Risk and Value Creation

Embed Size (px)

Citation preview

  • 8/13/2019 Risk and Value Creation

    1/25

    RISK AND VALUE MANAGEMENT: A

    CASE OF AUTOPLAST LTD.

    Department of Built Environment

    University of Central Lancashire

  • 8/13/2019 Risk and Value Creation

    2/25

    i

    TABLE OF CONTENTS

    Table of Contents ............................................................................................................................. iList of Tables ................................................................................................................................. iiiList of Figures ................................................................................................................................ iv1. INTRODUCTION ................................................................................................................... 1

    1.1. Risk................................................................................................................................... 11.2. Value Management .......................................................................................................... 11.3. Risk and Value Management ........................................................................................... 1

    2. THE CASE OF AUTOPLAST ................................................................................................ 32.1. The Risks Faced by the AutoPlast ................................................................................... 3

    2.1.1. Political Risks ........................................................................................................... 32.1.1.1. Macro Level Political Risk............................................................................................ 32.1.1.2. Micro Level Political Risk ............................................................................................ 4

    2.1.2. Economic Risk .......................................................................................................... 42.1.3. Social Risk ................................................................................................................ 42.1.4. Technological Risk ................................................................................................... 52.1.5. Legal Risk ................................................................................................................. 52.1.6. Environmental Risk .................................................................................................. 62.1.7. Competitive Risk ...................................................................................................... 6

    3. Hazards .................................................................................................................................... 83.1. ENVIRONMENTAL HAZARDS ................................................................................... 8

    3.1.1. Hazard 1: Waste in the Marine and Terrestrial Environment ................................... 83.1.1.1. Contingency Plan .......................................................................................................... 83.1.1.2. Disaster Plan ................................................................................................................. 8

    3.1.2. Hazard 2: Release potential toxic fumes ................................................................. 93.1.2.1. Contingency Plan .......................................................................................................... 93.1.2.2. Disaster plan ................................................................................................................ 10

    3.2. Technological hazards .................................................................................................... 103.2.1. Hazard 1 Bad Virus ................................................................................................. 10

  • 8/13/2019 Risk and Value Creation

    3/25

    ii

    3.2.1.1. Contingency Plan ........................................................................................................ 103.2.1.2. Disaster Plan ............................................................................................................... 11

    3.2.2. Hazard 2: Communication failure ........................................................................... 113.2.2.1. Contingency Plan ........................................................................................................ 113.2.2.2. Disaster Response ....................................................................................................... 12

    4. VALUE CHAIN ANALYSIS ............................................................................................... 134.1. Primary Activities .......................................................................................................... 13

    4.1.1. Operations ............................................................................................................... 134.1.2. Outbound Logistics ................................................................................................. 134.1.3. Marketing and Sales ................................................................................................ 154.1.4. Services ................................................................................................................... 15

    4.2.

    Support Activities ........................................................................................................... 15

    4.2.1. Infrastructure ........................................................................................................... 154.2.2. Human Resource Management ............................................................................... 164.2.3. Technology Development ....................................................................................... 164.2.4. Procurement ............................................................................................................ 16

    5. CONCLUSION ..................................................................................................................... 17REFERENCES ............................................................................................................................. 18

  • 8/13/2019 Risk and Value Creation

    4/25

    iii

    LIST OF TABLES

    Table 1. Quantitative Risk Register............................................................................................... 7

  • 8/13/2019 Risk and Value Creation

    5/25

    iv

    LIST OF FIGURES

    Figure 1.Value Chain Model ....................................................................................................... 14

  • 8/13/2019 Risk and Value Creation

    6/25

    Risk and Value Management 1

    1.INTRODUCTIONThe thrust of technological encroachment and globalization has experienced a significant

    progression during the last few decades. The volatility in the business world has increase now.

    One after another natural calamity has augmented this situation. This uncertain and risky

    situation stipulates to develop effective strategies to manage the risk at all organizational levels

    (Honohan & Laeven, 2005).

    1.1. RISKThe word risk is derived from an old French word risqu, meaning danger with a

    degree of likelihood (Littr, 1863). It is mostly ascribed to the probability of occurrence of some

    event (Bruin et al., 2000).

