72
Module 2 Resource Requirements

Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

Module 2

Resource Requirements

Page 2: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

3

• Resource Entity Responsibilities

• QSE Responsibilities

• Special Resource Requirements

• Resource Nodes

Topics in this module ...

Module Topics

Page 3: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

4

The ERCOT Market Environment

Page 4: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

5

Resource Entity

Resource Entity Responsibilities

• Resource Registration• Outage Scheduling (sort-of)

Resource Entity Responsibilities

• Resource Registration• Outage Scheduling

Page 5: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

6

Each Resource Entity shall provide ERCOT with information describing each of its All-Inclusive Resources connected to the transmission system.

Resource Asset Registration Form (RARF)

• Resource planning and model data

• Generation substation model data

• Resource Parameters

Resource Registration

Page 6: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

7

• Used to form Resource Constraints in ERCOT processes

• Day-Ahead Market

• Reliability Unit Commitment

• Security Constrained Economic Dispatch

• Load Frequency Control

• The Resource Entity’s QSE may update when justifiable

Resource Parameters

Resource Registration

Page 7: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

8

Generation Resource Parameters

Resource Registration

Parameter Names

Normal and Emergency Ramp Rate Curves

Minimum and Maximum On-Line Times

Minimum Off-Line Time

Hot, Intermediate and Cold Start Times

Hot-to-Intermediate Time

Intermediate-to-Cold Time

Maximum Daily Starts

Maximum Weekly Starts

Maximum Weekly Energy

Page 8: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

9

Load Resource Parameters

Resource Registration

Parameter Names

Minimum and Maximum Interruption Times

Minimum Notice Time

Minimum Restoration Time

Maximum Daily Deployments

Maximum Weekly Deployments

Maximum Weekly Energy

Page 9: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

10

Controllable Load Resource Parameters

Resource Registration

Parameter Names

Normal and Emergency Ramp Rate Curves

Maximum Deployment Time

Maximum Weekly Energy

Page 10: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

11

• Four Curves

• Normal Up & Down

• Emergency Up & Down

• Ten segments/steps per curve

• Defined by breakpoints

• No zero or negative values

A Few Words on Ramp Rates

Resource Registration

QSE must send telemetered Ramp Rates in Real-Time. Registered values are back-up.

Page 11: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

12

Generation Interconnect or Change Request (GINR)

• Connect new All-Inclusive Generation Resource of ten MW or greater

• Upgrade Net Dependable Capability

• Change Point of Interconnect (POI)

Standard Generation Interconnect agreement (SGIA)

• Negotiated with Transmission Service Provider

• Signed copy provided to ERCOT

Registration Flow and Timing

Planning Guide

Details in Section 5

Page 12: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

13

Registration Flow and Timing

Screening Study

Full Interconnect

StudyGINR Signed

SGIA

Initial Full

Operations Model

Planning Model

At least 90 days prior to first month in model

Typically 2 years from GINR to Energization

Page 13: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

14

Registration Flow and Timing

Screening Study

Full Interconnect

StudyGINR Signed

SGIA

Initial Full

Operations Model

Planning Model

At least 90 days prior to first month in model

Full

120 daysFor best results, submit

Full RARF early

Page 14: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

15

Resource Entity

Resource Entity Responsibilities

• Resource Registration• Outage Scheduling

Page 15: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

16

Each Resource Entity shall provide a rolling 12 month Resource Outage Plan with continuous updates.

Outage Scheduler entries include

• Estimated start and stop times

• Earliest start time and latest finish time

• Nature of work to be performed

Outage Scheduling

Page 16: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

17

Each Resource Entity shall provide a rolling 12 month Resource Outage Plan with continuous updates.

Also applies to RE-Owned Transmission Elements

Outage Scheduling

ST1 CT1 CT2

OOO

TSP-SystemResource Entity-Owned

Page 17: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

18

Outage Scheduling

Companies must designate a Single Point of Contact for all ERCOT communications regarding Outage Scheduling.

