27
REVIEWER - BUILDING TECHNOLOGY 5 1. FLAT SLAB INTRODUCTION Common practice of design and construction is to support the slabs by beams and support the beams by columns. This may be called as BEAM- SLAB CONSTRUCTION. The beams reduce the available net clear ceiling height. Hence in warehouses, offices and public halls sometimes beams are avoided and slabs are directly supported by columns. This types of construction is aesthetically appealing also. These slabs which are directly supported by columns are called FLAT SLABS. FLAT SLAB - a reinforced concrete slab supported directly by concrete columns without the use of beams. Concrete, reinforcement, and formwork are the three primary expenses in cast-in-place concrete floor construction to consider throughout the design process, but especially during the initial planning stages. Of these three, formwork comprises about 50 to 60 percent of the total cost and has the greatest influence on the overall cost of the floor system. The cost of the concrete, including placing and finishing, typically accounts for about 25 to 30 percent of the overall cost. The reinforcing steel has the lowest influence on overall cost TYPES OF FLOOR SLAB SUPPORT o Flat slab o Flat slab with drop panels o Flat slab with column head o Flat slab with drop panel and column head Drops: is a local thickening of the slab in the region of the columns USES OF DROPS PANELS Increase shear strength of slab increase negative moment capacity of slab stiffen the slab and hence reduce deflection Column head: is the local enlargement of the column in the junction with the slab USES OF COLUMN HEADS Increase shear strength of slab reduce the moment in the slab by reducing the clear or effective span Flat

Reviewer (Building technology)

Embed Size (px)

DESCRIPTION

reviewer, for construction field.

Citation preview

Page 1: Reviewer (Building technology)

REVIEWER - BUILDING TECHNOLOGY 5

1. FLAT SLAB

INTRODUCTION

Common practice of design and construction is to support the slabs

by beams and support the beams by columns. This may be called as BEAM-

SLAB CONSTRUCTION.

The beams reduce the available net clear ceiling height. Hence in

warehouses, offices and public halls sometimes beams are avoided and slabs

are directly supported by columns. This types of construction is aesthetically

appealing also. These slabs which are directly supported by columns are called

FLAT SLABS.

FLAT SLAB - a reinforced concrete slab supported

directly by concrete columns without the use of

beams.

Concrete, reinforcement, and formwork

are the three primary expenses in cast-in-place

concrete floor construction to consider throughout

the design process, but especially during the initial

planning stages. Of these three, formwork comprises

about 50 to 60 percent of the total cost and has the

greatest influence on the overall cost of the floor

system.

The cost of the concrete, including placing and finishing, typically accounts for about 25 to 30 percent of the overall cost.

The reinforcing steel has the lowest influence on overall cost

TYPES OF FLOOR SLAB SUPPORT

o Flat slab o Flat slab with drop panels o Flat slab with column head o Flat slab with drop panel and column head

Drops: is a local thickening of the slab in the region of the

columns

USES OF DROPS PANELS

Increase shear strength of slab

increase negative moment capacity of slab

stiffen the slab and hence reduce deflection

Column head: is the local enlargement of the column in the

junction with the slab

USES OF COLUMN HEADS

Increase shear strength of slab

reduce the moment in the slab by reducing the clear or effective span Flat

Page 2: Reviewer (Building technology)

BENEFITS:

Flexibility in room layout

Saving in building height

Shorter construction time

Ease of installation of M&E services

Prefabricated welded mesh

Buildable score

FLEXIBILITY IN ROOM LAYOUT

Allows Architect to introduce partition walls

anywhere required

Allows owner to change the size of room layout

Allows choice of omitting false ceiling and finish

soffit of slab with skim coating

SAVING IN BUILDING HEIGHT

Lower storey height will reduce building weight

due to lower partitions and cladding to façade

Approx. saves 10% in vertical members

Reduce foundation load

2, FLAT PLATE FLOOR AND ROOF SLAB SYSTEM

A two-way slab of uniform thickness supported by any combination of columns and walls, with or without edge beams, and

without drop panels, column capitals, and brackets.

The simplest form of two-way slab—simplest for analysis, design, detailing, bar fabrication and placing, and formwork.

A two-way concrete slab supported directly on columns with reinforcement in two orthogonal directions.

One of the most common forms of construction of floors in

buildings.

USED IN:

It is commonly used in multi-story construction such as hotels, hospitals, offices, apartment buildings and roof parking.

COMPARED TO FLAT SLAB:

Compared to flat plate system the flat slab system is suitable for higher loads and longer spans.

The flat plate is a two-way reinforced concrete framing system utilizing a slab of uniform thickness, the simplest of structural shapes. The flat slab is a two-way reinforced structural system that includes either drop panels or column capitals at columns to resist heavier loads and thus permit longer spans.

