Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Proceedings of the 5th International Conference on Integrity-Reliability-Failure, Porto/Portugal 24-28 July 2016
Editors J.F. Silva Gomes and S.A. Meguid
Publ. INEGI/FEUP (2016)
-985-
PAPER REF: 6345
RETROFIT OF A COLLAPSED MASONRY GALLEY WITH
HISTORICAL VALUE: PRELIMINARY STUDY OF ALTERNATIVE
SOLUTIONS AND RETROFITTING STRATEGIES
Enrica Di Miceli1(*)
, Vincenzo Bianco1(*)
, Maria Grazia Filetici2, Giorgio Monti
1
1Department of Structural Engineering and Geotechnics (DISG), Sapienza University of Rome, Italy 2Superintendence for Cultural Heritage of Rome, Piazza dei Cinquecento 67, 00185 Rome, Italy (*)Email: [email protected]
ABSTRACT
This work presents a preliminary study aiming at singling out the most suitable design
solution for the retrofitting of a collapsed masonry barrel vault placed in the central
archaeological area of Rome, in Italy. Main objectives to be pursued with the restoration are:
1) re-opening the monument to the public, and 2) endowing it with a walkway on the extrados
of the vault in order to allow visitors enjoy the sight of Circus Maximus. The paper is divided
into four parts, as follows: 1) firstly, a description of the current status of the monument is
provided, then 2) based on the results obtained by simple mechanical models, the possible
causes of the collapse are discussed, 3) some reconstruction strategies are presented and
compared to each other, also in economic terms, and eventually 4) the motivated selection of
the final solution to be implemented is presented.
Keywords: Architectural heritage, barrel vault, monument, preliminary design, retrofitting.
INTRODUCTION
The conservation and restoration of an archaeological monument are a challenge for engineers
and architects.
Most often, these artefacts are the result of a long process of transformations and
stratifications that have occurred over the centuries, and that have ended up modifying the
monument in terms of a) original structural behaviour, b) form and c) function, so that the
result with which technicians have to deal with is a very complex and unique structure.
Uniqueness and complexity require special attention and care both in the evaluation of
techniques and technologies to be used in the restoration (either consolidation or seismic
amelioration design), and in the choice of materials. In fact, when working on an important
monument of historical-architectural value, the design solution to be searched is always the
one that guarantees the best compromise between need to intervene and necessity to bring the
minimum disturbance to both the structure and its surroundings.
Moreover, it is essential to understand which materials to use in order to build any missing
and/or additional parts, without altering the “image” of the artefact. For this reason, it is
necessary a multidisciplinary approach that integrates all different expertise, hopefully
involving architects, archaeologists, historians, and engineers (e.g. Roca et al. 2010).
Stability and durability are also necessary conditions, but not sufficient to define the criteria
and to choose the intervention techniques, having to prefer the preservation of the monument
Symposium_13: Assessment and Strengthening of Existing Structures Subjected to Seismic Demands
-986-
in its environmental context and in accordance with its forms and structural design (DPCM
2011).
The restauration works to be carried on archaeological artefacts must be guided by the criteria
of both “integration” and “integrality” (e.g. Elia 2010).
The present work deals with the study of alternative restoration and seismic amelioration
solutions of a vaulted gallery, in the Central Archaeological Area of Rome. This latter
includes important archaeological monuments and offers a vast range of typologies and
typical (own) Roman architecture construction techniques (e.g. Lugli 1957).
In particular, these monuments are characterized by the presence of arches and vaults, that the
Romans built in various forms and in various ways. Initially, the arches were made of stone
blocks or bricks while later, with the introduction of the pozzolanic mortar, particularly
resistant, and mixed with stones of various sizes, vaults were built by the technique of the
concretion, also called opus caementicium. These vaults were designed as a monolith that is
as a single block of stone that would not have to exert horizontal load on retaining walls.
a)
b)
Fig. 1 - Bricks and vault: a) size of the bricks used in roman constructions; b) three-dimensional view of an opus
caementicium vault with the semilateres ribbing (image from Tomasoni 2015).
In fact, the opus caementicium could not ensure such a monolithical structural behavior since
it does not have a reliable tensile strength and for this reason, the occurrence of cracks turned
the vaults into pushing systems. From a construction point of view, the opus caementicium
was poured on a temporary structure made of wooden ribs that was subsequently removed
Proceedings of the 5th International Conference on Integrity-Reliability-Failure
-987-
after its hardening; for this reason, in structures built by this technique, traces of such wooden
ribs remain impressed in the intrados surface.
Later, Romans began to select the materials constituting the various layers of the vaults and to
sort such materials according to their specific weight, and implementing them according to
the static needs. For instance, in the dome of the Pantheon, light volcanic stones, that are
pumice stones, can be found in the top layers (e.g. Croci 2005). From the I century a. D., the
opus caementicium vaults were built with the so called semilateres that are brick ribbings
positioned along the directrix of the barrel vault and connected to each other with bipedales
bricks (Fig. 1a, b). These ribbings had the function to stiffen the structure, and to confine the
fresh concrete mass.
Any design proposal that involves the statics of a historic building should be based on: 1) an
accurate geometric and material survey, and 2) the interpretation of the static behaviour, so as
to highlight the critical points of the building (yielded from either original conditions,
intentional transformations, degradation or accident).
For this purpose, a part of this work has been dedicated to understanding the causes that may
have led to the collapse of the gallery, by means of simple mechanical models, to verify both
its static and seismic safety. This study is being essential to direct the development phases of
the design strategies and to define what might be considered the best solution in terms of
"advantages and disadvantages", i.e. in terms of a) total or partial achievement of all the goals,
b) respect of the restrictions, and c) the level of operational and economic feasibility.
Fig. 2 - Urban localization: general view of the central archaeological area of Rome.
Since the XV century studies about the static vaults were developed, but the first static
theories about the arches, vaults and domes, date back to the XVII century. Important is, for
example, the de La Hire’s contribution (e.g. de La Hire 1730,1731) who first used the
funicular polygon construction in the static analysis of the arches. Couplet (e.g. Couplet
1731,1732) introduced the concept of rotational hinge as a condition for the fracture.
Coulomb (e.g. Coulomb 1776) based his studies on finding the collapse safety factor and
introduced the friction and cohesion conditions between the blocks. During the XIX century,
starting from Navier, attention was also paid to the strength of materials to determine the
application points of resultant forces in the keystone and in the fractures joints. An early study
about the pressure curves was conducted by Mery (e.g. Mery 1840) who proposed a graphical
verification method of the arches that is still used nowadays.
Symposium_13: Assessment and Strengthening of Existing Structures Subjected to Seismic Demands
-988-
Currently the analysis and verification methods about the safety of arches and vaults are
numerous. The most significant studies developed over the past years encompass: 1) the
theory of plasticity and limit analysis applied to masonry structures (e.g. Heyman 1996, 1982;
Monti et al. 2013; Tomasoni 2015); 2) the membrane theory, which takes into account the
three-dimensional effects (e.g. Flugge 1973); 3) the analysis of the vaults through the finite
element modeling according to a "continuous" or a "discrete” approach (e.g. Lourenço 2002;
Roca et al. 2010). In particular, the limit analysis method has been proven to be one of the
most powerful techniques for engineering practice, due to the suitable compromise between
relative simplicity and prediction accuracy. In a preliminary phase, this method appears the
most appropriate and effective tool to verify the structures.
CURRENT STATUS OF THE MONUMENT
The so-called Galleria delle Volte Crollate (The Collapsed Vault’s Gallery), object of this
work, is part of an important archaeological site – the Augusto’s House on the Palatine hill –
which has not been completely explored yet. This site is therefore the subject of preliminary
assessments, both historical and archaeological, which are being studied by experts in this
field.
Fig. 3 - Previous retrofit intervention (XX century): plan with optical cones of images: details of the steel beams,
squat brick walls and wooden struts.
The Gallery is located in the central archaeological area of Rome, precisely in the south-west
area of the Augusto’s House (Fig. 2) and it was originally roofed by a depressed barrel vault
made by a conglomerate composed of irregularly shaped tuff stones and pozzolanic mortar,
according to a technique called opus caementicium. At a certain point of the history, and for
unknown reasons, the vault must have collapsed disintegrating in large conglomerate blocks.
Proceedings of the 5th International Conference on Integrity-Reliability-Failure
-989-
These resulting blocks, probably remained buried under soil and rubble for a long time, were
rearranged, according to a restoration design of the second half of the twentieth century
(between 1960 and 1980), by a complex and heterogeneous system comprising 1) steel
beams, 2) squat brick masonry walls, and 3) wood struts (Fig. 3). That design was meant to
restore the vaulted passage in order to make it usable by visitors. Only some portions of the
vault are still standing in their original place. The structures beneath the quota in question,
including the foundations, have not been excavated yet.
Anyway, the gallery is currently closed to the public. The status of the gallery, at a first sight,
does not appear to be safe enough to allow access to the visitors. Among the aspects that give
rise to some concern, are: 1) some of the wood struts are cracked, slightly damaged at their
extremities and probably not safe with respect to the buckling phenomenon, 2) some of the
steel beams are oxidized and with a flexural curvature that can be appreciated by naked eye
(Fig. 3), 3) static safety in some points relies on mutual contrast and interlock between
adjacent blocks that, in correspondence of the contact point, due to the high concentration of
stresses, are visibly cracked with resulting dusty rubble and likely loss of stability. Moreover,
in correspondence of the north-western entrance to the gallery, the downhill wall is
undergoing an outward rotation.
An accurate survey of the monument was carried out in order to determine 1) the geometrical
dimensions and relationships among the different parts it is composed of, 2) the constitutive
materials, their state of conservation, and relevant physical and mechanical properties
(qualitatively, by comparison with literature data), 3) the original structural conception and
possible successive modifications. As to the geometrical features, the vault is a barrel
depressed arch and its spring line (L) is 4.45m and its rise (f) is 0.59 m (Fig. 7). For what
concerns the materials: 1) the “structural part” of the vault is made of tuff conglomerate and
pozzolanic mortar; 2) the filling layer is constituted by two layers: the former in mortar and
flint aggregates and the latter, a thinner layer, in “cocciopesto” aggregates (Fig. 4). The
extrados shows traces of the so-called “suspensurae” (brick walls spaced apart that created a
ventilated interspace) and a pavement in bessali (Figs. 1a, 4) that leaves guess that the gallery
was also accessible at the extrados (Fig. 4).
Fig. 4 - The constitutive components of the Gallery vault.
Symposium_13: Assessment and Strengthening of Existing Structures Subjected to Seismic Demands
-990-
The gallery walls are characterized by different construction techniques. On one side, the
vault lied on a brickwork masonry (opus testaceum) and on the other, on a mighty wall of tuff
and travertine blocks that today stands at a height much lower than the original one.
A detailed survey of all the steel beams was carried out (type, span, degradation), by
numbering 41 beams in total (39 double T steel beams and two wooden ones). The safety
verification about the steel structures (Di Miceli 2016) has highlighted a situation of possible
risk: a) 29 beams are not verified for flexural static loads, and b) 4 are not verified for both
flexure and shear (Table 1). These first results, therefore, suggest to reconsider the twentieth -
century intervention, eliminating the steel and wood supporting structures and proposing
possible alternative solutions for the vaulted roof of the gallery, according to a more correct
interpretation of the monument structures.
Table 1 - Excerpt of the results of the steel beams safety analysis (Di Miceli 2016).
POSSIBLE EVOLUTION OF THE MONUMENT
Starting from the study of the bibliographic sources (e.g. Iacopi et al. 2006; Pensabene et al.
2011, 2013; Carandini et al. 2010), two different hypotheses about the architectural genesis of
the so-called Galleria delle volte crollate were taken into account:
1) the Gallery may be considered a vaulted substructure lying on the soil, and directly
cast on it, as a support of the bases in front of the Apollo’s Temple, which was part of the
Augustus’ House (Fig. 5). From a structural point of view, therefore, its stability would be
related to the bearing capacity of the underlying soil;
2) the Gallery is a self-supporting vaulted structure, with depressed cross-section, and its
stability is related to the mechanical properties of materials and its geometric shape.
The first hypothesis would be supported by the fact that, when Augustus decided not to futher
expand his house in favor of the construction of the Apollo’s Temple, he also decided to bury
all the previous structures and to raise the walking level. The construction of the vaulted
Proceedings of the 5th International Conference on Integrity-Reliability-Failure
-991-
gallery would be, therefore, contemporary with the construction of all the substructures in
front of the Apollo’s Temple. Another element in favor of the first thesis is that the barrel
vault would result supported, along its longitudinal development, on vertical structures made
in different ages and by different techniques, that are: 1) on the southern side, on the remains
of a brickwork masonry and, 2) on the northern side, on a wall with tuff and travertine blocks
(Fig. 5).
In support of the second hypothesis, however, some literature sources claim that the Gallery
would have been built as a vaulted walkway that connected the rooms of the western peristyle
of Augustus’ House with the structures of the eastern peristyle (Fig. 5). These latter have a
vault that is very similar, in terms of both materials and geometry, to that of the Gallery in
question and therefore it was very probably built in the same timeframe (Fig. 6a). Another
element, which would suggest that the gallery was built as a self-supporting structure, is
represented by the traces of the wooden planks still recognizable at its intrados (Fig. 6b).
Fig. 5 - General plan of the Augustus complex.
In the next section, all these assumptions have been reevaluated also on the basis of the results
obtained by means of simple, yet efficient computing models, trying to identify the causes
that may have led to the collapse of the vault, thus trying to answer the following questions:
1) Did the vault collapse due to the fact that it actually was a depressed vault?
2) Did the weight of the fill above, not foreseen by the original design, cause the collapse
either in static or seismic conditions?
3) Was the collapse of the vault caused by the illegal removal, according to an unfortunate
and widespread practice of the time, of some tuff and travertine blocks of the perimeter walls
thus weakening the supports of the vault itself? Note that similar episodes have been
unfortunately occurring in other monuments of the Palatine.
Symposium_13: Assessment and Strengthening of Existing Structures Subjected to Seismic Demands
-992-
a)
b)
Fig. 6 - Similar vault to that of our Gallery (a); traces of the wooden planks at the intrados of the vault (b).
PROBABLE CAUSES OF THE COLLAPSE
The safety of the arch, in its original features before collapse, was verified by means of simple
mechanical models in order to have an expeditious and preliminary estimate. The arch safety
was analysed against both static and seismic loads. Such a study can also be useful 1) to avoid
to reconstruct a structure that was affected by design mistakes and 2) to better address the
decisions to be taken in order to retrofit the gallery and make it usable by the visitors of the
Palatinum Area.
Fig. 7 - Scheme of the vault (a), and discretization in blocks of both the filling and the structural arch (b).
Proceedings of the 5th International Conference on Integrity-Reliability-Failure
-993-
Static Loads
The verification under static loads was carried out by means of Mery’s Method (Mery 1840),
verifying if, for a uniformly distributed load (self-weigh plus fill), the thrust line is contained
within the core of the arch. In that case, the arch would result safe, according to Mery.
A one-meter deep portion of the barrel vault was analysed. The Mery’s method was translated
into analytical formulations and implemented in a simple computer program. The arch was
discretized into a large number of blocks in order to calculate the various involved
parameters, that are, for instance: the weight of the vault and its overlying fill (Fig. 7).
The verification shows that the thrust line is entirely contained within the core (Fig. 8a). But
this result is not reliable enough to draw positive conclusions about the safety of the arch
since the model is affected by a drawback. In fact, since it imposes the passage of the force
resultant through both 1) the uppermost extremity of the core, in correspondence of the
keystone, and 2) the lowermost extremity of the core, in correspondence of the imposts, it
ends up providing, for static distributed loads, and whatever geometrical contour conditions, a
thrust line that is always contained in the arch core. Thus, that result could be misleading.
So a normal stress verification was carried out in correspondence of the arch sections in
which the vertical weights, due to both the filling and the blocks’ self-weight, are combined
with the horizontal force applied to the keystone (Figs. 8b and 9).
Fig. 8 - Static analysis: trust line (a); trend of the ratio between compressive masonry strength and demand (b).
For the mechanical properties of the constitutive material, rubble tuff block masonry,
(Circolare Esplicativa n°617) the unit compressive strength was assumed equal to 2
0.140 cmNR =σ . The trend of the ratio between the masonry strength and demand, along
the arch length, in terms of compression SR σσ , is plotted in Fig. 8b. As can be gathered
from this trend, which is plotted for different values of the structural masonry unit weight (30.250.15 mkNm ≤≤ γ ), the ratio SR σσ ranges from a minimum value of 50.2 and a
maximum value of 20.7 . Note that the trend of the ratio SR σσ along the arch shows a
singular point with a change of curvature approaching the imposts that is due to the change of
the sign of the thrust line eccentricity with respect to the arch mid line. It emerges that the
arch was properly designed to support the gravity loads to which it was subject.
Symposium_13: Assessment and Strengthening of Existing Structures Subjected to Seismic Demands
-994-
Fig. 9 - Verification of the sections: scheme of the normal component (N) along the transversal section.
Seismic Loads
The verification under seismic loads was carried out by means of the Limit Equilibrium
Analysis Method, assuming for the arch a collapse mechanism according to which four hinges
divide it into three rigid blocks (I, II and III in Fig. 10). Such labile mechanism has one
degree of freedom that is the downwards rotation 1θ of the block 21CC , while the rotations of
the remaining two blocks, 2θ and 3θ around their relevant instantaneous rotation center are
kinematically dependent on 1θ . The collapse mechanism, due to a seismic action directed
rightwards is represented in Fig. 10. In searching for the most probable collapse
configuration, coherent with the collapse mechanism above, the following assumptions were
made: 1) only the case of arch portions contained in an opening angle larger or equal to °15
were taken into consideration, 2) the first hinge 1C was assumed to be located at a distance of
about %5 of the arch springing line (L) from the left impost, and 3) the fourth hinge 4C was
assumed to be located at the right impost.
For the properties of masonry, the following assumptions have been taken: a) no tensile
strength; b) infinite compressive strength; c) absence of any slippage, i.e. infinite friction,
along the interfaces between the tuff irregular blocks and the mortar.
The horizontal seismic force that activates the overturning mechanism is defined by means of
the horizontal loads multiplier 0α , which is the mechanical ratio of the work done by the
stabilizing forces with respect to the work done by the overturning forces, in accordance to
the Virtual Work Principle (Circolare Esplicativa n°617):
�� ∙ ������ ∙ ��,� � � �����
��� ∙ ��,�� ������ ∙ ��,� � ��� (1)
stabovrt LL =⋅0α (2)
where: iP is the self-weight of the i-th rigid block, jP is the j-th carried weight, izd , is the
virtual horizontal displacement of the point of application of iP , jzd , is the virtual horizontal
displacement of the point of application of jP , iyd , is the virtual vertical displacement of the
Proceedings of the 5th International Conference on Integrity-Reliability-Failure
-995-
point of application of iP , and fiL is the work of internal forces. Note that when the vertical
displacements are directed downwards they positively contribute to the overturning work (
ovrtL ), and vice-versa ( stabL ).
The value Ra of the spectral seismic acceleration can be evaluated as follows (Circolare
Esplicativa N°617):
�� � �� ∙ ∑ �������∗ ∙ �� � �� ∙ ��∗ ∙ �� (3)
where CF is the Confidence Factor, function of the Knowledge Level KL ; g is the gravity
acceleration; and *M is the participating mass, which can be evaluated by (Circolare
Esplicativa N°617):
�∗ � ∑ �� ∙ ��,����� !"� ∙ ∑ ������ ∙ ��,�" (4)
The demand acceleration Da was assumed as the value corresponding to the constant
acceleration plateau of the site spectrum (Fig. 11 and Table 2), evaluated by means of the
Italian Standards for Constructions (NTC2008), and four limit states, that are: 1) Immediate
Occupancy Limit State (IOLS with return period yrsTR 30= ), 2) Damage Limit State (DLS
yrsTR 50= ), 3) Life Safety Limit State (LSLS yrsTR 475= ), and 4) Collapse Limit State
(CLS yrsTR 975= ). The capacity/demand ratio was calculated as follows:
D
R
a
a=ρ
(5)
Fig. 10 - Seismic analysis: assumed collapse mechanism.
In searching for the minimum value of the collapse multiplier, all the possible collapse
configurations consistent with the assumptions above, were analyzed. In doing that, the ratio
Symposium_13: Assessment and Strengthening of Existing Structures Subjected to Seismic Demands
-996-
between the positive amount of the stabilizing work stabL, in case of vertical displacement
with direction opposite to the relevant weight load ()()( , iiy Psigndsign ≠), and the negative
amount of the stabilizing work, in case of vertical displacement with the same direction as the
relevant weight load ()()( , iiy Psigndsign =), varies almost with continuity. In this way, the
collapse multiplier can also assume either negative or very low positive values. The former
ones were discarded since they do not have physical meaning while the amount of positive
values were analyzed in statistical terms (Fig.12). In fact, assuming the minimum value of 0α
would result excessively conservative.
Fig. 11 - Comparison between response spectra.
Table2 - Seismic parameters
ag [g] Fo Tc*[s] SS CC ST
IOLS 0.043 2.539 0.256 1 1 1.4
DLS 0.055 2.502 0.269 1 1 1.4
LSLS 0.121 2.630 0.293 1 1 1.4
CLS 0.152 2.615 0.301 1 1 1.4
For each of the analyzed limit states, a normal distribution of the probability density was
determined and the relevant value of the probability of attainment of the LS, conditioned to
the given value of the peak ground acceleration, was calculated as follows:
( )[ ] ρρ dDLSag ⋅=≤ ∫1
0
Pr|0.1Pr
(6)
where: PrD is the probability density function. The results are plotted in Fig. 12. As can be
gathered from that figure, the probability of failure of the several LS is: 18% for the IOLS,
25% for the DLS, 74% for the LSLS, and 86% for the CLS. This yields that the arch, in its
original shape and loading condition, was not safe with respect to the seismic loads given by
the Italian Regulation currently in force (NTC2008). So, it is possible to conclude that the
arch might have collapsed due to an earthquake attack.
Proceedings of the 5th International Conference on Integrity-Reliability-Failure
-997-
The results of the calculations would support the hypothesis that the gallery’s vault was
conceived as a structural one thus disproving the hypothesis that it was obtained by simply
casting the opus caementicium directly on the soil. Moreover, the traces of the wooden
planks, still visible on the intrados of the vaults remaining portions, would also support the
second hypothesis according to which the gallery was a structural one.
Fig. 12 - Probability density of the seismic capacity/demand ratio for different limit states:
Immediate Occupancy (IOSL), Damage (DSL), Life Safety (LSLS), Collapse (CSL).
In light of the considerations above, we can conclude that the vault, even though intentionally
conceived as a structural one, may have been affected by macroscopic design defects so that it
was not able to withstand seismic loads and probably collapsed due to an earthquake.
ALTERNATIVE RETROFITTING STRATEGIES
In this section, several restoration design alternatives are evaluated in terms of both feasibility
and economical expense. For each of such hypotheses, all the construction phases were first
singled out and subsequently evaluated in economic terms.
Fig. 13 - Current state of the Gallery (a); integration of perimeter walls and cutting of steel beams flush against
the wall so that the left portions remain incorporated in the new masonry (b).
Symposium_13: Assessment and Strengthening of Existing Structures Subjected to Seismic Demands
-998-
The main objectives to be pursued are: 1) making the gallery accessible to the public, 2)
recreating the original intrados surface, 3) increasing the safety of the structure for both static
and seismic loads, 4) suitably organize the construction site, given the delicate surroundings,
and 5) bring the minimum disturbance to both the supporting lateral walls and the underlying
structures, down to the foundations. In fact, as to this latter point, the structures beneath the
walls still have to be excavated and are partially unknown.
The cost analysis was carried out indicating for each constructive phase the relevant a) unit of
measure (u. m.), b) unit price (u. p.), and c) quantity of each specific component, in relation to
one linear meter of the Gallery’s longitudinal extension (37,27m long by 4,45m wide). Works
that are common to each of the design proposals have been listed in the relevant tables but not
quantified in economic terms, in order to carry out a comparative economic analysis
highlighting only the works peculiar of each solution. Prices were deducted from both
“Tariffa dei prezzi 2012 - Regione Lazio” (TPRL 2012) and “Listino noleggio Pernicini
2010” (LNP 2010).
Fig. 14 - Installation of possible tie rods (a), view after the demolition of the steel beams and the brick walls;
similar tie roads found in another monument in the archeological area of Rome (b).
Proceedings of the 5th International Conference on Integrity-Reliability-Failure
-999-
Fig. 15 - First solution: bridge crane scheme (a); reconstruction of the vault and the floor above (b).
First solution
1) Masonry reconstruction of the barrel vault with localized lifting and
repositioning of the blocks with an overhead travelling bridge crane
(Figs. from 13 to 15)
u. m.
u. p.
quantity price.
[€/ml]
1.1) The previous intervention in steel beams, wooden supports and brick
walls is initially left in place.
1.2) Integration of the perimeter walls (tuff, brick and travertine) of the
gallery, up to the maximum height of the vault extrados: this height is
deduced from two points in which the vault is still in the original
quota (Fig. 13a,b). If necessary, the perimeter walls are shaped to
create the impost of the vault.
On the north-west side (masonry blocks of tuff and travertine), where
the longitudinal access openings to the adjacent Domus Augusto’s
rooms can be found, the flat arches above such openings will be
rebuilt, at their original impost quota.
1.3) It will be necessary to verify that, after removal of a) wooden
supports, b) squat brick walls or other blocks, the vault portion left in
place is able to support both itself and the steel beams of the deck to
be positioned successively; otherwise it is necessary to intervene
locally with tie rods and consolidating injections (Fig. 14a, b).
ml
22,26
10
32,80
1.4) The collapsed vault blocks, currently stored inside the gallery, but
that are difficult to relocate properly in their original position, due to
the shortage of information, are lifted by the crane and taken to the
external storage area.
month
1.470,00
12
473,30
1.5) Installation of the longitudinal (assuming HEA1000 = 272kg/m) and
transversals beams (HEA 500 = 155kg/m) of the steel deck
(included the bracings), by means of the crane (Fig. 14b).
kg
kg
3,35
3,35
544
155 1.822,40
2.310,66
Symposium_13: Assessment and Strengthening of Existing Structures Subjected to Seismic Demands
-1000-
1.6) Bridge crane construction (installation) with two orders, where its
dimensions are calibrated on the basis of both the maximum and
minimum block size (Fig. 15a). Note that the cost includes the
electric winch.
month 14.000,0 12 4.507,64
1.7) The vault blocks are lifted and repositioned, with an electric winch;
construction of the wooden plank arch-centering; these operations
are done by subdividing the gallery length in successive sub-portions.
After completing a sub-portion the bridge crane is moved and
operations are iterated at the adjacent sub-portion.
mq
48,35
4,45
215,15
1.8) Removal of the elements composing the previous intervention (XX
century). The steel beams are cut along the cross section in
correspondence of the wall surface so that the left portion will remain
embedded in the wall and visible to the outside, thus leaving
historical memory of the previous intervention (Fig. 13b); the brick
walls are demolished; transport of end products in landfill.
1.9) Reconstruction of the missing “structural” portion of the vault. mq 230,00 2,225 511,75
1.10) Possible fill in lightweight material (only if it has a static function) to
the extrados of the new reconstructed parts.
1.11) The wooden plank arch-centering is disassembled.
1.12) Construction of a floor with corrugated steel sheet and reinforced
concrete slab: note that the beams depth is such as to leave a space
that allows to preserve the suspensurae (Fig. 15b).
mq
49,69
4,45 221,12
[€/ml] 10.604,06
[€] 395.213,3
Fig. 16 - Second solution: masonry reconstruction of barrel vault.
Second solution
2. Masonry reconstruction of barrel vault with lifting and
handling of blocks by crane (i.e. without bridge crane)
(Figs. 13,16)
u. m.
u. p.
quantity price.
[€/ml]
2.1) Numeration and accurate survey of the current position of the
collapsed vault blocks.
2.2) Consolidation of the vault blocks (for example with
injections) to improve their mechanical properties and to
ensure that – during the lifting stages – they will not undergo
any damage.
2.1) The vault blocks are lifted by crane, positioned outside the
Gallery, and stored in a nearby outdoor area.
month 1.470,00 12
473,30
2.2) Integration of the perimeter walls (tuff, brick and travertine)
Proceedings of the 5th International Conference on Integrity-Reliability-Failure
-1001-
of the gallery, up to the maximum height of the vault extrados:
this height is obtained by two points in which the vault is still
in the origin quota (Fig. 13a,b). If necessary, the perimeter
walls are shaped to create the impost of the vault.
On the north-western side (masonry blocks of tuff and
travertine), where the longitudinal access openings to the
adjacent Domus Augusto’s rooms can be found, the flat arches
above such openings will be rebuilt, at their original impost
quota.
2.3) Removal of the elements composing the previous
intervention (XX century). The steel beams are cut along the
cross section in correspondence of the wall surface so that
the left portion will remain embedded in the wall and visible
to the outside, thus leaving historical memory of the previous
intervention (Fig. 13b); the brick walls are demolished;
transport of end products in landfill.
2.4) Construction of the arch-centering along the Gallery. mq 48,35 4,45 215,15
2.5) Lifting and correct re-positioning of the vault blocks by the
crane.
2.6) Reconstruction of the missing structural vault portion. mq 230,00 4,45 1.023,50
2.7) Filling in lightweight material to the extrados of the new
reconstructed parts;
cast concrete (4 cm) with welded steel net (mesh 10x10
cm) and construction of a flooring, leaving in high or low
relief the parts of vault with suspensurae (Fig. 16).
mc
mq
mq
132,00
25,00
35,00
2,79
2,225
2,225
368,28
55,62
77,87
[€/ml] 2.213,72
[€] 82.505,3
Fig. 17 - Third solution: bridge crane scheme (a); reconstruction of vault
Symposium_13: Assessment and Strengthening of Existing Structures Subjected to Seismic Demands
-1002-
Fig. 18 - Fourth solution: steel bridge-like deck seismically isolated.
Third solution
3) Repositioning of the collapsed vault blocks, integration of the missing
parts with new masonry and construction of a steel bridge-like deck
(not isolated) at the extrados of the barrel vault to which the
underlying structures are eventually hung (Figs. 13, 17)
u. m.
u. p.
quantity price.
[€/ml]
3.1) Integration of the perimeter walls (tuff, brick and travertine) of the
gallery, up to the maximum height of the vault extrados: this height is
deduced from two points in which the vault is still in the original
quota (Fig. 13a,b). If necessary, the perimeter walls are shaped to
create the impost of the vault.
On the north-western side (masonry blocks of tuff and travertine),
where the longitudinal access openings to the adjacent Domus
Augusto’s rooms can be found, the flat arches above such openings
will be rebuilt, at their original impost quota.
3.2) Consolidation of the vault blocks (for example with injections) to
improve their mechanical properties and to ensure that – during the
lifting and handling stages - they will not undergo any damage.
3.3) Installation of the longitudinal (assuming HEA1000 = 272kg/m) and
transversal beams (HEA 500 = 155kg/m) of the steel deck (including
the bracings), by means of the crane (Fig. 17b).
kg
kg
3,35
3,35
544
155 1.822,40
2.310,66
3.4) Assemblage of the bridge crane and its positioning by crane
(Fig.17a).
month
month
14.000,0
1.470,0
12
12 4.507,64
473,30
3.5) Performing the following operations, proceeding by "modules":
3.5.1) lifting and positioning of the first block of the current module;
3.5.2) the block is fixed by tie rods to the transversal beams of the steel
bridge-like deck (Fig. 17a);
3.5.3) the bridge crane is moved on the possible second block of the same
module;
ml
31,00
5,05
156,00
Proceedings of the 5th International Conference on Integrity-Reliability-Failure
-1003-
3.5.4) lifting, positioning and fixing of the second block (if it exists) of the
current module;
3.5.5) the steel beams of the previous intervention are removed and the
relevant brick walls demolished;
3.5.6) construction of the arch-centering;
3.5.7) predisposition of the tie rods that will sustain the parts to be rebuilt;
3.5.8) reconstruction of the missing “structural” vault portion;
3.5.9) the arch-centering is disassembled;
3.5.10) installation of the tie rods for the parts to be rebuilt;
3.5.11) moving to the next “module”.
mq
mq
ml
48,35
230,00
31,00
4,45
2,225
3
212,15
511,75
93,00
3.6) The bridge crane is disassembled, after every block has been correctly
placed.
3.7) Construction of a floor with corrugated steel sheet and reinforced
concrete slab: note that the beams depth is such as to leave a space
that allows to preserve the suspensurae (Fig. 17b)
Mq
mq
49,69
35,00
4,45
4,45 221,12
155,75
[€/ml] 10.461,26
[€] 389.891,1
Fourth solution
4) Repositioning of the collapsed vault blocks, integration of the missing
parts with new masonry and construction of a steel bridge-like deck
(isolated) at the extrados of the barrel vault to which the underlying
structures are eventually hung (Figs. 13, 18).
u. m. u. p.
quantity price.
[€/ml]
4.1) Integration of the perimeter walls (tuff, brick and travertine) of the
gallery, up to the maximum height of the vault extrados: this height is
obtained by two points in which the vault is still in the original quota
(Fig. 13a,b). If necessary, the perimeter walls are shaped to create the
impost of the vault.
On the north-western side (masonry blocks of tuff and travertine),
where the longitudinal access openings to the adjacent Domus
Augusto’s rooms can be found, the flat arches above such openings
will be rebuilt, at their original impost quota.
4.2) Definition and identification of the supports (at least 4) of the deck on
which to place the seismic isolators (Fig. 18a).
4.3) Installation of seismic isolators. piece 2000 2 107,32
4.4) Consolidation of the vault blocks (for example with injections) to
improve their mechanical properties and to ensure that – during the
lifting stages - they will not undergo any damage.
kg
kg
3,35
3,35
544
155 1.822,40
2.308,15
4.5) Installation of the longitudinal (assuming HEA1000 = 272kg/m) and
transversals beams (HEA 500 = 155kg/m) of the steel deck
(including the bracings), by means of the crane.
kg
kg
3,35
3,35
544
155 1.822,40
2.310,66
4.6) Assemblage of the bridge crane and its positioning by crane. month
month
14.000,0
1.470,0
12
12 4.507,64
473,30
4.7) Performing the following operations, proceeding by "modules":
4.6.1) lifting and positioning of the first block of the current module;
4.6.2) the block is fixed by tie rods to the transversal beams of the steel
bridge (Fig. 18b);
4.6.3) the bridge crane is moved on the possible second block of the same
module;
4.6.4) lifting, positioning and fixing of the second block (if it exists) in the
current module;
4.6.5) the steel beams of the previous intervention are removed and the
relevant brick walls demolished;
4.6.6) construction of the arch-centering;
4.6.7) reconstruction of the missing “structural” vault portion (the pour);
4.6.8) the arch-centering is disassembled;
ml
mq
mq
ml
31,00
48,35
230,00
31,00
5,05
4,45
2,225
3
156,00
212,15
511,75
93,00
Symposium_13: Assessment and Strengthening of Existing Structures Subjected to Seismic Demands
-1004-
4.6.9) installation of the tie rods for the parts to be rebuilt;
4.6.10) moving to the next “module”.
4.8) Construction of the necessary joints to accommodate the seismic
displacements (Fig. 18a, b).
4.9) Construction of a floor with corrugated steel sheet and reinforced
concrete slab: note that the beams depth is such as to leave a space
that allows to preserve the suspensurae (Fig. 18b)
mq
mq
49,69
35,00
4,45
4,45 221,12
155,75
[€/ml] 14.461,26
[€] 538.971,1
Fifth solution
5) Construction of a bridge-like steel truss deck, by means of prefabricated
modules, whose cross-section is such as to recreate the same original
intrados profile. Subsequent processing of the blocks with cutting of the
cortical parts, both 1) at the intrados (curvilinear), and 2) intrados
(flat) in portions to be fastened at the steel truss deck, at the this
latter’s intrados and extrados, respectively. (Those portions could be of
dimensions such as to be handled by naked hand, that is without
crane).
u. m.
u. p.
quantity price.
[€/ml]
5.1) Numeration and accurate survey of the current position of the collapsed
vault blocks.
5.2) Integration of the perimeter walls (tuff, brick and travertine) of the
gallery, up to the maximum height of the vault extrados: this height is
deduced from two points in which the vault is still in the original quota
(Fig. 13a,b). If necessary, the perimeter walls are shaped to create the
impost of the vault.
On the north-western side (masonry blocks of tuff and travertine),
where the longitudinal access openings to the adjacent Domus
Augusto’s rooms can be found, the flat arches above such openings will
be rebuilt, at their original impost quota.
5.3) Consolidation of the vault blocks (for example with injections) to
improve their mechanical properties and to ensure that – during the
subsequent lifting and handling stages – they will not undergo any
damage.
5.4) The vault blocks are lifted by crane, positioned outside of the Gallery,
and stored in a nearby outdoor area.
month 1.470,0 12 473,30
5.5) Cutting of the cortical parts of the vault blocks by grinding machine:
1) at the intrados (curvilinear portions of the structural arch), and 2) at
the extrados (supported filling including the so-called “suspensurae”)
(Fig. 19).
day 30,00 240 193,18
5.6) Transportation to the construction site of all the modules of the steel
bridge-like truss deck.
per
trip
150,00 8 32,19
5.7) Positioning in place by crane and assemblage of the steel truss modules
(assumed indicatively 1m deep). Steel truss module (U140 = 16kg/m;
L20x20 = 1,14kg/m; U100 = 10,60kg/m) (Fig. 19).
kg
kg
kg
3,35
3,35
3,35
659,20
30,16
473,73
2.208,32
101,03
1.586,99
5.8) Removal of the elements composing the previous intervention. The
steel beams are cut flush against the wall surface so that the left part of
these will remain "incorporated" in the masonry (historical memory of
the previous intervention) (Fig. 13b); transportation of end products in
landfill.
5.9) Positioning in place and fastening to the steel truss deck of the cortical
elements (both intrados and curvilinear and extrados and flat). Such
operations could be carried out, at the intrados, by naked hands, per
small portions while, at the extrados, per larger portions, handled by
the crane. Cortical extrados portions are positioned in such a way to
Proceedings of the 5th International Conference on Integrity-Reliability-Failure
-1005-
result in high-relief with respect to the surrounding practicable floor.
5.10) Construction of an accessible floor by corrugated steel sheet and
reinforced concrete slab; construction of the practicable floor (in bas-
relief).
mq
mq
49,69
35,00
4,45
4,45
221,12
155,75
[€/ml] 4.971,88
[€] 185.301,9
Fig. 19 - Fifth solution: steel truss deck, with fastened cortical portion of the original barrel vault.
SELECTION OF THE FINAL SOLUTION
In the previous section, all the contemplated retrofit strategies were described in detail.
Advantages and disadvantages of those solutions are discussed hereinafter.
The first hypothesis substantially envisages the following phases: 1) positioning of a bridge
crane, 2) repositioning of the blocks, 3) building the wood plank arch-centering, 4) building
(casting) of the vault, 4) construction of the steel deck at the vault extrados. This solution
presents some aspects difficult to address properly: 1) after building the wooden plank arch-
centering, since the bridge crane should be still in place, it would heavily reduce the freedom
of movement at the extrados during the construction of the new portions of the vault, 2) the
resulting structure would be composed of old and new parts whose interaction would be
extremely delicate and difficult to handle, from a safety calculations standpoint, due to the
inevitable difference in mechanical properties, 3) the expeditious calculations herein
presented showed that the vault was ill conceived so that it is not reasonable to re-built,
faithfully to its original features, a structure that was already affected by huge defects, 4) it is
very expensive due to the hiring of both crane and bridge crane.
The second hypothesis aims at re-building the vault reducing the local operations by 1)
initially moving the blocks outside the gallery perimeter by crane, 2) building the wood plank
arch-centering, 3) building the missing parts of the gallery. This solution, even though less
expensive than the first one, due to the absence of the bridge crane hiring, still maintains the
safety-related issues. In fact, we would realize a structure that was evidently deficient, by also
pretending to rely on the interaction between old masonry and new masonry. This is even
more pretentious if we remark the heterogeneity of the masonry material itself, even more if it
is ancient. With respect to the previous one, this solution presents, anyway, the advantage of
Symposium_13: Assessment and Strengthening of Existing Structures Subjected to Seismic Demands
-1006-
reduced costs. Even if, in the present work, for the sake of brevity, the interventions necessary
to make both the vault and its supporting walls earthquake-resistant were not accounted for.
The third hypothesis envisages: 1) the positioning of the bridge crane, 2) building of the wood
plank arch-centering, 3) installation of the steel braces that will support the vault, 4)
realization of the missing parts of the vault that will remain hung at the steel deck realized at
the vault extrados. This solution eliminates the issues related to the interaction between old
and new masonry since the vault would remain hung at the steel deck, but maintains the
feasibility problems related to the interaction of constructive phases that affect the first
solution. Among the advantages of this solution there is also the reversibility (Brandi 1977).
In fact, since the new parts are hung at the steel deck, they could be removed.
The fourth solution envisages the seismic isolation of steel deck to which the vault should be
hung by steel rods. This solution is unfeasible for several reasons: 1) the steel deck would
need point-wise supports (four) with high local stress concentration that would require heavy
interventions on the supporting lateral walls, and 2) large portions of the lateral walls should
be cut in order to accommodate the lateral displacements that the steel deck would undergo
during an earthquake. Such solution would result too invasive, and not in agreement with the
restoration philosophy currently accepted. In fact, the full seismic rehabilitation strategy,
allowed by the 1981 Ministerial Decree (D.M.LL.PP 1981), has been progressively
abandoned in favor of the less invasive seismic amelioration strategy, which is the
intervention design solution currently accepted in Italy for the monuments (LINEE GUIDA
2010).
The fifth solution envisages the following phases: 1) moving the blocks outside of the gallery
perimeter, 2) positioning of the prefabricated steel truss modules on the longitudinal
supporting walls and their assemblage on site, 3) cutting of the cortical part of the blocks,
both intrados (curvilinear) and extrados (flat), 4) positioning and fastening of the cortical
parts, whose dimensions may be such as to allow bare hands movement, 5) construction of the
practicable floor at the extrados. Many are the advantages that seem to characterize this
solution, among which: 1) reversibility, 2) minimum disturbance to the supporting walls, due
to the continuous support, as opposed to the point-wise one of the fourth solution, for
instance, 3) relative inexpensiveness, due to the possibility of prefabrication of the deck in
modules, 4) improving safety by also connecting the two longitudinal walls thus improving
their behavior against seismic actions orthogonal to their longitudinal development.
Moreover, other materials, lighter and less vulnerable to corrosion than steel could be
adopted, such as Aluminum or Fiber Reinforce Polymers (FRP), respectively.
CONCLUSIONS
This paper presented a preliminary study of possible alternative retrofitting strategies of a
collapsed vault placed in the central archeological area of Rome, in Italy. It is a Gallery
placed inside the famous Augusto’s House area. For not documented reasons, this gallery
must have undergone a collapse, in an unknown time of history. Subsequently, in the second
half of the twentieth century, it was retrofitted by a complex intervention based on the use of
wooden struts, steel beams, and squat masonry blocks. This intervention, however, presents
many limits.
By means of simple mechanical models, the safety of the vault, considered in its original
features, showed that it was characterized by design defect that made it vulnerable to seismic
loads. Thus, it may have collapsed due to an earthquake.
Proceedings of the 5th International Conference on Integrity-Reliability-Failure
-1007-
The fifth, among the retrofitting design hypotheses taken into consideration, resulted the most
suitable one, in terms of a) reversibility, b) expensiveness, c) disturbance brought to the
existing surrounding structures, d) safety. This solution envisages 1) the construction of a
steel truss deck, whose shape aims at reproducing the same intrados profile as the original
gallery, continuously supported along the lateral walls, and 2) the fastening of the cortical
portions only, of the collapsed blocks, to the truss. This solution, also reduces the seismic
vulnerability of both vault itself and supporting walls, by dramatically reducing the masses
involved.
REFERENCES
[1]-Brandi, C., (1977). “Teoria del Restauro”, Einaudi, Torino, 1977.
[2]-Carandini, A., Bruno, D., (2010). “La casa di Augusto, dai Lupercalia al Natale”, Laterza,
Bari 2010.
[3]-Circolare 2 febbraio 2009, n. 617. “Istruzioni per l’applicazione delle Nuove norme
tecniche per le costruzioni, di cui al D.M. 14 gennaio 2008”.
[4]-Coulomb, C., A., de, (1776). “Essai sur une application de maximis et minimis à quelques
de statique, relatives à l’Architecture”. Mémories del Mathématique et de Physique presents à
l’Académie Royale des Sciences, année 1773, 343-382.
[5]-Croci, G., (2005). “Conservazione e restauro strutturale dei beni architettonici”, Roma
2005.
[6]-Como, M., (2010), “Statica delle costruzioni storiche in muratura. Archi, volte, cupole,
architetture monumentali, edifici sotto carichi verticali e sotto sisma, Roma 2010.
[7]-De La Hire, P., (1730). “Traité de mécanique, où l’on explique tout ce qui est necessaire
dans la pratique des Arts”. Mémoires de l’Académie Royale des Sciences, vol. 9, 1-333.
[8]-De La Hire, P., (1731). “Sur la construction des voûtes dans les édifices”. Histoire de
l’Académie Royale des Science, année 1712, 74-77.
[9]-Di Miceli, (2016), “Restauro della Galleria delle Volte Crollate: l’Ingegneria Strutturale al
servizio della Conservazione dei Monumenti Patrimonio dell’Umanità”, PhD Thesis, in
preparation, Department of Structural Engineering and Geotechniques, Sapienza University of
Rome, Italy.
[10]-D.M.LL.PP. (1986). “Norme tecniche relative alle costruzioni antisismiche”, Decree of
the Italian Ministry of Public Works, G.U. 12-5-1986, n. 108.
[11]-Elia, G.M., (2010). “Metodi e tecniche del restauro architettonico”, Roma 2010.
[12]-Flugge, W., (1973). “Stresses in shells”, Berlino 1973.
[13]-Heyman, J., (1966). “The stone skeleton”. International Journal of Solids and Structures,
2, 249-279.
[14]-Heyman, J., (1982). “The masonry arch”, Ellis Horwood, Chichester 1982.
[15]-Iacopi, I., Tedone, G., (2006). “Bibliotheca e Porticus ad Apollinis”, Mitteilungen des
Deutschen Archaologischen Instituts, Romische Abteilung, 112, 351-378.
Symposium_13: Assessment and Strengthening of Existing Structures Subjected to Seismic Demands
-1008-
[16]-LINEE GUIDA (2010). “Linee Guida per la valutazione e riduzione del rischio sismico
del patrimonio culturale allineate alle nuove Norme tecniche per le costruzioni (D.M. 2008)” -
Circolare n. 26/2010.
[17]-Lourenço, P.B., (2002). “Computations on historic masonry structures”, Progress in
Structural Engineering and Materials, 4(3), 301-319, 2002.
[18]-Lugli, G., (1957). “La tecnica edilizia romana: con particolare riguardo a Roma e Lazio”,
Vol. I, Roma 1957.
[19]-Méry, E., 1840. “Sur l’equilibre des voûtes en berceau”. Annales des ponts et Chausséss.
XIX.
[20]-Monti, G., Vailati, M., Gaetani, A., Paolone, A., (2013). “Modelli analitici di capacità
per archi di muratura rinforzati soggetti ad azioni sismiche”, Ingegneria sismica in Italia -
ANIDIS 2013 – XV Convegno, 30 giugno – 4 luglio 2013, Padova, Italy.
[21]-NTC 2008 – DM 14 Gennaio 2008. “Nuove norme tecniche per le costruzioni”. Gazzetta
Ufficiale della Repubblica Italiana, 4 febbraio 2008, n. 29.
[22]-Pensabene, P., Gallocchio, E., (2011). “Elementi architettonici della casa di Augusto sul
Palatino”, Architettura Classica, vol. LXII, n.s. 1, L’Erma di Bretschneider, Roma 2011, 475-
487.
[23]-Pensabene, P., Gallocchio, E., (2013). “Alcuni Interrogativi Sul Complesso Augusteo
Palatino”, Architettura Classica, vol. LXIV, n.s. II, 3, L’Erma di Bretschneider, Roma 2013,
557-582.
[24]-Roca, P., Cervera, M., Gariup, G., Pelà, L., (2010). “Structural analysis of masonry
historical constructions: Classical and advanced approaches”, Archives of Computational
Methods in Engineering, 17(3), 299–325, 2010.
[25]-Tomasoni, E., (2015). “Analisi, verifiche e consolidamento di archi e volte”, Palermo
2015.