Response-Audit Report on Jalayagnam-Vol.1

Embed Size (px)

Citation preview

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    1/40

    Go To Contents

    Response ofIrrigation & CommandArea Development Department

    to the Draft Performance Audit

    Report on

    JalayagnamVol. 1

    Irrigation & CAD Department.

    Government of Andhra Pradesh

    July 2012

    V

    1

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    2/40

    Go To Contents

    Table of Contents

    Sl.No.

    Name of the Para

    Reference to

    Paragraph

    1 Over view 1

    2 Audit Frame Work 2

    3 Planning 3

    4 Selection of Process 3.1

    5 Assessment of water resources 3.2

    6 Project formulation 3.3

    7 Requirement of Power 3.4

    8 Provision of Standby Pumps 3.5

    9 Benefit - Cost Ratio 3.6

    10 Inter-State issues 3.7

    11 Project Approvals 3.8

    12Taking up of Projects without fulfillment ofPre-requisites

    3.9

    13 Tendering and Contract Management 4

    14 Empanelment of Contracting agencies 4.1

    15Cartelization/Suspicious and unfairtendring practices

    4.2

    16 EPC System of Contracting 4.3

    2

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    3/40

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    4/40

    Go To Contents

    I&CAD Department sincerely expects at least for now, the information

    given in the accompanying document will result into suitable

    modifications of the draft Report. In any case, the version given by the

    Department shall also be included before passing any verdict in the

    final Report. It is also expected that the final Performance Report on

    Jalayagnam will also appreciate constraints faced by, and corrective

    steps taken by the Department from time to time. The final Report will

    not be a mere indictment and will also come out with the concrete

    constructive policy and other suggestions to be implemented at the

    Government and field levels.

    Genesis of the Projects under Jalayagnam

    It is important now, to explain how a project is approved and

    implemented in the public sector. In this connection, the first and

    foremost is the felt need for having such a project. Based on felt need,

    techno-economic feasibility and viability of a project is assessed. Only

    such viable projects after obtaining necessary financial concurrence gothrough a process leading to the administrative approval. Those

    projects having techno-economic viability, financial concurrence and

    the requisite political will (with technical and administrative sanctions)

    are implemented. This entire process is not static but a dynamic one

    based on the analysis of ground realities. This often, leads to

    variations between line and detailed estimates. It does not mean that

    one is correct and other estimate is inflated or incorrect (unlesssupported by corroborative evidence). Any one conversant with basic

    project management, knows that even detailed estimates (thats why

    called estimates) depend upon a number of variables such as designs

    etc., that evolves over a period of time. Before pronouncing any thing

    4

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    5/40

    Go To Contents

    fishy, the concerned agencies are supposed to verify facts, try to

    appreciate reasons and come to an informed conclusion.

    Detailing is possible to an extent and no system can take into account

    several emerging internal and external factors. In addition due to

    various reasons, a few projects though, having necessary

    administrative sanctions are not grounded for quite some time. As and

    when such projects are grounded, it leads to inevitable cost escalation.

    However, such incidents are part of contemporary public policy. Table

    1 below gives a comprehensive picture of all 86 projects including 4

    projects yet to take off though all taken up under Jalayagnam.

    Table 1: No of projects sanctioned in a financial year and Amount of

    Administrative approval of these projects

    (Amt. in Rs. Crs.)

    SN Financial

    Year

    No. of

    Projects

    Original admn.

    Sanction1 Prior to 2003-04 8 785.152 2003-04 4 1353.893 2004-05 36 71727.144 2005-06 6 2397.165 2006-07 3 4643.686 2007-08 10 11313.177 2008-09 15 75488.48

    82 167708.97Source: PMU of I&CAD

    In addition to the above 82 projects, due to various reasons 4 works

    sanctioned in 2008-09 amounting to Rs.17900.69 crores under

    Jalayagnam had so far, not been grounded. Some of the other projects

    such as Head works of Indira Sagar Polavaram Project (ISPP), delta

    5

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    6/40

    Go To Contents

    modernization and flood banks though, grounded had not yet been let

    out to the full extent of their administrative approval.

    As it could be seen from the Table 1, Jalayagnam is meant not only for

    sanctioning new projects but also aims at completing projects

    languishing even before the launching of this Program prior to 2004-

    05.

    Prior Scrutiny of Jalayagnam Projects by PAC

    It is pertinent to mention that in the last 4 to 5 years many of the

    irrigation projects taken up under Jalayagnam had already been

    audited by the Principal AG and as well as, also examined by the Public

    Accounts Committee (PAC). The department had also furnished

    detailed information on various irrigation projects to the Secretariat of

    AP Legislature as desired by the PAC as per details given in Annexure

    I. It goes without saying that Principal AG and other officials of the

    O/o Principal AG were active participants in all the PAC meetings. Thecopies of these documents were also as well, handed over to the

    Principal AG.