ADVANTAGES

Simple formwork and suitable for direct fix or sprayed ceiling.

No beams- simplifying under floor services.

Minimum structural depth and reduced floor to floor height.

Easy to construct.

Page 3: Reviewer (Building technology)

DISADVANTAGES

Medium spans.

Limited lateral load capacity as part of a

moment frame.

May need shear heads or shear

reinforcement at the columns or larger

columns for shear.

Long-term deflection may be controlling

factor.

May not be suitable for

supporting brittle (masonry)

partitions.

May not be suitable for heavy

loads.

THICKNESS OF SLAB: Slabs generally

range from 5 to 14 inches in thickness.

Spans are up to 35 feet, but may be

extended by post - tensioning.

CONNECTION AND DETAILING

STEEL COLUMN

Main consideration is to

ensure that the base plate for

the steel columns is cast into the concrete flat plate.

Positioning and alignment of the base plates are of utmost importance.

CONCRETE COLUMN

Connection is more simplified without the

need for base plate connection.

Reinforcement bars should be properly

detailed between the columns and slabs.

A BUILDING USING FLAT PLATE CONSTRUCTION

Rigid insulation & ballast

Protected roof membrane

Elevator equipment

Cast-in-place concrete flat plate

Ducts & diffusers

Suspended acoustical tile ceiling

Window assembly

Power & communication poles

Carpeting

Concrete columns

Precast concrete spandrel panels

Bolt insulation

Metal stud & dry wall assembly

Slab on grade & concrete pile foundation

Page 4: Reviewer (Building technology)

Vapor barrier

3. WAFFLE SLAB

A WAFFLE SLAB is a two-way concrete slab reinforced by ribs in two

directions.

In this type of slab intermediate beams are cast on a regular square grid

that gives the underside of the floor appearance of waffle, hence it is

named as WAFFLE SLAB.

WAFFLE SLAB construction is used for ceilings and floor constructions.

Dead weight of the slab is reduced as compared to flat slab of similar

span, as the intermediate beams of waffle supports the thin slab above

it.

Able to carry heavier loads and span longer distance than flat slabs as these systems are light in weight.

Suitable for spans of 7m – 15m; longer spans may be

possible with posttensioning.

Flexible

Relatively light, therefore less foundation costs and longer

spans are economic

Speed of construction

Excellent vibration control

The pockets both support the structure and help insulate

the floor above by trapping hot air inside the pockets

Durable finishes

Fire resistance

Higher formwork costs than for standard moulds and other

slab systems.

Slightly deeper members result in greater floor heights.

Slow. Difficult to prefabricate reinforcement span.

They are a tasty way to build thin and strong concrete slabs that

use a lot less material. They are more expensive to form than

conventional flat slabs, but because of their depth, architects can

design longer spans.

Waffle slabs are assumed to have band beams along all four

edges. Width of the band beams is taken as 1000 mm extending 500

mm from the center of the columns on both sides and depth as

equal to total thickness of floor.

The top of a waffle slab is generally smooth, like a traditional

building surface, but the underside has a shape reminiscent of a

waffle. Straight lines run the entire width and

length of the slab, generally raised several

inches from the surface.

WAFFLE SLABS have a thin topping slab

and narrow ribs spanning in both directions

between column heads or band beams. The

column heads or band beams are the same

depth as the ribs.

Page 5: Reviewer (Building technology)

The most common material for a waffle slab is concrete.

Waffle slabs use less concrete, however if well engineered, they can be stronger than a solid slab.

4. SLIPFORM METHOD

Slipform is a method of continuously pouring concrete into the form or mold or steel shuttering panels that envelop the

structure along its designed shape and are then moved upwards continuously, leaving below the structure in its final form

with the assistance of hydraulic jacks. And the formwork is raised vertically by hydraulic jacks in a continuous process.

It is a construction method in which concrete is poured into a

continuously moving form.

A form of construction that can be used to build concrete, reinforced

concrete or pre-stressed concrete structures.

Slip forming is used for tall structures:

a. Towers b. Chimney

c. Silos d. Bridges

e. Dams f. Oil Tanks

g. Medium to High-rise Housing h. Hospital and Hotels as well as

horizontal structures, such as ROADWAYS.

SLIPFORM PROCESS

The slipform system is a hydraulically operated formwork system. 3 tonne hydraulic jacks are mounted on strategically

located steel yoking frames to lift the formwork as the concrete is poured into the forms.

