to penalties

clause of contract

-Add milestone payments for Initial Concept

and Design Acceptance to shorten time

between payments

T. Franklin $45,000 60% $27,000

2Customer seeks to renegotiate

price based on final design

-Reduction in total projected revenue

-Business case may not be as strong

-Sales contribution from project may

need to be reduced

-Cost reduction may be needed

X X

-Track detailed cost changes throughout

design evolution to show cost adjustments

-Seek funding for changes to help absorb

non-recurring costs impacts

G. DuBois $33,050 50% $16,525

3

Specialize software is needed

based on current project

requirements

-Purchase of additional software

necessary

-Employees will need training

-Efficiency loss due to learning curve

X X X

-Negotiate with customer to use 'industry

standard' software

-Charge customer for added cost of special

software under scope change clause.

R. Nelson $77,000 25% $19,250

4

Produce Validation Testing

must be performed by 3rd

party

-Need to identify potential suppliers

-Added cost of paying 3rd party

-Schedule impact due to logisticsX X X

-Setup test program to use only internal

equipment

-Work with customer to see what tests they

can perform on our behalf

C. Jenkins $113,000 20% $22,600

5

Product Parts List exceeds

estimated value by more than

10%

-Recurring Cost in excess of business

case

-Reduced profit margin if price

remains unchanged

-Potential loss on effort

X

-Negotiate component costs with suppliers

-Renegotiate contract price with customer

based on customer-driven changes.

M. Hart $8,400 30% $2,520

6

Customer IT system/formats

cannot receive project

deliverables

-Will need to convert formats

internally

-May require specialize conversion

software

-Schedule impact if formatting issues

cannot be resolved

X X

-Test software export abilities within first

90 days

-Have customer provide list of formats to

evaluate import capabilities

R. Nelson $18,500 70% $12,950

$294,950

$100,845

Risk Values

Project Financial Summary:

42%

41%

$100,845

$119,643

75%

68%

$1.595M

$2.351M

Reporting Date

Risk Category DefinitionProject

Project Manager

Current ROS:

Estimated % Complete:

Initial Risk Value:

Current Risk Value:

Total Potential Risk (Unweighted)

Total Estimated Impact (Weighted)

Estimated Completion Date

% Budget SpendPlanned Completion Date

Category

Project Status

Customer Initial ROS:

Estimated Investment:

Current Investment:Project Start Date

Project Information

Step 5: Identify the Risk Owner

Ownership is a form of accountability. List the name(s) of those individuals who are primarily responsible for managing and mitigating the risk item.

Page 13: Risk Assessment Matrix - Manager's Resource Handbook · – Sums the total potential risk for a project as a function of cost • A Risk Assessment Matrix helps Project Teams plan

© All rights reserved. The Managers Resource Handbook by MHX Global LLP www.ManagersResourceHandbook.com v1

Watkins Smith Corporation

RF-30 Upgrade

Jessica Abrams

May 1, 2016

October 1, 2018 C Cost

August 12, 2018 S Schedule

December 3, 2017 R Resources

On Track O Other

Number Risk Description Impact of Risk C S R O Mitigation Strategy Risk OwnerTotal Risk

Value

Probability of

Occurrence

Predicted

Risk Value

1Customer delays release of end

product into market

-Delay in investment recovery

-Reduced Sales next yearX X

-Add customer-driven delays to penalties

clause of contract

-Add milestone payments for Initial Concept

and Design Acceptance to shorten time

between payments

T. Franklin $45,000 60% $27,000

2Customer seeks to renegotiate

price based on final design

-Reduction in total projected revenue

-Business case may not be as strong

-Sales contribution from project may

need to be reduced

-Cost reduction may be needed

X X

-Track detailed cost changes throughout

design evolution to show cost adjustments

-Seek funding for changes to help absorb

non-recurring costs impacts

G. DuBois $33,050 50% $16,525

3

Specialize software is needed

based on current project

requirements

-Purchase of additional software

necessary

-Employees will need training

-Efficiency loss due to learning curve

X X X

-Negotiate with customer to use 'industry

standard' software

-Charge customer for added cost of special

software under scope change clause.

R. Nelson $77,000 25% $19,250

4

Produce Validation Testing

must be performed by 3rd

party

-Need to identify potential suppliers

-Added cost of paying 3rd party

-Schedule impact due to logisticsX X X

-Setup test program to use only internal

equipment

-Work with customer to see what tests they

can perform on our behalf

C. Jenkins $113,000 20% $22,600

5

Product Parts List exceeds

estimated value by more than

10%

-Recurring Cost in excess of business

case

-Reduced profit margin if price

remains unchanged

-Potential loss on effort

X

-Negotiate component costs with suppliers

-Renegotiate contract price with customer

based on customer-driven changes.

