62
iNTERIM TECHNICAL REPORT 23 REVISION 1 VERIFICATION OF HIGH ENERGY LINE BREAK AND INTERNALLY GENERATED MISSILE REYIEW OUTSIDE CONTAINMENT FOR AUXILIARY FEEDWATER SYSTEM AND CONTROL ROOM VENTILATIONAND PRESSURIZATION SYSTEM NOTICE— THE ATTACHED FILES ARE OFFICIAL RECORDS OF THE DIVISION OF DOCUMENT CONTROL. THEY HAVE BEEN CHARGED TO YOU FOR A LIMITED TIME PERIOD AND MUST BE RETURNED TO THE RECORDS FACILITY BRANCH 016. PLEASE DO NOT SEND DOCUMENTS CHARGED OUT THROUGH THE MAIL, REMOVALOF ANY PAGE(S) FROM DOCUMENT FOR REPRODUCTION MUST BE REFERRED TO FILE PERSONNEL, DEADLINE RETURN DATE 1 8»~0~ 8'30gj.0017105000 8>> >>ASCII'gR 4 RECORDS FACILITYBRANCH STONE 8c WEBSTER ENGINEE

Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

iNTERIM TECHNICAL REPORT 23REVISION 1

VERIFICATION OF HIGH ENERGY LINE BREAK AND

INTERNALLYGENERATED MISSILE REYIEW

OUTSIDE CONTAINMENT FOR AUXILIARYFEEDWATER

SYSTEM AND CONTROL ROOM VENTILATIONAND

PRESSURIZATION SYSTEM

—NOTICE—THE ATTACHED FILES ARE OFFICIAL RECORDS OF THEDIVISION OF DOCUMENT CONTROL. THEY HAVE BEENCHARGED TO YOU FOR A LIMITED TIME PERIOD ANDMUST BE RETURNED TO THE RECORDS FACILITYBRANCH 016. PLEASE DO NOT SEND DOCUMENTSCHARGED OUT THROUGH THE MAIL, REMOVALOF ANYPAGE(S) FROM DOCUMENT FOR REPRODUCTION MUSTBE REFERRED TO FILE PERSONNEL,

DEADLINE RETURN DATE

1 8»~0~8'30gj.00171050008>> >>ASCII'gR

4

RECORDS FACILITYBRANCH

STONE 8c WEBSTER ENGINEE

Page 2: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

1

I

lt ~

Page 3: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

3i

TABLE OF CONTENTS

Section Title ~Pa e

INTRODUCTION ~ ~ ~ ~ ~ ~ ~ ~ ~ l-l

2 DEFINITION OF ITEMS REVIEWED. ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 2 1

2.1 HELB REVIEW@ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 2-1

2.2 IGM REVIEWo ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 2-1

AUXILIARYFEEDWATER SYSTEM. o ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 3 1

3.1 DESCRIPTION OF REVIEW... .. ............................... 3"1

3.1.13.1.2

HELB Reviews ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 3-1

IGM Review . ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 3-5

3.23.2.13.2.2

SUMMARY OF REVIEW RESULTS........HELB Review....,...................IGM Review..................

~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 3-8

~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 3 8

~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 3 8

3.3 EOI REPORTS ISSUED................. ~ ~ ~ ~ ~ ~ ~ e 3 9

3.4 EVALUATION OF REVIEW RESULTS............................... 3"10

HELB Review. ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 3 10

3.4.2t

3.5

3.5.13.5.2

CONCLUSIONS. ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 3-11

HELB Review...IGM Review..

~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 3 1 1

~ ~ ~ ~ ~ ~ ~ 3 ll

IGM Review...................................,............. 3-10

CONTROL ROOM VENTILATIONAND PRESSURIZATION SYSTEM......... 4-1

4.1 DESCRIPTION OF REVIEW...................................... 4-1

4.1.14.1.2

HELB Reviewo ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 4 1

I AGM Review...,.....

Page 4: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

I

Page 5: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

TABLE OF CONTENTS (CONT)

Section Title ~Pa e

4.2 SUMMARY OF REVIEW RESULTS.............. ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 4 8

4.2.14.2.2

HELB Review........IGM Review.

