RESPONSE TO ENGINEER'S COMMENT Bid Pack RFIT REF NO. : DATED: Contractor SPEC. REFERENCE : To ENGINEER'S COMMENTS CONTRACTOR'S RESPONSE REMARKS * … Work shall be consistent all over the project. Rest assured that the contractor is consistent and "NOT" violating any relevant building code and standards especially to this particular inspection which are the basis of acceptance or rejections of any work otherwise please provide the specific reference for the same and the contractor will to do the work accordingly. QATAR FOUNDATION EDUCATION CITY : QF OFFSITE WAREHOUSE AND DISTRIBUTION CENTRE : M/s/ CONSTRUCTION DEVELOPMENT COMPANY LLC : M/s LOUIS BERGER SAS 23-Jan-13 Section 19 2777-RFIT-06-00051 Rev. 00 * … You are kindly requested to save your research time and rectify the work on site,… Appreciate the kind request. Unfortunately, QCS requires the following standards as a mandatory requirement and plays an important role to do the work in line with the established local government requirements. * Inside research and vocabulary definition are uneeded… The same comment has no relevant specification. Please note the attached building code and standards are "NOT" research and the same is mandated reference of QCS. Kindly put on record that any attachments relevant to any inspection is a contractor's option in order to justify that the work was in lieu with specified. QCS was made in reference to the Western technical society. Page 1 of 1

Response to Engineer

  • Upload
    vhin84

  • View
    216

  • Download
    0

Embed Size (px)

DESCRIPTION

Response for the Enigneers OCS Comments

Citation preview

  • RESPONSE TO ENGINEER'S COMMENTBid Pack RFIT REF NO. : DATED:Contractor SPEC. REFERENCE :To

    ENGINEER'S COMMENTS CONTRACTOR'S RESPONSE REMARKS

    * Work shall be consistent all over the project. Rest assured that the contractor is consistent and "NOT" violating any relevant building code and standards especially to this particular inspection which are the basis of acceptance or rejections of any work otherwise please provide the specific reference for the same and the contractor will to do the work accordingly.

    QATAR FOUNDATION EDUCATION CITY

    : QF OFFSITE WAREHOUSE AND DISTRIBUTION CENTRE: M/s/ CONSTRUCTION DEVELOPMENT COMPANY LLC: M/s LOUIS BERGER SAS

    23-Jan-13Section 192777-RFIT-06-00051 Rev. 00

    * You are kindly requested to save your research time and rectify the work on site,

    Appreciate the kind request. Unfortunately, QCS requires the following standards as a mandatory requirement and plays an important role to do the work in line with the established local government requirements.

    * Inside research and vocabulary definition are uneeded The same comment has no relevant specification. Please note the attached building code and standards are "NOT" research and the same is mandated reference of QCS. Kindly put on record that any attachments relevant to any inspection is a contractor's option in order to justify that the work was in lieu with specified.

    QCS was made in reference to the Western technical society.