ID Task Mode Task Name Duration Start Finish 0 Residential Construction 152 days Wed 4/27/16 Thu 11/24/16 1 General Conditions 21 days Wed 4/27/16 Wed 5/25/16 2 Finalize plans and develop estimate with owner, architect 20 days Wed 4/27/16 Tue 5/24/16 3 Sign contract and notice to proceed 1 day Wed 5/25/16 Wed 5/25/16 4 Apply for Permits 0 days Wed 5/25/16 Wed 5/25/16 5 Secure foundation permit 0 days Wed 5/25/16 Wed 5/25/16 6 Secure framing permit 0 days Wed 5/25/16 Wed 5/25/16 7 Secure electrical permit 0 days Wed 5/25/16 Wed 5/25/16 8 Secure plumbing permit 0 days Wed 5/25/16 Wed 5/25/16 9 Secure HVAC permit 0 days Wed 5/25/16 Wed 5/25/16 General contractor[50%],Architec General contractor,Architect,Own 5/25 5/25 5/25 5/25 5/25 5/25 S T M F T S W S T Apr 10, '16 May 8, '16 Jun 5, '16 Jul 3, '1 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress Page 1 Project: Residential Constructio Date: Wed 4/27/16

Residential Construction

Embed Size (px)

Citation preview

Page 1: Residential Construction

ID Task

Mode

Task Name Duration Start Finish

0 Residential Construction

152 days Wed 4/27/16

Thu 11/24/16

1 General Conditions 21 days Wed 4/27/16Wed 5/25/16

2 Finalize plans and develop estimate with owner, architect

20 days Wed 4/27/16

Tue 5/24/16

3 Sign contract and notice to proceed

1 day Wed 5/25/16

Wed 5/25/16

4 Apply for Permits

0 days Wed 5/25/16

Wed 5/25/16

5 Secure foundation permit

0 days Wed 5/25/16

Wed 5/25/16

6 Secure framing permit

0 days Wed 5/25/16

Wed 5/25/16

7 Secure electrical permit

0 days Wed 5/25/16

Wed 5/25/16

8 Secure plumbing permit

0 days Wed 5/25/16

Wed 5/25/16

9 Secure HVAC permit

0 days Wed 5/25/16

Wed 5/25/16

General contractor[50%],Architect[50%],Owner[12%],Mortgage lender[12%]