~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 4 8

~ ~ ~ ~ ~ ~ ~ ~ \ ~ ~ ~

4.3 EOI REPORTS ISSUED...................... ~ ~ 4-9

4.4 EVALUATION OF REVIEW RESULTS............................... 4"ll4.4.14.4.2

HELB Reviewo ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~

GM Review...............I4.5 CONCLUSIONS.........

4.5.14.5.2 IGM Review.. ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 4-12

HELB Review................................................ 4 ll

APPENDIXES

A

B

EOI FILES

PROGRAM MANAGER'S ASSESSMENT

13.

Page 6: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated
Page 7: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

SECTION 1

INTRODUCTION

Stone 8 Webster Engineering Corporation (SWEC) has performed a high-energy

line break (HELB) and internally generated missile (IGM) review in accord-

ance with the SWEC Scope of Work defined in Appendix D (DCNPP-IDVP-PP-002)

of the Independent Design Verification Program (IDVP) Phase II Program

Management Plan issued by Teledyne Engineering Services (TES) as IDVP

Program Manager.

The review for adequate separation of safety-related equipment from the

effects of pipe whip, jet impingement, and IGMs was limited to the

following:

1. Evaluation of the effects of pipe whip and jet impingement originating

in any high energy piping system outside containment and IGMs outside

containment on the Auxiliary Feedwater (AFW) and Control Room Ventila-

tion and Pressurization (CRVP) Systems.

2. The evaluation was performed by area review of the geometric relation-

ship between postulated break locations, missile sources, safety-

related targets, and the restraints/shields required to mitigate the

effects of postulated pipe breaks and IGMs.

1" 1

Page 8: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated
Page 9: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

SECTION 2

DEFINITION OF ITEMS REVIEWED

2.1 HELB REVIEW

The Scope of Work for the HELB portion of the review is defined in Appendix

D (DCNPP-IDVP-PP-002) of the Program Management Plan, Page ll, Item No. 7,

and is stated:

"...Determine if adequate separation (distance, barriers, or

restraints) exists to accommodate potential piping failure results

(pipe whip, fluid jet,...) such that the system can accomplish itsdesigned safety-related function during exposure to such pipe

breaks..."

2.2 IGM REVIEW

The Scope of Work for the IGM portion of the review is defined in Appendix D

(DCNPP-IDVP-PP-002) of the Program Management Plan, Page 11, Item No. 7, and

is stated:

"...Determine if adequate separation (distance, barriers...) exists to

accommodate...internally generated missiles such that the system can

accomplish its designed safety-related function during exposure to...missiles."

2"1

Page 10: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated
Page 11: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

SECTION 3

AUXILIARYFEEDWATER SYSTEM

3.1 DESCRIPTION OF REVIEW

3.1.1 HELB Review

The adequate separation review consisted of the determination of AFW system

targets that may be affected by postulated breaks in high energy lines.

The steps taken to perform the review were as follows:

1. Identified AFW system piping and mechanical equipment (targets) on

Pacific Gas 8 Electric (PGGE) piping area drawings.

2. Identified AFW electrical components, conduits, and instrumentation

lines (targets) on PG&E electrical drawings.

.3. Identified the FSAR, Section 3.6A, high energy lines and postulated

break locations and type of break on PGSE piping area drawings for the

following high energy systems:

Condensate System

Main Steam System

Feedwater System

Steam Generator Blowdown System

3"1

Page 12: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

f l

Page 13: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

Steam Supply to the Auxiliary Feedwater Pump Turbine

Extraction Steam and Heater Drip System

Chemical and Volume Control System

Turbine and Generator Associated Systems.

Using the PG&E Line Designation Table (PGSE Drawing No. 102040, Change

9), all piping that exceeds the 200 F and 275 psig high energy line

criterion were identified on PGSE piping area drawings. The break

locations and types identified in the FSAR Section 3.6A were then

located on these drawings.

4. Identified pipe rupture restraint locations indicated in FSAR Section

3.6A on piping isometric drawings for high energy lines. Piping

isometric drawings were used for configurational purposes only and

primarily for the field verification portion of the review (see Section

7).

5. Established potential interaction zones (cubicles) in the plant for

high energy lines and AFW system safety-related targets. The inputs

from Sections 1, 2, and 3 were used to establish plant zones in which a

pipe rupture review occurred. A detailed location listing of all zones

within the plant was prepared for all AFW system piping, equipment, and

electrical components, as well as high energy lines. This information

was then transferred by color codes onto plot plan diagrams at all

major plant elevations. Wherever both color codes for system targets

and for high energy lines occurred simultaneously in any cubicle, a

pipe field verification review resulted.