    Some of the issues raised in the draft Performance Audit Report had

    been deliberated upon, and a considered view had already, been taken

    by PAC on certain substantive issues. It defies the conventional logic

    and rationale of once again raising these issues in the form of aconsolidated draft performance report even after the superior body

    (PAC) had examined several related issues including CAG paragraphs.

    However, the point wise detailed rebuttal is given in the successive

    paragraphs of this document.

    6

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    7/40

    Go To Contents

    The stand of department had time and again, been articulated in the

    PAC meetings and is reiterated even in this document. In view of

    enormity of Jalayagnam projects (both in terms of numbers and size),

    the department resorted to parallel processing of the desired set of

    actions. This approach is different from the sequential processing

    approach articulated by the O/o PAG. In other words, PAG essentially

    suggests so as to first complete the design, investigation and survey of

    the projects to be taken up; do the land acquisition (including

    acquisition of forest land, wild life sanctuary etc.); then go for various

    statutory clearances (in principle site clearance from MoEF, stage one

    forest clearance, deposit Net Present Value of forests and cost of

    compensatory afforestation; seek stage 2 forest clearance, obtain

    approval of the wild life board, clearance of Ministry of Tribal Affairs,

    go for approval of various directorates of Central Water Commission,

    TAC clearance of Ministry of Water Resources, and lastly investment

    clearance from the Planning Commission) before awarding the work to

    various contracting agencies. This suggestion is too simplistic tofollow; and also overlooks contingencies arising out of various court

    cases and other litigation; and suggests uniform process for all the

    irrigation projects.

    Several passing comments had been made such that investment

    clearance from the planning commission for the projects on interstate

    rivers and their tributaries is mandatory; taking up execution ofprojects without obtaining investment clearance is not only violative of

    the constitutional provisions, but is also likely to run in to trouble at

    the time of releasing water since Andhra Pradesh is down stream state

    for most of these rivers etc. Year wise analysis of river water going

    7

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    8/40

    Go To Contents

    into Bay of Bengal (Table 2) indicates huge variations. It is once

    clarified that there is no legal or constitutional hurdle for the lowest

    riparian state to plan and implement certain flood water based

    irrigation projects.

    Table 2: Variations in Annual flood flows of major rivers in Andhra

    Pradesh

    (surplus discharges in TMC)

    Name of theRiver

    Maximum Minimum

    Godavari 6081.07(1994-

    95)

    682.4(2009-10)

    Krishna 1329.304(1994-

    95)

    2.281 (2002-03)

    Vamsadhara 197.268(2006-

    07)

    31.561(2000-01)

    Pennar 117.18(2001-02) 0 ( in many years)

    Source: EnC (Irrigation)

    Allegation that no comprehensive study was undertaken by the State

    Government before taking up Jalayagnam to review (1) the quantum

    of utilizable water available to state (2) quantum of water being

    utilized by the existing projects (3) balance water including flood water

    available for utilization in new projects is strongly refuted. The

    comment that there was no evidence to indicate that the flood data of

    Krishna and Pennar rivers was analyzed to access the average number

    of days where flood flows are available annually and average annual

    total flood discharge is also out of place. As every river basin is unique

    and is different from any other basin, the question of adopting uniform

    8

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    9/40

    Go To Contents

    number of flood days for designing the projects that use flood flows

    does not arise.

    There is also a lot of criticism in the Draft Report about the

    Engineering, procurement and construction (EPC) system as adopted

    by Andhra Pradesh for Jalayagnam projects. It is incorrect to say that

    the tendering and contracting process lacked transparency and

    financial interest of the state for not safe guarded. The following steps

    taken by the Department for system improvement, increased

    transparency and better quality control further reiterate evolutionary

    EPC system:

    Measures taken for system Improvement:

    Jalayagnam, being an ambitious task with unprecedented level

    of challenges in implementation, the State Government had from time

    to time, taken several conscious decisions to streamline and improve

    the overall procurement process for ensuring timely execution of works

    with quality and overall transparency.

    (i) EPC Methodology: Keeping in view, the available manpower in

    the department as well as complex technical nature of the works in

    terms of design and introduction of latest technology, Government

    took a decision to go with internationally recognized and proven EPC

    methodology. The same methodology has also been used by some of

    the large Government of India Institutions. Major and mediumprojects were in turn divided into different packages. This was to

    ensure that major construction companies take up such work and

    bring in the latest technical know-how at a competitive price /rate.