The formwork system uses 1066mm high steel panels held rigidly by a framework built up from steel waler frames, trusses

and bracing. The framework provides rigidity to the slipform as well as support for timber decking to form a working platform for

placement of concrete, reinforcement steel and blockouts for doors and windows.

Concrete is poured into the forms in layers of approximately 200mm. The setting rates of concrete are constantly

monitored to ensure that it is matched with the speed at which the forms are raised. The jacks lift the form approximately 25mm per

stroke generally producing a slipforming rate of 300mm per hour.

Slipforming can be performed on either a continuous basis (i.e. 24 hours per day), or a discontinuous basis (i.e. pouring to a

predetermined height usually within one working day).

As the formwork is raised, reinforcement is held in the correct position using guides fixed to the top of the yokes. Horizontal

reinforcement is threaded under the yokes and tied to the vertical reinforcement.

Blockouts for doors and windows can be formed with either timber or steel. These are installed as the slipform proceeds

and can be stripped from the trailing decks. Similarly with rebates that are used to provide connections between beams, slabs and

the slipform walls.

When the formed concrete is exposed from the bottom of the steel form panels it can be sponged or treated if required.

Structural Systems experienced engineering and operational personnel ensure the smooth operation of the slipforming

process and control of verticality. Structural Systems technical staff is always available to advise on all aspects of slip forming

including coordination of various trades to optimize resources.

Page 6: Reviewer (Building technology)

THE SLIPFORM TYPICALLY COMPRISES THREE LEVELS OF WORKING:

1. UPPER REINFORCEMENT DECK - acts as a storage and distribution area.

2. WORKING DECK - the main working platform is at the top of the poured concrete level.

3. LOWER RUBBING UP DECK - provides access for concrete finishing.

EQUIPMENTS REQUIRED FOR SLIPFORM WORK:

1. CENTER POINT 8. STARTER / KICKER

2. FORM 9. YOKES

3. NORMAL BRACKETS 10. CENTRAL CONTROL SYSTEM

4. JACK 11. JACK HOLDER

5. YOKE LEG CLAMP 12. PANEL CLAMP

6. WALER CLEAT PLATES 13. WORKING PLATFORM

7. HANGING SCAFFOLDS 14. PUMP

ADVANTAGES:

Off-site assembly

Greater speed and earlier completion of construction projects

Early completion of lift motor rooms and early installation of lifts, plumbing and electrical services

Reduced craneage as forms are lifted by hydraulic jacks

Reduced scaffolding and temporary work platforms as the slipform system contains its own platforms for working. This also

results in a cleaner and less congested constructed site

A uniformity of wall sections and layouts can be achieved with the slipform method this is not achievable with conventional

formwork systems

Reduced labor costs, as the system provides an intensive work environment

Page 7: Reviewer (Building technology)

DISADVANTAGES

Non-stop work

Fixing door and window frames

High initial expense

Large quantities of equipment

Need 24-hour service facilities

Communication must be coordinated between ground level, crane drivers, slip form, and hoist operators

VERTICAL SLIP FORMING

The concrete form may be surrounded by a platform on which workers stand, placing steel reinforcing rods into the

concrete and ensuring a smooth pour. Together, the concrete form and working platform are raised by means of hydraulic jacks.

Generally, the slipform rises at a rate which permits the concrete to harden by the time it emerges from the bottom of the form.

TAPERED SLIPFORMING

Structural Systems is also heavily involved in the construction of conical chimneys, cooling towers, piers and

other tall concrete structures involving constant or changing thicknesses in walls, diameters and/or shapes. Structural

Systems has been involved in the construction of tapered towers and chimneys from 50m to 275m high with diameters

and wall thicknesses changing from 25m to 6m and 700mm to 250mm respectively.

While the slipforming process is similar to that used on the standard slipform equipment the logistics and

planning require greater attention the heights which often make the use of cranes impractical. Structural Systems

experience and expertise ensures the success of such projects.

Page 8: Reviewer (Building technology)

TYPICAL SECTION THROUGH SLIPFORM SYSTEM FOR TAPERED STRUCTURES

HORIZONTAL SLIPFORMING

For pavement and traffic separation walls concrete is

laid down, vibrated, work and settled in place while the form

itself slowly moves ahead.

5. SPAN TRUSS SYSTEM

A. ROOF

What is SPAN TRUSS SYSTEM? • Span truss systems are structural systems,

usually a beam used to support a load, a roof for instance or cover a very wide area in straight and very long distances.

• Structural material is a FACTOR. • TIMBER and STEEL are mostly used as

construction material.

PRINCIPLES OF SPAN TRUSS

• Steel trusses are being used for both buildings and bridges. But the design principles are different for different uses.

• Steel roof trusses are used for mainly for the Industrial buildings where free space requirement are essential for more working areas.