3-2

Page 14: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated
Page 15: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

The steps taken to perform the field verification were as follows:

6. Postulated break points were located in the high energy systems listed

in 3 above. This review consisted of visually verifying that the con-

figuration of the high energy piping was the same as the applicable

PGSE piping area drawings and isometric drawings of FSAR Section 3.6A.

If the piping configuration was different from that shown on the draw-

ings, it was noted and the effects of the relocation on AFW system

targets evaluated.

7. Pipe rupture restraint locations, types, and configurations on high

energy lines were verified. FSAR Section 3.6A piping isometrics were

used to identify the location, type, and configuration of the pipe

rupture restraints on the high energy piping run. Restraints were

visually compared to the configuration shown on the isometrics. If a

configuration or a location difference was encountered, it was noted

and the effects of the relocation of AFW system tragets evaluated.

8. AFW system mechanical targets (i.e., piping and piping system compon-

" ents) and locations were verified. The field routing of AFW piping and

piping components was visually compared to the routing on the PGSE

piping area drawings. If the routing was different, it was noted and

the effects on the AFW system targets were evaluated. If a target was

affected by jet impingement, the geometrical relationship between the

jet source and the target was sketched. If the effect on the target

was from pipe impact, this was noted.

3"3

Page 16: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated
Page 17: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

9. AFW system electrical and/or instrumentation target locations were

verified. Since the PG&E electrical and instrumentation drawings were

diagrammatic, electrical and instrumentation targets were precisely

located in the field. If a target was affected by jet impingement, the

geometrical relationship between the jet source and target was

sketched. If the effect on a target was from pipe impact, this was

noted.

10. Where HELBs affected system electrical equipment, ISC equipment, or

conduit, it was determined that the conduit is essential by listingequipment serviced by the conduit and determining that the listed

equipment must operate to mitigate the effects of the break in question

and bring the plant to a safe cold shutdown.

11. Where HELBs affected system piping and equipment, it was determined

that it is essential by determining that it must operate to mitigate

the effects of the break in question and to bring the plant to a safe

cold shutdown.

12. Where safety-related targets in an interaction area were found to be

shielded by structures of substantial size (e.g., building structure,

steel supports, large bore piping, etc), the effects of jet impingement

on the target were considered to be mitigated.

The results of the field review for HELBs are classified into one of the

following categories:

3-4

Page 18: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated
Page 19: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

EOI File - This document is generated when the licensing commit-

ment for protection assurance (proper restraints, shielding, or

separation) of an essential system or component is not met for

pipe whip or jet impingement for a postulated circumferential or

longitudinal break.

Meets Licensing Commitments - This category is used when a postu-

lated pipe break is properly restrained, shielded, or separated

from an AFW system safety-related target.

3.1.2 IGM Review

The adequate separation review consists of the determination of protection

assurance adequacy of AFW system targets that may be affected by postulated

sources of IGMs.

The steps taken to perform the review were as follows:

l. Identified sources of IGMs from FSAR Section 3.5.

2. Identified AFW system mechanical and electrical components existing in

the trajectory of the missiles as defined in the FSAR. Locations of

AFW piping and mechanical equipment were established from PGSE piping

area drawings. Locations of AFW electrical components and conduits

were identified in the field.

3-5

Page 20: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

I

Page 21: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

3. Identified missile shields or existing structures and components that

behave as effective missile barriers. This was accomplished by a

review of PGSE equipment location drawings. The review consisted of

the identification of natural plant barriers (concrete walls, floor

slabs, large equipment, etc), missile shields and their relationship to

the sources and trajectories of IGMs.

4. Determined if an AFW system mechanical and electrical component can be

hit by an unshielded missile. This task was performed by a thorough

review of FSAR Section 3.5. The information gathered from this review

were kinetic energies of IGMs, concrete wall penetration depths, and

reasons for not considering analysis (by PG&E). Engineering judgment

was used to determine the validity of the conclusions, especially in

the area where no analysis occurred.

The IGM portion of the review was conducted primarily by a plant walk-

down. Each of the sources of missiles was identified along with the

postulated trajectories. Missile shields and natural plant barriers,

(i.e., existing building structures) were noted. The relationship

between the sources, shields, barriers, walls, floor slabs, and safety-

related targets (if any) were evaluated in the field portion of the

review to determine if safety-related targets would be affected by a

postulated missile event.

