18
1 RHIC Machine/Detector Planning Meeting 15 Jan 08 Agenda End game for Run 8 issues APEX Update Planning Meeting Web Site: http://www.c-ad.bnl.gov/esfd/RMEM_08/rhic_planning.htm

RHIC Machine/Detector Planning Meeting · 2 Run 8 Log • 25 Oct, begin 45 degree cold wave (2.5 MW-NEW) • 1 Nov, Cool-down to 4.5 degrees begins • 4 Nov, Blue ring cold but still

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: RHIC Machine/Detector Planning Meeting · 2 Run 8 Log • 25 Oct, begin 45 degree cold wave (2.5 MW-NEW) • 1 Nov, Cool-down to 4.5 degrees begins • 4 Nov, Blue ring cold but still

1

RHIC Machine/Detector Planning Meeting15 Jan 08

Agenda

– End game for Run 8 issues– APEX Update

Planning Meeting Web Site: http://www.c-ad.bnl.gov/esfd/RMEM_08/rhic_planning.htm

Page 2: RHIC Machine/Detector Planning Meeting · 2 Run 8 Log • 25 Oct, begin 45 degree cold wave (2.5 MW-NEW) • 1 Nov, Cool-down to 4.5 degrees begins • 4 Nov, Blue ring cold but still

2

Run 8 Log• 25 Oct, begin 45 degree cold wave (2.5 MW-NEW)• 1 Nov, Cool-down to 4.5 degrees begins• 4 Nov, Blue ring cold but still stabilizing• 6 Nov, Blue and Yellow cold and stable (0.9 weeks into run)• 8 Nov, Beam in Blue ring, “Setup Mode begins”• 16 Nov, Beam in Blue and Yellow rings• 18 Nov, First collisions (2.6 weeks into run)• 19 Nov, Experiment Magnets on, begin night shifts for experiments, “Ramp-

up Mode” begins (2.7 weeks into run)• 26 Nov (1600 hrs), Machine declared operational for Physics (3.7 weeks into

run)• 29 Nov, PHENIX in physics mode• 1 Dec STAR in limited physics mode (min-bias)• 31 Dec, STAR in full physics mode• 28 Jan, 0800, end dAu run (9 weeks physics)• 28 Jan, maintenance and begin 100x100 GeV pp setup

Page 3: RHIC Machine/Detector Planning Meeting · 2 Run 8 Log • 25 Oct, begin 45 degree cold wave (2.5 MW-NEW) • 1 Nov, Cool-down to 4.5 degrees begins • 4 Nov, Blue ring cold but still

3

Run8 RHIC dAu Integrated Luminosity for Physics (singles corrected)

0.0

20.0

40.0

60.0

80.0

100.0

120.0

140.0

160.0

180.0

200.0

26-Nov-07

3-Dec-07

10-Dec-07

17-Dec-07

24-Dec-07

31-Dec-07

7-Jan-08

14-Jan-08

21-Jan-08

28-Jan-08

Since beginning of Physics

inte

grat

ed lu

min

osity

(nb

-1)

STAR

PHENIX

Lmax

Lmin

Page 4: RHIC Machine/Detector Planning Meeting · 2 Run 8 Log • 25 Oct, begin 45 degree cold wave (2.5 MW-NEW) • 1 Nov, Cool-down to 4.5 degrees begins • 4 Nov, Blue ring cold but still

4

Run8 RHIC dAu Available Luminosity per day

0.0

1.0

2.0

3.0

4.0

5.0

6.0

7.0

8.0

26-Nov

3-Dec

10-Dec

17-Dec

24-Dec

31-Dec

7-Jan

14-Jan

21-Jan

Since beginning of Physics

b-1 p

er d

ayPHENIX

L Max/day

L Min/day

STAR

APEX/Maintenance day

APEX

μ

Page 5: RHIC Machine/Detector Planning Meeting · 2 Run 8 Log • 25 Oct, begin 45 degree cold wave (2.5 MW-NEW) • 1 Nov, Cool-down to 4.5 degrees begins • 4 Nov, Blue ring cold but still

