Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Page 1 of 214.1.B Response to CCC Slant Well CDP comment letter.docx
RESPONSE TO COMMENTS IN MAY 13, 2011 NOTICE OF INCOMPLETE PERMIT APPLICATION
FOR SLANT TEST WELL PROJECT
Comment 1: Page 2 – As you know, agreement to conduct the consolidated permit process requires
concurrence from the applicant, the local jurisdictions within which a CDP would be required, and the
Coastal Commission. The application included concurrence in the form of letters by officials within
the invoiced jurisdictions. Please provide evidence that the Local Coastal Programs, ordinances or
other authorities of these jurisdictions allow these officials to provide the necessary concurrence, or
alternatively, provide a resolution from the governing body of each jurisdiction providing the
necessary concurrence.
There are four Local Coastal Programs (LCPs) in which the Regional Desalination Project will be located;
of these, the City of Monterey’s LCP is a partially‐approved LCP and requires the Coastal Commission
approval of Coastal Development Permit (CDP) applications. Evidence that the LCPs have allowed these
officials to provide the necessary concurrence have been included in the overall CDP application
submitted on March 31, 2011 (Application No. E‐11‐009). Additional copies of those concurrences and
the supporting authorization were included in our May 31, 2011 response regarding the overall Regional
Desalination Project CDP application. Additionally, copies of City of Marina documents have been
included here as Attachment A. The City of Marina is the LCP in which the Slant Test Well is located.
Comment 2: Page 2 –The Commission’s consolidated permit process also requires that public
participation not be substantially impaired due to the consolidation. As part of our consideration of
the requested consolidated review, please identify all measures that have or will be taken to
maximize public participation within each affected jurisdiction, including all required public noticing
requirements and public hearings for discretional approvals, solicitation of comments, etc.
The following summarizes public participation activities that have been conducted to date for the overall
Monterey Bay Regional Desalination Project (which includes the Test Well Program) and those
anticipated to be implemented in the future.
Public Participation in Coastal Water Project EIR Process
Pursuant to the California Environmental Quality Act (CEQA), Public Resources Code Sections 21000 et
seq. and the CEQA Guidelines, California Code Regulations, Title 14, Sections 15000 et seq. (collectively
“CEQA”), the California Public Utilities Commission (CPUC) prepared an Environmental Impact Report
(EIR) that analyzes the environmental effects of Project. For the purposes of CEQA, the CPUC is the lead
agency for the EIR, and Monterey County Water Resources Agency (MCWRA) and Marina Coast Water
District (MCWD) are responsible agencies. Pursuant to CEQA Guidelines Section 15096, MCWRA and
MCWD responded to consultation from the CPUC, attended meetings to discuss the scope and content
of the EIR, and commented on the Draft EIR.
Page 2 of 214.1.B Response to CCC Slant Well CDP comment letter.docx
A Notice of Preparation (NOP) was prepared by the CPUC pursuant to CEQA to notify interested parties
that it was preparing an EIR to evaluate potential environmental impacts of the Coastal Water Project
(CWP). (The Regional Desalination Project was an alternative to the CWP.) On September 28, 2006, the
NOP was mailed to approximately 230 interested parties, including local, state, and federal agencies;
news publication; and other groups or individuals who had previously expressed interest in the project.
Comments were requested by November 9, 2006. A Notice of Availability (NOA) was also prepared by
the CPUC, (in English, Spanish, and Mandarin) in order to notify potentially interested members of the
public about the availability of the NOP. On October 4, 2006, approximately 38,000 copies of the NOA
were distributed by mail to all California American Water Company (CAW) and Marina Coast Water
District (MCWD) ratepayers, and to owners of properties adjacent to some of the proposed facilities.
The 30‐day project scoping period, which began with the distribution of the NOP and NOA, remained
open through November 9, 2006. During the scoping period, the CPUC held a series of four scoping
meetings in Monterey County including the cities of Castroville, Seaside and Monterey. The meetings
were held as follows:
October 24, 2006, 7:00 P.M. at North Monterey County High School (13990 Castroville Boulevard, in Castroville)
October 25, 2006, 1:30 P.M. at Hyatt Monterey (1 Old Golf Course Road, in Monterey)
October 25, 2006, 7:00 P.M. at Hyatt Monterey (1 Old Golf Course Road, in Monterey)
October 26, 2006, 1:30 P.M. at Embassy Suites (1441 Canyon Del Rey Boulevard, in Seaside)
The CPUC placed display ads for the scoping meetings in four newspapers, in three languages, on several
different days, as follows:
The Carmel Pinecone, October 20, 2006
El Sol, October 17, 2006
El Sol, October 21, 2006
El Sol, October 24, 2006
The Salinas Californian, October 19, 2006
The Salinas Californian, October 23, 2006
The Monterey Herald, October 19, 2006
The Monterey Herald, October 22, 2006
At each scoping meeting, CPUC staff and consultants gave presentations on CAW’s application, the
proposed action, and potential alternatives. Following these presentations, meeting participants were
invited to visit one or more of five different stations around the room. Each station involved a different
aspect of the project. Participant questions and comments were recorded on flip charts, and comment
cards were also available for participants to fill out at the meeting or to send in at a later date.
Page 3 of 214.1.B Response to CCC Slant Well CDP comment letter.docx
On December 22, 2006, the CPUC issued a scoping report, summarizing issues and concerns identified
by the public and various agencies during the scoping project. The scoping report was available for
review on the Internet and was mailed to agencies and individuals who requested copies
Work Group Meetings
Starting in January 2007, the Division of Ratepayer Advocates (DRA) of the CPUC worked in conjunction
with the University of California Santa Cruz, Center for Integrated Water Research (CIWR) to evaluate
whether there was an alternative regional approach to the CWP that would be less expensive for
ratepayers and that could be presented as an alternative to the CWP. The DRA and the CIWR viewed
public participation as critical to the development of an implementable water supply program and
facilitated a series of public meetings which led to the establishment of the Regional Plan Technical
Work Group, Public Information and Involvement Work Group, and Regional Plenary Oversight Group
(REPOG). The meetings for each group were attended by a wide range of agencies, general public,
interest groups, and other parties and provided a forum for identifying project components, confirming
criteria, evaluating alternatives, assembling portfolios, and establishing a preferred community‐based
regional water supply alternative that addresses the regulatory replacement needs of SWRCB Order 95‐
10 and the Seaside Basin Adjudication.