    Under this system, the agency awarded with the work, has to take up

    9

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    10/40

    Go To Contents

    the investigation, survey, designs and construction of their package on

    a turn key basis. In this system there will not be any scope to account

    for deviation of quantities, revision of estimate etc. The EPC system

    adopted in Andhra Pradesh was however, different from internationally

    recognized EPC on more than one count. Internationally, there is no

    cap on the tender premium. However, it was fixed at 5% and any

    tender over this cap was bound to be rejected in Andhra Pradesh

    Model. Similarly, tender value quoted below a certain percentage of

    IBM, the bidder is expected to provide additional performance security.

    Under the Andhra Pradesh system the price adjustment provision is

    followed in respect of only 4 components Steel, Cement, POL and

    Metals used in Electro Mechanical components; while global EPC allows

    for price adjustment for all components including that for labor and

    material especially, beyond agreement period.

    Another positive aspect of EPC methodology is that investigation and

    design for the complete project is taken up. Tenders have been called

    for all the projects, keeping in view that project conceptualization canbe done comprehensively this way. It has also facilitated timely and

    speedily requisitions being given to land acquisition authorities as

    there are several EPC agencies conducting survey and investigation. It

    also ensures that land is available in advance and government need

    not face constraints of non availability of land at critical stages of

    projects when the costs will be higher and projects will be delayed. It

    has been attempted to match the milestone fixed, financial outlay andtargeted dates for completion of the projects under this system.

    (ii) E Procurement: The entire tender process has been made

    through a well established e-procurement process where, all the

    10

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    11/40

    Go To Contents

    information is available on line. Guidelines in consultation with IT

    department are being followed.

    (iii) Rationalization of Internal Bench Marks (IBMs).: A high

    level technical committee looks into finalization of IBM for all these

    EPC packages consisting of Advisor/ Senior Technical Officers to the

    Government, Chief Engineer, Central Design Office and concerned

    Project Chief Engineer. This is to ensure the rationalization of

    estimates for consistency and uniformity in the approach. The central

    design office had also communicated certain standard drawings,

    designs and specification to all concerned for bringing uniformity,

    reducing errors and cutting down delays.

    (iv) Institutional & Administrative Mechanism: A State Level

    Standing Committee undertakes technical and financial evaluation of

    the bids received. The committee consists of Engineer-in-Chief, Chief

    Engineer, Designs; and Commissioner of Tenders, Chief Engineer

    (Projects) and a representative of Finance Department (DFA). Therecommendation of this state level Technical Evaluation Committee is

    further examined by the High Power Committee/ Committee of

    Secretaries. All the major packages beyond Rs 100 crores go to

    High Power Committee which is chaired by the Chief Secretary. These

    recommendations are taken into consideration by the Government

    before acceptance of bids. An Advisory committee has also been

    constituted to deliberate upon technical issues and also opine uponprovisions of agreement as to an item of work is covered in it or not.

    They also brainstorm on further improvements.

    11

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    12/40

    Go To Contents

    (v) Land Acquisition: Over 6 lakh acres land for both projects site

    and submergence area had been acquired by I&CAD Department for

    Jalayagnam project through the methodology of consent award. This

    prevents litigation and future cost escalation. Innovative arrangements

    for expediting land acquisition were made by constituting District &

    State level negotiating Committees with suitable delegations

    facilitating consent awards and litigation free land acquisition.

    However, this step had not overcome litigations due to political and

    other reasons. Despite taking all the possible care, some critical

    patches of land acquisition are still sub-judice.

    (vi) Quality Monitoring Systems (Involvement of independent

    agency, multi-pronged approach): The Government has given the

    utmost importance to the maintenance of highest standard of quality

    in all these works. Detailed quality guidelines have been issued to the

    field Engineers and close monitoring of quality standards have been

    ensured. The present arrangement vis--vis monitoring of quality has

    multi-pronged approach involving a combination of three agencies.

    a. EPC agencies in the first instance, are themselves responsible to

    set up a quality control lab conducts certain tests and keep this

    record available for scrutiny.

    b. Departmental Quality Control Agency

    c. Third Party Quality Control Agencies a novel idea of engaging

    reputed professional agencies who are independent to monitorthe quality execution of works. These agencies have been

    selected at State level through a transparent open bidding

    system, and they do not depend upon the payment of their bills

    on the project authorities as they draw their payment at state

    12

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    13/40

    Go To Contents

    level. The Government also decided to create posts of Chief

    Engineer, Quality Control for different regions.

    In addition to these agencies, quality is also checked up at

    random by the Vigilance & Enforcement wing as well as, by the

    Advisors to the Government and other senior technical officers. Many

    prominent experts from IIT and other reputed institutions have also

    been visiting these works.

    (vii) Transparency: On line sharing of information has been put in

    place to bring further transparency and encourage involvement of

    public at large in the day-to-day progress of execution of works as well

    as maintenance of quality standards. Special software has been

    developed for project monitoring as well as quality monitoring and

    they have been made available online to the general public through

    web page through Centre for Good Governance (CGG), Hyderabad.

