Research Proposal for high voltage network

Embed Size (px)

Citation preview

  • 7/27/2019 Research Proposal for high voltage network

    1/27

    1

    A METAHEURISTIC LOAD SHEDDING ALGORITHM USING

    VOLTAGE AND FREQUENCY PARAMETERS

    CHARLES MWANIKI

    A research proposal submitted to the Faculty of Engineering in Partial fulfillment of the

    requirements for the Doctor of Philosophy in Electrical Engineering Jomo Kenyatta

    University of Agriculture and Technology.

    J.K.U.A.T

    July, 2013

  • 7/27/2019 Research Proposal for high voltage network

    2/27

    2

    DECLARATION

    I declare that this research proposal is my original work and it has not been presented for an

    award of a degree, diploma or certificate in this or any other university.

    CHARLES MWANIKI SIGN:_________________DATE: _____________

    RECOMMENDATION/APPROVAL

    This research proposal has been submitted with my approval as the university supervisor.

    DR CHRISTPHER MAINA MURIITHI SIGN_______________DATE: ________

    This research proposal has been submitted with my approval as the university co-supervisor.

    DR NICODEMUS ABUNGU SIGN___________________DATE: ______________

  • 7/27/2019 Research Proposal for high voltage network

    3/27

    3

    TABLE OF CONTENTS

    DECLARATION ....................................................................................................................... 2

    RECOMMENDATION/APPROVAL ....................................................................................... 2

    TABLE OF CONTENTS ........................................................................................................... 3

    1 INTRODUCTION .............................................................................................................. 4

    1.1 Background .................................................................................................................. 4

    1.2 Problem Statement ....................................................................................................... 4

    1.3 Relevance of Study/Justification ................................................................................. 5

    1.4 Objectives .................................................................................................................... 6

    1.4.1 Main objective ...................................................................................................... 6

    1.4.2 Specific objectives ................................................................................................ 7

    1.4 Scope of Study ............................................................................................................. 7

    1.5 Importance of the study ............................................................................................... 7

    2 LITERATURE REVIEW ................................................................................................... 8

    2.1 Under voltage Load Shedding ..................................................................................... 8

    2.2 Under frequency Load Shedding ............................................................................... 10

    2.3 Under voltage under frequency Load Shedding .......................................................... 17

    3 METHODOLOGY ........................................................................................................... 20

    3.1 Metaheuristics algorithm ........................................................................................... 20

    3.2 Harmony Search Algorithm ....................................................................................... 20

    3.3 Cuckoo Search Optimization ..................................................................................... 21

    4 THESIS DEVELOPMENT SCHEDULE......................................................................... 23

    5 BUDGET .......................................................................................................................... 24

    6 REFERENCES ................................................................................................................. 25

  • 7/27/2019 Research Proposal for high voltage network

    4/27

    4

    1 INTRODUCTION1.1 BackgroundThe developing industries and their growing infrastructure have stressed the power industry to

    supply sufficient power. The generation capacity should increase in proportion to the increase

    in the number of loads. Large power transfers across the grid lead to the operation of the

    transmission lines close to their limits. Additionally, generation reserves are minimal and

    often the reactive power is insufficient to satisfy the load demands. Due to these reasons

    power systems become more susceptible to disturbances and outages. Some of the

    disturbances experienced by the power system are faults, loss of a generator and or

    transmission line and sudden switching of loads [1-3]. These disturbances vary in their

    intensity. As a result it is necessary to study the system and monitor it in order to prevent it

    from becoming unstable.

    The two most important parameters to monitor are the system voltage and frequency, both of

    which must be maintained within prescribed limits standards to ensure that the system

    remains stable. The frequency is mainly affected by the active power, while the voltage is

    mainly affected by the reactive power. Specifically, the frequency is affected by the difference

    between the generated power and the load demand. This difference is caused due to

    disturbances which reduce the generation capacity of the system. For example, due to the loss

    of a generator, the generation capacity decreases while the load demand remains constant. If

    the other generators in the system are unable to supply the power needed, then the system

    frequency begins to decline. To restore the frequency within the prescribed limits a load

    shedding scheme is applied to the system.

    In addition, the reactive power demand of the load affects the voltage magnitude at that

    particular bus. When the power system is unable to meet the reactive power demands of the

    loads, the voltages become unstable. In such situations, capacitor banks are switched on to

    supply the reactive power to the loads. However, when these capacitor banks are unable to

    restore the voltage levels within their upper and lower limits, the system resorts to load

    shedding.

    1.2 Problem StatementLoad shedding is an emergency control action to ensure system stability, by curtailing system

    load. The emergency load shedding would only be used if the frequency or voltage falls

    below a specified frequency/voltage threshold. Typically, the load shedding protects againstexcessive frequency or voltage decline by attempting to balance real and reactive power

  • 7/27/2019 Research Proposal for high voltage network

    5/27

    5

    supply and demand in the system. The number of load shedding steps, amount of load that

    should be shed in each step, the delay between the stages, and the location of shed load are the

    important objects that should be determined in a load shedding algorithm.

    Despite being successful to a great extent, the conventional load shedding schemes have

    certain disadvantages. The amount of a load step is, at times, large which causes excessive

    load to be shed. Most schemes do not have the flexibility to increase the number of load

    shedding steps, thereby introducing transients in the system.

    The most LS schemes proposed so far used voltage and frequency parameters, separately and

    also, the under-frequency and under-voltage relays are working in the power system without

    any coordination. The individual use of these indices may be also not reliable/effective, and

    may even lead to the over load shedding problems. Studying on the under-frequency load

    shedding is often done using the system frequency response models. The impact of voltage

    variation on the frequency deviation is not considered in these models. Furthermore, the

    UVLS methods that are proposed so far for adjusting the under-voltage relays, does not

    consider the frequency behavior. These two parameters (voltage and frequency) are not

    independent and the coordination between UFLS and UVLS schemes is therefore crucial. The

    dependency between voltage and frequency will affect LS performance.