Many meetings were held in 2007, including a series of three meetings of the Monterey Regional Plan
Work Group (Work Group) facilitated by DRA/UCSC CIWR, four Regional Plenary Oversight Group
(REPOG) meetings, and two meetings of the managers of the local water and wastewater agencies1.
Meeting dates were as follows:
Work Group Meeting 1 July 18, 2007
Work Group Meeting 2 August 22, 2007
REPOG Meeting August 29, 2007
Work Group Meeting 3 September 19, 2007
REPOG Meeting September 26, 2007
Water Managers Meeting October 24, 2007
REPOG Meeting October 31, 2007
Water Managers Meeting December 10, 2007
REPOG Meeting December 18, 2007
The meetings provided a forum for identifying project components, confirming criteria, evaluating
alternatives, assembling water project portfolios, and establishing a preferred local regional water
supply alternative that addresses both the “replacement needs” (Order 95‐10 and Seaside Adjudication)
and the “regional needs.” Presentations and materials are available at the DRA project website2.
1 Castroville Water District (Eric Tynan), Marina Coast Water District (Jim Heitzman), Monterey County Water Resources Agency (Curtis Weeks), Monterey Peninsula Water Management District (Dave Berger and Andy Bell), Monterey Regional Water Pollution Control Agency (Keith Israel) 2 http://ciwr.ucsc.edu/monterey/supply/index.html
Page 4 of 214.1.B Response to CCC Slant Well CDP comment letter.docx
Prior to Work Group Meeting 1, project descriptions were gathered from existing documents and from
discussions with community and agency leaders to draft a Project Information table describing each of
the projects and relevant information. A condensed set of project and program evaluation criteria was
established from the Draft Plan of Study prepared by the Work Group on May 25, 20073 and from the
Monterey Peninsula Integrated Regional Water Management Plan (IRWMP).
Draft and Final CWP EIR
As previously mentioned, one result of the Work Group and REPOG meetings was the formation of an
alternative to CAW’s CWP. Presented as the Monterey Regional Water Supply Program (or Regional
Program), the resulting alternative consisted of a portfolio of projects that included desalination,
recycled water use, aquifer storage and recovery, and conservation. The Monterey Bay Regional
Desalination Project is one of the components of the Phase 1 Regional Program evaluated in the CWP
EIR. The Draft EIR was circulated for public review and comment in accordance with CEQA. The Draft EIR
was released on January 30, 2009 with a 75‐day review period that ended on April 1, 2009. During the
review period, the CPUC conducted four public participation meetings: on March 2, 2009 in Seaside (in
both the afternoon and evening), on March 3, 2009 in Castroville, and on March 4, 2009 in Carmel.
Following circulation of the Draft EIR and incorporation of public comments and responses to
comments, the CPUC published the Final EIR on October 30, 2009. The Final EIR was then reviewed by a
CPUC administrative law judge, who submitted a proposed decision to the CPUC concerning certification
of the Final EIR. On December 17, 2009, the CPUC issued Decision D.09‐12‐108, certifying the Final EIR.
Project Website
A project website was launched in 2008 that served to help inform the public regarding the REPOG
process. That website was located on the Internet at www.waterformontereycounty.org. Recently, that
website has been converted into a more project‐specific website that is located on the Internet at
http://mryrdp.org/. The revised website was initiated on May 10, 2011 and currently contains a project
description, project history, project library, cost and schedule information, information on the
Community Involvement Forum (discussed further below) and a means for contacting someone about
the project. Documents relating to the Regional Desalination Project are currently being uploaded to
the project website. Documents currently available include the Water Purchase Agreement, Settlement
Agreement, Coastal Development Permit (CDP) Application and the Coastal Commission response to the
CDP Application. Additional documents will be uploaded as they are completed and become available.
Community Involvement Forum
In addition to the scoping, Work Group and REPOG meetings, as well as the public participation
meetings, held prior to and as part of the EIR review process, a Community Involvement Forum (CIF) has
3 http://ciwr.ucsc.edu/monterey/meetings/DraftPlanofStudyv2.pdf
Page 5 of 214.1.B Response to CCC Slant Well CDP comment letter.docx
been established to help the public learn about the design and construction of the Regional Desalination
Project. In these forums, the public is invited to voice their concerns and learn the various aspects of the
Regional Project plan. The Regional Desalination Project CIF meets quarterly on the Monterey
Peninsula, is open to everyone, and provides an opportunity to get involved and learn more about
regional supply issues. The first CIF meeting was held on March 31, 2011 in Pacific Grove. Details of
that meeting, including meeting agenda, presentation and summary, are available at the Project
website4. A second meeting is scheduled for June 15, 2011 in Seaside.
Public Information Specialist
On May 2, 2011, a Request for Statement of Qualifications was issued for the services of a Public
Information Specialist to provide public information services for the Regional Desalination Project.
Statement of Qualifications (SOQ) were submitted on May 23, 2011. The Regional Desalination Project
team is presently reviewing those qualifications, and it is expected a public information specialist will be
retained with Notice to Proceed in late June of 2011.
The objectives of the public information services consist of the following: 1) providing timely and
accurate information about the Project to the public and various stakeholders, 2) coordinating outreach
communications across the multiple Owners’ component projects to provide consistent and responsive
channels for communication with the public, and 3) providing coordination/support materials to a
Community Involvement Forum(CIF) Facilitator who, under a separate subconsultant agreement, is
leading the CIF described above.
The Public Information Consultant will be expected to provide the following:
Development of a Public Communications Plan to guide communications about the project with
the public and stakeholder groups, including identification of key stakeholders, community
education/outreach efforts, and coordination with other outreach activities by the Owners, to
effectively communicate Project goals and status, and address needs of stakeholder groups.
Development and dissemination of general informational materials about the project such as
newsletters, information packets, news releases
Development of technical information for outreach or response to media
Presentations or other support for public meetings
Updating and maintaining the project website.
4 http://www.waterformontereycounty.org/community_forum.php
Page 6 of 214.1.B Response to CCC Slant Well CDP comment letter.docx
Comment 3: Page 2 – We would also appreciate identification of any commitment by the involved
jurisdictions to conduct, if deemed necessary by Commission staff, a public hearing to receive
comments and information about the proposed project.
