Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
United States Nuclear Regulatory Commission Official Hearing Exhibit
In the Matter of: Entergy Nuclear Operations, Inc. (Indian Point Nuclear Generating Units 2 and 3)
ASLBP #: 07-858-03-LR-BD01 Docket #: 05000247 | 05000286 Exhibit #: Identified: Admitted: Withdrawn: Rejected: Stricken:
Other:
NYS000242-00-BD01 10/15/201210/15/2012
NYS000242 Submitted: December 21, 2011
REVIEW OF INDIAN POINT SEVERE ACCIDENT OFF SITE CONSEQUENCE ANALYSIS
ISR Report 13014-01-01
21 December 2011
presented to
Office of the Attorney General - State of New York 120 Broadway, New York, NY 10271-0332
prepared by
11111 INTERNATIONAL SAFETY RESEARCH
The production of this report has followed the standard review and quality control procedures of International Safety Research.
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page ii
38 Colonnade Road N., Ottawa, Ontario K2E 7J6 Tel: +1 613 241-4884 Fax: +1 613 241-1250
E-mail: [email protected] www.i-s-r.ca
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page iii
EXECUTIVE SUMMARY With the operating licenses of Indian Point Unit 2 (IP2) and Unit 3 (IP3) scheduled to expire in 2013 and 2015 respectively, the facilities' owner, Entergy, submitted a license renewal application (LRA) to the Nuclear Regulatory Commission (NRC) seeking to extend its operating licenses for another twenty years. NRC regulations require a site-specific analysis of actions to mitigate the environmental impacts resulting from a severe accident at the applicant’s plant. As part of the LRA, Entergy was required to submit an Environmental Report (ER) that included a Severe Accident Mitigation Alternatives (SAMA) analysis. As part of the relicensing proceeding, NRC Staff completed a Final Supplemental Environmental Impact Statement (FSEIS) which evaluates, among other things, Entergy’s SAMA analysis. The State of New York has intervened in the relicensing proceeding and has challenged, among other things, Entergy's and NRC Staff's SAMA analysis. Central to the SAMA analysis is a cost-benefit analysis. The MELCOR Accident Consequence Code Systems-2 (MACCS2) code is used to estimate economic costs associated with a severe nuclear accident using site-specific inputs entered by the user. This cost is then used in the SAMA analysis to determine which SAMAs are cost-beneficial. The NRC approved and released the FSEIS for IP in December 2010. Upon review of the FSEIS, specifically Appendix G, the New York State Office of the Attorney General (OAG) submitted Contention 12-C which asserts that NRC staff and Entergy have substantially underestimated the costs of decontamination measures required following a severe nuclear accident.1 This underestimation is attributed primarily to the selection of inappropriate MACCS2 decontamination input parameters for the area surrounding the Indian Point station (i.e., New York City (NYC) and surrounding metropolitan areas). Consequently, OAG requested that International Safety Research (ISR) in Ottawa, Canada:
1. examine Entergy’s use of the MACCS2 code, including Entergy’s input file for the long-term phase of a severe nuclear accident (i.e., CHRONC);
2. determine whether and to what extent the economic costs of a severe accident at Indian Point were underestimated due to, for example, the use of generic assumptions concerning decontamination costs that are not necessarily applicable to the densely populated area surrounding IP2 and IP3 found in the NYC metropolitan region; and
3. specifically address pertinent comments contained in US NRC’s evaluation of OAG contentions (Appendix G of the FSEIS).
To focus the approach, ISR conducted a sensitivity analysis to determine which CHRONC input parameters have the greatest effect on the offsite economic cost risk (OECR), which is the per year total economic cost of a severe accident used in the SAMA analysis. For each of the sensitive parameters thus determined, ISR identified: the definition of the parameter; the input values chosen by Entergy; the explicit or implicit rationales for Entergy’s selection of those values; a range of more appropriate values (where applicable) based on available data, currency and relevance to the location of Indian Point; and a re-calculation of the OECR using the more appropriate value(s).
1 Previously, the State of New York had submitted Contentions 12, 12-A, and 12-B in response to earlier submissions by Entergy and NRC. These Contentions were consolidated as 12-C.
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page iv
The results of the sensitivity analysis demonstrated that the MACCS2 output was most sensitive to variation in the following CHRONC input parameters:
� decontamination costs and times; � value of nonfarm wealth; � depreciation rate; � societal discount rate of property; � relocation costs; and � fraction of nonfarm property due to improvements.
In its SAMA analysis, Entergy adopted all of the CHRONC input parameters, with the exception of farm and nonfarm wealth and the long-term exposure period, from MACCS2 Sample Problem A, adjusted only for the Consumer Price Index (CPI) to account for inflation. Sample Problem A is a collection of example MACCS2 input modules, developed initially for analysis of the Surry reactor in Virginia. The input parameters were based on the guidance provided in NUREG-1150. The Sample Problem A dataset was not intended to be a set of default input values for MACCS2. Instead, MACCS2 was designed so that users could define inputs based on site-specific data. ISR concluded that the use of Sample Problem A values for the cost sensitive parameters does not accurately incorporate available decontamination data, and the population and building characteristics of New York City and surrounding metropolitan areas. ISR conducted research to determine more appropriate input values for these sensitive cost input parameters. For the decontamination cost and time input parameters, ISR utilized multiple sources to determine a more appropriate range of input values. ISR confirmed that of the parameters considered in this report, the cost and time of decontamination were the most underestimated by Entergy. ISR then ran the MACCS2 code using Entergy’s MACCS2 input files substituted with values deemed appropriate by ISR for the sensitive decontamination parameters. The MACCS2 results indicate that the Entergy OECR cost values are underestimated by a factor ranging from four for the lowest ISR values and seven for the highest ISR values. This underestimation of the OECR could influence the cost-benefit analysis which forms the basis for the selection of alternatives.
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page v
TABLE OF CONTENTS 1. INTRODUCTION ................................................................................................................................... 1
1.1 BACKGROUND ................................................................................................................................. 1 1.2 OBJECTIVE AND SCOPE .................................................................................................................... 1 1.3 REPORT OUTLINE............................................................................................................................. 2 1.4 CONTENTION HISTORY RELATED TO INPUT PARAMETERS .................................................................... 3
2. MELCOR ACCIDENT CONSEQUENCE CODE SYSTEMS-2 (MACCS2) .......................................... 4
2.1 GENERAL ........................................................................................................................................ 4 2.2 CODE STRUCTURE ........................................................................................................................... 4 2.3 CHRONC MODULE ......................................................................................................................... 4 2.4 ECONOMIC COST MODEL .................................................................................................................. 5 2.5 MITIGATIVE ACTIONS MODEL ............................................................................................................. 5 2.6 SAMPLE PROBLEM A ........................................................................................................................ 7
3. SENSITIVITY ANALYSIS ..................................................................................................................... 9
3.1 DETERMINING PARAMETER SENSITIVITY ............................................................................................ 9 3.2 SENSITIVITY RESULTS ...................................................................................................................... 9
4. INPUT PARAMETER ANALYSIS ...................................................................................................... 11
4.1 GENERAL ...................................................................................................................................... 11 4.2 NONFARM DECONTAMINATION COSTS AND TIMES ............................................................................. 11
4.2.1 Parameter definition ............................................................................................................ 11 4.2.2 Source of Entergy’s values ................................................................................................. 12 4.2.3 Discussion of CDNFRM ...................................................................................................... 13 4.2.4 Discussion of TIMDEC ........................................................................................................ 24
4.3 VALUE OF NONFARM WEALTH ......................................................................................................... 25 4.3.1 Parameter definition ............................................................................................................ 25 4.3.2 Source of Entergy’s value ................................................................................................... 25 4.3.3 Discussion ........................................................................................................................... 26
4.4 PROPERTY DEPRECIATION RATE ..................................................................................................... 27 4.4.1 Parameter definition ............................................................................................................ 27 4.4.2 Source of Entergy’s value ................................................................................................... 27 4.4.3 Discussion ........................................................................................................................... 27
4.5 SOCIETAL DISCOUNT RATE FOR PROPERTY...................................................................................... 28 4.5.1 Parameter definition ............................................................................................................ 28 4.5.2 Source of Entergy’s value ................................................................................................... 28 4.5.3 Discussion ........................................................................................................................... 28
4.6 PER CAPITA COST OF LONG-TERM RELOCATION ............................................................................... 28 4.6.1 Parameter definition ............................................................................................................ 28 4.6.2 Source of Entergy’s value ................................................................................................... 29 4.6.3 Discussion ........................................................................................................................... 29
4.7 NONFARM WEALTH IMPROVEMENTS FRACTION ................................................................................ 29 4.7.1 Parameter definition ............................................................................................................ 29 4.7.2 Source of Entergy’s value ................................................................................................... 30 4.7.3 Discussion ........................................................................................................................... 30
4.8 COMPARISON OF ENTERGY’S MACCS2 INPUT VALUES WITH THOSE FROM OTHER NUCLEAR POWER PLANTS IN THE US ..................................................................................................................................... 30
5. CONCLUSION .................................................................................................................................... 32
6. REFERENCES .................................................................................................................................... 33
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page vi
ANNEX A RESPONSE TO US NRC STAFF EVALUATION (APPENDIX G) ................................... 36
ANNEX B MACCS2 USER INPUT SENSITIVITY ANALYSIS ........................................................... 41
ANNEX C CDNFRM CALCULATION ................................................................................................. 46 ANNEX D VALWNF CALCULATION ................................................................................................. 57
ANNEX E MACCS2 ECONOMIC COST FLOWCHARTS ................................................................. 59
ANNEX F TIMELINE OF CERTAIN REFERENCES .......................................................................... 64
LIST OF TABLES Table 1: Reduction in contamination for each DF ......................................................................12 Table 2: Modified decontamination costs (2005 USD) for NYC using building density multiplier16 Table 3: Suggested values of CDNFRM assuming cost (cesium) = cost (plutonium) (costs in
2005 USD) .........................................................................................................................18 Table 4: Suggested values of CDNFRM assuming cost (cesium) = 2 × cost (plutonium) (costs in
2005 USD) .........................................................................................................................18 Table 5: Summary of the decontamination costs (2005 USD) based on Reichmuth's studies ...19 Table 6: Comparison of cesium ground concentrations .............................................................19 Table 7: Costs using CONDO values assuming the NYC metro area is classified as urban and
the area outside the NYC metro area is classified as semi-urban (costs in 2005 USD) ......21 Table 8: Costs using CONDO values assuming the NYC metro area is classified as hyper-urban
and the area outside the NYC metro area is classified as urban (costs in 2005 USD) ........21 Table 9: Costs using RISO values assuming the NYC metro area is classified as urban and the
area outside the NYC metro area is classified as semi-urban (costs in 2005 USD) ............22 Table 10: Costs using RISO values assuming the NYC metro area is classified as hyper-urban
and the area outside the NYC metro area is classified as urban (costs in 2005 USD) ........22 Table 11: Summary of ISR’s decontamination costs .................................................................23 Table 12: Comparison of sensitive parameter values for IP with other US nuclear stations (costs
in 2005 USD) .....................................................................................................................31 Table 13: Summary of ISR proposed inputs and calculated OECRs (costs in 2005 USD) .........32 Table 14: Entergy’s CHRONC input parameters (all input cost values are in 2005 USD) ..........42 Table 15: Input sensitivity results ..............................................................................................44 Table 16: Annual average CPI values .......................................................................................46 Table 17: Decontamination in semi-urban areas - building fractions ..........................................47 Table 18: Decontamination in urban areas - building fractions ..................................................47 Table 19: Decontamination in hyper-urban areas - building fractions ........................................47 Table 20: Light decontamination in semi-urban areas (CONDO) ...............................................48 Table 21: Heavy decontamination in semi-urban areas (CONDO) ............................................49 Table 22: Light decontamination in urban areas (CONDO) .......................................................50 Table 23: Heavy decontamination in urban areas (CONDO) .....................................................51 Table 24: Light decontamination in hyper-urban areas (CONDO) .............................................52 Table 25: Heavy decontamination in hyper-urban areas (CONDO) ...........................................53 Table 26: Decontamination in semi-urban areas (RISO) ...........................................................54 Table 27: Decontamination costs for urban areas (RISO) .........................................................55 Table 28: Decontamination costs for hyper-urban areas (RISO) ...............................................56 Table 29: VALWNF values and calculation ...............................................................................58
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page vii
LIST OF FIGURES Figure 1: The population dose associated with mitigative actions .............................................. 6 Figure 2: The relative costs associated with mitigative actions ................................................... 7 Figure 3: ISR’s methodology for determining light and heavy decontamination costs (CDNFRM)
..........................................................................................................................................15 Figure 4: Graphical summary of decontamination costs (2005 USD) with ranges .....................23 Figure 5: OECR vs heavy decontamination cost (2005 USD) ....................................................24 Figure 6: OECR (2005 USD) for decontamination times up to 50 years ....................................25 Figure 7: Composition of decontamination costs for plutonium [7] .............................................37 Figure 8: Sensitivity plot ............................................................................................................45 Figure 9: Total cost of long-term protective actions ...................................................................60 Figure 10: Cost to condemn nonfarm property ..........................................................................61 Figure 11: Cost to condemn farmland .......................................................................................61 Figure 12: Cost of milk disposal ................................................................................................62 Figure 13: Cost of non-dairy disposal ........................................................................................62 Figure 14: Cost of early protective actions ................................................................................63
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page viii
GLOSSARY Term or Abbreviation Description
ATMOS Atmospheric Transport and Deposition. The first module in MACCS2. It calculates air and ground concentrations, plume size, and timing information for all plume segments as a function of downwind distance.
CDNFRM The MACCS2 input that defines the nonfarmland decontamination cost.
CHRONC Intermediate- and Long-Term-Phase Calculations. The third module in MACCS2. It calculates the consequence of the long-term effects of radiation and computes the decontamination and economic impacts incurred because of the accident.
CPI Consumer Price Index.
CRAC2 Code Systems for Calculating Reactor Accident Consequences. It was developed in support of the Reactor Safety Study, WASH-1400 to assess the risk from potential accidents at nuclear power plants.
DPRATE Defines the depreciation rate that applies to property improvements during a period of interdiction. This depreciation rate is intended to account for the loss of value of buildings and other structures resulting from a lack of habitation and maintenance.
DSCRLT Defines the long-term phase dose criterion. This is the maximum allowable direct exposure dose commitment to the long-term critical organ during the long-term phase action period (TMPACT).
DSEIS Draft Supplemental Environmental Impact Statement.
DSRATE Defines the expected rate of return from land, buildings, equipment, etc. For example, the inflation-adjusted real mortgage rate for land and buildings could be used.
DSRFCT or Decontamination Factor (DF)
Dose Reduction Factor. An input in MACCS2, defines the effectiveness of the various decontamination levels in reducing dose. A dose reduction factor of three means that the resulting population dose at that location will be reduced to one-third of what it would be without decontamination.
In MACCS2, dose reduction factor is used interchangeably with decontamination factor (DF), which often solely refers to the reduction in contamination and not necessarily reduction in dose. MACCS2 expects that the DF be entered under the variable name DSRFCT.
EARLY Emergency-Phase Calculations. The second module in MACCS2. It calculates the consequences due to exposure to radiation in the first seven (7) days (the emergency phase) of the accident.
Entergy Entergy Nuclear Indian Point 2, LLC, Entergy Nuclear Indian Point 3, LLC, and Entergy Operations, Inc., the owner of Indian Point Energy Center containing two operating nuclear reactors.
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page ix
Term or Abbreviation Description
ER Environmental Report submitted by Entergy as part of its License Renewal Application (LRA).
Farmability A measure of how appropriate the land is for farming, mainly due to the deposition of radionuclides onto that land.
FRNFIM Defines the fraction of nonfarm wealth in the region due to improvements. This value includes buildings and infrastructure such as roads and utilities, as well as any nonrecoverable equipment or machinery.
FSEIS Final Supplemental Environmental Impact Statement.
Gaussian A mathematical probability distribution function, the "normal distribution."
GCP Gross County Product. GCP refers to the market value of all final goods and services produced within a county in a given period.
GDP Gross Domestic Product. GDP refers to the market value of all final goods and services produced within a country in a given period.
GMP Gross Metro Product. GMP refers to the market value of all final goods and services produced within a metropolitan area in a given period.
Groundshine A term describing the dose from contamination deposited on the ground.
Habitability A measure of how habitable the land is, mainly due to the radiation dose rate in the area.
Habitability Criterion
The decision on which mitigative action to implement hinges on the habitability criterion (HC). The HC is dependent on and calculated from the long-term projected dose (DSCRLT) that a person would get if they continued to live in the contaminated area for the specified time (TMPACT).
Interdiction In MACCS2, the prevention of people residing in an area due to higher than acceptable levels of radioactive contamination. It is a mitigative action to reduce to the total radiation dose to affected members of the public.
IP2 Indian Point Unit 2.
IP3 Indian Point Unit 3.
IPEC Indian Point Energy Center. This is Entergy's term for the location of the Indian Point reactors, spent fuel pools, and related facilities.
LRA License renewal application.
MACCS2 The MELCOR Accident Consequence Code Systems-2.
MELCOR Methods for Estimation of Leakages and Consequences of Releases.
NRPB National Radiological Protection Board (United Kingdom)
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page x
Term or Abbreviation Description
NRC The US Nuclear Regulatory Commission. The NRC regulates commercial nuclear power plants and other uses of nuclear materials.
NUREG-1150 An NRC Report titled “Severe Accident Risks: An Assessment for Five US Nuclear Power Plants”. The study contains analysis and example values for five nuclear power stations in the US: Surry, Peach Bottom, Sequoyah, Grand Gulf and Zion.
NYS New York State.
OAG New York State Office of the Attorney General.
OECR Offsite Economic Cost Risk. The OECR is a frequency-averaged cost, on a per year basis. It is an actuarial assessment of the cost that takes into account the low frequency of severe accidents. It is the most relevant output value for the cost-benefit evaluation in SAMA analysis.
POPCST Defines the per capita removal cost for temporary or permanent relocation of population and businesses in a region rendered uninhabitable during the long-term phase time period. This cost is assessed if any of the following actions are required: decontamination alone, decontamination followed by interdiction, or condemnation. The MACCS2 User Guide recommends that this value be derived in a way that takes account of both personal and corporate income losses for a transitional period as well as moving expenses.
PSA Probabilistic Safety Assessment. A systematic methodology to evaluate risks associated with a complex engineered entity. Probabilities of events occurring and their consequences are important products of a PSA.
