Rf Fire Department Connection in Let Flow Assessment

Embed Size (px)

Citation preview

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    1/68

     

    © January 2016 Fire Protection Research Foundation

    FIRE PROTECTION RESEARCH FOUNDATION

    ONE B ATTERMARCH P ARK | QUINCY, M ASSACHUSETTS, USA 02169-7471

    E-M AIL: [email protected] | WEB: WWW.NFPA.ORG/FOUNDATION 

    Fire Department Connection(FDC) Inlet Flow Assessment

    FINAL REPORT 

    PREPARED BY:

    Y. Pock Utiskul, Ph.D., Neil P. Wu, P.E., and Elizabeth Keller 

    Exponent, Inc.Bowie, MD, USA

     

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    2/68

     

    FOREWORD 

     A Fire Department Connection (FDC) is “A connection through which the fire department can

    pump supplemental water into the sprinkler system, standpipe, or other system, furnishing water

    for fire extinguishment to supplement existing water supplies.” FDCs are required on all

    standpipe systems per NFPA 14, Standard for the Installation of Standpipe and Hose Systems,and sprinkler systems per NFPA 13, Standard for the Installation of Sprinkler Systems.

    In 2007, the Technical Committee for NFPA 14 added the requirement for one 2 ½ inch inlet per

    every 250 gallons per minute (gpm), but this requirement lacks supporting scientific

    documentation, so there was a need to conduct flow testing to determine the amount of water

    that is possible to flow into an FDC inlet.

    The Fire Protection Research Foundation initiated this project to determine the actual flow that

    can be achieved for each 2 ½ inch inlet on an FDC to provide technical basis to the NFPA 14

    Technical Committee for a possible change to the standard.

    The Fire Protection Research Foundation expresses gratitude to the report authors Y. PockUtiskul, Ph.D., Neil P. Wu, P.E., and Elizabeth Keller who are with Exponent, Inc. TheFoundation also expresses gratitude to the Maryland Fire and Rescue Institute (MFRI) wherethe tests were conducted. The Research Foundation appreciates the guidance provided by theProject Technical Panelists and all others that contributed to this research effort. Thanks arealso expressed to the National Fire Protection Association (NFPA) for providing the projectfunding through the NFPA Research Fund.

    The content, opinions and conclusions contained in this report are solely those of the authors

    and do not necessarily represent the views of the Fire Protection Research Foundation, NFPA,

    Technical Panel or Sponsors. The Foundation makes no guaranty or warranty as to theaccuracy or completeness of any information published herein.

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    3/68

     

     About the Fire Protect ion Research Foundation

    The Fire Protection Research Foundation  plans, manages, and communicates research on a

    broad range of fire safety issues in collaboration with scientists and laboratories around the

    world. The Foundation is an affiliate of NFPA.

     About the National Fire Protection Associat ion (NFPA)

    Founded in 1896, NFPA is a global, nonprofit organization devoted to eliminating death, injury,property and economic loss due to fire, electrical and related hazards. The association deliversinformation and knowledge through more than 300 consensus codes and standards, research,training, education, outreach and advocacy; and by partnering with others who share an interestin furthering the NFPA mission.

     All NFPA codes and standards can be viewed online for free. 

    NFPA's membership totals more than 65,000 individuals around the world.

    Keywords: fire department connection, FDC, FDC inlet, flow testing, standpipe systems,NFPA 14 

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    4/68

     

    PROJECT TECHNICAL P ANEL 

    Scott Futrell, Futrell Fire Consult & Design, Inc.

    Dave Hague, Liberty Mutual

    Jeff Hebenstreit, UL LLC

    Steve Leyton, Protection Design & Consulting (AFSA representative)

    Bob Morgan, Fort Worth Fire Department

    Maurice Pilette, Mechanical Designs Ltd

    Pete Schwab, Wayne Automatic Fire Sprinklers

    Kyle Smith, Cobb County Fire and Emergency Services

    Ronald Webb, S.A. Comunale Company, Inc. (NFSA representative)

    Chad Duffy, NFPA Staff Liaison

    PROJECT SPONSOR 

    National Fire Protection Association 

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    5/68

     

    Thermal Sciences

    Fire Department Connection

    Inlet Flow Requirements:

    A Report on Full-scale

    Testing Results

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    6/68

     

    1505254.000 7849

    Fire Department Connection

    Inlet Flow Requirements:

    A Report on Full-scale

    Testing Results 

    Prepared for

    Fire Protection Research FoundationOne Batterymarch ParkQuincy, MA 02169

    Prepared by

    Y. Pock Utiskul, Ph.D., P.E., CFEI Neil P. Wu, P.E., IAAI-CFI, CBOElizabeth KellerExponent, Inc.17000 Science Drive, Suite 200Bowie, MD 20715

    January 8, 2016

     Exponent, Inc.

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    7/68

    January 8, 2016

    1505254.000 7849ii

    Contents

    Page

    List of Figures iv 

    List of Tables vi 

    Acronyms and Abbreviations vii 

    Limitations viii 

    Executive Summary ix 

    1  Background 1 

    1.1 

    Project History 1 

    1.2  Research Objectives and Project Scope 1 

    1.2.1  Review of Source Material for the Traditional Flow Requirement 2 

    1.2.2  Development of Full-Scale Flow Test Plan 2 

    1.2.3  Full-scale Flow Testing 3 

    1.2.4  Report and Summary of Best Practices 3 

    1.3  Project Assumptions 3 

    2  Literature Review 4 

    2.1  Current FDC Requirements 4 

    2.2  History of the NFPA 14 Requirement 5 

    2.3  Jurisdictional Adoptions and Procedures 6 

    2.3.1  Code Adoptions 7 

    2.3.2  Standpipe Firefighting Operations 10 

    2.4  Existing FDC Flow Test Data 11 

    2.5  Summary 12 

    3  Testing Program Summary 14 

    4  FDC Descriptions 16 

    4.1  Single FDCs 16 

    4.2  Siamese FDCs 17 

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    8/68

    January 8, 2016

    1505254.000 7849iii

    4.3  Triamese FDC 17 

    5  Test Setup 23 

    5.1  Test Apparatus 24 

    5.1.1  Water Flow Activities 24 

    5.1.2  Supply Hose Line 28 

    5.1.3  Flow Test Assembly 28 

    5.1.4  Flow Rate Measurements 31 

    5.1.5  Pressure Loss Measurements 32 

    5.1.6  DAQ System 33 

    5.1.7  Still Photography and High Definition Video 33 

    5.2  Flow Test Protocols 33 

    6  Test Results 35 

    7  Analysis and Discussion 40 

    7.1  Single FDC 40 

    7.2  Siamese FDC 41 

    7.3  Triamese FDC 43 

    7.4  FDCs Pressure Loss Characteristics 44 

    7.5  Section Summary 47 

    Key Findings 48 

    9  Acknowledgements 50 

    Appendix A 51 

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    9/68

    January 8, 2016

    1505254.000 7849iv

    List of Figures

    Page

    Figure 1 Map of municipalities included in survey 6 

    Figure 2 Single FDCs 17 

    Figure 3 Single flush FDC (FDC-1) 18 

    Figure 4 Single flush FDC (FDC-2) 18 

    Figure 5 Single flush FDC (FDC-3) 19 

    Figure 6 Siamese freestanding FDC (FDC-4) 19 

    Figure 7 Siamese freestanding FDC (FDC-4); view from bottom showing single clapper 20 

    Figure 8 Siamese projecting FDC (FDC-5) 20 

    Figure 9 Siamese projecting FDC (FDC-5); view through outlet showing double inletclappers 21 

    Figure 10 Triamese flush FDC (FDC-6) 21 

    Figure 11 Triamese flush FDC (FDC-6); view through inlet showing clappers 22 

    Figure 12 Fire department pumper apparatus 25 

    Figure 13 Test facility and drafting basin at MFRI 26 

    Figure 14 Test platform with single FDC and test apparatus secured to test platform 26 

    Figure 15 Test platform with siamese FDC and test apparatus secured to test platform 27 

    Figure 16 Test platform with triamese FDC and test apparatus secured to test platform 27 

    Figure 17 Flow test schematic for single FDC 29 

    Figure 18 Flow test schematic for siamese FDC 29 

    Figure 19 Flow test schematic for triamese FDC 30 

    Figure 20 Flow rate measurement with in-line averaging pitot tube 31 

    Figure 21 Single FDC flow test 36 

    Figure 22 Siamese FDC flow test 36 

    Figure 23 Triamese FDC flow test 37 

    Figure 24 Measurement layout 37 

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    10/68

    January 8, 2016

    1505254.000 7849v

    Figure 25 Single FDC pressure loss data 40 

    Figure 26 Siamese FDC pressure loss data 42 

    Figure 27 Triamese FDC pressure loss data 44 

    Figure 28 FDC pressure loss characteristics 46 

    Figure 29 Pumper control and pressure gauges 53 

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    11/68

    January 8, 2016

    1505254.000 7849vi

    List of Tables

    Page

    Table 1 Test Matrix 15 

    Table 2 FDC Descriptions 16 

    Table 3 Test Measurement Results 38 

    Table 4 FDC Pressure Loss Coefficients 45 

    Table 5 Pressure Data 51 

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    12/68

    January 8, 2016

    1505254.000 7849vii

     Acronyms and Abbreviations 

    CFC California Fire Code

    DAQ data acquisition systemFDC fire department connection

    FM FM Global

    FPRF Fire Protection Research Foundation

    ft feet

    gpm gallons per minute

    hz hertz

    in inch

    IBC International Building Code

    ICC International Code Council

    IFC International Fire Code

    lb pound

    MFRI Maryland Fire and Rescue Institute

     NFPA National Fire Protection Association

     NH American National Fire Hose Screw Threads

     NPT National Pipe Threads

    SCH schedule

    SOP standard operating procedures

    UL Underwriters Laboratories

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    13/68

    January 8, 2016

    1505254.000 7849viii

    Limitations

    At the request of the Fire Protection Research Foundation (FPRF), Exponent assessed fire

    department connection (FDC) inlet flow requirements. This report summarizes a literaturereview and full-scale flow testing of multiple types of FDCs. The scope of services performed

    during this literature review and testing program may not adequately address the needs of other

    users of this report, and any re-use of this report or its findings, conclusions, or

    recommendations presented herein are at the sole risk of the user.