    1.2. VALUE MANAGEMENTThere are two schools of thought about the value management process in the

    organization. The first school of thought advocates following the state of the art engineering

    mechanisms that seeks to achieve the desired outcomes at minimum possible cost (Dell'Isola,

    1984). The second school of thought emphasizes upon the strategic interaction of organizations

    with the external environment, including clients and other stakeholders (Barton, 1996).

    1.3. RISK AND VALUE MANAGEMENTThe recent changes in business environments have posed a great challenge for the

    organisation to maximize their value (Gupta, 2011). There must be a strong rationale behind risk

  • 8/13/2019 Risk and Value Creation

    7/25

    Risk and Value Management 2

    management activities. If risk management is not worthwhile, then there is no need to be

    involved in this practice.

  • 8/13/2019 Risk and Value Creation

    8/25

    Risk and Value Management 3

    2.THE CASE OF AUTOPLASTThe AutoPlast Ltd. is a company located in the industrial park of Blumac Town. The

    company is involved in the business of manufacturing plastic products for the automobile

    industry.

    2.1. THE RISKS FACED BY THE AUTOPLASTThe company is currently facing a number of risks that are being explained as under:

    2.1.1. Political RisksThe risk that a future outcome may be affected by the political changes in the country is

    called political risk (Kennedy, 1988). The AutoPlast Ltd. is also facing this risk. Currently, the

    factory site of AutoPlast Ltd. has the immunity. The government may change its decision about

    the awarded immunity or the new government may revoke the immunity.

    For the purpose of quantification, we may divide the political risk into two categories:

    2.1.1.1. Macro Level Pol iti cal Risk

    This type of political risk affects all the businesses operating in the country. (Ilan &

    McKee, 1999). Apparently, AutoPlast is not facing any kind of macro level political risk.

    However, the possibility of such a risk cannot be avoided. Hence, the company must not ignore

    this risk while devising their risk management strategies. This risk can be quantified through rate

    of the change of governments before their stipulated time.

  • 8/13/2019 Risk and Value Creation

    9/25

    Risk and Value Management 4

    2.1.1.2. Micro Level Pol it ical Risk

    Micro level political risk is the risk that is limited to different project only. The

    companies are required to remain focused on the changes occurring in the relative industry and

    local economy where the business is operating (Ilan et al., 2006).

    Currently, in case of AutoPlast Ltd., company is facing the micro level risks. The local

    authorities are trying that the company must relocate its factory site because of the hazardous

    incident that took place in the past. This risk can be quantified by the evaluating the number of

    incidents took place because of micro level political risk political risk.

    2.1.2. Economic RiskThe economic risk can be referred to the possibility that a downfall in the economy will

    negatively affect the business. The economics factors like inflation, changes in interest rates,

    changes in GDP and GNP may have potential effects on businesses

    AutoPlast Ltd. is operating in a relatively stable economy i.e. UK. However, the changes

    in the international economy have potential effects on the economy of UK. Therefore, the

    company must have a contingency plan to cope with such an adverse situation resulting from the

    economic risk.

    2.1.3. Social RiskThe organizations actions that may have adverse effects on the society are referred to the

    social risks. Currently, the organization is facing the social risk of unemployment in the society

    in case it relocates its site. The local community workers working at the company will be

  • 8/13/2019 Risk and Value Creation

    10/25

    Risk and Value Management 5

    unemployed in case the site is relocated. The company must make the administration and

    authorities aware about this issue in order to reduce the pressure for relocation of the site.

    2.1.4. Technological RiskThe risk associated with technologies including information technology is referred to

    technological risk. This risk may include the failure of the technology or the technology become

    obsolete.

    Presently, AutoPlast Ltd. is not facing any significant technological risk. However, this

    risk may exist in two forms.

    i) The firm should use the new technologies to ensure that society is saved from thehazardous effects of the incidents like happened in the past.

    ii) A new competitor may use some effective technology to gain competitiveadvantage.

    2.1.5. Legal RiskLegal risk can be referred to uncertainty of future events because of the legal

    environment in which a company is operating. Currently, in case of AutoPlast Ltd. the company

    is facing legal risk. The legal risk is about to surface for the organization. Although, presently

    companys site has the immunity about relocation, but the pressure exerted by the administration

    and society may result in relocation of the company. Moreover, the company may have to face

    the penalties from the regulatory bodies.