As noted in the previous response, the Project Partners are committed to providing timely public
information and opportunities for public comment. To that end, and in coordination with the City of
Marina, the Partners agree to hold a public hearing on behalf of the Commission on the Monterey Bay
Regional Desalination Project Coastal Development Permit application and the Test Well Program‐
specific Coastal Development Permit applications, if so requested by the Coastal Commission.
Comment 4: Page 2 – Please provide copies of all those permits already approved and a list of all other
discretionary permit and approvals needed to construct and operate elements of the facility located
within the coastal zone.
Table 1, presented below, shows all permits and approvals required for proposed construction and
operation of the Slant Test Well included in the Monterey Bay Regional Desalination Project – Test Well
Program. The application for the State Lands Commission (SLC) lease is presently being prepared; we
are actively coordinating with SLC to obtain the required lease. The remaining permits to be obtained
are ministerial in nature, and will be submitted following receipt of the Coastal Development Permit.
Table 1: Permits Required for Construction and Operation of Slant Test Well Program
Agency or Department Permit or Approval
State Water Resources Control Board, Central Coast Regional Water Quality Control Board
General Construction Activity Storm Water Permit (WQO 99‐08‐DWQ)
General Permit ‐ Waste Discharge Requirements. (Water Code 13000 et seq.) for low threat discharges to land
California Coastal Commission Coastal Development Permit (Public Resources Code 30000 et seq.)
California State Lands Commission Lease for portion of Slant Test Well west of Mean High Tide Line
Monterey County Health Department, Environmental Health Division
Well Construction Permit (MCC, Title 15 Chapter 15.08, Water Wells)
Comment 5: Page 2 – Please also provide completed Local Agency Review Forms (Appendix B of the
CDP Application), including the status of any CEQA analysis along with any CEQA documentation, form
each of the local jurisdictions within which the project‐related development would be located.
A completed Local Agency Review Form for the City of Marina, the LCP in which the Slant Test Well is
located, is included in Attachment B of this letter. The corresponding CEQA documentation was included
with the overall CDP application submitted on March 31, 2011 and the Test Well CDP application
submitted on April 11, 2011.
Page 7 of 214.1.B Response to CCC Slant Well CDP comment letter.docx
Comment 6: Page 2 – The proposed wells would intersect an aquifer in an overdrafted groundwater
basin. Please describe whether MCWRA or other entity will need to acquire water rights to use water
from this source. If water rights are needed, please provide evidence demonstrating that MCWRA has
obtained such rights or that it has the ability to acquire such rights (e.g., through eminent domain or
other means). If water rights are needed but cannot be obtained, please describe how absence of
those rights would affect this proposed project – e.g. changes to the proposed well locations, designs,
or operations, whether there are other feasible means to obtain source water, etc.
The response to this comment was provided in our May 31, 2011 submittal on the overall Regional
Desalination Project CDP application. A copy of this response is included as Attachment C to this letter.
Comment 7: Page 2 – Please also demonstrate how the proposed water withdrawals are consistent
with agreements developed to manage the nearby affected surface water and groundwater sources,
including the Seaside Basin Adjudication, the Salinas Basin Management Plan, and any other relevant
provisions of surface water or groundwater management agreements.
The Slant Test Well is expected to extract approximately 95% seawater and only 5% seawater‐intruded
groundwater and will only be operated periodically over a three‐to‐six month period. Therefore, the
Slant Test Well will have no appreciable or long‐term impact on the groundwater basin.
The following discussion pertains to the overall Regional Desalination Project, of which the Slant Test
Well would be one component:
The Seaside Groundwater Basin is distinct from the Salinas Valley Groundwater Basin. The Seaside
Groundwater Basin is located approximately five miles south from the proposed Brackish Source Water
Wells. All of the analyses conducted to date indicate that there will be no impact on groundwater
conditions within the Seaside Basin. Groundwater modeling performed through the North Marina
Groundwater Model (NMGM) shows groundwater levels are nearly identical between the baseline
conditions and proposed project conditions at the southwestern boundary of the model (See DEIR
Appendix E, Figures 12 and 17). The southwestern boundary of the NMGM is located just to the
northeast of Light Fighter Drive. The boundary between the Salinas Valley Groundwater Basin aquifer
system and the Seaside Groundwater Basin is located further to the southwest, with a northeastern
boundary near the Bayonet Golf Course. Since the analyses show minimal change in groundwater
elevations near the southeastern boundary of the NMGM area, and there is a physical boundary
between the Salinas and Seaside Groundwater Basins, there is no evidence there will be any impacts to
the Seaside Basin.
The purpose of the Salinas River Basin Management Plan is to eliminate the seawater intrusion problem
which affects the Salinas River Basin and to provide adequate water supply to meet anticipated water
needs within the Basin through the year 2030.
In the Salinas River Basin, groundwater management activities are led by the Monterey County Water
Resources Agency. MCWRA has a mission and purpose of managing, protecting, and enhancing the
Page 8 of 214.1.B Response to CCC Slant Well CDP comment letter.docx
quantity and quality of water and providing specified flood control services for present and future
generations of Monterey County. MCWRA has implemented a number of water resource management
strategies and projects that address the overall health of the Salinas Valley Groundwater Basin, including
water balance, water quality, and seawater intrusion. Initially, MCWRA, through its predecessor agency,
constructed and has since operated Nacimiento and San Antonio Dams and Reservoirs. These two
projects have allowed MCWRA to conserve winter runoff for release during the summer irrigation
season, thereby increasing groundwater recharge via the Salinas River. Through this management
strategy, groundwater levels have been raised above the levels they would have been without the
reservoir operations.
Additionally, the Castroville Seawater Intrusion Project (CSIP) was implemented in 1998 to reduce
groundwater pumping in the greater Castroville area by delivering recycled water for agriculture.