Resuspension A term describing what fraction of the radioactive particles deposited on the ground are kicked back (resuspended) into the air. This is important when discussing the inhalation of radioactive particles.
RTW Reproducible Tangible Wealth. A value last calculated by the US Bureau of Economic Analysis in 1995. It represents total tangible wealth of a region, i.e. buildings, land, equipment, etc.
SAMA Severe Accident Mitigation Alternative.
Sample Problem A Sample Problem A is one of 14 example problems provided with the MACCS2 code that incorporates input data specific to the Surry reactor consequence analysis.
Sensitivity Analysis Measuring how much an output changes by varying an input.
Sandia Sandia National Laboratories.
TGWHLF Groundshine weathering half-lives (seconds)
TIMDEC Defines the time required for completion of each of the decontamination levels. The user must define a decontamination time for each of the decontamination levels. Decontamination begins at the end of the intermediate phase.
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page xi
Term or Abbreviation Description
TMPACT Defines the long-term dose projection period. Protective actions such as decontamination, or decontamination followed by interdiction are evaluated to determine if the exposure of an individual during this period can be reduced so that it does not exceed the long-term phase allowable dose.
VALWNF Defines the value of the nonfarm wealth in the region. Nonfarm wealth includes all public and private property not associated with farming that would be unusable if the region was rendered either temporarily or permanently uninhabitable. This value should include the cost of land, buildings, infrastructure, and the cost of any nonrecoverable equipment or machinery.
WASH-1400 The Reactor Safety Study was a report produced in 1975 for the NRC.
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 1
1. INTRODUCTION 1.1 Background The Indian Point Nuclear Generating Station is a three-unit nuclear power plant station located in Buchanan, New York, approximately 24 miles north of the New York City boundary (the Bronx county) and 38 miles north of the Wall Street area in Manhattan. The plant is owned and operated by Entergy Nuclear Indian Point 2, LLC, Entergy Nuclear Indian Point 3, LLC, and Entergy Operations, Inc. (Entergy). Unit 1 was shut down in 1974. Units 2 and 3 (IP2 and IP3) were commissioned in the mid 1970s, with their licenses set to expire in 2013 and 2015, respectively. Both IP2 and IP3 are pressurized water reactors manufactured by Westinghouse, each with approximately a 1,000 MW generating capacity. Entergy has submitted a license renewal application (LRA) to the Nuclear Regulatory Commission (NRC) seeking to extend its operating licenses for another twenty years. As part of the LRA, Entergy was required to submit an Environmental Report (ER) that included a Severe Accident Mitigation Alternatives (SAMA) analysis. As part of the relicensing proceeding, NRC Staff completed a Final Supplemental Environmental Impact Statement (FSEIS) which evaluates, among other things, Entergy’s SAMA analysis. The New York State Office of the Attorney General (OAG) submitted a Contention (Consolidated Contention 12-C)2 which asserts that the submitted Environmental Report (ER), NRC Staff’s Draft Supplemental Environmental Impact Statement (DSEIS), Entergy’s December 2009 SAMA Reanalysis (SAMA Reanalysis), and NRC Staff’s Final Supplemental Environmental Impact Statement (FSEIS) failed to address site specific assumptions and inputs related to clean-up and decontamination costs in the New York City metropolitan region in the event of a severe accident at IP2 or IP3. In Consolidated Contention 12-C, the State of New York (NYS) asserts that NRC Staff and Entergy substantially underestimate the costs of decontamination measures which must be considered in the LRA process. The computer code used to estimate the cost of decontamination and evacuation/relocation after a severe accident at a nuclear power plant is called the MELCOR Accident Consequence Code Systems, or MACCS. The US Nuclear Regulatory Commission (NRC) has relied on the successor code, known as MACCS2, for SAMA consequence calculations in connection with applications to renew operating licenses for nuclear power plants. 1.2 Objective and scope The objective of this report is to review and assess Entergy’s use of the MACCS2 code to estimate the economic costs associated with a severe accident at IP2 or IP3 for its SAMA analysis, and NRC Staff’s evaluation of Entergy’s SAMA analysis as part of the FSEIS (see Annex A). This review and evaluation encompasses the assumptions inherent in the MACCS2 code, the input parameters developed and used by Entergy for its SAMA analysis, and the NRC’s discussion and approval of these parameters, methodology, and results in the FSEIS. ISR’s analysis is focused on the effect of the critical input parameters on the total economic cost of a severe nuclear accident. 2 The Board consolidated Contentions 12, 12-A, 12-B, and 12-C as Consolidated Contention 12-C.
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 2
There are several major factors which contribute to the eventual costs of a severe nuclear accident (e.g. release characteristics, weather pattern, population profile, clean-up, etc.) as evaluated by the MACCS2 code. This analysis focuses on those factors directly associated with the long-term management of the nuclear accident, specifically decontamination, interdiction (i.e. relocation) and condemnation of buildings and property. The MACCS2 code contains several modules which address issues related to the consequence evaluation of severe accidents. The "CHRONC" module contains the input parameters which ISR has evaluated and which are related to Consolidated Contention 12-C, and is therefore the only module considered in this report. 1.3 Report outline The following section (1.4) provides further detail of the technical aspects of the contention submitted by NYS regarding the SAMA analysis for IP2 and IP3. Section 2 contains a description of the MACCS2 code, with an emphasis on the CHRONC module, the economic cost model and the mitigative actions model. Section 3 describes the methodology and results of the sensitivity analysis used to determine which MACCS2 input parameters have the greatest effect on the total economic cost. Section 4 contains the analysis of each input parameter determined to be sensitive in Section 3. For each sensitive parameter, the following are provided:
1. The parameter name, value assigned by Entergy and the definition from the MACCS2 user guide;
2. The fundamental source or methodology employed to determine the value; 3. A discussion of the appropriateness of the methodology or the quantities used, and
ISR’s conclusions regarding more applicable methodologies or inherent quantities to account for the site-specific conditions related to the Indian Point reactors, including present time, location (i.e. NYS), economy and national and international best practices.
Section 4 also includes a comparison of the input values used by Entergy to those previously used by other nuclear power plants in the US. Section 5 presents ISR’s conclusions based on the analysis conducted in Section 4. Section 6 contains a listing of references. Annex A contains responses to specific comments in NRC Staff Evaluation (Appendix G). Annex B contains a listing of the CHRONC module inputs and the results of the sensitivity analysis. Annex C contains the details of the calculations used in the determination of decontamination costs. Annex D contains the calculation for the value of nonfarm wealth. Annex E contains a set of flowcharts that describe the MACCS2 economic model. Annex F contains a timeline of certain references referred to throughout this report.
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 3
1.4 Contention history related to input parameters The following is a chronological list of key events that comprise the NYS Contention 12 history. This listing focuses on the technical aspects of the contentions, specifically those aspects that are pertinent to the review of the MACCS2 input parameters.
� In April 2007, Entergy submitted its ER to the NRC describing, among other things, its SAMA analysis.
� On November 30, 2007, NYS submitted Contention 12, which asserted that Entergy had not, in its ER, accurately modeled the cleanup and decontamination costs for a severe accident over an urban area such as the Westchester County/New York City area surrounding Indian Point.
� On December 22, 2008, NRC Staff released the DSEIS, which describes the environmental impacts of the license renewal for IP2 and IP3. The DSEIS adopted Entergy’s SAMA analysis as set forth in its ER.
� In February 2009, NYS filed Contention 12-A, which was consolidated on June 1, 2009 with previous Contention 12. The salient points of the contention were:
o The MACCS2 model assumed large-sized radionuclides (i.e. plutonium) as opposed to small-sized particles (i.e. cesium), which are likely in a severe accident and more costly to remove and clean up;
o The analysis should incorporate the results of: 1. D. Chanin and W. Murfin, Site Restoration: Estimation of Attributable Costs
from Plutonium-Dispersal Accidents, SAND96-0957, Unlimited Release, UC-502, (May 1996) (“Site Restoration”) regarding the costs of a plutonium-dispersal accident, and
2. Studies examining the costs of a terrorist attack and spent fuel pool fire at Indian Point.
� In December 2009, Entergy submitted a revised SAMA Analysis. The revision was due to an error made by Entergy in its original analysis and subsequent correction to the meteorological data file.
� On March 11, 2010, NYS filed Contention 12-B, which asserted that Entergy’s SAMA re-analysis underestimates decontamination and clean up costs associated with a severe accident in the New York Metropolitan area and, therefore, underestimates the cost of a severe accident.
� On December 3, 2010, NRC Staff released the FSEIS. In response to NYS Contentions 12, 12-A, and 12-B, NRC staff concluded that decontamination costs were reasonable, acceptable and consistent with that of other nuclear power plants.
� On February 3, 2011, NYS filed Contention 12-C. The salient points of the contention were that the FSEIS is inadequate because:
o It uses cost data for moderate decontamination for an event that would require heavy decontamination;
o It does not scale up the decontamination cost data from Sandia’s Site Restoration, which was based on Albuquerque, NM, to a much higher population-density area such as the New York City Metropolitan Area; and
o Entergy’s values are based on particles of larger diameter than one would get from a reactor accident. Smaller particles are more difficult to decontaminate.
� The Board consolidated Contentions 12, 12-A, 12-B, and 12-C as Consolidated Contention 12-C.
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 4
2. MELCOR ACCIDENT CONSEQUENCE CODE SYSTEMS-2
(MACCS2) 2.1 General MACCS2 (Chanin, 1998 [1]) is a Gaussian plume model for calculation of radiological atmospheric dispersion and consequences, developed by Sandia National Laboratories (Sandia). MACCS2 may be used for severe accident analysis, design-basis accidents and other accidents. Its development was sponsored by the United States Nuclear Regulatory Commission (NRC) as a successor to an older code, Code Systems for Calculating Reactor Accident Consequences (CRAC), for the performance of commercial nuclear industry probabilistic safety assessments (PSAs) [2]. While the underlying models of CRAC and MACCS/MACCS2 are largely similar, the main difference between the two is that a number of CRAC parameters are “hard-wired” and, thus, cannot be changed in the CRAC code. In MACCS and MACCS2, those same parameters are user-defined and, thus, can be derived from site-specific data. After its verification in the early 1990s, MACCS2 was released for unrestricted use. 2.2 Code structure MACCS2 is executed in three steps. The first module, ATMOS, calculates air and ground concentrations, plume size, and timing information for all plume segments as a function of downwind distance. The next module, EARLY, calculates the consequences due to exposure to radiation in the first seven (7) days (the emergency phase) of the accident. The last module, CHRONC, calculates the consequence of the long-term effects3 of radiation and computes the economic impacts incurred due to the accident. The purpose of this report is to analyze the inputs used by Entergy in its SAMA analysis that are associated with long-term economic costs. All of these inputs are contained in the CHRONC module of the code. For this reason, further discussion of the MACCS2 code will be focused on the CHRONC module only. 2.3 CHRONC module The CHRONC module contains the input parameters that pertain to both the intermediate and long-term phases of the nuclear accident consequence management. It simulates the events that occur following the emergency-phase time period modeled by the EARLY module. CHRONC calculates both the individual health effects and the economic cost of the long-term decontamination and relocation associated with a severe accident. Based primarily on the CHRONC input parameters, MACCS2 determines the economic cost of a severe accident. The CHRONC module contains two models: the economic cost model and mitigative actions model. As described below, these models form the framework for the determination of the output costs associated with a severe accident. 3 MACCS2 allows the user to define the period for “long-term”, but it is recommended that 30 years be used since this is consistent with the EPA in its Superfund Guidance (EPA, 1991).
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 5
2.4 Economic cost model The economic cost model of the MACCS2 code is intended to estimate the direct offsite costs from a severe nuclear accident. The following costs are calculated by the MACCS2 code:
1. Food and lodging costs for short-term relocation of people who are evacuated or relocated during the emergency phase of the accident;
2. Decontamination costs for property that can be returned to use after decontamination; 3. Depreciation of property (farm and nonfarm) while it is temporarily interdicted following
decontamination to allow for radioactive decay to reduce ground contamination to acceptable levels;
4. Costs resulting from the disposal of contaminated milk and crops; and 5. Costs due to permanent interdiction of property (i.e. condemnation).
The various factors contributing to each of these costs are depicted in the flowcharts given in Annex E. If other indirect costs were included such as medical expenses regarding adverse health effects and the costs of disposal of contaminated wastes, the total economic cost would increase. 2.5 Mitigative actions model In MACCS2, there are five possible mitigative strategies4 for any given spatial sector5:
1. No mitigative actions (i.e. do nothing); or 2. Decontaminate areas using the first (i.e. lowest) decontamination factor (DF), DF1; or 3. Decontaminate areas using the second (i.e. highest) decontamination factor, DF2; or 4. Decontaminate areas using DF2 and implement temporary interdiction for up to 30
years; or 5. Condemn the area.
The decision on which mitigative action will be implemented hinges on the habitability criterion (HC). The HC is dependent on the long-term projected dose (MACCS2 input DSCRLT) that a person would get if they continued to live in the contaminated area for the specified time (MACCS2 input TMPACT). Long-term phase doses are the sum of the groundshine and resuspension inhalation committed (50-year) doses [1]. The HC recommended by the EPA in EPA-400 [3] is 0.04 Sv (DSCRLT) in 5 years (TMPACT). The guidelines published in EPA-400 are widely accepted and used by several states including New York, where they have been used as the basis for the NYS radiological emergency preparedness plan (2010) [4].
4 There are five strategies assuming there are two decontamination levels. 5 Spatial sectors are based on a polar-coordinate grid defined by a number of radial divisions (e.g. 16) and the endpoint distances.
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 6
The MACCS2 decision sequence for determining which mitigative action to implement is as follows and is depicted in Figure 1:
1. If there is no decontamination and the projected radiation dose to the public in the contaminated area is less than the HC, relocation or other mitigative actions are not required, otherwise:
2. If after decontamination using DF1, the dose is less than the HC, decontaminate to DF1 and allow return to property after the time required to decontaminate (MACCS2 input TIMDEC1), otherwise:
3. If after decontamination using DF2, the dose is less than the HC, decontaminate to DF2 and allow return to property after the time required to decontaminate (MACCS2 input TIMDEC2), otherwise:
4. If decontamination using DF2 and temporary relocation for any time up to 30 years results in a dose less than the HC, decontaminate to DF2 and move back after TIMDEC2 plus the interdiction time (governed by log-linear relationship based on radioactive decay and weathering), otherwise:
5. Condemn the property (i.e. permanent interdiction). MACCS2 incorporates the following cost effectiveness caveat: if the cost of decontamination and interdiction up to 30 years is greater than the cost of condemning the property, then condemnation is chosen [1]. The relative costs of each possible mitigative action are shown in Figure 2.
0.8
8
80
0 10 20 30 40 50 60 70 80
Proj
ecte
d do
se o
ver l
ong-
term
actio
n pe
riod
(Sv)
Downwind distance from reactor (mi)
No mitigative actions Decon (DF1) Decon (DF2)
Decon (DF2) + temporary interdiction Long-phase relocation dose criterion Population dose
No mitigative actions
Decontamination only (DF 1, e.g. DF=3)Decontamination only (DF 2, e.g. DF=15)
Deco
ntam
inat
ion
(DF 2
) + te
mpo
rary
inte
rdict
ion
Cond
emna
tion
Dose criterion for long-term phase relocation
FOR ILLUSTRATIVE PURPOSES ONLY
Figure 1: The population dose associated with mitigative actions
5 4 3 2 1
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 7
0.8
8
80
0 10 20 30 40 50 60 70 80
Rela
tive
cost
of m
itiga
tive
actio
n pe
r per
son
(non
-farm
) or p
er h
ecta
re (f
arm
)
Downwind distance from reactor (mi)
No mitigative actions
Decontamination only (DF 1, e.g. DF=3)Decontamination only (DF 2, e.g. DF=15)
Deco
ntam
inat
ion
(DF 2
) + te
mpo
rary
inte
rdict
ion
Cond
emna
tion
FOR ILLUSTRATIVE PURPOSES ONLY
Figure 2: The relative costs associated with mitigative actions
2.6 Sample Problem A The MACCS2 code package includes 14 sample problems containing sets of example inputs that were designed to be used to verify that the MACCS2 code was installed and running properly [1]. Sample Problem A (one of the 14 sample problems in the code package) incorporates site-specific data for the Surry site in Virginia that were obtained from NUREG-1150. The developers of MACCS2 intended that Sample Problem A be used to test the improvements that had been made to the previous version of the code. These improvements include: the capability to consider multiple source terms and emergency response assumptions in a single run; and the implementation of the new COMIDA2 food pathway model [1]. Nowhere in the MACCS or MACCS2 documentation is it suggested that the input values of the code sample problems be considered recommended or "default" values. David Chanin, the developer of the MACCS2 code, discussed the use of Sample Problem A as default values. In his 2005 paper, The Development of MACCS2: Lessons Learned [5], he stated “We also went so far as to scrupulously avoid using the common ‘default value’ in referring to the code’s provided ‘Sample Problem’ input data files. ‘Sample data’ and ‘example usage’ were the terms used to remind the analyst that they, and they alone, were responsible for reviewing MACCS and MACCS2 input data and resultant code outputs to ensure appropriateness for their application.”
5 4 3 2 1
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 8
All but the following three Entergy MACCS2 CHRONC input parameters were derived (i.e. taken directly or adjusted for inflation) from Sample Problem A: the value of nonfarm wealth (VALWNF), the value of farm wealth (VALWF) and the long-term exposure period (EXPTIM). As determined in the following section, of the three values, only the value of nonfarm wealth is a cost sensitive parameter.