    The feedback boxes were also kept at different public offices

    throughout the State.

    (viii) EPC Codes-A compendium of instructions on EPC was

    developed and shared with all concerned to bring clarity. A separate

    chapter on EPC was also annexed to the existing PWD codes following

    due process.

    (ix) Financial Management Projects had been prioritized for earlycompletion in consultation with the Finance Department. The

    Department had also taken steps to complete 13 projects and ensure

    utilization of partial benefits from another 23 projects. However, by

    very nature of irrigation projects, benefits commensurate with financial

    13

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    14/40

    Go To Contents

    expenditure can not always be achieved unless the entire project is

    completed. The year wise budget and expenditure on Jalayagnam

    projects is given in Table 3. It would be pertinent to point out that

    budgetary releases were a major constraint on the overall expenditure.

    As on 29th Febuary 2012, 13 major and medium irrigation projects

    have been completed creating new IP of 1,37,254 acres and

    stabilization of another 1,89,379 acres. In another 21 projects water

    has been released to 14,37,995 ac of new IP and stabilization of

    2,06,853 acres. By doing systemic improvements, an additional

    ayacut of 1,18,374 ac has been achieved under four old projects.

    Thus the total new IP created under major and medium irrigation

    projects under Jalayagnam is 16.936 lakh ac and another 3.962 lakh

    ac had been stabilized (Total 20.899 lakh ac).

    Table 3: Annual Budget, Expenditure & Irrigation Potential

    created under Major & Medium Irrigation Projects (2004-05 TO

    2011-12)

    S.NoFinancial

    Year

    Budget

    (Rs. In Crs.)

    Expenditure

    (Rs. In Crs.)

    Irrigation

    Potential

    (Lakh Acres)

    1 2 3 4 5

    1 2004-05 4,246.00 3,331.00 1.10 (New)

    14

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    15/40

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    16/40

    Go To Contents

    Despite the financial constraints, efforts have been made to

    prioritize the projects and complete them as per agreements and

    the Action Plan for completion of various ongoing projects has been

    prepared by the I & CAD Department. A large number of projects

    are at advanced stage. Approximately half of these projects are

    above 50% level. The action plan has been prepared in detail

    taking into account the present physical progress of works,

    clearances, land availability, other constraints etc. and with a

    focused approach on those projects which can be completed.

    Constraints

    The projects taken up under Jalayagnam are not being completed

    as per target in view of paucity of human resources (Table 4).

    There are 5 posts of ENCs, 33 posts of CEs and 88 posts of SEs. In

    view of various court cases, only in-charge arrangements are made

    to these posts instead of regular promotions. In addition, frequent

    change of incumbency of officers at different levels due totransfers / in-charge arrangements / retirements, there is no

    continuity and the successors are unable to take timely follow up

    action to sustain the tempo of works. As a result the progress is

    hampered and the targets are not met with. It is, therefore,

    suggested to collect the up to date project/package wise particulars

    for appraisal and to take appropriate follow up action.

    The need for continuation of third party quality control agency in

    full scale/ with reduced staff/ termination as per agreement

    conditions by entrusting balance work to the departmental quality

    16

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    17/40

    Go To Contents

    control staff has to be reviewed as full time Chief Engineer Q.C with

    his staff is in existence at present.

    Table.4: Availability of Technical Officers in I &CAD Department

    Sl.No

    Posts 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12

    1EE 447sanctioned posts

    Vacancies

    Nil 236 1 Nil 8 283 31 242 92

    2

    DEE1578sanctioned posts

    vacancies

    35 378 293 301 35 423 71 183 201

    3

    AEE

    5846sanctioned posts

    vacancies

    1276 1374 2515 1693 502 1030 2673 1567 488*

    * 1111+1300 (2411) Assistant Executive Engineer posts notified to

    APPSC for Direct Recruitment.

    All the activities of the Department are reviewed by various officials

    from time to time and corrective actions are taken. In addition to

    periodic high level reviews by Honble Chief Minister and

    Minister (M&MI), all developments pertaining to Jalayagnam

    projects are informed by the Department to the State Cabinet at an

    interval of at least once in two months.