5. Where an IGM affected system conduits, essential conduits were defined

by listing equipment services by the conduit and by determining if the

3-6

Page 22: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated
Page 23: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

connected equipment must operate to mitigate the effects of the IGM in

question and to bring the plant to a safe cold shutdown.

6. Where an IGM affected system piping or mechanical equipment, essential

equipment was defined by determining if it must operate to mitigate the

effects of the IGM in question and to bring the plant to a safe cold

shutdown.

The steps taken to perform the field verification were as follows:

7. Located the sources of IGMs identified in the FSAR Section 3.5, Page

8b. The sources are:

~ Main Turbine

~ Main Feedwater Pump Turbine

~ Auxiliary Feedwater Pump Turbine.

8. Located mechanical and electrical safety-related targets. See Section

.3.1.1 (8. and 9.).

9. Iocated missile shields and existing structures and/or components which

act as barriers.

The results of the field review for IGMs are classified into the following

categories:

3 7

Page 24: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

ik

Page 25: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

~ EOI File - This document is generated when the licensing commit-

ment for protection assurance of an essential safety-related

target is not met for the effects of an IGM.

Meets Licensing Commitments - This category is used when an IGM is

shielded or does not intersect a target in its trajectory.

3.2 SUMMARY OF REVIEW RESULTS

3.2.1 HELB Review

393 Break Locations were identified.

214 Restraints and restraint locations were identified.

35 Mechanical targets were located.

136 Electrical and I/C targets were located.

1 EOI file was issued.

3 Jet impingement loadings on AFW piping were referred to the IDVP

Manager.

3.2.2 IGM Review

0 EOI files were issued.

3 IGM sources were identified.

1 Missile shield was observed in place for purposes of shielding

potential missiles from the AFW Pump Turbine.

3-8

Page 26: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated
Page 27: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

2 Plant barriers were identified (turbine pedestal and main con-

densers) for the purpose of shielding potential missiles for the

Main Feedwater Pump Turbine.

0 Safety-related targets were identified as affected by the LP

turbine missile.

3.3 EOI REPORTS ISSUED

One EOI file was issued as a result of the review of effects of postulated

HELBs on the AFW system outside containment.

EOI File 8049 was issued because of concern that a postulated longitudinal

pipe break at node 1800 on line 594 could damage conduit KK 792, resulting

in loss of power to the components required to provide AFW flow.

PG&E has provided additional analysis of the effects of HELB on conduit

KK 792 that addresses both the blowdown thrust force and envelopment temp-

erature due to jet impingement from the postulated longitudinal split on

line 594. The additional analysis provided uses the ANSI/ANS 58.2-1980

method for calculation of jet envelopment temperature which is technically

acceptable, although different from the method currently referenced in FSAR

Section 3.6A. PGSE has made a commitment to amend the FSAR to include the

ANSI/ANS 58.2-1980 method for jet temperature calculation.

Additional evaluation of the blowdown thrust force interaction with conduit

KK 792 is provided in the DCP External Action Sheet, IDVP File No. 8049,

Revision 10. The PGRE evaluation indicates that the actual jet impingement

3-9

Page 28: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated
Page 29: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

pressure (12.6 psig) on conduit KK 792 is below the allowable jet pressure

(42 psig) as determined by standard Bechtel methodology, and, therefore, the

jet blowdown force from a longitudinal split at node,1800 on line 594 will

have no adverse affect on conduit KK 792. The evaluation provided by PGSE

is sufficient to resolve the concern of EOI File 8049 with respect to jetblowdown thrust force on conduit KK 792.

The concern of EOI File 8049 has been satisfactorily addressed by PGRE. No

physical modifications are required, and this EOI file has been closed.

3.4 EVALUATION OF REVIEW RESULTS

3.4.1 HELB Review

Since only one EOI file was issued with a sample size of 393 break locations

and the concern of that EOI file has been resolved, no generic concern

exists for assurance of adequate separation of the AFW System from the

effects of HELBs outside containment.

3.4.2 IGM Review

Since no EOI files were issued, no generic concern exists for the assurance

of adequate separation of the AFW System from the effects of IGMs outside

containment.

