Upload
thomas-martin
View
219
Download
0
Embed Size (px)
Citation preview
7/29/2019 Rev Plan for Unit 8 9 10 1112
1/33
For All Design Problems
Remember to
Begin with the End in Mind
7/29/2019 Rev Plan for Unit 8 9 10 1112
2/33
Cover Sheetfor Plans
andCalculations
7/29/2019 Rev Plan for Unit 8 9 10 1112
3/33
Plan of the Piping Configuration
7/29/2019 Rev Plan for Unit 8 9 10 1112
4/33
Calculations
for the Sizesof the PipingSelected andthe Pressure
Available at
the Sourcesof the Fire
ProtectionWater
7/29/2019 Rev Plan for Unit 8 9 10 1112
5/33
A Hydraulic
Graph toShow theWaterSupply andthe Design
OperatingPoint for theFlow and
Pressure ofthe FireProtection
System
7/29/2019 Rev Plan for Unit 8 9 10 1112
6/33
Water Supply to Sprinkler System
includes Total Demand RequirementsFire Sprinkler Water Requirement
Area of Operation in Hazard times DensityDemand PLUS Overage Factor due to Laws ofFluid Mechanics (usually 10 percent as a rule of
thumb)Hose Stream Requirement Based on Occupancy Hazard Classification
Duration of Fire Event in minutes
= Total Water Demand in Gallons
Very important for sizing water storage tanks orcalculating the size of a pond.
7/29/2019 Rev Plan for Unit 8 9 10 1112
7/33
Water Supply to Sprinkler System
includes Total Demand RequirementsArea and Density are determined from
Graph on next page from NFPA-13
Hose Stream Demand and Duration are
determined from NFPA TablesLight Hazard 100 gpm for 30 minutes
Ordinary Hazard 250 gpm for 60-90 minutes
Extra Hazard 500 gpm for 90-120 minutes
Factor for Overage is 10 Percent unless
directed by AHJ to use a different factor.
7/29/2019 Rev Plan for Unit 8 9 10 1112
8/33
7/29/2019 Rev Plan for Unit 8 9 10 1112
9/33
Water Flow from Sprinkler
7/29/2019 Rev Plan for Unit 8 9 10 1112
10/33
Orifice Discharge Formula
The orifice discharge formula is simplified for sprinkler heads
because of the uniform diameter.The discharge in GPM (Q) = the orifice coefficient (k) timesthe square root of the pressure (p) at the orifice.
Q = k p^.5 See text page 1098K for sprinkler heads are shown in the text, page 1093
7/29/2019 Rev Plan for Unit 8 9 10 1112
11/33
Orifice Discharge Formula The orifice discharge formula is simplified for sprinkler
heads because of the uniform diameter.
Q = k p^.5 Because k will be constant for all calculations, the
quantity of flow (Q) at each sprinkler head will be
different due to change in pressure in the pipingsystem due to friction loss based on the diameterand roughness of the piping.
From the water supply end toward the most remoteopening the flow rate will decrease.
From the most remote opening toward the water supply
the flow rate will increase.
7/29/2019 Rev Plan for Unit 8 9 10 1112
12/33
Number of Spklrs to be Calculated
A very important element not included inthis Textbook
It must be a whole number, round up
Number of sprinklers per branch
1.2 * A^.5 SA = Design Area
S = Distance between sprinklers on branch line
1st Total sprinklers to be calculated Design Area Area per Sprinkler
It must be a whole number, round up
7/29/2019 Rev Plan for Unit 8 9 10 1112
13/33
Heads in Design Area
OH1 2000sf
2000108=18.5 or 19
1.2*2000^.5
12 = 4.47or 5 hds perbranch
(14 * 108) +(5 * 90 =
1962 sf + 1more head
7/29/2019 Rev Plan for Unit 8 9 10 1112
14/33
System Design Approaches
Hydraulic Method in an Engineered System
Best because
it fits the piping layout
Maybe for economics
Maybe for conservation of pressure available
Maybe because of the way the building will be used
it fits the piping materials specified, many options
it fits the height of the building, elevation head is a big concern
it fits types of sprinklers heads used or required it fits the density of water required for the hazard more
accurately
it can be used to control the velocity of flow in the piping.
(32 fps maximum, some AHJ use 20 fps max.)