Resource Entity must designate their QSE

• QSE responsible for Outage Scheduler

• QSE acts on behalf of Resource Entity

Page 18: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

19

Outage Request lead time

ERCOT Action

More than 45 days ERCOT shall accept or reject, but may discuss alternatives to minimize reliability and cost impact.

9 to 45 days ERCOT must approve/accept or reject within 5 business days after submission.

4 to 8 days ERCOT shall approve/accept or reject by 1800 hours, 3 days prior to the Outage

3 days ERCOT shall approve/accept or reject by 1800 hours, 2 days prior to the Outage

ERCOT approves or rejects Outage Requests

Response time for Outage Requests

Page 19: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

20

Outage Request lead time

ERCOT Action

More than 45 days ERCOT shall approve or reject no later than 30 days prior to the Outage

No less than 30 days ERCOT shall approve or reject no later than 15 days prior to the Outage

Different requirements for Black Start and Reliability Must Run Resources

Response time for Reliability Resource Outage Requests

RMR

Page 20: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

21

Qualified Scheduling Entity (QSE)

QSE Responsibilities

• Offers• Current Operating Plan• Telemetry• Financial Settlement• Creditworthiness

QSE Responsibilities

• Offers• Current Operating Plan• Telemetry• Financial Settlement• Creditworthiness

Page 21: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

22

Resource Offers

Three-Part Supply Offer

22

Energy Offer Curve can be submitted without Start-up or Minimum Energy Offers

Minimum Energy OfferStartup Offer Energy Offer Curve$/MWh

MW

$/Start

$/MWh

Page 22: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

23

• Block offers• Single Price and Quantity• Fixed or Variable

• Single Resource may be offered for multiple Services

Ancillary Service (AS) Offers:

Resource Offers

Fixed Quantity Block

$ / M

W

MW

Variable Quantity Block

$ / M

W

MW

Page 23: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

24

Qualified Scheduling Entity (QSE)

QSE Responsibilities

• Offers• Current Operating Plan• Telemetry• Financial Settlement• Creditworthiness

Page 24: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

25

Current Operating Plan

ResourceName Hour Resource

Status Resource Limits AS Resource Responsibility

BIGGEN 1 20

BIGGEN 2 20

LTLGEN 1 20

BIGLOAD 1 20

QSE must maintain a COP • For each hour of the next 7 days• For each Resource they represent

Page 25: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

26

Current Operating Plan

ResourceName Hour Resource

Status Resource Limits AS Resource Responsibility

BIGGEN 1 20 ONREG

BIGGEN 2 20 ON

LTLGEN 1 20 OFFNS

BIGLOAD 1 20 ONCLR

QSE must maintain a COP • For each hour of the next 7 days• For each Resource they represent

Page 26: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

27

Generation Resources Planning to be Off-Line

Current Operating Plan Resource Status

Status Description

OFF Off-Line but available for commitment

OFFQS Off-Line but available for SCED Dispatch as a Quick Start Generation Resources

OFFNS Off-Line but reserved for Non-Spin

EMR Available for commitment as RMR, or for ERCOT-declared Emergency Conditions

OUT Off-Line and unavailable

Page 27: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

28

Generation Resources Planning to be On-Line

Current Operating Plan Resource Status

Status Description

ON On-Line with Energy Offer Curve

ONREG On-Line with Energy Offer Curve and providing Regulation Service

ONOS On-Line with Output Schedule

ONRR On-Line as a synchronous condenser

ONRUC On-Line for RUC-Committed hour

ONOPTOUT On-Line for RUC Buy-Back hour

ONTEST On-Line for operational testing

ONEMR On-Line EMR

Page 28: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

29

Load Resources

Current Operating Plan Resource Status

Status Description

ONRL Available for Dispatch of Responsive Reserve Service

ONCLR Controllable Load Resource available for Dispatch by SCED with a Real-Time Market Energy Bid

