Upload
others
View
8
Download
0
Embed Size (px)
Citation preview
TR-9419-CSE96-1101, Rev. 0 Attachment 2 Page 1 of 23
Attachment 2
Test Procedure and Completed Data Sheets
qezoa80<04 qesm4PDR ADQCK 05000335,P PDR
ABB Combustion Engineering Nuclear Operations
TR-9419-CSE96-110 Attachment 2 Page 2 of 23
TP-9419-CSE96-2104, Rev. 0 Page 1 of 11
Test Procedure
Steam Generator Tube
In-Situ Hydrostatic Pressure Test Tool
Hydro Chamber Pressure Determination
Procedure No. TP-9419-CSE96-2104 Rev. 0
ABB Combustion Engineering Nuclear Operations
Prepared By;
Reviewed By: 54'c dt .4c~K F. AUea. Coaaeehene Enynocr
Date;
Approved By: +C eMerero+J. F. HalL Frmcepal C
Date:
Approved By.J. D. FcrreL Manager. Field r Opcranexn
ABB Combustion Engineering Nuctear Operations
ABB Combustion Engineering Nuclear Operations
TR-9419-CSE96-1101, Rev. 0 Attachment 2 Page 3 of 23
TP-9419SE96-2104, Rev. 0 Page 2 of 11
Table of Contents
Section ntents P~ae No
lo
20
3,0
4.0
5.0
6.0
Objective
References
Quality Assurance
Discussion and Background
Prerequisites
Limitations and Precautions
70 Test Procedure
7.1
72
Static Test
Dynamic Test
Figure 1
Data Sheet 1, Static Pressure Test
Data Sheet 2, Dytmnic Pressure Test
Data Sheet 3, Remark Continuation Page
Attachment 1 Faxed cover sheet with Review and Approval Signatures
10
ABB Combustion Engineering Nuclear Operations
ABB Combustion Engineering Nuclear Operations
TR-9419-CSE96-1101,—Rev. 0- Attachment 2 Page 4 of 23
TP-9419-CSE96-2104. Rav. 0 Page 3 of 11
I.O Objective
The objective of this test is to determine the relationship between the hydro pump outletpressure, the hydro chamber pressure and the seal bladder pressure under flow conditionsfor the steam generator localized in-situ presswe test tools. In addition, static testing willbe performed to establish a baseline relationship under non-flow conditions. The dataunder flow conditions willbe used to ensure that in the event ofa leaking defectindication, the leakage rate is measured at the appropriate pressure(s) within the hydrochamber. Testing willbe performed on both the axial and circumferential tools.
20 References
2.1 QAM-100, Fourth Edition, Revison 4
2.2 Final Test Report for the Steam Generator Tube In-Situ Hydrostatic Test Tool.TR-ESE-'030,
Rev, 00, T. R. No. 83D, dated April 5, 1994.
3.0 Quality Assurance
The test described herein is to be treated as Safety Related, Quality Class 1, in accordancewith the requirements in Reference 2.1.
4.0 Discussiori and Background
Reference 2.2 describes the development and qualification testing for the localized in-situtest tool. The tool described in Reference 2.2 was developed to pressure test primarilycircumferential defect indications in steam generator tubes at the tubesheet region. It isalso applicable to the testing ofaxial indications. An additional tool was evolved for thctesting ofaxial defects which are greater in length than those which can be accommodatedby the hydro chamber in thc original tool. Since the tool design for the circumferentialdefects has greater restrictions than those for axial defects, thc test report is bounding forthe axial tool.
The localized test tool contains two pressure circuits; one for seal and gripper bladders,and onc for the hydro chamber. The hydro chamber circuit is pressurized by an airoperated positive displacement pump. The bladder circuit is pressurized by either an air
operated positive displacement pump or a hand pump.
The positive displacement pumps used in the system are able to maintain a precise controlat a given static pressure. Under flow conditions, such as those experienced during a tubeleak. the pump discharge pressure fluctuates between a high and low limitwith each pumppulse. The magnitude of this band is a function of the flow rate and the restrictions withinthe hose/tool assembly. Due to these dynamic head losses, the actual pressure in thchydro chamber willbe less than that observed at the pump discharge.