    The full-scale flow test strategy and any recommendations made are strictly limited to the test

    conditions included and detailed in this report. The combined effects (including, but not limited

    to) of different environmental conditions, equipment, and scenarios are yet to be fully

    understood and may not be inferred from these test results alone.

    The findings formulated in this review are based on observations and information available at

    the time of writing. The findings presented herein are made to a reasonable degree of scientific

    and engineering certainty. If new data becomes available or there are perceived omissions or

    misstatements in this report, we ask that they be brought to our attention as soon as possible so

    that we have the opportunity to fully address them.

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    14/68

    January 8, 2016

    1505254.000 7849ix

    Executive Summary

    This report summarizes full-scale flow testing of multiple types of FDCs. For an automatic

    standpipe, an FDC is defined as, “A connection through which the fire department can pump thesecondary water supply to an automatic standpipe system at the required system demand.

    Supplemental water can also be provided into the sprinkler system or other system furnishing

    water for fire extinguishment to supplement existing water supplies.”1  In the case of a manual

    standpipe, the FDC is defined as, “A connection through which the fire department can pump

    the primary water supply to a manual standpipe system at the required system demand.”2 

    Industry standards, such as National Fire Protection Association (NFPA) 14, Standard for the

     Installation of Standpipe and Hose Systems, and NFPA 13, Standard for the Installation of

    Sprinkler Systems, require FDCs be installed on standpipe systems and automatic sprinkler

    systems, respectively.

    Since 2007, NFPA 14 has required one (1) 2.5-inch diameter FDC inlet for every 250 gallons

     per minute (gpm) of water flow to satisfy the standpipe system demand; however, there is

    currently a lack of supporting scientific documentation to substantiate this flow limitation per

    inlet. Flow testing to characterize the maximum actual flow rate that can be achieved for each

    2.5-inch FDC inlet is required to support the current 250 gpm requirement or recommend a

    change to the standard.

    In summary, this project involved full-scale flow testing of multiple FDCs to determine actual

    flow characteristics and pressure loss associated with various FDC assemblies. The tests

    utilized suppression equipment consistent with real-world installations in structures and typical

     procedures for emergency response to a structure fire, including the use of a fire department

     pumper apparatus and hose to connect and flow water through the FDC assemblies.

    1 NFPA 14-2013, Section 3.3.3.1.1.2 NFPA 14-2013, Section 3.3.3.1.2.

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    15/68

    January 8, 2016

    1505254.000 7849x

    The overriding goal of this research project was to provide a technical basis to the NFPA 14

    Technical Committee for a possible change to the standard. A full listing of project

    observations as they relate to the current NFPA guidance is provided in Section 8 of this report.

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    16/68

    January 8, 2016

    1505254.000 78491

    1 Background

    1.1 Project History

    For an automatic standpipe, a fire department connection (FDC) is defined as, “A connection

    through which the fire department can pump the secondary water supply to an automatic

    standpipe system at the required system demand. Supplemental water can also be provided into

    the sprinkler system or other system furnishing water for fire extinguishment to supplement

    existing water supplies.”3  In the case of a manual standpipe, the FDC is defined as, “A

    connection through which the fire department can pump the primary water supply to a manual

    standpipe system at the required system demand.”4  Industry standards, such as National Fire

    Protection Association (NFPA) 14, Standard for the Installation of Standpipe and HoseSystems, and NFPA 13, Standard for the Installation of Sprinkler Systems, require FDCs be

    installed on standpipe systems and automatic sprinkler systems.

    Since 2007, NFPA 14 has required one (1) 2.5-inch diameter FDC inlet for every 250 gallons

     per minute (gpm) of water flow to satisfy the standpipe system demand; however, there is

    currently a lack of supporting scientific documentation to substantiate this flow limitation per

    inlet. Flow testing to characterize the maximum actual flow rate that can be achieved for each

    2.5-inch FDC inlet is required to support the current 250 gpm requirement or recommend a

    change to the standard.

    1.2 Research Objectives and Project Scope

    The overall project research objective was to provide a technical basis to the NFPA 14

    Technical Committee for a possible change to the standard.

    The scope of work included, but was not limited to, the following primary tasks:

    1.  A review of any source material for the traditional 250 gpm flow limitation for each 2.5-

    inch diameter FDC inlet (see Section 2);

    3 NFPA 14-2013, Section 3.3.3.1.1.4 NFPA 14-2013, Section 3.3.3.1.2.

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    17/68

    January 8, 2016

    1505254.000 78492

    2.  Development of a full-scale test plan for flow testing to characterize the flow of water

    into a 2.5-inch diameter inlet(s) on an FDC (see Sections 3 through 5);

    3.  Full-scale flow testing per the full-scale flow testing plan developed above, including

    three separate types of FDCs (see Section 6); and

    4.  Report of final results and summary of recommendation(s) to the NFPA 14 Technical

    Committee for the actual flow expected into a 2.5-inch FDC inlet, as well as the pressure

    loss characteristics of the FDC.

    A more detailed description of the tasks performed by Exponent to fulfill the project objectives

    is provided below.

    1.2.1 Review of Source Material for the Traditional Flow Requirement

    Exponent collected, reviewed, and summarized available source material for the traditional 250

    gpm flow limitation for each 2.5-inch diameter FDC inlet. This task included a review of

    historical records documenting any proposed additions or changes to the relevant industry

    standards (e.g., NFPA 13 and NFPA 14) in relation with the 250 gpm and 2.5-inch diameter

    FDC inlets, as well as a review of the current standard operating procedures (SOPs) and/or code

    requirements for the number of FDCs required by municipalities in varying regions throughout

    the United States (see Section 2).

    1.2.2 Development of Full-Scale Flow Test Plan

    Exponent, in conjunction with the Project Technical Panel, developed an comprehensive

     program for full-scale flow testing to characterize the flow of water into a 2.5-inch diameter

    inlet on an FDC following the SOP established in NFPA 13E, Recommended Practice for Fire

     Department Operations in Properties Protected by Sprinkler and Standpipe Systems. The

    testing utilized a fire department pumper and standard hose to connect to the inlet(s) of multiple

    types of FDCs instrumented with flow measuring devices to determine how much flow can be

    achieved as a function of the pressure loss.

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    18/68

    January 8, 2016

    1505254.000 78493

    1.2.3 Full-scale Flow Testing

    The full-scale flow testing involved testing of multiple FDCs installed on a test manifold. All

    tests utilized actual suppression equipment and procedures, including a fire department pumper

    apparatus and hose. All water flow activities were conducted by qualified active duty

    firefighters. Exponent collaborated with the Maryland Fire and Rescue Institute (MFRI), who

     provided their facilities and expertise. Their training staff was utilized to provide technical

    insight on standard FDC connection procedures and to facilitate the tests. Active duty

    firefighters from MFRI performed all water flow activities.

    1.2.4 Report and Summary of Best Practices

    Exponent collected and processed the test data from the full-scale testing program in this formal

    research engineering report. This report provides:

    1.  An overview of the project work to date;

    2.  A summary of the full-scale test data;

    3.  Comparison with current NFPA guidance; and

    4.  Identification of future potential research.

    1.3 Project Assumptions

    The following are key assumptions and limitations related to the test program:

      The FDCs procured for this test program are only a small set of samples intended to

     provide a preliminary understanding of FDC hydraulic characteristics (i.e., flow and

     pressure loss) in a broad range of FDC configurations. The test results from this study

    are not intended to be representative of all FDCs available or used in systems.

      FDC flow rate data obtained from this test is specific to the upstream supply line

    configuration and components used in this test program (i.e., hoses and fittings).

      These upstream supply components, including the fire department pumper, are typical

    equipment used during fire department operations. Friction losses associated with the

    upstream equipment are well documented.

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    19/68

    January 8, 2016

    1505254.000 78494

    2 Literature Review

    2.1 Current FDC Requirements

    FDC requirements are currently defined by NFPA 14 for standpipe systems and NFPA 13 for

    sprinkler systems. The purpose of a standpipe system is to eliminate the need for excessively

    long runs of hose for manual firefighting inside a structure. Standpipes allow firefighters to

    connect a hose to a permanently installed valve on the standpipe system inside a building and

    fight a fire with a shortened amount of hose. FDCs allow firefighters to supplement, or fully

    supply, the standpipe water flow from an external water source, such as a hydrant or pond,

    through a pumper apparatus to the structure. The current (2013) edition of NFPA 14 requires

    that the full standpipe system demand be available from FDCs, and states in Section 7.12.3:

    Fire department connection sizes shall be based on the standpipe system demand and

    shall include one 2 1  ⁄  2 in. (65 mm) inlet per every 250 gpm (946 L/min).