3" 10

Page 30: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

I

Page 31: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

3.5 CONCLUSIONS

3.5.1 HELB Review

No additional verification or sampling is required since no generic concern

was found as a result of the HELB review.

3.5.2 IGM Review

No additional verification or sampling is required.

3-11

Page 32: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

I

Page 33: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

SECTION 4

CONTROL ROOM VENTILATION AND PRESSURIZATION SYSTEM

4.1 DESCRIPTION OF REVIEW

4.1.1 HELB Review

The adequate separation review consists of the determination of CRVP system

targets that may be affected by postulated breaks in high energy lines.

The steps taken to peform the review were as follows:

l. Identified CRVP system mechanical equipment (targets) required to main-

tain Control Room habitability for a HELB outside containment on PG&E

air-conditioning drawings.

2. Identified CRVP electrical components and conduit and I/C lines

(targets) on PG&E electrical drawings.

3. Identified the FSAR Section 3.6A high energy lines and postulated break

locations and type of break on PG&E piping area drawings for the

following high energy systems:

Condensate System

~ Main Steam System

~ Feedwater System

4-1

Page 34: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

~,

Page 35: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

Steam Generator Blowdown System

Steam Supply to the Auxiliary Feedwater Pump Turbine

Extraction Steam and Heater Drip System

Chemical and Volume Control System

Turbine and Generator Associated Systems.

Using the PG&E Line Designation Table (PGSZ Drawing No. 102040, Change

9); all piping that exceeded the 200 F and 275 psig high energy line

criterion was identified on PGSE piping area drawings. The break loca-

tions and types identified in the FSAR Section 3.6A were then located

on these drawings.

4. Identified pipe rupture restraint locations indicated in FSAR Section

3.6A on piping isometric drawings for high energy lines. Piping

isometric drawings were used for configurational purposes only and

primarily for the field verification portion of the review (see Section

8).

5. Established potential interaction zones (cubicles) in the plant for

HELBs and CRVP safety-related targets. The inputs from Sections 1, 2,

a'nd 3 were used to establish plant zones in which a pipe rupture review

occurred. A detailed location listing of all zones within the plant

was prepared for all CRVP system equipment and electrical components,

as well as high energy lines. This information was then transferred by

color codes onto plot plan diagrams at all major plant elevations.

Wherever both color codes for system targets and for high energy lines

4-2

Page 36: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated
Page 37: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

occurred simultaneously in any cubicle, a pipe rupture field verifica-

tion review resulted.

6. Performed the field verification in those interaction zones established

in Section 5.

The steps taken to perform the field verification were as follows:

7. Postulated break points were located in the high energy systems listed

in 3 above. This review consisted of visually verifying that the con-

figuration of the high energy piping was the same as the applicable

PGScE piping area drawings and isometric drawings of FSAR Section 3.6A.

If the piping configuration was different from that shown on the draw-

ings, it was noted and the effects of the relocation on CRVP system

targets evaluated.

8. Rupture restraint locations, types, and configurations on high energy

"lines were verified. FSAR Section 3.6A piping isometrics were used to

identify the location, type, and configuration of the pipe rupture

restraints on the high energy piping run. Restraints were visually

compared to the configuration shown on the isometrics. If a config-

uration or a location difference was encountered, it was noted and the

effects of the relocation of CRVP system targets evaluated.

9. CRVP system mechanical targets and locations were verified. The review

showed that all CRVP mechanical targets required to operate to maintain

Control Room habitability for a HELB outside containment were located

4-3

Page 38: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated
Page 39: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

in plant area "H". Since no HELBs were postulated in this area, an

interaction between HELBs and the mechanical portion of this system did

not occur; therefore, a field review was not performed for the

mechanical portion of the CRVP System.

10. CRVP system electrical and/or instrumentation target locations were

verified. Since the PGSE electrical and instrumentation drawings were

diagrammatic, electrical and instrumentation targets were precisely

located in the field. If a target was affected by jet impingement, the

geometrical relationship between the jet source and target was

sketched. If the effect on a target was from pipe impact, this was

noted.

11. Where HELBs affected system electrical equipment, IRC equipment, or

conduit, it was determined that the conduit was essential by listing

equipment serviced by the conduit and by determining that the serviced

equipment must operate to maintain the Control Room habitability and

bring the plant to a safe cold shutdown.