• The span of truss varies from 10 ft (3m) to 300 ft (91m) depending on the type of requirement and the available spaces.

Page 9: Reviewer (Building technology)

SPAN TRUSS CONSTRUCTION

For span up to about 20m, the spacing of steel trusses is likely to be about 4m. i.e. 1/5 of span.

For economic spacing of roof trusses, the cost of truss should be equal to twice the cost of purlins + the cost of roof

covering.

As a guide the spacing of the roof trusses can be kept: a. ¼ of span up to 15.0m.

b. 1/5 of span up to 15m to 30m.

A slope of 22 degrees is common for corrugated steel and asbestos roofing sheets.

CONFIGURATIONS:

The pitch of roof truss depends on the roofing materials.

a) Min. recommended for GI sheet—1in 6.

i.e h/l=1/6 h=l/6

b) For A.C sheet -1 in 12

i.e h=l/12.

A rough estimate of section height for a gabled truss is that for roof slope 1:16, H=L/25 to L/30.

For slope 1:10, H=L/35 to L/40 where H is the depth at support.

For parallel trusses the relation is approximately H=L/20.

The most advantageous angle between the diagonals and the bottom chord is 45°-50° in a triangular lattice and 35° -45°in a diagonal one.

WHERE IS IT USE? • Single-storey industrial buildings • Arenas • Theaters • Exhibition Halls • Stadiums • Airplane Hangars • many more

LONG SPAN TRUSSES

Long span trusses are any span in excess of or longer than 60 feet or 18 meters. So how does the structural material matter? According to the AIA Long-Span Building Panel, 60 ft (18.288m) for an office is considered long span but 60 ft for a gymnasium is not because 60 ft may be long span for a sawn timber beam, but a short span for a steel beam. The basic qualities of materials used are the answer. e.g. Steel; stronger, easy application, widely used.

Page 10: Reviewer (Building technology)

ARRANGEMENT

Two types of general arrangement of the structure of a typical single-storey

building are shown in Figure 1.2 and in Figure 1.3.

PORTAL FRAME ARRANGEMENT

In the first case (Figure 1.2), the lateral stability of the structure is

provided by a series of portal trusses

The connections between the truss and the columns provide resistance to a

global bending moment.

Loads are applied to the portal structure by purlins and side rails.

BEAM AND COLUMN ARRANGEMENT

The roof structure is arranged with main trusses spanning from

column to column, and secondary trusses spanning from main truss to main

truss.

ROOF SPAN TABLE:

Page 11: Reviewer (Building technology)

TYPES OF ROOF SPAN

Page 12: Reviewer (Building technology)

B. FLOOR

TRUSS – is essentially a triangulated system of straight interconnected structural elements.

CONFIGURATION OF TRUSSES

Page 13: Reviewer (Building technology)

PARALLEL CHORD TRUSSES – Parallel chord trusses are also used as pre-fabricated floor joists, beams and girders in

multi-storey buildings.

Modified Warren is used with additional verticals

introduced in oredr to reduce the unsupported length of

compression chord members.

FLOOR TRUSS, also referred to as OPEN WEB

STEEL JOIST is a lightweight truss cocnsisting of parallel

chords and a triangulated web system.

Steel joist are fastened to its supporting members

usually by field welding.

SPACING OF TRUSS IS DETERMINED BY:

Magnitude of floor load

Spanning capability of deck

Load carrying capacity of truss/joist

Floor construction depth desired

Unlike structural steel beams, steel joists must use

BRIDGING placed perpendicular to the span to attain its

stability.

2 TYPES OF BRIDGING

a. HORIZONTAL BRIDGING

b. DIAGONAL BRIDGING

JOIST GIRDERS – Are designed to carry the end reactions from equally-spaced joists applied to the panel points.

ADVANTAGES:

Longer clear spans in most cases,

elimination of beams.

Floor uniformity

Greater nailing area for sub-flooring.

Elimination of unsightly electrical wires,

plumbing and heating eyesores.

Size of room not limited by joist span table.

Speed of installation. Accurate costing

DISADVANTAGES:

Increased fabrication cost

6. LIFT-SLAB CONSTRUCTION

History:

Early 1950’s

Philip N. Youtz

Thomas B. Slick

A product of two Conceived Ideas

Page 14: Reviewer (Building technology)

“YOUTZ-SLICK METHOD”

GENERAL DESCRIPTION:

Fast Method of Building Construction Cast in place multi-leveling system

Minimal use of Cranes and hoists

Concrete floors and roof slabs are cast atop one another.