~ •• II:---------------------------
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 9
3. SENSITIVITY ANALYSIS 3.1 Determining parameter sensitivity ISR conducted a sensitivity analysis to determine which input parameters directly and most significantly affect the costs of mitigative actions following a severe accident. In order to evaluate the sensitivity of each of the CHRONC input parameters, ISR varied each input parameter, one at a time, and performed a MACCS2 simulation run for Indian Point Station 2 (IP2) using Entergy’s five input files (i.e., ATMOS, EARLY, CHRONC, weather file and site file). Since only the source terms contained in the ATMOS module vary between IP2 and IP3, ISR assumed that the general conclusions resulting from the sensitivity analysis are applicable to both stations. ISR chose to quantify the effect of changing each parameter by calculating the change in the resulting total offsite economic cost risk (OECR). ISR selected the total OECR as it is the value used in the cost-benefit analysis in the SAMA analysis and therefore the most pertinent value derived from the MACCS2 output. The details of this calculation can be found in Annex B. The OECR calculated by Entergy was $ 2.12E+05/yr in 2005 US dollars (USD) for IP2 and was used as a reference for a basis of comparison to ISR’s calculated OECRs in Section 4. 3.2 Sensitivity results To ascertain the relative sensitivity, ISR increased each input parameter by 10%6 and the percentage increase in the total OECR was calculated. The results are listed in Annex B, Table 15. The results of ISR’s sensitivity analysis indicated that the most sensitive CHRONC input parameters are (in order of decreasing sensitivity):
1) GWHLF – Long-term groundshine coefficients 2) DSCRLT – Long-term phase dose criterion (Sv) 3) VALWNF – Value of nonfarm wealth ($/person) 4) TMPACT – Time action period ends (seconds) 5) DSRATE – Societal discount rate for property (/year) 6) FRNFIM – Nonfarm wealth improvements fraction 7) TGWHLF – Groundshine weathering half-lives (seconds) 8) DPRATE – Property depreciation rate (/year) 9) POPCST – Per capita cost of long-term relocation ($/person) 10) CDNFRM – Nonfarm decontamination cost ($/person) 11) TIMDEC – Decontamination times (for all decontamination levels) (seconds)
The values for the groundshine parameters, GWHLF and TGWHLF, were adopted from the guidance published by the US NRC for the main MACCS2 input parameters [6]. Since these groundshine parameters are radionuclide-specific, calculated from first physical principles and are not time or location-dependent, there is no need for further analysis of these parameters. 6 10% was chosen by ISR because it is a sufficiently small increase such that the change is linear and continuous throughout the increase.
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 10
As discussed in Section 2.5, the values for the DSCRLT and TMPACT parameters are those recommended by the EPA and adopted by the state of New York. Therefore, there is no need for further analysis of these parameters. For decontamination, the CDNFRM and TIMDEC parameters are assessed in Section 4.2. ISR assessed the remaining five sensitive parameters in Sections 4.3 to 4.7 respectively.
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 11
4. INPUT PARAMETER ANALYSIS 4.1 General ISR carefully examined the MACCS2 CHRONC input file produced by Entergy. For each sensitive input, ISR determined the input parameter's definition, the value chosen by Entergy, the rationale or source for their value, and a discussion of what may be considered to be a more appropriate value, if required. The following sections describe and discuss the findings of this analysis. 4.2 Nonfarm decontamination costs and times 4.2.1 Parameter definition Parameter name: CDNFRM Entergy values: $5,184 per person, $13,824 per person (both in 2005 USD) CDNFRM is the nonfarmland decontamination cost for each decontamination level (i.e. decontamination factor, described below). The MACCS2 User’s Guide does not specify which cost components of the decontamination process should be included (e.g. characterization, decontamination, disposal, compensation, etc.); therefore it is up to the user to identify these components. Parameter name: TIMDEC Entergy values: 5.18E+06 s, 1.04E+07 s (60 d, 120 d) TIMDEC is the time required for completion of each decontamination level (i.e. decontamination factor, described below). The decontamination factor (DF) and the decontamination level are used interchangeably in MACCS2 with the dose reduction factor (MACCS2 input DSRFCT), which is defined as “the effectiveness of the various decontamination levels in reducing dose. A dose reduction factor of 3 means that the resulting population dose at that location will be reduced to one-third of what it would be without decontamination.” [1] DSRFCT = (population dose before clean-up) / (population dose after cleanup) Usually for decontamination activities, the decontamination factor is defined as: DF = (contamination before clean-up) / (contamination after cleanup) It is this definition that will be used for DF in the remainder of this section. The following table expresses DFs as decontamination efficacy in percentages.
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 12
Table 1: Reduction in contamination for each DF
DF Reduction in contamination
2 50% 3 67% 5 80% 7 85.7% 10 90% 15 93.3% 20 95%
Decontamination factors may be classified as follows [7]: 2<DF<5 = “Light” decontamination 5<DF<10 = “Moderate” decontamination DF>10 = “Heavy” decontamination Some examples of the activities associated with the various values of DF are [7]: Light decontamination – prompt vacuuming of all structural exteriors followed by detergent scrubbing. Building interiors would be decontaminated by such methods as vacuuming/shampooing. Turf/lawn areas that could not be decontaminated would be removed. Tree foliage would be hosed down, with wash water collected to avoid run-off. Moderate decontamination - roofing would be removed and replaced. All landscape material would be replaced. Interiors of buildings would be emptied of all removable contents (e.g. desks, chairs, personal items, etc). Heavy decontamination – A DF of 10 indicates that 90% of the radioactive contamination is removed by the decontamination technique. Based on experience following the Chernobyl accident, there is “…no method to achieve surface decontaminations of these (DF>10) levels short of completely demolishing (razing) of buildings and disposing of the material in a licensed burial facility” [7]. This is understood to mean that decontamination of an entire building to a level greater than 10 may not be possible. Other authors also come to the same conclusion [8,9]. 4.2.2 Source of Entergy’s values Entergy selected DFs of 3 and 15. These DFs and their corresponding decontamination times, 60 days and 120 days respectively, were taken from Sample Problem A (see Section 4.8), which follows the assumptions made in NUREG-1150 [10]. Even though a DF of 15 is unlikely to be achievable, ISR also used these two DFs to evaluate Entergy’s use of the MACCS2 model. MACCS2 requires a user-specified nonfarm decontamination cost (in $/person) to be input for each DF. The values selected by Entergy are $5,184/person and $13,824/person for DFs of 3 and 15 respectively. Entergy obtained these values by adjusting the corresponding MACCS2
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 13
Sample Problem A values ($3,000/person and $8,000/person) by the CPI. Although many other SAMA analyses submitted to the NRC by US licensees use the same approach (see Sections 2.6 and 4.8), Entergy did not supply a rationale for this approach. 4.2.3 Discussion of CDNFRM Decontamination costs are the dominant factor in the evaluation of the remediation cost following a severe nuclear accident. Due to the fact that there is very little data on actual severe reactor accidents in a hyper-urban area such as NYC, significant, detailed research is required to accurately determine these input parameters. As stated in NUREG-1150, one may extrapolate from other types of nuclear accidents (primarily weapon-related) or field radiological decontamination work and experiments. Decontamination following any radioactive release will vary considerably in cost depending on the chosen DF and the radionuclide(s) involved. For the case of a severe nuclear accident, it is well documented that decontamination of small sized particles such as cesium (137Cs) in urban areas represents the most significant challenge [11]. This is because cesium, with its solubility and ability to ion exchange with sodium and potassium present in the concrete, will migrate rapidly such that at 5 mm into the material, its concentration may have only dropped to 50% of that at the surface. This migration, of course, increases with time (i.e. decontamination of cesium is more difficult as time post-event passes). Because cesium is highly soluble, it bonds to water molecules, leading to more and deeper penetration, and making it more difficult to isolate and decontaminate. This was verified by Farfan [12] who measured cesium penetration to more than 5 mm in building structures in Pripyat (near Chernobyl), some 25 years post-event. In addition, the solubility of cesium generates further problems for decontamination if it is introduced into the water cycle. ISR acknowledges that the determination of the costs of decontamination following a severe nuclear accident is very complex. In an effort to maintain simplicity and accuracy, ISR has chosen the following methodology to calculate a realistic nonfarm decontamination cost (CDNFRM) using various sources:
1. Divide the spatial grid defined in the Entergy MACCS2 site input file into two discrete areas within the 50 mile radius of IP for the purpose of evaluation: a) the “NYC metropolitan area” and b) “the areas outside of the NYC metropolitan area”;
2. For each of these two areas, calculate the cost of light and heavy decontamination using the per square kilometer decontamination cost obtained from the following sources:
Approach A: Site Restoration [7] as modified by Survey of Costs [13]: In these references, Sandia (Chanin) and Luna describe a methodology to estimate decontamination costs using the results from US plutonium dispersal tests as a basis;
Approach B: Reichmuth [14]: In this reference Reichmuth presents results from radiological dispersal device economic consequence analysis in the US and Canada;
Approach C: CONDO [8]: This is a decontamination cost estimation tool from the UK National Radiological Protection Board (NRPB);
Approach D: RISO [9]: This reference presents results from decontamination experiments carried out by RISO National Laboratory in Denmark;
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 14
3. Sum the cost of decontamination for both areas to obtain a single total cost for the 50-
mile radius area surrounding the power plant for each the light and heavy decontamination;
4. Divide the total cost by the total population in the 50-mile radius surrounding the power plant (19,228,712)7 to obtain a per capita cost for both light and heavy decontamination (i.e. CDNFRM); and
5. Update the per capita cost to 2005 costs using CPI. A flowchart depicting ISR’s methodology for calculating the CDNFRM using each of the four sources (Approaches A to D) is shown in Figure 3.
7 This population is the sum of all sector populations as defined in the Entergy MACCS2 site input file.
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 15
Value ofCDNFRM
(2005)
CONDO,cost per km2
RISO,cost per km2
ISR assumingDF (Pu) = DF (Cs)
andDF (Pu) = ½ DF (Cs)
Entergy, fromMACCS2 Sample
Problem A(CPI adjusted)
CONDO, using areafractions for mediumpopulation densities
Entergy Site file,using spatial grid
areas
Reichmuth
CONDO, using areafractions for high
population densities
Site Restoration asmodified by Survey of
Costs and ISRcost per km2
Cost per km2 for cesium,for a generic area
Cost per km2 for cesium,for NYC metro area and
elsewhere
Cost per km2 forplutonium, for NYC metro
area and elsewhere
Cost per km2 for cesium,for NYC metro area and
elsewhere
Entergy Site file,using population
data
Total cost for cesium, forentire 50-mi radius area
Per capita cost forcesium, for entire 50-mi
radius area
Per capita cost forcesium, for entire 50-mi
radius area
Per capita cost forcesium, for NYC andVancouver, Canada
areas
Approach A Approach C Approach D
Approach B
Figure 3: ISR’s methodology for determining light and heavy decontamination costs (CDNFRM)
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 16
Approach A: Determining decontamination costs using current US data from Site Restoration and Survey of Costs Site Restoration [7] used historical data (from various actual releases of plutonium and other radionuclides) to derive the costs of a cleanup following plutonium dispersal in an urban area, namely Albuquerque, N.M. In their report, Sandia specifically states that costs were not estimated for hyper-dense population8 areas. In Survey of Costs, Luna [13] subsequently used the Site Restoration analysis as a basis for calculating the cost of cleanup of the hyper-dense population area of interest here, NYC. To do this he:
� Used the actual area coverage (i.e. land use) percentage in NYC for Site
Restoration’s 5 categories (e.g. residential, commercial, industrial, streets and vacant land); and
� Multiplied his results by the population density ratio of NYC to Albuquerque, to account for the greater structure density in NYC.
In Survey of Costs, Luna pre-supposes that building density is directly proportional to population density. Instead of making that assumption, ISR used the actual building densities for NYC and Albuquerque obtained from US Census data ([15], [16]) to arrive at decontamination costs, which are shown in Table 2. ISR derived the building density multiplier for residential and commercial land (i.e. 8.98) from an average of the five NYC boroughs of 13,980 buildings/mi2 [15] versus 1,557 buildings/mi2 for Albuquerque [16].
Table 2: Modified decontamination costs (2005 USD) for NYC using building density multiplier
Luna,
Survey of Costs
Site Restoration (Albuquerque) ISR Using Actual Building Densities (NYC)
Land Use Area Fraction in NYC
Light (2<DF<5) ($M/km2)
Moderate (5<DF<10) ($M/km2)
Heavy (DF>10) ($M/km2)
Building Density Multiplier
Light (2<DF<5) ($M/km2)
Moderate (5<DF<10) ($M/km2)
Heavy (DF>10) ($M/km2)
Residential 0.287 $20.31 $45.99 $84.51 8.98 $182.38 $412.99 $758.90 Commercial 0.164 $32.09 $48.55 $139.84 8.98 $288.17 $435.98 $1,255.76 Industrial 0.068 $45.51 $47.55 $84.12 1.00 $45.51 $47.55 $84.12 Streets 0.250 $3.97 $4.62 $61.88 1.00 $3.97 $4.62 $61.88 Vacant land 0.238 $19.29 $20.38 $22.64 1.00 $19.29 $20.38 $22.64 Overall cost $121.17 $167.09 $392.99 $539.32 $921.52 $2,183.30
8 Values delineating population densities (PD in persons/km2) to characterize regions are taken from [14], viz
� Rural – 0<PD<50 � Urban – 50<PD<3000 � High Density Urban – 3000<PD<10,000 � Hyper Density Urban – 10,000<PD
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 17
Decontamination of Plutonium versus Cesium Because Site Restoration derived the costs of a cleanup following a plutonium dispersal, ISR determined that an appropriate multiplicative factor for the overall costs shown for plutonium in Table 2 is required to estimate the costs of the decontamination of cesium, which is the radionuclide of primary concern in a severe nuclear accident. Plutonium dispersion accidents involve explosions that create large-sized aerosols. Outlaw et. al. [17] showed that roughly half the aerosols produced by the explosive dispersion of plutonium are larger than 30 microns. For particle sizes larger than about 30 microns, gravitational settling is important and the particles tend to deposit on the soil near the site of the explosion. This limits the size of the zone to decontaminate, increases the mass loading (g/m2) on the surfaces to decontaminate, and limits particle mobility in the environment. Severe reactor accidents create relatively smaller-sized aerosols [18]. Nucleation of particles from supersaturated vapors is the more important source of aerosols in reactor accidents. Particle sizes of about 3.5 – 4 microns are typical for this process, while for core debris interactions with concrete they are typically around 1 micron. The smaller particles have a lower deposition velocity and they tend to disperse further downwind. Their concentration on the surface is typically lower and the size of the zone to decontaminate is larger. In addition, severe reactor accidents disperse a wide range of fission products (e.g. cesium, rubidium, and others) and possibly some actinides (e.g. plutonium). Soluble radionuclides such as cesium are more difficult to remove from porous surfaces than insoluble radionuclides such as plutonium. To illustrate the difference in the DF achievable for the two different radionuclides, we present the results obtained with the technique of strippable coatings. Sandia performed identical experiments attempting to remove both cesium and plutonium from concrete. The results from these tests were that the DF for cesium is 1.2 while the DF for plutonium is 5.8 [19]. This is consistent with CONDO decontamination factors, which for cesium is always less than or equal to plutonium [8] and confirms that cesium is more difficult to remove than plutonium. See Annex A for a more detailed discussion on the comparison of cesium and plutonium decontamination. Therefore, ISR has determined that the DF for cesium may be less than or equal to plutonium, but will never be greater. ISR considered two cases: (1) the cost of cesium decontamination equals that of plutonium; and (2) the cost of cesium decontamination is twice that of plutonium. Both cases assume that the cost of decontamination varies linearly with DF. The calculations for the nonfarm decontamination cost (CDNFRM) employ both cases for the costs determined by Site Restoration/Luna in Table 3 and Table 4 respectively.
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 18
Table 3: Suggested values of CDNFRM assuming cost (cesium) = cost (plutonium) (costs in 2005
USD)
Light Decontamination (DF=3) Heavy Decontamination (DF=15)
NYC metro Area Outside NYC Metro Area NYC metro Area Outside
NYC Metro Area Cost per km2 ($) from Site Restoration/Survey of Costs 5.39E+08 1.21E+08 2.18E+09 3.93E+08
Total area within 50-mi radius (km2) 356 19986 356 19986
Total cost for the area ($) 1.92E+11 2.42E+12 7.77E+11 7.85E+12 Total cost over 50-mi radius ($) 2.61E+12 8.63E+12
Population over 50-mi radius 19,228,712 19,228,712
CDNFRM Per capita cost ($, 2005) 135,927 448,889
Table 4: Suggested values of CDNFRM assuming cost (cesium) = 2 × cost (plutonium) (costs in
2005 USD)
Light Decontamination (DF=3) Heavy Decontamination (DF=15)
NYC metro Area Outside NYC Metro Area NYC metro Area Outside
NYC Metro Area Cost per km2 ($) from Site Restoration/Survey of Costs 1.08E+09 2.42E+08 4.37E+09 7.86E+08
Total area within 50-mi radius (km2) 356 19986 356 19986
Total cost for the area ($) 3.84E+11 4.84E+12 1.55E+12 1.57E+13 Total cost over 50-mi radius ($) 5.23E+12 1.73E+13
Population over 50-mi radius 19,228,712 19,228,712
CDNFRM Per capita cost ($, 2005) 271,854 897,778
The cost of light decontamination is between $136,000 and $272,000 per person, while the cost of heavy decontamination is between $449,000 and $898,000 per person. Approach B: Determining decontamination costs using current US data from Reichmuth US Homeland Security and EPA have recognized that cesium represents a major problem for radiological decontamination. As such they have commissioned studies such as: a) identification of the economic extent of the threat of a cesium-based radiological dispersal device (RDD) [14]; and b) determination of the efficacy of novel decontamination methods (e.g. strippable coatings as discussed above) on cesium-contaminated surfaces [20,21]. Reichmuth has conducted many studies evaluating the economic consequences of nuclear weapons and RDD effects on major metropolitan centers in the US and Canada [22]. Of particular relevance here is her work with RDDs involving cesium. While the mechanisms for dispersal differ between a reactor accident and an RDD event, the key factor in determining cost
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 19
is removal of cesium from porous substances, such as concrete, found in urban areas. The table below summarizes two of Reichmuth’s studies:
Table 5: Summary of the decontamination costs (2005 USD) based on Reichmuth's studies
Target (population density)
Cesium activity9
Effected Area
Total Cost of Restoration
Cost per person
NYC (10,000 persons/km2))
1 x 104 Ci (3.7 x 1014 Bq)
10 km2 $20 Billion $200,000
Vancouver (5000 persons/km2)
1 x 103 Ci (3.7 x 1013 Bq)
6 km2 $8 Billion $251,493
Reichmuth derived costs based on a dose rate limit for rehabitation. The data above is based on a “clean-up standard” of 500 mrem/y (5 mSv/y), which is similar to the habitability criterion used in the Entergy MACCS2 simulation: 2,000 mrem (20 mSv/y) in the first year and 500 mrem/y (5 mSv/y) for the following four years. To verify if these costs were derived for contamination levels that are relevant to the case of a severe accident at Indian Point, we compared the cesium activity concentrations for the three scenarios in the table below.