    In contrast, for sprinkler systems, the current (2013) edition of NFPA 13 states in Section 6.8.1,

    that FDC(s) shall consist of two (2) 2.5-inch inlets, unless otherwise designated by the Authority

    Having Jurisdiction (AHJ), or where piped to a 3-inch or smaller riser.5  Further clarification is

     provided in the annex, which states that the purpose of the FDC is to supplement the water

    supply, but not necessarily provide the entire sprinkler system demand. NFPA 13-2013 further

    states that FDCs are not intended to deliver a specific volume of water.6 

    The FDC requirements in NFPA 14 are more explicit than the requirements in NFPA 13 and

    specifically call for FDCs to have one (1) 2.5-inch diameter hose connection for each 250 gpm

    of system demand. A typical standpipe system in a fully sprinkler protected facility may need

    up to four (4) FDC inlets to satisfy the system demand. Where adopted, the requirements of

     both standards must be met, including those requiring the more restrictive FDC capacity of 250

    gpm for every 2.5-inch diameter inlet in a combined sprinkler/standpipe system.

    5 NFPA 13-2013 Section 6.8.16 NFPA 13-2013 Section A.6.8.1

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    20/68

    January 8, 2016

    1505254.000 78495

     NFPA 14 also requires manual standpipe systems be designed to provide 100 psi at the topmost

    outlet, with hydraulic calculations terminating at the FDC.7  The intent of the standard is for a

    fire department pump to be the source of flow and pressure8, however, pressure loss values for

    the FDC itself are not provided in the standard and data from the manufacturers is currently

    unavailable (see Section 2.4).

    Although not directly related to FDC inlet flow, the 2016 edition of NFPA 20, Installation of

    Stationary Pumps for Fire Protection, offers an interesting correlation of flow (pump rating in

    gpm) to the number of hose valve outlets required. For pumps rated from 100 to 1,000 gpm, the

    number of outlets required approximately follows a similar 250 gpm per 2.5-inch valve ratio as

     prescribed in NFPA 14, however, there is more variability at certain higher flows (above 1,250

    gpm), where greater than 250 gpm is allowed per each 2.5-inch diameter valve.9 

    2.2 History of the NFPA 14 Requirement

    The current FDC requirement in Section 7.12.3 of NFPA 14 first appeared in the Report on

    Proposals for the 2007 edition of the standard. The substantiation of the request states that the

     proposal is the result of the Standpipe Task Group, which met in June 2004 and forwarded its

    recommendations to the Technical Committee on Standpipes for action.10,11  Since it first

    appeared in the 2007 edition of NFPA 14, Section 7.12.3 has resulted in proposals to remove the

    restriction based on manual standpipe pumper tests that indicate 2.5-inch diameter inlets on an

    FDC are capable of significantly more flow.12

      One response to a proposal to modify the section

    states that the restriction is intended to simplify and assist contractors in understanding how

    many inlets to provide for firefighting operations, not just for testing.13

      The 2.5-inch inlet flow

    requirement of 250 gpm is understood to be a conservative value under ideal delivery conditions

    and allows for redundancy for firefighting operations in the event that an FDC is lost.14

      Other

    7 NFPA 14-2013 Section 7.8.1.2.8 NFPA 14-2013 Section A.7.8.1.2.9 NFPA 20-2016 Table 4.27(a).10 NFPA 14 Report on Proposals 2005, 14-58 Log #47.11 Minutes have been requested for the June 2004 meeting of the Standpipe Task Group.12 NFPA 14 Report on Proposals 2012, 14-70 Log #16.13 NFPA 14 Report on Comments 2012, 14-35 Log #38.14 NFPA 14 Report on Proposals 2012, 14-70 Log #16.

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    21/68

    January 8, 2016

    1505254.000 78496

    reasons for the fixed inlet flow requirement include the anticipation of pressure loss possible

    due to the location of fire hydrants and arrangement of supply hose from the hydrant to a

     pumper and from the pumper to the FDC, including the distance traveled and elevation

    changes.15

     

    2.3 Jurisdictional Adoptions and Procedures

    A survey of several major municipalities in varying regions throughout the United States was

    conducted to determine their current code adoptions relative to standpipe systems and specific

    requirements for number of FDC inlets serving standpipe systems, as shown in Figure 1. In

    addition, literature was reviewed to determine the most common arrangement for equipment

    supplying an FDC.

    Figure 1 Map of municipalities included in survey

    15 NFPA 14 Report on Comments 2012, 14-34 Log #9.

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    22/68

    January 8, 2016

    1505254.000 78497

    2.3.1 Code Adoptions

    2.3.1.1 Los Angeles, Califo rnia

    The 2014 City of Los Angeles Fire Code adopts portions of the California Fire Code (CFC) and

    the 2012 edition of the International Code Council (ICC) International Fire Code (IFC).

    16

     Section 905.2 states that standpipe systems shall be installed according to an amended version

    of NFPA 14-2013. The amended portion does not affect the requirements of Section 7.12.3.17

     

    The current Los Angeles Municipal Code (6 th edition) outlines the amendments to NFPA 14 and

    the amended portion does not affect the requirements of Section 7.12.3.18

      In addition to Section

    7.12.3, the previous edition of the Los Angeles Municipal Code also mandated the number of

    FDCs based on the height of the highest outlet above the FDC and the number of the standpipe

    risers.19  This requirement no longer applies to new construction after January 2014.

    2.3.1.2 New York, New York

    The 2014 New York City Fire Code, Section 905.2, states that standpipe systems shall be

    installed in accordance with the construction codes, including the Building Code.20 The 2014

     New York City Building Code, Section 905.2, states that standpipe systems shall be installed

    according to an amended version of NFPA 14-2007. The amended portion deletes Section

    7.12.3.21  Instead, the New York City Administrative Code, Section 27-940, requires at least one

    siamese connection, an FDC with two-way inlets, for each 300 feet of exterior building wall.

    2.3.1.3 Chicago, Illinois

    The Municipal Code of Chicago, Title 15, Fire Prevention, Section 15-16-1020, requires at least

    one siamese connection on each street exposure, to a limit of two street exposures. If any

    16 http://www.ecodes.biz/ecodes_support/free_resources/2014LACityFire/14Fire_main.html, Section 101, as ofSeptember 21, 2015.

    17 2014 Los Angeles Fire Code Chapter 80, Referenced Standards.18 City of Los Angeles Municipal Code, 6th Edition, Ordinance No. 182847, Section 94.2020.0, NFPA 14.19 City of Los Angeles Municipal Code, 5th Edition, Ordinance No. 179324, Section 94.2020.8, Table 4.8.220 http://www.nyc.gov/html/fdny/apps/pdf_viewer/viewer.html?file=firecode_chap_09.pdf&section=firecode_2014,

    as of September 21, 2015 21 2014 New York City Building Code Appendix Q, Modified National Standard for Automatic Sprinkler,

    Standpipe, Fire Pump and Fire Alarm Systems.

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    23/68

    January 8, 2016

    1505254.000 78498

    exposure is more than 250 feet long, two siamese connections are required, spaced at least 200

    feet apart.22 

    2.3.1.4 At lanta, Georgia

    The state of Georgia adopts State Minimum Fire Safety Standards, based on the 2012 edition of

    the IFC, with modifications. Section 905.1 states that standpipe systems shall be installed in

    accordance with NFPA 14-2013, as amended. The amended portion does not affect the

    requirements of Section 7.12.3, however, a new section (7.12.4) is added that states that the

    location of FDCs shall be approved by the Fire Chief.23 

    2.3.1.5 Orlando, Flor ida

    The Orlando Building Code incorporates the 2014 Florida Building Code

    24

    , which is based onthe 2012 edition of the ICC International Building Code (IBC). Section 905.2 states that

    standpipe systems shall be installed in accordance with the Florida Building Code and NFPA

    14-2010.25  In addition, the City of Orlando Fire Prevention Code adopts NFPA 1, Uniform Fire

    Code, Chapter 13, Fire Protection Systems, and amends Section 13.2.2.1 to state that two (2)

    siamese connections shall be provided in the path of fire department access, one at each end of

    the building or as remotely located as possible.26 

    2.3.1.6 Kansas City, Missouri

    The Kansas City, Missouri Code of Ordinances adopts the 2012 edition of the IBC, with

    amendments.27,28  Section 905.2 of the 2012 IBC states that standpipe systems shall be installed

    in accordance with NFPA 14-2010. The amended portion does not affect the requirements of

     NFPA 14 Section 7.12.3.

    22 http://www.amlegal.com/nxt/gateway.dll/Illinois/chicagobuilding/buildingcodeandrelatedexcerptsofthemunic?f=templates$fn=default.htm$3.0$vid=amlegal:chicagobuilding_il; Current through March 18, 2015.

    23 Georgia Minimum Fire Safety Standards (Chapter 120-3-3), effective January 1, 2015.24 Orlando, Florida Code of Ordinances, Supplement 57, Update 2, Chapter 13, Building Code.25 Florida Building Code, Building, 5th Edition (2014), Chapter 35, Referenced Standards.26 Orlando, Florida Code of Ordinances, Supplement 57, Update 2, Chapter 24, Fire Prevention Code, Section

    24.27.27 Kansas City, Missouri Code of Ordinances, Article II, Sec. 18-40.28 The Kansas City, Missouri Code of Ordinances further adopts the 2000 edition of the IFC, with amendments, in

    Sec. 26-100, however, the 2012 edition of the IBC is the more recent and restrictive adoption of NFPA 14, andtherefore prevails.

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    24/68

    January 8, 2016

    1505254.000 78499

    2.3.1.7 Fort Worth, Texas

    The Fire Code of the City of Forth Worth adopts the 2009 edition of the IFC, with

    amendments.29

      Section 905.2 of the 2009 IFC states that standpipe systems shall be installed in

    accordance with NFPA 14-2007. The amended portion does not affect the requirements of

     NFPA 14 Section 7.12.3.

    2.3.1.8 Seatt le, Washington

    The Seattle Building Code adopts the 2012 edition of the IBC, with amendments.30

      Section

    905.2 of the 2012 IBC states that standpipe systems shall be installed in accordance with NFPA

    14-2010.