ONRGL Controllable Load Resource available for Regulation Service, with any remaining capacity available for Dispatch by SCED with a Real-Time Market Energy Bid

OUTL Not available

Page 29: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

30

Current Operating Plan

ResourceName Hour Resource

Status Resource Limits AS Resource Responsibility

BIGGEN 1 20 ONREG

BIGGEN 2 20 ON

LTLGEN 1 20 OFFNS

BIGLOAD 1 20 ONCLR

QSE must maintain a COP • For each hour of the next 7 days• For each Resource they represent

ResourceName Hour Resource

StatusResource Limits

AS Resource ResponsibilityHEL HSL LSL LEL

BIGGEN 1 20 ONREG 770 750 50 40

BIGGEN 2 20 ON 800 750 50 40

LTLGEN 1 20 OFFNS 110 100 20 15

BIGLOAD 1 20 ONCLR 80 80 30 30

Page 30: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

31

Current Operating Plan Resource Limits

COP limits are bounded by

Reasonability LimitsCOPRARF Resource

Capacity

High Reasonability Limit (HRL)

High Emergency Limit (HEL)

High Sustained Limit (HSL)

Low Sustained Limit (LSL)

Low Emergency Limit (LEL)Low Reasonability Limit (LRL)

Page 31: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

32

Limit DefinitionHigh Reasonability Limit A value above which the Resource is not expected

to operate under most conceivable conditions.High Emergency Limit Maximum temporary production capability of

Resource. Achievable for at least 30 minutes.High Sustained Limit Maximum sustained production capability of

ResourceLow Sustained Limit Minimum sustained production capability of

ResourceLow Emergency Limit Minimum temporary production capability of

Resource. Achievable for at least 30 minutes.Low Reasonability Limit A value below which the Resource is not expected

to operate under most conceivable conditions.

Limit Definitions

Current Operating Plan Resource Limits

Page 32: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

33

Current Operating Plan

ResourceName Hour Resource

StatusResource Limits

AS Resource ResponsibilityHEL HSL LSL LEL

BIGGEN 1 20 ONREG 770 750 50 40

BIGGEN 2 20 ON 800 750 50 40

LTLGEN 1 20 OFFNS 110 100 20 15

BIGLOAD 1 20 ONCLR 80 80 30 30

ResourceName Hour Resource

StatusResource Limits AS Resource Responsibility

HEL HSL LSL LEL Reg-up Reg-Down Responsive Non-Spin

BIGGEN 1 20 ONREG 770 750 50 40 10 10 150 0

BIGGEN 2 20 ON 800 750 50 40 0 0 100 0

LTLGEN 1 20 OFFNS 110 100 20 15 0 0 0 100

BIGLOAD 1 20 ONCLR 80 80 30 30 0 0 0 0

QSE must maintain a COP • For each hour of the next 7 days• For each Resource they represent

Page 33: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

34

Reflects:

• Self-Arranged Quantities

• Ancillary Service Trades

• Ancillary Services sold in Day-Ahead Market

AS Resource Responsibility indicates the amount of each Ancillary Service the QSE plans to carry on each Resource

Current Operating Plan AS Resource Responsibility

Which Resources?

Page 34: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

35

Scenario 1

Current Operating Plan

• Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin

• Generation Resource IMCHEIPR provides 30 MW of Reg-Up

• Load Resource WGTMKR provides 50MW of Responsive Reserve

Complete the QSE’s Current Operating Plan on the next slide

A QSE intends to commit their Resources for an Operating Hour as follows:

Let’s see now…

Page 35: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

36

Scenario 1

Current Operating Plan

A QSE intends to commit their Resources for an Operating Hour as follows:

ResourceName Hour Resource

StatusResource Limits AS Resource Responsibility

HEL HSL LSL LEL Reg-up Reg-Down Responsive Non-Spin

IMXPNSVE 18 OFFNS 108 100 20 17 0 0 0 100

IMCHEIPR 18 ONREG 620 600 50 40 30 0 0 0

WGTMKR 18 ONRL 75 75 25 25 0 0 50 0

Page 36: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

37

Qualified Scheduling Entity (QSE)

QSE Responsibilities

• Offers• Current Operating Plan• Telemetry• Financial Settlement• Creditworthiness

Page 37: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

38

Resource Real-Time communications

Telemetry

ERCOT Wide-Area Network

QSE Control Systems

ICCP

SCADA

ERCOT Systems

SCADA

QSEs communicate with ERCOT through Inter-Control Center Protocol (ICCP)

• SCADA telemetry from Resources• ERCOT instructions to Resources

Page 38: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

39

ICCP Data Quality Codes

Telemetry

Normal Value

Current Source

Validity

ERCOT Wide-Area Network

QSE Control Systems

ICCP

SCADA

ERCOT Systems

SCADA

For status indications only

Requirements vary by circumstance• Data Type• QSE to ERCOT• ERCOT to QSE

Page 39: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

40

ICCP Data Quality Codes

Telemetry

Category General Values

Validity

VALIDHELDSUSPECTNOT_VALID

Current Source

TELEMETEREDCALCULATEDMANUALESTIMATED

NormalValue

Current state is NORMALCurrent state is ABNORMAL

ICCP Handbook

Details in ERCOT ICCP Handbook

Page 40: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

41

Qualified Scheduling Entity (QSE)

QSE Responsibilities

• Offers• Current Operating Plan• Telemetry• Financial Settlement• Creditworthiness

Page 41: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

42

• ERCOT settles with QSE

• QSE settles with Resource Entity

• QSE responsible for any Creditworthiness impactswith ERCOT

QSE Settles with ERCOT and Resource Entity

Financial Settlements and Creditworthiness

Page 42: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

Special Resource Requirements

Page 43: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

44

Topics in this Section Include

Special Resource Requirements

Combined Cycle Generation Resources1

2 Split Generation Resources

3 Quick Start Generation Resources

Page 44: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

45

• Combination of Combustion Turbines (CT) with heat recovery Steam Turbines (ST)

• Operates in one or more configurations

Combined Cycle Train (CCT)

Combined Cycle Generation Resources

My Combined Cycle Train

ST CT1 CT2 CT3

Page 45: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

46

• A registered configuration of a Combined Cycle Train

• Treated as a single Resource

• Offers

• Commitment

• Dispatch

• Settlement

Combined Cycle Generation Resource (CCGR)

Combined Cycle Generation Resources

MyCCT_3

My Combined Cycle Train

ST CT1 CT2 CT3

MyCCT_4

Page 46: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

47

Resource Entity registers all desired configurations

Combined Cycle Generation Resources

ConfigurationsConfiguration Codes

MyCCT_1 MyCCT_2 MyCCT_3 MyCCT_4

Uni

tsIn

clud

ed

CT1 X X X XCT2 Alt Alt X XCT3 Alt Alt Alt XST X X X

Page 47: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

48

Resource Entity must also provide Transition Matrix

Combined Cycle Generation Resources

Allowable Transitions

To Configuration

Offline MyCCT_1 MyCCT_2 MyCCT_3 MyCCT_4

From

C

onfig

urat

ion

Offline X XMyCCT_1 X X XMyCCT_2 X X X XMyCCT_3 X X XMyCCT_4 X X

Page 48: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

49

ResourceName Hour Resource

StatusResource Limits AS Resource Responsibility

HEL HSL LSL LEL Reg-up Reg-Down Responsive Non-Spin

MyCCT_1 20 OFF 110 100 50 50 0 0 0 0

MyCCT_2 20 ON 165 150 75 75 0 0 0 0

MyCCT_3 20 OFF 330 300 150 150 0 0 0 0

MyCCT_4 20 OFF 495 450 225 225 0 0 0 0

QSE submits COP for each registered CCGR

Combined Cycle Train Current Operating Plan

Only one CCGR from a Combined Cycle Train may be shown as on-line during a given hour