12. Where safety-related targets in an interaction area were found to be

shielded by structures of substantial size (e.g., building structure,

steel supports, large bore piping, etc), the effects of jet impingement

on the target were considered to be eliminated.

The results of the field review for HELBs are classified into one of the

following categories:

4-4

Page 40: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated
Page 41: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

~ EOI Pile - This document is generated when the licensing commit-

ment for protection assurance (proper restraints, shielding, or

separation) of an essential system or component is not met for

pipe whip or jet impingement from a postulated circumferential or

longitudinal break.

Meets Licensing Commitments - This category is used when a break

is properly restrained, shielded, or separated from a safety-

related target of concern.

4.1.2 IGM Review

The adequate separation review consists of the determination of protection

assurance adequacy of CRVP system targets that may be affected by postulatedt

sources of IGMs.

The steps taken to perform the review were as follows:

l. Identified sources of IGMs from FSAR Section 3.5.

2. Identified CRVP system mechanical and electrical components existing in

the trajectory of the missiles as defined in the FSAR. Locations of

CRVP hardware (ducting, blowers, dampers, etc) were established from

PGSE air-conditioning drawings. Locations of CRVP electrical compon-

ents and conduits were identified in the field.

4-5

Page 42: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated
Page 43: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

3. Identified missile shields or existing structures and components that

behave as effective missile barriers. This was accomplished by a

review of PG&E equipment location drawings. The review consisted of

the identification of natural plant barriers (concrete walls, floor

slabs, large equipment, etc), missile shields and their relationship to

the sources and trajectories of IGMs.~ /

4. Determined if a CRVP system mechanical and electrical component can be

hit by an unshielded missile. This task was performed by a thorough

review of FSAR Section 3.5. The information gathered from this review

were kinetic energies of IGM's, concrete wall penetration depths, and

reasons for not considering analysis (by PG&E). Engineering judgment

was used to determine the validity of the conclusions, especially in

the area where no analysis occurred.

The IGM portion of the review was conducted primarily by a plant walk-

down. Each of the sources of missiles was identified along with the

postulated trajectories. Missile shields and natural plant'arriers,(i.e.,'xisting building structures) were noted. The relationship

between the sources, shields, barriers, walls, floor slabs, and safety-

related targets (if any) were evaluated in the field portion of the

review to determine if safety-related targets would be affected by a

postulated missile event.

5. Where an IGM 'affected system conduits, essential conduits were defined

by listing equipment serviced by the conduit and by determining if the

4-6

Page 44: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated
Page 45: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

connected equipment must operate to maintain Control Room habitability

and to bring the plant to a safe cold shutdown.

6. Where an IGM affected system components (ducting, blowing, dampers,

etc), essential components were defined by determining that the

affected components must operate to maintain Control Room habitability

and to bring the plant to a safe cold shutdown.

The steps taken to perform the field verification were as follows:

7. Located the sources of IGMs identified in the FSAR Section 3.5, Page

Sb. The sources are:

Hain Turbine

o Main Feedwater Pump Turbine

4 Auxiliary Feedwater Pump Turbine.

8. Located mechanical and electrical safety-related targets. See Section

4.1.1 (9. and 10.).

9. Located missile shields and exisiting structures and/or components

which act as barriers.

The results of the field review for IGMs are classified into the following

categories:

4-7

Page 46: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated
Page 47: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

4 EOI File - This document is generated when the licensing commit-

ment for protection assurance of an essential safety-related

target is not met for the effects of an IGM.

Meets Licensing Commitments - This category is used when an IGM is

shielded or does not intersect a target in its trajectory.

4.2 SUMMARY OF REVIEW RESULTS

4.2.1 HELB Review

314 Break Locations were identified.

31 Restraints and restraint locations were identified.

12 Electrical and I/C targets were located.

2 EOI files were issued.

4.2.2 IGM Review

0 EOI files were issued.

3 IGM sources were identified.

Plant barrier was verified for the Feedwater Pump Turbine missile.

4.3 EOI REPORTS ISSUED

Two EOI files were issued as a result of the review of effects of postulated

HELBs on the CRVP system containment.

4-8

Page 48: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated
Page 49: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

EOI File 8007 was issued because of concern over potential damage to CRVP

electrical conduit K6844 resulting from the pipe whip effects of a postu-

lated circumferential break at node 3510 on Main Steam Line No. 3.