ABB Combustion Engineennp Nuciear Operations
ABB Combustion Engineering Nuclear Operations
TR-9419-CSE96-1101, Rev. 0 Attachment 2 Page 50f23
TP-9419-CSE96-2104, Rev: 0 Page 4 of 11
Reference 2.2 describes testing which was performed under flowconditions to establishthe relationship between the hydro pump discharge pressure and the hydro chamberpressure. This test consisted ofmeasuriiig the swing of the pressure gauge at thedischarge ofthe hydro pump at various leak rates at an initial static hydro chamberpressure of4,000 psig as directly measured in a controlled leak test fixture.Implementation ofthis data in an in-situ field test requires an iterative process as the hydrochamber pressure is not directly measurable. The process involves matching the pumpdischarge pressure swing relative to the desired pressure and observe the pump stroke rateas compared to the data in the test report. In addition, the test report explicitly states thatthe leak rate correction data apply only to the as-tested configuration.
For the testing at St. I.ucie Unit I, it was requested that the capability be provided to testin the straight tube portions at elevations well above the tubesheet. This necessitated thefabrication ofhoses longer than those described in Reference 2.2. For non leaking defectindications. the length of the hose does not affect measuring the desired pressure in thehydro chamber as the system is static and the pressure is equal to that at the pumpdischarge. For leaking defects, the change in system resistance due to the change in hoselength does have an effect on the dynamic response ofthe pump discharge pressure gaugeand its subsequent relationship to the hydro chamber pressure. Consequently, for aleaking defect, the actual pressure in the hydro chamber is indeterminate withoutadditional testing.
In order to determine the pressure in the hydro chamber with the current hoseconfiguration, two methods willbe considered.
I) Hydro pump discharge pressure swing correlation method, and,
2) Seal bladder pressure intensification method.
Item l is the method described in Reference 2.2. Item 2 is based upon an observationduring laboratory testing and field application. Experience during previous testing hasshown that the bladder circuit pressure increases as its initial pre-charge pressure isapproached by the increasing pressure in the hydro chamber. This pressure increase hasbeen termed 'intensification.'nce the bladder pre-charge pressure is reached in thehydro chamber, the bladder pressure willincrease with increasing hydro chamber pressure.This pressure has been observed to be approximately 200-300 psid under static conditions.It is expend that the relationship willbe similar under flow (leak) conditions.
Establishing this relationship willprovide an accurate, indirect method of measuring thepressure in the hydro chamber under leaking conditions. As the bladder circuit is not in aflow path, there are no head losses to consider. Pulsations may be evident in the bladdercircuit due to the reciprocating nature of the hydro pump. However, these pulsations willreflect the true pressure in the bladder circuit independent of the head losses experienced
ABB Combustion Engineering Nuctear Operations
ABB Combustion Engineering Nuclear Operations
TR-9419-CSE96-1101, Rev. 0 Attachment 2 Page 6 of 23
TP-941&CSE96-2104, Rev. 0 Page 5 of 11
by the hydro circuit. By inference, the pressure in the hydro chamber can then bedeterminNL
This test willfocus on establishing method 2 as the method ofchoice for determining thehydro chamber pressure under flow conditions. However, additional data willbe recordedin order to provide for the use ofmethod 1 should method 2 prove to be invalid.
5 0 Limitations and Precautions
5.1 As noted in Section 4, the method 1 correlation is a Function of system dynamicresistance. Use of the test results in method 1 correlations is limited to systems with anidentical configuration to that tested. The hose configuration in this test is identical to thatin Figure 2 ofReference 2.2 with the exception that the length of the 3/16" braided hosehas been increased from 30 feet to 50 feet. Use of the longer hose length in the test willqualify method 2 fo'r use in the as tested configuration..
6.0 Prerequisites
6.1 Allpressure gauges to be used in the test shall be verified to be within the calibrationperiod.
NoteThe test procedure is intended to provtde a protocol. It is notintended to limitthe type of testing conducted. As an example,«ddittonal pressures may be tested or conditions changed in order toadapt to lessons learned during the test. Any changes or additionsshaH be recorded and explained on the appropriate data sheet. Blankdata sheets may be copied to provide for each parameter change.
NoteMinor leakage may occur during the conduct of this test.Acceptability of leakage with respect to continued operation of thetest is at the discretion of the test operator. However, any leakageshaH be recorded in the remarks section of the data sheet.
7 0 Test Procedure
NoteThe static test will be performed using both the circumferential/axialtool and the long axial tool. The order of performance is at thediscretion of the test operator. Data sheet 1 is used to recordinformation for the static test.