Page 49: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

50

• Configuration Number (1, 2, 3, 4, etc)

• Resource Limits for configuration

• Ramp Rates for configuration

• Ancillary Services provided

QSE provides telemetry at the Train level

Combined Cycle Train Telemetry

QSE Control Systems

ICCP ERCOT SystemsSCADA

Page 50: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

51

• Power output (MW and MVAR)

• Resource breaker and switch status

• Other operational data*

… and also at the individual unit level

Combined Cycle Train Telemetry

QSE Control Systems

ICCP ERCOT SystemsSCADA

* See Protocol 6.5.5.2 for details

Page 51: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

52

The DreamSteam combined cycle plant is registered as follows:

Scenario 2

Combined Cycle Generation Resources

ConfigurationsConfiguration Codes

MyCCT_1 MyCCT_2 MyCCT_3

Uni

tsIn

clud

ed CT1 X X X

CT2 Alt Alt X

ST X X

Allowable Transitions

To ConfigurationOffline MyCCT_1 MyCCT_2 MyCCT_3

From

C

onfig

urat

ion Offline X

MyCCT_1 X X

MyCCT_2 X X

MyCCT_3 X

Page 52: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

53

DreamSteam’s QSE plans to start the Resource at 0900

Scenario 2

Combined Cycle Generation Resources

If DreamSteam is running only the CT1 unit, can ERCOT instruct DreamSteam to simultaneously start both the CT2 and ST units?

Can ERCOT instruct DreamSteam to simultaneously start the CT1, CT2 and ST units at 0700?

DreamSteam

ST CT1 CT2

Page 53: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

54

Topics in this Section Include

Special Resource Requirements

Combined Cycle Generation Resources1

2 Split Generation Resources

3 Quick Start Generation Resources

Page 54: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

55

• Single physical Resource that is not a Combined Cycle Train

• Meter output split across multiple owners

• Each split modeled as a separate Resource

• Each owner may have separate QSE

What is a Split Generation Resource?

Split Generation Resources

M

Physical Resource

Page 55: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

56

• Each Resource Entity registers their portion

• Resource Parameters must be consistent

• Limits and Ramp Rates appropriate for each split

• Temporal values identical across all splits

Setting up a Split Generation Resource

Split Generation Resources

M

Page 56: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

57

• Serves as the Single Point of Contact

• Provides real-time telemetry for total physical Resource

• May or may not be one of the controlling QSEs

Resource Entities shall designate a Master QSE

Split Generation Resources

M

Physical Resource

Page 57: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

58

• All related Split Generation Resources must be committed or decommitted together

• In case of status conflicts,

• If one SGR is “OUT,” all are “OUT”

• Else, if one SGR is “ON,” all are “ON”

Each QSE maintains COP for their split

Split Generation Resources Current Operating Plan

M

Page 58: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

59

Master QSE telemeters required data for total physical Resource

Each QSE telemeters required data for their split

Split Generation Resource Telemetry Requirements

ERCOT Systems

M

ICCP

Master

ICCP

ICCP

ERCOT checks for consistency and notifies QSEs of any errors

Page 59: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

60

Topics in this Section Include

Special Resource Requirements

Combined Cycle Generation Resources1

2 Split Generation Resources

3 Quick Start Generation Resources

Page 60: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

61

• A Generation Resource that can come online from a cold state within ten minutes

• Must qualify by test

• Receive deployment instruction from ERCOT

• Qualified MW is observed output 10 minutes after instruction

Quick Start Generation Resource (QSGR)