EOI File 8008 was issued because of concern over potential damage to CRVP

electrical conduit K6844 resulting from the pipe whip effects of a postu-

lated circumferential break at node 4145 on Main Steam Line No. 4.

EOI Files 8007 and 8008 share a common concern; therefore, the following

discussion will address both Open Item files concurrently.

PGSE has provided additional evaluation (DCP Completion Sheet for EOI File8007, Revision 2, signed February 18, 1983, and DCP Completion Sheet for EOI

File 8008, Revision 2, signed February 18, 1983) of the pipe whip effects of

postulated circumferential breaks in the relief valve headers of Main Steam

Lines No. 3 and No. 4, at nodes 3510 and 4145, respectively. The PG&E

response indicates that the postulated accident sequence defined in EOI

Files 8007 and 8008 is not required as a design basis. This positionrepresents an interpretation of Paragraph 1(d) of the AEC letter from A.

Giambusso to F. T. Searls (PGSE), dated December 18, 1972, in that:

a. the dead-ended section of the main steam header does not have

sufficient, internal energy to produce pipe whip because of itslimited pressure reservoir; and

b. steam blowdown from the opposite end of the postulated break

represents an energy source external to the dead-ended section of

4-9

Page 50: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

I

Page 51: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

the header, and, consequently, need not be considered for pipe

whip of the dead-ended section of header.

The Nuclear Services Corporation (NSC) report on rupture restraints outside

containment indicates that the existing restraints on the main steam headers

are inactive, which is consistent with the DCP position taken. From NSC

Report, PGE 01"28, Table 7-5, which compares allowable restraint loads with

applied restraint loads, there are no applied loads listed nor protection

requirements specified for either restraint 1030-14RT or 1031-11RT.

In addition to the PG&E response provided, the specific concerns of EOI

Files 8007 and 8008 (i.e., potential damage to conduit K6844) have been

further evaluated by'he IDVP. Utilizing information gathered since these

EOI files were initially written, the IDVP has conducted a systems safety

evaluation which concluded that the cables in conduit K6844 are not

essential for reactor shutdown under the conditions associated with the

postulated main steam breaks at nodes 3510 and 4145.

On the basis of the additional evaluation and analysis provided, the con-

cerns of EOI Files 8007 and 8008 have been resolved, and these files have

been closed.

4-10

Page 52: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated
Page 53: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

4.4 EVALUATION OF REVIEW RESULTS

4.4.1 HELB Review

Since only two EOI files were issued with a sample size of 314 break

locations and the concern of those EOI files has been resolved, no generic

concern exists for assurance of adequate separation of the CRVP System from

the effects of HELBs outside containment.

4.4.2 IGM Review

Since no EOI files were issued, no generic concern for the assurance of

adequate separation of the CRVP from the effects of IGMs outside contain-

ment.

4.5 CONCLUSIONS

4.5.1 HELB Review

No additional verification or sampling is required since no generic concern

was found as a result of the HELB review.

4.5.2 IGM Review

No additional verification or sampling is required.