Table 6: Comparison of cesium ground concentrations
Scenario Cesium activity concentration
Reichmuth (NYC) 3.7 x 1013 Bq/km2
Reichmuth (Vancouver) 6.2 x 1012 Bq/km2
Entergy (NYC) (worst case) 1.0 x 1013 Bq/km2 The cesium activity concentrations and the decontamination costs per person reported by Reichmuth are similar to those determined in this report. The decontamination techniques proposed by Reichmuth included sandblasting the exterior and completely demolishing the affected buildings, both of which correspond to heavy decontamination. Therefore using Reichmuth’s results, the cost for nonfarm heavy decontamination (CDNFRM, DF=15) is between $200,000 and $252,000 per person. Approach C: Determining decontamination costs using CONDO The data and analysis technique reported in this section is derived from CONDO, a software tool for estimating the consequences of decontamination options developed by the NRPB in the UK [8]. CONDO is supported by a database that contains the effectiveness (i.e. DF), cost and required labour for the decontamination of cesium and plutonium using several techniques.
9 Activity is reported here in the traditional unit of radioactivity, Curies (Ci) and the SI unit, Becquerels (Bq). 1 Ci = 3.7 x 1010 Bq.
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 20
CONDO prescribes the following processes for a DF of approximately 3 for cesium:
� Soil and grass - grass cutting and collection, plant and shrub removal; � Trees/shrubs - hosing down; � Paved surfaces - fire hosing; � Buildings roofs - peelable coatings; � Building walls - peelable coatings; and � Building interiors - vacuum cleaning;
and prescribes the following processes for a DF of 10 or greater (where applicable) for cesium:
� Soil and grass - turf removal; � Trees/shrubs - felling and replacement; � Paved surfaces - sand blasting and waste collection; � Buildings roofs - sandblasting with waste collection; � Building walls - sandblasting with waste collection; and � Building interiors - replacement.
In general, decontamination costs are calculated by CONDO using the following methodology:
1. From the CONDO database, retrieve a cost per km2 of land for a specific area (e.g. paved surfaces) and technique (e.g. fire hosing) for both fragmented10 and continuous11 areas.
2. Multiply these costs by the surface fraction of the area depending on the type of population density (e.g. for semi-urban areas, the surface fraction of paved surfaces is 0.40);
3. Further multiply the costs by a factor to account for building heights or fractions of soil/grass covered by plants, trees, etc. (e.g. building interiors in a semi-urban area have a multiplicative factor of 11.55);
4. Further multiply the fragmented cost by the fragmented percentage and the continuous cost by the continuous percentage and add the two to obtain a total cost for the specific area and technique; and
5. Add the costs of all techniques to obtain a total cost of decontamination. The NYC metropolitan area is comprised of both urban and hyper-urban population densities. To account for this, ISR performed two calculations for the total cost of decontamination to determine an appropriate range of decontamination costs using the techniques listed above for light and heavy decontamination:
� Urban calculation: assumes the NYC metropolitan area has an urban population density of greater than 1,000 persons per km2, and everywhere else in the 50-mi radius area is semi-urban with a population density less than 1,000 persons per km2.
� Hyper-urban calculation: assumes NYC metropolitan area has a hyper-urban population density of about 10,000 persons per km2, and everywhere else in the 50-mi radius area
10 Fragmented areas are those that are not relatively uniform over a large area and thus require small-scale decontamination. 11 Continuous areas are those that are relatively uniform over a large area and thus large-scale decontamination may be used.
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 21
is urban with a population density between 1,000 and 10,000 persons per km2.
Annex C contains the details of these calculations; the final values are summarized in the tables below. The cost of light decontamination is between $19,000 and $30,000 per person, while the cost of heavy decontamination is between $90,000 and $140,000 per person. Table 7: Costs using CONDO values assuming the NYC metro area is classified as urban and the
area outside the NYC metro area is classified as semi-urban (costs in 2005 USD)
Light Decontamination
(DF=3) Heavy Decontamination
(DF=15)
NYC metro Area Outside NYC Metro Area NYC metro Area Outside
NYC Metro Area Cost per km2, ($) (Annex C) 2.78E+07 1.82E+07 1.31E+08 8.40E+07
Total area (km2) 356 19986 356 19986 Total cost for the area ($) 9.90E+09 3.64E+11 4.66E+10 1.68E+12 Total cost over 50-mi radius ($) 3.74E+11 1.73E+12
Population over 50-mi radius 19,228,712 19,228,712
CDNFRM Per capita cost ($, 2005) 19,431 89,734
Table 8: Costs using CONDO values assuming the NYC metro area is classified as hyper-urban
and the area outside the NYC metro area is classified as urban (costs in 2005 USD)
Light Decontamination
(DF=3) Heavy Decontamination
(DF=15)
NYC metro Area Outside NYC Metro Area NYC metro Area Outside
NYC Metro Area Cost per km2, ($) (Annex C) 5.61E+07 2.78E+07 2.64E+08 1.31E+08
Total area (km2) 356 19986 356 19986
Total cost for the area ($) 2.00E+10 5.56E+11 9.40E+10 2.62E+12 Total cost over 50-mi radius ($) 5.76E+11 2.71E+12
Population over 50-mi radius 19,228,712 19,228,712
CDNFRM Per capita cost ($, 2005) 29,933 140,430
Approach D: Determining decontamination costs using RISO The methodology followed for the CONDO/NRPB decontamination costs in the preceding section was repeated using the costs per km2 reported by the Riso National Laboratory (RISO) [9] as a starting point. ISR chose techniques from RISO that most closely correlated to those selected in the CONDO analysis; all of these techniques are used for light decontamination and therefore heavy decontamination is not considered for the RISO analysis.
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 22
The area-specific values (i.e. area and fragmented fractions) used for the CONDO analysis (Approach C) are also used here to account for semi-urban, urban and hyper-urban areas. The RISO cost rates are provided in Annex C; a summary of the results is shown in Table 9 and Table 10. ISR determined that the cost of light decontamination is between $36,000 and $59,000 per person.
Table 9: Costs using RISO values assuming the NYC metro area is classified as urban and the area outside the NYC metro area is classified as semi-urban (costs in 2005 USD)
Light Decontamination (DF=3)
NYC metro Area Outside NYC Metro Area
Cost per km2 ($) (Annex C) 5.46E+07 3.34E+07 Total area within 50-mi radius (km2) 356 19985 Total cost for the area ($) 1.94E+10 6.68E+11 Total cost over 50-mi radius ($) 6.87E+11 Population over 50-mi radius 19,228,712 CDNFRM Per capita cost ($, 2005) 35,726
Table 10: Costs using RISO values assuming the NYC metro area is classified as hyper-urban and
the area outside the NYC metro area is classified as urban (costs in 2005 USD)
Light Decontamination (DF=3)
NYC metro Area Outside NYC Metro Area
Cost per km2 ($)(Annex C) 1.17E+08 5.46E+07 Total area within 50-mi radius (km2) 356 19985 Total cost for the area ($) 4.17E+10 1.09E+12 Total cost over 50-mi radius ($) 1.13E+12 Population over 50-mi radius 19,228,712 CDNFRM Per capita cost ($,2005) 58,916
Summary of ISR’s decontamination costs A summary of decontamination costs obtained by ISR using Approaches A to D described above is shown in Table 11 and in Figure 4. The MACCS2 code restricts decontamination costs (CDNFRM) to a maximum of $100,000/person; therefore, ISR modified the source code to allow for the greater decontamination costs proposed here. The total economic cost, and therefore the OECR, reaches a maximum for decontamination costs around $200,000/person as shown in Figure 5. This is the threshold near which the cost
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 23
of decontaminating equals that of condemning and thus the total cost of condemnation, which is governed by the value of nonfarm wealth (VALWNF). If the cost of heavy decontamination is greater than $200,000/person, the resulting OECR is $581,000/year, which is 2.74 times the OECR calculated by Entergy ($212,000/year for IP2).
Table 11: Summary of ISR’s decontamination costs
Approach Reference or Source of Data CDNFRM ($/person, 2005)
Light Decontamination
Heavy Decontamination
- Entergy (Sample Problem A) 5,184 13,824
A Site Restoration/Luna 136,000 - 272,000 449,000 – 898,000
B Reichmuth Not available 200,000 – 252,000
C CONDO 19,000 - 30,000 90,000 – 140,000
D RISO 36,000 - 59,000 Not available
- Aggregate 19,000 – 272,000 90,000 – 898,000
$-
$100,000
$200,000
$300,000
$400,000
$500,000
$600,000
$700,000
$800,000
$900,000
$1,000,000
Entergy (Sample Problem A)
Chanin/Luna Reichmuth* CONDO RISO* Aggregate of the four sources
examined in this report
Per c
apita
non
-farm
dec
onta
min
atio
n co
st
Reference or source of data
Light decontamination Heavy decontamination
*There was no data available for light decontamination based on Reichmuth's studies or for heavy decontamination based on RISO's studies
Columns indicate the midpoint of the range represented by the high-low values
Figure 4: Graphical summary of decontamination costs (2005 USD) with ranges
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 24
0.00E+00
1.00E+05
2.00E+05
3.00E+05
4.00E+05
5.00E+05
6.00E+05
7.00E+05
0 50 100 150 200 250 300 350 400O
ECR
($/y
r)
CDNFRM, DF=15 ($ thousand/person)
Figure 5: OECR vs heavy decontamination cost (2005 USD)
4.2.4 Discussion of TIMDEC The decontamination times (TIMDEC) used by Entergy (i.e. 60 and 120 days for DF of 3 and 15 respectively) were taken directly from MACCS2 Sample Problem A. As stated in Section 3.2 these values were an assumption from NUREG-1150. To assess whether or not these durations are reasonable, they are compared to decontamination times of actual severe accidents. Large-scale decontamination of the area affected by the Chernobyl accident terminated four years after the accident [23]. This included the decontamination of tens of thousands of buildings in the most contaminated cities and villages of the former USSR. Since large-scale decontamination efforts have ceased, it is not possible to estimate the total duration of clean-up for the Chernobyl accident; however, it is reasonable to expect that the decontamination time would be at least four years of continuous time (i.e. 24 h/day) for a severe accident at Indian Point. Fukushima City is home to roughly 300,000 residents and sits 60 kilometers (35 miles) northwest of the Fukushima Daiichi nuclear plant. The decontamination efforts at Fukushima City took time to organize. After many trial decontaminations, the large-scale decontamination work may start in 2012, a full year after the accident [24],[25]. A trial decontamination of the Onami District in Fukushima City started on October 18, 2011 [26]. Originally, there was a plan to complete the decontamination of 367 households by the end of 2011, but decontamination is now expected to take much longer [27]. Many reports suggest that decontamination of the area around the nuclear plant could take decades [28] [29]. This suggests that an upper bound for the decontamination time could be approximately 30 years. ISR calculated the effect on cost of increasing decontamination times up to 30 years as shown in Figure 6. The MACCS2 code restricts the decontamination time input to a maximum of one year; therefore, ISR modified the source code to allow for greater decontamination times. The total economic cost, and therefore the OECR, increases with decontamination time since relocation costs increase. As the OECR increases due to decontamination time, it becomes more cost-effective to condemn infrastructure and buildings and therefore the OECR plateaus. Based on the data from Chernobyl and Fukushima, ISR believes that a reasonable range of decontamination times for the purpose of evaluation is between 4 and 30 years for heavy
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 25
decontamination and between 2 and 15 years for light decontamination12. For this range of possible decontamination times, ISR determined that the resulting OECR is 3.0 to 5.7 times greater than the OECR calculated by Entergy (2.12E+05 $/year for IP2).
0.00E+00
2.00E+05
4.00E+05
6.00E+05
8.00E+05
1.00E+06
1.20E+06
1.40E+06
0 5 10 15 20 25 30
OEC
R ($
/yr)
Decontamination (DF=15) time (years)Decontamination (DF=3) time is half as long
Figure 6: OECR (2005 USD) for decontamination times up to 30 years
4.3 Value of nonfarm wealth 4.3.1 Parameter definition Parameter name: VALWNF Entergy value: $208,838 per person, (2004 USD) The MACCS2 manual [1] defines VALWNF as:
VALWNF defines the value of the nonfarm wealth in the region. Nonfarm wealth includes all public and private property not associated with farming that would be unusable if the region was rendered either temporarily or permanently uninhabitable. This value should include the cost of land, buildings, infrastructure, and the cost of any non recoverable equipment or machinery.
4.3.2 Source of Entergy’s value Entergy’s report details their calculation of VALWNF [30], which, along with the value of farm wealth (VALWF) and the long-term exposure period (EXPTIM)13, was the only value not derived from Sample Problem A. Entergy’s report states that VALWNF cannot be readily calculated without recent data from the US Bureau of Economic Analysis, specifically data on “reproducible tangible wealth”. In the absence of this data, Entergy used SECPOP2000 [31] to generate the original VNFRM values, as originally tabulated in Entergy’s report [30]. In MACCS2, the user 12 The assumption from NUREG-1150 that the time for light decontamination is half as long as the time for heavy decontamination is adopted here. 13 EXPTIM is the duration of the long-term exposure period considered by CHRONC [1]. Entergy selected a value of 30 y, which is the EPA standard default [1].
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 26
must enter the value of nonfarm wealth in two input files: (1) the site data input file requires a value of nonfarm wealth (VNFRM) for each economic region or in the case of NY, each county; (2) the CHRONC input file requires a value of nonfarm wealth (VALWNF) for the entire region of interest (i.e. the 50-mile radius zone) that is an aggregate of the VNFRM values. ISR determined that the OECR output value is not sensitive to changes in the VNFRM values entered in the site data input, but is sensitive to the VALWNF value entered in the CHRONC input file. SECPOP2000 is a sector population, land fraction and economic estimation program capable of generating MACCS2 input data. Originally developed by the Environmental Protection Agency as SECPOP to calculate population estimates, Sandia National Labs was tasked to develop a new version, SECPOP2000, which would include the 2000 census population data and 1997 economic data14 [31]. The Entergy report concludes that the SECPOP2000-provided values were not entirely adequate because the database uses 1997 economic data. In an effort to better represent the economic worth of the area, Entergy obtained the Gross County Product (GCP) (or Gross Metro Product (GMP)) values per spatial sector. Entergy divided the GCP by the population to obtain a value of GCP/person. Entergy then added this GCP/person value to the original VNFRM value to obtain a final VNFRM value which it felt better represents the economic worth of that sector. Finally, Entergy weighted these values by population to obtain a final VALWNF value for use as the MACCS2 CHRONC input. 4.3.3 Discussion ISR concluded that Entergy’s calculations of VALWNF are outdated since the values obtained from SECPOP2000 were not scaled up from 1997 values to 2004 values. ISR scaled the SECPOP VNFRM values from 1997 to 2004 dollars by using the increase in GDP: $8,332 billion for 1997 and $11,853 billion for 2004 [32], resulting in an increase by a factor of 1.43. All of the SECPOP VNFRM values were increased by a factor of 1.43 to better represent economic worth in 2004 dollars. To follow through with Entergy’s methodology, the GCP is then added to obtain VNFRM for each county. The spreadsheet for the calculation is included in Annex D. The population-weighted sum of all counties within the 50-mile radius around Indian Point yields a VALWNF value of $284,189 per person, which is significantly higher than the value used by Entergy, which was $208,838. Using VALWNF of $284,189 per person would increase the final cost (OECR) by about 18%. All values in the determination of VALWNF are in 2004 USD for comparison to Entergy’s value, which is also in 2004 USD. 14 The SECPOP manual [31] states that its references for VNFRM (1997 economic data) include: 1998 and 1999 Statistical Abstract of the United States, US Dept. of Commerce, Economics and Statistics Admin., Bureau of the Census, 1999 County and City Data Book, US Dept. of Commerce, Bureau of the Census, Data User Services Div.
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 27
4.4 Property depreciation rate 4.4.1 Parameter definition Parameter name: DPRATE Entergy value: 0.2 per year The MACCS2 manual defines DPRATE as:
…the depreciation rate that applies to property improvements during a period of interdiction. This depreciation rate is intended to account for the loss of value of buildings and other structures resulting from a lack of habitation and maintenance.
In MACCS2, the loss of value of buildings and other structures is assumed to depreciate exponentially (decrease per unit time is a constant fraction of the remaining value). 4.4.2 Source of Entergy’s value There is no readily available data with respect to depreciation rates for untended property following a period of interdiction. As such, the existing value of 0.20 (or 20%) is taken from Appendix VI of Reactor Safety Study (WASH-1400). This value was assumed by the author to reflect the cost of property maintenance. 4.4.3 Discussion It should be noted that the authors of WASH-1400 acknowledged that this depreciation rate is the “only parameter in the equation (for the present value of property following a period of interdiction) whose value could be seriously in error”. However, ultimately this value was, to quote WASH-1400, “judged to be appropriate in view of the lack of maintenance during interdiction. Where property is maintained, depreciation is usually judged to be in the range of 3 to 5%.” No, more specific, reasoning or calculations were provided in WASH-1400. The values for a well maintained building quoted in WASH-1400 are consistent with the Modified Accelerated Cost Recovery System (MACRS) recommended in the Internal Revenue Service’s (IRS) Publication 946, How to Depreciate Property [33]. It appears reasonable that a building that is not maintained would depreciate more quickly than a building that is regularly maintained. The depreciation rate of 3 to 5% is therefore accepted as a lower bound for the depreciation rate, assuming that buildings are maintained during the interdiction. Since no other value of the depreciation rate for a building that is not maintained could be located, the value of DPRATE of 20% is accepted and the final cost (OECR) does not change.
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 28
4.5 Societal discount rate for property 4.5.1 Parameter definition Parameter name: DSRATE Entergy value: 0.12 per year (for 2005) The MACCS2 manual defines DSRATE as:
…the expected rate of return from land, buildings, equipment, etc. For example, the inflation-adjusted real mortgage rate for land and buildings could be used.