General contractor,Architect,Owner,Mortgage lender

5/25

5/25

5/25

5/25

5/25

5/25

S T M F T S W S T M

Mar 13, '16 Apr 10, '16 May 8, '16 Jun 5, '16 Jul 3, '16

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 1

Project: Residential Constructio

Date: Wed 4/27/16

Page 2: Residential Construction

ID Task

Mode

Task Name Duration Start Finish

10 Secure miscellaneouspermits

0 days Wed 5/25/16

Wed 5/25/16

11 Site Work 3 days Thu 5/26/16 Mon 5/30/16

12 Clear and grub lot

1 day Thu 5/26/16 Thu 5/26/16

13 Install temporary power service

1 day Fri 5/27/16 Fri 5/27/16

14 Install underground utilities

1 day Mon 5/30/16

Mon 5/30/16

15 Foundation 42 days Tue 5/31/16 Wed 7/27/16

16 Excavate for foundations

3 days Tue 5/31/16 Thu 6/2/16

17 Form basement walls

13 days Fri 6/3/16 Tue 6/21/16

18 Place concrete for foundations & basement walls

12 days Wed 6/22/16

Thu 7/7/16

19 Cure basement walls for 7 days

7 days Fri 7/8/16 Mon 7/18/16

20 Strip basement wall forms

2 days Tue 7/19/16 Wed 7/20/16

21 Waterproof/insulatebasement walls

2 days Thu 7/21/16 Fri 7/22/16

5/25

Site excavation contractor

Electric company

Electric contractor,Plumbing contractor

Site excavation contractor

Concrete contractor

Concrete contractor

Concrete contractor

Concrete contractor

S T M F T S W S T M

Mar 13, '16 Apr 10, '16 May 8, '16 Jun 5, '16 Jul 3, '16

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 2

Project: Residential Constructio

Date: Wed 4/27/16

Page 3: Residential Construction

ID Task

Mode

Task Name Duration Start Finish

22 Perform foundation inspection

1 day Mon 7/25/16

Mon 7/25/16

23 Backfill foundation

2 days Tue 7/26/16 Wed 7/27/16

24 Framing 22 days Thu 7/28/16 Fri 8/26/16

25 Install 1st floor joists

2 days Thu 7/28/16 Fri 7/29/16

26 Lay 1st floor decking

2 days Mon 8/1/16 Tue 8/2/16

27 Frame 1st floor walls

4 days Wed 8/3/16 Mon 8/8/16

28 Frame 1st floor corners

1 day Tue 8/9/16 Tue 8/9/16

29 Install 2nd floor joists

2 days Wed 8/10/16

Thu 8/11/16

30 Frame 2nd floor decking

2 days Fri 8/12/16 Mon 8/15/16

31 Frame 2nd floor walls

3 days Tue 8/16/16 Thu 8/18/16

32 Frame 2nd floor corners

2 days Fri 8/19/16 Mon 8/22/16

33 Complete roof framing

3 days Tue 8/23/16 Thu 8/25/16

34 Conduct framinginspection

1 day Fri 8/26/16 Fri 8/26/16

Inspector

Site excavation contractor

Framing contractor

Framing contractor

Framing contractor

Framing contractor

Framing contractor

Framing contractor

Framing contractor

Framing contractor

Framing contractor

Inspector

S T M F T S W S T M

Mar 13, '16 Apr 10, '16 May 8, '16 Jun 5, '16 Jul 3, '16

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 3

Project: Residential Constructio

Date: Wed 4/27/16

Page 4: Residential Construction

ID Task

Mode

Task Name Duration Start Finish

35 Dry In 22 days Fri 8/26/16 Mon 9/26/16

36 Install 1st floor sheathing

3 days Mon 8/29/16

Wed 8/31/16

37 Install 2nd floor sheathing

3 days Thu 9/1/16 Mon 9/5/16

38 Install roof decking

3 days Fri 8/26/16 Tue 8/30/16

39 Install felt, flashing and shingles

3 days Tue 9/13/16 Thu 9/15/16

40 Hang 1st floor exterior doors

1 day Fri 9/16/16 Fri 9/16/16

41 Install 1st floor windows

3 days Mon 9/19/16

Wed 9/21/16

42 Install 2nd floor windows

3 days Thu 9/22/16 Mon 9/26/16

43 Exterior Finishes 19 days Tue 9/27/16 Fri 10/21/16

44 Complete exterior brick

16 days Tue 9/27/16 Tue 10/18/16

45 Complete exterior siding

3 days Wed 10/19/16

Fri 10/21/16

46 Utility Rough-B97Ins and Complete Concrete

21 days Wed 8/31/16

Wed 9/28/16

47 Rough-in plumbing

5 days Tue 9/6/16 Mon 9/12/16

Framing contractor

Framing contractor

Framing contractor

Roofing contractor

Framing contractor

Framing contractor

Framing contractor

Masonry contractor

Plumbing contractor

S T M F T S W S T M

Mar 13, '16 Apr 10, '16 May 8, '16 Jun 5, '16 Jul 3, '16

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 4