Prepared to the Previous ground floor

Cast Around The Columns

No beams / Drop panels / Column capitals

Post-tensioned Slabs

Increased Column Spacing and Reduced Slab Thickness

Casted Concrete members are literally “LIFTED” into their

final positions.

Each tiers are Simultaneously lifted.

Hydraulic Machine Lifters(Hydraulic Jacks)

- Temporarily mounted on the top of the Column.

Slabs are connected by Lift Rods to steel

Lifting Collars.

Lift Rods & Lifting Collars are Cast in and

anchored to the slabs and surrounding

columns.

Columns:-Steel and Concrete

Widely used for : Office, Institutional,

apartment and Hotel Buildings

Not too heavy load

Not too long/wide span (Modular)

METHOD OF CONSTRUCTION: Foundation -Backfilled

Slab on Grade

Prepared Ground Floor -provided Basement/s

All slabs are casted on site. -by Mould or formworks

Tiered/Filed Stacks of Concrete Floor and Roof Slabs -post-tensioned (preferable)

Holes/Openings on the Slabs -for Steel/Concrete Columns

Erected and plumbed

Lifting Collar is attached –Slab and Column

Provides a Hook to the Lifting Rod at each collar

Permanent/Temporary

All Lifting Collars (slabs) are lifted. - after the 1st tier was erected (columns)

Suspended to the ground (temporarily)

SEQUENCE OF LIFTING OPERATION: (2 METHODS) FIRST METHOD:

Column extends to its final height Cast all Roof & Floor Slabs Half of the Slabs are lifted (temporarily) Roof Slab remains and gain its permanent position Other Half (except basement slab) are lifted

SECOND METHOD: Higher structure require more stages Cast all Roof & Floor Slabs Slabs are lifted simultaneously up to the(Mid-

count)

Page 15: Reviewer (Building technology)

Roof Slab gains first its permanent position Follow through consecutively

CONSIDERATIONS Types of Column:

Steel Varies in external lateral dimensions 8 to 12 inch (for a given building) Columns dimensions remains constant Steel areas vary by specifying each columns of

different Flange Web thickness

Concrete: pre-cast reinforced concrete longitudinal and lateral reinforcing bars pre-stressed columns

Longitudinal wire tendons Mild steel lateral reinforcement COLUMNS ARE RIGIDLY ANCHORED - to their foundation by built up on bases to stand vertically In fire-resistive construction steel columns are protected by

concrete

metal lath

pearl plaster

A hollow steel column with concrete improves their fire resistance.

SIZE OF SLAB:

Overhead operated Hydraulic Jacks should act in unison to avoid local overstressing.

Min. number of Jacks operated 12 to 18

in considering the number of equipment the number can increase up to 36 jacks

COLUMN SPACING & SLAB THICKNESS

Vary from 25-30ft or more and may differ in two directions

Slabs are usually solid vary from 5-10inchs thick (for longer span waffle slabs are used)

The slabs are reinforced with wire mesh PRE-STRESSING

Slabs are usually pre-stress by post tensioning in both directions, usually the tendons are inclined from the lower center portion of the slab to the upper portion.

LIFTING COLLARS

Before each column is erected, the lifting collar required for each slab is placed on the column with approximately ¼ in clearance between them.

SLAB CASTING

Sequential as they occupy the building ground up (securely anchored to the lifting collars) CONNECTING SLABS TO COLUMN

After lifting collars are welded to steel columns.

ADVANTAGES The use of cranes and hoists when erecting the building is minimal, since construction materials are placed on the roof slab

and lifted along with them.

The use of formwork for the concrete slabs is minimal; only the sides need to formed, and there is no need to shore the formwork. Concrete floor construction at ground level is convenient and requires no shores, scaffolds or c ranes.

Page 16: Reviewer (Building technology)

There is little need for finishing of the bottom of lift slabs, since they will be as smooth as the floor finish of the sab below; thus the bottom of the slab can be used directly as a ceiling.

Lift slab can be used for heights up to about 16 stories.

Economical column spacing ranges from 22 to 32 feet. Columns may be pipe, tubes or wide flange sections; concrete columns may be used in 3- to 4-story buildings not requiring splices.

Because lift slab uses concrete, the technique offers good fire resistance and good acoustic ratings.

Originally, lift-slabs were reinforced with mild steel reinforcing, which limited column spacing or required very thick slabs. With the advent of post-tensioning however, column spacing was increased and the thicknesses of the slabs were reduced. Contemporarily, all lift-slabs are post-tensioned.

Locations of partitions are unaffected by beams because they are eliminated as in conventional flat-plate construction.

If pre-stressed, deflections are minimal, and the slabs are crack-free.

Less manpower.