7/29/2019 Rev Plan for Unit 8 9 10 1112
15/33
Hydraulic Design Procedure
Determine the Design Conditions
Determine the Water Demand based on Conditions
Determine the Water Supply Static & Residual Pres.
Layout the piping with relation to the building
structure and building usage.Determine the Flow Rate and the Residual Pressurerequired at the Most Remote Sprinkler Head
Determine the difference in the Residual Pressurefrom the Water Supply and the OperatingSprinklers including the Changes in Elevation
Finally, size the piping.
An Example Water Supply
7/29/2019 Rev Plan for Unit 8 9 10 1112
16/33
An Example Water Supply
Graph with Design Limits
7/29/2019 Rev Plan for Unit 8 9 10 1112
17/33
Testing the Water Supply
Flow Test
- usually local water department - contractors
- insurance underwriters
- routine for fire insurance rating
Static pressure - no flow, theoretical, done whilemains are being used
Residual pressure - with a flow rate
7/29/2019 Rev Plan for Unit 8 9 10 1112
18/33
Flow Test Diagram
7/29/2019 Rev Plan for Unit 8 9 10 1112
19/33
Pitot Tube to Measure Pressure
7/29/2019 Rev Plan for Unit 8 9 10 1112
20/33
Pitot Reading Conversion
Log Graph
7/29/2019 Rev Plan for Unit 8 9 10 1112
21/33
Log Graph
7/29/2019 Rev Plan for Unit 8 9 10 1112
22/33
An Example Water Supply
7/29/2019 Rev Plan for Unit 8 9 10 1112
23/33
Water Supply to Sprinkler SystemFire Sprinkler Water Requirement
Area of Operation in Hazard times Density Demand PLUSOverage Factor due to Laws of Fluid Mechanics (usually10 percent as a rule of thumb)
Plus required Hose Stream
Pressure Requirement
Minimum Pressure required at most remote sprinkler
head to produce the flow rate required. Plus Elevation Head, the height of the most remote
sprinkler head.
Plus Friction Loss due flow through the piping.
l ll
7/29/2019 Rev Plan for Unit 8 9 10 1112
24/33
Example Illustration
An Example Water Supply
7/29/2019 Rev Plan for Unit 8 9 10 1112
25/33
An Example Water Supply
Graph with Design Limits
D t i i th Q tit f W t R d i
7/29/2019 Rev Plan for Unit 8 9 10 1112
26/33
Determining the Quantity of Water Reqd is
based on the Protected Hazard
7/29/2019 Rev Plan for Unit 8 9 10 1112
27/33
Set-up for CalculationsHead layout 1st step variable Follow the Rules
Piping arrangement 2nd step variable Tree Configuration
Branches perpendicular to supporting structure
Area of sprinkler operation - 3rd variable Set Formula to Determine the Shape
Calculations 4th step extremely variable Simple, IF you keep track of where flow is going
7/29/2019 Rev Plan for Unit 8 9 10 1112
28/33
Example of Process
Starting Flow Rate Density times Area of Head Coverage
Starting Pressure Calculation p = (Q/k)^2, but not less than 7 psi
If less than 7 psi, then use 7 psi to start
Pressure Required at 2
nd
Head H-W pressure loss calculation
Calculating New Flow Rate for 2nd
Head Q = k(p^.5) Use the p required at that point
f h h l
7/29/2019 Rev Plan for Unit 8 9 10 1112
29/33
An Overview of the Whole
Hydraulic Calculation Process
It is an Iterative Process.
That is, making repetitions or beingrepetitious to achieve solutions.
And, that is what it takes to achieve themost suitable and economical solutions in
engineering any part of any building.
7/29/2019 Rev Plan for Unit 8 9 10 1112
30/33
Tag theNodes to
KeepOrder
7/29/2019 Rev Plan for Unit 8 9 10 1112
31/33
Tag the Nodes to Keep Order
A 1st Branch toRiser Nipple
B 1st BranchRiser Nipple toCross Main
C 2nd BranchRiser Nipple to
Cross MainD 3rd BranchRiser Nipple toCross Main
E 4th BranchRiser Nipple toCross Main
F Cross Main to
Feed Main
7/29/2019 Rev Plan for Unit 8 9 10 1112
32/33
Example ofCalculation
7/29/2019 Rev Plan for Unit 8 9 10 1112
33/33
Example ofCalculation