M. Hart $8,400 30% $2,520

6

Customer IT system/formats

cannot receive project

deliverables

-Will need to convert formats

internally

-May require specialize conversion

software

-Schedule impact if formatting issues

cannot be resolved

X X

-Test software export abilities within first

90 days

-Have customer provide list of formats to

evaluate import capabilities

R. Nelson $18,500 70% $12,950

$294,950

$100,845

Risk Values

Project Financial Summary:

42%

41%

$100,845

$119,643

75%

68%

$1.595M

$2.351M

Reporting Date

Risk Category DefinitionProject

Project Manager

Current ROS:

Estimated % Complete:

Initial Risk Value:

Current Risk Value:

Total Potential Risk (Unweighted)

Total Estimated Impact (Weighted)

Estimated Completion Date

% Budget SpendPlanned Completion Date

Category

Project Status

Customer Initial ROS:

Estimated Investment:

Current Investment:Project Start Date

Project Information

Step 6: Quantify the Total Value of Each Risk

Calculate the total financial value of the risk, if it were to occur. This is a similar exercise to estimating a new project. • How much more time would be needed? • How many hours of effort are required? • What is the Hourly Rate? • What additional expenses (travel, materials, supplies) are there?

Page 14: Risk Assessment Matrix - Manager's Resource Handbook · – Sums the total potential risk for a project as a function of cost • A Risk Assessment Matrix helps Project Teams plan

© All rights reserved. The Managers Resource Handbook by MHX Global LLP www.ManagersResourceHandbook.com v1

Number HoursRate

($/Hour)

Travel

($2000/Trip)

Other

ExpensesTotal

1 300 $30 $16,000 $20,000 $45,000

2 490 $45 $6,000 $5,000 $33,050

3 600 $45 $0 $50,000 $77,000

4 500 $30 $8,000 $90,000 $113,000

5 240 $35 $0 $0 $8,400

6 100 $35 $0 $15,000 $18,500

Cost Calculations

Step 6 (Continued): Keep The Assumptions Nearby

Your assumptions may need to change as time goes by. Include these values in your template off to the side, or on another tab of the spreadsheet. The “Total” value corresponds to the “Total Risk Value” in the Risk Assessment Matrix. Things to include: • Time (Hours) • Hourly Rates • Travel Costs • Additional expenses (software,

materials, supplies)

Page 15: Risk Assessment Matrix - Manager's Resource Handbook · – Sums the total potential risk for a project as a function of cost • A Risk Assessment Matrix helps Project Teams plan

© All rights reserved. The Managers Resource Handbook by MHX Global LLP www.ManagersResourceHandbook.com v1

Watkins Smith Corporation

RF-30 Upgrade

Jessica Abrams

May 1, 2016

October 1, 2018 C Cost

August 12, 2018 S Schedule

December 3, 2017 R Resources

On Track O Other

Number Risk Description Impact of Risk C S R O Mitigation Strategy Risk OwnerTotal Risk

Value

Probability of

Occurrence

Predicted

Risk Value

1Customer delays release of end

product into market

-Delay in investment recovery

-Reduced Sales next yearX X

-Add customer-driven delays to penalties

clause of contract

-Add milestone payments for Initial Concept

and Design Acceptance to shorten time

between payments

T. Franklin $45,000 60% $27,000

2Customer seeks to renegotiate

price based on final design

-Reduction in total projected revenue

-Business case may not be as strong

-Sales contribution from project may

need to be reduced

-Cost reduction may be needed

X X

-Track detailed cost changes throughout

design evolution to show cost adjustments

-Seek funding for changes to help absorb

non-recurring costs impacts

G. DuBois $33,050 50% $16,525

3

Specialize software is needed

based on current project

requirements

-Purchase of additional software

necessary

-Employees will need training

-Efficiency loss due to learning curve

X X X

-Negotiate with customer to use 'industry

standard' software

-Charge customer for added cost of special

software under scope change clause.

R. Nelson $77,000 25% $19,250

4

Produce Validation Testing

must be performed by 3rd

party

-Need to identify potential suppliers

-Added cost of paying 3rd party

-Schedule impact due to logisticsX X X

-Setup test program to use only internal

equipment

-Work with customer to see what tests they

can perform on our behalf

C. Jenkins $113,000 20% $22,600

5

Product Parts List exceeds

estimated value by more than

10%

-Recurring Cost in excess of business

case

-Reduced profit margin if price

remains unchanged

-Potential loss on effort

X

-Negotiate component costs with suppliers

-Renegotiate contract price with customer

based on customer-driven changes.