DISADVANTAGES

The lift-slab method does have limitations, the principal one being that buildings must be specifically planned for the lift-slab method, or it will not have any economic advantages over conventional construction.

Failures and Deficiencies

JACK SYSTEMS WITH INADEQUATE TAKE-UP DEVICES

As the slab fell the bottom latch at each rod would theoretically close on a groove passed by the latch, arresting the fall of the slab. If the slab fell suddenly the full 6 inch stroke, there could be a catastrophic impact load on the latches if the lathes could act quickly enough, or a relatively unimpeded fall of the slab, if the latches could not act quickly enough.

UNEQUAL LIFTING

Distortion, unleveled slabs and cracking may happen on the floor slabs.

7. RIBBED FLOOR SLAB

Ribbed slabs are made up of wide band beams running between columns with equal depth narrow ribs spanning the orthogonal direction. A thick top slab completes the system.

Hollow blocks made of lightweight concrete or other materials are arranged between the ribs or the voids between ribs are left out without any filling material. The use of these blocks makes it possible to have the following:

• Smooth ceiling • Hygienic consideration • Insulation (sound and temperature)

ADVANTAGES:

• Longer spans with heavy loads (12-15m) • Reduction in dead loads due to voids • Electrical and mechanical installations can be placed

between voids • Good resistance to vibrations and increase the

tension resistance of the concrete

DISADVANTAGES • Higher formwork costs than for other slab

systems • Slightly greater floor thicknesses

THERE ARE TWO MAIN TYPES OF RIBBED FLOORS: 1. Hollow block floors

Hollow blocks are used to fill portions of the slab thickness; this results in deeper arm for the reinforcement while saving the amount of concrete and hence the own weight of the slab.

The reinforcement is located between the

Page 17: Reviewer (Building technology)

blocks inside the ribs.

Blocks may be concrete blocks or styro-foam

Most suitable for small irregularly shaped floors 2. Moulded Floors

For large symmetrically supported floors, the moulded type of floor

is most suitable and economical. Steel or fibreglass moulds can be

used for temporary formwork.

KEY COMPONENTS OF RIBBED FLOOR SLAB

A, TOPPING SLAB:

Topping slab thickness is not to be less than 1/12 the clear distance

between ribs, nor less than 5.0 cm. The topping slab is designed as a

continuous beam supported by the ribs.

Shrinkage reinforcement is provided in the topping slab in both

directions in a mesh form.

B. RIBS Minimum dimensions:

Ribs are not to be less than 10 cm in width, and a depth of not more than 3.5 times the minimum web width. Clear spacing between ribs is not to exceed 75.0 cm as specified.

C. LOADS:

The load on ribs consists of dead and live loads. The dead load includes own weight of the slab, weight of the surface finish, and equivalent partition load. The live load is dependent on the intended use of the building. DIRECTION:

In ONE-WAY RIBBED SLABS ribs may be arranged in any of the two principal

directions. Two options are possible; the first is by providing ribs in the shorter direction, which leads to smaller amounts of reinforcement in the ribs, while large amounts of reinforcement are required in the supporting beams, associated with large deflections.

The second option is by providing ribs in the longer direction, which leads to

larger amount of reinforcement in the ribs, while smaller amounts of reinforcement are required in the supporting beams associated with smaller deflections compared to the first option.

Page 18: Reviewer (Building technology)

8. Wall Panel System: RIBBED WALL Definition of Rib

Something resembling a rib in form, position, or use, as a supporting or strengthening part.

Surface of a vault accenting the ridges or dividing the surface into panels. Definition of Wall Rib Panel

Panel Rib is our most economical wall system. In fact, this wall system is more economical than wood, concrete or masonry alternatives.

Page 19: Reviewer (Building technology)

BENEFITS

Variety of gauge thicknesses to meet most codes and specifications

Engineered for durability and aesthetically pleasing

Long panel lengths minimize end laps for optimum wall integrity

Superior paint finishes reduces maintenance costs

Recessed fastener locations give the panel a semi-concealed profile with bold architectural lines

Embossed surface provides attractive architectural finish STANDARD WALL RIB PANEL The panels are attached with self-drilling, color-matched fasteners

• Available in 26, 24 or 22 gauge • 36” wide panel with 1-1/4” high ribs 12” on center • Available up to 41’ in length • Installed with self-drilling color- matched fasteners

OTHER TYPES OF WALL RIB PANEL A. VEE RIB WALL PANEL

The Vee Rib wall panel features a V-groove pattern, semi-concealed fasteners located in the bottom of the groove, and 1-1/4" reveals. Its surface, embossed for esthetic appeal, reduces glare. Self-drilling fasteners and 36" panel width provide for economical installation.