Through implementation of CSIP, MCWRA was able to address approximately 40 to 45% of the
remaining seawater intrusion problem caused by pumping near the coastal zone. The Salinas Valley
Water Project (SVWP) was implemented in 2010 to address the remaining 55 to 60% of the seawater
intrusion problem. Collectively, these two projects, along with other management strategies, have
provided MCWRA a basis to manage the Salinas Valley Groundwater Basin to stop seawater intrusion
and to provide a hydrologically‐balanced basin
The Regional Desalination Project (of which the Test Well Program is part) builds upon the success and is
consistent with the Salinas Basin Management Plan. The Regional Desalination Project will extract a
combination of ocean water and seawater intruded brackish water through the proposed Brackish
Ground Water Wells. The siting and performance of the Brackish Groundwater Wells has been
thoroughly analyzed through the use of existing and enhanced groundwater models to establish their
consistency with the Salinas River Basin Management Plan. The Regional Desalination Project enhances
water quantity through the utilization of a combination of ocean water and groundwater that is too
saline for other uses and enhances water quality through reduction of salinity concentrations in the
intruded aquifer.
Finally, the Regional Desalination Project includes an aquifer storage and recovery component that will
allow for storage of seasonal (wintertime) Carmel River water and desalinated water in the Seaside
Groundwater Basin. As part of the Seaside Basin adjudication, a safe yield was calculated for the basin.
However, as the Regional Desalination Project will not extract groundwater from the Seaside Basin, the
project is aligned with that adjudication agreement. The Seaside Basin adjudication decision also
determined that augmenting the total yield of the basin through artificial groundwater recharge, storage
and recovery served the public interest. To that end, the adjudication decision allocated storage in the
basin to basin users using a formula that involved multiplying each producer’s storage allocation
percentage by the total useable storage space, less space reserved by the Wastermaster. The Regional
Desalination Project will facilitate CAW’s use of this storage space, thereby making the project
consistent with the terms of the Seaside Basin Adjudication and providing direct benefits to the basin
through supplemental groundwater recharge and maintenance of groundwater elevations.
Page 9 of 214.1.B Response to CCC Slant Well CDP comment letter.docx
Comment 8: Page 2 – Please also identify/describe any expected effects of the proposed withdrawals
on coastal resources, including those related to agricultural activities and local and regional efforts to
reduce seawater intrusion in this area.
The Slant Test Well is one of two test wells and eight clusters of monitoring wells proposed for
installation as part of the Regional Desalination Project. The Slant Test Well and adjacent monitoring
wells will be constructed and operated to gain valuable information on the hydrologic and hydraulic
characteristics of the basin as well as additional intake water quality data for use in design of the reverse
osmosis treatment system. Pumping from the Slant Test Well will be intermittent and temporary in
nature will not have any long‐term or significant impacts on the groundwater basin.
The overall proposed Regional Desalination Project has an expected benefit to agricultural activities and
to local and regional efforts to reduce seawater intrusion, and no expected effect on environmental
groundwater users. The proposed withdrawals will reduce groundwater levels in (extract from) the 180‐
Foot Aquifer in the immediate vicinity of the wells. This decline in groundwater levels is a key
component of the overall proposed project to protect against seawater intrusion. The reduced
groundwater levels immediately adjacent to the wells will create a trough of lower groundwater levels
near the coast. As groundwater flows from areas of high groundwater to areas of low groundwater
levels (at the well sites), saline groundwater with a source from Monterey Bay will flow toward the
trough and be captured by the proposed wells. The lowered groundwater levels in the immediate
vicinity of the extraction wells eliminates the potential for seawater to be drawn further inland towards
municipal and agricultural supply wells. Thus, the wells create a barrier to seawater intrusion, which has
impacted the basin since the early to mid‐20th century.
Under current conditions, and without the proposed project, the combined operations of Nacimiento
and San Antonio Reservoirs and operations of CSIP and SVWP have resulted in a reversal of the
groundwater gradient, aiding in returning the groundwater flow from the Salinas Valley Groundwater
Basin towards Monterey Bay, which was the historical direction of flow. Until implementation of the two
Reservoirs, CSIP, and later SVWP, seawater intrusion was drawn inland toward agricultural and
municipal production wells, with brackish groundwater reaching nearly as far as the City of Salinas.
Through the operation of the proposed project wells, the project will extract groundwater flows that
have been reversed as a result of CSIP and SVWP. This will result in the gradual lowering of salinity in
the impacted aquifer over a period of decades as low salinity groundwater recharge in the inland
Forebay Area flushes the aquifer, eventually returning portions of the impacted aquifer back to
conditions suitable for beneficial uses by agriculture or others.
While the proposed project wells lower groundwater levels when creating a trough, this condition will
not impact coastal resources as there are no production wells in the area near the wells due to high
salinity in the groundwater; environmental groundwater users, if any, would be sensitive to changes in
the overlying “A” Aquifer, which is above the Salinas Valley Aquitard and is not pumped by the deeper
proposed project wells.
Page 10 of 214.1.B Response to CCC Slant Well CDP comment letter.docx
Comment 9: Page 3 – Please clarify whether the information provided with the April 14, 2011 CDP
application submittal is consistent with that contained in the MCWRWA’s April 7, 2011 Coastal Water
Project EIR Addendum.
Included in the April 14, 2011 Test Well CDP application (CDP Application No. 3‐11‐036) was the
Monterey Bay Regional Desalination Project Addendum to the Coastal Water Project – Environmental
Impact Report for the Test Well Program, prepared by MCWRA and dated April 7, 2011. This Addendum
was slightly different than the one included with the CDP application for the overall Regional
Desalination Project (CDP Application No. E‐11‐009) only in that it incorporates information from an
additional biological survey of the MCWD Reservation Road site, conducted in April of 2011. Specifically,
the April 2011 survey identified Monterey spineflower at the MCWD site (the site of the slant test well),
and therefore the corresponding section in Appendix 3 of the Addendum was revised to reflect this
information. The Test Well CDP application submittal is, however, consistent with what is contained in
the Test Well Program Addendum.
Comment 10: Page 3 – The application states that the project expects to determine optimal pumping
rates and confirm long‐term sustainable rates for proposed permanent wells that may be developed
to provide source water for the Regional Desal Project. The full‐scale project assumes development of
up to six wells, which could include a slant well with an expected yield of between 2,600 and 3,000
gallons per minute (gpm). Please identify the basis for this expected yield and provide documentation
used to develop this expected yield.