    2.3.1.9 Distri ct of Columbia

    The 2013 District of Columbia Fire Code is based on the 2012 edition of the IFC.31  Section

    905.2 states that standpipe systems shall be installed according to NFPA 14-2010, with

    exceptions. The exceptions do not affect the requirements of Section 7.12.3.32

     

    2.3.1.10 Las Vegas, Nevada

    The Municipal Code of the City of Las Vegas adopts the 2012 edition of the IFC, along with the

    Southern Nevada Fire Code Amendments.33  Section 905.2 of the 2012 IFC states that standpipe

    systems shall be installed according to NFPA 14-2010. The Southern Nevada Fire Code

    Amendments change the requirements of Section 7.12.3 to address the sprinkler system demand

    (if a combined system); however, they do not affect the inlet flow requirement of 250 gpm. The

    requirements of 7.8.1.1 are changed to require manual standpipe systems be designed to provide

    125 psi (instead of 100 psi) at the topmost outlet.34

     

    29 Fort Worth Ordinance Number 19607-03-2011.30 Seattle Municipal Code, Supplement 2, Update 2, Title 22, Subtitle I,  Building Code.31 http://www.ecodes.biz/ecodes_support/Free_Resources/2013DistrictofColumbia/13Fire/13DCFire_main.html, ,

    as of September 21, 2015 32 2013 District of Columbia Fire Code, Chapter 80, Referenced Standards.33 Municipal Code of the City of Las Vegas, Supplement 23, Title 16, Chapter 16.16,  International Fire Code.34 2014 Southern Nevada Fire Code Amendments.

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    25/68

    January 8, 2016

    1505254.000 784910

    2.3.2 Standpipe Firefighting Operations

    A review of the literature revealed that there is scarce information currently published regarding

    the arrangement and connection of hose from the water source, through a fire department

     pumper apparatus, to an FDC. A research study by the U.S. Fire Administration recommends

    that fire departments have water supply SOPs that establish which units are responsible for

    supplying FDCs, possibly including special pumping procedures. The study cites one SOP that

    includes details for water supply operations: Dallas, Texas specifies that two pumpers supply

    the standpipe system for redundancy or in case higher pressure is required. Dallas also does not

    allow the use of “large diameter hose” to connect the pumper to the standpipe.35 

    There are many studies detailing standpipe operations, however, they focus on the building

    interior connections and the attack hose and nozzle configurations. A research study by the

    Oakland Fire Department aimed at updating their high-rise firefighting procedures surveyed ten

    (10) major municipalities and determined that a majority of the fire departments surveyed use a

    2.5-inch hose with a 1 1/8-inch smooth bore nozzle for standpipe operations, however, some use

    a 1 ¾-inch hose with a 7/8-inch smooth bore nozzle. The research study further determined that

    a high-rise building standpipe system must be augmented by fire apparatus for effective

    firefighting practices.36  A similar research study performed by the New Orleans Fire

    Department surveyed 12 major municipalities and found that most departments surveyed only

    have a casual reference to water supply operations in their SOPs, which instructs the first due

    engine to connect to the FDC and supply the system with “appropriate pressure.” Field tests

    conducted during the same research study determined that a 1,250 gpm dual stage pump in a

     pumper apparatus could develop outlet pressures of 200 to 600 psi.37

     

    The 2015 edition of NFPA 13E provides basic procedures and information for use in fire

    department operations involved with automatic sprinkler and standpipe systems. Figure 4.3.4(b)

    specifies a minimum 2.5-inch hose to supply the FDC from the pumper for supplementing an

    35 U.S. Fire Administration/Technical Report Series, “Special Report: Operational Considerations for HighriseFirefighting.” USFA-TR-082/April 1996.

    36 Edwards, J. “High-Rise Firefighting: An Analysis of Procedures for Operational Effectiveness.” Oakland FireDepartment, Oakland, CA.

    37 Savelle, G. “Fire Department High Pressure Pumping Operations at High-Rise Fires.” New Orleans FireDepartment, New Orleans, LA.

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    26/68

    January 8, 2016

    1505254.000 784911

    automatic sprinkler system; however, a minimum hose diameter is not specified for standpipe

    operations. Instead, Section 6.3.3 states that lines from a pumper should be connected and

    charged to the pressure required to give the desired working pressure on the standpipe outlets

     being used. In addition, Section 6.3.4.1 states that the pump operator should consider the

    following factors in calculating the pump discharge pressure:

      Friction loss in the hose supplying the FDC;

      Friction loss in the standpipe system itself;

      Pressure loss due to the elevation of the nozzles;

      The number and details of the attack lines operating from the standpipe; and

      The pressure desired at the nozzles.

    Pressure losses for fire hoses of various lengths and diameters are well characterized and

    documented 38

    , allowing the supply hose diameter to be chosen based on the needs of the fire

    department.

    2.4 Existing FDC Flow Test Data

    Data sheets from six (6) FDC manufacturers were reviewed for existing flow test data or friction

    loss information. Of the approximately 30 models reviewed (most with multiple configurations,

    i.e., clappers, inlet arrangement, etc.), none currently provide any flow test data or friction loss

    information. Most provide (minimum) inlet flow capacities in line with the NFPA 14

    requirement for one (1) 2.5-inch diameter inlet per 250 gpm of flow. Three manufacturers

     provided pressure ratings on at least one FDC, ranging from 175 to 500 psi.

    FDC data sheets generally referenced listings from Underwriters Laboratories (UL) and/or

    approval by FM Global (FM). UL 405, Standard for Fire Department Connection Devices, wasreviewed and references NFPA 14 for the installation of FDCs for standpipe systems. UL 405

    does not provide flow test data; however, it does specify that FDCs are tested to 300 psig for

    38 Scheffey, J.L., et al., Determination of Fire Hose Friction Loss Characteristics, The Fire Protection ResearchFoundation, October 2013.

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    27/68

    January 8, 2016

    1505254.000 784912

    leakage and strength of body. 39

      In addition, FM 1530, Approval Standard for Fire Department

    Connections, was reviewed and also does not provide flow test data; however, it specifies that

    the minimum rated working pressure shall be 175 psig.40

     

    2.5 Summary

    FDCs allow firefighters to supplement, or fully supply, the standpipe water flow from an

    external water source, such as a hydrant or pond, through a pumper apparatus to a structure.

     NFPA 14 requires that the full standpipe system demand be available from FDCs and requires

    one (1) 2.5-inch diameter inlet for every 250 gpm of standpipe demand. The FDC requirements

    in NFPA 14 are more prescriptive than those in NFPA 13. In a combined sprinkler/standpipe

    system, the more restrictive requirements of NFPA 14 generally apply. In addition, NFPA 14

    requires manual standpipe systems be designed to provide 100 psi at the topmost outlet, with

    hydraulic calculations terminating at the FDC, however, pressure loss values for the FDC itself

    are not provided in the standards and data from the manufacturers is currently unavailable.

    Several major municipalities in varying regions throughout the United States were surveyed to

    determine their current code adoptions relative to standpipe systems and specific requirements

    for number of FDC inlets serving standpipe systems. Of the 10 municipalities surveyed, the

    majority adopt NFPA 14 with no modification of the default NFPA 14 FDC inlet flow

    requirements. Municipalities that do not adopt NFPA 14 requirements generally use the number

    of exposures and length of the building exposure side to determine the number of FDCs

    required.

    While the current NFPA requirements do not include the number and the length of the building

    exposure sides as a factor to determine the number of required FDCs, it is recognized that

    certain jurisdictions highlight the need for redundancy of FDCs by taking the building exposures

    into consideration. Based on this information, redundancy appears to be an important factor for

    overall system reliability.

    39 UL 405, 6th Edition, August 23, 2013.40 FM 1530, August 1970.

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    28/68

    January 8, 2016

    1505254.000 784913

    In addition, literature was reviewed to determine the most common arrangement for equipment

    supplying an FDC. Although there is a lack of information specific to water supply operations

    at high-rise structure fires, it was determined that pressure losses for fire hoses of various

    lengths and diameters are well characterized and documented, allowing pressure loss of the

    FDC component to be calculated independent of the upstream supply components.

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    29/68

    January 8, 2016

    1505254.000 784914

    3 Testing Program Summary

    Exponent, with guidance from the Project Technical Panel, conducted a series of flow tests on

    common FDCs with the following goals: 1) to determine the maximum flow rate that can be

    achieved for each 2.5 inch diameter inlet and 2) to measure the pressure losses associated with

    the FDCs as a function of flow rate. Three common types of FDCs were acquired for this test

     program, including single, siamese (two-way inlets), and triamese (three-way inlets). A more

    detailed description of each acquired FDC is provided in Section 4.

    A fire department pumper, Model 2011 Pierce Arrow XT, rated at 2,000 gpm capacity with a

    minimum net pressure of 150 psi was utilized to supply water flow from a municipal fire

    hydrant. Each FDC inlet was connected via a standard 2.5-inch diameter hose with a 100-foot

    length (two 50-foot sections). A pressure transducer was instrumented upstream of each FDC

    inlet. Downstream of the FDC outlet, an in-line averaging pitot tube was instrumented to obtain

    the total flow rate as well as the pressure loss across the FDC assembly. With the exception of

     pressure readings on the supply hoses from the fire department pumper and the differential

     pressure on the in-line averaging pitot tube, all pressure measurements were recorded via a data

    acquisition system to allow for real-time monitoring of the flow condition to ensure pressure

    data during the steady state flow conditions were captured at a target flow rate.