    Most of the Jalayagnam projects were taken up in the drought prone

    district of Andhra Pradesh which had witnessed continuous labour

    migration, decline in agricultural activity, farmers indebtedness and

    suicides. As a remedial measure to this decline Prime Ministers

    rehabilitation package for these districts in the state of Karnataka,

    Andhra Pradesh and Maharashtra was initiated. Irrigation project

    became a major activity in these districts to assure water to the crops

    17

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    18/40

    Go To Contents

    to check the decline in the farming activity in these districts. All the

    medium Irrigation Projects in the drought prone district and some of

    the major Irrigation Project like PCLIS. Dummugudem Tail pond were

    therefore included in the Prime Minister relief package for these

    districts. Therefore, the reason for simultaneously launching of the

    projects must not be lost sight of while evaluating the various factors

    like, preparation of DPR, time line for launching of the project finances

    etc., If these reasons are kept in view, then many of the findings of

    the audit can be explained, as to why Government of Andhra Pradesh

    took up projects on a such a large scale in such as short time. The

    nature of problem required urgent measures, which became the

    genesis for taking up these projects.

    The existence of farm land at a higher contour than the water levels in

    the rivers, the position of Andhra Pradesh being a tail end state for

    both Krishna & Godavari rivers directed the state Government to

    explore for solution through available technology of lifts and big

    motors and pumps. When technology and resources are available thennot directing them to bring relief to the farmers would have been

    incorrect. We can produce power in a desert, but we cannot produce

    water.

    Therefore, the whole launching of Jalayagnam was directed by the

    emerging situation in the drought prone district of Andhra Pradesh.

    This requires to be kept in view while assessing the performance ofJalayagnam.

    In nutshell, PAG is requested to consider the information given in this

    document for finalizing the final performance report, duly considering

    18

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    19/40

    Go To Contents

    the criteria, as given in the draft performance report. The performance

    of the entity has to be Judged against a criteria through a

    methodology mutually agreed between the audit and entity. In this

    case, although audit has pointed out at many places shortcomings, at

    no place, there is a conclusion arrived after judging against a criteria

    i.e., a Government order, codes or even a model for undertaking such

    projects.

    In the absence of the performance being judged against a criteria, the

    whole report appears as on exercise in piecemeal collecting evidence

    and arrive at conclusions without stating, which codes, rule, order,

    GFR has been violated or ignored while grounding projects. Therefore,

    it would be correct to suggest that all the finding be subjected to the

    criteria as already indicated, then we can arrive at final conclusion,

    which would also be correct and then recommendation can be made to

    improve the performance to attain the policy objectives of Jalayagnam.

    Our replies for each finding is given. We would expect our replies to begiven equal printing space along with the findings while the final report

    is being submitted to the legislature. The findings of audit and the

    reply of entity should be given in equal measure and detail, even if the

    audit does not agree with the replies given. Then only findings and

    final conclusion will carry conviction and will be fair to the entity. With

    these remarks on detailed reply is submitted.

    Annexure-A

    19

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    20/40

    Go To Contents

    As per the report of the C & AG of India of Government of

    Andhra Pradesh, the details of the Performance Audit under gone

    since last 6 years are as follows:

    Sl.No.C & AGReport

    Year endedGist of the paras Audit Para No.

    1. 2004-05Performance Audit Not Conducted

    2. 2005-06Performance Audit Not Conducted

    3. 2006-07

    Godavari Water Utilisation

    Authority

    (I) J.Chokka Rao Devadula LiftIrrigation Scheme (JCRDLIS)(II) Sripadasagar Project (SSP)(III) Alisagar Lift Irrigation Scheme(ALIS)(iv) Arugula Rajaram Gupta Lift

    Irrigation Scheme (ARGLIS)

    (V) Lendi Project and(vi) Dummugudem Project consistingof Rajeev Sagar and Indira Sagar LiftIrrigation Scheme.

    3.2(Pg.Nos.56-71)

    4. 2007-08Performance Audit Not Conducted

    5. 2008-09 Third Party QualityControl/Assurance (TPQC) inexecution of Irrigation projects:AMRP, Pulichinthala, Telugu GangaProject, AVR HNSS, VeligondaProject, Komarambheem, Palemvagu,Kinnerasani, Thotapalli, Peddagadda,Tarakarama Theerthasagaram,

    Jhanjavathi Project, SomasilaSwarnamukhi Link Canal, Pushkara,Venkatanagar LIS.

    Accelerated Irrigation benefit

    Programme:

    In Andhra Pradesh, 30 Major/Medium

    1.3(Pg.Nos.50-63)

    20

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    21/40

    Go To Contents

    Irrign. Projs. and 67 MI Schemeswere identified under AIBP.1.SRSP Stage.I2.Annamayya proj3.Priyadarsini Jurala

    4.Somasila Project5.Nagarjunasagar6.Madduvalasa7.Gundlavagu,8.Maddigedda,9.Kanpur Canal,10.Yerrakalava,11.Vamsadhara Ph.I,12.Flood Flow Canal of SRSP,13.SRSP-II

    14.Tadipudi LIS,15.Pushkara LIS,16.Rallvagu,17.Gollavagu,18.Mathadivagu,19.Peddavagu,20.Gundlakamma Reservoir,21.Velligallu Reservoir,22.Alisagar LIS23.J.Chokarao LIS24.A.R.Guthpa LIS,

    25.Nilwai26.Khomram Bhim27.Thotapalli barrage project.28.Tarakarama Thirtha SagaramProj.29.Swarnamukhi Medium IrrigationProject,30.Palemvagu and 67 Minor Irrigaaation Schemes.