M. Hart $8,400 30% $2,520

6

Customer IT system/formats

cannot receive project

deliverables

-Will need to convert formats

internally

-May require specialize conversion

software

-Schedule impact if formatting issues

cannot be resolved

X X

-Test software export abilities within first

90 days

-Have customer provide list of formats to

evaluate import capabilities

R. Nelson $18,500 70% $12,950

$294,950

$100,845

Risk Values

Project Financial Summary:

42%

41%

$100,845

$119,643

75%

68%

$1.595M

$2.351M

Reporting Date

Risk Category DefinitionProject

Project Manager

Current ROS:

Estimated % Complete:

Initial Risk Value:

Current Risk Value:

Total Potential Risk (Unweighted)

Total Estimated Impact (Weighted)

Estimated Completion Date

% Budget SpendPlanned Completion Date

Category

Project Status

Customer Initial ROS:

Estimated Investment:

Current Investment:Project Start Date

Project Information

Step 7: Estimate Probability of Occurrence

Estimate the probability that each risk will occur. This estimate should be revised over time. If a risk becomes real, set the probability to 100%. Reduce the probability as issues and risks are mitigated or eliminated.

Page 16: Risk Assessment Matrix - Manager's Resource Handbook · – Sums the total potential risk for a project as a function of cost • A Risk Assessment Matrix helps Project Teams plan

© All rights reserved. The Managers Resource Handbook by MHX Global LLP www.ManagersResourceHandbook.com v1

Watkins Smith Corporation

RF-30 Upgrade

Jessica Abrams

May 1, 2016

October 1, 2018 C Cost

August 12, 2018 S Schedule

December 3, 2017 R Resources

On Track O Other

Number Risk Description Impact of Risk C S R O Mitigation Strategy Risk OwnerTotal Risk

Value

Probability of

Occurrence

Predicted

Risk Value

1Customer delays release of end

product into market

-Delay in investment recovery

-Reduced Sales next yearX X

-Add customer-driven delays to penalties

clause of contract

-Add milestone payments for Initial Concept

and Design Acceptance to shorten time

between payments

T. Franklin $45,000 60% $27,000

2Customer seeks to renegotiate

price based on final design

-Reduction in total projected revenue

-Business case may not be as strong

-Sales contribution from project may

need to be reduced

-Cost reduction may be needed

X X

-Track detailed cost changes throughout

design evolution to show cost adjustments

-Seek funding for changes to help absorb

non-recurring costs impacts

G. DuBois $33,050 50% $16,525

3

Specialize software is needed

based on current project

requirements

-Purchase of additional software

necessary

-Employees will need training

-Efficiency loss due to learning curve

X X X

-Negotiate with customer to use 'industry

standard' software

-Charge customer for added cost of special

software under scope change clause.

R. Nelson $77,000 25% $19,250

4

Produce Validation Testing

must be performed by 3rd

party

-Need to identify potential suppliers

-Added cost of paying 3rd party

-Schedule impact due to logisticsX X X

-Setup test program to use only internal

equipment

-Work with customer to see what tests they

can perform on our behalf

C. Jenkins $113,000 20% $22,600

5

Product Parts List exceeds

estimated value by more than

10%

-Recurring Cost in excess of business

case

-Reduced profit margin if price

remains unchanged

-Potential loss on effort

X

-Negotiate component costs with suppliers

-Renegotiate contract price with customer

based on customer-driven changes.

M. Hart $8,400 30% $2,520

6

Customer IT system/formats

cannot receive project

deliverables

-Will need to convert formats

internally

-May require specialize conversion

software

-Schedule impact if formatting issues

cannot be resolved

X X

-Test software export abilities within first

90 days

-Have customer provide list of formats to

evaluate import capabilities

R. Nelson $18,500 70% $12,950

$294,950

$100,845

Risk Values

Project Financial Summary:

42%

41%

$100,845

$119,643

75%

68%

$1.595M

$2.351M

Reporting Date

Risk Category DefinitionProject

Project Manager

Current ROS:

Estimated % Complete:

Initial Risk Value:

Current Risk Value:

Total Potential Risk (Unweighted)

Total Estimated Impact (Weighted)

Estimated Completion Date

% Budget SpendPlanned Completion Date

Category

Project Status

Customer Initial ROS:

Estimated Investment:

Current Investment:Project Start Date

Project Information

Step 8: Compute the Expected Value

Multiply the Total Risk Value (Step 6) by the Probability of Occurrence (Step 7) to establish the Predicted Risk Value. This is often referred to as an expected value or a weighted value.