Project: Residential Constructio

Date: Wed 4/27/16

Page 5: Residential Construction

ID Task

Mode

Task Name Duration Start Finish

48 Conduct rough-in plumbing inspection

1 day Tue 9/13/16 Tue 9/13/16

49 Place concrete for basement floor

11 days Wed 9/14/16

Wed 9/28/16

50 Rough-in electrical

5 days Tue 9/6/16 Mon 9/12/16

51 Conduct rough-in electrical inspection

1 day Tue 9/13/16 Tue 9/13/16

52 Rough-in HVAC 3 days Wed 9/14/16Fri 9/16/16

53 Conduct rough-in HVAC inspection

1 day Mon 9/19/16

Mon 9/19/16

54 Rough-in communication - phone, cable, computer, alarm

2 days Wed 8/31/16

Thu 9/1/16

55 Interior Finishes 30 days Tue 9/27/16 Mon 11/7/16

56 Insulation 11 days Tue 9/27/16 Tue 10/11/16

57 Place wall insulation - 1st floor

1 day Tue 9/27/16 Tue 9/27/16

Inspector

Concrete contractor

Electric contractor

Inspector

Heating and AC contractor

Inspector

Electric contractor

Insulation contractor

S T M F T S W S T M

Mar 13, '16 Apr 10, '16 May 8, '16 Jun 5, '16 Jul 3, '16

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 5

Project: Residential Constructio

Date: Wed 4/27/16

Page 6: Residential Construction

ID Task

Mode

Task Name Duration Start Finish

58 Place wall insulation - 2nd floor

1 day Wed 9/28/16

Wed 9/28/16

59 Place ceiling insulation - 2nd floor

1 day Mon 10/10/16

Mon 10/10/16

60 Conduct insulation inspection

1 day Tue 10/11/16

Tue 10/11/16

61 Drywall 9 days Wed 9/28/16Mon 10/10/16

62 Install drywall- 1st floor walls

2 days Wed 9/28/16

Thu 9/29/16

63 Install drywall- 1st floor overhead

2 days Fri 9/30/16 Mon 10/3/16

64 Install drywall2nd floor walls

2 days Tue 10/4/16 Wed 10/5/16

65 Install drywall2nd floor overhead

2 days Thu 10/6/16 Fri 10/7/16

66 Tape and float1st floor drywall

1 day Tue 10/4/16 Tue 10/4/16

Insulation contractor

Insulation contractor

Inspector

Drywall contractor

Drywall contractor

Drywall contractor

Drywall contractor

Drywall contractor

S T M F T S W S T M

Mar 13, '16 Apr 10, '16 May 8, '16 Jun 5, '16 Jul 3, '16

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 6

Project: Residential Constructio

Date: Wed 4/27/16

Page 7: Residential Construction

ID Task

Mode

Task Name Duration Start Finish

67 Tape and float2nd floor drywall

1 day Mon 10/10/16

Mon 10/10/16

68 Paint and Wallpaper

17 days Wed 10/5/16

Thu 10/27/16

69 Texture all except entry and kitchen - 1st floor

1 day Wed 10/5/16

Wed 10/5/16

70 Paint all except entry and kitchen - 1st floor

1 day Thu 10/6/16 Thu 10/6/16

71 Hang wallpaper entry and kitchen - 1st floor

1 day Fri 10/7/16 Fri 10/7/16

72 Texture all - 2nd floor

1 day Thu 10/6/16 Thu 10/6/16

73 Paint all - 2nd floor

1 day Fri 10/7/16 Fri 10/7/16

74 Paint exterior siding & trim work

4 days Mon 10/24/16

Thu 10/27/16

75 Cabinets 6 days Mon 10/10/16Mon 10/17/16

Drywall contractor

Painting contractor

Painting contractor

Painting contractor

Painting contractor

Painting contractor

S T M F T S W S T M

Mar 13, '16 Apr 10, '16 May 8, '16 Jun 5, '16 Jul 3, '16

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 7

Project: Residential Constructio

Date: Wed 4/27/16

Page 8: Residential Construction

ID Task

Mode

Task Name Duration Start Finish

76 Install 1st floor - kitchencabinets

2 days Mon 10/10/16

Tue 10/11/16

77 Install 1st floor - master bath and guest cabinets

1 day Wed 10/12/16

Wed 10/12/16

78 Install 2nd floor - hall bath and private bath cabinets

1 day Thu 10/13/16

Thu 10/13/16

79 Install chair rails, crown moldings, trim

2 days Fri 10/14/16 Mon 10/17/16

80 Finish Plumbing 6 days Wed 10/12/16Wed 10/19/16

81 Complete 1st floor - kitchenplumbing

1 day Wed 10/12/16

Wed 10/12/16

82 Complete 1st floor - master bath and guest plumbing

2 days Thu 10/13/16

Fri 10/14/16

Finish carpentry contractor

Finish carpentry contractor

Finish carpentry contractor

Finish carpentry contractor

Plumbing contractor

Plumbing contractor

S T M F T S W S T M