4.5.2 Source of Entergy’s value Entergy used the existing value of 0.12 (or 12%) as a representative value based on a number of measures of rate of return on debt or equity given in NUREG/CR-4551. This included the conventional mortgage rate from 1970-1986 and the return on equity of stock composites, the Standard and Poors (S&P) 500 and Fortune 500 companies. Ultimately, these values were all within 5 percentage points of 12%. 4.5.3 Discussion Again, one of the factors used to determine DSRATE in NUREG/CR-4551 was the conventional mortgage rate at the time. This is supplemented by the fact that WASH-1400 also used mortgage rate in its determination of DSRATE. Therefore, ISR used the 2005 conventional mortgage rate in the US as the updated value of DSRATE. From HSH Associates’ national mortgage statistics, ISR determined that a representative 2005 conventional long-term mortgage rate was between 5% and 7% [34]. Using this range of values for DSRATE, the final cost (OECR) would decrease by about 8% to 12%. 4.6 Per capita cost of long-term relocation 4.6.1 Parameter definition Parameter name: POPCST Entergy value: $8,640 per person (2005 USD) The MACCS2 manual defines POPCST as:
…the per capita removal cost for temporary or permanent relocation of population and businesses in a region rendered uninhabitable during the long-term phase time period. This cost is assessed if any of the following actions are required: decontamination alone, decontamination followed by interdiction, or condemnation. This value should be derived in a way that takes account of both personal and corporate income losses for a transitional period as well as moving expenses.
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 29
4.6.2 Source of Entergy’s value Entergy’s use of the value of $8,640 was based on a CPI-adjustment of a moving cost of $5,000 in 1986 found in NUREG/CR-4551 to 2005. The value was recommended based on a combination of:
� Scaling the Burke et. al. recommended moving cost of $4,000 (given in Economic Risks of Nuclear Power Reactor Accidents) from 1982 to 1986 to yield $4,500; and
� The moving cost based on the per capita income of 1986 of $14,600 to assume 140 days of lost wages, i.e. $5,600.
Based on these two values ($4,500 and $5,600), NUREG/CR-4551 used a value of $5,000. It should be noted that only lost wages were considered in these values with the argument that, with the majority of personal possessions being contaminated and hence undesirable, moving costs would be extremely low in comparison to lost wages. 4.6.3 Discussion ISR agrees that moving expenses will contribute very little to POPCST in comparison to lost wages. Therefore, ISR calculated the new value of POPCST considering two factors: (1) personal income per day; and (2) the number of days of lost wages. Based on the most recent data from the United States Census Bureau, the average per capita income in New York State is $27,877/year or $76/day (adjusted to 2005 USD using CPI) [35]. As stated above, the interdiction duration in NUREG/CR-4551 is 140 days; in WASH-1400, it is over 6 months. Based on current unemployment benefits policies, the regular duration of state benefits is 26 weeks while the current temporary extensions of benefits bring the total to a maximum of 93 weeks [36]. It should be noted that NY state benefits do not correspond to the full amount of loss of income (it corresponds to about 50% of wages). Nevertheless, the calculation of loss of income is based on the full average income. Therefore, based on personal income and unemployment benefit policies currently in place in NYS, the new value of POPCST is calculated to be between $10,640/person (for 140 days of lost wages) to $49,857/person (for 93 weeks of lost wages). Using the range of values, the final cost (OECR) would increase by 5% to 108%. 4.7 Nonfarm wealth improvements fraction 4.7.1 Parameter definition Parameter name: FRNFIM Entergy value: 0.8 (unitless)
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 30
The MACCS2 manual defines FRNFIM as:
…the fraction of nonfarm wealth in the region due to improvements. This value includes buildings and infrastructure such as roads and utilities, as well as any non-recoverable equipment or machinery.
4.7.2 Source of Entergy’s value Entergy’s value for FRNFIM was taken directly from Sample Problem A. It should be noted that the guidance provided in NUREG/CR-4551 states that this value be between 0.7 and 0.9. 4.7.3 Discussion A fraction of 0.8 is applicable to rural or semi-urban lands. With hyper-density urban centers such as NYC, more analysis is warranted. Recently a plot of land sold in NYC for $345 million for 3.4 acres [37]. This corresponds to $2.5B/km2. This plot of land was used to build the Time-Warner Centre, currently valued at (with infrastructures) about $2 Billion [38], or $143B/km2. So for a hyper-dense area, a FRNFIM value of close to unity would be justified. Since the geographic region for this study includes lower population densities, we recommend using FRNFIM of 0.9. This would increase the final cost (OECR) by about 3%. 4.8 Comparison of Entergy’s MACCS2 input values with those from other nuclear power plants in the US Table 12 provides a comparison of the MACCS2 input values used by Entergy with those of other nuclear power plant license applicants. For comparison purposes:
a. only values for parameters discussed in Sections 4.2 to 4.7 of this report (i.e. the most sensitive for cost determination) are provided; and
b. all cost-parameter values were CPI-adjusted (by ISR) to 2005 values (using the US Department of Labor, Bureau of Labor Statistics), the reference year used for the Indian Point analysis.
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 31
Table 12: Comparison of sensitive parameter values for IP with other US nuclear stations (costs in
2005 USD)
Station Year CDNFRM (DF=3)
CDNFRM (DF=15)
TIMDEC (DF=3/ DF=15)
VALWNF DPRATE DSRATE POPCST FRNFIM
Surry [1] * 1987 $5,158 $13,754 60 d/ 120 d $144,412 0.2 0.12 $8,596 0.8
Clinton [39] 2000 $5,172 $13,791 60 d/ 120 d $121,265 0.2 0.12 $8,620 0.8
North Anna [40] 2000 $3,981 $10,616 60 d/
120 d $160,148 0.2 0.12 $8,279 0.8
Arkansas [41] 2002 $5,191 $13,846 NA $136,903 0.2 0.12 $8,649 NA
Indian Point (Entergy) 2005 $5,184 $13,824 60 d/
120 d $208,838 0.2 0.12 $8,640 0.8
Levy [42] 2007 $5,415 $14,441 60 d/ 120 d $178,217 0.2 0.12 $9,025 NA
NA – not available in public documentation *MACCS2 Sample Problem A input parameter values For all the stations listed in Table 12, the decontamination costs (CDNFRM) and relocation costs (POPCST) were determined by scaling up the costs in MACCS2 Sample Problem A using the difference in CPI. The value of non-farm wealth (VALWNF) appears to be site-specific, likely resulting from location census data. The decontamination times (TIMDEC), depreciation rate (DPRATE), rate of return (DSRATE) and fraction of non-farm wealth due to improvements (FRNFIM) are all equivalent to the values used in the Surry analysis (i.e. Sample Problem A). Table 12 shows that no matter the specific location or attributes of the facility, the input values appear to be taken from Sample Problem A. As described in the preceding sections of Section 4, ISR has concluded that reliance on Sample Problem A values (with the exception of VALWNF) has led to a significant underestimation of the costs of a severe accident at Indian Point.
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 32
5. CONCLUSION ISR concludes that Entergy’s input parameters to the MACCS2 code underestimated the total economic cost of a severe nuclear accident primarily because of the direct use of MACCS2 Sample Problem A input values for the CHRONC module. The underestimation was mostly due to costs and times for decontamination that were unrealistic given current known decontamination data and the complexities of a urban to hyper-urban area such as that surrounding IP. ISR has derived more appropriate values and calculated the effect on the MACCS2 output. A summary of the ISR-proposed range of inputs and calculated OECR for all of the sensitive parameters is provided in Table 13. For all cases, only a single input parameter is varied, keeping all others as determined by Entergy. If all of the ISR proposed inputs are used, the OECR is determined to be between 4 and 7 times the currently calculated Entergy value.
Table 13: Summary of ISR proposed inputs and calculated OECRs (costs in 2005 USD)
Parameter Description Entergy's value
ISR's proposed input value
ISR's calculated OECR ($/yr) and
ratioa Minimum Maximum Minimum Maximum
CDNFRM (DF=3)
Per capita cost of nonfarm light decontamination
$5,184 $19,000 $272,000 4.21E+05
(1.99) 1.25E+06
(5.88) CDNFRM (DF=15)
Per capita cost of nonfarm heavy decontamination
$13,824 $90,000 $898,000
TIMDEC (DF=3)
Time required for light decontamination 60 d 2 y 15 y 6.44E+05
(3.04) 1.20E+06
(5.66) TIMDEC (DF=15)
Time required for heavy decontamination 120 d 4 y 30 y
VALWNF Per capita value of nonfarm wealth (2004 USD)
$208,838 $284,189 2.51E+05 (1.18)
DPRATE Depreciation rate 20% 20% 2.12E+05 (1.00)
DSRATE Societal discount rate for property 12% 5% 7% 1.87E+05
(0.88) 1.95E+05
(0.92)
POPCST Per capita cost of long-term relocation $8,640 $10,640 $49,857 2.23E+05
(1.05) 4.41E+05
(2.08)
FRNFIM Nonfarm wealth improvements fraction 80% 90% 2.19E+05
(1.03)
Using all of ISR’s proposed input values 9.07E+05 (4.28)
1.47E+06 (6.96)
Notes: a The ratio shown in brackets is the ratio of the ISR-calculated OECR to the Entergy-calculated OECR ($2.12E+05/yr).
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 33
6. REFERENCES
1. D. Chanin, et al. 1998. Code Manual for MACCS2: Volume 1, User’s Guide. NUREG/CR-6613. SAND97-0594. Vol. 1.
2. US Department of Energy, Office of Environment, Safety and Health. MACCS2 Computer Code Application Guidance for Documented Safety Analysis Final Report. June 2004.
3. EPA. Manual of Protective Action Guides and Protective Actions for Nuclear Incidents. 1992.
4. New York State Emergency Management Office. Protecting Public Health and Safety. New York State Radiological Emergency Plan 2010.
5. D. Chanin. The Development of MACCS2: Lessons Learned. 2005. Energy Facilities Contractor Operating Group Safety Analysis Working Group, Annual Workshop, April 29-May 5, 2005, Santa Fe, NM.
6. J.L. Sprung, et al. Evaluation of Severe Accident Risks: Quantification of Major Input Parameters. MACCS Input. Prepared by Sandia National Laboratories. NUREG/CR-4551 Vol. 2, Rev. 1, Part 7.
7. D. Chanin & W. Murfin. Site Restoration: Estimation of Attributable Costs From Plutonium-Dispersal Accidents. 1996. SAND96-0957.
8. CONDO: Software for estimating the consequences of decontamination options, Report for CONDO version 2.1, T Charnock, J Brown, AL Jones, W Oatway and M Morrey, NRPB-W43, May 2003.
9. J. Roed, K.G. Anderson, H. Prip. 1995. Practical Means for Decontamination 9 Years after a Nuclear Accident. RISO National Laboratory, Roskilde, Denmark. RISO-R-828(EN). December 1995.
10. NUREG-1150, Severe Accident Risks: An Assessment for Five US Nuclear Power Plants (Second Draft for Peer Review) – Summary Report (Volume 1), Appendices (Volume 2) June 1989.
11. L. Warming. Forced Decontamination of Fission Products Deposited on Urban Areas. A Literature Study. 1984. RISO-M-2472.
12. EB Farfan, et al. Assessment of 90Sr and 137Cs penetration into reinforced concrete (extent of "deepening") under natural atmospheric conditions. Health Phys. 2011 Sep;101(3):311-20.
13. R. Luna, H. Yoshimura & M. Soo Hoo. Survey of Costs Arising from Potential Radionuclide Scattering Events. 2008. WM2008 Conference, February 24-28, 2008, Phoenix AZ.
14. B. Reichmuth, S. Short, T. Wood, Economic Consequences of a Rad/Nuc Attack: Cleanup Standards Significantly Affect Risk, Pacific Northwest Laboratory, Working Together Conference, April 28, 2005, Boston, MA.
15. US Census Bureau 2000 Census. New York Census Data: Population & Housing Density. Retrieved from the internet on November 22nd, 2011. http://www.census-charts.com/Density/New_York.html
16. US Decennial Census. Census 2010 Data. http://www.census.gov/prod/www/abs/decennial/index.htm.
17. D. Outlaw, J.J. Cohen, J.F. Tinney, Risk Assessment for Emergency Planning Related to Nuclear Weapons Accidents, Science Applications International Corporation, SAIC-85-1849, DNA001-83-C-0375, September 1985.
18. Nuclear Energy Agency Committee on the Safety of Nuclear Installations, State-of-the-art Report on Nuclear Aerosols, NEA/CSNI/R(2009)5, 17-Dec-2009.
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 34
19. K. Holt. Testing for Radiological Decontamination Strippable Coating for Cellular
Bioengineering, Inc. (Cs-137, Pu-239, Am-241) 20. EPA. Removing Radiological Contamination from Concrete Using Strippable Coatings.
Retrieved from the internet on November 22nd, 2011. http://www.epa.gov/nhsrc/news/news102908.html
21. EPA. Evaluation of Five Technologies for the Mechanical Removal of Radiological Contamination from Concrete Surfaces. Retrieved from the internet on November 22nd, 2011. http://cfpub.epa.gov/si/si_public_record_report.cfm?address=nhsrc/&dirEntryId=234944
22. T. Cousins and B. Reichmuth, “Preliminary Analysis of the Economic Impact of Selected RDD Events in Canada”, presentation at the CRTI Summer Symposium 2007, Gatineau, Quebec, 11-14 June 2007 (CRTI 05-0043RD) – extracted from J. Medalia, “ “Dirty Bombs”: Technical Background, Attack Prevention and Response, Issues for Congress”, Congressional Research Service, R41890.
23. IAEA. Environmental Consequences of the Chernobyl Accident and their Remediation: Twenty Years of Experience. Report of the Chernobyl Forum Expert Group ‘Environment’. IAEA, 2006.
24. Decontamination effort starts in Fukushima exclusion zone, November 19, 2011, http://ajw.asahi.com/article/0311disaster/fukushima/AJ201111190038
25. Gov't nuclear cleanup work has to wait at least until late March, Mainichi Japan, December 12, 2011, http://mdn.mainichi.jp/mdnnews/news/20111212p2g00m0dm016000c.html
26. GSDF members start helping with Fukushima decontamination effort, AP Japan Today, Dec 08, 2011.http://www.japantoday.com/category/national/view/gsdf-members-start-helping-with-fukushima-decontamination-effort
27. Decontamination work at homes in Fukushima not going well as radiation lingers, Mainichi Japan) November 24, 2011 http://mdn.mainichi.jp/mdnnews/news/20111124p2a00m0na014000c.html
28. The Decontamination after the Incident in Fukushima Area Will Last for Decades, July 10, 2011, http://www.asitbreaks.com/the-decontamination-after-the-incident-in-fukushima-area-will-last-for-decades-5349.html
29. Rally to demand Fukushima decontamination, AFP October 31, 2011, http://www.nzherald.co.nz/environment/news/article.cfm?c_id=39&objectid=10762831
30. Enercon Services Inc. “Site Specific MACCS2 Input Data for Indian Point Energy Center”, Revision 1. December 1, 2009.
31. Sandia National Labs. 2003. SECPOP2000: Sector Population, Land Fraction, and Economic Estimation Program. NUREG/CR-6525, Rev. 1. Prepared by N.E. Bixler, et al. Prepared for Division of Risk Analysis and Applications, Office of Nuclear Regulatory Research, US Nuclear Regulatory Commission.
32. US Bureau of Economic Analysis. Retrieved from the internet on Dec 13, 2011, http://www.bea.gov/national/nipaweb/TableView.asp?SelectedTable=5&ViewSeries=NO&Java=no&Request3Place=N&3Place=N&FromView=YES&Freq=Year&FirstYear=1997&LastYear=2004&3Place=N&Update=Update&JavaBox=no
33. IRS. Figuring Depreciation Under MACRS. Retrieved from the internet on Nov. 24, 2011. http://www.irs.gov/publications/p946/ch04.html
34. HSH Associates. HSH’s National Monthly Mortgage Statistics: 2005. Retrieved from the internet on Dec. 14, 2011. http://www.hsh.com/natmo2005.html
35. US Census Bureau. New York Quick Facts. Retrieved from the internet on Dec. 11, 2011. http://quickfacts.census.gov/qfd/states/36000.html
36. New York State Benefit Extensions (Last updated October 11, 2011), http://www.labor.state.ny.us/ui/claimantinfo/importantnews.shtm#Benefit-Extensions
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 35
37. A. Haughwout, J. Orr & D. Bedoll. The Price of Land in the New York Metropolitan Area.
Current Issues in Economics and Finance. Second District Highlights. 2008. 38. S. Chan, R. Rivera. Property Values in New York Show Vibrancy. New York Times.
January 13, 2007. 39. G.A. Teagarden, Erin Engineering. Clinton CHRONC Input File. 2004. Retrieved from
http://pbadupws.nrc.gov/docs/ML0421/ML042180110.pdf 40. North Anna MACCS2 Output File for the AP1000 analysis. 2004. Retrieved from
http://pbadupws.nrc.gov/docs/ML0633/ML063320168.pdf 41. Arkansas Nuclear One – Unit 2 Applicant’s Environmental Report, Operating License
Renewal Stage. Attachment E: Severe Accident Mitigation Alternatives Analysis. 42. Levy Nuclear Plant Units 1 and 2 COL Application, Part 3: Environmental Report.
Chapter 7: Environmental Impacts of Postulated Accidents Involving Radioactive Materials.
43. Sandia National Labs. Technical Assistance in Support of the Indian Point Units 2 and 3 License Renewal Initial Assessment - Technical Review. Predecisional Draft. January 8, 2010. DPP-18-005.
44. S. Fetter, F. von Hippel. The Hazard from Plutonium Dispersal by Nuclear-warhead Accidents. Science & Global Security, Vol. 2, pp.21-41, 1990. Specific reference to US Atomic Energy Agency Proposed Final Environmental Impact Statement Liquid Metal Fast Breeder Reactor Program, Appendix II-G. WASH-1535, 1974.
45. Brookhaven National Laboratories. Decontamination Technologies Task 3. Urban Remediation and Response Project Prepared for New York City Department of Health and Mental Hygiene. June 30, 2009.
46. J.L. Dick & T.P. Baker. Operation Plumbbob. Monitoring and Decontamination Techniques for Plutonium Fallout on Large-Area Surfaces. Airforce Special Weapons Center WT-1512. March 3, 1967.