Page 17: Risk Assessment Matrix - Manager's Resource Handbook · – Sums the total potential risk for a project as a function of cost • A Risk Assessment Matrix helps Project Teams plan

© All rights reserved. The Managers Resource Handbook by MHX Global LLP www.ManagersResourceHandbook.com v1

Watkins Smith Corporation

RF-30 Upgrade

Jessica Abrams

May 1, 2016

October 1, 2018 C Cost

August 12, 2018 S Schedule

December 3, 2017 R Resources

On Track O Other

Number Risk Description Impact of Risk C S R O Mitigation Strategy Risk OwnerTotal Risk

Value

Probability of

Occurrence

Predicted

Risk Value

1Customer delays release of end

product into market

-Delay in investment recovery

-Reduced Sales next yearX X

-Add customer-driven delays to penalties

clause of contract

-Add milestone payments for Initial Concept

and Design Acceptance to shorten time

between payments

T. Franklin $45,000 60% $27,000

2Customer seeks to renegotiate

price based on final design

-Reduction in total projected revenue

-Business case may not be as strong

-Sales contribution from project may

need to be reduced

-Cost reduction may be needed

X X

-Track detailed cost changes throughout

design evolution to show cost adjustments

-Seek funding for changes to help absorb

non-recurring costs impacts

G. DuBois $33,050 50% $16,525

3

Specialize software is needed

based on current project

requirements

-Purchase of additional software

necessary

-Employees will need training

-Efficiency loss due to learning curve

X X X

-Negotiate with customer to use 'industry

standard' software

-Charge customer for added cost of special

software under scope change clause.

R. Nelson $77,000 25% $19,250

4

Produce Validation Testing

must be performed by 3rd

party

-Need to identify potential suppliers

-Added cost of paying 3rd party

-Schedule impact due to logisticsX X X

-Setup test program to use only internal

equipment

-Work with customer to see what tests they

can perform on our behalf

C. Jenkins $113,000 20% $22,600

5

Product Parts List exceeds

estimated value by more than

10%

-Recurring Cost in excess of business

case

-Reduced profit margin if price

remains unchanged

-Potential loss on effort

X

-Negotiate component costs with suppliers

-Renegotiate contract price with customer

based on customer-driven changes.

M. Hart $8,400 30% $2,520

6

Customer IT system/formats

cannot receive project

deliverables

-Will need to convert formats

internally

-May require specialize conversion

software

-Schedule impact if formatting issues

cannot be resolved

X X

-Test software export abilities within first

90 days

-Have customer provide list of formats to

evaluate import capabilities

R. Nelson $18,500 70% $12,950

$294,950

$100,845

Risk Values

Project Financial Summary:

42%

41%

$100,845

$119,643

75%

68%

$1.595M

$2.351M

Reporting Date

Risk Category DefinitionProject

Project Manager

Current ROS:

Estimated % Complete:

Initial Risk Value:

Current Risk Value:

Total Potential Risk (Unweighted)

Total Estimated Impact (Weighted)

Estimated Completion Date

% Budget SpendPlanned Completion Date

Category

Project Status

Customer Initial ROS:

Estimated Investment:

Current Investment:Project Start Date

Project Information

Step 9: Sum the Total Project Risk

To calculate the Total Project Risk, sum all the values you calculated in Step 8. In this example: From Step 6: Total Potential Risk (Unweighted): ~$295k From Step 8: Total Estimated Impact (Weighted): ~101k

Page 18: Risk Assessment Matrix - Manager's Resource Handbook · – Sums the total potential risk for a project as a function of cost • A Risk Assessment Matrix helps Project Teams plan

© All rights reserved. The Managers Resource Handbook by MHX Global LLP www.ManagersResourceHandbook.com v1

Final Tips for Creating a Risk Assessment Matrix

1. Create the Matrix Before Project Starts To Fully Understand Risks

2. Factor Costs Into Business Case / Financial Models

3. Reevaluate Often with Project Team – Have Any Risks Become Real?

– Are Risks Still Valid?

– Are Probabilities Still Accurate?

– Any New Items to Add?