    6. 2009-10 Mahatma Gandhi( Kalwakurthy) Lift Irrigation Scheme

    2.2( Pg.Nos.32-46 )

    21

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    22/40

    Go To Contents

    22

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    23/40

    Go To Contents

    23

    3.Planning:

    3.1 Selection of projects:

    Andhra Pradesh is a predominantly Agrarian State

    similar to many other large states in India. A Majority of the

    population (More than 70%) depends and derives their

    livelihoods and sustain on Agriculture and Agro based

    activities. The growth of the State economy and majority

    peoples well being therefore depends to a large extent on

    the continuous growth and expansion of sustainable

    Agriculture Sector.

    The Single most important input for sustainable

    Agriculture is water, which is primarily dependent on normal

    or good monsoon rainfall. It is observed that in normal

    rainfall years also, agriculture yields depend on timely

    incidence of Rainfall both in terms of quantity & quality. The

    effect of deficit rainfall is virtually crippling Agriculture

    Sector to a large extent in the State. The Disastrous

    consequences of continuous drought during 2000 to 2004

    had broken the entire rural Agriculture based economy of

    the State.

    The districts affected due to droughts are as follows

    DistrictTotal

    Mandals

    2000-01 2001-022002-

    032003-04

    2004-05

    Srikakulam 38 16 38 28 11 8

    Vizianagaram

    34 17 34 34 11 6

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    24/40

    Go To Contents

    24

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    25/40

    Go To Contents

    25

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    26/40

    Go To Contents

    26

    3.3.1 Feasibility studies:

    Vamsadhara Stage-II Phase II

    This project is a part of Vamsadhara Stage-I which is

    cleared in all aspects. As the Government of Orissa is

    objecting to the construction of Barrage from view point of

    submersion, the project could not be taken up.

    As such the phase-II component has been proposed

    without head works but with side weir channel. In view of

    that there is no difference in the status of availability of

    water and ayacut to be benefited.

    That is the reason why the project has been taken up

    with the reports already prepared by the Department.

    CBR Lingala Canal:

    The Chitravathi Balancing Reservoir is an existing reservoir

    to store 10 tmc Water. This balancing Reservoir is a part of

    TBPHLC system and is intended to stabilize the ayacut of

    59500 acres under Pulivendula Branch Canal and to serve

    the Lingala Canal of 25000 acres. This scheme has been

    proposed by suitably adjusting 10 tmc of water to the above

    extents of canal system by adopting micro irrigation system

    in the Pulivendula Branch Canal. Thus, the 10 tmc would be

    available from the TBPHLC in the event of surplus years. So

    the CBR right canal that is Lingala has been taken up within

    the system made possible due to savings in the existing

    Pulivendula Branch Canal. However, the CBR which is to

    receive waters from the TBPHLC is not receiving adequate

    quantity of water. In view of that the part of surplus water

    that is being received into the Gandikota Reservoir System

    is envisaged to be drawn to supplement the CBR system to

    make the CBR system more effective from the view point of

    the functionality by lifting waters from Gandikota Reservoir

    System.

    The integration of the operations of CBR system with

    the Gandikota Reservoir is for improving efficiency of the

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    27/40

    Go To Contents

    27

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    28/40

    Go To Contents

    28

    3.3.3 Preparation of Detailed Project Reports

    Sripada Yellampally Project

    The preparation of DPR for this project was entrusted to M/s

    Aarvee Associates before the award of the contract and

    closely monitored, whereas the Agreement for the works of

    SYP Stage-II Phase-I and NTPC Lift Scheme were concluded

    on 03-04-2005 & 07-04-2005 respectively. The work of

    preparation of DPR is mainly intended to get the project

    clearances from CWC, which is a continuous process.

    However in the mean time the works also are put on ground

    to save delay.

    Dr.B.R.A.P.C.S.S.

    This project is taken up as per the Godavari Water

    Disputes Tribunal (GWDT) report, dated 06th

    October 1975, wherein the State of Maharashtra

    and Andhra Pradesh have agreed in-principle to

    take up this project at appropriate time with

    agreed water utilization and with assured

    availability of water. The Government of Andhra Pradesh has accorded

    permission for preparation of detailed project

    report for diverting 160 TMC of water from

    Pranahita river to Sripada Sagar Project Reservoir

    and creating additional Ayacut of about 12.20 lakh

    acres including drinking water and industrial

    requirement of Hyderabad vide G.O.Rt. No. 623, I& CAD Dept., dated 15-07-2005.