Available in 26, 24 or 22 gauge

36 “ wide panel with 1-1/4” recessed ribs 12” on center

Available up to 39’ in length

Installed with self-drilling color-matched fasteners

Fasteners installed in V-groove

Embossed exterior surface B. REVERSE-ROLLED VERSION OF PANEL RIB

Panel is an attractive, high quality, low maintenance panel based on a “reverse rolled” RPR Panel is a reverse-rolled version of our popular Panel Rib profile. This economical wall system features self-drilling, color-matched fasteners and a 36" panel width to provide fast and easy installation.

Reverse rolled version of VP’s Panel Rib design

Available in 26, 24 or 22 gauge

36” wide panel with 1-1/4” deep ribs 12” OC

Available up to 41’ in length

Installed with self-drilling color-matched fasteners

Fasteners installed in recessed rib TECH FOUR WALL PANEL

A unique architectural wall system that is easy to install featuring concealed fasteners and an attractive, embossed finish. These durable panels easily adapt to a variety of insulation options (including batt, blanket or rigid board). Tech Four offers 16” coverage with 1/4” high, 4” wide alternating fluted profile. Available in lengths of up to 40’, Tech Four can provide continuous coverage from foundation to eave — eliminating the need for end laps and assuring superior weather tightness. Manufactured in sturdy 24 gauge steel for added strength and erectability. MEGA RIB

Mega-Rib is a 7.2 rib spacing that provides optimum strength and spanning capabilities. Mega-Rib is a metal roof and wall panel that is equally well suited for industrial and commercial applications. Imperial RIB

Panel Type - Exposed Fastener Metal Panel

Page 20: Reviewer (Building technology)

TONGUE AND GROOVE CONNECTION

EXAMPLES OF FLAT TYPE WALL PANEL USING TOUNGE AND GROOVE CONNECTION

Panel Width Coverage - 36" Rib Height - 3/4“

Gauges - 29 and 26 gauge

Metal Panel Substrate – Galvalume

Paint Finish Type - Siliconized Polyester

Kinds of Flat Type Wall Panel System

GLASS WALL PANEL

Glass wall panel on concrete – glass panels are inserted between a concrete slabs to for a wall panel.

WOOD WALL PANEL

Tongue and Groove – flat wood panels are interconnected using the tongue and groove connection.

WOOD GLASS METAL/STEEL MASONRY

Page 21: Reviewer (Building technology)

FLAT TYPE WALL PANEL USING HIDDEN DIVIDERS CONNECTION

FLAT TYPE WALL PANEL USING ½ MOULDING CONNECTION

FLAT TYPE WALL PANEL USING ¼ MOULDING CONNECTIONS

Hidden divider – metal connections are used to combined two wood wall panels

Moulding connection – wood panels are connected using plastic moulding with optional insert for electrical

wirings (used for insulation)

REVEALED DIVIDER – unlike the hidden divider connection, the revealed divider are can be seen for aesthetics

purposes (with optional insert for electrical wirings for insulation purposes).

DIVIDERS THAT ACT AS CONNECTOR TO THE WOOD PANEL

½ MOULDING REVEALS

WITH OPTIONAL INSERT

¼ MOULDING REVEALS

WITH OPTIONAL INSERT

Page 22: Reviewer (Building technology)

CURVED WOOD PANEL (FOR POST/COLUMN PURPOSES) WOOD PANEL WITH DESIGN

OTHER EXAMPLES OF FLAT WOOD PANEL:

INSTALLATION: WOOD PANELS

THINGS TO REMEMBER:

INSTALLING ON A FRAMED WALL & ON SOLID BACKING Check the studs to be sure they are vertical and on 16" or 24" spacing. Also make sure that backing is provided at all corners, at the top and bottom of the wall and around any openings. Outside walls should have a vapor barrier over the faces of the studs.

1” DIVIDER MOULDING

WITH VELO ANODIZED

MOLDING

Page 23: Reviewer (Building technology)

INSTALLING ON A MASONRY WALL First check the masonry walls for excessive moisture. Walls with moisture must be completely waterproofed

before they are paneled. Moisture can sometimes be caused by condensation. If this is the case, add a waterproof vapor barrier over the wall (below grade, do this before furring it).

BEFORE PANEL INSTALLATION:

• Install 1" x 2" or 1/2" plywood furring strips–ripped 11" wide–horizontally or vertically, placing them on 16" centers. They are best when fastened with masonry anchors drilled into the wall. Furring strips also can easily be glued on. It can also be used to make imperfectly framed walls even and flat.

• Inspect your furring strips as you put them up to make sure they are creating an even, flat surface. Make any necessary adjustments by shimming behind the uneven strips with pieces of plywood or tapered wood shingles. Nail the shingles with brads to keep them in position.

