Resource Planning and Scheduling

Embed Size (px)

Citation preview

  • 8/16/2019 Resource Planning and Scheduling

    1/29

    Resource Planning and

    Scheduling

    CSTM 462

    “Resource Loading” Fall 2012

  • 8/16/2019 Resource Planning and Scheduling

    2/29

    Schedule

    October 01/02- Resource Loading Lecture

    October 03/04- ASiMI Lab

    Week of October 08- No ClassDownload Software-Download instructionsgiven in October 03/04 Lab

    October 15/16- Midterm- Lectures 1-7- OpenNotes during exam

  • 8/16/2019 Resource Planning and Scheduling

    3/29

    Float

  • 8/16/2019 Resource Planning and Scheduling

    4/29

    Schedule – Typical Critical Path Method

  • 8/16/2019 Resource Planning and Scheduling

    5/29

    Schedule – “RACS” 

    Resource Allocation Control System

  • 8/16/2019 Resource Planning and Scheduling

    6/29

    Resource Loading

  • 8/16/2019 Resource Planning and Scheduling

    7/29

    Resource Curve

  • 8/16/2019 Resource Planning and Scheduling

    8/29

    Importance of Resource Planning

    and Scheduling

     A network schedule that does not include

    resource constraints assumes that an

    unlimited quantity of resources is available

    to the project. Schedules developedwithout resource constraints may not be

    feasible or realistic when actual resources

    are considered.

  • 8/16/2019 Resource Planning and Scheduling

    9/29

    The five categories of resource

    planning techniques.

    1. Resource Loading

    2. Resource Aggregation

    3. Resource Availability Analysis4. Resource-Constrained Scheduling

    5. Resource Leveling

  • 8/16/2019 Resource Planning and Scheduling

    10/29

    Resource Loading

    • Resource loading allows the planner to

    assign resources such as labor,

    equipment and materials to each activity in

    the project schedule.

    • These units might be craftsmen, pieces of

    equipment or quantities of construction

    materials.

    • Craftsmen or equipment the norm.

  • 8/16/2019 Resource Planning and Scheduling

    11/29

    Loading the Schedule

    Form Concrete

    Six Carpenters

    Fabricate Wall FormsEight Carpenters

    Set Wall Forms

    Five Carpenters

    6 6 6 6 14 14 14 8 8 8 13 13 5 5 5 5 5 5

  • 8/16/2019 Resource Planning and Scheduling

    12/29

    Resource Aggregation

    • Resource aggregation totals each type ofresource used in the schedule for each time unitbetween scheduled project start and finish.

    • Look at the early and late start and finish dates.

    • Remember your resource requirements for thecritical path doesn’t change only the floatactivities

    • You like to see a bell curve on your resource

    aggregation always keeping in mind the earlyand late dates on the items with float.

    • EX-Average daily manpower per week graph

  • 8/16/2019 Resource Planning and Scheduling

    13/29

    Resource Availability Analysis

    • Simply compares the amount of resources

    required to the maximum amount of

    resources that are available for use.

    • In the real world can we get more

    resources.

  • 8/16/2019 Resource Planning and Scheduling

    14/29

    Time-and-Resource-Constrained

    Scheduling

    • Time constrained or resource constrained.

    • Time use an end date.

    • Resources schedules the project onavailable resources.

  • 8/16/2019 Resource Planning and Scheduling

    15/29

    Resource Availability Analysis

    • Simply compares the amount of resources

    required to the maximum amount of resources

    that are available for use

    • In the real world can we get more resources.• When the assigned resources exceed those

    available:

     – Shift non-critical activities within the schedule

     – Obtain more resources

     – Extend the schedule to lower the demand during the

    original schedule.

  • 8/16/2019 Resource Planning and Scheduling

    16/29

     

  • 8/16/2019 Resource Planning and Scheduling

    17/29

    Time and Resource

    Constrained Scheduling• Schedules can be time constrained or

    resource constrained but not both.

     – Time use an end date

     – Resource schedules the project on available

    resources

    • Time- get more resources

    • Resource- a shortage extend the time

  • 8/16/2019 Resource Planning and Scheduling

    18/29

    Resource Leveling

    •  Attempts to keep the requirements for a construction resource asconstant as possible over the duration of the project.

    • Non-critical activities are shifted within the schedule using theavailable total float in order to level resource usage and the plannedproject completion date is unchanged as a result of the levelingprocess.

    • This techniques are used when the project duration is fixed.• Maximizing the effects of resource leveling requires performing both

    a backward and forward pass again through the network.

    • The primary objective is to reduce the peaks and valleys withoutincreasing the duration.

    • Delaying those activities to the last available space.• Use of algorithms and the software program for this class.

  • 8/16/2019 Resource Planning and Scheduling

    19/29

    Leveling

    Basically delaying the scheduled

    performance of non-critical activities .

    The daily total resource usage of the project

    decreases at the beginning of the project

    and increases at the end.

  • 8/16/2019 Resource Planning and Scheduling

    20/29

    Resource Curves

    • The bell shape

    • Leveling resources

    • Planning tool• Tracking Tool

  • 8/16/2019 Resource Planning and Scheduling

    21/29

     

    Resource Leveling

     – Some people in

    the industry find it

    too random

     – Look at loading

    and make

    changes

     – Getting

    appropriate

    information from

    you

    subcontractors.1

    2 3 4 5 6 7 8 9 10 11 12

    Before

    After0

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    Equivalent Person

    Time in Weeks

    Resource Profile Before & After Leveling

  • 8/16/2019 Resource Planning and Scheduling

    22/29

    Resource Curve

  • 8/16/2019 Resource Planning and Scheduling

    23/29

    Float & Resource Leveling

  • 8/16/2019 Resource Planning and Scheduling

    24/29

    Float & Resource Leveling

  • 8/16/2019 Resource Planning and Scheduling

    25/29

  • 8/16/2019 Resource Planning and Scheduling

    26/29

  • 8/16/2019 Resource Planning and Scheduling

    27/29

     Advanced Scheduling andMeasuring Productivity Workshop 27 

    Schedule – “RACS” Resource Allocation Control System

  • 8/16/2019 Resource Planning and Scheduling

    28/29

     Advanced Scheduling andMeasuring Productivity Workshop 28 

    Schedule

  • 8/16/2019 Resource Planning and Scheduling

    29/29