  • 8/13/2019 Risk and Value Creation

    11/25

    Risk and Value Management 6

    2.1.6. Environmental RiskEnvironmental risk is referred to probability of environmental effects resulting from the

    organizational activities. This risk includes the adverse outcomes for the living orgasms on the

    earth. This is a significant risk in case AutoPlast Ltd. Firstly, as the companys site is located at

    the bank of the river; therefore, the floods from the river are a continuous source of danger.

    Moreover, in case of fire previously toxic fumes results in many of health issues among the

    society.

    2.1.7.

    Competitive Risk

    The competitive risk is referred to probability of adverse outcome because of the changes

    in existing competition in the market. The market share is rapidly lost in case the company does

    not remain competitive. AutoPlast Ltd. is facing a significant competitive risk. Currently, new

    cheaper products those are comparable to AutoPlasts products. Because of this issue the

    company is unable to achieve its sales targets during the last 3 years.

  • 8/13/2019 Risk and Value Creation

    12/25

    Risk and Value Management 7

    Table 1. Quantitative Risk Register

  • 8/13/2019 Risk and Value Creation

    13/25

    Risk and Value Management 8

    3.HAZARDSThere are two types of hazards being discussed here.

    3.1. ENVIRONMENTAL HAZARDSPlastic manufacturing companies or in this case AutoPlast Ltd. leads to many problems as

    large volumes of waste are created.

    3.1.1. Hazard 1: Waste in the Marine and Terrestrial EnvironmentMarine environment has been largely studied. A lot of large amount of plastic product,

    debris, are found in Open Ocean, Deep Ocean, coast lines etc. This is not because of dumping in

    rivers or oceans but also caused by littering on land, as well as leakages and spillages (Niemeier

    & Rice, 1999).

    3.1.1.1. Cont ingency Plan

    The company is required to devise the strategies to cope with the losses resulting from

    floods. Firstly, the company must get insured its all assets in order to avoid the losses resulting

    from the flood. Secondly, the company must take care of the issues concerning the marine life.

    The AutoPlast Ltd. is required to make such wares houses where the finished goods and the raw

    material can be stored safely.

    3.1.1.2. Di saster Plan

    Although, the water proof compounds can serve better in order to avoid the mixing of

    plastic wastes in the water. However, under the sever circumstance this mixing may take place.

  • 8/13/2019 Risk and Value Creation

    14/25

    Risk and Value Management 9

    The company should have the setup for shifting of finished goods and raw material to a

    temporary facility where the material can be stored safely.

    3.1.2. Hazard 2: Release potential toxic fumesRelease of dangerous plastic products to air also effects surrounding environment. The

    company has experienced in the past that in case of fire the release of toxic fumes significantly

    affected the local community. The following steps must be undertaken in order to avoid the

    negative effects of incidents like took place in future:

    The company must install fire extinguishers at different place.

    The electric appliances must be plugged out when they are not in use in order to avoid theshort circuits.

    The fire alarm system and smoke detection systems must be installed to generate promptsignals.

    3.1.2.1. Conti ngency Plan

    The company must keep some of the hired people that should remain on call. In case of

    the failure of above staff the company must call these people to restrict the losses resulting from

    such incidents. The company must develop a procedural manual to deal with such an incident,

    which should have clear distinction of the roles played by the different organizational

    departments and members.

  • 8/13/2019 Risk and Value Creation

    15/25

    Risk and Value Management 10

    3.1.2.2. Di saster plan

    In case the contingency plan fails and disaster takes place, then the company must have a

    disaster plan in place. The proper treatments should be provided to the effected ones by the

    company in case of toxic fumes. The company must have the connection with such a companies

    and agencies that are trained to deal with such incidents. Under the severe circumstances, the

    company must have a backup plan for shifting of human beings from the affected place to a safer

    place.

    3.2. TECHNOLOGICAL HAZARDSFollowing are the potential technological hazards most likely to faced by AutoPlast Ltd.

    3.2.1. Hazard 1 Bad VirusWith the advancement in technology, everything is just one-click away (Willies, 1991).

    The viruses affect the data. The virus corrupts the data and cannot be utilized further. In case of

    AutoPlast Ltd. as flood has as the flood overflow the factory premises causes lot of damage to

    other things also disrupts technological failure. Following steps be adopted to deal with these

    hazards:

    1. Proper antivirus should be installed.2. Precautions should be taken against important files they must not be saved on internet.3. The security services must be achieved.