Mar 13, '16 Apr 10, '16 May 8, '16 Jun 5, '16 Jul 3, '16

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 8

Project: Residential Constructio

Date: Wed 4/27/16

Page 9: Residential Construction

ID Task

Mode

Task Name Duration Start Finish

83 Complete 2ndfloor - hall bath and private bath plumbing

2 days Mon 10/17/16

Tue 10/18/16

84 Conduct finishplumbing inspection

1 day Wed 10/19/16

Wed 10/19/16

85 Finish Electrical 3 days Wed 10/19/16Fri 10/21/16

86 Complete 1st floor circuits to service panel

1 day Wed 10/19/16

Wed 10/19/16

87 Complete 2ndfloor circuits to service panel

1 day Thu 10/20/16

Thu 10/20/16

88 Conduct finishelectrical inspection

1 day Fri 10/21/16 Fri 10/21/16

Plumbing contractorS T M F T S W S T M

Mar 13, '16 Apr 10, '16 May 8, '16 Jun 5, '16 Jul 3, '16

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 9

Project: Residential Constructio

Date: Wed 4/27/16

Page 10: Residential Construction

ID Task

Mode

Task Name Duration Start Finish

89 Complete communicationswiring - phone, cable, computer, alarm

2 days Thu 10/20/16

Fri 10/21/16

90 Finish HVAC 3 days Mon 10/24/16Wed 10/26/16

91 Complete 1st floor - zone 1 HVAC

1 day Mon 10/24/16

Mon 10/24/16

92 Complete 2ndfloor - zone 2 HVAC

1 day Tue 10/25/16

Tue 10/25/16

93 Conduct HVAC inspection

1 day Wed 10/26/16

Wed 10/26/16

94 Carpet, Tile and Appliances

8 days Thu 10/27/16

Mon 11/7/16

95 Tile entry, kitchen and baths

3 days Thu 10/27/16

Mon 10/31/16

96 Carpet 1st floor

2 days Tue 11/1/16 Wed 11/2/16

97 Carpet 2nd floor

2 days Thu 11/3/16 Fri 11/4/16

98 Install appliances

1 day Mon 11/7/16

Mon 11/7/16

S T M F T S W S T M

Mar 13, '16 Apr 10, '16 May 8, '16 Jun 5, '16 Jul 3, '16

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 10

Project: Residential Constructio

Date: Wed 4/27/16

Page 11: Residential Construction

ID Task

Mode

Task Name Duration Start Finish

99 Landscaping and Grounds Work

12 days Fri 10/28/16 Mon 11/14/16

100 Pour concrete driveway and sidewalks

2 days Fri 10/28/16 Mon 10/31/16

101 Install backyard fence

2 days Tue 11/8/16 Wed 11/9/16

102 Sod and complete plantings - front yard

2 days Thu 11/10/16

Fri 11/11/16

103 Sod and complete plantings - backyard

1 day Mon 11/14/16

Mon 11/14/16

104 Final Acceptance 8 days Tue 11/15/16Thu 11/24/16

105 Complete final inspection for certificate of occupancy

1 day Tue 11/15/16

Tue 11/15/16

106 Cleanup for occupancy

1 day Wed 11/16/16

Wed 11/16/16

107 Perform final walk-through inspection

1 day Thu 11/17/16

Thu 11/17/16

S T M F T S W S T M

Mar 13, '16 Apr 10, '16 May 8, '16 Jun 5, '16 Jul 3, '16

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 11

Project: Residential Constructio

Date: Wed 4/27/16

Page 12: Residential Construction

ID Task

Mode

Task Name Duration Start Finish

108 Complete punchlist items

5 days Fri 11/18/16 Thu 11/24/16

S T M F T S W S T M

Mar 13, '16 Apr 10, '16 May 8, '16 Jun 5, '16 Jul 3, '16

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 12

Project: Residential Constructio

Date: Wed 4/27/16

Page 13: Residential Construction

General contractor[50%],Architect[50%],Owner[12%],Mortgage lender[12%]

General contractor,Architect,Owner,Mortgage lender

5/25

5/25

5/25

5/25

5/25

5/25

M F T S W S T M F T S W S T M F T S W S

Jul 3, '16 Jul 31, '16 Aug 28, '16 Sep 25, '16 Oct 23, '16 Nov 20, '16 Dec 18, '16 Jan 15, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 13

Project: Residential Constructio

Date: Wed 4/27/16

Page 14: Residential Construction

5/25

Site excavation contractor

Electric company

Electric contractor,Plumbing contractor

Site excavation contractor

Concrete contractor

Concrete contractor

Concrete contractor

Concrete contractor

M F T S W S T M F T S W S T M F T S W S

Jul 3, '16 Jul 31, '16 Aug 28, '16 Sep 25, '16 Oct 23, '16 Nov 20, '16 Dec 18, '16 Jan 15, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 14