5

Run8 RHIC dAu Integrated Luminosity for Physics

0.0

50.0

100.0

150.0

200.0

250.0

300.0

350.0

400.0

26-Nov-07

3-Dec-07

10-Dec-07

17-Dec-07

24-Dec-07

31-Dec-07

7-Jan-08

14-Jan-08

21-Jan-08

28-Jan-08

4-Feb-08

11-Feb-08

Since beginning of Physics

μb-1

per

day

STARPHENIXLmaxLminPHENIX Projected (previous 7 day average)STAR Projected (previous 7 day average)Poly. (Lmin)Poly. (Lmax) PHENIX Goal

STAR Goal

Page 6: RHIC Machine/Detector Planning Meeting · 2 Run 8 Log • 25 Oct, begin 45 degree cold wave (2.5 MW-NEW) • 1 Nov, Cool-down to 4.5 degrees begins • 4 Nov, Blue ring cold but still

6

Through 10 Jan 2008

RHIC Cryo Operations FY06-08

0.00

1.00

2.00

3.00

4.00

5.00

6.00

7.00

8.00

9.00

10.00

-30 -10 10 30 50 70 90 110 130 150 170 190

Days since beginning of Run

MW

RHIC Cryo 06RHIC Cryo 07RHIC Cryo 08

Page 7: RHIC Machine/Detector Planning Meeting · 2 Run 8 Log • 25 Oct, begin 45 degree cold wave (2.5 MW-NEW) • 1 Nov, Cool-down to 4.5 degrees begins • 4 Nov, Blue ring cold but still

7

Through 10 Jan 2008

RHIC Operations FY06-08

0.00

5.00

10.00

15.00

20.00

25.00

30.00

35.00

-30 -10 10 30 50 70 90 110 130 150 170

Days since beginning of Run

MW

CAD Power 06CAD Power 07CAD Power 08

Page 8: RHIC Machine/Detector Planning Meeting · 2 Run 8 Log • 25 Oct, begin 45 degree cold wave (2.5 MW-NEW) • 1 Nov, Cool-down to 4.5 degrees begins • 4 Nov, Blue ring cold but still

8

Through 10 Jan 2008

BNL Energy Use FY 2004-8(C-AD Bldg 911 power is in AGS-Exp/Mach)

0

1

2

3

4

5

6

7

8

9

10

11

121-

Oct

-03

1-D

ec-0

3

1-Fe

b-04

1-A

pr-0

4

1-Ju

n-04

1-A

ug-0

4

1-O

ct-0

4

1-D

ec-0

4

1-Fe

b-05

1-A

pr-0

5

1-Ju

n-05

1-A

ug-0

5

1-O

ct-0

5

1-D

ec-0

5

1-Fe

b-06

1-A

pr-0

6

1-Ju

n-06

1-A

ug-0

6

1-O

ct-0

6

1-D

ec-0

6

1-Fe

b-07

1-A

pr-0

7

1-Ju

n-07

1-A

ug-0

7

1-O

ct-0

7

1-D

ec-0

7

Date

Dai

ly A

vera

ge P

ower

(MW

)

AGS-Mach RHIC otherRHIC Cryo CAD Bldg less SMDTandem AGS-ExpNSRL BoosterSite Base Peak-Av

Page 9: RHIC Machine/Detector Planning Meeting · 2 Run 8 Log • 25 Oct, begin 45 degree cold wave (2.5 MW-NEW) • 1 Nov, Cool-down to 4.5 degrees begins • 4 Nov, Blue ring cold but still

9

BNL Energy Use FY 2004-8(C-AD Bldg 911 power is in AGS-Exp/Mach)

