Upload
richard-blair
View
190
Download
5
Embed Size (px)
Citation preview
Projects:
Elizabeth Quay Pedestrian Bridge
Role:
Projects Engineer
Employer:
DASSH JV
Main Contractors:
Leighton Broad
Links:
Elizabeth Quay Pedestrian Bridge is a landmark project on the foreshore of Perth city. An architecturally driven project encompasses extensive temporary works and bespoke finishes resulted for a very challenging and rewarding build.
Tendering, engineering, planning, programming, technical analysis and subcontractor vetting prior to contract award.
Upon contract award my works involved and provided me experience with; Extensive temporary works design, deep excavation planning, dewatering management, concrete mix designing and thermal analysis, extensive reinforcement feasibility redesign, detailed design of architectural finishes, design of electrical systems, formworks design, lift studies, non-destructive material testing, developing weld procedures, subcontract management, developing safe work procedures, temporary access design, air handing system design, managing detailing and fabrication of over 500t of high grade fabricated structural steel, technical query management and quality assurance management. Elizabeth Quay Project tested me on every level, enabling me to learn an incredible amount.
Projects:
Post Tensioned Structures
Perth, WA
Role:
Projects Engineer
Employer:
SRG Limited
Main Contractors:
Broad Constructions
Brookfield Multiples
BGC
John Holland
Lend Lease
Probuild
Built
Various Post tenioned structures throughout Meropolitan Perth and regional WA
Tendering, project management, procurement, labour management, value
engineering, contracts negotiation and contract administration for a variety of post tensioning projects in Perth, WA.
PT installed to slab on grade, suspended slabs, transfer structures, pre cast beams, tilt panels and slip forms
BBR Multistring, SSL flat slab PT, Macalloy stress bar, Bridon, Ancon, Radaelli and BBR cable stays systems
Experience with tendering, contracts, logistics, pre pour inspections, pressure grouting works, enterprise bargaining agreements and human resources.
Projects:
Bridge Maintenance Projects
Various Locations, WA
Role:
Project Engineer
Employer:
SRG Limited
Main Contractor:
Downer Mouchel JV
Main Roads WA
The ministry of
Defence
Multiple bridge maintenance / remedial projects through regional WA
Procurement, site management, labour management and contracts administration for a variety of bridge maintenance projects in Perth and rural WA.
Typically rural project carried out on a rostered basis requiring manpower management working 7 days a week to maintain tight programme requirements to keep main traffic routes open.
Experience with tendering, contract administration, rural site logistics, Mainroads WA concrete mix designs, external post tensioning works, intricate formwork / false works, concrete repair works, traffic management, timber bridge construction, hydro demolition, concrete cutting, cathodic protection and guard rail
Project:
Queen Elizabeth School
Wimborne, England
Role:
Senior Site Engineer /
Site Manager
Employer:
Woodmace Civil
Engineering LTD
Main Contractor:
Carillion Mouchel JV
£56m New build secondary school in Wimborne, Dorset.
Procurement, site engineering, site management and surveying management for
an ecological secondary school development involving many bespoke and maiden construction methodologies
European first fully insitu suspended Cobiax flooring system.
UK first Rehau Air attneutaion installation and comissioning
Multi sub level Biomass incinerator construction
Mains utlity installation for Gas, Water, HV, Pressurised Sewearge, and air handling
Extensive RC installation, hardstanding, archtectural finishes, landscaping and resing bound surfacing, and attenuation ponds
Experience with Design and Construct, temporary works, cofferdam construction, new and innovative technologies, below ground waterproofing and man management for 100+ operatives
Project:
Waitrose Distribution
Facility / Cold Store
Bracknell, England
Role:
Site Engineer
Employer:
Woodmace Civil
Engineering LTD
Main Contractor:
Carters Group
Procurement, site engin
eering, and surveying for deep drainage, piling, ground stabilisation, hardstand and landscaping.
30,000m³ lime stabilised fill material
20,000m² Fibre reinforced concrete hardstand
Mono post tensioned slab on grade Experience with ground stabilisation, pre cast tilt up construction, bulk earthworks, insitu concrete works, deep drainage, attenuation tanks and heavy plant.
Project:
Mixed use development
1 Lambs Passage
London, UK
Role:
Junior Designer /
Draftsman
Employer:
Godsell Arnold
Partnership LTD
Main Contractor:
Bovis Lend Lease
Extensive substructure works on a heritage listed basements, pile and capping beam arrangement to accommodate brick cellars dating back to 1900s.
Extremely tight site footprint requiring detailed forethought to aid constructability
Design works carried out on CADS3DMax, drafting on AutoCAD
Experience with metro multi-storey construction, heritage remedial works, concrete frame construction, detailed design software, RC concrete mix designing and reo detailing / scheduling