In order to produce 10,500 AF of potable water supply per year, assuming that the treatment facility will
operate at a recovery rate of 44%, 22.7 million gallons per day (mgd) of raw water supply is required. To
achieve this, the project assumed (as described in the CWP EIR) that six wells pumping at up to 2,800
gallons per minute (gpm) would be required (Table 5‐3A on page 5‐22 of the CWP FEIR). Further, the
FEIR also states that the project would be operated, such that on an average annual basis, the project
would produce and deliver the 10,500 AFY of water. While six wells pumping continuously at 2,800 gpm
produces more than the stated 22.7 mgd, the assumed pumping rate of 2,800 gpm was selected to
provide some flexibility in the operational rates of the wells once installed. This flexibility is required
because the actual pumping rate of the wells may vary from the 2,800 gpm assumed based on actual
well capacity (as determined following well installation and development) and because the recovery rate
will be based in part on the salinity concentrations produced at the well sites. Once in operation, the
Brackish Source Water Wells will be operated to meet a flow set point at the desalination plant, and the
volume pumped will be controlled using a combination of Variable Frequency Drive (VFD) pumping
systems and cycling wells on and off.
The assumption of the wells operating at 3,000 gpm is required to meet regulatory requirements for
stressing the aquifer during well testing to determine the zone of influence. So while this production
rate was assumed for testing purposes, the Brackish Source Water Wells will not be operated at this
higher pumping rate.
Page 11 of 214.1.B Response to CCC Slant Well CDP comment letter.docx
Our May 31, 2011 response to the Commission’s letter dated April 29, 2011 regarding the CDP
application for the overall Regional Desalination Project included a detailed discussion of the numerical
modeling that was conducted to site the proposed Brackish Source Water Wells (and therefore the
locations of the proposed test wells) and to determine the estimated rate at which the wells would be
pumped. Based on the large amount of hydrogeologic data that is available for the Salinas Valley
Groundwater Basin and the numerical modeling conducted to date, the Partners believe that the model
results provide a high degree of certainty as to the selected/final well locations, the rates at which the
wells would likely be operated, and the usability of those wells as intended for this project.
Comment 11: Page 3 – The application states the water produced during well construction would be
temporarily stored to reduce turbidity and then discharged into an existing injection well. It also
states that the applicant has not yet identified a method to dispose of water that would be extracted
from the well during a long‐term (i.e. 3‐6 month) pump test. Please identify methods considered for
discharge, the status of obtaining the necessary approvals to dispose of pump test water, and provide
the selected or preferred discharge methods, along with any impacts to coastal resources associated
with that method.
At this time, a long‐term pump test is not planned for the Slant Test Well. Necessary data and
information will be gathered from the Slant Test Well during and following well development and from a
short‐term (approximately 24‐hour) aquifer pumping test. As stated in the Slant Test Well CDP
application, water developed during the construction and testing activities will be temporarily stored to
reduce turbidity and then will be discharged to land via an existing on‐site injection well.
Multiple alternatives were considered for on‐ and off‐site water disposal prior to selection of the
existing injection well for water disposal. These other alternatives included:
Ocean disposal from the bluff
Ocean disposal with a water monitor (water cannon)
Ocean disposal via a beach‐based diffuser
Disposal into the local sanitary sewer
Onsite percolation through the existing onsite clarifiers
Onsite percolation through percolation ponds
Offsite disposal via offsite transport/trucking
Offsite disposal into the MRWPCA Outfall via a temporary pipeline along the shoulder of
Highway 1
Offsite disposal into the MRWPCA Outfall via a temporary pipeline located to the east of
Highway 1
Offsite disposal into the MRWPCA Outfall via a temporary pipeline along to the west of Highway
1 (along Dune Road and the Armstrong Ranch property)
Piping from the MCWD Reservation Road site through existing, un‐used piping to a location east
of Del Monte Boulevard where the test water would be either discharged into the existing sewer
system for transport to the Monterey Regional Water Pollution Control (MRWPCA) Agency plant
Page 12 of 214.1.B Response to CCC Slant Well CDP comment letter.docx
or discharged via a temporary pipeline installed in existing disturbed rights‐of‐ways for
connection to the MRWPCA outfall.
Each of these options was considered in discussions with the Coastal Commission and Central Coast
Regional Water Quality Control Board (RWQCB) staff, and the selected alternatives (use of the onsite
injection well) was determined to be the most benign disposal method. Further, per discussions with
the Central Coast RWQCB, disposal via the existing on‐site injection well can be achieved via compliance
with the State’s existing General Permit for low threat discharges to land (Order No. 2003‐0003). This
compliance entails preparation and submittal of a Notice of Intent to comply with the General Permit
(which was included in the Slant Test Well CDP Application), and followed by preparation and submittal
of a report following completion of testing. Additionally, recommendation of this permit by the Central
Coast RWQCB (and compliance thereunder) demonstrates that the anticipated impacts from this
discharge are not significant. Should it become necessary to address long‐term operation of the Slant
Test Well, we will return to the Coastal Commission to address any additional permitting issues that
would accompany that operational and test well water disposal scenario.
Comment 12: Page 3 –It appears that portions of the proposed project would be located near areas of
environmentally sensitive habitat, including coastal dune habitat, and the application identifies
several sensitive species that could be present near the project site. Please identify any proposed
locations for project components – e.g., monitoring wells, test equipment, etc. – that have been
identified as ESHA in LCPs or other documents.
Attachment D to this letter identifies where Slant Test Well components will be located relative to
identified environmental sensitive habitat areas (ESHAs) and other sensitive species. The proposed
location of the Slant Test Well has been selected to avoid identified environmentally sensitive habitat
areas.
Comment 13: Page 3 – Please also identify all feasible alternatives to locating the proposed project
developments within the ESHA (e.g. locating within existing disturbed areas instead of non‐developed
areas) and identify any alternative construction and operations methods that would avoid impacts to
ESHA (e.g. directional drilling instead of trenching).
The Regional Desalination Project components have been sited to avoid ESHA and other sensitive
habitats whenever possible, siting facilities in disturbed areas or in or adjacent to paved roadways. As
can be seen in Figure 1, the construction areas required for the Slant Test Well have been relocated at
the MCWD Reservation Road site to avoid sensitive species and habitats. The areas containing sensitive
species, as shown in Figure 1, will be cordoned off to clearly establish those areas as off‐limits to
construction. The environmentally sensitive habitat areas will be clearly designated (and fenced) in the
field to protect these species and critical habitat areas from disturbance during construction activities.