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 36
ANNEX A Response to US NRC Staff Evaluation (Appendix G) ISR response to “US NRC Staff Evaluation of Severe Accident Mitigation Alternatives for Indian Point Unit Nos. 2 and 3 in Support of License Renewal Application Review” (Appendix G) Background As part of its review of Entergy’s application for renewal of the Indian Point (IP) reactor units, New York State Attorney General (NYAG) contracted ISR to review specific comments in the above-referenced document. This is done below in a format of repeating the NRC comments verbatim, followed by ISR’s response to each question or statement. The NRC report excerpts are listed in the order that they appear in Appendix G. NRC Comments and ISR response:
1) Page G-23, lines 37 – 43 Sandia noted that the primary constituent in weapons grade plutonium, Pu239, is an alpha emitter, whereas the primary contaminant from an NPP accident, Cs137, is a gamma emitter. As such, Pu239 is more difficult and expensive to characterize and verify in the field than gamma emitters like Cs137. Furthermore, Pu239 is primarily an inhalation hazard with half-life of 24,000 years, whereas Cs137 is primarily an external health hazard with half-life of about 30 years. The need for evacuating the public is much greater with plutonium because if inhaled, the health consequences can be severe.
Public evacuation and the associated costs are not part of the assessment. The SAMA analysis includes the costs of longer-term dose reduction measures such as permanent relocation and decontamination. It is the cost of these measures that should be assessed for plutonium and cesium. From above, NRC/Sandia is implying that characterization is a major part of the costs of decontamination. The main cost of decontamination is not radionuclide detection/characterization, but decontamination, removal, transport and storage of waste and/or building demolition. The cost fraction of urban characterization of plutonium has been calculated by Chanin in Site Restoration [7] as less that 1 % of the total and is depicted in the graph below (see Figure 7). (Note that in the graph, characterization is included in the “other costs” category).
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 37
Figure 7: Composition of decontamination costs for plutonium [7]
2) Page G-24, lines 7-11
Sandia considered the decontamination activities described in the Site Restoration study together with the differences in health hazards posed by Pu239 versus Cs137, and concluded that the activities required to support clean-up of moderate plutonium contamination align more closely with clean-up activities for heavy cesium contamination. Sandia performed the comparison of decontamination cost values on this basis.
NRC is quoting, almost verbatim, from the Sandia report [43], which uses the following argument to arrive at the conclusion above:
For decontamination of 137Cs, less costly options are available rather than complete destruction and removal of infrastructure. Road surfaces contaminated with cesium could be planed or scraped just a few millimeters, using commercial equipment, to significantly reduce the radiation dose and could be sealed with asphalt. If needed a pavement overlay could be added, which is considerably cheaper than complete destruction. Such actions would reduce the dose to a low enough level to assure protection of public health and safety. 137Cs does present some risk from resuspension and inhalation, but because it is primarily a dose hazard, reducing the dose through scraping and placing a cover over the remaining contamination may be expected to be sufficient. The life expectancy of an asphalt roadway is more than 30 years, providing time for the remaining 137Cs to decay.
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 38
A pavement overlay could also be used to encapsulate the 239Pu to prevent disturbance or migration. However, anytime long-lived contamination is left in place, even if encapsulated, loss of control, which would result in a health hazard to the public, must be considered. It is reasonable to consider that control may be maintained for the life of pavement surface (i.e., 30 years); however, it is not practical to assume that control could be maintained for the thousands of years the 239Pu would be present. Given the long term health hazard present from the 239Pu, it is expected that decontamination efforts would be focused on complete removal, which is consistent with the Site Restoration study decontamination description for heavy contamination. Considering the decontamination activities described above, the activities required to support decontamination of moderate plutonium contamination align more closely with decontamination activities for heavy decontamination of cesium.
The Sandia report [43] relies heavily on the cost of decontamination of a road to estimate the costs of decontamination of buildings, houses, soil and vegetation in urban areas. A review of the literature does not support this extrapolation.
A severe reactor accident will result in contamination containing fission products (cesium and other radionuclides) and actinides (plutonium). The choice of decontamination techniques will be based on an analysis of the exposure pathways for all these radionuclides. In some locations, the hazard from plutonium could be the driving factor while in other places the hazard from cesium could dominate. Any effective decontamination technique will result in some removal of cesium, plutonium and any other radionuclides. Therefore, using the example of road decontamination presented by Sandia, if complete removal of the road is justified for plutonium, it will also result in the full decontamination of cesium. The concern for plutonium resuspension is due to the fact that it initially does not bind to surfaces because plutonium oxide it is not readily soluble. This property also makes it initially easy to remove. Over time plutonium settles into the surface and resuspension becomes less significant. The airborne concentration after the passage of the plume relative to the concentration on the ground can be characterized by a resuspension coefficient )(tK . This resuspension coefficient varies with time as plutonium particles sink into the soil or are washed away. Reference [44] suggests the following relation for the plutonium resuspension coefficient. K t K e Kat( ) � ��
�0 where K0
310� � �cm 1 K�
� �� 10 7 cm 1 a � 5 year -1
After 30 years, the resuspension coefficient becomes negligible and the long term health hazard from plutonium is much less than for other radionuclides.
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 39
If long-term control is disregarded and scraping and overlay is justified for plutonium decontamination, then there would be an equal if not greater percentage of plutonium removed compared to cesium. This is because unlike plutonium, cesium is soluble and can penetrate porous surfaces, making it more difficult to decontaminate15. In general, a greater depth of scraping would be required to achieve the same decontamination factor for cesium as for plutonium. Regardless of the depth of scraping, the ultimate cost of decontamination is still the same for both radionuclides since a single technique is used. If long-term control and maintenance of material, infrastructure, property, etc. is of primary concern as Sandia suggests for roads, complete demolition and removal will in most cases be desired as the decontamination strategy for all areas (e.g. roads, buildings, grass, trees, etc.). Only in this case is plutonium (and other alpha emitters) the driving factor for decontamination; but demolition and removal of an entire area is a form of condemnation, not decontamination, and represents the most expensive mitigative option. If immediate decontamination and re-habitation is preferred, despite long-term control and maintenance concerns, heavy plutonium decontamination activities are likely to align with medium cesium decontamination activities due to cesium’s solubility as discussed above. This is the more realistic scenario for decontamination since condemnation of property such as that in and around NYC would be the least preferred option. As alluded to, this discussion must be extended to include the decontamination of buildings, not just roads, as this will be the highest cost contributor. Buildings occupy greater than 50% of urban area and cost approximately 20 times more than roads to decontaminate due to interior and exterior surface areas. Therefore NRC/Sandia’s conclusion that “…the activities required to support clean-up of moderate plutonium contamination align more closely with clean-up activities for heavy cesium contamination” is simply misleading since:
� only a single activity (e.g. not scraping and removal, but scraping or removal) will be selected for decontamination of a given surface (e.g. roads) following a nuclear accident; and
� long-term control is likely to be a minor concern relative to condemning property and buildings.
Using debatable analysis of the cost of road clean-up leads to the wrong conclusion.
3) Page G-24, lines 20 – 26
The Site Restoration study (Table 6-2) provides an estimated cost of $178.4 million/km2 for clean-up of moderate plutonium contamination in urban areas, of $14,900 per person when expressed on a per capita basis for New York City. In contrast, a cost of $13,824 per person was used in Entergy’s MACCS2 analysis
15 ISR has examined many references [8,21,45,46] that confirm this assertion and state that the decontamination factor for cesium is equal to or less than that for plutonium for all decontamination techniques.
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 40
for decontamination of heavy cesium contamination. Thus, the decontamination cost of the Site Restoration study ($14,900 per person) is not significantly different than the value used by Entergy in the SAMA analysis ($13,824 per person).
One cannot simply divide the decontamination cost per km2 by population density – but rather building density must be taken into account [13]. Luna proposed that the ratio of population densities of New York City to Albuquerque be used to approximate this. Entergy has questioned this assumption. Accordingly, ISR used census values of building densities in both cities to arrive at a multiplicative ratio of about 9 for residential and commercial land. As shown in Approach A in Section 4.2.3, this leads to a cost of heavy decontamination between $449,000 and $898,000 per person. If this correction is not made, then the result is that a cleanup of a contaminated area in Albuquerque would be the same as a contaminated area of equal size in New York City.
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 41
ANNEX B MACCS2 User Input Sensitivity Analysis A listing of the MACCS2 CHRONC input parameters, their ranges, units and Entergy values are provided in Table 14. The results of the ISR sensitivity analysis on all of the quantitative parameters are provided in Table 15. The OECR calculated in Table 15 is obtained by adding the total offsite economic cost for each of the eight release categories16 after weighting them by their respective frequencies:
��
�8
1iiitotal CfOECR
where fi is the frequency (i.e. probability) of release category i and Ci is the total economic cost of release category i.
16 The eight release categories are pre-defined releases of radionuclides which vary by several parameters such as release delay, duration and heat. The probability of each release category is calculated using probabilistic safety analyses, which considers the possible failures of structures, systems and components of the nuclear power plant.
Rev
iew
of I
ndia
n P
oint
Sev
ere
Acc
iden
t IS
R R
epor
t 130
14-0
1-01
O
ff S
ite C
onse
quen
ce A
naly
sis
P
age
42
Tabl
e 14
: Ent
ergy
’s C
HR
ON
C in
put p
aram
eter
s (a
ll in
put c
ost v
alue
s ar
e in
200
5 U
SD)
Fiel
d D
escr
iptio
n M
ACC
S2
Ran
ge
min
MAC
CS2
R
ange
m
ax
Uni
ts
Ente
rgy
Inpu
t va
lue
1
Ente
rgy
Inpu
t va
lue
2
Ente
rgy
Inpu
t va
lue
3 C
DFR
M
Farm
land
Dec
onta
min
atio
n C
ost
1 1.
00E+
05
dolla
rs/h
ecta
re
972
2160
CD
NFR
M
Non
farm
Dec
onta
min
atio
n C
ost
1 1.
00E+
05
dolla
rs/p
erso
n 51
84
1382
4
DLB
CST
D
econ
tam
inat
ion
Wor
ker L
abor
Cos
t
1
1.00
E+06
do
llars
/man
-yea
r 60
480
DO
SE
LON
G
CO
MID
A2
Mod
el L
ong-
Term
Dos
e Li
mit
0 1.
00E+
10
Sv
0.00
5 0.
015
D
OS
EM
ILK
C
OM
IDA
2 M
odel
Firs
t-Yea
r Milk
Dos
e Li
mit
0
1.00
E+10
Sv
0.
025
0.07
5
DO
SEO
THR
C
OM
IDA
2 M
odel
Firs
t-Yea
r Non
milk
Dos
e Li
mit
0
1.00
E+10
Sv
0.
025
0.07
5
DP
FRC
T Fa
rm P
rodu
ctio
n D
airy
Fra
ctio
n
0
1 un
itles
s 0.
198
DP
RAT
E
Pro
perty
Dep
reci
atio
n R
ate
0 1
per y
ear
0.2
DS
CR
LT
Long
-Ter
m P
hase
Dos
e C
riter
ion
1.00
E-20
1.
00E+
05
Sv
0.04
D
SC
RTI
In
term
edia
te-P
hase
Dos
e C
riter
ion
0 1.
00E+
05
Sv
1.00
E+05
D
SR
ATE
S
ocie
tal D
isco
unt R
ate
for P
rope
rty
0
1 pe
r yea
r 0.
12
DS
RFC
T D
econ
tam
inat
ion
Fact
ors
1.
01
100
unitl
ess
3 15
DU
R_I
NTP
HAS
D
urat
ion
of In
term
edia
te-P
hase
Per
iod
0 3.
15E+
07
seco
nds
0
EV
ACST
E
mer
genc
y-P
hase
Cos
t of
Eva
cuat
ion/
Rel
ocat
ion
0 10
00
dolla
rs/p
erso
n-da
y 46
.7
EXPT
IM
Max
imum
Exp
osur
e Ti
me
for C
HR
ON
C
Cal
cula
tions
0 1.
00E+
10
seco
nds
9.45
E+08
FRA
CLD
Fr
actio
n of
Site
Are
a th
at is
Lan
d
1.00
E-06
1
unitl
ess
0.95
FR
CFR
M
Frac
tion
of S
ite L
and
Use
d fo
r Far
min
g
1.00
E-06
1
unitl
ess
0.38
2
FR
FDL
Farm
Lab
or C
ost F
ract
ion
0 1
unitl
ess
0.3
0.35
FRFI
M
Farm
Wea
lth Im
prov
emen
ts F
ract
ion
0 1
unitl
ess
0.25
FR
MP
RD
A
vera
ge A
nnua
l Far
m P
rodu
ctio
n V
alue
0 1.
00E+
05
dolla
rs/h
ecta
re
371
FRN
FDL
Non
farm
Lab
or C
ost F
ract
ion
0 1
unitl
ess
0.7
0.5
FR
NFI
M
Non
farm
Wea
lth Im
prov
emen
ts F
ract
ion
0 1
unitl
ess
0.8
Rev
iew
of I
ndia
n P
oint
Sev
ere
Acc
iden
t IS
R R
epor
t 130
14-0
1-01
O
ff S
ite C
onse
quen
ce A
naly
sis
P
age
43
Fiel
d D
escr
iptio
n M
ACC
S2
Ran
ge
min
MAC
CS2
R
ange
m
ax
Uni
ts
Ente
rgy
Inpu
t va
lue
1
Ente
rgy
Inpu
t va
lue
2
Ente
rgy
Inpu
t va
lue
3 G
WC
OEF
Lo
ng-T
erm
Gro
unds
hine
Coe
ffici
ents
1.
00E-
20
1 un
itles
s 0.
5 0.
5
KSW
TCH
D
iagn
ostic
Out
put O
ptio
n S
witc
h
0
1 in
tege
r 0
LVLD
EC
N
umbe
r of D
econ
tam
inat
ion
Stra
tegi
es
1
3 in
tege
r 2
NG
WTR
M
Num
ber o
f Ter
ms
in G
roun
dshi
ne
Wea
ther
ing
Equa
tion
1
2 in
tege
r 2
NR
WTR
M
Num
ber o
f Ter
ms
in R
esus
pens
ion
Wea
ther
ing
Equa
tion
1
3 in
tege
r 3
NU
MW
PI
Num
ber o
f Rad
ionu
clid
es fo
r Wat
er
Inge
stio
n
1 10
in
tege
r 4
POPC
ST
Per
Cap
ita C
ost o
f Lon
g-Te
rm R
eloc
atio
n
1.00
E-06
1.
00E+
06
dolla
rs/p
erso
n 86
40
REL
CST
R
eloc
atio
n C
ost p
er P
erso
n-D
ay
0 10
00
dolla
rs/p
erso
n-da
y 46
.7
RW
CO
EF
Long
-Ter
m R
esus
pens
ion
Fact
or
Coe
ffici
ents
1.00
E-20
1
per m
eter
1.
00E-
05
1.00
E-07
1.
00E-
09
TFW
KF
Farm
Wor
ker's
Wor
k Fr
actio
n
0
1 un
itles
s 0.
1 0.
33
TF
WKN
F N
onfa
rm W
orke
r’s W
ork
Frac
tion
0 1
unitl
ess
0.33
0.
33
TG
WH
LF
Gro
unds
hine
Wea
ther
ing
Hal
f-Liv
es
1.00
E-06
1.
00E+
12
seco
nds
1.60
E+07
2.
80E+
09
TI
MD
EC
Dec
onta
min
atio
n Ti
mes
1.
00E-
06
3.15
E+07
se
cond
s 5.
18E
+06
1.04
E+07
TMPA
CT
Tim
e Ac
tion
Per
iod
End
s
TM
IPN
D
1.00
E+10
se
cond
s 1.
58E+
08
TRW
HLF
R
esus
pens
ion
Wea
ther
ing
Hal
f-Liv
es
1.00
E-06
1.
00E+
12
seco
nds
1.60
E+07
1.
60E+
08
1.60
E+09
VA
LWF
Val
ue o
f Far
m W
ealth
(per
Hec
tare
)
1.00
E-06
1.
00E+
06
dolla
rs/h
ecta
re
5007
1 (2
004
US
D)
VALW
NF
Val
ue o
f Non
farm
Wea
lth (p
er C
apita
)
1.00
E-06
1.
00E+
06
dolla
rs/p
erso
n 20
8838
(2
004
US
D)
WIN
GF
Wat
er T
rans
fer F
ract
ion
to H
uman
s
0
1 un
itles
s 5.
00E-
06
WSH
FRI
Initi
al W
ater
Was
hoff
Frac
tion
0 1
unitl
ess
0.01
0.
005
W
SHR
TA
Ann
ual W
ater
Was
hoff
Frac
tion
0 1
/yea
r 0.
004
0.00
1
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 44
Table 15: Input sensitivity results
Input parameter changed Entergy’s Value
New Value (Entergy plus 10%)
Total OECR ($/yr) Sensitivity
- - - 2.12E+05 -
EVACST 46.7 51.4 2.12E+05 0%
RELCST 46.7 51.4 2.12E+05 0%
TIMDEC (DF1) 5.18E+06 5.70E+06 2.15E+05 1%
TIMDEC (DF2) 1.0368E+07 1.14E+07 2.15E+05 1%
VALWF 50071 5.51E+04 2.12E+05 0%
VALWNF 208838 2.30E+05 2.23E+05 5%
EXPTIM 9.45E+08 1.04E+09 2.12E+05 0%
CDFRM (DF1) 972 1069.2 2.12E+05 0%
CDFRM (DF2) 2160 2376 2.12E+05 0%
CDNFRM (DF1) 5184 5702.4 2.14E+05 1%
CDNFRM (DF2) 13824 15206.4 2.15E+05 2%
CDNFRM (DF1 AND DF2) 5184, 13824 5702.4, 15206.4 2.17E+05 2%
FRFDL (DF1) 0.3 0.33 2.12E+05 0%
FRNFDL (DF1) 0.7 0.77 2.12E+05 0%
TFWKF (DF1) 0.1 0.11 2.12E+05 0%
TFWKNF (DF1 and DF2) 0.33 0.36 2.12E+05 0%
DLBCST 60480 66500 2.12E+05 0%
DPRATE 0.2 0.22 2.17E+05 2%
DSRATE 0.12 0.14 2.19E+05 3%
POPCST 8640 9500 2.17E+05 2%
VALWF 50071 55000 2.12E+05 0%
FRFIM 0.25 0.28 2.12E+05 0%
FRNFIM 0.8 0.88 2.18E+05 3%
DSCRLT 0.04 0.044 2.00E+05 -6%
DOSELONG 0.005 0.0055 2.12E+05 0%
DOSEMILK 0.025 0.028 2.12E+05 0%
DOSEOTHR 0.025 0.028 2.12E+05 0%
TMPACT 1.58E+08 1.74E+08 2.20E+05 4%
GWHLF (all groundshine terms) 0.5 0.55 2.29E+05 8%
TGWHLF (all groundshine terms) 1.60E+07 1.76E+07 2.18E+05 3%
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 45
Input parameter changed Entergy’s Value
New Value (Entergy plus 10%)
Total OECR ($/yr) Sensitivity
RWCOEF (all resuspension terms) 1.00E-07 1.10E-05 2.13E+05 0%
TRWHLF (all resuspension terms) 1.60E+08 1.76E+07 2.13E+05 0%
WSHFRI (all waterborne radionuclides) 0.01 0.011 2.12E+05 0%
WSHTRA (all waterborne radionuclides) 0.004 0.0044 2.12E+05 0%
WINGF (all waterborne radionuclides) 5.00E-06 5.50E-06 2.12E+05 0%
Figure 8: Sensitivity plot
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 46
ANNEX C CDNFRM Calculation This annex includes ISR’s calculation of CDNRFM using CONDO and RISO values, in tabular form. ISR took all values from CONDO [8] or RISO [9]. Costs in CONDO were quoted in 1996 pounds (GBP); ISR assumed a currency exchange rate of 1.6 USD per GBP. Costs reported by RISO were quoted in 1995 Euros or ECUs, which at the time was approximately equivalent to USDs, and then CPI-adjusted to 2011 costs. Finally, all costs were CPI-adjusted to 2005 costs for comparison to Entergy’s decontamination costs. CPI adjustments were based on the CPI values given in the table below. For soil/grass areas, ISR assumed that plants and shrubs occupied 30% of the area, trees occupied 20% of the area and soil and grass occupied 50% of the area. This assumption was made for all population densities (i.e. semi-urban, urban and hyper-urban). Since the decontamination of soil/grass areas is less cost and labour intensive than that of buildings and paved areas, the effect of any errors in these assumptions is not significant.
