PX4- J3 PROJECT - JAMNAGAR . L&T - WEEKLY REVIEW MEETING Date : 04 th May’15 L&T Hydrocarbon Engineering Hydrocarbon Construction & Pipelines (D)

RIL J3 Meeting 08th May 2015-Weekly Meeting

Embed Size (px)

DESCRIPTION

Weekly Review Format for Construction Project

Citation preview

Page 1: RIL J3 Meeting 08th May 2015-Weekly Meeting

PX4- J3 PROJECT - JAMNAGAR .

L&T - WEEKLY REVIEW MEETING

Date : 04th May’15L&T Hydrocarbon EngineeringHydrocarbon Construction & Pipelines (D)

Page 2: RIL J3 Meeting 08th May 2015-Weekly Meeting

Overall Progress- Balance RCC Works

2

Sr. No Area/ Structure Bal Concrete As on 29-Apr

Total Qty. (Cum)

Plan for May 2015

Plan Till Date

Achieved Till Date

Backlog Till Date

1 Refrigeration Area 941 890 32 23 92 Crystallisation Train 1 506 367 58 56 23 Common Area 1129 433 70 31 394 ISOM Area 1100 410 39 37 25 SS70 388 268 4 4 6 TA Area 2746 807 262 125 1377 AEU Area 1303 539 18 90 -728 TA+AEU PR Rigid Bays 399 365 55 24 319 Crystallisation Train 2 1631 317 47 7 40

10 Crystallisation Train 3 4257 1383 224 96 128 Total = 14401 5780 809 493 316

Page 3: RIL J3 Meeting 08th May 2015-Weekly Meeting

Readiness as on 08-05-2015

3

Sr. No Area/ Structure Qty. (Cum)

1 PX-4 ISBL COMM. FACILITY SUPPORTING PLATFORM FOR MV-AYZ202-V000005 14

2 PX-4 ISBL SS-70 (SCREED CONCRETE) BACKLOG QTY. 8

3 PX-4 ISBL SS-70 TRANSFERMER BAY PCC (8-9/D-E) 15

4 PX-4 ISBL UG WORKS (MH/CB) PCC 8

5 PX-4 ISBL REST SHED AT REFRIGERATION AREA 6

6 RLS PRECAST YARD (MH/CB) BACKLOG QTY. 6

TOTAL = 57