Further, a Restoration Plan has been prepared for the Regional Desalination Project as a whole, defining
an approach for mitigation to reduce the impacts to specific biological resources, as well as various
mitigation measures and recovery plans identified in the EIR (p. 6.4‐8). A copy of this Restoration Plan is
Page 13 of 214.1.B Response to CCC Slant Well CDP comment letter.docx
included as Attachment E to this letter. The Restoration Plan supplements the information provided in
the CWP FEIR and provides for the mitigation of potential impacts to the following biological resources:
Monterey spineflower (Chorizanthe pungens var. pungens) – FE/1B5,
Hooker’s manzanita (Arctostaphylos hookeri) – 1B,
Monterey ceanothus (Ceanothus cuneatus var. rigidus) – 4
Coast wallflower (Erysimum ammophilum) – 1B
Sandmat manzanita (Arctostaphylos pumila) – 1B
Kellogg’s horkelia (Horkelia cuneata ssp. sericea) – 1B
Smith’s blue butterfly (Euphilotes enoptes smithi) habitat (buckwheat) – FE
Mitigation goals and methods were developed for both temporary and permanent impacts with an
overall mitigation approach emphasizing onsite mitigation whenever possible. Offsite mitigation is
considered only when necessary as an alternative to, or in conjunction with, onsite restoration. Success
criteria, as defined in the Restoration Plan, are presented for both the temporary and permanent impact
areas and varies depending on the mitigation approach taken.
In addition to the Restoration Plan, the CWP FEIR contains mitigation strategies for each potentially
significant impact to ESHA in the project corridor, including various methods to avoid construction
impacts and implementing water quality improvement measures for coastal discharge.
5 FE: species listed as Federally Endangered under the Endangered Species Act; 1B: California Native Plant Society (CNPS) List 1B, Rare, Threatened or Endangered plants in California and elsewhere; 4: CNPS List 4 – plants of limited distribution
Page 14 of 21 4.1.B Response to CCC Slant Well CDP comment letter.docx
Figure 1: Location of Construction Area at MCWD Reservation Road Site
Page 15 of 21 4.1.B Response to CCC Slant Well CDP comment letter.docx
Comment 14: Page 3 – The application states that the expected project life is up to 50 years and cites
two separate coastal erosion rates for the proposed project location – a 2.7 foot per year rate
identified by the USGS and a 5.5 foot per year rate identified by the Coastal Regional Sediment
Management Project (CRSMP). However, it uses the lesser of the two rates as the basis for its project
siting. Please provide an analysis of the proposed project location based on the CRSMP findings,
including anticipated rates of sea level rise and including a safety factor of at least 1.5.
The Slant Test Well component of the Regional Desalination Project is expected to have a project life of
up to 30 years. Over the 30‐year life of the well, the estimated setback distance is 227 feet from the
current bluff edge, resulting in a safety factor of 2.2. This is explained in more detail in the following
paragraphs.
The California Coastal Commission (CCC) guidelines (Establishing Development Setbacks from Coastal
Bluffs, California Coastal Commission Memorandum W11.5, January 16, 2003) call for an estimation of
bluff edge position projected into the future a minimum of 50 years (CCC‐W11.5, Table 2, Point 1). The
CCC guidelines require that the 50‐year projected bluff edge is determined by a long‐term erosion rate,
based on data with a period of record exceeding 50 years (CCC‐W11.5, Table 2, Point 5). This includes
quiet erosional periods (e.g. 1950’s to 1960’s) as well as more erosive periods (e.g., the 1982‐1983 and
1997‐1998 El Nino events). The long‐term erosion rate used in our analysis to determine the well
setback from the bluff edge was calculated in the United States Geological Survey (USGS) Open File
Report‐1251 (2006) and is based on data from 1910 to 2002, satisfying CCC guidelines. A Technical
Memorandum (TM) entitled Summary of Historical Erosion Rates in the Vicinity of the Marina Coast
Water District Marina State Beach (MCWRA, 2010) was developed to determine an adequate set‐back
distance from the existing coastal bluff for a proposed Slant Test Well entry point which will be
constructed in the vicinity of the MCWD Office Site, located near Marina State Beach, Marina, California.
The location of the proposed test well represents the southern‐most location of the proposed well field,
and is one of the project locations closest to the shoreline. A copy of this TM is included as Attachment
F.
As part of the TM, a literature review of existing published erosion rates in the Project area was
conducted. Results of the review are summarized in Table 1 below. A coastal erosion study by the USGS
and published in the Journal of Coastal Research is entitled Rates and Trends of Coastal Change in
California and the Regional Behavior of the Beach and Cliff System (Hapke, et al, 2009). This study
calculated an average long‐term shoreline erosion rate for Monterey Bay of 1.97 ft/yr using Light
Detection and Ranging (LIDAR) remotely sensed data. The 2009 publication was based on the USGS
Open File Report‐2006‐ 1219 (Hapke, et al, 2006) where the average long‐term shoreline erosion rate of
1.97 ft/yr based on remotely‐sensed LIDAR data was first reported. More detailed studies have shown
that the long‐term shoreline erosion rate varies along the coast of Monterey Bay, from an average of
1.97 ft/yr to a maximum of 5.9 ft/yr (see Table 2). However, neither the average nor the maximum long‐
term shoreline erosion rates accurately represents the potential erosion at the proposed Slant Test Well
site. In order to estimate long‐term erosion at the site and in the immediate area, long‐term erosion
transects (vectors) from the USGS Open File Report (OFR) 2006‐ 1251, entitled USGS National
Page 16 of 21 4.1.B Response to CCC Slant Well CDP comment letter.docx
Assessment of Shoreline Change: A GIS Compilation of Vector Shorelines and Associated Shoreline
Change Data for the Sandy Shorelines of the California Coast, were used. These long‐term coastal
erosion rate transects are shown on Figure 2.
Table 2: Published Bluff/Cliff Erosion Rates
Source of Information
Location/Description
Erosion Type
Erosion Rates
m/yr ft/yr
USGS OFR 2007‐1112 (Cliff Edges)
Short Term Maximum Transects near MCWD Site Area
Bluff/Cliff Edges
0.45 1.48
USGS OFR 2007‐1133, Table 4 Average Cliff Retreat Rate for Monterey Bay
Bluff/Cliff Edges
0.4 1.31
Surfrider Foundation At the erosion “hotspots” area located at Opal Cliffs, Depot Hill and Manresa in Santa Cruz County
Bluff/Cliff Edges
0.2 to 0.63
0.66 to 2.0
City of Santa Cruz ‐Personal Communication with Laura Moore
Bluff retreat for City of Santa Cruz Bluff/Cliff Edges
0 to 0.63
0 to 2.0
Journal of Coastal Research Volume 25 Issue 3, Pages 603‐615, May. 2009
Average Long‐Term Shoreline Erosion for Monterey Bay Shoreline 0.6 1.97
USGS OFR 2006‐1219, Page 47 Average Long‐Term Shoreline Erosion for Monterey Bay
Shoreline 0.6 1.97
USGS OFR 2007‐1133, Page 18 Long‐Term Maximum Erosion at Sand City near Fort Ord
Shoreline 1.8 5.9
USGS OFR 2006‐1219, Page 47 Long‐Term Maximum in Monterey Bay at Indian Head Beach
Shoreline 1.3 4.3
USGS OFR 2006‐1251 (Sandy Shorelines)
Short‐Term Maximum Transects for the MCWD Site Area
Shoreline 1.31 4.3
CRSMP Table 11, November 2008
Short‐Term Adjusted for Anticipated Seawater Level Rise
Shoreline 1.67 5.5
USGS OFR 2006‐1251 (Sandy Shorelines)
Long‐Term Maximum Transects for the MCWD Site Area
Shoreline 0.81 2.7
Source: Summary of Historical Erosion Rates in the Vicinity of the Marina Coast Water District Marina State Beach, Marina, CA (MCWRA,2010)
1. Range of Short-Term Erosion Rates for Area of MCWD Site is 0.17 to 0.60 m/yr 2. Surfrider Foundation’s State of the Beach Report 3. Range of Short-Term Erosion Rates for Area of MCWD Site is 0.78 to 1.31 m/yr 4. Range of Long-Term Erosion Rates for Area of MCWD Site is 0.64 to 0.81 m/yr
Page 17 of 21 4.1.B Response to CCC Slant Well CDP comment letter.docx
Figure 2: Long Term Average Erosional Rates
Page 18 of 21 4.1.B Response to CCC Slant Well CDP comment letter.docx
Figure 2 shows the site‐specific long‐term shoreline erosion rates as calculated by the USGS along
equally spaced transect lines near the MCWD Reservation Road site. Of the four transects (which
intersect the MCWD property), the transect having the highest erosion rate (i.e. 0.81 m/yr ‐‐ 2.7 ft/yr)
was selected to estimate the 50‐yr set‐back CCC requirement. Using a long‐term erosion rate of 2.7
ft/yr, the estimated 50 year setback distance is 135 feet from the current bluff edge. The proposed slant
test well entry point is 227 feet from the bluff edge, which allows a 92‐foot buffer zone (based on the
projected 50‐year bluff edge location). To account for uncertainties in the analysis, CCC suggests using a
safety factor of at least 1.5 (CCC‐W11.5, Page 14). The estimated 92 foot buffer zone allows for a safety
factor of 1.7, providing a sufficient buffer zone to cover uncertainties inherent to the analysis. This
assessment does not, however, account for projected future sea‐level rise.
The Association of Monterey Bay Area Governments report Coastal Regional Sediment Management
Plan for Southern Monterey Bay [CRSMP] (Philip Williams and Associates, November 2008) included an
assessment of future sea‐level rise on Monterey Bay erosional rates. In this report, the CRSMP
evaluated increases in erosional rates based on a sea level rise rate of 3.0 ft/century (one foot over the
next 50 years, assuming an exponentially accelerating rise). As noted in the document, this estimate is
considered precautionary for long‐term planning for sea‐level rise and is in line with Coastal Commission
measures which require consideration of a three‐foot sea‐level rise over the next century. This
estimated 50‐year sea level rise resulted in corresponding incremental shoreline recession rate of
approximately 0.8 feet per year, averaged over the next 50 years. Therefore, using the long‐term
erosion rate of 2.7 ft/yr (as established above) with an incremental increase of 0.8 ft/yr to account for
future projected sea level rise, results in an estimated yearly erosional rate of 3.5 ft/yr. Based on this
rate, the estimated 50 year setback distance becomes 175 feet from the current bluff edge. As noted
above, the proposed slant test well entry point is 227 feet from the bluff edge, which allows for a 52‐
foot buffer zone (based on the projected 50‐year bluff edge location). This corresponds to a factor of
safety (FS) of 1.3. While this FS is less than the 1.5 recommended by the CCC, the anticipated life of this
well is 30 years and the distance projected above is for a 50‐year period. For comparison purposes, using
the erosion rate of 3.5 feet per year and a well setback of 227 feet from the bluff edge (as noted above),
it will take approximately 65 years for the bluff erosion to reach the wellhead location (corresponding to
a factor of safety of 2.2). If the conservative erosion rate of 5.5 ft/yr is used instead (as noted in Table 11
of the CRSMP), which is already adjusted for anticipated sea level rise, it will take approximately 41
years for the bluff erosion to reach the wellhead location (corresponding to a factor of safety of 1.4);
well beyond the anticipated 30‐year operating life of the well.
Page 19 of 21 4.1.B Response to CCC Slant Well CDP comment letter.docx
Comment 15: Page 3 ‐ If the analysis shows that any proposed project components could be affected
by coastal erosion during the anticipated project life, please identify measures, such as relocation of
project components or planned retreat that would avoid or reduce that risk. These measures should
also address potential impacts to coastal resources – e.g., effects of relocation or planned retreat on
ESHA, access, etc. Please note that the project should not rely on shoreline protective devices or bluff
armoring to address coastal erosion impacts.
As described above, the Slant Test Well currently proposed for the Regional Desalination Project at the
MCWD Reservation Road site is situated far enough from the coastal bluff as to be protected through its
operating life of 30 years. When (and if) this well is replaced in 30 years, the well’s location will be re‐
evaluated with respects to coastal erosion and, if found in danger of future erosion, will be relocated
further inland in another location. Such relocation would be subject to environmental review and the
corresponding permitting process at that time.