Table 16: Annual average CPI values
Year Average CPI Year Average CPI
1986 109.6 2001 177.1
1987 113.6 2002 179.9
1988 118.3 2003 184.0
1989 124.0 2004 188.9
1990 130.7 2005 195.3
1991 136.2 2006 201.6
1992 140.3 2007 207.342
1993 144.5 2008 215.303
1994 148.2 2009 214.537
1995 152.4 2010 218.056
1996 156.9 2011 224.550
1997 160.5
1998 163.0
1999 166.6
2000 172.2 Source: US Department of Labor, Bureau of Labor Statistics, Consumer Price Index – All Urban Consumers (CPI-U), US City Average. Extracted from ftp://ftp.bls.gov/pub/special.requests/cpi/cpiai.txt on November 10, 2011.
Rev
iew
of I
ndia
n P
oint
Sev
ere
Acc
iden
t IS
R R
epor
t 130
14-0
1-01
O
ff S
ite C
onse
quen
ce A
naly
sis
P
age
47
Ta
ble
17: D
econ
tam
inat
ion
in s
emi-u
rban
are
as -
build
ing
frac
tions
Surf
ace
Low
sh
ield
ed
build
ing
frac
tion
of
land
are
a
Low
pr
opor
tion
Wei
ghte
d va
lue
Med
ium
sh
ield
ed
build
ing
frac
tion
of
land
are
a
Med
pr
opor
tion
Wei
ghte
d va
lue
Hig
h sh
ield
ed
build
ing
frac
tion
of
land
are
a
Hig
h pr
opor
tion
Wei
ghte
d va
lue
Tota
l w
eigh
ted
area
Ext
erna
l w
alls
1.
7 0.
05
0.08
5 1.
6 0.
8 1.
28
5.5
0.15
0.
825
2.19
Roo
fs
1 0.
05
0.05
1
0.8
0.8
1 0.
15
0.15
1
Inte
rnal
w
alls
8.
86
0.05
0.
443
8.71
0.
8 6.
968
27.6
0.
15
4.14
11
.551
Ta
ble
18: D
econ
tam
inat
ion
in u
rban
are
as -
build
ing
frac
tions
Ext
erna
l w
alls
1.
7 0.
05
0.08
5 1.
6 0.
6 0.
96
5.5
0.35
1.
925
2.97
Roo
fs
1 0.
05
0.05
1
0.6
0.6
1 0.
35
0.35
1
Inte
rnal
w
alls
8.
86
0.05
0.
443
8.71
0.
6 5.
226
27.6
0.
35
9.66
15
.329
Ta
ble
19: D
econ
tam
inat
ion
in h
yper
-urb
an a
reas
- bu
ildin
g fr
actio
ns17
Ext
erna
l w
alls
1.
7 0.
05
0.08
5 1.
6 0.
15
0.24
5.
5 0.
8 4.
4 4.
725
Roo
fs
1 0.
05
0.05
1
0.15
0.
15
1 0.
8 0.
8 1
Inte
rnal
w
alls
8.
86
0.05
0.
443
8.71
0.
15
1.30
65
27.6
0.
8 22
.08
23.8
295
17 T
he p
ropo
rtion
frac
tions
(low
, med
ium
and
hig
h) s
how
n he
re fo
r hyp
er-u
rban
are
as w
ere
deriv
ed b
y IS
R u
sing
ext
rapo
latio
n fro
m u
rban
val
ues
Rev
iew
of I
ndia
n P
oint
Sev
ere
Acc
iden
t IS
R R
epor
t 130
14-0
1-01
O
ff S
ite C
onse
quen
ce A
naly
sis
P
age
48
Ta
ble
20: L
ight
dec
onta
min
atio
n in
sem
i-urb
an a
reas
(CO
ND
O)
Are
a Pr
oces
s D
F Fr
agm
ente
d C
ost (
$/km
2 ) C
ontin
uous
C
ost (
$/km
2 )
Surf
ace
frac
tion
(Sem
i-U
rban
)
Add
ition
al
frac
tion
to
sepa
rate
su
rfac
e fr
actio
n
Frag
men
ted
frac
tion
Fina
l Fr
agm
ente
d
Cos
t ($/
km2)
Fina
l C
ontin
uous
C
ost (
$/km
2)
Roa
ds -
pave
d ar
eas
Fire
hos
ing
or h
igh
pres
sure
ho
sing
3 to
5 7.
68E+
04
1.39
E+05
0.
40
1.00
0.
5 1.
54E+
04
2.78
E+04
Build
ing
- roo
fs
Peel
able
co
atin
gs
5 9.
12E+
06
4.16
E+06
0.
40
1.00
0.
75
2.74
E+06
4.
16E+
05
Build
ing
- wal
ls
Peel
able
co
atin
gs
5 4.
32E+
06
4.16
E+06
0.
40
2.19
0.
75
2.84
E+06
9.
11E+
05
Build
ing
- in
terio
rs
Vacu
umin
g,
clea
ning
an
d w
ashi
ng
5 1.
60E+
06
1.60
E+06
0.
40
11.5
5 0.
75
5.54
E+06
1.
85E+
06
Pla
nts
and
shru
bs
Rem
oval
1.
4 6.
88E+
05
9.28
E+04
0.
20
0.30
0.
75
3.10
E+04
1.
39E+
03
Tree
s Fe
lling
and
rem
oval
10
4.
16E+
06
4.16
E+06
0.
20
0.20
0.
75
1.25
E+05
4.
16E+
04
Soil
and
gras
s C
uttin
g an
d co
llect
ion
3 1.
92E+
05
1.41
E+04
0.
20
0.50
0.
75
1.44
E+04
3.
52E+
02
To
tal
(199
6 U
SD)
1.13
E+07
3.
25E+
06
1.46
E+07
To
tal
(200
5 U
SD)
1.82
E+07
Rev
iew
of I
ndia
n P
oint
Sev
ere
Acc
iden
t IS
R R
epor
t 130
14-0
1-01
O
ff S
ite C
onse
quen
ce A
naly
sis
P
age
49
Tabl
e 21
: Hea
vy d
econ
tam
inat
ion
in s
emi-u
rban
are
as (C
ON
DO
)
Are
a Pr
oces
s D
F Fr
agm
ente
d
Cos
t ($/
km2)
C
ontin
uous
C
ost (
$/km
2)
Surf
ace
frac
tion
(Sem
i-U
rban
)
Add
ition
al
frac
tion
to
sepa
rate
su
rfac
e fr
actio
n
Frag
men
ted
frac
tion
Fina
l Fr
agm
ente
d C
ost (
$/km
2)
Fina
l C
ontin
uous
C
ost (
$/km
2)
Roa
ds -
pave
d ar
eas
Rem
oval
and
re
plac
emen
t 50
3.
84E+
07
1.34
E+07
0.
40
1.00
0.
5 7.
68E+
06
2.69
E+06
Build
ing
- roo
fs
San
dbla
stin
g 10
3.
20E+
06
4.32
E+06
0.
40
1.00
0.
75
9.60
E+05
4.
32E+
05
Build
ing
- wal
ls
San
dbla
stin
g 10
3.
20E+
06
4.32
E+06
0.
40
2.19
0.
75
2.10
E+06
9.
46E+
05
Build
ing
- in
terio
rs
Vacu
umin
g,
clea
ning
and
w
ashi
ng
5 1.
14E+
07
1.14
E+07
0.
40
11.5
5 0.
75
3.94
E+07
1.
31E+
07
Pla
nts
and
shru
bs
Rem
oval
1.
4 6.
88E+
05
9.28
E+04
0.
20
0.30
0.
75
8.64
E+04
2.
88E+
04
Tree
s Fe
lling
and
rem
oval
10
4.
16E+
06
4.16
E+06
0.
20
0.20
0.
75
1.25
E+05
4.
16E+
04
Soil
and
gras
s Tu
rf re
mov
al
10
8.80
E+04
8.
96E+
04
0.20
0.
50
0.75
6.
60E+
03
2.24
E+03
To
tal
(199
6 U
SD)
5.03
E+07
1.
72E+
07
6.
75E+
07
To
tal
(200
5 U
SD)
8.40
E+07
Rev
iew
of I
ndia
n P
oint
Sev
ere
Acc
iden
t IS
R R
epor
t 130
14-0
1-01
O
ff S
ite C
onse
quen
ce A
naly
sis
P
age
50
Ta
ble
22: L
ight
dec
onta
min
atio
n in
urb
an a
reas
(CO
ND
O)
Are
a Pr
oces
s D
F Fr
agm
ente
d C
ost (
$/km
2)
Con
tinuo
us
Cos
t ($/
km2)
Surf
ace
frac
tion
(Urb
an)
Add
ition
al
frac
tion
to
sepa
rate
su
rfac
e fr
actio
n
Frag
men
ted
frac
tion
Fina
l Fr
agm
ente
d
Cos
t ($/
km2)
Fina
l C
ontin
uous
C
ost (
$/km
2)
Roa
ds -
pave
d ar
eas
Fire
hos
ing
or h
igh
pres
sure
ho
sing
3 to
5 7.
68E+
04
1.39
E+05
0.
40
1.00
0.
5 1.
54E+
04
2.78
E+04
Build
ing
- roo
fs
Peel
able
co
atin
gs
5 9.
12E+
06
4.16
E+06
0.
50
1.00
0.
6 2.
74E+
06
8.32
E+05
Build
ing
- wal
ls
Peel
able
co
atin
gs
5 4.
32E+
06
4.16
E+06
0.
50
2.97
0.
6 3.
85E+
06
2.47
E+06
Build
ing
- in
terio
rs
Vacu
umin
g,
clea
ning
an
d w
ashi
ng
5 1.
60E+
06
1.60
E+06
0.
50
15.3
3 0.
6 7.
36E+
06
4.91
E+06
Pla
nts
and
shru
bs
Rem
oval
1.
4 6.
88E+
05
9.28
E+04
0.
10
0.30
0.
5 1.
03E+
04
1.39
E+03
Tree
s Fe
lling
and
rem
oval
10
4.
16E+
06
4.16
E+06
0.
10
0.20
0.
5 4.
16E+
04
4.16
E+04
Soil
and
gras
s C
uttin
g an
d co
llect
ion
3 1.
92E+
05
1.41
E+04
0.
10
0.50
0.
5 4.
80E+
03
3.52
E+02
To
tal
(199
6 U
SD)
1.40
E+07
8.
28E+
06
2.
23E+
07
To
tal
(200
5 U
SD)
2.78
E+07
Rev
iew
of I
ndia
n P
oint
Sev
ere
Acc
iden
t IS
R R
epor
t 130
14-0
1-01
O
ff S
ite C
onse
quen
ce A
naly
sis
P
age
51
Ta
ble
23: H
eavy
dec
onta
min
atio
n in
urb
an a
reas
(CO
ND
O)
Are
a Pr
oces
s D
F Fr
agm
ente
d C
ost (
$/km
2)
Con
tinuo
us
Cos
t ($/
km2)
Su
rfac
e fr
actio
n (U
rban
)
Add
ition
al
frac
tion
to
sepa
rate
su
rfac
e fr
actio
n
Frag
men
ted
frac
tion
Fina
l Fr
agm
ente
d C
ost (
$/km
2)
Fina
l C
ontin
uous
C
ost (
$/km
2)
Roa
ds -
pave
d ar
eas
Rem
oval
and
re
plac
emen
t 50
3.
84E+
07
1.34
E+07
0.
40
1.00
0.
5 7.
68E+
06
2.69
E+06
Build
ing
- roo
fs
San
dbla
stin
g 10
3.
20E+
06
4.32
E+06
0.
50
1.00
0.
6 9.
60E+
05
8.64
E+05
Build
ing
- wal
ls
San
dbla
stin
g 10
3.
20E+
06
4.32
E+06
0.
50
2.97
0.
6 2.
85E+
06
2.57
E+06
Build
ing
- in
terio
rs
Vacu
umin
g,
clea
ning
and
w
ashi
ng
5 1.
14E+
07
1.14
E+07
0.
50
15.3
3 0.
6 5.
22E+
07
3.48
E+07
Pla
nts
and
shru
bs
Rem
oval
1.
4 6.
88E+
05
9.28
E+04
0.
10
0.30
0.
5 2.
88E+
04
2.88
E+04
Tree
s Fe
lling
and
rem
oval
10
4.
16E+
06
4.16
E+06
0.
10
0.20
0.
5 4.
16E+
04
4.16
E+04
Soil
and
gras
s Tu
rf re
mov
al
10
8.80
E+04
8.
96E+
04
0.10
0.
50
0.5
2.20
E+03
2.
24E+
03
To
tal
(199
6 U
SD)
6.38
E+07
4.
10E+
07
1.
05E+
08
To
tal
(200
5 U
SD)
1.31
E+08
Rev
iew
of I
ndia
n P
oint
Sev
ere
Acc
iden
t IS
R R
epor
t 130
14-0
1-01
O
ff S
ite C
onse
quen
ce A
naly
sis
P
age
52
Ta
ble
24: L
ight
dec
onta
min
atio
n in
hyp
er-u
rban
are
as (C
ON
DO
)
Are
a Pr
oces
s D
F Fr
agm
ente
d C
ost
($/k
m2)
Con
tinuo
us
Cos
t ($/
km2)
Surf
ace
frac
tion
(Hyp
er-
Urb
an)18
Add
ition
al
frac
tion
to
sepa
rate
su
rfac
e fr
actio
n
Frag
men
ted
frac
tion18
Fina
l F
ragm
ente
d
Cos
t ($/
km2)
Fina
l C
ontin
uous
C
ost (
$/km
2)
Roa
ds -
pave
d ar
eas
Fire
hos
ing
or
high
pre
ssur
e ho
sing
3 to
5 7.
68E+
04
1.39
E+05
0.
25
1.00
0.
5 9.
60E+
03
1.74
E+04
Build
ing
- roo
fs
Peel
able
co
atin
gs
5 9.
12E+
06
4.16
E+06
0.
70
1.00
0.
4 2.
55E+
06
1.75
E+06
Build
ing
- wal
ls
Peel
able
co
atin
gs
5 4.
32E+
06
4.16
E+06
0.
70
4.73
0.
4 5.
72E
+06
8.26
E+06
Build
ing
- in
terio
rs
Vacu
umin
g,
clea
ning
and
w
ashi
ng
5 1.
60E+
06
1.60
E+06
0.
70
23.8
3 0.
4 1.
07E+
07
1.60
E+07
Pla
nts
and
shru
bs
Rem
oval
1.
4 6.
88E+
05
9.28
E+04
0.
05
0.30
0.
5 5.
16E+
03
6.96
E+02
Tree
s Fe
lling
and
rem
oval
10
4.
16E+
06
4.16
E+06
0.
05
0.20
0.
5 2.
08E+
04
2.08
E+04
Soil
and
gras
s C
uttin
g an
d co
llect
ion
3 1.
92E+
05
1.41
E+04
0.
05
0.50
0.
5 2.
40E+
03
1.76
E+02
To
tal
(199
6 U
SD)
1.90
E+07
2.
61E+
07
4.
51E+
07
To
tal
(200
5 U
SD)
5.61
E+07
18 T
he s
urfa
ce a
nd fr
agm
ente
d fra
ctio
ns s
how
n he
re fo
r hyp
er-u
rban
are
as w
ere
deriv
ed b
y IS
R u
sing
ext
rapo
latio
n fro
m u
rban
val
ues
Rev
iew
of I
ndia
n P
oint
Sev
ere
Acc
iden
t IS
R R
epor
t 130
14-0
1-01
O
ff S
ite C
onse
quen
ce A
naly
sis
P
age
53
Tabl
e 25
: Hea
vy d
econ
tam
inat
ion
in h
yper
-urb
an a
reas
(CO
ND
O)
Are
a Pr
oces
s D
F Fr
agm
ente
d
Cos
t ($/
km2)
C
ontin
uous
C
ost (
$/km
2)
Surf
ace
frac
tion
(Hyp
er-
Urb
an)19
Add
ition
al
frac
tion
to
sepa
rate
su
rfac
e fr
actio
n
Frag
men
ted
frac
tion19
Fina
l Fr
agm
ente
d C
ost
($/k
m2)
Fina
l C
ontin
uous
C
ost
($/k
m2)
Roa
ds -
pave
d ar
eas
Rem
oval
an
d re
plac
emen
t 50
3.
84E+
07
1.34
E+07
0.
25
1.00
0.
5 4.
80E+
06
1.68
E+06
Build
ing
- roo
fs
San
dbla
stin
g 10
3.
20E+
06
4.32
E+06
0.
70
1.00
0.
4 8.
96E+
05
1.81
E+06
Build
ing
- wal
ls
San
dbla
stin
g 10
3.
20E+
06
4.32
E+06
0.
70
4.73
0.
4 4.