    3.2.1.1. Cont ingency Plan

    The following steps must undertaken regarding the contingency plans:

  • 8/13/2019 Risk and Value Creation

    16/25

    Risk and Value Management 11

    Store data in different locations Storing data in multiple formats Safety precautions against potential threats

    3.2.1.2. Disaster Plan

    In case the destruction takes place as result of the virus attacks, the AutoPlast must have

    the setup for the recovery of their important data. The company should be able to develop such a

    system that has a strong buffer against the virus attacks.

    3.2.2. Hazard 2: Communication failureThe failure of information technology may adversely affect the communication systems.

    The organization must develop the following steps:

    Installation of new systems in the organization. Different softwares must be periodically updated. The systems should be checked periodically for their proper functioning.

    3.2.2.1.Contingency Plan

    Following steps should be undertaken as contingency plan:

    The company must install different systems for communications, so that the other systemmay be used in case of failure of one system.

    The employees must be trained about the proper use of these systems.

  • 8/13/2019 Risk and Value Creation

    17/25

  • 8/13/2019 Risk and Value Creation

    18/25

    Risk and Value Management 13

    4.VALUE CHAIN ANALYSISThe value chain model is a systematic approach that was developed by M.E. Porter

    (1985) in his book on competitive advantage. The tradition value chain model is given in Figure

    1. The activities performed by the organization are divided here into two categories:

    i) Primary Activitiesii) Support ActivitiesAutoPlast is currently facing reduction in its sales. Therefore, the company needs to

    identify the activities that are not creating the value for the company. A detailed proposed

    description of all the activities is as follows:

    4.1. PRIMARY ACTIVITIESPrimary activities are being explained as follows:

    4.1.1. OperationsThe company is involved in manufacturing of plastic parts for automobile industry. The

    company is currently not diversified. The company should follow diversification. This will help

    to manage the risk associated with the business operations.

    4.1.2. Outbound LogisticsThe outbound logistics is a key area of interest for the company. Maintaining the own

    fleet of logistics will add in extra costs as compared to the obtained benefits. Therefore, it is

    advisable that the company must outsource these services to the logistic companies.

  • 8/13/2019 Risk and Value Creation

    19/25

    Risk and Value Management 14

    Figure 1.Value Chain Model

    Source: (Porter, 1985)

  • 8/13/2019 Risk and Value Creation

    20/25

    Risk and Value Management 15

    4.1.3. Marketing and SalesAutoPlast should follow an effective strategy for sales market. The promotional

    campaign should be undertaken in order to make all the customers aware of the products of the

    company. The quality aspects of the company products must be highlighted so that the company

    may compete with the products coming from Eastern Europe.

    4.1.4. ServicesCurrently, the provision of services is quite limited by the company. The company can

    produce more value by providing different kind of services to its customers e.g. repair and

    maintenance services.

    4.2. SUPPORT ACTIVITIESThe value creation process through support activities in AutoPlast Ltd.is being explained

    as follows:

    4.2.1. InfrastructureAutoPlast Ltd. has still not expanded its infrastructure. The company must undertake the

    expansion within its infrastructure. Production facilities must be expanded to the different

    geographical regions. This will save a lot of extra cost incurred on handling and logistic, thereby

    creating value for the company.

  • 8/13/2019 Risk and Value Creation

    21/25

    Risk and Value Management 16

    4.2.2. Human Resource ManagementThe company must maintain a clear hierarchal structure. Moreover, the company must

    bring diversification in its staff. This will create a soft image of the company in the market as the

    company providing equal opportunities regardless of any kind of discrimination. This

    diversification will also help in adding value to the company as the people with different abilities

    and skills will provide a rich workforce to the company.

    4.2.3. Technology DevelopmentThe company must work on developing innovative technology for the purpose of

    production and market. Initially, this development of technology may incur additional costs, but

    the company should consider this cost as investment that will yield greater benefits in future.

    4.2.4. ProcurementThe company should have developed an effective and efficient procurement system. A

    proper procurement department must be developed so that the prompt decision can be

    undertaken at the operational levels in order save the time and extra costs associated with the

    procurement.

  • 8/13/2019 Risk and Value Creation

    22/25

    Risk and Value Management 17

    5.CONCLUSIONThere are rapid changes in the situations where the companies are doing their businesses

    now a day. A stagnant strategy cannot produce the desired results. The company must be

    reviewing the implemented plans and strategies periodically and adjustments should be made if

    required. The flexible strategies and plans can be more beneficial for the company. Moreover,

    the company must work on the current issues. The urgent remedical measures must be

    undertaken to avoid the disaster situations.