    For each flow test, water was charged to the FDC inlet(s) starting from a low flow condition to

    develop bulk flow (no greater than 150 gpm), then gradually increased to a target flow rate for

    the FDC assembly as outlined in the test matrix (see Table 1). Where multiple FDC inlets were

    tested simultaneously, the flow was equally distributed to each inlet. At the respective target

    flow rate, a minimum of 2 minutes was allowed for a steady state condition to develop. After a

    maximum flow was reached, the flow was gradually decreased to a lower target flow rate and

    the measurements were repeated. The achievement of the maximum flow was determined based

    on the flow capacity available of from the hydrant, as well as the general safety observations

    during the test. As a safety precaution, due to a potential for high velocity flow, it was

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    30/68

    January 8, 2016

    1505254.000 784915

    determined that the theoretical maximum flow was approximately 750 gpm per each 2.5-inch

    diameter FDC inlet (three times the current prescriptive requirement of 250 gpm).41 

    A detailed description of the test apparatus setup, measurements, and the test protocols is

     provided in Section 5.

    Table 1 Test Matrix

    TestNo.

    FDC ID FDC Type Test ID*Flow to Inlet

    NumberTarget Flow [gpm]

    1 FDC-1 Single FDC-1-1 1 250, 500, Max

    2 FDC-2 Single FDC-2-1 1 250, 500, Max3 FDC-3 Single FDC-3-1 1 250, 500, Max

    4FDC-4 Siamese

    FDC-4-1 1 250, 500, Max

    5 FDC-4-2 1 and 2 500, 1000, Max

    6FDC-5 Siamese

    FDC-5-1 1 250, 500, Max

    7 FDC-5-2 1 and 2 500, 1000, Max

    8

    FDC-6 Triamese

    FDC-6-1A 1 250, 500, Max

    9 FDC-6-1B 2 (center inlet) 250, 500, Max

    10 FDC-6-2 1 and 2 500, 1000, Max

    11 FDC-6-3 1, 2, and 3 750, 1200, Max

    * Test ID nomenclature used in this test program follows the format: XXX-X-Y, where “XXX-X” is FDC ID and “-Y”represents the number of charged inlet(s).

    41 Water flow at 750 gpm through a 2.5-inch diameter conduit will result in a flow velocity of approximately 49ft/s.

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    31/68

    January 8, 2016

    1505254.000 784916

    4 FDC Descriptions

    In conjunction with FPRF, Exponent procured a total of six (6) FDCs for testing. A description

    of each FDC procured is provided in Table 2, below.

    Table 2 FDC Descriptions

    FDC ID FDC Type Descript ion Figure Manufacturer

    FDC-1 Single

    Flush single inlet

    Material: Brass

    Size: 2.5-in x 2.5-in

    Figure 3 A

    FDC-2 Single

    Flush single inlet

    Material: Brass

    Size: 2.5-in x 2.5-in

    Figure 4 B

    FDC-3 Single

    Flush single inlet

    Material: Brass

    Size: 2.5-in x 2.5-in

    Figure 5 C

    FDC-4 Siamese

    Freestanding siamese with singleclapper two-way inlet

    Material: Brass

    Size: 4-in x 2.5-in x 2.5-in

    Figure 6

    Figure 7B

    FDC-5 Siamese

    Projecting siamese with doubleclappers two-way inlets

    Material: Brass

    Size: 4-in x 2.5-in x 2.5-in

    Figure 8

    Figure 9

    D

    FDC-6 Triamese

    Flush triamese with triple clappersthree-way inlets

    Material: Brass

    Size: 6-in x 2.5-in x2.5-in x 2.5-in

    Figure 10 B

    4.1 Single FDCs

    Three (3) single FDCs (FDC-1, FDC-2, and FDC-3) from three different manufacturers were

     procured for testing. All three FDCs procured were flush type with a 2.5-inch American

     National Fire Hose Screw Threads (NH) swivel female inlet and a 2.5-inch National Pipe

    Thread (NPT) female outlet. The appearances and dimensions of all three single FDCs were

    very similar, but FDC-1 was slightly longer, while FDC-2 and FDC-3 were almost identical.

    All three single FDCs were equipped with rubber gaskets on the inlet side, although there were

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    32/68

    January 8, 2016

    1505254.000 784917

    slight variations in gasket thickness and width among the three single FDCs. A comparison of

    the single FDCs is provided in Figure 2. None of the single FDCs were equipped with clappers.

    4.2 Siamese FDCs

    Two (2) siamese FDCs (FDC-4 and FDC-5) from different manufacturers were obtained for

    testing. Both siamese FDCs contained two (2) 2.5-inch NH swivel female inlets equipped with

    rubber gaskets and a 4-inch NPT female outlet. FDC-4 was a freestanding type (integral 90°

    orientation) with a single inlet clapper, as shown in Figure 6 and Figure 7. FDC-5 was a

     projecting type with dual inlet clappers, as shown in Figure 8 and Figure 9. The clappers in

     both siamese FDCs (FDC-4 and FDC-5) were not equipped with a spring-loaded closing

    mechanism (snoot type clappers).

    4.3 Triamese FDC

    One triamese FDC (FDC-6) was procured for testing, as shown in Figure 10 and Figure 11. The

    triamese FDC was a flush wall-mount type with three (3) 2.5-inch female NPT inlets with triple

    inlet clappers and a 6-inch NPT female outlet. No rubber gasket was provided with the triamese

    FDC and the clappers were not equipped with a spring-loaded closing mechanism.

    Figure 2 Single FDCs

    FDC-1 FDC-2 FDC-3

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    33/68

    January 8, 2016

    1505254.000 784918

     

    Figure 3 Single flush FDC (FDC-1)

    Figure 4 Single flush FDC (FDC-2)

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    34/68

    January 8, 2016

    1505254.000 784919

     

    Figure 5 Single flush FDC (FDC-3)

    Figure 6 Siamese freestanding FDC (FDC-4)

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    35/68

    January 8, 2016

    1505254.000 784920

     

    Figure 7 Siamese freestanding FDC (FDC-4); view from bottom showing single clapper

    Figure 8 Siamese projecting FDC (FDC-5)

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    36/68

    January 8, 2016

    1505254.000 784921

     

    Figure 9 Siamese projecting FDC (FDC-5); view through outlet showing double inlet clappers

    Figure 10 Triamese flush FDC (FDC-6)

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    37/68

    January 8, 2016

    1505254.000 784922

     

    Figure 11 Triamese flush FDC (FDC-6); view through inlet showing clappers

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    38/68

    January 8, 2016

    1505254.000 784923

    5 Test Setup

    The FDC flow testing was performed at MFRI in College Park, Maryland.42  The overall intent

    of the testing was to provide a repeatable scientific experiment that characterizes the flow

    characteristics at the maximum actual flow rate for each 2.5-inch FDC inlet. The data generated

    was then used to support the current 250 gpm requirement or recommend a change to the

    standard. The following are key assumptions related to the testing:

      The FDCs procured for this test program are only a small set of samples intended to

     provide a preliminary understanding of FDC hydraulic characteristics (i.e., flow rate and

     pressure loss). The test results from this study are not representative of all available

    FDCs of similar types.

      FDC flow rate data obtained from this test program is specific to the upstream supply

    line configuration and components used in this test program (i.e., hoses and fittings).

      These upstream supply components are commonly used during fire department

    operations and their friction loss characteristics are well documented.

    A series of flow tests were conducted on common FDCs with the following objectives: 1) to

    determine the maximum flow rate that can be achieved for each 2.5 inch inlet and 2) to measure

    the pressure losses associated with each type of FDC as a function of the flow rate. Data

    collected during these tests included:

      Total FDC discharge flow rates;

      Pressure losses;

      Test observations;

      Still photography; and

      High definition video.

    42 MFRI provides a world class test facility for research, development, and testing of fire protection systems and

    fire service technologies in live-fire conditions. 

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    39/68

    January 8, 2016

    1505254.000 784924

    MFRI provided the facility for the flow tests, the fire department apparatus and water supply,

    and qualified personnel to conduct the actual water flow.

    Exponent performed the following tasks:

      Test observations and data monitoring;

      Providing and installing the flow rate and pressure measurement devices and data

    acquisition system (DAQ);

      Still photography; and

      High definition video recording;

    5.1 Test Apparatus

    The test apparatus setup is described herein as follows.

    5.1.1 Water Flow Activit ies

    Water flow activities were handled by MFRI. All tests were conducted by three active duty

    firefighters utilizing a fire department pumper 43

    , Model 2011 Pierce Arrow XT, rated at 2,000

    gpm capacity and capable of charging water through up to six (6) 2.5-inch hose lines with a

    minimum net pressure of 150 psi per NFPA 1901, Standard for Automotive Fire Apparatus.

    The fire department pumper used in this test program is shown in Figure 12.

    The test apparatus utilized water from a municipal hydrant producing a static pressure of 100 psi

    and a residual pressure of 50 psi at a 3,757 gpm flow rate.44  Water was discharged into a

    collection funnel, allowing the water to flow into a drafting basin with its drainage open during

    testing (see Figure 13 and Figure 14).

    43 Engine 122, College Park Volunteer Fire Department, Maryland.44 Hydrant Test – Hydrant 62, dated 6/1/2013

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    40/68

    January 8, 2016

    1505254.000 784925

     

    Figure 12 Fire department pumper apparatus

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    41/68

    January 8, 2016

    1505254.000 784926

     

    Figure 13 Test facility and drafting basin at MFRI

    Figure 14 Test platform with single FDC and test apparatus secured to test platform

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    42/68

    January 8, 2016

    1505254.000 784927

     

    Figure 15 Test platform with siamese FDC and test apparatus secured to test platform

    Figure 16 Test platform with triamese FDC and test apparatus secured to test platform

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    43/68

    January 8, 2016

    1505254.000 784928

    5.1.2 Supply Hose Line

    In all flow tests, 2.5-inch diameter double-jacket rubber-lined standard fire hoses with a total

    length of 100 feet (two 50-foot length sections) were used to supply water to the FDC inlets.

    The use of a 2.5-inch diameter hose eliminated the need for any hose adapters before connecting

    to the FDC inlets and the 100-foot length was required given the location of the fire department

     pumper and the test apparatus during the test.

    While the total flow rate obtained from this test program is specific to the selected hose size and

    configuration, the pressure loss for each FDC is a function of the flow rate and is independent of

    the hose configuration or pressure losses from the upstream components. Pressure losses for

    fire hoses with different lengths and diameters are well characterized and documented.45 

    5.1.3 Flow Test Assembly

    During each flow test, the FDC assembly was secured to the test platform to allow for safely

    discharging water into the drafting basin. A pressure transducer was instrumented upstream of

    each FDC inlet. Downstream of the FDC outlet, an in-line averaging pitot tube was

    instrumented to obtain the total flow rate, as well as the pressure drop across the FDC. The

    inlets and outlet of the FDC were connected with steel pipes with appropriate lengths to allow

    for accurate pressure measurements at approximately five times the pipe diameter (5D) length

    upstream and up to ten times the pipe diameter (10D) length downstream of the FDC. With the

    exception of pressure readings on the supply hoses from the fire department pumper and the

    differential pressure on the in-line averaging pitot tube, all pressure measurements were

    recorded via a data acquisition system to allow for real-time monitoring of the flow condition to

    ensure pressure data during the steady state flow conditions were captured at a target flow rate.

    Calibrated pressure transducers (Omega PX309) were used for the pressure measurements in

    this test program. Figure 17 through Figure 19 provide the schematics for the flow test

    assembly.

    45 Scheffey, J.L., et al., Determination of Fire Hose Friction Loss Characteristics, The Fire Protection ResearchFoundation, October 2013.

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    44/68

    1505254.000 7849

    29

    Figure 17 Flow test schematic for single FDC

    Figure 18 Flow test schematic for siamese FDC

    Supply fromStreet

    Hydrant 

    Single FDC

    PU1,n

    In

    PD, t

    PressureTransducer

    Pumper

    Pp1

     

    2.5” Hose Line100 ft  1 ft (~5D)

    2.5” Steel Pipe 2 ft (~10D)

    2.5” Steel Pipe 

    Supply fromStreet

    Hydrant 

    Siamese FDC

    PU1, n

    In

    PD, t

    PressureTransducer

    Pumper

    Pp1

    2.5” Hose Line

    2.5” Steel Pipes 3 ft (~10D)

    4” Steel Pipe 

    PU2, n

    2.5” Hose Line

    100 ft

    Pp2

    1 ft (~5D)

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    45/68

    1505254.000 7849

    30

     

    Figure 19 Flow test schematic for triamese FDC

    Supply fromStreet

    Hydrant 

    Triamese FDCPU1, n

    PD, t

    PressureTransducer

    Pumper

    Pp1

      2.5” Hose Line

    2.5” Steel Pipes 

    3 ft (~6D)6” Steel Pipe

    PU2, n

    2.5” Hose Line

    100 ftP

    p2 

    1 ft (~5D)

    PU3, n

    Pp3

     

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    46/68

    January 8, 2016

    1505254.000 784931

    5.1.4 Flow Rate Measurements

    During the flow testing, the FDC flow rate was determined based on the measurements of the

    differential pressure between the total pressure (stagnation pressure) and the normal pressureusing an in-line averaging pitot tube instrumented downstream of the FDC. Three different

    models of in-line averaging pitot tubes (Dwyer DS-300-2-1/2, DS-300-4, and D-S400-6) were

    used depending upon the type and outlet size of the FDC. A schematic for the in-line pitot tube

    is shown in Figure 20.

    Figure 20 Flow rate measurement with in-line averaging pitot tube

    A calibrated digital manometer (Dwyer 477-7-FM) was used to measure the differential

     pressures at the in-line pitot tube, which were then used to calculate the total discharge flow rate

     based on the following expression46

    :

    46 Dwyer Instruments, Inc. DS Flow Sensors – Installation and Operating Instructions Flow Calculations, FR72-

    440451-01 Rev. 2, July 2004

    FlowDirection

    Connecting to digitalmanometer and

    pressure transducer  

    Connecting to digital manometer  

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    47/68

    January 8, 2016

    1505254.000 784932

    5.668 ∙  ∆/  (1)

    where Q is the flow rate expressed in gpm; K  is the flow coefficient (0.62 for a 2.5-inch pipe,

    0.67 for a 4-inch pipe, and 0.71 for a 6-inch pipe); D is the inside pipe diameter in inches; P is

    the differential pressure in inches-of-water-column; and S  f  is specific gravity of water at the

    flowing condition.47 

    5.1.5 Pressure Loss Measurements

    In general, pressure losses through the FDC can be theoretically estimated based on the

    difference between the total pressures measured upstream and downstream of a hydraulic

    component when the change in elevation is negligible. The total pressure (Pt ) is given as a sum

    of the normal pressure (Pn) and the velocity pressure (Pv):

          (2)

    The normal pressure is the pressure acting against, or perpendicular to the hydraulic component

    wall. The velocity pressure is a measure of the energy required to keep the water in motion.

    The velocity pressure always acts in the direction of water flow, while the normal pressure acts

     perpendicular to the velocity pressure.48

     

    For this test program, the pressure loss associated with each FDC was determined based on the

    difference between the total pressure obtained from upstream and downstream of the FDC and

    the pressure losses associated with the steel pipes upstream and downstream of the FDC. The

    downstream total pressure was directly measured using the in-line averaging pitot tube, whereas

    the upstream total pressure was estimated from the summation of the measured upstream

    normal pressure and the calculated velocity pressure, which is given as49

    :

      0.001123/  (3)

    47 At the time of the test, water temperature was approximately 60°F corresponding to the specific gravity of 1.48 NFPA, Automatic Sprinkler Systems Handbook, 10th Edition, p. 80049 NFPA 13-2013, Section 23.4.2.2

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    48/68

    January 8, 2016

    1505254.000 784933

    where Q is inlet flow rate in gpm and D is the inside pipe diameter in inches. For single FDCs,

    the inlet flow rate is equal to the measured discharge flow rate. For the siamese and triamese

    FDCs, the inlet flow rate is determined based on the assumption that the inlet flows are equally

    divided and conservation of mass applies (i.e., the sum of the inlet flows equals the discharge

    flow).

    5.1.6 DAQ System

    With the exception of pressure readings on the supply hoses from the fire department pumper

    and the differential pressure on the in-line averaging pitot tube, all pressure measurements were

    recorded via a Fluke 2638A Hydra Series III DAQ system to allow for real-time monitoring of

    the pressures and flow conditions at one second intervals (1 Hz). The DAQ system was used to

    capture the pressure data during steady state flow conditions, as well as to post process the

     pressure data to minimize the potential effect of vibration and other measurement noise during

    the flow testing.

    5.1.7 Still Photography and High Definition Video

    Still photography and high definition video were recorded during the flow testing. Still

     photography was captured using a Nikon D3300 digital camera and high definition video was

    captured using multiple Canon Vixia high definition camcorders.

    5.2 Flow Test Protocols

    The operation of the fire department apparatus and water flow activities were conducted by

    MFRI and qualified personnel (i.e., active duty firefighters) in accordance with NFPA 13E.

    Exponent instrumented the measurement devices, recorded observations, and monitored the data

    collected during testing.

    The test preparation protocol was as follows:

    1.  Connect the FDC inlet(s) and outlet to the upstream and downstream steel pipe sections

    that were pre-instrumented with appropriate pressure transducers and an in-line pitot

    tube.

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    49/68

    January 8, 2016

    1505254.000 784934

    2.  Secure the FDC and test apparatus to the test platform.

    3.  Connect the 2.5-inch supply hose lines to the inlet steel pipe sections and to the fire

    department pumper.

    4.  Straighten the supply hose line as much as possible to minimize the pressure loss.

    5.  Ensure the drainage to the drafting basin and the general test assembly are in proper

    operating condition.

    6.  Initialize and ensure proper operation of the fire department pumper (conducted by

    MFRI) in accordance with NFPA 1901, NFPA 13E, and SOPs, as approved by MFRI

    and the qualified operator(s).

    The test protocol was as follows:

    1.  Start the DAQ system and allow for background data to be collected for a minimum of 1

    minute.

    2.  Start high definition video recording simultaneously with data collection.

    3.  Charge water to the FDC inlet(s) with low flow condition (no greater than 150 gpm) and

    ensure no or minimal leaks on the test assembly and proper discharge of water to the

    drafting basin.

    4.  Monitor the flow rate on DAQ system and gradually increase the flow to the target flow

    rates as outlined in the test matrix.

    5.  Record the pressure readings at the pumper for the upstream supply hose.

    6.  When the target flow rate is reached, allow a minimum of 2 minutes for steady state flow

    conditions to develop.

    7.  Repeat Steps 4 and 5 to collect data at the next target flow rate.

    8.  After the maximum flow is reached and the data collected, gradually decrease to a lower

    target flow rate and repeat the measurements.

    9.  Still photographs were recorded throughout the test as necessary.

    10. After the completion of all data collection for all target flow rates, stop the fire

    department pumper, and turn of all data collection equipment.

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    50/68

    January 8, 2016

    1505254.000 784935

    6 Test Results

    The following section is a presentation of the data collected during the flow tests along with a

     brief discussion of the data processing to determine the flow rate achieved during the test andultimately the pressure losses associated with the FDCs.