Project: Residential Constructio

Date: Wed 4/27/16

Page 15: Residential Construction

Inspector

Site excavation contractor

Framing contractor

Framing contractor

Framing contractor

Framing contractor

Framing contractor

Framing contractor

Framing contractor

Framing contractor

Framing contractor

Inspector

M F T S W S T M F T S W S T M F T S W S

Jul 3, '16 Jul 31, '16 Aug 28, '16 Sep 25, '16 Oct 23, '16 Nov 20, '16 Dec 18, '16 Jan 15, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 15

Project: Residential Constructio

Date: Wed 4/27/16

Page 16: Residential Construction

Framing contractor

Framing contractor

Framing contractor

Roofing contractor

Framing contractor

Framing contractor

Framing contractor

Masonry contractor

Framing contractor

Plumbing contractor

M F T S W S T M F T S W S T M F T S W S

Jul 3, '16 Jul 31, '16 Aug 28, '16 Sep 25, '16 Oct 23, '16 Nov 20, '16 Dec 18, '16 Jan 15, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 16

Project: Residential Constructio

Date: Wed 4/27/16

Page 17: Residential Construction

Inspector

Concrete contractor

Electric contractor

Inspector

Heating and AC contractor

Inspector

Electric contractor

Insulation contractor

M F T S W S T M F T S W S T M F T S W S

Jul 3, '16 Jul 31, '16 Aug 28, '16 Sep 25, '16 Oct 23, '16 Nov 20, '16 Dec 18, '16 Jan 15, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 17

Project: Residential Constructio

Date: Wed 4/27/16

Page 18: Residential Construction

Insulation contractor

Insulation contractor

Inspector

Drywall contractor

Drywall contractor

Drywall contractor

Drywall contractor

Drywall contractor

M F T S W S T M F T S W S T M F T S W S

Jul 3, '16 Jul 31, '16 Aug 28, '16 Sep 25, '16 Oct 23, '16 Nov 20, '16 Dec 18, '16 Jan 15, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 18

Project: Residential Constructio

Date: Wed 4/27/16

Page 19: Residential Construction

Drywall contractor

Painting contractor

Painting contractor

Painting contractor

Painting contractor

Painting contractor

Painting contractor

M F T S W S T M F T S W S T M F T S W S

Jul 3, '16 Jul 31, '16 Aug 28, '16 Sep 25, '16 Oct 23, '16 Nov 20, '16 Dec 18, '16 Jan 15, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 19

Project: Residential Constructio

Date: Wed 4/27/16

Page 20: Residential Construction

Finish carpentry contractor

Finish carpentry contractor

Finish carpentry contractor

Finish carpentry contractor

Plumbing contractor

Plumbing contractor

M F T S W S T M F T S W S T M F T S W S

Jul 3, '16 Jul 31, '16 Aug 28, '16 Sep 25, '16 Oct 23, '16 Nov 20, '16 Dec 18, '16 Jan 15, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 20

Project: Residential Constructio

Date: Wed 4/27/16

Page 21: Residential Construction

Plumbing contractor

Inspector

Electric contractor

Electric contractor

Inspector

M F T S W S T M F T S W S T M F T S W S

Jul 3, '16 Jul 31, '16 Aug 28, '16 Sep 25, '16 Oct 23, '16 Nov 20, '16 Dec 18, '16 Jan 15, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 21

Project: Residential Constructio

Date: Wed 4/27/16

Page 22: Residential Construction

Electric contractor

Heating and AC contractor

Heating and AC contractor

Inspector

Flooring contractor

Flooring contractor

Flooring contractor

Appliance contractor

M F T S W S T M F T S W S T M F T S W S

Jul 3, '16 Jul 31, '16 Aug 28, '16 Sep 25, '16 Oct 23, '16 Nov 20, '16 Dec 18, '16 Jan 15, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 22

Project: Residential Constructio

Date: Wed 4/27/16

Page 23: Residential Construction

Concrete contractor

Fencing contractor

Landscape contractor

Landscape contractor

Inspector

Maid service

Owner

M F T S W S T M F T S W S T M F T S W S

Jul 3, '16 Jul 31, '16 Aug 28, '16 Sep 25, '16 Oct 23, '16 Nov 20, '16 Dec 18, '16 Jan 15, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Page 23

Project: Residential Constructio

Date: Wed 4/27/16

Page 24: Residential Construction

General contractorM F T S W S T M F T S W S T M F T S W S

Jul 3, '16 Jul 31, '16 Aug 28, '16 Sep 25, '16 Oct 23, '16 Nov 20, '16 Dec 18, '16 Jan 15, '17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress