Results-based Scaling up Rural Sanitation and Water Supply Program (RB-SupRSWS)
(Cr. 5739-VN - P152693)
Implementation Support Mission (Oct 4-15, 2021)
Aide Memoire
A. Introduction
1. A World Bank (WB) team1 undertook a virtual Implementation Support Mission for the above-referenced
RB-SupSWS from Oct 4 to 15, 2021. The WB team would like to thank the Program implementing agencies2
that are the Ministry of Agriculture and Rural Development (MARD), the Ministry of Health (MOH), the
Ministry of Finance (MOF), the Ministry of Education and Training (MOET), the Committee for Ethnic Minority
Affairs (CEMA), State Audit of Vietnam (SAV), and the participating Provinces. The objectives of the mission
were to: (i) Review with the implementing agencies and the participating provinces the overall progress of
program implementation, particularly 2021 implementation plans and potential Disbursement-Linked Indicators
(DLIs) results, compliance of the Program Action Plan (PAP) activities, and environmental and social aspects;
(ii) Discuss the budget allocation for program implementation in 2021 and potential budget allocation for 2022;
(iii) Review 2020 verification results for lessons learnt; (iv) Refine the program targets for 2021 & 2022; and (v)
Review the program implementation progress in selected province.
B. Key mission findings
2. Program restructuring: the proposed project restructuring has been fully accomplished with the amendment
to the program financing agreement countersigned by MOF Minister on September 6, 2021. The amendment to
the program’s financing agreement allows (i) a two-year extension to the program closing date until July 31,
2023, (ii) partial cancellation in amount of US$ 8.84m of credit’s proceeds allocated to DLI 1.3 and DLI 2.1, (iii)
revision to the definition of sustainable water supply schemes, and (iv) revision to the program’s result framework
and disbursement linked indicators by adding the expected results for 2021 and 2022. Following the amendment
of the program financing agreement, the program operation manual (POM) is being amended accordingly and it
is expected that the revised POM will be approved by MARD within November for application.
3. Overall program implementation progress: with the approved extension of the program closing date, the
Program is back on track to meet its PDO and there is a high chance that the Program can achieve the targeted
results for water and sanitation, though achievements will be at different levels for individual provinces. More
than 4.1 million peoples are defined as program direct beneficiaries (80% of the targeted), more than 200,000
households have access to improved water service (81% of the targeted), more than 56,000 households have
access to sustainable water supply services (54% of the targeted), 627 communes achieve status of commune
wide sanitation (92% of the targeted), there are 156 communes where the schools and health clinics maintain
hygienic status (46% of the targeted), and the program’s approach has been adopted in the new national target
program, for rural development – phase 3 (detailed achievements are presented in Annex 1). The Mission
appreciate effective effort from SAV, CO and provinces for successfully completing the 2020 result verification
work in time though all challenges from the COVID 19 pandemic. While there were good achievements in
meeting the targeted results for capacity building and new infrastructure development, the program was lagging
in meeting the targets on sustainability. The team was discussing with MARD, MOET, MOH and program
participating provinces on measures to increase results achieved towards sustainability in the coming time,
especially in 2022. Those measures will focus on better arrangement of Operation and Maintenance (O&M)
entities for water supply schemes, improvement of capacity of agencies performing O&M activities, effective
implementation of behavior change activities to raise demand from users for clean water and improved sanitation,
and introduction of appropriate water tariff system with adequate subsidies provided to the end users to ensure
financial capability of the O&M agencies
11The mission was led by Ms. Nguyễn Diễm Hăng (Senior Water Supply and Sanitation Specialist, Task Team Leader) and Mr. Nguyễn
Quang Vinh (Senior Water Supply and Sanitation Specialist, Co-Task Team Leader) and comprise Mr. David Baringo (Senior Social
Development Specialist), Ms. Hoàng Thúy Quỳnh (Social Development Specialist), Ms. Dương Cẩm Thúy (Senior Environment Specialist),
Ms. Trân Thi Phương Mai (Senior Financial Management Specialist), Mr. Lê Toàn Thăng (Senior Procurement Specialist), Ms. Trân Thi
Thuy Linh (Program Assistant), Ms. Nguyễn Thi Hồng Yến (Financial Consultant), Ms. Nguyễn Thúy Hà (WSS Consultant), Mr. Lê Tuyên
Hồng Hải (WSS Consultant), and Mr. Đặng Đình Thám (WSS Consultant) 2 The list of persons met is provided in Annex 10.
2
4. Progress of Program components: Updated scope and achieved results of program activities are described
below (details are provided in Annex 2):
(i) Rural water supply: it is expected that the Program will cover 843 water supply schemes, from which 751
schemes are constructed or upgraded using the program’s finance and the rest are financed from other sources
and they can jointly deliver about 290,000 new water connections. Out of 751 schemes directly financed by
program, 578 schemes have been completed and are under operation by the end of 2020 and the construction
of the remained schemes is underway with different progress levels. Among 843 water supply schemes, it is
expected that 433 schemes are meeting Program sustainability criteria with about 135,000 connections. The
O&M arrangement is varied from province to province which includes community self-operation, special
unit under the local commune governments, PCERWASSes or contracting out to private utilities. Application
of water tariff is also varied from province to province without a clear linkage with the cost of a proper O&M.
(ii) Rural sanitation and hygiene: the Program supports improving sanitation and hygiene in the selected
communes of the participating provinces through promoting improved household sanitation, rehabilitation
and construction of water supply and sanitation facilities in schools, health care stations under the concept of
commune-wide sanitation and sustainable commune-wide sanitation. It is expected that 690 communes could
achieve commune-wide sanitation status, and among them 460 communes could meet status of sustainable
commune-wide sanitation.
(iii) Capacity building and implementation support: to support participating provinces during implementation,
there are several ministries and agencies involved with different roles and activities under overall
coordination from MARD. This support was effectively provided in the past years but starting from August
2021 there was a change in funding arrangement for these activities which only allows use of counterpart
funds instead of borrowed funds. This change caused shortage or/and delays in funding intended activities
and created risks of failure in providing adequate support to provinces as required under the Program. At
provincial level, capacity building activities mostly focus on preparation and implementation of different
plans, but recent spreading of Covid19 pandemic and delays in allocation of funds have negatively affected
progress in 2021. While all ministries and provinces are in stage of preparing budget plan for 2022, an
adequate allocation for implementing committed activities under the program should be secured.
5. Achievements per DLIs: The updated achievement of DLIs are described in detail (a) Institutional DLIs:
Based on the 2020 verification results all provinces have achieved the implementation of the Annual Program
Plans and Reports’ disclosure (DLI 3.1). Regarding the Behavior Change Communication (BCC) implementation
(DLI 1.1) and Capacity Building plans (DLI 3.2) all but one province (only Hoa Binh) have achieved the
implementation of planned activities. (b) Infrastructure DLIs: based on the 2020 verification results: 237
Communes reported CWS status (DLI 1.2); 83,998 new functioning household water connections were reported
(DLI 1.3); (c) sustainability DLIs: 47,357 sustainable water connections were reported (DLI 2.1); 130 sustainable
CWS communes were reported (DLI 2.2).
Table 1: Summary results achieved and verified to date
DLI Program
Target
Achieved 2016-2019
Results
Achieved 2020
Results
Total
results
to date
#
Total
results
to date
%
2021
Plan
DLI 1.1 # of Behavior Change Communication Plans implemented 105 66 20 86 82% 21
DLI 1.2 # of new commune achieving CWS 680 390 237 627 92% 71
DLI 1.3 # of new or rehabilitated Functioning Water Supply
Connections to households 255,000 123,710 83,998 207,708 81% 60,771
DLI 2.1 # of households with Sustainable Water Systems 105,000 8912 47,357 56,269 54% 49,735
DLI 2.2 # of Communes which have maintained CWS (from 2 CY
ago) 340 26 130 156 46% 216
DLI 3.1 # of Annual Program Plans and Program Reports disclosed 215 172 43 215 100% 43
3
DLI 3.2 # Annual Capacity Development Plans implemented 105 71 20 91 87% 21
6. Disbursement progress: The Program has disbursed 70% of the funds (US$134.4 million) to date, and an
additional USD 15 million is expected to be disbursed by Dec 2021.
7. High performing provinces: The high performing provinces of the water component include Son La, Yen
Bai, Phu Tho; the high performing group of the sanitation component includes Ha Giang, Thai Nguyen, Dak
Nong. These provinces are able to meet the allocated targets for water and/or sanitation by the current closing
date; and are able to exceed their targets with the extended implementation period. The Bank team suggests that
these provinces keep up their good performance and continue to submit additional results in water and sanitation,
thus contributing to an aggregated higher Program performance. (Detail progress in Annex 2)
8. Poor performance provinces: The poor performance provinces of the water component include Lang Son,
Lam Dong and Dak Nong. The poor performance provinces of the sanitation component include Hoa Binh,
Gia Lai and Lai Chau. These are provinces having risks of not having sufficient budget for all the expected
construction work in the provinces due to the possibilities of low verified results. The Bank team request
additional effort in these province and support from MARD, MOH, MOET for those provinces. (Detail progress
in Annex 2)
9. 2021 Budget allocation: 19/21 provinces have investment budget allocation approved by PPCs and been
preparing disbursement dossiers to CO/MARD. Dien Bien and Binh Thuan do not have this allocation for the
sub-projects due to their confusion in budget planning and so far Dien Bien has just got budget allocation from
MPI, while Binh Thuan is still waiting for such allocation. The total investment budget approved for the 19
provinces is about VND 500 bil, equivalent to USD 21 mil, which is much lower than the allocation in previous
year because the main activities in many provinces now shift to maintaining the sustainability of the constructed
facilities. Regarding the recurrent budget, which needs to cover all “soft” activities such as communication,
capacity building, etc as the Program restructures, the Mission is pleased to know that though the allocation of
counterpart funds by the provinces used to lag behind, for this year 20/21 provinces approved their counterpart
fund allocation, except for Binh Thuan, where the budget plan is under consideration and expected to be approved
in October 2021. The total counterpart fund approved for the provinces is about VND 43 billion in 2021,
equivalent to about USD 1.9 mil. which is evaluated as sufficient for most of the provinces to carry out planned
communication and capacity building activities (see detail in Annex 4).
10. The NTP-NRD that is linked to the RB-SupRSWS period 2021 - 2025 has been approved by the GoV and
starts to continue the implementation.
Main issues of the Program
11. Weak Program M&E system: the Program’s M&E system is not meeting the requirement due to poor
coordination between provincial implementing agencies and between provinces with central ministries. The
program reports usually are submitted with delays, lack of required information, poor presentation without
identifying the issues, reasons and measures for addressing them. This creates difficulties in timely interventions
from the MARD leadership, CO, Bank management and Bank team in guiding and helping provinces to improve
the performance as well as for the Bank team to evaluate the PAP action compliance. Thus the M&E system
needs improvement in assuring that accurate and timely information of program implementation is collected and
reported. The team was discussing with the program Coordination Office (CO) - MARD and related agencies
and request CO to allocate additional resources to fulfil the roles of a leading agency for M&E activities as
described in the POM. In addition, some templates for the reports have been revisited as part of the revision of
POM to ensure simplicity, but appropriateness of the information being reported. The program implementing
agencies in provinces were also requested to strengthen their capacity and procedures to improve quality of M&E
system. The Mission strongly request MARD to (i) improve CO capacity and collaboration between central
ministries/agencies; (ii) allocate sufficient resources to CO for improving quality of monitoring and reporting on
safeguard compliance; (iii) issue a letter to provinces to enforce reporting obligations before Oct 31. It was agreed
by management of the Water Resource Agency-MARD that CO resources will be strengthened from
NCERWASS as needed. It is important that the reports are submitted in a timely manner and of good quality for
the Bank to provide no objection for disbursements.
4
12. 2021 Investment budget advance and fund flow: Several advance requests were submitted but then
rejected by MOF. As requested by MOF (MOF letter of 27 Sep 2021 to MARD), the provinces have to disburse
all the fund balance from 2020 before requesting any new advance, or the fund balance from 2020 must be
deducted from the 2021 budget withdrawn. CO/MARD has urgently worked with provinces for these. The budget
advance has been delayed due to the Program extension/restructuring procedures (not until 6 September 2021 did
MOF countersign the revision of Financing Agreement) and now suffer further delay due to this requirement.
This consequently brings more challenge to investment activities in provinces.
13. 2021 Counterpart fund allocation: Due to the changes in the Program financing arrangements after July
2021, the recurrent budget allocation with ODA funds is no longer allowed but shifted to counterpart fund. The
Mission has been informed that while MARD and VIHEMA have received sufficient counterpart funds for 2021
activities, MOET and CEMA will not get budget for activities from August to December 2021 and now wait for
MOF approval on 2022 budget. Similarly, SAV is also waiting for MOF approval of budget for verification of
2021 and 2022 results. It is agreed that MARD will coordinate with SAV, MOET and CEMA in working with
MOF for speeding up the approval process. At the province level, some provinces seem to have lower counterpart
funds allocated for “soft” intervention activities, in comparison with the planned 2021 targets, such as Tuyen
Quang, Bac Giang, Phu Tho, Lao Cai.
14. Sustainability of water schemes: So far only about 54% of the Program target on sustainability has been
achieved. While the Program can be fully meeting the overall committed targets, there is a need to focus on
ensuring long term sustainability of the achieved results. The Mission has worked with 5 provinces and has
concerns on the persistent issues of low capacity of water operators and low water tariff in in rural area. There is
higher risk in provinces such as Cao Bang, Bac Kan, Ha Giang, Lai Chau, Dak Nong, Lang Son, Dien Bien, Yen
Bai where almost all water schemes are operated by the communes. The Mission discussed the solution with
NCERWASS in detail and recommend that MARD will utilize NCERWASS to conduct a study on post-program
O&M arrangement to identify strengths and weaknesses in the existing O&M arrangement in participating
provinces, propose necessary modification and disseminate successful lessons/ best practices that could be
replicated among the program participating provinces and scaling up in other provinces under the New Rural
Development NTP that will be implemented in next 5 years. From discussions with provinces, there was a
proposal to assign O&M of small water schemes to the Grassroots Irrigation Organizations in localities, while
the water supply schemes of medium size could be assigned to the Irrigation Exploitation Company – an entity
under the PPC responsible for managing medium and large irrigation schemes, or to the PCERWASSes. The
Mission fully supported such proposal and requested CO, NCERWASS to conduct a follow-up survey with
provinces to have more information that could help to identify in the above study the most appropriate options
for PPCs’ consideration.
15. Sustainability of CWS communes: so far only 46% of sustainable CWS target of the Program is reached
(156/340 communes). While the Program can be fully meeting the overall committed sanitation targets, there are
risks due to (i) potential shortage of counterpart funds allocated for “soft” intervention activities in some
provinces; (ii) the covid 19 pandemic which does not allow direct communication activities, which are most
effective intervention in BCC programs.
Program Action Plan (PAP)
16. Complaint mechanism and beneficiary feedback: These channels have been maintained through systems
of hotline telephone numbers in DARDs and in the Provincial Inspectorates. However, no feedback has been
posted (as reported by the provinces).
17. Procurement: Procurement implementation is progressing well in 13 out of 21 reporting provinces,
however reporting activity still remains weak, and even worse than in the previous mission. As advised by the
previous mission, the Procurement Progress Reports of the Program should be forwarded to the Bank at least 5
days prior to a mission, however by October 3, 2021, a project progress report has just been submitted to the
Bank team with very limited information on procurement. By October 3, 2021, only 13 out of 21 provinces have
reported a summarized number of the awarded contracts with 234 contracts awarded from beginning of the year
2021. The mission has advised/requested CO in various meetings during the mission that the reporting should be
in accordance with requirements included in the Financing Agreement: the reporting is an obligation of Borrower
represented by CO. By October 13, 2021, the updated consolidated report had just been submitted to the Bank.
5
And the most updated report shows that among 21 project provinces, 15 provinces have implemented
procurement in 2021. At the end of Quarter III, 422 contracts have been awarded, and so far, the PAP on
procurement is complied. MARD Inspectorates submitted the Internal Audit Report by May 31, 2021. The Bank
appreciates the procurement findings included in the Internal Audit report and request all provinces to implement
the recommendations/commitments included, and advise MARD Inspectorates that the recommended monitoring
indicators on procurement, included in the POM, be reported by next internal audit report. The complaint on
procurement in Binh Thuan has been resolved satisfactorily to the Bank, however the complaint in Daklak is still
pending, the mission would request CO/MARD Inspectorate to have a report on this case by October 31, 2021.
Due to weak reporting as aforesaid, the procurement performance is rated as Moderate Satisfactory.
18. Adequate budget allocation and timely transfer of funds: By the mission time (October 2021), 19/21
provinces have allocated IDA fund and 20/21 provinces have counterpart fund. The budget allocation was made
lately in all provinces in 2021, with the earliest decision in April 2021 and latest in September 2021. While
counterpart fund allocation is limited, several provinces made significant amounts of IDA allocation this year.
This practice caused high rates of unutilized IDA 2021 budget in the provinces, namely: Ninh Thuan – 65% of
allocated budget will not be spent; Dak Lak – 44%; Kon Tum - 38%; Bac Giang – 26%; and Hoa Binh – 100%
(no withdrawal will be made in 2021, only utilization of 2020 budget). This PAP action is assessed as partially
achieved by the mission.
19. Audited financial statements and internal audit function: Audited Program financial statements 2020 was
submitted before 31 July 2021 in accordance with Financing Agreement. The financial statements include all
sources and expenditures of the Program. Quality of audit report is satisfactory to the Bank. Internal audit function
has been improved gradually for the Program with participation of majority of provinces and leading role of
MARD Inspectorate. Regarding the Internal Audit Report, ONLY 15 out of 21 project provinces have done
internal audit. The mission reminded the PPCs of the 6 remaining provinces (Bac Giang, Phu Tho, Lao Cai, Lai
Chau, Lam Dong and Ninh Thuan) on this important fiduciary compliance and requested the PPCs to allocate
adequate resources to perform the function.
20. Social safeguards: Training workshops for local staff and consultations with beneficiaries were
continuously conducted with cumulative number of participants being 85,618 and 348,033, respectively. EM
participation rate in workshop is similar to last mission at 59% but the rate in consultation reduced from 58% to
38%. Vulnerable people also participated in these activities, but their attendance was not recorded. This mission
also observed the same proportion of women engaging in training activities as the last mission, at 49% but a
reduction from 39% to 22% in consultation. The participation rate of EM women in consultation reduces from
33% to 26%. Some provinces such as Cao Bang, Lao Cai, Hoa Binh, Son La, etc. lag behind with participation
rate less than 15%. Gender guidelines expect these percentages to be above 30%. There has been no pending or
non-compliant issue of land acquisition identified during the mission; no complaint has been identified so far. In
this mission, reporting on social aspects is delayed and there are difficulties in consolidating data from provinces,
from Health and Education components. The mission advises that the implementing agencies should 1) improve
the reporting progress; 2) verify consistency in the number reported; 3) promote more EM and gender targeted
consultation activities, with greater efforts in those provinces with low participation rates. The social performance
is assessed as Moderately Satisfactory due to delay in reporting implementation and reduction in some gender
and EM indicators.
21. Environmental safeguards: To facilitate the reporting process, the task team worked and agreed with the
Client on the revised environmental report template during the past period. The revised report template including
aspects on water supply scheme, school and commune health stations were circulated to participating provinces
by Aug 2021. However, by the mission period, reporting on environmental safeguard was slowly progressed and
largely delayed. It was noted that 20 provinces carried out environmental reporting for WSSes while only 08
provinces conducted environmental reporting for school and health sanitation. According to the submitted
reports, no issue during the construction happened during the past period. However, some issues were still noted:
(i) provincial reports did not provide adequate information as required; (ii) some WSSs lack water exploitation
permits although construction was completed (Bac Giang, Daknong, Hoa Binh, Lam Dong, Lao Cai, Phu Tho,
Ninh Thuan, Binh Thuan, Lai Chau, Lang Son); (iii) some WSSs lack the water discharge permits (Hoa Binh,
Ninh Thuan, Lao Cai, Binh Thuan, Phu Tho). The mission strongly requested CO to take action to improve the
reporting situation and pending issue. The environmental performance is assessed as Moderately Satisfactory due
to the poor reporting implementation and pending issues.
6
Other topics
22. Action plan
Actions Responsible Deadline
POM approval
Nov 10,
2021
1.Program Funding
1.1 Submission of withdraw applications for provinces Provinces, CO Nov 30,
2021
2. PAP compliance
2.1 Program M&E improvement. Quarterly consolidated report #3
including all agreed improvement from all 21 provinces, including
procurement, social and environmental aspects submit to the Bank for
review
CO,
NCERWASS,
VIHEMA,
provinces
Nov 10,
2021
2.2 MARD will issue a letter to provinces to enforce reporting
obligations
MARD Nov 10,
2021
3. Sanitation:
3.1 BCC and CB plans in remaining provinces approved for
implementation
CO, VIHEMA,
MOET,
provinces
Nov 10,
2021
4. Water Supply
4.1 Review on suitable O&M models for rural water supply schemes NCERWASS June 30,
2022
4.2 Update the situation of water exploitation permits and discharge
permits of all 21 provinces
NCERWASS Nov 10,
2021
4.3 Provinces urgently complete and send the dossiers/ evidence of water
schemes to NCERWASS for reviewing their eligibility before the
verification of 2021 results.
Provinces/
NCERWASS
Nov 30,
2021
23. Next mission: The next mission is scheduled for Mar 2022, but technical visits will take place regularly.
7
List of Annexes:
Annex 1: Results Framework
Annex 2: Detailed Program progress
Annex 3: Disbursement Linked Indicator results
Annex 4: 2021 Budget allocation
Annex 5: Social aspects
Annex 6: Notes of virtual meetings with 5 provinces
Annex 7: SAV 2020 result verification and 2021 verification plan
Annex 8: Provinces requiring more attention/support for new and sustainable FWSCs
Annex 9: Provinces requiring more attention/ support for new and sustainable CWS communes
Annex 10: List of people the Mission has met
8
Annex 1: Results Framework
Target
(original)Achiev.
Target
(original)Achiev.
Target
(original)Achiev.
Target
(original)Achiev.
Target
(original)Achiev.
Total of
population number 0 400,000 0 1,200,000 225,902 1,500,000 923,389 1,000,000 1,487,173 1,000,000 1,528,410
Female 0 47%43% 42%
46.5%
Female headed
HHs0 12%
21.0% 19.0%17.7%
EM HHs 0 39% 47.8% 46.0% 60.1%
PDO Indicator 2:
Households with access to sustainable
water supply services
(gender disaggregated by head of
household)
X number 0 0 0 0 0 25,000 8,912 80,000 47,357 105,000 56,269
PDO Indicator 3:
Communes achieving commune-wide
sanitationX number 0 50 0 150 27 200 134 140 229 140 237 680 627
PDO Indicator 4: Communes where
schools and health clinics have maintained
hygienic status
X number 0 0 0 0 45 0 125 26 170 130 340 156
PDO Indicator 5: New approaches for
BCC and supply chain activities are
included in the successor program to the
NTP3
No/Yes No No No No Yes No Yes Yes Yes Yes Yes yes yes
Intermediate Results Indicator 1:
Development and implementation of
behavior change communication (BCC)
plans; at the provincial, district, and
commune level
X Provinces 0 21 12 21 13 21 21 21 20 21 20 105 86
Intermediate Results Indicator 2: Schools
reached through targeted BCC campaignsnumber 0 100 0 300 377 400 402 280 643 280 802 1,360 2,224
Intermediate Results Indicator 3:
Clinics with antenatal programs which are
covered by BCC
Number
(cumulative –
activities
repeated
each year)
0 25 19 75 143 100 134 70 272 70 287 340 855
Intermediate Results Indicator 4: National
BCC program is launchedYes / No No No No No No Yes Yes Yes Yes Yes Yes Yes yes
Intermediate Results indicator 5: Increase
in hand washing with soap after using the
latrine increased among the target
population compared to non-program
communes
% 0 0 0 0 0 30 33% 20% 54% 20% 20 54%
PDO Indicator 1: Direct Program
Beneficiaries
(Disaggregated by; % female, % female
headed households and % EM household)
5,100,000X
Intermediate Results Area 1: Key hygienic behaviors changed amongst the population and increased access to basic services
2016
Results Indicators
4,164,874
Baseline
2018
Program Development Objective: To improve hygiene behavior, increase and sustain access to rural sanitation and water supply in rural areas in
the Participating Provinces.
2019
Program
total target
(original)
2020
Current
achievement
(2016-2020)
2017
Core DLIs Unit
9
Target
(original)Achiev.
Target
(original)Achiev.
Target
(original)Achiev.
Target
(original)Achiev.
Target
(original)Achiev.
Total of
household
connection
number 0 0 0 25,000 9,495 80,000 53,342 90,000 60,873 60,000 83,998 255,000 207,708
Female headed
households
1,139 11,202 12,936 14,764 12,593 40,041
Intermediate Results Indicator 7:
Schools and health centers with new and
rehabilitated water supply and sanitation
facilities
number 0 200 0 600 108 800 603 560 815 560 726 2,720 2,252
Intermediate Results Indicator 8: Annual
Program Plans and Reports disclosed
X number 0 43 43 43 43 43 43 43 43 43 43 215 215
Intermediate Results Indicator 9: Reports
on beneficiary feedback received and
feedback has been used
Number of
Provinces
with
Beneficiary
feedback
reports
produced and
used
0 5 1 10 1 15 21 21 21 21 21 72 65
Intermediate results indicator 10:
Approved Annual Capacity Development
Plan for Provinces implemented
X
Number of
provinces
which have
implemented
0 21 18 21 13 21 21 21 19 21 20 105 91
Intermediate results indicator 11: Systems
are in place and being used to monitor and
support sustainability of commune-wide
sanitation
Number of
communes
with systems
in place to
monitor
0 0 0 0 0 34 4 94 1,977 128 130 256 2,111
Results Indicators Core DLIs Unit Baseline
2016 2017 2018 Program total
target
(original)
Intermediate Results Area 2: Adequate water and sanitation infrastructure is in place and in working condition
Intermediate Results Area 3: Improved capacity for program implementation
Current
achievement
(2016-2019)
Intermediate Results Indicator 6:
New and rehabilitated functioning
household water supply connections
(FWSC)
(gender disaggregated)
X X
2019
10
Annex 2: Detailed Program progress
Water supply:
1. New water connections: Although the overall 2020 result is better than the previous year (see para. 4), several
provinces (Lam Dong, Lang Son, Dak Nong) are lagging with cumulative result less than 45% of their targets so far.
There were several reasons for such delays, which included (i) unclear implementation arrangement and insufficient
funding allocations during the initial years of program implementation, (ii) slow processing documentations required
under the Government’s regulations for a construction investment project, (iii) complexity of site conditions where
many system are constructed in mountainous and isolated locations, (iv) weak capacity of the implementing agencies,
and (v) restrictions associated with measures imposed by the Government in combating COVID19 pandemic. The
Mission agreed that NCERWASS will step up targeted support to the lagging-behind provinces and will carry out
monthly monitoring of the implementation progress to secure the 2021 results and planned achievement for 2022.
2. Sustainability of water schemes: 47,357 households benefit from 72 sustainable water schemes in 2020. Though
this result is much better than that of the previous year (and some provinces may over-achieve their Program targets)
the overall cumulative result by the end of 2020 is only 54% of the Program target, 11 provinces achieved less than
50% their Program targets, even 4 of them have had no result to date (Lang Son, Bac Kan, Binh Thuan, Lam Dong).
The reasons for low achievement are associated with delays in completing construction activities for new or expanded
water supply schemes, unclear arrangement of O&M service, weak capacity of O&M entities and slow application
of the adequate water tariff system. It is challenging and requires more targeted support for the lagging behind
provinces to achieve the Program target. It is agreed that MARD will send a letter to the provinces requesting the
PPCs to direct the involved DPCs and CPCs to take full responsibility for the sustainability of the water schemes.
3. Information, Education and Communication (IEC) activities: though IEC activities have been implemented
in all provinces, more effort need to be done at scheme level to improve the willingness to pay and water use from
local people. In 5 provinces that the mission has virtual meetings with, there are many issues related to unwillingness
of proper water tariff application or water unuse, which is decisive impact on the scheme sustainability. The mission
requested PCERWASSs to support water scheme operators to carry out IEC activities as needed.
4. M&E system in MARD: The Water Resources Directorate inform the Mission that the web-based M&E
system for all indicators under WRD has been finalized incorporating the set of indicators for rural water supply
and start application. However it needs time for changing the provincial practice, so far the reporting are still
mainly based on paper work.
5. Water Exploitation Permit: There are 226 permits that have been approved under the Program (in quarter 2
of 2021, there were additional 17 permits issued in Hòa Bình, Sơn La, Bình Thuận, Đăk Lăk và Đăk NMr.), and
other 26 applications are under consideration for approval. The Mission request provinces, especially Lao Cai, to
urgently finalize this procedure by 31 December 2021.
6. NCERWASS’s support: It is extremely important that NCERWASS continue to provide technical support to
provinces in last few months of 2021 and throughout 2022 to improve the water scheme sustainability. The Mission
strongly request MARD to allocate sufficient resource for NCERWASS for the support activities and also the
survey on suitable O&M models to help PPCs for better institutional arrangement for water schemes constructed
under the Program and also NRD NTPs.
Sanitation
7. CWS: Currently 11/21 provinces have completed and/or exceeded the allocated CWS targets, while 10 provinces
have not yet completed their targets: Lang Son, Cao Bang, Thai Nguyen, Bac Giang, Tuyen Quang, Lai Chau, Dien
Bien, Phu Tho, Hoa Binh, Gia Lai, in which Lai Chau, Phu Tho and Hoa Binh still have many communes that have
not reach CWS (respectively 8, 14, 28 communes. To incentivize good sanitation results, BCC activities have to be
enhanced and the operation of the sanitation shops should be improved. The mission emphasized that the SANCON
model still needs continued support to be developed in newly intervened and sustainable communes.
8. Sustainable CWS: By the end of 2020, 2/21 provinces have completed and exceeded the targets: Ha Giang,
Daknong. Provinces that achieved very low results (below 20%) are: Gia Lai and Cao Bang. The mission
11
recommends that the remaining 19/21 provinces need to have a plan for close intervention and supervision,
especially in health centers and schools.
9. BCC and CB plans: 18/21 provinces have approved 2021 BCC plans and remaining 03 provinces (Son La, Lam
Dong and Binh Thuan) has BCC plans under consideration for approval. Regarding CB plan, 16/21 provinces have
the approved plan and the remaining (Son La, Phu Tho, Lam Dong, Ninh Thuan, Binh Thuan) are under
consideration. Due to critical covid 19 pandemic in last 03 months, so far only 12 provinces start with the
implementation.
10. M&E system in MOH and MOET: Currently, 745 communes of 18/21 provinces using the M&E software,
3 provinces have not yet implemented (Thai Nguyen, Tuyen Quang, and Gia Lai) because software training has not
been organized to districts and communes. VIHEMA has sufficient 2020 counterpart fund allocated and been
selecting a firm to updating the web-based M&E system and will provide coaching sessions in applying the M&E
platform to all 21 provinces. M&E indicators for school water supply and sanitation facilities is under MOET
consideration for integrating with MOET’s web based M&E system for all monitoring indicators in schools. The
Mission is informed that while waiting for the process, MOET still maintain the paper reporting system with
provinces.
11. Nutrition integration and antenatal program: VIHEMA reported that 278 communes in 21 provinces are
implementing the antenatal programs and integrating nutrition topics into BCC activities. VIHEMA is continuously
guiding DoH/CDC to integrate nutrition topics into BCC training and activities by sending reminders and close
monitoring to provinces.
12. National BCC program: MOH is still directing the provinces to implement the national BCC program on clean
water and rural sanitation throughout the country. In 2021, MOH has developed infographics and leaflets and
implemented BCC activities on personal hygiene, handwashing with soap against COVID-19 through mass media
and social networks. These activities will continue to be strengthened in the provinces.
13. Support for poor HHs: VIHEMA reports that 3,182 households in 21 provinces have built latrines in 2021 with
program financial support, accumulated number to October 2021 is 63,309 latrines, reaching 64.8% of the target. 3
provinces have completed (Thai Nguyen, Lao Cai, Bac Kan) and 4 provinces have achieved 80-90% of their allocated
targets (Tuyen Quang, Bac Giang, and Ha Giang).
14. VIHEMA activities: VIHEMA has continued providing guidance and support the provinces through its staff
and a consulting firm, in planning, applying for counterpart funding and implementing the “soft activities” in 2021,
especially activities related to COVID-19 prevention (implementing communication campaigns on handwashing
with soap, personal hygiene...). VIHEMA agrees to provide more guidance and support to weak performance
provinces in this last quarter of the year.
15. MOET activities: MOET has provided support provinces and carried out an assessment on awareness/ behavior
change of students and teachers on water and sanitation issues under Program’s provinces. MOET will send the
survey report to WB on October 30, 2021 for review. However, the support from MOET will be just limited at on-
line support as no counterpart budget available for last five months of 2021. MOET will send request to the provinces
to push up the implementation of BCC activities, with special attention to support weak provinces such as Lai Chau,
Hoa Binh, Cao Bang.
16. CEMA activities: Though plan and budget from the loan for implementation until the end of July 2021 was
available, however, due to the COVID-19 pandemic, CEMA was unable to carry out any activities. Similar to MOET,
the support from CEMA in last few months of 2021 will be limited at on-line support as no budget available for last
five months of 2021.
12
Annex 3: Disbursement Linked Indicator results
%
1 Lạng Sơn 5 4 25 24 96% 1 13,000 4,791 37% 8,209 5,353 - 0% 5,353 13 5 38% 8 5 5 5 5
2 Hà Giang 5 5 35 35 100% 0 11,300 10,971 97% 329 4,653 1,531 33% 3,122 18 19 106% (1) 5 5 5 5
3 Cao Bằng 5 5 35 34 97% 1 12,600 8,735 69% 3,865 5,188 1,099 21% 4,089 18 3 17% 15 5 5 5 5
4 Bắc Kạn 5 5 30 34 113% -4 10,400 10,615 102% (215) 4,282 - 0% 4,282 15 5 33% 10 5 5 5 5
5 Thái Nguyên 5 5 35 34 97% 1 12,500 9,010 72% 3,490 5,147 1,240 24% 3,907 18 17 94% 1 5 5 5 5
6 Bắc Giang 5 4 50 49 98% 1 13,200 9,125 69% 4,075 5,435 5,892 108% (457) 25 5 20% 20 5 5 5 4
7 Tuyên Quang 5 4 45 40 89% 5 12,900 9,810 76% 3,090 5,312 3,278 62% 2,034 23 11 48% 12 5 5 5 4
8 Yên Bái 5 4 50 50 100% 0 11,000 11,081 101% (81) 4,529 4,639 102% (110) 25 10 40% 15 5 5 5 5
9 Lào Cai 5 5 35 35 100% 0 11,000 9,172 83% 1,828 4,529 1,159 26% 3,370 18 5 28% 13 5 5 5 5
10 Sơn La 5 5 25 28 112% -3 13,400 17,603 131% (4,203) 5,518 7,726 140% (2,208) 13 8 62% 5 5 5 5 5
11 Điện Biên 5 4 45 44 98% 1 10,700 15,477 145% (4,777) 4,406 4,266 97% 140 23 10 43% 13 5 5 5 4
12 Lai Châu 5 2 25 17 68% 8 9,400 6,876 73% 2,524 3,871 2,309 60% 1,562 13 5 38% 8 5 5 5 2
13 Phú Thọ 5 4 54 40 74% 14 11,700 15,864 136% (4,164) 4,818 5,682 118% (864) 27 14 52% 13 5 5 5 4
14 Hòa Bình 5 2 60 32 53% 28 13,800 8,339 60% 5,461 5,682 2,912 51% 2,770 30 11 37% 19 5 5 5 1
15 Kon Tum 5 4 25 25 100% 0 12,300 8,016 65% 4,284 5,065 492 10% 4,573 13 5 38% 8 5 5 5 5
16 Gia Lai 5 3 30 21 70% 9 11,000 6,585 60% 4,415 4,529 1,488 33% 3,041 15 2 13% 13 5 5 5 4
17 Daklak 5 4 30 33 110% -3 14,000 11,270 81% 2,730 5,765 4,188 73% 1,577 15 4 27% 11 5 5 5 5
3 Daknong 5 4 15 18 120% -3 11,700 4,945 42% 6,755 4,818 516 11% 4,302 8 9 113% (1) 5 5 5 5
19 Lam Dong 5 3 16 18 113% -2 12,500 2,525 20% 9,975 5,147 - 0% 5,147 8 2 25% 6 5 5 5 3
20 Binh Thuan 5 5 10 10 100% 0 11,900 11,067 93% 833 4,900 - 0% 4,900 5 4 80% 1 5 5 5 5
21 Ninh Thuan 5 5 5 6 120% -1 14,700 15,831 108% (1,131) 6,053 7,852 130% (1,799) 3 2 67% 1 5 5 5 5
Total 105 86 680 627 53 255,000 207,708 81% 47,292 105,000 56,269 54% 48,731 346 156 190 105 105 105 91
Total
achieved
until 2020
Total
achieved
until 2020
Orginal
Target
Orginal
Target
DLI 3.2. CB plan achieved
Province/
Commune
DLI 1.1. BCC plan
achieved DLI 1.2 CWS DLI 1.3 Water Connection DLI 2.1 Sustainable water connection
%Remaining
target
Total
achieved
until 2020
Orginal
Target
Orginal
Target
Remaining
target
DLI 3.1. Annual plan
and report achieved
Orginal
Target
Total
achieved
until 2020
%Remaining
target
Total
achieved
until 2020
%Remaining
target
Total
achieved
until 2020
DLI 2.2. Sustainable CWS
Orginal
Target
Total
achieved
until 2020
Orginal
Target
13
Annex 4: 2021 Budget allocation
Total of
allocation Allocated On-lending
1 Hà Giang 850,000 402,000 337,000 111,000 Approved 58,654,536 30,224,000 3,778,000 5,481,813 19,170,723 - Approved 58,445,360 Approved Approved Approved The application was
sent to WB on Sep.9
2 Cao Bằng 1,590,000 40,000 1,270,000 280,000 Approved 32,991,480 21,032,000 2,629,000 1,903,449 7,427,031 - Approved 34,364,740 Approved Approved Approved In preparation
3 Tuyên Quang 522,361 136,805 285,556 100,000 Approved 11,010,640 8,085,090 1,010,640 900,000 1,014,910 3,000,000 Approved 10,982,910 Approved Approved Approved The application was
sent to CO on Sep.14
4 Bắc Cạn 2,730,000 339,000 2,167,000 224,000 Approved 41,445,000 26,656,000 3,332,000 0.00 11,457,000 - Approved 40,334,300 Approved Approved Approved The application was
sent to WB on Aug. 25
5 Lạng Sơn 1,152,000 88,000 996,000 68,000 Approved 21,435,975 13,742,200 1,717,775 1,700,000 4,276,000 Approved 18,893,980 Approved Approved Approved The application was
sent to WB on Aug. 25
6 Bắc Giang 1,248,200 700,000 529,700 18,500 Approved 21,808,000 14,464,000 1,808,000 5,036,000 500,000 135,000 Approved 16,179,090 Approved Approved Approved The application was
sent to WB on Aug. 25
7 Thái Nguyên 2,000,000 1,321,000 356,000 323,000 Approved 35,237,875 25,783,000 3,222,875 2,752,000 3,480,000 2,500,000 Approved 35,095,850 Approved Approved Approved The application was
sent to WB on Aug. 25
1 Yên Bái2,890,000 98,000 2,733,000
59,000 Approved 14,354,750 10,982,000 1,372,750 2,000,000 - - Approved 14,354,000 Approved Approved Approved The application was
sent to CO on Sep.10
2 Lào Cai 725,330.0 203,330 480,000 42,000 Approved 11,348,000 9,584,000 1,198,000 150,000 416,000 1,000,000 Approved 10,583,130 Approved Approved Approved The application was
sent to WB on Sep.9
3 Sơn La 407,000.0 196,774 150,802 59,424 Approved -
The allocated
budget in the
program has
been disbursed
- Approved Submitted
to PPC
Submitted
to PPC
4 Điện Biên 3,150,000.0 500,000 2,130,000 520,000 Approved Submitted to
PPC 20,000,000 Approved Approved Approved
5 Lai Châu 2,314,000.0 220,000 1,810,000 284,000 Approved 34,896,000 25,416,000 3,177,000 454,000 5,849,000 2,500,000 Approved 34,509,810 Approved Approved Approved The application was
sent to CO on Sep.7
6 Phú Thọ 1,000,000.0 50,000 900,000 50,000 Approved 31,820,000 8,576,000 1,072,000 - 22,172,000 2,000,000 Approved 19,880,240 Approved Approved Submitted
to PPC
7 Hòa Bình 5,598,014.0 503,573 4,200,441 894,000 Approved 43,793,240 28,000,000 3,500,000 9,937,000 2,356,240 3,500,000 Approved - Approved Approved Approved
1 Kon Tum 1,829,000 1,529,000 200,000 100,000 Approved 40,392,000 35,904,000 4,488,000 0 Approved 24,911,850 Approved Approved Approved
2 Gia Lai 916,170 112,300 612,870 191,000 Approved 37,094,295 24,754,363 3,094,295 2,218,084 7,027,553 5,141,010 Approved 34,156,980 Approved Approved Approved The application was
sent to CO in Sep.
3 Dak Lak 2,235,785 632,000 1,226,705 377,080 Approved 45,575,000 36,384,000 4,548,000 2,947,000 1,696,000 Approved 25,575,000 Approved Approved Approved The application was
sent to CO in 18/8
4 Dak Nong 1,000,000 350,000 550,000 100,000 Approved 28,948,500 23,588,000 2,948,500 678,800 1,733,200 Approved 28,912,380 Approved Approved Approved The application was
sent to CO in 18/8
5 Lam Dong 760,000 200,000 350,000 210,000 Approved 45,098,000 34,984,000 4,373,000 621,000 5,120,000 2,000,000 Approved 40,909,210 Approved Developing Developing
The application was
sent to CO in August
but have to adjust
6 Ninh Thuan 482,338 0 326,093 156,245 Approved 67,104,500 56,720,000 7,090,000 3,294,500 Approved 23,263,603 Approved Approved Developing
The application was
sent to CO but have
to adjust
7 Binh Thuan
No
allocation
from MPI
20,000,000 Approved Developing Developing
TOTAL FOR
PROVINCES43,300,198 7,621,782 21,611,167 4,167,249 - 623,007,791 434,878,653 54,359,835 36,779,146 96,990,157 21,776,010 - 511,352,433
Submit the dosier for
withdrawal
2021 plans
PROVINCE
RECURRENT BUDGET INVESTMENT BUDGET
NO. Total
Water
sector
Education
sector Approved
Counterpart
Fund
NORTH-EAST PROVINCES
NORTH-WEST PROVINCES
CENTRAL HIGHLAND AND NINH THUAN, BINH THUAN
Health sector
Annual plan BCC plan CB planTotal
Water sector
Health sector
Education
sector Approved
Plan to
withdraw
budget 2021
14
Annex 5: Social aspects
Nr Capacity Building
Indicators Cao
Bằng Thái
Nguyên Tuyên Quang
Yên Bái
Hà Giang
Lạng Sơn
Bắc Kan
Lào Cai
Phú Thọ
Bắc Giang
Hòa Bình
Sơn La Lai
Châu Điện Biên
Đắk NMr.
Đắk Lắk
Kon Tum
Lâm Đồng
Gia Lai Bình
Thuận Ninh
Thuận Total %
1 Trainers/communic
ators
#participant 23 6 56 1,123 3 40 556 2 236 2,220 41 521 33 522 10 20 5 30 21 99 44 5,611
#women participants
14 3 31 508 1 35 440 0 254 1,093 39 208 25 163 3 10 1 9 16 48 19 2,920 52%
2 Training/workshop
s
#participant 1,317 670 6,616 6,567 78 491 3,614 673 1,627 3,840 898 2,404 296 42,385 2,588 3,292 244 2,489 803 3,390 1,336 85,618
#women participants
447 193 3,503 3,171 16 321 1,961 193 699 2,829 170 886 69 21,026 990 1,272 35 516 283 2,658 636 41,874 49%
# EM participants
1,258 154 2,650 1,727 54 398 3,181 367 424 303 770 1,605 181 35,570 394 553 48 197 253 47 381 50,515 59%
# EM women participants
440 53 1,941 336 12 235 1,512 118 128 47 118 984 42 190 96 236 73 97 112 38 172 6,980 14%
3 Consultati
on
# participants
12,557 8,909 11,127 12,978 19,495 37,793 29,988 12,136 2,674 1,958 48,790 13,820 13,060 41,983 13,287 14,414 16,441 17,017 13,050 158 6,398 348,033
# women participants
840 3,509 1,056 3,598 5,271 15,061 4,879 3,080 342 196 5,830 567 1,694 7,570 2,512 2,936 6,759 6,209 4,907 70 330 77,216 22%
# EM participants
1,884 3,735 1,484 3,701 9,370 12,041 17,723 3,275 144 278 29,560 1,351 7,036 17,266 2,875 2,648 7,592 5,506 2,869 0 488 130,826 38%
# EM women participants
814 1,115 931 642 1,757 1,513 4,544 1,959 50 110 4,182 443 1,414 4,702 488 612 2,441 4,973 1,481 0 262 34,433 26%
4 Total
# Total participants
13,897 9,585 17,799 20,668 19,576 38,324 34,158 12,811 4,537 8,018 49,729 16,745 13,389 84,890 15,885 17,726 16,690 19,536 13,874 3,647 7,778 439,262
# women participants
1,301 3,705 4,590 7,277 5,288 15418 5036 1604 1652 2491 6,039 1,661 1,788 28,759 3,505 4,218 6,795 6,734 5,206 2,776 985 122,010
% women 9.4 38.7 25.8 35.2 27.0 40% 15% 13% 36% 31% 12% 10% 13% 34% 22% 24% 41% 34% 38% 76% 13% 28%
# EM participants
3,142 3,889 4,134 5,428 9,424 12,439 20,904 3,642 568 581 30,330 2,956 7,217 52,836 3,269 3,201 7,640 5,703 3,122 47 869 181,341
% EM participants
23 41 23 26 48 32% 61% 28% 13% 7% 61% 18% 54% 62% 21% 18% 46% 29% 23% 1% 11% 41%
15
Annex 6: Notes of virtual meetings with 5 provinces
I. BAC KAN ON OCT. 6, 2021
1. Progress to date
2. Implementation Status and Pending Issues
Plan and budget for 2021:
Provincial annual plan, BCC and CB plans have been approved. The counterpart fund was approved. The application
for budget withdrawal has been sent to WB and MOF.
2021 activity implementation: PCERWASS, CDC and DOET are implementing the planned activities and will complete
all core activities at the end of 2021.
New and sustainable CWS: Bac Kan has achieved and exceeded the allocated CWS target in 2020. In 2021, 100% of
the sustainable CWS target can be achieved if CDC, DOET make efforts to implement BCC activities and work closely
to carry out monitoring activities at schools and health stations.
New and sustainable FWSC: The province has achieved the DLI 1.3 in 2020 and can be able to achieve DLI 2.1 at the
end of 2022 but the sustainability of water schemes is a very important issue that needs the attention of all stakeholders,
especially from PPC.
- Total of registered water schemes in the program is 156 schemes. 130 schemes from WB’s fund and 17 schemes
funded by other donors were completed and verified from 2016-2020. There are 26 schemes are in progress of
construction and will be completed at the end of 2021.
- 100% of water schemes are small and managed by CPC; There are 25 of 130 schemes (20%) have not yet applied
the water tariff. The applied water tariffs are very low, only 1000 – 3000 VND/m3 and there is no reserve fund to
repair breakdowns or solve problems (if any)
- The capacity of the O&M team is still weak, that affects the quality of O&M activities.
Gender and Ethnic Minorities: Currently, the participation rate of women in program activities such as capacity
building, consultation, O&M of water schemes, etc. is low, accounting for just over 20%.
Quarterly report: the submitted report has not updated all the information and is inaccurate in some points, especially
the content related to the environment, gender and ethnic minorities.
3. Agreements/ Recommendations:
- PPC will re-evaluate the application of the current water tariff at water schemes and the ability of the community to
pay, report to the Provincial People's Council about the water tariff compensation to ensure the quality and
sustainable O&M of water schemes.
- It is recommended that PPC considers to apply different O&M models of water schemes in the intervention
communes, for example, assign O&M of small water schemes to the community irrigation groups, while the water
supply schemes of medium size could be assigned to PCERWASS.
- The province should pay attention to ensure the water quality of water schemes, both the frequency of monitoring
and the quality according to the requirements of MOH.
- The province will direct all related agencies to strengthen the monitoring and supervision of O&M activities of water
schemes;
- PCERWASS will continue to train/ support the O&M teams in technical terms for O&M works, promptly detecting
problems and guide remedial action; continue to support the O&M team to carry out IEC activities to increase the
community's responsibility in managing water schemes.
- The province will strengthen the gender and ethnic minority activities, especially women's participation in project
activities.
- The province will: i) provide missing information, complete the quarterly report and send to CO/WB; ii) reviews,
corrects and submits capital withdrawal documents at the request of the MOF as soon as possible;
- PCERWASS will send the documents/ dossiers of water schemes as soon as possible for review and approval of the
eligibility in 2021.
# %
DLI 1.1 BCC plan achieved 5 5 100% 0 1 1
DLI 1.2 CWS 30 34 113% 0 0 0
DLI 1.3 FWSC 10,400 10,615 102% 0 1,671 0
DLI 2.1 Sustainable FWSC 4,282 - 0% 4,282 3,720 562
DLI 2.2 Sustainable CWS 15 5 33% 10 13 0
DLI 3.1 Annual plan/ report 10 10 100% 0 2 2
DLI 3.2 CB plan achieved 5 5 100% 0 1 1
DLIsAllocated
targets
Results achieved
until 2020Remaining
targets2021 Plan 2022 plan
16
II. CAO BANG ON OCT 7, 2021
1. Progress to date
2. Implementation Status and Pending Issues
Plan and budget for 2021: provincial annual plan, BCC and CB plans have been approved. The counterpart fund was
approved. The province is preparing the application for budget withdrawal and expect to send to CO in Oct. 2021
2021 activity implementation: Due to the slow approval of counterpart funds and plans, all related sectors have not been
able to carry out any activities yet.
New and sustainable CWS: Cao Bang can achieve the CWS target at the end of 2021 and the sustainable CWS target at
the end of 2022 but the province needs to put a lot of effort towards sustainable CWS.
New and sustainable FWSC: It will be difficult for the province to achieve water targets and especially the long-term
sustainability of water scheme.
- Total of registered water schemes in the program is 87 schemes. From 2016-2020, 70 schemes were completed
and verified. There are 15 schemes in progress of construction. 2 remaining schemes will be started in 2022.
- 100% of water schemes are managed by CPC; Most of the schemes are small, from 50-400 connections/ scheme;
- No strong involvement of CPC in the application of water tariffs and the management of water schemes. Some
schemes have not yet applied the water tariff after one year putting into use. There are still 36 schemes not yet
apply the water tariff (50%). The applied water tariffs are low, from 2000 – 5000 VND/m3.
- Construction quality is not good: The construction period of some schemes still lasted for 2 years and not yet
handed over now. Some schemes after construction have not been able to operate due to technical problems or not
have enough water source in the dry season.
- The IEC activities about clean water have not been implemented much to the community, they are only simple
activities such as community consultations/ meetings on connection, setting water tariff.
Gender and Ethnic Minorities: Currently, the participation rate of women in program activities such as capacity
building, consultation, O&M of water schemes, etc. is low.
Quarterly report: the submitted report has not updated all the information and is inaccurate in some points, especially
the content related to the environment, gender and ethnic minorities.
3. Recommendations:
- The province committed to speed up the construction progress to complete the remaining schemes.
- DARD to suggest/ report PPC on the plan for O&M models of water schemes in the intervention communes,
especially for inter-communal schemes.
- DARD/ PCERWASS will review the construction progress and quality of water schemes, provides specific
solutions, reports to PPC, national agencies and WB on 30/11/2021.
- The province should pay attention to ensure the water quality of water schemes, both monitoring frequency and
quality according to the requirements of MOH.
- PCERWASS continues to train/ support the O&M teams in technical terms and strengthens monitoring of scheme
operations, promptly detecting problems and guide remedial action; continue to support the O&M team to carry
out IEC activities to increase the community's responsibility in managing water schemes, especially ethnic
minorities’ and women's participation in project activities.
- The province will: i) provide missing information, complete the quarterly report and send to CO/WB; ii) reviews,
corrects and submits capital withdrawal documents at the request of the MOF as soon as possible;
- PCERWASS will send the documents/ dossiers of water schemes as soon as possible for review and approval of
the eligibility.
# %
DLI 1.1 BCC plan achieved 5 5 100% 0 1 1
DLI 1.2 CWS 35 34 97% 1 1 0
DLI 1.3 FWSC 12,600 8,735 69% 3,865 2,832 1,033
DLI 2.1 Sustainable FWSC 5,188 1,099 21% 4,089 2,459 1,630
DLI 2.2 Sustainable CWS 18 3 17% 15 8 7
DLI 3.1 Annual plan/ report 10 10 100% 0 2 2
DLI 3.2 CB plan achieved 5 5 100% 0 1 1
2022 plan2021 PlanDLIsAllocated
targets
Results achieved until
2020Remaining
targets
17
III. DAK NONG ON OCT. 8, 2021
1. Progress to date
2. Implementation Status and Pending Issues
Plan and budget for 2021: provincial annual plan, BCC and CB plans have been approved. The counterpart fund was
approved. The application for budget withdrawal has been sent to WB and MOF in August 19, 2021.
2021 activity implementation: Due to the late approval of counterpart funds and plans, only the health sector has
commenced the first activity in early October. The water and health sectors have yet to carry out any activities.
New and sustainable CWS: Dak Nong has achieved and exceeded the allocated new and sustainable CWS targets in
2020.
New and sustainable FWSC: It may be difficult for Dak Nong to achieve the allocated water targets
- Total of registered water schemes in the program is 24 schemes. 12 schemes were completed and verified from
2016-2020. In 2021 there are 11 schemes in progress of construction. 1 remaining schemes will be started at the
end 2021.
- Responsibility for O&M: Dak Nong PPC has issues a notification on September 13, 2021 on the assignment of
water schemes under the SuP program to Dak Nong Irrigation Exploitation One Member Limited Liability
Company to operate and manage. Currently, out of 12 schemes, 2 schemes are managed by PCERWASS, the
remaining 10 schemes are managed by CPCs.
- There are 7/12 schemes not yet apply the water tariff (58%). The applied water tariffs are from 3000 – 7000
VND/m3
- The construction and the preparation/ submission of the evidences for reviewing the eligibility of water schemes
are very slow.
- Some schemes do not have enough connections (after construction) according to the approved design and some
schemes are at risk of not operating after construction is completed. For example, the water supply scheme in
Long Son commune has been inactive for a long time.
- The communication activities about clean water have not been implemented much to the community, they are only
simple activities such as community consultations/ meetings on connection, setting water tariff.
3. Agreements/ Recommendation:
- The province committed to speed up the construction progress to complete the remaing schemes
- It is recommended that the Irrigation Exploitation Company, the unit will be assigned to responsible for O&M of
the water schemes, closely coordinate with PCERWASS and the District PMU to participate in supervising the
construction and IEC implementation process as well as training courses on program criteria to understand the
requirement for sustainability of water schemes.
- PCERWASS and district PMUs will review and re-evaluate all 12 completed schemes, propose solutions for
solving the encountered problems, especially water scheme for Long Son commune, Dak Mil district. This
assessment report will be completed and send to MARD/NCERWASS and WB by 11/30/2021
- PCERWASS will review and revise the quarterly report, add missing information and send to CO as soon as
possible. The timely and complete submission of quarterly reports is one of the conditions for approving the
provincial budget withdrawal application.
- PCERWASS and the District PMUs will collect and submit the evidence for reviewing the eligibility of water
schemes soon (both new and sustainable schemes), before November 30, 2021.
- PCERWASS will coordinate with District PMUs to: i) adjust the application for budget withdrawal and send to
CO before October 15, 2021; ii) Urgently apply for discharge permits for 24 schemes funded by WB
# %
DLI 1.1 BCC plan achieved 5 4 80% 1 1 1
DLI 1.2 CWS 15 18 120% -3 1 0
DLI 1.3 FWSC 11,700 4,945 42% 6,755 4,169 2,586
DLI 2.1 Sustainable FWSC 4,818 516 11% 4,302 2,069 2,500
DLI 2.2 Sustainable CWS 8 9 113% -1 6 3
DLI 3.1 Annual plan/ report 10 10 100% 0 1 1
DLI 3.2 CB plan achieved 5 5 100% 0 1 1
2021 Plan 2022 planDLIsAllocated
targets
Results achieved
until 2020 Remaining
targets
18
IV. LAI CHAU ON OCT. 6, 2021
1. Progress in Lai Chau province
No Indicator Allocated
targets
Result achieved until 2020 Remainin
g targets
2021
Plan
2022
Plan # %
DLI 1.2 CWS 25 17 68% 8 8 0
DLI 1.3 Water connection 9,400 6,876 73% 2,524 2500 1000
DLI 2.1 Sustainable
connection 3,871 2,309 60% 1,562 1,800 500
DLI 2.2 Sustainable CWS 13 5 38% 8 4 4
The mission had a meeting with leaders of DARD, DOH, DoET, CDC, and PCERWASS, which was chaired by Mr.
Vuong Duc Loi – Vice Director of Lai Chau DARD. The list of participants is attached as an annex.
The mission discussed with the implementing agencies on the implementation progress, details as below:
2. Challenges/difficulties:
Work plan 2021: The BCC and CB plans 2021 have been approved and will stared in October 2021.
Budget for 2021: The province has allocated investment capital and non-business budget in September 2021.
The province has submitted the dossier of fund withdrawal to and is waiting for approval of CO.
Sustainable CWS and CWS communes: According to the work plan 2021, the province targets to achieve 8
CWS communes and 4 sustainable CWS communes. Thus, it is expected that the province will complete the
target of CWS communes by the end of 2021, and the target of sustainable CWS communes by the end of 2022.
To achieve the targets in the two years, it requires the determination and close coordination of the sectors, and
enough allocated counterpart fund for annual demand.
New FWSC: According to the assessment, it will be difficult for the province to achieve the target in 2021
because the 5 water schemes that are expected to register for verification in 2021 have not yet started construction
and are under tendering process.
Sustainable FWSC: It is expected that the province will achieve 1.562 connections and complete the target for
the whole period in 2021. The province should focus on overcoming the following challenges to ensure the
effectiveness and sustainability of the water schemes: i) The low water tariff (2000 dong/m3), thus the income
cannot cover the monthly expenditures; ii) the capacity of the O&M team is limited; iii) Support of PCERWASS
to the water schemes is limited. Therefore, local people are not fully aware of the water schemes, so they do not
trust and are willing to use the water.
Issues of gender, ethnic minorities and periodic report: The percentage of women participating in the
activities is low. According to the provincial periodic report, The province has issued the environmental impact
report for 3rd quarter but it has no changes to the 2nd quarter report, the province should update and finalize the
report with the latest information for each quarter.
3. Agreement
- The province committed to speed up the progress to achieve the target, in which it is committed to advise the
PPC to arrange annual non-business budget for completing 2 disbursement targets of DLI 1, DLI 3.2 in the
remaining 2 years.
- CDC and DoET will coordinate to review the status of water and sanitation schemes of the communes
intervened in 2021, ensuring to achieve 8 CWS communes and 4 sustainable CWS in 2021, the remaining 4
sustainable CWS communes in 2022.
- DARD will advise the PPC to promulgate the water tariff framework, and advise the PPC to issue an official
letter on assigning the above units for the water scheme management to improve their management and
operation responsibilities.
- DARD will review and assess the status of 11 operating water schemes in the framework of the program,
based on that, DARD will advise PPC on the report sent to CO and WB by 30th November.
19
V. LAM DONG ON OCT. 7, 2021
1. Progress in Lam Dong province
No Indicator Allocated
targets
Result achieved until 2020 Remainin
g targets
2021
Plan
2022
Plan # %
DLI 1.2 CWS 16 18 113% 0 0 0
DLI 1.3 Water connection 12,500 2,525 20% 9,975 6,000 4,000
DLI 2.1 Sustainable connection 5,147 - 0% 5,147 1,400 1,000
DLI 2.2 Sustainable CWS 8 2 25% 6 11 5
The mission had a meeting with leaders of DARD, DOH, DoET, CDC, and PMU, which was chaired by Mr. Nguyen
Van Son – Director of Lam Dong DARD. The list of participants is attached as an annex.
The mission discussed with the implementing agencies on the implementation progress, details as below:
2. Challenges/Difficulties:
Work plan 2021: The BCC and CB plans have not been approved because DoET has not yet developed and
supplemented activities of 2021 into the provincial BCC and CB plans.
Budget in 2021: The province has allocated the investment and non-business capital for the sectors. PMU has
developed the budget withdrawal dossier and sent it to CO.
New and sustainable CWS communes: The province has completed and exceeded the target of CWS communes, so
the province will focus on achieving the target of sustainable CWS communes, It is expected that the province is likely
to achieve the target of 11 sustainable CWS communes in 2021.
New FWSC: By the end of 2020, the province has only completed 20% of new FWSCs, according to the mission, it
would be very difficult for the province to achieve the annual target of connections, and at the same time the target of
connections for the whole period because: i) Construction progress of 9 water schemes is very slow. Of which 7
schemes transited from 2020 have just achieved 50-90%, 2 schemes have not yet started construction; ii) The estimated
total number of connections of 9 above schemes is about 10,000 ones that is very risky for the province to achieve the
target if this number can not be achieved.
Sustainable FWSC: By the end of 2020, the province has not had any sustainable FWSCs, thus it is likely to not
achieve the target of sustainable FWSCs for the whole period and risky to achieve the small number of sustainable
FWSCs because: i) The water schemes have not met the required percentage of operating connections; ii) The post-
investment support from the PMU to the schemes is not regular.
Issues related to environment, society, bidding and periodic reports: The province has sent environmental and
social impact report for the third quarter, but the report has not updated information; Additionally the tendering report
does not reflect details on whether it complies with the action plans outlined in the PAP.Thus, the province is requested
to revise the 3rd quarter reports and send to CO by 10 October.
3. Agreement
- DARD/PMU will review the investmenet progress of the water schemes vs the achieved/potential achived results
until the end of the Program, and adjust the plan/targets as needed.
- PMU committed to re-assign the officers participating in the program, including the focal points in charge of
reporting, post-investment support for the schemes, preparing the evidence dossiers for the schemes, capacity
building, etc.
- DARD report the PPC to urgentlt finanliaze the hand-over proceduress for improving the O&M activities of water
supply schemes constructed under the Program.
- PMU will finalize the 3rd quarterly reports properly, including environmental, social and procurement information
and send to CO by 30 October.
- The PMU will urgently work with DoET and DoH to speed up the development and approval of the BCC and CB
Plans 2021 to ensure that BCC communication activities can begin in October as scheduled.
- The PMU will urgently collect the eligibility information of water supply schemes registered for 2021 verification
and submit to NCERWASS to review.
20
Annex 7: SAV 2020 result verification and 2021 verification plan 2020 Verification:
The field verification of 2020 results started on March 15 and was interrupted in early May when several provinces (Bac
Can, Thai Nguyen, Hoa Binh, Phu Tho, Tuyen Quang, Son La, Ha Giang) had to cease field verification activities due to
new wave of Covid 19 pandemic. The field verification resumed in early June and completed by July 10, 2021 with great
efforts of the IVA/SAV and the provinces. The verification process for all provinces was completed successfully and the
verification report was issued by SAV on July 30, 2021. The table below indicate a substantial improvement in 2020
verification failure rate compared to 2019, particularly for DLI 1.2 and DLI 2.2.
DLIs 2019 2020
DLI
1.2 14.2% 5.2%
DLI
1.3 10.3% 10.0%
DLI
2.1 3.8% 3.3%
DLI
2.2 3.7% 0.8%
This seems that there is much improvement in sanitation aspect, while there is still more effort needed in water component
implementation with main reasons for failures for DLI 1.3 and DLI 2.1of having no water, using other sources of water,
connected before 1/1/2016, and non-household connections.
2021 verification plan:
Nr. Activities Implementation plan/Deadline
1 Agreed on the ToR for procurement of IVA for 2021-2022 program results verification 20/10-15/11/21
2 Procurement of IVA for 2021-2022 program results verification Nov – Dec 2021
3 The Comprehensive Results Reports (CRR) submitted by the provinces to CO/MARD 31/12/2021
4 MARD submits the Consolidated CRR to the World Bank for review 10/01/2022
5 Feedback from the WB on the Consolidated CRR 20/01/2022
6 Full list of water schemes registered for 2021 result verification (with no objection letter of WB) is submitted by NCERRWASS
26/01/2022
7 Tet holiday 28/1-6/02/2022
8 The Paper Audit starts 08/02/2022
9 Final official CRR submitted to SAV (including Full household lists of all CWS communes, full connection list of DLI 1.3 and DLI 2.1, and full list of institutions in CWS communes and DLI 2.2)
15/02/2022
10 Complete the paper audit in 21 provinces 08/03/2022
11 Preliminary results of the paper audit submitted to WB 15/03/2022
12 Report on Technical assessment of WSSs (if necessary) by NCERWASS 20/03/2022
13 Enumerators training 14-18/3/2022
14 Sample selection and field survey plans 18/3/2022
15 Approve sample selection and field survey plans 25/3/2022
16 Field verifiction starts 28/3/2022
17 Draft Paper Audit report submitted 15/4/2022
18 Paper Audit report approved 30/4/2022
19 Field verification completes 28/5/2022
20 First draft of the Verification Report submitted to WB by SAV 20/6/2022
21 Final draft of the verification report cleared by SAV and WB presented to MARD and provinces 10/7/2022
22 Feedback from MARD and provinces on the draft verification report 20/7/2022
23 Finalise and issue the final verification report 30/7/2022
21
Annex 8: Provinces requiring more attention/support for new and sustainable FWSCs
No
New FWSCs Sustainable FWSCs
Situation Solution Province Target
Results achieved to 2020
% achiev
. Target
Results achieved to 2020
% achiev
.
1 Lam Dong
12.500
2.525 20%
5.147
- 0%
The province is able to not achieve the target of new connections (DLI 1.3) because construction of 9 invested schemes is slow. The province is unable to achieve the target of sustainable FWSCs (DLI 2.1) and risky to achieve the very low percentage if there is no solutions for them.
The PPC should have drastic direction to PMU to speed up the construction progress. PMU needs to coordinate with the water factories to review the schemes’ operation according to the sustainability criteria; to strengthen IEC activities to increase the percentage of water users
2 Lang Son
13.000
4.791 37%
5.353
- 0%
The province is able to not achieve the target of sustainable FWSCs (DLI2.1) because of late water tariff collection by the schemes and the high water loss.
PCERWASS should continue to support, guide the O&M teams and CPCs to implement well the O&M tasks, ensuring the schemes satisfy the criteria of sustainability.
3 Bac Kan 10.400 10.615 102% 4.282 - 0%
The water schemes are CPC-manages small-scale ones; their collection of the water tariff is difficult because they had not collected it in the past while the water tariff is low.
The PPC should consider assigning the water schemes to PCERWASS for management. In the difficult areas, the province can apply the subsidy policies for the water tariff.
4 Binh Thuan 11.900 11.067 93% 4.900 - 0% In 2020, the province registered for sustainable verification of 3 schemes, but they are not eligible due to the insufficient dossiers.
The PPC should direct the PMU and PCERWASS to closely collaborate in preparing the dossiers so that the schemes can be eligible for sustainable verification in 2021.
5 Kon Tum
12,300
8,016 65%
5,065
492
10%
District PMUs are investment owners of many water schemes then asigning CPC/communities to O&M. The coordination between PCERWASS and the district PMUs and PCERWASS’s monitoring, supporting to water schemes O&M are challenging. High risk of unsustainable operation
Request PPC to direct the relevant agencies, in order to strengthen their coordination, direct CPCs to apply water tariff and support O&M team to improve water schemes sustainability; Strengthen IEC activities to increase the proportion of people using clean water
6 Dak Nong
11.700
4.945 42%
4.818
516
11%
The province is able to not achieve the target of new connections (DLI 1.3) because the actual number of connections is lower than the designed ones
The PPC should direct to enhance the collaboration between PCERWASS and the PMUs in order to speed up the construction progress and support the operating schemes after construction, ensuring their sustainable operation.
7 Cao Bang 12.600 8.735 69% 5.188 1.099 21%
The construction progress of the water schemes is slow, the province is able to not achieve the target of DLI1.3. The operating schemes are difficult to achieve the sustainability criteria because i) The low water tariff or have not collected the water tariff; ii) the construction quality of some schemes is not good
The PPC should: i) Direct CPCs to apply the water tariff and the subsidy policy for the areas with the high percentage of the poor; ii) Request PCERWASS to collaborate with the tenderer to review the difficult schemes to fix the challenges; iii) Request PCERWASS to enhance communication activities in terms of both quality and quantity.
22
Annex 9: Provinces requiring more attention/support for new and sustainable CWS communes
No
New CWS communes Sustainable CWS communes
Situation Solution Province Target
Results
achieved
to 2020
%
achiev. Target
Results
achieved
to 2020
%
achiev.
1 Hoa Binh 60 32 53% 30 11 37%
It is difficult for the province to achieve the
remaining targets of CWS and sustainable
CWS because the investment in the school
water and sanitation has been completed, and
most of the invested communes do not overlap
with the BCC-intervened ones.
CDC and DoET should collaborate to review the
status of water and sanitation of 28 CWS
communes and 13 sustainable CWS communes,
then to direct district DoET, schools, and health
stations to have solutions for the ineligible
criteria.
2 Gia lai 30 26 87% 15 2 13%
5 communes in Gia Lai need intervention to
improve sanitation facilities of the health
centers to meet CWS criteria. Gia Lai CDC
could not use the program fund to improve
these because they were planned to be
improved using other fund source. However
the CDC could not know when these
improvements are implemented and having
been still waiting since 2020.
CO/VIHEMA work with Gia Lai PPC/DoH
requesting the province to allow CDC to use the
program fund to improve these 5 commune health
centers sanitation facilities to meet program CWS
criteria so that the province can fulfill its
sanitation DLI target.
3 Lai Chau 25 17 68% 13 5 38%
The province have many communes to be
intervened to achieve the targets of CWS and
sustainable CWS communes in the remaining
years while these communes have the low
percentage of hygienic latrines, therefore, the
Health and Education sectors need to be
allocated the annual counterpart fund soon to
deploy the BCC activities.
The PPC should early allocate the counterpart
fund according to the sectors’ demand for 2-year
extension so that they can achieve the remaining
target.
Health and Education sectors need to work closely to
develop and implement the BCC plan, review the
operational status of water and sanitation schemes
in schools and health stations in the intervened
communes, thereby timely have solutions for the
ineligible criteria, ensuring to achieve the target. 4 Cao Bang 35 34 97% 18 3 17%
The remaining number of sustainable CWS
communes targeted for 2-year extension is very
high, thus the province is able to complete the
target by the end of 2022.
5 Bac Giang 50 49 98% 25 5 20%
This group of provinces has the low percentage
of achieved sustainable CWS communes and
targets to complete the high number in 2021 in
order to complete the DLI 2.2 in 2021.
CDC and DoET sectors should collaborate to
review the status of water and sanitation schemes
in schools and health stations in the communes
which are planned to implement the sustainable
CWS communes in 2021, thereby to develop the
solutions for the ineligible criteria, ensuring to
achieve the target.
6 Lam
Dong 16 18 113% 8 2 25%
7 Dak Lak 30 33 110% 15 4 27%
8 Lao Cai 35 35 100% 18 5 28%
23
Annex 10: List of people the Mission has met
Central Agencies
No. Name Position
MARD - WRD
1. Lương Văn Anh Deputy Director General 2. Lê Hùng Nam Head of Coordination Office
3. Hoàng Anh Tuấn Deputy Head of Coordination Office
4. Lê Khăc Lương Expert
MARD - Inspectorate
5. Đào Văn Thanh Vice Chief Inspector 6. Nguyễn Thanh Tâm Expert
MARD - NCERWASS
7. Nguyễn Thành Luân Deputy Director of NCERWASS
8. Nguyễn Sơn Tung Deputy Director of NCERWASS
9. Phan Thanh Sơn NCERWASS
10. Nguyễn Duy Dung NCERWASS
11. Vu Trung Kiên NCERWASS
12. Đào Ngoc Tú NCERWASS
13. Pham Thi Minh Thúy NCERWASS
14. Dương Tú Oanh NCERWASS
15. Nguyễn Thi Vân Anh NCERWASS
16. Hà Thi Thu Hiên NCERWASS
17. Pham Thi Nhung NCERWASS
MOH – VIHEMA
18. Đỗ Manh Cường Deputy Manager 19. Cao Tuyết Hanh Expert
20. Mr. Hồng Consultant
MOET
21. Nguyễn Nho Huy Deputy Director General
22. Nguyễn Thi Thu Hăng Expert
CEMA
23. Trân Văn Đoài Deputy Director General 24. Mr. Khuê Consultant
SAV
25. Nguyễn Bá Dung Director General, ICD, Director, SAV PMU 26. Hà Minh Tuấn Deputy Director, SAV PMU 27. Đỗ Thi Bình Manager, member of SAV PMU 28. Ms. Nguyễn Phương Nga Vice Manager, member of SAV PMU 29. Nguyễn Thu Hăng Accountant, member of SAV PMU 30. Nguyễn Ngoc Anh Member of SAV PMU
Provincial agencies
No. Name Position
Bac Kan province
1 Do Thi Minh Hoa Province Vice Chairwomen
2 Ha Kim Oanh DARD Vice Director
3 Be Ngoc Hung PCERWASS Director
4 Vi Duy Tuyen DOH Vice Director
5 Ma The Quyen DOET Director
24
6 Lang Thi Lanh CDC Staff
7 Do Thi Hong Nhung PCERWASS Staff
Dak Nong Province
1 Le Trong Yen Province Vice Chairman
2 Hoang Cong Tho DARD Vice Director
3 Tran Van Hung DOH Vice Director
4 Phan Thi Hieu DOF Vice Director
5 Nguyen Hoai Duong PCERWASS Director
6 Le Nhon DOET Staff
7 Tong Ngoc Lam CDC Staff
8 Le Van Tai PCERWASS Staff
9 Le Van Hoang District Vice Chairman - Dak Mil district
10 Dang Thai Son District PMU Director - Dak Mil district
11 Le Tien Lien District PMU Director – Tuy Duc district
12 Bui Van Huong District PMU Vice Director – Dak Glong district
13 Vi Thanh Quang District PMU Vice Director - Dak RLap district
14 Nguyen Anh Tu District Vice Chairman – Cu Jut district
15 Nguyen Van Hop District Vice Chairman – Dak Glong district
16 Tran Van Quang District PMU Director – Dak Song district
17 Phan Thanh Hoang District PMU Director – Krong No district
Cao Bang Province
1 Nguyen Cong Doanh DARD Vice Director
2 Hoang Dinh Da PCERWASS Director
3 Nong Chi Chuyen CDC Vice Director
4 Nguyen Van Hau DOET Staff
5 Nong Thu Le CDC Staff
6 Nguyen Van Bang PCERWASS Staff