0

5

10

15

20

25

30

1-O

ct-0

3

1-D

ec-0

3

1-Fe

b-04

1-A

pr-0

4

1-Ju

n-04

1-A

ug-0

4

1-O

ct-0

4

1-D

ec-0

4

1-Fe

b-05

1-A

pr-0

5

1-Ju

n-05

1-A

ug-0

5

1-O

ct-0

5

1-D

ec-0

5

1-Fe

b-06

1-A

pr-0

6

1-Ju

n-06

1-A

ug-0

6

1-O

ct-0

6

1-D

ec-0

6

1-Fe

b-07

1-A

pr-0

7

1-Ju

n-07

1-A

ug-0

7

1-O

ct-0

7

1-D

ec-0

7

Date

Dai

ly A

vera

ge P

ower

(MW

)

RHIC Cryo RHIC otherAGS-Exp TandemBooster AGS-MachCAD Bldg less SMD NSRLSite Base Peak-Av

Through 10 Jan 2008

20 MW, incremental cost per day for power = $75*24hr*20MW=$34K

Page 10: RHIC Machine/Detector Planning Meeting · 2 Run 8 Log • 25 Oct, begin 45 degree cold wave (2.5 MW-NEW) • 1 Nov, Cool-down to 4.5 degrees begins • 4 Nov, Blue ring cold but still

10

http://www.bnl.gov/cad/esfd

AGS-Booster-Tandem/Linac Startup

RHIC Cryo Cooldown/Warm-up

RHIC Cryo Operation

RHIC Cryo off

RHIC Research with √s = 200 GeV/n d-Au

RHIC Research with √s = 200 GeV pp

RHIC Au-Au development at÷ s = 9 GeV

NSRL (NASA Radiobiology)

Shutdown (RHIC)

C-A Operations-FY08

Program Element Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

FY 2008

15 Jan 08

setup with beams in both rings Planned, subject to change

19.6 weeks

Sep

concurrent with RHIC

ramp up luminosity

9 weeks

4

Page 11: RHIC Machine/Detector Planning Meeting · 2 Run 8 Log • 25 Oct, begin 45 degree cold wave (2.5 MW-NEW) • 1 Nov, Cool-down to 4.5 degrees begins • 4 Nov, Blue ring cold but still

11

RHIC Machine/Detector Planning Meeting

Next Meeting

22 Jan 08

Planning Meeting Web Site: http://www.c-ad.bnl.gov/esfd/RMEM_08/rhic_planning.htm

Page 12: RHIC Machine/Detector Planning Meeting · 2 Run 8 Log • 25 Oct, begin 45 degree cold wave (2.5 MW-NEW) • 1 Nov, Cool-down to 4.5 degrees begins • 4 Nov, Blue ring cold but still

12

Through 10 Jan 2008

BNL Energy Use FY 2006-8(C-AD Bldg 911 power is in AGS-Exp/Mach)

0

5

10

15

20

25

30

35

40

45

50

1-O

ct-0

5

1-D

ec-0

5

1-Fe

b-06

1-A

pr-0

6

1-Ju

n-06

1-A

ug-0

6

1-O

ct-0

6

1-D

ec-0

6

1-Fe

b-07

1-A

pr-0

7

1-Ju

n-07

1-A

ug-0

7

1-O

ct-0

7

1-D

ec-0

7

Date

Dai

ly A

vera

ge P

ower

(MW

)

$-

$10

$20

$30

$40

$50

$60

$70

$80

$90

$100

$110

$/M

Whr

RHIC Cryo RHIC otherAGS-Mach CAD Bldg less SMDTandem BoosterAGS-Exp NSRLSite Base Peak-Av$/MWhr

begin "balanced billing"

Page 13: RHIC Machine/Detector Planning Meeting · 2 Run 8 Log • 25 Oct, begin 45 degree cold wave (2.5 MW-NEW) • 1 Nov, Cool-down to 4.5 degrees begins • 4 Nov, Blue ring cold but still

