Rev Plan for Unit 8 9 10 1112

Embed Size (px)

Citation preview

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    1/33

    For All Design Problems

    Remember to

    Begin with the End in Mind

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    2/33

    Cover Sheetfor Plans

    andCalculations

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    3/33

    Plan of the Piping Configuration

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    4/33

    Calculations

    for the Sizesof the PipingSelected andthe Pressure

    Available at

    the Sourcesof the Fire

    ProtectionWater

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    5/33

    A Hydraulic

    Graph toShow theWaterSupply andthe Design

    OperatingPoint for theFlow and

    Pressure ofthe FireProtection

    System

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    6/33

    Water Supply to Sprinkler System

    includes Total Demand RequirementsFire Sprinkler Water Requirement

    Area of Operation in Hazard times DensityDemand PLUS Overage Factor due to Laws ofFluid Mechanics (usually 10 percent as a rule of

    thumb)Hose Stream Requirement Based on Occupancy Hazard Classification

    Duration of Fire Event in minutes

    = Total Water Demand in Gallons

    Very important for sizing water storage tanks orcalculating the size of a pond.

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    7/33

    Water Supply to Sprinkler System

    includes Total Demand RequirementsArea and Density are determined from

    Graph on next page from NFPA-13

    Hose Stream Demand and Duration are

    determined from NFPA TablesLight Hazard 100 gpm for 30 minutes

    Ordinary Hazard 250 gpm for 60-90 minutes

    Extra Hazard 500 gpm for 90-120 minutes

    Factor for Overage is 10 Percent unless

    directed by AHJ to use a different factor.

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    8/33

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    9/33

    Water Flow from Sprinkler

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    10/33

    Orifice Discharge Formula

    The orifice discharge formula is simplified for sprinkler heads

    because of the uniform diameter.The discharge in GPM (Q) = the orifice coefficient (k) timesthe square root of the pressure (p) at the orifice.

    Q = k p^.5 See text page 1098K for sprinkler heads are shown in the text, page 1093

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    11/33

    Orifice Discharge Formula The orifice discharge formula is simplified for sprinkler

    heads because of the uniform diameter.

    Q = k p^.5 Because k will be constant for all calculations, the

    quantity of flow (Q) at each sprinkler head will be

    different due to change in pressure in the pipingsystem due to friction loss based on the diameterand roughness of the piping.

    From the water supply end toward the most remoteopening the flow rate will decrease.

    From the most remote opening toward the water supply

    the flow rate will increase.

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    12/33

    Number of Spklrs to be Calculated

    A very important element not included inthis Textbook

    It must be a whole number, round up

    Number of sprinklers per branch

    1.2 * A^.5 SA = Design Area

    S = Distance between sprinklers on branch line

    1st Total sprinklers to be calculated Design Area Area per Sprinkler

    It must be a whole number, round up

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    13/33

    Heads in Design Area

    OH1 2000sf

    2000108=18.5 or 19

    1.2*2000^.5

    12 = 4.47or 5 hds perbranch

    (14 * 108) +(5 * 90 =

    1962 sf + 1more head

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    14/33

    System Design Approaches

    Hydraulic Method in an Engineered System

    Best because

    it fits the piping layout

    Maybe for economics

    Maybe for conservation of pressure available

    Maybe because of the way the building will be used

    it fits the piping materials specified, many options

    it fits the height of the building, elevation head is a big concern

    it fits types of sprinklers heads used or required it fits the density of water required for the hazard more

    accurately

    it can be used to control the velocity of flow in the piping.

    (32 fps maximum, some AHJ use 20 fps max.)

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    15/33

    Hydraulic Design Procedure

    Determine the Design Conditions

    Determine the Water Demand based on Conditions

    Determine the Water Supply Static & Residual Pres.

    Layout the piping with relation to the building

    structure and building usage.Determine the Flow Rate and the Residual Pressurerequired at the Most Remote Sprinkler Head

    Determine the difference in the Residual Pressurefrom the Water Supply and the OperatingSprinklers including the Changes in Elevation

    Finally, size the piping.

    An Example Water Supply

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    16/33

    An Example Water Supply

    Graph with Design Limits

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    17/33

    Testing the Water Supply

    Flow Test

    - usually local water department - contractors

    - insurance underwriters

    - routine for fire insurance rating

    Static pressure - no flow, theoretical, done whilemains are being used

    Residual pressure - with a flow rate

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    18/33

    Flow Test Diagram

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    19/33

    Pitot Tube to Measure Pressure

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    20/33

    Pitot Reading Conversion

    Log Graph

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    21/33

    Log Graph

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    22/33

    An Example Water Supply

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    23/33

    Water Supply to Sprinkler SystemFire Sprinkler Water Requirement

    Area of Operation in Hazard times Density Demand PLUSOverage Factor due to Laws of Fluid Mechanics (usually10 percent as a rule of thumb)

    Plus required Hose Stream

    Pressure Requirement

    Minimum Pressure required at most remote sprinkler

    head to produce the flow rate required. Plus Elevation Head, the height of the most remote

    sprinkler head.

    Plus Friction Loss due flow through the piping.

    l ll

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    24/33

    Example Illustration

    An Example Water Supply

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    25/33

    An Example Water Supply

    Graph with Design Limits

    D t i i th Q tit f W t R d i

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    26/33

    Determining the Quantity of Water Reqd is

    based on the Protected Hazard

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    27/33

    Set-up for CalculationsHead layout 1st step variable Follow the Rules

    Piping arrangement 2nd step variable Tree Configuration

    Branches perpendicular to supporting structure

    Area of sprinkler operation - 3rd variable Set Formula to Determine the Shape

    Calculations 4th step extremely variable Simple, IF you keep track of where flow is going

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    28/33

    Example of Process

    Starting Flow Rate Density times Area of Head Coverage

    Starting Pressure Calculation p = (Q/k)^2, but not less than 7 psi

    If less than 7 psi, then use 7 psi to start

    Pressure Required at 2

    nd

    Head H-W pressure loss calculation

    Calculating New Flow Rate for 2nd

    Head Q = k(p^.5) Use the p required at that point

    f h h l

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    29/33

    An Overview of the Whole

    Hydraulic Calculation Process

    It is an Iterative Process.

    That is, making repetitions or beingrepetitious to achieve solutions.

    And, that is what it takes to achieve themost suitable and economical solutions in

    engineering any part of any building.

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    30/33

    Tag theNodes to

    KeepOrder

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    31/33

    Tag the Nodes to Keep Order

    A 1st Branch toRiser Nipple

    B 1st BranchRiser Nipple toCross Main

    C 2nd BranchRiser Nipple to

    Cross MainD 3rd BranchRiser Nipple toCross Main

    E 4th BranchRiser Nipple toCross Main

    F Cross Main to

    Feed Main

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    32/33

    Example ofCalculation

  • 7/29/2019 Rev Plan for Unit 8 9 10 1112

    33/33

    Example ofCalculation