A88 Combustion Engineering Nuciear Operations
ABB Combustion Engineering Nuclear Operations
TR-9419-CSE96-110'1. Rev. 0 Attachment2 Page7of23
TP-9419-CSE96-2104, Rev. 0 Page 6 of 11
7,1.1 Assemble the test fixture, in-situ tool and pump circuits as shown in Figure l. Record the
tool (circ. or long axial), hydro pump pressure gauge, hydro chamber pressure gauge and
bladder pressure gauge serial numbers on the data sheet.
712 Operate the bladder pump to fillthe bladder circuit tubing with water. Pressurize the
bladder circuit to approximately 4,000 psig ~200 psig and release the pressure at the
pump discharge. Repeat this process at least 10 times to remove air from the bladder
CIrcuit.
713 Using the bladder pump, pressurize the bladder circuit to an initial pressure of 1,500 psig= 100 psig as indicated by the bladder pressure gauge. Observe the pressure gauge
reading to ensure that there are no significant leaks. Record the initial bladder pressure
9 0 psig hydro chamber pressure on Data Sheet 1.
7,1.4 Close/verify closed'the leak rate control valve.
NoteThe static test is to be conducted at target hydro chamber pressures of1,500, 1,600, 1,800, 3,000, 4,000 and 5,000 psig.
7.1,5 Pressurize the hydro circuit to the target pressure s 100 psig as indicated by the hydro
chamber pressure gauge. Observe for leaks and steady pressure readings on all gauges.
Record all pressure gauge as read values on the data sheet. Repeat this step for each ofthe target pressures fisted on the data sheet.
7.1,6 Ensure all necessary data have been recorded on the data sheet, signature and date signify
completion.
7 1,7 Repeat steps 7.1.3 through 7.1.6 for an initial bladder pressure of 2,000 psig < 100 psig.
7 1.8 Repeat steps 7.1.1 through 7.1,7 for the second tool.
7 2 ~Dggj~g
NoteThe dynamic test willbe performed using both thecircumferential/axial tool and the long axial tool. The order ofperformance is at the discretion of the test operator. Data sheet 2 is
used to record information for the dynamic test.
7 2,1 Assemble the test fixture, in-situ tool and pump circuits as shown in Figure 1. Record the
tool (circ. or long axial), hydro pump pressure gauge, hydro chamber pressure gauge and
bladder pressure gauge serial numbers on the data sheet.
ABB Combustion Engineenng Nuciear Operations
ABB Combustion Engineering Nuclear Operations
I+ W'/
TR-9419-CSE96-1101 Rev. 0. —. Attachment 2 Page 8 of 23
TP-941 94SE96-2104, Rev. 0 Page 7 af 11
,NoteIfthe hydro tool has not beta separated from the hose, the bladdercircuit does not require degassing and the following step is N/A.
7,2.2 Operate the bladder pump to fillthe bladder circuit tubing with water. Pressurize thebladder circuit to approximately 4,000 psig a 200 psig and release the pressure at the
pump discharge. Repeat this process at least 10 times to remove air from the bladderCircuit.
7.2.3 Using the bladder pump, pressurize the bladder circuit to 1,500 psig ~ 100 psig as
indicated by the bladder pressure gauge. Observe the prcssure gauge reading to ensurethat there are no significant leaks. Record the initial bladder pressure 0 psig hydrochamber pressure on Data Sheet 2.
7.2.4 Close/verify closed the leak rate control valve.
NoteThe dynamic test is to be conducted at target hydro chamberpressures of 1,700, 3,000, 4,000 and 5,000 psig. Each target pressurerequires a separate data sheet.
7.2.5 Pressurize the hydro circuit to the target pressure + 100 psig as indicated by the hydrochamber pressure gauge. Observe for leaks and steady pressure readings on all gauges.Record all static pressures as the zero pump rate values.
P
NoteIterative adjustment of the leak rate control valve aad the hydropump air control regulator willbe for establishing the desired pumpstroke rate at a given target hydro chamber pressure.
7 2.6 Slowly open the leak rate control valve to establish a hydro pump stroke rate of 20strokes/minute while maintaining thc target pressure as indicated by thc hydro chamberpressure gauge. Adjust the hydro pump air control regulator and the leak rate controlvalve as necessary. Ifthe hydro chamber pressure is not steady, adjust to the targetpressure at approximately the middle of the swing. Record all prcssure reading's on thedata sheet. Repeat this step for each of the pump stroke rates listed on the data sheet.
7,2.7 Ensure all necessary data have been recorded on the data sheet, signature and date signifycompletion.
7,2.8 Repeat step 7.2.4 through 7,2.7 for each of the target pressure values.
7.2.9 Repeat steps 7.2.1 through 7.2.8 for the second tool.
ABB Combustion Engineering Nuciear Operations
ABB Combustion Engineering Nuclear Operations
A.h
CD0)O0UCr/l
0DfllD(O
(D(D
(0ZCorDQ
0(D
0DVl
OO3FLtO
fn4.
g
82',
Q
0
I I-lydro
Pump
IlydroPumpGauge
In-Situ Tool
Steam GeneratorTube
Bladder Pressure
Gauge
HydroChamber
Figure 1
Test Apparatus Configuration
Hydro ChamberGauge
Leak Rate
Control Valve
Bladder
Pump
TR-9419-CSE96-1101, . Rev. 0 Attachment 2 Page 10 of 23
TP-941 &CSE96-2104, Rev. 0 Page 9 of 11
Data Sheet 1
Static Pressure Test
Tool (circ. or long axial)
Initial Bladder Pressnre~sig
Target HydroChamber Pressure
S1
Observed HydroChamber Pressure
S1
Hydro PumpDischarge Pressure
( si
Bladder Pressure
SI
Hydro Pump Discharge Pressure Gauge No.Hydro Chamber Pressure Gauge No.Bladder Pump Discharge Pressure Gauge No.
Remarks:
Completed by:Name tSitsaaatre
Date:
Witnessed by:Name ~signattle
Date:
ABB Combustion Engineenng Nudear Operations
ABB Combustion Engineering Nuclear Operations
/+w ~g
TR-9419-CSE96-1101, Rev. 0 Attachment 2 Page 11 of 23
TP-941&CSE96-2104, Rev. 0 Page 10 of 11
Data Sheet 2
Dynamic Pressure Test
Tool (circ. or long axial)
initial Bladder Pressure psig Hydro Chamber Target Pressure pstg
Pump Rate
Strokes/min
0 static20
40
6080
100
Hydro ChamberPressure"'t
Maximum Minimum
Hydro PumpDischarge Pressure"
( siMaximum
Bladder Pressure"'
siMaximum Minimum
Notes: i) For non-fiuctuaung pressure values. record pressure as the maximum pressure achieved.
Hydro Pump Discharge Pressure Gauge No.Hydro Chamber Pressure Gauge No.Bladder Pump Discharge Pressure Gauge No.
Remarks:
Completed by:Name. Signamre
Date:
Witnessed by:Nuns.signamn
Date:
ABB Combustion Engineering Nuclear Operations
ABB Combustion Engineering Nuclear Operations
TR-9419-CSE96-1101~ev 0. Attachment 2 Page 12 of 23
TP-941 &CSE96-2104, Rev. 0
Data Sheet 3
Remark Continuation Page
Page 11 of 11
Test (static or dynamic
Initial Bladder Pressure
Tool (circ. or long axial)
psig Hydro Chamber Target Pressure pstg
Remarks:
Completed by:.'rane isigaature
Date:
Witnessed by:.'raaa signamre
Date:
ABB Combustion Engineering Nuctear Operations
ABB Combustion Engineering Nuclear Operations
TR-9419-CSE96-1 1Gi~aLQ Attachment 2 Page 13 of 23
Z8 d~ ZG'%Md 'WLQi ~ M:LZ 966TWV~
~~$w~f g Q ~p j'y6'Msprd-2l/ gcuo
TP-941~EBS-2104. Rev. 0 Pe 1 of 11
Test Procedure
Stcam Generator Tube
In4itu Hydrostatic Pressure Test Tool
Hydro Chamber Pressure Determination
Procedure No. TP-9419 CSE96-2104 Rev. 0
ABB Combuarion Engineering hhclear Operations
Prepared By:
6,5. cd nse:~6- o- L
Approved By:a R A<4 Kaaa~r, fic14 geary~ Dare:
ASS Combuarion Enqinwring Naalaar operations
Jul LG '96 l4:51
ZGrZG'd G6Z~~t Ol telic SSZ G98
TOTAL P.82
ABB Combustion Engineering Nuclear Operations
TR-9419-CSE96-1101, Rev. 0 Attachment 2 Page 14 of 23
TP-9419-CSE96-2104, Rev. 0 Page 9 of 11
Data Sheet 1
Static Pressure Test
T I( '*. I g 'd)~initial Bladder Pressure~Is ~ sig
Target HydroChamber Pressure
S1
/ tabs
Ige'/Ossa
4 >ssn
hatt~
Observed HydroChamber Pressure
Sl
5'oo/4 "c
Hydro PumpDischarge Pressure
S1
I 5oc(ge-r Zo~3cc=
sstC~o
Ste&O
Bladder Pressure
S1
g)h3v~ K'43$ ,0 +
Hydro Pump Discharge Pressure Gauge No. 5,- Io - r~ ~lHvdro Chamber Pressure Gauge No. A- 7 - oo 0Bladder Pump Discharge Pressure Gauge No. W-n' zo>M
Remarks:
Completedby: C~>z,,~ <~k.'Nacm s Silttgure
Witnessed by: 3 I ~ < lol.Vattse Sittaatttre
Date: 4 « ~~
Date:~<a/ Rte
ABB Combustion Engineering Nuctear Operations
ABB Combustion Engineering Nuclear Operationsp+->)
TR-9419-CSE96-11 Attachment 2 Page 15 of 23
TP-941 &CSE96-2104, Rev. 0 Page 9 of 11
Data Sheet 1
Static Pressure Test
Tool (circ. or long axial)
Initial Bladder Pressnre~gee= sig
Target HydroChamber Pressure
SI
1 Ir"oa
Q tteIOO
tasse~
Observed HydroChamber Pressure
s1
I 5ow
dt OC
Hydro PumpDischarge Pressure
( si
/tssoo
3 05o~ee=miso a
Bladder Pressure
( si
+2 So
Hydro Pump Discharge Pressure Gauge No. rS - r -IWIHydro Chamber Pressure Gauge No. FS — I I - o3~Bladder Pump Discharge Pressure Gauge No. - - o<M
Remarks:
Completed by: Ct=-~Vane; Silsatstrn
Date: ~ " ~8
slatsse St tnatttrts
ABB Combustion Engineenng Nuoiear Operations
ABB Combustion Engineering Nuclear Operations
TR-9419-CSE96-1101-,-Rev. 0 Attachment 2 Page 16 of 23
TP-941&CSE96-2104, RN'. 0
Data Sheet 1
Static Pressure Test
Page 9 of 11
Tool (circ. or long axial) r QC .
Initial Bladder Pressure~/3'uc sig
Target HydroChamber Pressure
( si
/4 oo
'3 oooQeo0
OO
Observed HydroChamber Pressure
SI
gooIbm'7
ogoo
Hydro PumpDischarge Pressure
st
i geoIS oel8oG3ccQdf(g ~
Bladder Pressure
( si
I $ 00
20 m-a
Sl ~Ct
~I5ogt go z.
Hydro Pump Discharge Pressure Gauge No. - l - oHydro Chamber Pressure Gauge No. S - I - loO 3~Bladder Pump Discharge Pressure Gauge No. S - ( 7 - laO 33
Remarks:GI<t Lf LH~~ Q ~: A owg 5~,% Qj-sp o, ~ 5th'K-(<) S Q Caw,t
"Is4sa Mi w W k. g I
Completed by: C~u~~a l-r ~kstuns tSirtaarttrc
Wiutessed by: .~ f'f:.'Iarrsc Siltarttrc
Date: < '> ~<
Date:~d-Vd
ABB Combustion Engineering Nuotear Operations
ABB Combustion Engineering Nuclear Operations
TR-9419-CSE96-1101, Rev. 0 Attachment2 Page17of23
TP-9419-CSE96-2104, Revs 0 Page 9 of 11
Data Sheet 1
Static Pressure Test
Tool (circ. or long axial) C QC
Initial Bladder Pressnre~2seo sig
Target HydroChamber Pressure
SI
t ~aO
/bt 4
i go~.tso cd
df dt O a
~C~
Observed HydroChamber Pressure
SI
l g)c
f7~~gg~ oeeoc~oo
Hydro PumpDischarge Pressure
SI
t5ctQs o
IGcc3~
Bladder Pressure
SI
'Coo Ot
sst 35'O
QgaQ
8 20~ (t)Qg6~ Z
Hydro Pump Discharge Pressure Gauge No. 5-i 3 - LdeelHydro Chamber Pressure Gauge No. PS - i l - eo 3
Bladder Pump Discharge Pressure Gauge No. 5- I - leos s
RemarkS: ( ) 5c, 4 gc.40O~ 6 -~d~~ R.A ~i~.- ~ J.~ ~ADO~~S
(2X S< 4 Ittt.a ~ - ~ L1t 2u S Aoo tes
)n ~.~ Q al ( S~t tusaa Z~~. O aWf'0
Completed by: C~t-./eP/aD F/~ IC.'st aalu Sittaatttte
Witnessed by: . Woi.'same Stttatttre
Date: ~6/ / pts
Date: Co-/(-~4
ABB Combustion Engineering Nuotear Operations
ABB Combustion Engineering Nuclear Operations
TR-9419-CSE96-1101, Rev. 0- Attachment 2 Page 18 of 23
TP-9419-CSE96-2104, Rev. 0 Page 10 of 11
Data Sheet Z
Dynamic Pressure Testr
Tool (circ. or long axial) 5t 0 L
initial Bladder Pressure I >~> psig Hydro Chamber Target Prmeuref keio pdg
Pump Rate
Strokes/min
Hydro ChamberPressure'"
st
Hydro PumpDischarge Pressure "
( si
BladderPressure"'t
Maximum Minimum Maximum Minimum Maximum Minimum
0 (static)
100
/&5olpga o
/g uO
l7o~l9cc
5ptoo
I '7 >t=e
I 7am
/~>of lo&/go>
/g@ o
j 9co
/EoO
r9su
Notes: t) For non-ftuctuaung pressure values. record pressure as the maximum pressure achieved.
Hydro Pump Discharge Pressure Gauge No. 6's - l7- l c ~ t
eye ch b p* G re.~Bladder Pump Discharge Pressure Gauge No. F5-l'7-l«~9
Remarks:
Completed by:Vgmg rSithggttyg
(:7 Date: < I ~<
Witnessed by:Vgmg ignanae
Date: 6-il-C
ABB Combustion Engineering Nuctear Operations
ABB Combustion Engineering Nuclear Operations
p4-5 i
TR-9419-CSE96-1101„~ev. 0 Attachment 2 Page 19 of 23
TP-941 &ZSE96-2104. Rev. 0 Page 10 of 11
Data Sheet 2
Dynamic Pressure Test
Tool (circ, or long axial) %t AL
Initial Bladder Pressure le~ psig Hydro Chamber Target Pressure 38~~ psig
Pump Rate
Strokesimin
0 static)
Hydro ChamberPressure'"
SI
Maximum Minimum Maximum Minimum
Qqoo
Hydro PumpDischarge Pressure"'l
Bladder Pressure"'
sitMaximum Minimum
geoPZgl40.Qj Q100
'3looQ)v3 5~qD
gqoC0'%co
A/00 f+oo
Q7 oo oc
$ 2Oe-
/goo
gazoo
Notes: l) For non-lluctuating pressure values. record pressure as the maximum pressure achieved.
Hydro Pump Discharge Pressure Gauge No.Hydro Chamber Pressure Gauge No. - s - l s - I 49'
Bladder Pump Discharge Pressure Gauge No. A-(7- Ic933
Remarks:
Completed by: C ~ g CI-i~ 5vame tSiltature
Witnessed by: ec i~V tStttanare
e
Date:~i
A88 Combustion Engineering Nuclear Operations
ABB Combustion Engineering Nuclear Operations
r~-: <
TR-941 9-CSE96-1 101,>ev 0 Attachment 2 Page 20 of 23
Tp-941 9-CSE96-2104, Rev. 0 Page 10 of 11
Data Sheet 2
Dynamic Pressure Test
Tool (circ. or long axial) 'i(> I >~>aq~~
Initial Bladder Pressure I zc 0 psig Hydro Chamber Target Pressure+~4+ psig
Pump Rate
Strokes/min
Hydro ChamberPressure"'t
Maximum Minimum
Hydro PumpDischarge Pressure '
siMaximum Minimum
Bladder Pressure'"
slMaximum Minimum
0 static) b+~ 8'I~o&20 t8 +ceo
!liO
Q7E)C)
80100
Notes: i) For non-fluctuaung pressure values. record pressure as the maximum pressure achevcd.