    The FDC flow testing was performed at the MFRI facility located at 4500 Paint Brach Parkway,

    College Park, Maryland 20742 on October 26, 2015. A total of eleven (11) tests were

    conducted; three (3) tests using three single FDCs (FDC-1 through FDC-3), four (4) tests using

    two siamese FDCs (FDC-4 and FDC-5), and four (4) tests using one triamese FDCs (FDC-6).

    Figure 21 through Figure 23 provide representative views of the flow testing for each FDC type.

    As shown in Figure 24, the differential pressures were measured using a digital manometer at

    the in-line pitot tube. Using Eq. (1) the differential pressures were then used to calculate the

    total discharge flow rates presented in Table 3.

    The pressure measurements in this test program included the total pressure measured

    downstream of the discharge pipe (,) and the normal pressure(s) measured upstream of the

    respective inlet pipe(s) (,,  ,and  ,). At their respective flow rates, the pressureswere recorded for a minimum of two minutes to ensure that steady state flow conditions were

    established. The average pressure data over the steady state period are reported in Table 3.

    Additionally, detailed pressure data recorded at the pumper for each test is provided in

    Appendix A, for reference. The pressure losses associated with the FDCs were determined

    directly based on the pressure measurement downstream of the hose lines, as discussed in this

    section, independently from the pumper pressure data.

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    51/68

    January 8, 2016

    1505254.000 784936

     

    Figure 21 Single FDC flow test

    Figure 22 Siamese FDC flow test

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    52/68

    January 8, 2016

    1505254.000 784937

     

    Figure 23 Triamese FDC flow test

    Figure 24 Measurement layout

    FromPumper  

    NTS

    FDCPU1, n

    In-line Pitot

    Manometer for FlowRate Measurement 

    PD, t

     

    PressureTransducer

    Discharge2.5” Hose Inlet pipe Discharge pipe 

    Discharge pipepressure loss

    ∆,) 

    Inlet pipepressure loss

    ∆,) 

    FDCPressure Loss

    (∆) 

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    53/68

    January 8, 2016

    1505254.000 784938

    Table 3 Test Measurement Results

    Test ID

    FDCType

    Flowto

    Inlet(s)

    Manometer[inch-H2O]

    TotalDischargeFlow [gpm]

     Average Pressure [psi]50

      FDCPressureLoss [psi]PD,t  PU1,n  PU2,n  PU3,n 

    FDC‐1‐1 

    Single  1 

    160  271  3.4  2.0  ‐ ‐ 0.2 

    551 

    503 

    12.2 

    7.6  ‐ ‐

    1.2 

    1047  693  23.6  14.0  ‐ ‐ 1.3 

    FDC‐2‐1 

    Single 1 

    172  281  3.7  2.0  ‐ ‐ 0.0 

    495  478  10.3  5.7  ‐ ‐ 0.6 

    503  481  11.0  6.1  ‐ ‐ 0.4 

    926  652  24.7  15.6  ‐ ‐ 0.6 

    FDC‐3‐1 

    Single 1 

    118  233  3.5  2.3  ‐ ‐ 0.0 

    551  503  11.4  6.6  ‐ ‐ 0.9 

    962  664  20.7  13.9  ‐ ‐ 3.3 

    1167  732  26.4  17.6  ‐ ‐ 3.5 

    FDC‐

    4‐

    Siamese 1

     

    53  448  1.2  1.1  ‐ ‐ 5.5 

    101 

    642 

    2.4 

    8.5  ‐ ‐

    14.6 

    109  618  2.7  5.8  ‐ ‐ 16.7 

    153  761  3.2  12.0  ‐ ‐ 24.9 

    FDC‐4‐2 

    Siamese 2 

    216  906  5.8  8.5  8.3  ‐ 8.1 

    304  1073  7.7  9.3  10.5  ‐ 9.2 

    401  1232  10.1  12.5  14.2  ‐ 12.5 

    478  1345  11.9  17.5  16.3  ‐ 17.5 

    588  1492  13.7  19.3  19.1  ‐ 20.3 

    FDC‐5‐1 

    Siamese 1 

    80  552  1.4  1.3  ‐ ‐ 8.3 

    129  700  3.1  6.5  ‐ ‐ 17.1 

    159  777  4.1  8.2  ‐ ‐ 20.9 

    FDC‐5‐2 

    Siamese 2 

    198  865  5.1  8.6  8.1*  ‐ 8.4 

    255  982  6.9  19.4  19.7*  ‐ 18.8 

    445  1298  10.5  22.2  23.8*  ‐ 22.8 

    551  1445  12.8  27.8  24.4*  ‐ 28.9 

    FDC‐6‐1A 

    Triamese 1 

    14  554  0.28  7.4  ‐ ‐ 15.8 

    15  566  0.35  11.4  ‐ ‐ 20.1 

    FDC‐6‐1B 

    Triamese 1 

    44  979  0.9  10.6  ‐ ‐ 36.9 

    46  1006  0.9  10.4  ‐ ‐ 38.3 

    53  1076  1.8  5.9  ‐ ‐ 36.9 

    FDC‐6‐2 

    Triamese 2 

    47  1012  1.1  2.3  0.2*  ‐ 8.4 

    63  1171  1.2  6.0  2.0*  ‐ 14.4 

    98  1467  1.8  10.4  10.4*  ‐ 23.7 

    135 

    1717 

    2.6 

    16.8 

    13.8*  ‐

    35.0 

    FDC‐6‐3 

    Triamese 3 

    92  1420  2.3  7.5  5.1  7.4*  11.5 

    98  1462  1.9  5.6  5.6  4.5*  10.4 

    139  1748  3.5  12.6  9.2  8.3*  18.6 

    141  1755  3.5  10.7  9.2  9.1*  16.7 

    151  1818  3.7  12.4  9.6  8.1*  18.9 

    50  Note (*) Supplemental technique is used to determine certain upstream pressure due to cavitation created by hose orientationsduring testing. 

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    54/68

    January 8, 2016

    1505254.000 784939

    The maximum flow for each test was based on the available flow capacity at the hydrant and

    additional safety considerations. For this test program, the maximum flows were measured at

    732 gpm for single FDCs. For the siamese and the triamese FDCs, the maximum flow rates

    achieved were 1,492 gpm and 1,818 gpm, respectively, when all inlets were simultaneously

    charged.

    As presented in Table 3, the normal pressure(s) measured upstream of the inlet pipe(s) (,, 

    ,, and  ,) for siamese and triamese FDCs are relatively similar at their respective flow

    rates, with a variation of up to ±3 psi. This observation is supportive of the fact that the inlet

    flows to the siamese and triamese FDCs are equally split. As such, only ,was used to

    further calculate the upstream normal pressure (,) based on Eq. (3) as follows:

    ,   ,  0.001123/  (4)

    where  is inlet flow (gpm), and  is inside diameter of the inlet pipe (in). In addition, the

     pressure loss associated with the FDC is given as:

    ∆   ,  ∆, ,  ∆,  (5)

    where ∆, and ∆, are the pressure losses associated with the inlet and outlet pipes

    respectively. The pressure loss attributed to the fully developed, steady state, incompressible

    flow through a pipe section is estimated based on the Darcy-Weisbach equation as follows:

    ∆  0.000216/, (6)

    where is friction loss factor as provided by a Moody diagram,  is length of pipe (ft),  is water

    density (lb/ft3), is flow in pipe (gpm), and  is inside diameter of pipe (in). Following Eq. (4),(5), and (6), the pressure losses that occur between the inlet and the outlet of the FDCs at a

    given flow rate are estimated and summarized in the last column of Table 3.

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    55/68

    January 8, 2016

    1505254.000 784940

    7 Analysis and Discussion

    The following section is a discussion of the data and observations collected during the flow tests

    and serves to supplement the presentation of the data in Section 6.

    7.1 Single FDC

    A total of three single FDCs (FDC-1, FDC-2, and FDC-3) were tested and their pressure losses

    as a function of flow rates are presented in Figure 25. The error bars represent a single standard

    deviation for the data collected during the steady state flow condition. Also included in Figure

    25 are solid lines representing a fitted trend line for the pressure losses as a function of flow rate

     based on the following expression:

    ∆   / , (7)

    where  is the average pressure loss coefficient for the FDC,  is the total discharge flow,

    and  is the inside diameter of the FDC discharge outlet.

    Figure 25 Single FDC pressure loss data

    0

    1

    2

    3

    4

    5

    6

    0 200 400 600 800

           P      r      e      s      s      u      r      e

     

           L      o      s      s        [      p      s        i        ]

    Flow Rate [gpm]

    FDC‐1‐1

    FDC‐2‐1

    FDC‐3‐1

    CFDC = 0.0041

    CFDC = 0.0032

    CFDC = 0.0014

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    56/68

    January 8, 2016

    1505254.000 784941

    Based on the test results, the maximum flow rate for the single FDCs during testing was

    approximately 730 gpm, 2.8 times the prescriptive requirement of 250 gpm per inlet provided in

     NFPA 14. In addition, it is possible that a higher flow rate could have been achieved during the

    single FDC testing given the capacity of the water supply and the pumper. However, a limit for

    flow of no greater than 750 gpm per inlet was selected due to a safety consideration based on a

    high velocity flow (approximately 49 ft/s).

    Based on the test results, FDC-2 produced the lowest pressure losses, while FDC-3 provided the

    greatest pressure loss among the three single FDCs. While slight differences in the pressure

    losses were observed among the three single FDCs, especially at a higher flow rates, the

    variation was small (within ±2 psi). The rubber gaskets used in each manufacturer’s FDC are

    slightly different in size and thickness, which could account for the variation observed at higher

    flow rates.

