Upload
kitty-himani-tyagi
View
218
Download
0
Embed Size (px)
Citation preview
RESOURCE ALLOCATIONChapter#8
1
Nature of resources2
Labour Equipment Materials Space Services Time Money
Identifying resource requirements
3
List of resources required With their expected level of demand Resources:
Also includes those are not part of activity specific E.g. project manager, office stationary, office
space etc Allocate resources to critical activities
first
Schedules
4
Activity schedule - indicating start and completion dates for each activity
Resource schedule - indicating dates when resources needed + level of resources
Cost schedule showing accumulative expenditure
Resource allocation
5
Identify the resources needed for each activity and create a resource requirement list
Identify resource types - individuals are interchangeable within the group (e.g. ‘VB programmers’ as opposed to ‘software developers’)
Allocate resource types to activities and examine the resource histogram
Methods used in allocating and scheduling resources
6
Precedence graph Activity bar chart Resource histograms
Resource histogram:systems analysts
7
WEEK 1 2 3 4 5 6 7
1
2
3
4
5
STA
FF R
EQ
D.
Resource smoothing
8
It is usually difficult to get specialist staff who will work odd days to fill in gaps – need for staff to learn about application etc
Staff often have to be employed for a continuous block of time
Therefore desirable to employ a constant number of staff on a project – who as far as possible are fully employed
Hence need for resource smoothing
Resource smoothing
9
WEEK 1 2 3 4 5 6 7
1
2
3
4
5
STA
FF R
EQ
D.
8
Procedure for resource leveling
1
3
2
4a,2
b,3c,5
(4)
(2)
(2)
a
b
c
1 2 3 4 5
days
8
6
4
2
0
wor
kers
a
c c
cb b
After leveling
a
b
c
8
6
4
2
0w
orke
rs 1 2 3 4 5
days
a b
c
12
Id. Duration (weeks)
Precedents
A 2B 2 AC 2 AD 2 BE 4 CF 1 C,D
13
A
B D
E
F
C
Bar chart14
A
BC
DE
F
Histogram15
After smoothing16
A
BC
DE
F
Histogram after smoothing17
Activity bar chart
SPM (5e) resource allocation© The McGraw-Hill Companies, 2009
18
Resource histograms19
20
21
Resource clashes
22
Where same resource needed in more than one place at the same time
can be resolved by: delaying one of the activities
taking advantage of float to change start date delaying start of one activity until finish of the
other activity that resource is being used on - puts back project completion
moving resource from a non-critical activity bringing in additional resource - increases
costs
Prioritizing activities
23
There are two main ways of doing this: Total float priority – those with the
smallest float have the highest priority Ordered list priority – this considers a set
of simple criteria.
Burman’s priority list
24
Give priority to: Shortest critical activities Other critical activities Shortest non-critical activities Non-critical activities with least float Non-critical activities
Allocating individuals to activities
25
The initial ‘resource types’ for a task have to be replaced by actual individuals.
Factors to be considered: Availability Criticality Risk Training Team building – and motivation
Cost Schedules26
Staff Costs Overheads Usages charges