    Accordingly, an Expert Technical Committee was

    constituted by the Government of Andhra Pradesh

    vide G.O.Ms No. 193, dated 27-10-2005 to

    evaluate and finalize the bids and to take up the

    work of preparation of Detailed Project Report.

    The Government after careful examination of the

    recommendations of the above committee decided

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    29/40

    Go To Contents

    29

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    30/40

    Go To Contents

    30

    3.3.4 Identification of targeted ayacut:

    AMR SLBC Project:

    The Government in 4/95 decided to take up Lift Scheme

    from the foreshore of Nagarjuna Sagar Reservoir to give

    early benefits without prejudice to Tunnel Scheme vide

    G.O.Ms.No.55, I&CAD Department, dt.17.4.1995, as the

    Tunnel Scheme would require 7 to 8 years to complete.

    Accordingly, the Lift Scheme works were taken up and

    completed. Partial benefits have been giving from 2001

    onwards from Lift Scheme. Tunnel Scheme is taken up in

    2005 as a permanent solution. Since the possibility of

    drawing water by gravity is available for this project, the

    Tunnel scheme is taken up. For most of other schemes,

    there is no alternative except taking up of Lift.

    SOMASILA SWARNAMUKHI LINK CANAL (S.S.L.C.)

    The details of the Village wise and Mandal wise identified

    targeted Ayacut pertaining to SSLC Scheme have already

    been furnished to the audit. However a copy of the same is

    enclosed herewith.

    VELIGONDA PROJECT

    In the project scope of all works pertaining to canal

    networks, Mandal wise ayacut was prescribed. This is for

    the reason that in the absence of detailed ayacut registers

    the Village wise ayacut cant be arrived at. In fact the

    preparation of ayacut registers is one of the tasks in the

    EPC agreement which can be arrived at only after

    finalization of HPs, BC Maps etc. So far, the village wise

    ayacut finalized package wise is as follows.

    Package II- 41,000 Acres

    Package III- 9,500Acres

    Package IV- 19,500 Acres

    Package VI- 2,50,000Acres

    TOTAL 3,20,000Acres

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    31/40

    Go To Contents

    31

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    32/40

    Go To Contents

    32

    3.4.1 Indira Sagar Dummugudem LIS

    The APTRANSCO has requested the department to deposit

    Rs.290.14 Crores towards the estimated cost of the

    transmission scheme for ISDLIS for providing 229.096 MW.

    The Chief Engineer during 09/2009 has addressed the

    Government for according permission to deposit the

    amount with APTRANSCO. In turn, the Government have

    communicated certain remarks, which were attended by

    the department during 01/2010 duly obtaining the data

    from the APTRANSCO. Later the Government have

    instructed to ascertain from APTRANSCO during 10/2010

    details of Phases in which the amount of Rs.290.14 Crores

    can be deposited with amount of each installment.

    Accordingly a report was submitted to the Government by

    the Chief Engineer during 11/2010. The Government vide

    G.O.Ms No.59, dt: 19-09-2011 have accorded permission

    to deposit the amount in 4 installments. Accordingly an

    amount of Rs.136.32 Crores was deposited during 02/2012

    for taking up the works of transmission scheme. There is

    no time lag in completion of the scheme from the govt. or

    department side.

    Hence, the para may be dropped.

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    33/40

    Go To Contents

    33

    3.4.2 Rajiv Dummugudem

    RDLIS: RDLIS: AP Transco agreed to provide

    220 KV and 132 KV transmission line and requested the

    I&CAD department to deposit an amount of Rs.175.35

    Crores, The Chief Engineer has requested the Government

    during 08/2010 to accord permission to deposit the

    amount. Replies to remarks of the Government were

    submitted during 03/2012 and permission is awaited.

    There is no time lag in completion of the scheme from the

    Government or department side.

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    34/40

    Go To Contents

    34

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    35/40

    Go To Contents

    35

    4.3 JPDNSS:

    DNSS: The WAPCos estimated and submitted power

    quirement in the DPR as 1565.4 MW for 6 pump houses

    JPDNSS. The actual power requirement calculated by I

    CAD Department for 6 pump houses is 1135.87 MW, for

    ich estimate is prepared and approved by the IBM

    mmittee. Information regarding number of pumps to be

    erated and month wise requirement will be submitted

    er approval of design of pumps and motors.

    nce, the para may be dropped.4.4 AVR Handri Niva Sujala Sravanti :