4"11

Page 54: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

~ 4J

Page 55: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

APPENDIX A

EOI FILES

Page 56: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

) ~J

Page 57: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

APPENDIX A

REVH 0

DCHPP IDVP STATUS REPORT

LATEST REVH

FILE HOB

8007

8007

8007

8007

8007

8007

8007

8008

8008

8008

8008

8008

8008

8008,8049

8049

8049

8049

80498049

8049

8049

8049

8049

IN980498049

8049

8049

8049

8049

DATE

820913

820913

820913

82%13820913

820913

820913

820913

820913

820913

820913

820913

820913

820913

821025

821025

821025

821025

821025

821025

821025

821025

821025

821025

821025

821025

821025

821025

821025

821025

821025

REVR

0

1

2

3

5

6

01

2

3

4

5

6

0

1

23

5

6789

10

11

12

13

14

15

ie

DATE

820913

821001

821018

830225

830304

830310

830310

820913

821001

821018

830225

830304

830310

830310

821025

821026

821029

821207

821215

830103

830111

830207

830309

830309

830406

830406

830406

830428

830503

830509

830509

BY

%EC

%EC

TES

TES

SMEC

TES

TES

SMEC

%EC

TES

TES

%EC

TES

TES

%EC

%EC

TES

TES

%EC

TES

TES

%EC

TES

TES

TES

%EC

TES

TES

%EC

TES

TES

STATUS

OIR

PPRR/OIP

PRR/OIP

OIR

PPRR/CI

PRR/Cl

CR

OIR

PPRR/OIP

PRR/OIP

OIR

PPRR/CI

PRR/CI

CR

OIR

PPRR/OIP

PRR/OIP

OIR

PPRR/OIP

PRR/OXP

OIR

PPRR/CI

PRR/Cl

CR

OXR

PPRR/OIP

PRR/OIP

OIR

PPRR/CI

PRR/CI

CR

SUBJECT

EFFECT OF THE BREAK-PIPE RCPT

EFFECT OF THE BREAK-PIPE RUPT

EFFECT OF THE BREAK"PIPE RUPT

EFFECT OF THF. BREAK+XPE RUPT

EFFECT OF THE BRBK-PIPE RUPT

EFFECT OF THE BRFAK-PIPE RUPT

EFFECT OF THE BRBK"PIPE RUPT

EFFECT OF THE BREAK-PIPE RUPT

EFFECT OF THE BREAK"PIPE RUPT

EFFECT OF THE BREAK+IPE RUPT

EFFECT OF THE BREAK"PIPE RUPT

EFFECT OF THE BREAK-PXPF. RUPT

EFFFCT OF THE BREAK-PIPE IlPTEFFECT OF THE BREAK+IPE RUPT

AFM SYSTEM-PIPE BREAK XH LIHE

AFM SYSTEM-PIPE BREAK IH LINE

AFM SYSTEM'IPE BRBK XH LIHE

AFM SYSTEM-PIPE BREAK Ik LIHE

AFM SYSTEM-PIPE BREAK Ik LIHE

AFM SYSTEM+IPE BRBK IH LIHE

AFM SYSTEM-PIPE BRBK IH LIHE

AFM SYSTEM-PIPE BREAK IH LIHE

AFM SYSTEM-PIPE BREAK IH LIHE

AFM SYSTEM-PIPE BREAK IH LIHE

AFM SYSTEM+IPE BREAK IH LIHE

AFM SYSTEM-PIPE BRBK IH LINE

AFM SYSTEM-PIPE BREN IH LXHE

AFM SYSTEM-PIPE BREAK IH LIHE

AFM SYSTEM-PIPE BREAK IH LIHE

AFM SYSTEM-PIPE BREAK IH LIHE

AFM SYSTEM"PIPE BREAK IH LIHE

RESTRAIHT

RESTRAIHT

RESTRAIHT

RESTRAIHT

RESTRAIHT

RESTRAIHT

RESTRAIHT

RESTRAIHT

RESTRAIHT

REST RAIkT

RESTRAIHT

RESTRAIHT

RESTRAIHT

RESTRAIHT

594

594

594

594

594

594

594

594

594594

594

594

594

594

594

594

594

1030-14RT

1030-14RT

1030-14RT

1030-ihRT1030-14RT

1030-14RT

1030-14RT

1031"11RT

1031"11RT

1031"11RT

1031-11RT

1031-iiRT1031-iiRT1031-11RT

Page 58: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

I

Page 59: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

APPENDIX B

PROGRAM MANAGER'S ASSESSMENT

Page 60: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

C II

Page 61: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

APPENDIX B

PROGRAM NNAGER'S ASSESSMENT

Independent review by TES of the tasks performed by SWEC to verify theHELB and IGM outside containment for 'he AFW System and CVRP System.wasdone in accordance with IDVP Phase II Program Management Plan datedJune 18, 1982 and the Engineering Procedure EP-1-014.

The review involved a visit to the site and several visits to the SWEC

offices for detailed discussions and review, wi th SWEC personnel, of thework performed by SWEC including the methodology used in the evaluation ofthis task.

The files issued by SWEC were reviewed thoroughly and specificrecommendations were made to the IDVP Program Manager delineatingappropriate resolution.

As a result of the verification of the initial sampling selected bySWEC and the assessment of the impact of SWEC findings, TES as ProgramManager, is of the opinion that no additional verification is required.

Page 62: Rev 1 to 'Verification of High Energy Line Break & Internally … · 2017. 2. 28. · interimtechnicalreport 23 revision 1 verification of high energy line break and internallygenerated

~ ~