  • 8/13/2019 Risk and Value Creation

    23/25

    Risk and Value Management 18

    REFERENCES

    Barton, R.T., 1996. The application of value management to the development of project

    concepts. In Langford, D.A. & Retik, A., eds.Proc. CIB W-65 International Symposium,

    Organisation and Management in Construction: Shaping Theory and Practice. London,

    1996. E & FN Spon.

    Bernstein, P.L., 1998.Against the Gods: The Remarkable Story of Risk. New York: John Wiley

    & Sons.

    Bruin, W.B., Fischhoff, B., Millstein, S.G. & Felsher, H.B., 2000. Verbal and numerical

    expressions of probability: its a fiftyfifty chance. Organizational Behavior and

    Human Decision Processes, 81(1), pp.115-31.

    Connaughton, J.N. & Green, S.D., 1996. Value Management in Construction: A Clients Guide.

    London: Value Management in Construction: A Clients Guide.

    Construction Industry Board, 1997. Constructing Success: Code of Practice for Clients in the

    Construction Industry. London: Thomas Telford.

    Dell'Isola, A., 1984. Value Engineering in the Construction Industry. 3rd ed. New York: Van

    Nostrand Reinhold.

    Fishburn, P.C., 1984. Foundations of risk measurement. I. risk as probable loss.Management

    Science, 30(4), pp.396-406.

    Green, S.D., 1994. Beyond value engineering: SMART value management for building projects.

    International Journal of Project Management, 12(1), pp.49-56.

    Green, S.D. & Simister, S.J., 1996. Group decision support for value management. In Langford,

    D.A. & Retik, A., eds. The Organisation and Management of Construction. London,

    1996. E. & F.N. Spon.

  • 8/13/2019 Risk and Value Creation

    24/25

    Risk and Value Management 19

    Gregory, D. et al., 2009. The dictionary of Human geography. 5th ed.

    Gupta, P.K., 2011. Risk management in Indian companies: EWRM concerns and issues.Journal

    of Risk Finance, 12(2), pp.121-39.

    Honohan, P. & Laeven, L., 2005. Systemic Financial Crises: Containment and Resolution. New

    York: Cambridge University Press.

    Ilan, A. & McKee, D.L., 1999. Towards a Macro-environmental Model of International

    Franchising.Multinational Business Review, 7(1), pp.76-82.

    Ilan, A., Mitchell, M., Gurumoorthy, R. & Steen, T., 2006. Managing micro-political risk: A

    cross sectional study. Thunderbird International Business Review, 48(5), pp.623-42.

    Investopedia, n.d.Political Risk. [Online] Available at:

    http://www.investopedia.com/terms/p/politicalrisk.asp[Accessed 01 June 2013].

    Kennedy, C., 1988. Political Risk Manageqment: A Portfolio Planning Model.Business

    Horizons, 31, p.21.

    Laudon, K.C. & Laudon, J.P., 2012.Management information systems: Managing the digital

    firm. 12th ed. Prentice Hall.

    Littr, L., 1863.Dictionnaire de la langue franaise.

    Miles, L.D., 1972. Techniques for Value Analysis and Engineering. New York: McGraw-Hill.

    Niemeier, R.W. & Rice, F.L., 1999. Rubber products manufacturing industry. Special Hazard

    Review.

    OBrien, J.A. & Marakas, G.M., 2011.Management Information Systems. 10th ed. New York:

    McGraw-Hill.

    Ore, O., 1953. Cardano, The Gambling Scholar. Translated by S.H. Gould. New Jersey:

    Princeton University Press.

    http://www.investopedia.com/terms/p/politicalrisk.asphttp://www.investopedia.com/terms/p/politicalrisk.asphttp://www.investopedia.com/terms/p/politicalrisk.asp
  • 8/13/2019 Risk and Value Creation

    25/25

    Risk and Value Management 20

    Porter, M.E., 1985. Competitive Advantage. New York : The Free Press.

    Schrck, G. & Steiner, M., 2010. Risk management and value creation in banks. In M. Frenkel,

    U. Hommel & M. Rudolf, eds.Risk Management: Challenge & Opportunity. 2nd ed.

    New Delhi, India: Springer. pp.53-78.