• Get the first corner panels exactly plumb, using a level or chalked plumb line snapped onto the wall. Its outer edge must be centered on a framing member. The edge against the corner may have to be trimmed to bring the outer edge over a stud or furring strip. Double-check all your measurements before sawing the panel. Cut with a fine-tooth saw–never use one with coarse teeth.

• When the first panel is readied, nail (or glue and nail) it to the wall. Move on with

additional panels, avoiding a fit that's too tight between the panels. Leave the thickness of a dime between panels to avoid expansion problems.

• The gaps will not show greatly if the area between panels is pre-colored with a marking

pen or a stripe of paint the same color as the grooves. PANELLING WITH NAILS:

• Cover your hammer head with a rag to protect the face of your panels when nailing. Place nails every 4 to 6 inches along the panel edges and every 8 to 12 inches throughout the rest of the panel on studs. Always begin nailing at one edge and move across the panel to the other edge. Never nail opposite edges first, then the middle of a panel.

• Place the panel in position on the adhesive and drive several nails loosely across the top to hinge it in the proper position.

• Now press the panel firmly against the adhesive and tap all over it with a hammer and cloth-padded wood block or rubber mallet.

• Heavy panels need additional support, with nails 16 to 20 inches apart.

MASONRY WALL PANEL What is a Sandwich Panel? Insulated wall panels are also referred to as sandwich panels. An inner core of insulation is surrounded or sandwiched between two precast concrete layers or wythes.

Page 24: Reviewer (Building technology)

What is a Wythe? A wythe is a layer within, or on the surface of a sandwich panel or insulated wall panel.

What is a Wythe Tie? A Wythe Tie is the name of the material that connects two or more layers of concrete (wythes) together in an insulated wall panel. EXAMPLE OF MASONRY SANDWICH WALL PANEL: Styromesh Wall Panel is an alternative building system that can be used in place of wood or metal-framed walls, hollow block walls or pre-cast panels.

Styromesh panel used a dowel to connect the styromesh on the foundation and tie wired it to make it stable and

ready for plastering.

METAL WALL PANEL

Metal Wall Panel is used to surface the exterior of a building to

protect against exposure to the elements, prevent heat loss, and

visually unify the face of the building.

CONCRETE PLASTER

STYROMESH SANDWICH PANEL WITH

REINFORCING STEEL WIRES

Page 25: Reviewer (Building technology)

FLAT PLATE

Definition:

- A two-way slab of uniform thickness supported by any combination of columns and walls, with or without edge

beams, and without drop panels, column capitals, and brackets.

- The simplest form of two-way slab—simplest for analysis, design, detailing, bar fabrication and placing, and

formwork.

- A two-way concrete slab supported directly on columns with reinforcement in two orthogonal directions. One of the

most common forms of construction of floors in buildings.

Used in:

- It is commonly used in multi-story construction such as hotels, hospitals, offices, apartment buildings and roof

parking.

7/8’’ 16 gauge hat chanel 16” – 24” spacing

Metal wall panel

moulding

Page 26: Reviewer (Building technology)

Compared to flat slab:

- Compared to flat plate system the flat slab system is suitable for higher loads and longer spans.

- The flat plate is a two-way reinforced concrete framing system utilizing a slab of uniform thickness, the simplest of

structural shapes. The flat slab is a two-way reinforced structural system that includes either drop panels or column

capitals at columns to resist heavier loads and thus permit longer spans.

Advantages:

- Simple formwork and suitable for direct fix or sprayed ceiling.

- No beams- simplifying under floor services.

- Minimum structural depth and reduced floor to floor height.

- Easy to construct.

Disadvantages:

- Medium spans.

- Limited lateral load capacity as part of a moment frame.

- May need shear heads or shear reinforcement at the columns or larger columns for shear.

- Long-term deflection may be controlling factor.

- May not be suitable for supporting brittle (masonry) partitions.

- May not be suitable for heavy loads.

Thickness of slab:

Slabs generally range from 5 to 14 inches in thickness. Spans are up to 35 feet, but may be extended by post -

tensioning.

Connection and detailing:

a. Steel column

- Main consideration is to ensure that the base plate for the steel columns is cast into the concrete flat plate.

- Positioning and alignment of the base plates are of utmost importance.

b. Concrete column

- Connection is more simplified without the need for base plate connection.

- Reinforcement bars should be properly detailed between the columns and slabs.

Page 27: Reviewer (Building technology)

Sources:

Flat plate flooring system

Guide to long-span concrete floors

Concrete roof systems

Analysis and design of flat plate

Design concept for flat plate system