    For the range of the tested flow rates, the pressure losses associated with all tested single FDCs

    were generally small. While the error bars suggest a greater variability of the data taken at a

    higher flow rate, the maximum pressure loss is expected to be low even at values approximately

    three times that of the prescriptive flow rate.

    7.2 Siamese FDC

    Two siamese FDCs (FDC-4 and FDC-5) were tested, each with only one inlet charged and with

     both inlets simultaneously charged. The pressure losses are presented in Figure 26. The error

     bars represent a single standard deviation for the data collected during the steady state flow

    condition. Also included in Figure 26 are solid lines representing a fitted trend line for the

     pressure losses as a function of flow rate based on Eq. (7).

    The total flow rate data provided in Figure 26 is the total discharge flow rate measured within

    the discharge pipe. Based on the test results, the maximum flow that was achieved during

    testing was 777 gpm when only one inlet was charged with water and 1,492 gpm when both

    inlets were charged. Similar to the single FDC flow testing, the flow tests for the siamese FDCs

    were concluded at the selected maximum flows based on safety considerations.

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    57/68

    January 8, 2016

    1505254.000 784942

    As observed in this test program, the greatest pressure loss associated with the siamese FDC

    was approximately 25 psi when only one inlet was charged at 761 gpm and 29 psi when both

    inlets were charged with a total flow of 1,445 gpm. In general, at a respective total discharge

    flow rate, the pressure losses associated with the siamese FDC is optimized (i.e., minimized)

    when both inlets are charged.

    Figure 26 Siamese FDC pressure loss data

    Models of siamese FDCs with varying clapper designs were included in the testing. FDC-4 was

    a freestanding type (integral 90° orientation) FDC with a single inlet clapper and FDC-5 was a

    wall-mount type FDC with dual inlet clappers (see Figure 6 through Figure 9). When only one

    inlet was charged (FDC-4-1 and FDC-5-1 tests), both FDC-4 and FDC-5 produced similar

     pressure loss characteristics, with FDC-4 producing slightly higher pressure loss values at a

    given flow rate. When both inlets were simultaneously charged (FDC-4-2 and FDC-5-2 tests),FDC-4 hydraulically performed better, with lower pressure losses compared to FDC-5. Based

    on these test results, the presence of an internal clapper can influence the pressure loss

    characteristics of the FDC.51

      The results also indicated that when only one inlet was charged,

    there was no noticeable difference in the pressure losses experienced between FDCs with one or

    51 The orientation of the freestanding siamese FDC (FDC-4) during testing may have had some impact on clapper behavior, but such impact is expected to be minimal.

    0

    5

    10

    15

    20

    25

    30

    35

    40

    0 200 400 600 800 1000 1200 1400 1600

           P      r      e      s      s      u      r      e        L      o      s      s        [      p      s        i        ]

    Total Flow Rate [gpm]

    FDC‐4‐1

    FDC‐4‐2

    FDC‐5‐1

    FDC‐5‐2CFDC = 0.0341

    CFDC = 0.0397

    CFDC = 0.0095

    CFDC = 0.0154

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    58/68

    January 8, 2016

    1505254.000 784943

    two inlet clappers. The difference in pressure loss was noticeable in the two-clapper model

    when both inlets were charged, as both clappers likely interfered with the flow, creating higher

     pressure losses. None of the clappers in the FDCs tested utilized a spring-loaded closing

    mechanism.

    Further, the results also suggest that the difference in the geometry and shape of FDC-4 and

    FDC-5 (i.e., freestanding versus projecting) is less influential to the pressure loss performance

    than the presence of the clappers. The geometry of the freestanding model is expected to

    inherently contain a greater flow restriction compared to that of the projecting model (i.e., a

    convergence plus a sharp, 90° turn versus a convergence alone). However, the fact that the

    freestanding model with one clapper (FDC-4) showed better hydraulic performance than the

     projecting model with two clappers (FDC-5) indicates that the clappers have a greater impact to

    the pressure losses than the geometry of the FDC.52

     

    7.3 Triamese FDC

    One triamese FDC (FDC-6) equipped with non-spring-loaded inlet clappers was tested and the

     pressure loss data is presented in Figure 27 below, along with error bars for the standard

    deviation and the trend lines following Eq. (7). Four separate tests were performed on the

    triamese FDC, including two tests with only one inlet charged (FDC-6-1A and FDC-6-1B); one

    test with two inlets charged (FDC-6-2) and one test with all three inlets charged (FDC-6-3).

    52 This observation is specific to the FDCs tested and may not be universally applicable to all FDCs.

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    59/68

    January 8, 2016

    1505254.000 784944

     

    Figure 27 Triamese FDC pressure loss data

    Based on the test results, the maximum flow rate that was achieved was 1,076 gpm when only

    one inlet was charged (FDC-6-1B), with the corresponding pressure loss at approximately 40

     psi. A maximum flow rate of 1,717 gpm was achieved when two inlets were charged (FDC-6-

    2) with a corresponding pressure loss of 35 psi and a maximum flow rate of 1,818 gpm was

    achieved when all three inlets were charged (FDC-6-3) with a corresponding pressure loss of 19

     psi. For tests FDC-6-2 and FDC-6-3, the tests concluded with their maximum flow rate when

    the water supply reached its maximum capacity, i.e. when the hydrant residual pressure reduced

     below 20 psi.53  In general, at a respective total discharge flow rate, the pressure loss associated

    with the triamese FDC reduced with more inlets connected, similar to the observations made for

    the siamese FDCs.

    7.4 FDCs Pressure Loss Characteristics

    The pressure loss associated with water flow through FDCs can be expressed as a direct

    function of a squared flow rate, , a characteristic length (i.e., pipe diameter) to the fifth

     power, , and a pressure loss coefficient, , as previously shown in Eq. (7), which follows

    53 NFPA, Fire Protection Handbook, 20th Edition, Section 15, Chapter 2, p. 15-24.

    0

    5

    10

    15

    20

    25

    30

    35

    40

    0 200 400 600 800 1000 1200 1400 1600 1800 2000

           P      r      e      s      s      u      r      e

     

           L      o      s      s        [      p      s        i        ]

    Total Flow Rate [psi]

    FDC‐6‐1A

    FDC‐6‐1B

    FDC‐6‐2

    FDC‐6

    ‐3

    CFDC = 0.0815

    CFDC = 0.0456

    CFDC = 0.3496

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    60/68

    January 8, 2016

    1505254.000 784945

    the form of the Darcy-Weisbach equation. In general, the pressure loss coefficient is strongly

    dependent on the geometry of the component considered and the greater the coefficient, the

    greater the pressure loss.54  The FDC pressure loss coefficient, , based on the test results

    from this test program are as provided in Table 4.

    Table 4 FDC Pressure Loss Coefficients

    FDC ID Test ID Flow to InletsFDC Pressure Loss Coef.

    () FDC-1 FDC-1-1 1 0.00032

    FDC-2 FDC-2-1 1 0.00014

    FDC-3 FDC-3-1 1 0.00041

    FDC-4

    FDC-4-1

    FDC-4-2

    1

    2

    0.0396

    0.0095

    FDC-5FDC-5-1

    FDC-5-2

    1

    2

    0.0341

    0.0154

    FDC-6

    FDC-6-1 (A&B)

    FDC-6-2

    FDC-6-3

    1

    2

    3

    0.3496

    0.0815

    0.0456

    Given that the pressure losses obtained from this test program track reasonably well with the

     pressure loss expression in Eq. (7), using the FDC pressure loss coefficient, extrapolated data

     based on the pressure loss coefficients for all tested FDCs are presented in Figure 28.

    54 Munson et al, Fundamentals of Fluid Mechanics, 5th Edition, 2006, p.437

  • 8/16/2019 Rf Fire Department Connection in Let Flow Assessment

    61/68

    January 8, 2016

    1505254.000 784946

     

    Figure 28 FDC pressure loss characteristics

    The pressure losses across single FDCs are the lowest in comparison to that of siamese andtriamese FDCs. This observation is consistent with the geometry of the single FDCs that is

    typically smooth, clapper-less, and contains very little resistance in comparison to that of the

    siamese or the triamese FDCs, where inherent flow restrictions including turns, bends, and

    clappers are incorporated as part of their designs.

    Based on the pressure loss characteristics of the FDCs obtained in this study, when only one

    inlet is charged with a flow rate of 500 gpm, two times that of the current NFPA 14

    requirement, a resultant pressure loss of approximately 10 psi or less is expected. This level of

     pressure loss is equivalent to a pipe pressure loss created by flowing 500 gpm of water through

    an approximately 14-foot length of 2.5-inch schedule (SCH) 40 steel pipe.55

      In addition, when

    multiple inlets are charged with a flow rate of 500 gpm per inlet, substantial flow rates can be

    achieved for siamese and triamese FDCs, while the pressure loss across the FDC is only

    55 Based on the Darcy-Weisbach formula for friction loss

    0

    5

    10

    15

    20

    25

    30

    35

    40

    45

    0 200 400 600 800 1000 1200 1400 1600 1800 2000

           P      r      e      s      s      u      r      e

     

           L      o      s      s        [      p      s        i        ]

    Total Flow Rate [gpm]

    FDC-3-1

    CFDC = 0.0041

    FDC-1-1

    CFDC = 0.0032

    FDC-2-1

    CFDC = 0.0014

    FDC-6-3

    CFDC = 0.0456

    FDC-6-2

    CFDC = 0.0815

    FDC-6-1

    CFDC = 0.3496

    FDC-4-2

    CFDC = 0.0095

    FDC-4-1

    CFDC = 0.0397

    FDC-5-2

    CFDC = 0.0154

    FDC-5-1

    CFDC = 0.0341

    250 gpm

    NFPA 14 500 g