Comment 16: Page 4 – Please identify the total expected energy use during well construction and
testing and the associated direct and indirect GHG emissions. This should include those associated
with construction vehicle use and those associated with electricity used during pumping.
The proposed Slant Test Well Program has both construction‐ and operation‐related emissions.
Construction emissions are associated with site preparation, drilling and well construction; operational
emissions are associated with pumping for well sampling, and aquifer pumping tests. Because pumping
will involve the use of electricity generated offsite, there are both direct emissions associated with
construction and indirect emissions associated with operations. For purposes of this analysis, the
construction and operational emissions were calculated using separate models.
Construction‐related Emissions
Construction emissions are associated with site preparation, drilling and well construction. To account
for both direct and indirect emissions associated with these activities, the CalEEMod model was used
(CalEEMod Version: CalEEMod 2011.1). The CalEEMod is a statewide land use emissions computer
model designed to provide a uniform platform for government agencies, land use planners, and
environmental professionals to quantify potential criteria pollutant and greenhouse gas (GHG) emissions
associated with construction from a variety of land use projects. The following inputs were used to run
CalEEMod:
Land Use / Construction Phases
o Land use ‐ light industrial
o Land affected ‐ 28,700 square feet (Slant Test Well Project Description, March 2011)
o Construction schedule – 4 months (Slant Test Well Project Description, March 2011)
o Construction will have two phases: Site Preparation and Drilling/Well Construction
Off Road Vehicles
o Drilling schedule – 120 days
o Site Preparation estimated to use tractors/loaders/backhoes for a single 8 hour period
Page 20 of 21 4.1.B Response to CCC Slant Well CDP comment letter.docx
o Drill rig estimated at 600 HP and drilling estimated at 8 hours per day, 5 days per week
o Fork lift estimated at 4 hours a day
o Trips and Vehicle Miles Traveled (VMT) ‐ Total of 5 hauling trips
Also associated with construction is final well development, which has indirect emissions associated
with electricity usage; final well development inputs assumed that 70 hours of pumping were required
for the latter stages of well development.
The results of the CalEEMod model for construction‐related emissions are included in Attachment G to
this letter.
Operations‐related Emissions
Operational emissions for the Slant Test Well are associated with pumping operations during the
planned short‐term aquifer pumping test and a three‐ to six‐month test operations period. The pumps
that would be used for well development will be powered by electricity, not combustion onsite. As a
result, the emissions are indirect as they are generated by the power producer. In order to obtain an
accurate emission estimate based on specific pumping data, the Local Government Operations Protocol
(Protocol) was used (Local Government Operations Protocol, Version 1.1, May 2010). The Protocol was
designed to provide a standardized set of guidelines to assist local governments in quantifying and
reporting GHG emissions associated with operations. The Protocol was developed in partnership by the
California Air Resources Board (CARB), California Climate Action Registry (CCAR), and ICLEI – Local
Governments for Sustainability (ICLEI), in collaboration with The Climate Registry and dozens of
stakeholders.
The Protocol recommends two approaches to determining emissions associated with electricity use:
1. Utility‐specific emission factors that have been third party verified to the standard of the CCAR
Power/Utility Protocol or The Climate Registry Electric Power Sector Protocol; or
2. eGRID regional default emission factors (by subregion) or California Grid Average Factors
(eGRID2010 Version 1.1, Year 2007 Summary Tables (created May 2011).
The use of eGRID default emissions factors were deemed more appropriate for this application since the
utility specific emission factors provided overall emissions and not a clearly defined emissions per power
unit used. eGRID emission factors for California were provided by eGRID2010 Version 1.1 Year 2007
Summary Tables. The subregion used was CAMX, which includes Western Electricity Coordinating
Council (WECC) California and the region for this project.
Emissions Summary
Emissions were calculated for both construction and operation. Emissions were quantified as carbon
dioxide equivalent (CO2e) and presented in units of metric tons (MT). CO2e the industry standard
measure for describing how much global warming a given amount of GHG may cause, using the
functionally‐equivalent amount of carbon dioxide (CO2) as the reference. The units of MT are the
Page 21 of 21 4.1.B Response to CCC Slant Well CDP comment letter.docx
industry standard unit of measure for GHG presented as CO2e (Emission Facts: Metrics for Expressing
Greenhouse Gas Emissions: Carbon Equivalents and Carbon Dioxide Equivalents, EPA420‐F‐05‐002,
February 2005). Table 3 summarizes the GHG emissions associated with the proposed Slant Test Well.
Detailed emission information is provided in Attachment G.
Table 3: Slant Test Well Direct and Indirect GHG Emissions
Description GHG Emissions (MT CO2e)
Construction 274.35
Operations 64.13
Total 338.48
As a reference, CEQA analyses use significance thresholds to evaluate project impacts, but there is
significant uncertainty about significance thresholds for GHG. In response to uncertainty about GHG
standards for new projects, CARB developed statewide interim thresholds of significance for common
project types that, collectively, are responsible for substantial GHG emissions. In applying these interim
thresholds, CARB developed a preliminary threshold of 7,000 MT CO2e/yr for industrial projects.
However, this applies to only operations and not construction. CARB is not establishing thresholds for
construction projects, but rather is proposing mandatory performance standards. This threshold,
however, helps to put into perspective the operational emissions associated with the Slant Test Well
project, with an estimated GHG emissions of 388 MT, which is approximately 5% of the CARB
significance threshold of 7,000 MT CO2e/yr.
Attachment A – City of Marina City Council Action and Consolidated Permit
Approach Concurrence Letter
Attachment B – City of Marina Local Agency Review Form
Attachment C – Water Rights Issues Related to the Monterey Regional
Desalination Project (Downey Brand LLP, 2011)
Attachment D – Location of Slant Test Well Facilities relative to ESHAs
Attachment E – Monterey Bay Regional Desalination Project Conceptual Draft
Rare Plant and Habitat Restoration Plan (DD&A, 2011)
Attachment F – Summary of Historical Erosion Rates in the Vicinity of the
Marina Coast Water District Office, Marina State Beach, Marina, California
(Geoscience, 2010)
Attachment G – GHG Emission Results
Attachment H – Updated Slant Test Well CDP Application Materials
Attachment I – Revised Addendum to the Coastal Water Project – Environmental
Impact Report for the Test Well Program (June 6, 2011)