24E+
06
8.58
E+06
Build
ing
- inte
riors
Vacu
umin
g,
clea
ning
and
w
ashi
ng
5 1.
14E+
07
1.14
E+07
0.
70
23.8
3 0.
4 7.
58E+
07
1.14
E+08
Pla
nts
and
shru
bs
Rem
oval
1.
4 6.
88E+
05
9.28
E+04
0.
05
0.30
0.
5 1.
44E+
04
1.44
E+0
4
Tree
s Fe
lling
and
rem
oval
10
4.
16E+
06
4.16
E+06
0.
05
0.20
0.
5 2.
08E+
04
2.08
E+04
Soil
and
gras
s Tu
rf re
mov
al
10
8.80
E+04
8.
96E+
04
0.05
0.
50
0.5
1.10
E+03
1.
12E+
03
To
tal
(199
6 U
SD)
8.58
E+07
1.
26E+
08
2.
12E+
08
To
tal
(200
5 U
SD)
2.64
E+08
19 T
he s
urfa
ce a
nd fr
agm
ente
d fra
ctio
ns s
how
n he
re fo
r hyp
er-u
rban
are
as w
ere
deriv
ed b
y IS
R u
sing
ext
rapo
latio
n fro
m u
rban
val
ues
Rev
iew
of I
ndia
n P
oint
Sev
ere
Acc
iden
t IS
R R
epor
t 130
14-0
1-01
O
ff S
ite C
onse
quen
ce A
naly
sis
P
age
54
Ta
ble
26: D
econ
tam
inat
ion
in s
emi-u
rban
are
as (R
ISO
)
Are
a Pr
oces
s C
ost (
$/km
2), 2
011
Surf
ace
frac
tion
(Sem
i-U
rban
)
Add
ition
al
frac
tion
to
sepa
rate
su
rfac
e fr
actio
n
Fina
l Cos
t ($
/km
2)
Roa
ds -
pave
d ar
eas
Hig
h pr
essu
re h
osin
g 1.
22E+
06
0.40
1.
00
4.88
E+05
Build
ing
- ro
ofs
Rot
atin
g br
ush
3.86
E+06
0.
40
1.00
1.
55E
+06
Build
ing
- w
alls
H
igh
pres
sure
hos
ing
1.22
E+06
0.
40
2.19
1.
07E+
06
Build
ing
- in
terio
rs
Vacu
umin
g, c
lean
ing
and
was
hing
7.
64E+
06
0.40
11
.55
3.53
E+07
Soil
and
gras
s C
uttin
g an
d co
llect
ion
4.18
E+04
0.
20
1.00
8.
36E+
03
Tota
l (2
011
USD
) 3.
84E+
07
Tota
l (2
005
USD
) 3.
34E+
07
Rev
iew
of I
ndia
n P
oint
Sev
ere
Acc
iden
t IS
R R
epor
t 130
14-0
1-01
O
ff S
ite C
onse
quen
ce A
naly
sis
P
age
55
Ta
ble
27: D
econ
tam
inat
ion
cost
s fo
r urb
an a
reas
(RIS
O)
Are
a Pr
oces
s C
ost (
$/km
2)
Surf
ace
frac
tion
(Urb
an)
Add
ition
al
frac
tion
to
sepa
rate
su
rfac
e fr
actio
n
Fina
l Cos
t ($
/km
2)
Roa
ds -
pave
d ar
eas
Hig
h pr
essu
re h
osin
g 1.
22E+
06
0.40
1.
00
4.88
E+05
Build
ing
- roo
fs
Rot
atin
g br
ush
3.86
E+06
0.
50
1.00
1.
93E
+06
Build
ing
- wal
ls
Hig
h pr
essu
re h
osin
g 1.
22E+
06
0.50
2.
97
1.81
E+0
5
Build
ing
- int
erio
rs
Vacu
umin
g, c
lean
ing
and
was
hing
7.
64E+
06
0.50
15
.33
5.85
E+07
Soi
l and
gra
ss
Cut
ting
and
colle
ctio
n 4.
18E+
04
0.10
1.
00
4.18
E+03
Tota
l (2
011
USD
) 6.
28E+
07
Tota
l (2
005
USD
) 5.
46E+
07
Rev
iew
of I
ndia
n P
oint
Sev
ere
Acc
iden
t IS
R R
epor
t 130
14-0
1-01
O
ff S
ite C
onse
quen
ce A
naly
sis
P
age
56
Ta
ble
28: D
econ
tam
inat
ion
cost
s fo
r hyp
er-u
rban
are
as (R
ISO
)
Are
a Pr
oces
s C
ost (
$/km
2)
Surf
ace
frac
tion
(Hyp
er-
Urb
an)20
Add
ition
al
frac
tion
to
sepa
rate
su
rfac
e fr
actio
n
Fina
l Cos
t ($
/km
2)
Roa
ds -
pave
d ar
eas
Hig
h pr
essu
re h
osin
g 1.
22E+
06
0.25
1.
00
3.05
E+05
Build
ing
- roo
fs
Rot
atin
g br
ush
3.86
E+06
0.
70
1.00
2.
71E+
06
Build
ing
- wal
ls
Hig
h pr
essu
re h
osin
g 1.
22E+
06
0.70
4.
73
4.04
E+06
Build
ing
- int
erio
rs
Vacu
umin
g, c
lean
ing
and
was
hing
7.
64E+
06
0.70
23
.83
1.27
E+08
Soi
l and
gra
ss
Cut
ting
and
colle
ctio
n 4.
18E+
04
0.05
1.
00
2.09
E+03
Tota
l (2
011
USD
) 1.
34E+
08
Tota
l (2
005
USD
) 1.
17E+
08
20 T
he s
urfa
ce fr
actio
ns s
how
n he
re fo
r hyp
er-u
rban
are
as w
ere
deriv
ed b
y IS
R u
sing
ext
rapo
latio
n fro
m u
rban
val
ues
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 57
ANNEX D VALWNF Calculation The description, justification and discussion regarding the VALWNF are found in Section 4.3. This annex includes the tabulated values for the re-calculation of VALWNF. All though portions of them lie within the 50-mile radius zone, Entergy did not include the following counties in the determination of VALWNF: Pike, PA, Hunterdon, NJ, Middlesex, NJ, Monmouth, NJ, Ocean, NJ, Somerset, NJ, and Richmond, NY. Entergy excluded these counties because they comprise less than 50% of any spatial element in the 50-mile radius zone [30].
Rev
iew
of I
ndia
n P
oint
Sev
ere
Acc
iden
t IS
R R
epor
t 130
14-0
1-01
O
ff S
ite C
onse
quen
ce A
naly
sis
P
age
58
Tabl
e 29
: VA
LWN
F va
lues
and
cal
cula
tion
Stat
e C
ount
y
2004
GC
P (B
illio
ns
USD
) 20
04 p
op.
(Mill
ion)
20
04 G
CP
($/p
erso
n)
Orig
inal
(1
997)
VN
FRM
fr
om
SEC
POP
($/p
erso
n)
US
GD
P In
crea
se
fact
or
from
199
7 to
200
4
Ente
rgy
Fina
l (2
004)
VN
FRM
($
/per
son)
ISR
Fin
al
(200
4)
VNFR
M
($/p
erso
n)
Pop.
w
eigh
ting
fa
ctor
ISR
W
eigh
ted
(200
4)
VNFR
M
over
en
tire
data
set
($
/per
son)
N
Y Ki
ngs
47.4
2.
5 18
,960
10
4,71
4 1.
42
123,
701
167,
921
0.13
21
,830
N
Y Q
ueen
s 33
4.6
5.81
57
,590
16
9,12
6 1.
42
226,
728
298,
181
0.31
92
,436
C
T Fa
irfie
ld
49.8
0.
9 55
,333
23
2,65
9 1.
42
287,
881
386,
304
0.05
19
,315
C
T Li
tchf
ield
7.
1 0.
19
37,3
68
148,
522
1.42
18
6,01
6 24
8,64
9 0.
01
2,48
6 C
T N
ew H
aven
40
.8
0.84
48
,571
14
4,10
5 1.
42
192,
427
253,
569
0.05
12
,678
N
J B
erge
n 50
.8
0.9
56,4
44
205,
863
1.42
26
2,18
6 34
9,29
6 0.
05
17,4
65
NJ
Esse
x 39
.8
0.8
49,7
50
147,
351
1.42
19
7,40
0 25
9,36
5 0.
04
10,3
75
NY
Sul
livan
2.
6 0.
08
32,5
00
104,
859
1.42
13
9,37
4 18
1,66
8 0.
004
727
NJ
Mor
ris
31.3
0.
49
63,8
78
213,
389
1.42
27
7,66
1 36
7,43
5 0.
03
11,0
23
NJ
Pass
aic
19.9
0.
5 39
,800
12
1,88
0 1.
42
161,
864
213,
181
0.03
6,
395
NJ
Sus
sex
4.5
0.15
30
,000
13
6,19
7 1.
42
165,
741
223,
748
0.01
2,
237
NJ
Uni
on
25.9
0.
53
48,8
68
160,
860
1.42
20
9,70
8 27
7,70
0 0.
03
8,33
1 N
Y D
utch
ess
11.9
0.
29
41,0
34
129,
000
1.42
16
9,41
7 22
4,54
4 0.
02
4,49
1 N
Y N
assa
u 63
.1
1.34
47
,090
19
2,75
5 1.
42
239,
932
321,
294
0.07
22
,491
N
Y O
rang
e 12
.9
0.37
34
,865
11
3,97
6 1.
42
148,
873
197,
002
0.02
3,
940
NY
Put
nam
2.
5 0.
1 25
,000
15
4,92
6 1.
42
180,
274
245,
391
0.01
2,
454
NY
Roc
klan
d 11
.8
0.29
40
,690
16
3,10
5 1.
42
203,
359
272,
716
0.02
5,
454
NY
Suffo
lk
63.2
1.
47
42,9
93
149,
615
1.42
19
2,47
1 25
5,82
9 0.
08
20,4
66
NY
Uls
ter
6.3
0.18
35
,000
10
4,09
0 1.
42
138,
739
183,
074
0.01
1,
831
NY
Wes
tche
ster
43
.4
0.94
46
,170
21
7,27
8 1.
42
263,
389
355,
260
0.05
17
,763
To
tal
All
coun
ties
with
in th
e 50
-mi r
adiu
s zo
ne
VALW
NF
284,
189
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 59
ANNEX E MACCS2 economic cost flowcharts This annex includes visual representations (flowcharts) of the MACCS2 code, related to how it interprets and calculates total costs. The fields indentified in red are user-defined inputs, while normal borders are calculated values.
~ •• II:---------------------------
Rev
iew
of I
ndia
n P
oint
Sev
ere
Acc
iden
t IS
R R
epor
t 130
14-0
1-01
O
ff S
ite C
onse
quen
ce A
naly
sis
P
age
60
(CL)
To
tal c
ost o
f lon
g-te
rm
prot
ectiv
e ac
tion
($)
(P)
Pop
ulat
ion
bein
g co
nsid
ered
(per
sons
)(A
F)Fa
rmla
nd a
rea
with
in th
e ar
ea b
eing
con
side
red
(hec
tare
s)
(CF)
Per
uni
t are
a co
st o
f lon
g-te
rm p
rote
ctiv
e ac
tion
for
farm
pro
perty
($/h
ecta
re)
(CN
F)
Per
per
son
cost
of l
ong
term
pro
tect
ive
actio
n fo
r non
farm
pro
perty
($
/per
son)
CD
NFR
M(C
D) U
nit c
ost o
f de
cont
amin
atio
n ($
/per
son,
non
farm
)
(CC
) U
nit c
ost o
f com
pens
atio
n fro
m lo
ss o
f usa
ge o
f pr
oper
ty (d
epre
ciat
ion,
de
terio
ratio
n, a
nd lo
sses
) ($/
pers
on, n
onfa
rm)
POPC
ST(C
R) U
nit c
ost o
f re
loca
ting
the
popu
latio
n ($
/per
son,
non
farm
)
(VA
LWP
) U
nit v
alue
of w
ealth
for t
he
regi
on a
t the
tim
e th
e la
nd
is d
ecla
red
habi
tabl
e ($
/per
son,
non
farm
)
VALW
NF
(VA
LW) U
nit v
alue
of
wea
lth fo
r the
regi
on a
t th
e tim
e of
the
acci
dent
($
/per
son,
non
farm
)
(VA
LWP
I)P
ost-i
nter
dict
ion
perio
d un
it va
lue
of w
ealth
from
im
prov
emen
ts m
ade
to th
e pr
oper
ty
($/p
erso
n, n
onfa
rm)
(VA
LWP
L)P
ost-i
nter
dict
ion
perio
d un
it va
lue
of w
ealth
re
sulti
ng fr
om la
nd it
self
($/p
erso
n, n
onfa
rm)
VALW
NF
(VA
LW) U
nit v
alue
of w
ealth
fo
r non
farm
pro
perty
in
regi
on (c
ost o
f lan
d,
build
ings
, inf
rast
ruct
ure)
($
/per
son)
FRN
FIM
(FIM
) Fra
ctio
n of
wea
lth in
th
e re
gion
resu
lting
from
im
prov
emen
ts
(Uni
tless
)
DPR
ATE
(RD
P) D
epre
ciat
ion
rate
(s
-1)
TMPA
CT
(TH
) Tim
e at
whi
ch th
e no
nfar
m p
rope
rty is
re
turn
ed to
hab
itabi
lity
(s)
DSR
ATE
Infla
tion
adju
sted
rate
of
inve
stm
ent r
etur
n (s
-1)
(CC
)U
nit c
ost o
f com
pens
atio
n as
a
resu
lt of
loss
of u
sage
of
the
prop
erty
(dep
reci
atio
n,
dete
riora
tion,
and
loss
es) (
$/he
ctar
e, fa
rm)
CD
FRM
(CD
)U
nit c
ost o
f de
cont
amin
atio
n ($
/hec
tare
, far
m)
VALW
F(V
ALW
) Uni
t val
ue o
f wea
lth fo
r fa
rmla
nd in
regi
on
(cos
t of l
and,
bui
ldin
gs,
infra
stru
ctur
e)
($/h
ecta
re)
FRFI
M(F
IM) F
ract
ion
of w
ealth
fo
r far
m p
rope
rty re
sulti
ng
from
impr
ovem
ents
(U
nitle
ss)
DPR
ATE
(RD
P) D
epre
ciat
ion
rate
(s
-1)
(TF)
Tim
e at
whi
ch th
e fa
rmla
nd is
retu
rned
to
habi
tabi
lity
(s)
DSR
ATE
(RIR
) Inf
latio
n ad
just
ed
rate
of i
nves
tmen
t ret
urn
(s-1
)Tota
l cos
t of L
ong-
Term
pro
tect
ive
Act
ions
($)
Fi
gure
9: T
otal
cos
t of l
ong-
term
pro
tect
ive
actio
ns
Red
box
es in
dica
te u
ser i
nput
s
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 61
(CCNF) Cost to condemn nonfarm
property ($/person)
VALWNF(VALW) Unit value of
wealth for the region at the time of the accident ($/person, nonfarm)
POPCST(CR) Unit cost of
relocating an individual ($/person, nonfarm)
Cost to condemn Nonfarm Property ($/person)
Figure 10: Cost to condemn nonfarm property
(CCF) Per unit area cost to
condemn farm property ($/hectare)
VALWF(VALW) Unit value of
wealth for the farmland at the time of the accident
($/hectare, farm)
Cost to condemn Farmland ($/hectare)
Figure 11: Cost to condemn farmland
Red boxes indicate user inputs
Red boxes indicate user inputs
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 62
(CMD) Unit cost of milk disposal
($/hectare)
FRMPRD(FP) Average annual farm
production value ($/hectare)
DPFRCT(FDP) Fraction of annual
farm production value which comes from dairy farm
production (Unitless)
(FMD) Fraction of the year over which milk disposal
occurs (Unitless)
Unit cost of Milk Disposal ($/hectare)
Figure 12: Cost of milk disposal
(CNMD) Unit cost of non-milk disposal ($/hectare)
FRMPRD(FP) Average annual farm
production value ($/hectare)
DPFRCT(FDP) Fraction of annual
farm production value which comes from dairy farm
production (Unitless)
Unit cost of Non-dairy Disposal ($/hectare)
Figure 13: Cost of non-dairy disposal
Red boxes indicate user inputs
Red boxes indicate user inputs
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 63
(CE)Cost of early
protective action being taken ($)
EVACST(I)
Daily cost of the action per individual ($)
(D)Duration of the action (days)
(P)Number of individuals
involved (persons)
Cost of early protective actions
Figure 14: Cost of early protective actions
Red boxes indicate user inputs
Review of Indian Point Severe Accident ISR Report 13014-01-01 Off Site Consequence Analysis
Page 64
ANNEX F Timeline of certain references 1975 WASH-1400, Calculation of Reactor Accident Risks, Appendix VI, Nuclear Regulatory
Commission, 1975.
1987 NUREG-1150, Reactor Risk Reference Document (Draft for Comment) -Main Report (Volume 1), Appendices A-I (Volume 2), and Appendices J-O (Volume 3), February 1987.
1989 NUREG-1150, Severe Accident Risks: An Assessment for Five Us. Nuclear Power Plants (Second Draft for Peer Review) -Summary Report (Volume 1), Appendices (Volume 2), June 1989.
1990 NUREG-1150, Severe Accident Risks: An Assessment for Five Us. Nuclear Power Plants - Final Summary Report (Volume 1), Appendices A, B, and C (Volume 2), Appendices D and E (Volume 3), December 1990.
1990 NUREG/CR-4551, J. L. Sprung, et aI., Evaluation of Severe Accident Risks: Quantification of major input parameters -MACCS Input, Volume 2, Revision 1, Part 7, December 1990.
1996 SAND96-0957, D.l. Chanin & W.B. Murfin, Site Restoration: Estimation of Attributable Costs from a Plutonium-Dispersal Accident, Sandia National Laboratories, Albuquerque, NM, UC-502 (May 1996).
1997 MACCS2 computer code, public release.
1998 NUREG/CR-6613, SAND97-0594, D.l. Chanin & M.L. Young, Code Manual for MACCS2, Volume 1, User's Guide, Sandia National Laboratories, Albuquerque, NM, (May 1998).
2008 R.E. Luna, H.R. Yoshimura, M.S. Soo Hoo, Survey of Costs Arising from Potential Radionuclide Scattering Events, WM2008 Conference, February 2008, Phoenix, AZ.