Hydro Pump Discharge Pressure Gauge No. PS -l1 - I o~~ IHyd Ch b P G gNBladder Pump Discharge Pressure Gauge No. Cs-t7-too33
Remarks:
Completed by:.'rane isignanue
Date: rl '< 9<
Witnessed by:v siyenee
Date: 6 ~i 5'6
ABB Combustion Engineenng Nuctear Operations
ABB Combustion Engineering Nuclear Operations
+-3 i
TR-9419-CSE96-1101;.Re. e--- Attachment 2 Page 21 of 23
TP-941&CSE96-2104, Rev. 0 Page 10 of 11
sr 'rr
Tool (circ. or long axial)
Data Sheet 2
Dynamic Pressure Test
lultlal Bladder Pressure~the-'h psig Hydro Chamber Target Pressure J1+0 pslg
Pump Rate
Strokes/min
. Hydro ChamberPressure"'I
Hydro PumpDischarge Pressure "
sl
Bladder Pressure "
( siMaximum Minimum Maximum Minimum Maximum Minimum
0 static) l ~ ~ l1+~ tgOO
60 Q gether~o DesWee
]g Cu
1'Voa
< A-ai~5Q/Qoc:I Zcy»
I3o~
IQ~odt I 0t-"s
/dr'eo
/6OO/ 4tao/bet ol7ZO
l7om
7oo
g. Ieto
t75 ot160r Pcycp
Notes: t) For non-fluctuaung pressure values. record pressure as the maxtmum pressure achiared.
Hydro Pump Discharge Pressure Gauge No. s- i7- foalhid Ch I Ih o h*ha.~Bladder Pump Discharge Pressure Gauge No. 5- 6- Ia»>
Remarks: lo
I
Completed by; C vz a I-h~ kVgtttc h St ttgtttye
Witnessed by:V .Sittgtttgg
Date:~th/rr
ABB Combustion Engineering Nuclear Operations
ABB Combustion Engineering Nuclear Operations
TR-94'i 9-CSE96-1101,,R&V. 0 Attachment 2 Page 22 of 23
TP-9419-CSE96-2104, Rev. 0 Page 10 of 11
Data Sheet 2
Dynamic Pressure Test
Tool (circ. or long axial) A~ <
fnitial Bladder Pressure t ~cs~ psig Hydro Chamber Target Pressure 3t"S o psig
Pump Rate
Strokes/min
Hydro ChamberPressure"'l
Hydro PumpDischarge Pressure"'l
Bladder Pressure'"
Sl
0 static)
Maximum Minimum Maximum
%5 5C'ryos
Minimum
3/o"Maximum Minimum
100
>So~
n es o
3~o
dl e~7~o
$ rfoo
'3 goo
$gOO
9(oestqOsO
Q v~0~
Q clasO
ggoQQ ~c2
IL 9'~o 39~D
Notes: l) For non-Auctuaung pressure values. record pressure as the mmumum pressure achieved.
Hvdro Pump Discharge Pressure Gauge No. 55- I 1 - loooIHvdro Chamber Pressure Gauge No. s -I —I~ >~Bladder Pump Discharge Pressure Gauge No. E5- f '7 -0~2~
Remarks:
Completed by:Vasne rsignantte
Wimessed by.!4 .Signature
Date: » ~>
Date:~~ri c
ABB Combustion Engineenng Nuclear Operations
ABB Combustion Engineering Nuclear Operations'
/f w/
TR-9419-CSE96.-'i iG1,MKLQ. Attachment 2 Page 23 of 23
TP-9419-CSE96-2104, Rev. 0 Page 10 of 11
Data Sheet Z
Dynamic Pressure Test
Tool (circ. or long axial) Cl P<
initial Bladder Pressure I>~ psig Hydro Chamber Target Pressure &3oa psig
Pump Rate
Strokes/min
Hydro ChamberPressure"I
SI
Hydro PumpDischarge Pressure"'
si
Bladder Pressure"'
siMaximum Minimum Maximum Minimum Maximum Minimum
0 static)20AO"+z.
100
~r~+geo
H5~~
gl eQ
~9~C I~o
%5oo
g'leo93~
I toes
3'3goo
"f5~o q$ ocs
Notes: I) For non-fluctuaung pressure values. record pressure as the maximum pressure actueved.
Hydro Pump Discharge Pressure Gauge No. FS. t1- /choo I
Hydro Chamber Pressure Gauge No. S — l - toe >~Bladder Pump Discharge Pressure Gauge No. C" - tv - (eass
Remarks: Low L~K lent
Completed by:Wane.si gaamce
Date: b " <<
Witnessed by:Name Signcun
ABB Combustion Engineering Nuciear Operations
ABB Combustion Engineering Nuclear Operations
TR-9419-CSE96-1101, Rev. 0 Attachment 3 Page 1 of 5
Attachment 3
Pressure Gauge Calibration Records
ABB Combustion Engineering Nuclear Operationsp- 4/
~ ~
~ ~ ~ ~
~ ~ ~
~ ~ ~k
~: ~ ~ .