4. Change Probabilities and Assumptions As Needed to Continuously Understand Financial Values

For Step-By-Step Instructions and to Download The Template: http://www.managersresourcehandbook.com/project-risk-matrix-template/

Page 19: Risk Assessment Matrix - Manager's Resource Handbook · – Sums the total potential risk for a project as a function of cost • A Risk Assessment Matrix helps Project Teams plan

© All rights reserved. The Managers Resource Handbook by MHX Global LLP www.ManagersResourceHandbook.com v1

Final Tips for Creating a Risk Assessment Matrix

1. Create it Before Project Starts To Fully Understand Risks

2. Factor Costs Into Business Case / Financial Models

3. Reevaluate Often with Project Team – Have Any Risks Become Real?

– Are Risks Still Valid?

– Are Probabilities Still Accurate?

– Any New Items to Add?

4. Change Probabilities and Assumptions As Needed to Continuous Understand Financial Values

For Step-By-Step Instructions and to Download The Template: http://www.managersresourcehandbook.com/project-risk-matrix-template/

Step 10: Review & Update Matrix Over Time

Review with Project Team often to keep ahead of changes in the project!

Page 20: Risk Assessment Matrix - Manager's Resource Handbook · – Sums the total potential risk for a project as a function of cost • A Risk Assessment Matrix helps Project Teams plan

© All rights reserved. The Managers Resource Handbook by MHX Global LLP www.ManagersResourceHandbook.com v1

Watkins Smith Corporation

RF-30 Upgrade

Jessica Abrams

May 1, 2016

October 1, 2018 C Cost

August 12, 2018 S Schedule

December 3, 2017 R Resources

On Track O Other

Number Risk Description Impact of Risk C S R O Mitigation Strategy Risk OwnerTotal Risk

Value

Probability of

Occurrence

Predicted

Risk Value

1Customer delays release of end

product into market

-Delay in investment recovery

-Reduced Sales next yearX X

-Add customer-driven delays to penalties

clause of contract

-Add milestone payments for Initial Concept

and Design Acceptance to shorten time

between payments

T. Franklin $45,000 60% $27,000

2Customer seeks to renegotiate

price based on final design

-Reduction in total projected revenue

-Business case may not be as strong

-Sales contribution from project may

need to be reduced

-Cost reduction may be needed

X X

-Track detailed cost changes throughout

design evolution to show cost adjustments

-Seek funding for changes to help absorb

non-recurring costs impacts

G. DuBois $33,050 50% $16,525

3

Specialize software is needed

based on current project

requirements

-Purchase of additional software

necessary

-Employees will need training

-Efficiency loss due to learning curve

X X X

-Negotiate with customer to use 'industry

standard' software

-Charge customer for added cost of special

software under scope change clause.

R. Nelson $77,000 25% $19,250

4

Produce Validation Testing

must be performed by 3rd

party

-Need to identify potential suppliers

-Added cost of paying 3rd party

-Schedule impact due to logisticsX X X

-Setup test program to use only internal

equipment

-Work with customer to see what tests they

can perform on our behalf

C. Jenkins $113,000 20% $22,600

5

Product Parts List exceeds

estimated value by more than

10%

-Recurring Cost in excess of business

case

-Reduced profit margin if price

remains unchanged

-Potential loss on effort

X

-Negotiate component costs with suppliers

-Renegotiate contract price with customer

based on customer-driven changes.

M. Hart $8,400 30% $2,520

6

Customer IT system/formats

cannot receive project

deliverables

-Will need to convert formats

internally

-May require specialize conversion

software

-Schedule impact if formatting issues

cannot be resolved

X X

-Test software export abilities within first

90 days

-Have customer provide list of formats to

evaluate import capabilities

R. Nelson $18,500 70% $12,950

$294,950

$100,845

Risk Values

Project Financial Summary:

42%

41%

$100,845

$119,643

75%

68%

$1.595M

$2.351M

Reporting Date

Risk Category DefinitionProject

Project Manager

Current ROS:

Estimated % Complete:

Initial Risk Value:

Current Risk Value:

Total Potential Risk (Unweighted)

Total Estimated Impact (Weighted)

Estimated Completion Date

% Budget SpendPlanned Completion Date

Category

Project Status

Customer Initial ROS:

Estimated Investment:

Current Investment:Project Start Date

Project Information

Page 21: Risk Assessment Matrix - Manager's Resource Handbook · – Sums the total potential risk for a project as a function of cost • A Risk Assessment Matrix helps Project Teams plan

© All rights reserved. The Managers Resource Handbook by MHX Global LLP www.ManagersResourceHandbook.com v1

The Manager's Resource Handbook is an online source of tools, templates and articles for managers and leaders in today’s business environment. Our mission is the help managers and businesses succeed through the benefit of

our experience.

You can contact us at:

http://www.ManagersResourceHandbook.com Like us on Facebook!

Follow us on Twitter!