13

Through Nov 2007

FY 2006-7 Power Bill

$-

$20

$40

$60

$80

$100

$120

$140Ju

n-05

Sep-

05

Dec

-05

Mar

-06

Jun-

06

Aug-

06

Nov

-06

Feb-

07

May

-07

Aug-

07

Nov

-07

Feb-

08

May

-08

Aug-

08

Nov

-08

Feb-

09

$/M

Whr

With Balanced Billing

Without BalancedBillingProjection

Page 14: RHIC Machine/Detector Planning Meeting · 2 Run 8 Log • 25 Oct, begin 45 degree cold wave (2.5 MW-NEW) • 1 Nov, Cool-down to 4.5 degrees begins • 4 Nov, Blue ring cold but still

14

Experiments luminosity goals for Run 8, 100 x 100 GeV pp

– PHENIX• Delivered luminosity = 140 nb-1

• Recorded luminosity = 35 nb-1

– Longitudal Polarization goal: 26 nb-1

– Transverse polarization luminosity goal: 9 nb-1

• Assumed efficiencies: 48% vertex, 64% up, 82% live 25% overall• Assumed polarization: 65%• Approximate physics weeks: 12

– STAR• Delivered luminosity = 90 nb-1

– Longitudal polarization goal: 60 nb-1

– Transverse polarization luminosity goal: 30 nb-1

• Slow detector sampled luminosity (Transverse and Longitudal) = 30 nb-1

• Assumed efficiencies: 50% uptime, 65% live 33% overall• Assumed polarization: 65%• Approximate physics weeks: 12

• pp2pp: 3 days of dedicated running • Goals: 20M elastics, 300K double pomeron exchange events

An issue: In 2006 it took 6 weeks of physics running to get from ~45% polarization to ~60% polarization, above goals assume 65% from physics day 1

(Last update 23 Oct 07)

Page 15: RHIC Machine/Detector Planning Meeting · 2 Run 8 Log • 25 Oct, begin 45 degree cold wave (2.5 MW-NEW) • 1 Nov, Cool-down to 4.5 degrees begins • 4 Nov, Blue ring cold but still

15

Phenix Goal

Phenix GoalPHENIX Goal

STAR Goal

STAR and PHENIX Plan

Page 16: RHIC Machine/Detector Planning Meeting · 2 Run 8 Log • 25 Oct, begin 45 degree cold wave (2.5 MW-NEW) • 1 Nov, Cool-down to 4.5 degrees begins • 4 Nov, Blue ring cold but still

16

(last update 10/23/07)Experiments luminosity goals for Run 8 100 x 100 GeV/n d-Au

– PHENIX• Delivered luminosity = 230 nb-1

• Recorded luminosity = 58 nb-1

• Assumed efficiencies: 48% vertex, 53% live 25% overall• Approximate weeks: 10

– STAR• Delivered luminosity = 120 nb-1

• Fast Detector sampled luminosity = 60 nb-1

• Slow Detector sampled luminosity = 30 nb-1

• Fast detector overall sampling efficiency = 50%• Approximate weeks: 10

– Monopole Proposal – Detector Tests• Once ~ 20:1 signal to background is achieved in building 902, move to 10:00 IR,

reestablish good signal to background and then request collisions

Page 17: RHIC Machine/Detector Planning Meeting · 2 Run 8 Log • 25 Oct, begin 45 degree cold wave (2.5 MW-NEW) • 1 Nov, Cool-down to 4.5 degrees begins • 4 Nov, Blue ring cold but still

17

PHENIX Goal

STAR Goal

STAR and PHENIX Plan

Page 18: RHIC Machine/Detector Planning Meeting · 2 Run 8 Log • 25 Oct, begin 45 degree cold wave (2.5 MW-NEW) • 1 Nov, Cool-down to 4.5 degrees begins • 4 Nov, Blue ring cold but still

18

Fischer et.al. Possible 30 week run schedule