~ . ~ ~ . ~
0 I iree Ia. ~ . ~ > ~
' ~ ' CS ~ ~ ~ 0
I ~ ~ ~
~ ~ I ~ ' ~ ~
~ ~ ~ ~ ~ ~ ~ ~ ~ ~
~ ~ ~ ~ ~ ~ ~
f>Ir
HEMy ~ I
5
~ ~
~ '
~ '~ ' ~ ' ~ ~ ~
~ ~ ~ ~
~ ~ ' ~
~ '
~ ~ ~ ~ ~ ~ ~ - ~
~ ~ ~ ~ ~ s
~ ~ ~ ~ >0 ~
~ I
er ~
~ ~
~: ~ ~
~ ~ ~
~ 4 ~ . ~
~ ~ I ~
~ ~ ~
~ ~
~ ~ ~ ~ ' ~ ~
~ ~ ~ t ~ ~ ~ ~ I ~
~, ~ ~ ~ 0 ~
N'%mrf%58W
~ ~
J' ~
~ '~ ' ~ ~ ' ~ ~
' ~ ~
~ '~ ~ ~ ~ ~ '
j - o
~ ~
IJ
i
~ ~ ~ ~ ~ ~ ~ - ~
TR-9419-CSE96-11 Attachment3 Page4of5
STO-400-159Rev. 00
ABB-Combustion Engineering~ ¹xclear Operations
Page 5 of 5
Attachment 1
CERTlFICATE OF CAUBRATlON
instrunlent Type
Manufaaurer
Range 0- 'O @cc racy
Mfg. Serial No.
C.E lO No P'5 -(7 /db ZB
Calibration Date
Calibration Due Date
Calibration Document:
gl Procedure
[ ) Manutacturer s Specifications
Test Equipment Used To Perform Calibration:
Test EquipmentK~~ Senal or ID No.
V -oo<Test Equipment Serial or lo No.
CAiJBRATlON RESULTS
Standard Value As Found i As Left
(Cg
Standard Value As Found As Left
lo
CAUSRATION HAS afEH P& FORM EO UnUDNQ MEASUREMEHT Ofvlcf5 WHICH H*vE KNOWN RELATIONSIII&To NssSTANOAAOS Wlifaf SUCH ST*NO*ROS KXIS . WHcfaf 5UCH STAHOARO5 Oo NQT Q(IST, AH A~QVEO IVOC OUREWAnicN IH ACCOROAHCE Wnl TH MAHUFA~iRfcL'5RECQMMfiIQATIQNS HA5 BfcEN USEQ AHO THE STAHOAAOSOOCUMEHi co.
REMAR(S:
1 ACCEPTEO ( 1 REJECTEDCALlBRATED BY:
ORGANIZATION:
ABB Combustion Engineering Nuclear Operations
TR-941 9-CSE96-1 10~ev Q. Attachment 3 Page 5of5
STD-400-159Rev. 00
ABB-Combustion EngineeringNuclear Operations
page 5 of 5
Attachment 1
CERTlFICATE OF CALIBRATlON
Instrunlent Type
Manufacturer
Range 0- ra eevraeyg~2FSMfg. Serial No.
C-E ID No.
Calibrarion Date
Calibration Oue Date
CalIbratIon Oacurnent.
(+ Pracedure ~~~
) Manufacturer's Specifications
Rev.
Test Equipment Used To Perform Calibration:
Test EquipmentHI= ISL=
Serial or IO No.
~rrTest SquIonlent Serial or IO No.
CALIBRATIONRESULTS
Standard Value As Found l As Len
0 Rl<i I lao f46 I locp Q<ciLao CI I Z lou ' 2 lrr0
I~i~ I f~I o~oI ~ I
lo Iio lo
Standard Value As Found As Left
CAUSRATloN H*5 IEKH PEaIFORMKO UnUZINO MEASUREMENT QEVIC'ES WHICH HAVK KNOWN RELATIONSHIPS Ta Nes
STANQARQS WHERE SUCH STANOARQS KXISi. WHERE SUCH 5i ANOARQ5 QO NOT EXIST. AN APPROVEQ PROCEQUR
WRITTEN IN ACCOROANCE VIPiil THE MANUFA~iRER'5 RFCOarIMEVQATloaIS HAS BEgaI USEO ANO THE STANOAROS
QOCUMEN a =O.
R":MAR(S
()Cl ACC:?T"=D I l R"=J"=CT"-OCALIBRAT "0 BY:
ORGAraNaIZATION:
ABB Combustion Engineering Nuclear OperationsIg(