26
RESOURCE ALLOCATION Chapter#8 1

Resource Allocation Compatible

Embed Size (px)

Citation preview

Page 1: Resource Allocation Compatible

RESOURCE ALLOCATIONChapter#8

1

Page 2: Resource Allocation Compatible

Nature of resources2

Labour Equipment Materials Space Services Time Money

Page 3: Resource Allocation Compatible

Identifying resource requirements

3

List of resources required With their expected level of demand Resources:

Also includes those are not part of activity specific E.g. project manager, office stationary, office

space etc Allocate resources to critical activities

first

Page 4: Resource Allocation Compatible

Schedules

4

Activity schedule - indicating start and completion dates for each activity

Resource schedule - indicating dates when resources needed + level of resources

Cost schedule showing accumulative expenditure

Page 5: Resource Allocation Compatible

Resource allocation

5

Identify the resources needed for each activity and create a resource requirement list

Identify resource types - individuals are interchangeable within the group (e.g. ‘VB programmers’ as opposed to ‘software developers’)

Allocate resource types to activities and examine the resource histogram

Page 6: Resource Allocation Compatible

Methods used in allocating and scheduling resources

6

Precedence graph Activity bar chart Resource histograms

Page 7: Resource Allocation Compatible

Resource histogram:systems analysts

7

WEEK 1 2 3 4 5 6 7

1

2

3

4

5

STA

FF R

EQ

D.

Page 8: Resource Allocation Compatible

Resource smoothing

8

It is usually difficult to get specialist staff who will work odd days to fill in gaps – need for staff to learn about application etc

Staff often have to be employed for a continuous block of time

Therefore desirable to employ a constant number of staff on a project – who as far as possible are fully employed

Hence need for resource smoothing

Page 9: Resource Allocation Compatible

Resource smoothing

9

WEEK 1 2 3 4 5 6 7

1

2

3

4

5

STA

FF R

EQ

D.

8

Page 10: Resource Allocation Compatible

Procedure for resource leveling

1

3

2

4a,2

b,3c,5

(4)

(2)

(2)

a

b

c

1 2 3 4 5

days

8

6

4

2

0

wor

kers

a

c c

cb b

Page 11: Resource Allocation Compatible

After leveling

a

b

c

8

6

4

2

0w

orke

rs 1 2 3 4 5

days

a b

c

Page 12: Resource Allocation Compatible

12

Id. Duration (weeks)

Precedents

A 2B 2 AC 2 AD 2 BE 4 CF 1 C,D

Page 13: Resource Allocation Compatible

13

A

B D

E

F

C

Page 14: Resource Allocation Compatible

Bar chart14

A

BC

DE

F

Page 15: Resource Allocation Compatible

Histogram15

Page 16: Resource Allocation Compatible

After smoothing16

A

BC

DE

F

Page 17: Resource Allocation Compatible

Histogram after smoothing17

Page 18: Resource Allocation Compatible

Activity bar chart

SPM (5e) resource allocation© The McGraw-Hill Companies, 2009

18

Page 19: Resource Allocation Compatible

Resource histograms19

Page 20: Resource Allocation Compatible

20

Page 21: Resource Allocation Compatible

21

Page 22: Resource Allocation Compatible

Resource clashes

22

Where same resource needed in more than one place at the same time

can be resolved by: delaying one of the activities

taking advantage of float to change start date delaying start of one activity until finish of the

other activity that resource is being used on - puts back project completion

moving resource from a non-critical activity bringing in additional resource - increases

costs

Page 23: Resource Allocation Compatible

Prioritizing activities

23

There are two main ways of doing this: Total float priority – those with the

smallest float have the highest priority Ordered list priority – this considers a set

of simple criteria.

Page 24: Resource Allocation Compatible

Burman’s priority list

24

Give priority to: Shortest critical activities Other critical activities Shortest non-critical activities Non-critical activities with least float Non-critical activities

Page 25: Resource Allocation Compatible

Allocating individuals to activities

25

The initial ‘resource types’ for a task have to be replaced by actual individuals.

Factors to be considered: Availability Criticality Risk Training Team building – and motivation

Page 26: Resource Allocation Compatible

Cost Schedules26

Staff Costs Overheads Usages charges