    NSS Project proposes to provide Irrigation facility to 6,

    ,500 Ac in the four districts of Rayalaseema and

    nking water to about 33 Lakh people living in urban

    eas like Dhone, Pattikonda, Guntakal, Kalyanadurg,

    yadurg, Dharmavaram, Puttaparthi, Kadiri,

    enukonda, Madakasira, Hindupur, Rayachoti,

    danapalli, Thambaplli, Vayalpad, Pileru, Palamaner,

    nganur, Pakala, Chittoor etc., and the rural areas

    route the canal using about 40 TMC of the flood waters

    the Krishna River. The Project is a lift Irrigation scheme

    awing the flood waters of the Krishna from the

    sailam Reservoir during the monsoon period. The flood

    ters of Krishna are proposed to be drawn from a point

    ar confluence of the Krishna and Tungabhadra Rivers in

    e fore-shore of the Srisailam Reservoir without affecting

    e other committed uses under Srisailam and below

    luding Nagarjuna Sagar and Krishna delta. water from

    e Reservoir will be drawn when the Reservoir level is

    66.67m and above, through an approach channel and

    ad regulator near Malyala village in Kurnool District and

    ed to EL +290.00m from there, the water will be

    nveyed through a system of gravity canals cum lifts.

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    36/40

    Go To Contents

    36

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    37/40

    Go To Contents

    37

    4.3.6 Adequacy of time for bidding:

    Adequate time has been provided to the Bidders for carrying out

    the preliminary survey and investigation before tendering

    depending upon the nature of work involved in the

    Project/package. Hence this is not a deviation from FIDIC model

    of EPC system and the contention of the audit that sufficient

    time is not provided to the Contractors towards preliminary

    survey and investigation before tendering is not correct.

    Indira Sagar Dummugudem Lift Irrigation scheme : The

    works of Indira Sagar Lift Irrigation scheme, except Pump

    houses were divided in to 3 packages and Tenders were called

    for in Tender No.2/2006-07, Dated.17.07.2006, in Cat.-I. Due

    to Technical problems Tenders of these packages were cancelled

    and were invited again vide Tender No.4/2006-

    07,Dated.27.10.2006.

    Financial Bids for Tender No.4/2006-07 were opened on

    dt.16.11.2006 and Bids received for package Nos.21 & 22 and

    there is no response for package No.23.

    The tender for package No.23 was again called in tender

    No.5/2006-07,Dated.18.11.2006. But, no response even for

    second call.

    Based on the instruction of the CE/GLIS, Warangal, the

    package No.23 is divided into small packages one package in

    Cat-I (package No.31) and three packages in Cat.-II (package

    Nos.49,50 &51) vide CE/GLIS, Warangal

    Lr.No.CE/GLIS/WGL/DCE/DEE/Camp-2, Dated.02.01.2007 as

    smaller packages may have response.

    Tenders were called for package Nos.31, 49, 50 & 51, in tender

    No. 6/2006-07,dated.06.01.2007 for package No.31 and tender

    No. 7/2006-07,dated.06.01.2007 for package Nos.49, 50 & 51.

    For the response of above tenders, single bids were received for

    31,50 & 51 and awarded

    Hence, the para may be dropped

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    38/40

    Go To Contents

    38

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    39/40

    Go To Contents

    39

    4.3.9 Payment schedules:

    In EPC System, payments are made to contractor as

    per Payment Schedule. The total work specified under EPC

    turn-key contract is divided into several components of

    work to facilitate payments component wise. The

    contractors bid price as approved shall be divided among

    the components of work as per respective percentage of

    total bid price. The payment for each of the componentworks shall be limited to the respective amounts arrived

    on the basis of percentages specified.

    Payment schedule can be revised (based on

    detailed investigation, drawings and detailed estimation)

    due to variance in estimate. For revision of payment

    schedule, Chief Engineer is empowered for changes from

    component to component and Superintending Engineer

    from sub-component to sub-component within the

    component duly keeping the total price bid value

    unaltered.

    Further from each bill, 7.50% of bill amount will be

    retained by Department until completion of whole work

    and on termination of contract in midway due to

    Contractors fault, all property at Site becomes

    Department property and any amount due to the

    Department will be treated as debt and will be recovered

    from agency with interest as per Agreement Clause.

    Hence the contractor may not leave the work midway

    because of revision of payment schedule at initial phases

    as pointed out by Audit and no loss will be caused to the

    public exchequer.

    Contractors are also allowed to revise Payment

    Schedules several times to their advantage

    resulting in front end payments. Such upward

    revision of costs for items executable in the initial

    phases would result in loss to public exchequer if

    the contracting agency stops the work midway.

    RDLIS:

    As per para 306(T) of AP Public works account code, the

  • 7/27/2019 Response-Audit Report on Jalayagnam-Vol.1

    40/40

    Go To Contents