Quick Start Generation Resources

QSGR

Page 61: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

62

ResourceName Hour Resource

StatusResource Limits AS Resource Responsibility

HEL HSL LSL LEL Reg-up Reg-Down Responsive Non-Spin

QSGR1 20 OFFQS 55 50 20 20 0 0 0 0

QSGR2 20 OFFQS 55 50 20 20 0 0 0 30

QSGR3 20 OFFQS 85 80 0 0 0 0 0 80

QSE submits COP for QSGR

Quick Start Generation Resource Current Operating Plan

With Status of “OFFQS,” Resource will remain offline until

• Dispatched by SCED

• Started by QSE

Page 62: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

63

• Resource Status of OFFQS

• Breaker Status of Open

• Ramp Rate = (Qualified 10 min MW) / 5 min

• LSL = 0

Waiting for Dispatch by SCED

Quick Start Generation Resource Telemetry Requirements

QSGR

Page 63: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

64

• Resource Status of ON

• Breaker Status of Closed

• LSL less than actual output until reaching actual LSL

After Dispatch by SCED

Quick Start Generation Resource Telemetry Requirements

Page 64: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

65

• Once SCED brings QSGR Basepoint back to LSL

• Set LSL=0

• Ramp Rate must allow dispatch to zero in 5 min

• Non-zero Basepoint

• QSGR is still needed

• Resume normal LSL

Decommitment Process

Quick Start Generation Resource Telemetry Requirements

QSGR

QSE may test no more than two non-consecutive SCED executions in an

Operating Hour

Page 65: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

66

• Once SCED brings QSGR Basepoint back to LSL

• Set LSL=0

• Ramp Rate must allow dispatch to zero in 5 min

• Zero Basepoint

• QSGR no longer needed

• May shut down normally

Decommitment Process

Quick Start Generation Resource Telemetry Requirements

QSGR

Page 66: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

Resource Nodes

Page 67: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

68

• A type of Settlement Point

• The point where a Resource is• Offered• Priced• Financially settled

• Typically defined by “First Fork” rule

Resource Nodes

What is a Resource Node?

EPS Meter Resource Node

Page 68: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

69

• Each configuration treated as a single Resource

• Could operate in multiple configurations over the day

• Need a “one size fits all” Settlement Point

Resource Nodes

But what about Combined Cycle Trains?

EPS Meter Resource Node

ST1 CT1 CT2

Page 69: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

70

Provides a single point where all configurations are

• Offered• Priced• Financially settled

Resource Nodes

Introducing, the Logical Resource Node …

EPS Meter Resource Node

Logical Resource Node

Each Combined Cycle Train has a unique

Logical Resource NodeST1 CT1 CT2

Page 70: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

71

• Still have physical Resource Nodes• CCU Resource Nodes• First fork rule

• All CCU Resource Nodes are mapped to Logical Resource Node

Resource Nodes

Introducing, the Logical Resource Node …

EPS Meter Combined Cycle Unit (CCU) Resource Node

Logical Resource Node

ST1 CT1 CT2

Page 71: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

72

Transactions at Resource Nodes and other Settlement Points

Transaction

Settlement Point3PSO CCGR

3PSO

DAM Energy

Only Offer

DAM Energy Bid

PTP Obligation Bids

QSE to QSE Trades

Resource Node X X X X X

CCP Logical Resource Node X

CCU Resource Node X X X X

Load Zone X X X X

Hub X X X X

Notes:1. CCP = Combined Cycle Plant2. CCU = Combined Cycle Unit3. 3PSO = Three Part Supply Offer4. CCGR = Combined Cycle Generation Resource

Page 72: Resource Requirements · • Generation Resource IMXPNSVE provides its entire capacity as Offline Non-Spin • Generation Resource IMCHEIPR provides 30 MW of Reg-Up • Load Resource

73

• Resource Entity Responsibilities

• QSE Responsibilities

• Special Resource Requirements

• Resource Nodes

You’ve learned about ...

Summary