    Economical considerations need to be considered before shedding the load since certain loads

    cannot be kept offline. Further, Load shedding is an emergency control operation and should

    be on a priority basis, which means shedding less important loads, while expensive industrial

    loads are still in service.

    Therefore, this study focuses on developing an algorithm that is more reliable and effective

    than the conventional schemes, that uses voltage and frequency parameters simultaneously for

    making load shedding decisions. This will help in power system planning, operation and

    control.

    1.3 Relevance of Study/JustificationThe increase in electrical power consumption is directly proportional to the increase in people

    population. As of 10th July, 2009, the world population was estimated by the United States

    Census Bureau at 6.77 billion. This figure is expected to reach about 9 billion by the year

    2040. Many environmental and economic constraints prevent the construction of new or

    upgrading of the existing generation and transmission capacities. Additionally, generation

    reserves are minimal and often the reactive power is insufficient to satisfy the load demands.

  • 7/27/2019 Research Proposal for high voltage network

    6/27

    6

    Given this trend, power systems are expected to be more heavily loaded and moving closer

    and closer to stability limit and more susceptible to disturbances and outages.

    Blackouts of power systems always have been a historical problem in interconnected power

    systems. However in recent years by improving monitoring and protection techniques, it is not

    possible to completely prevent of blackouts [1-3]. Sudden and large changes in generation

    capacity such as the outage of a generator can produce a sever imbalance between generation

    and load demand. This may lead to a rapid decline in frequency, because the system may not

    respond fast enough. If voltage and frequency get out from permissible range the system is in

    unstable condition. In this condition the system controller's operate and attempt to restore the

    voltage and frequency in the permissible range. If the disturbance is so large the controller's

    cant restore the voltage and frequency in the permissible range. In this condition the last

    solution to avoid the power system breakdown has been load shedding strategy.

    Recent blackouts have brought our attention to the issues of voltage stability in the system.

    Voltage decline can be a result of a disturbance. Its main cause, however, is insufficient

    supply of reactive power. This has led researchers to focus on techniques to maintain voltage

    stability. The loss of a generator causes an unbalance between the generated power and the

    load demand. This affects the frequency and voltage. Load shedding schemes must consider

    both these parameters while shedding load. By shedding the correct amount of load from the

    appropriate buses, the voltage profile at certain buses can be improved [4].

    While considering the amount of load to be shed and the step size, it is also important to take

    into account the reactive power requirements of each load. Quite often, disturbances such as a

    generator loss cause the voltage to decline. An effective way to restore voltage is to reduce the

    reactive power demand. Thus when loads absorbing a high amount of reactive power are first

    shed; the voltage profile can be improved.

    1.4 Objectives1.4.1 Main objectiveThe main objective of the research is to investigate the applicability of a metaheuristic load

    shedding algorithm using both frequency and voltage parameters.

  • 7/27/2019 Research Proposal for high voltage network

    7/27

  • 7/27/2019 Research Proposal for high voltage network

    8/27

    8

    2 LITERATURE REVIEWDifferent methods for load shedding and restoration have been developed by many

    researchers. Currently there are various under frequency and under voltage load shedding

    techniques used in the power industry worldwide.

    2.1 Under voltage Load Shedding

    Lopes et all [5] suggests a method which carries out load shedding in case of two conditions.

    One, where the load shedding occurs due to a post disturbance low voltage condition and

    secondly, where the load shedding results due to the inability of the system to achieve a stable

    operating condition during post disturbance. This method uses the load flow in order to decide

    the buses from which to shed load. The initial set of control actions are first carried out. These

    actions are capacitor switching, tap changing transformer and secondary voltage control.

    Jianfeng et al [6] have developed a method with risk indices in order to decide which buses

    should be targeted for load shedding to maintain voltage stability. The buses with a high risk

    of voltage instability are considered first. This is estimated from the probability of a voltage

    collapse occurrence. The risk indices are the products of these probabilities and impact of

    voltage collapse.

    Another method [7][31] dealing with the particle swarm approach for under voltage load

    shedding has been researched. The particle swarm Optimization concept is a group or cluster

    of particles in which each particle is known to have individual memory like an animal in its

    herd or flock. The flock is initiated with some initial velocity and the particles move in

    different directions to come up with the best solution. The best solution is shared with every

    particle of the group so that they can move from there on based on this new acquired

    knowledge. This same idea is used for under voltage load shedding to recognize the best

    possible load shedding scheme considering the system conditions and disturbance particular

    to that situation.

    Ladhani and Rosehart [8] propose load modeling for an under voltage load shedding scheme.

    They also suggest offering economic incentives to customers for discontinuing the use of

    power during load control periods. This way the brunt of a sudden load shed is not borne by

    the customer alone. Also, systematic load control will lead to the stability of the system even

    when it is not faced with a disturbance.

  • 7/27/2019 Research Proposal for high voltage network

    9/27

    9

    Yorino et al [9] suggests a new planning method for planning the VAR allocation using the

    FACTS devices. Here, the total economic cost for a voltage collapse along with its corrective

    control and load shedding are taken into account to come up with the optimum VAR planning

    scheme. Thus, the objective function is to minimize the cost while keeping in mind the

    voltage stability of the system.

    Mozino [10] discusses the currently existing under voltage load shedding schemes.

    They are divided into two categories; decentralized and centralized. The decentralized load

    shedding involves setting relays at buses with loads to be shed and tripping the respective

    relays. The centralized scheme is more advanced. The relays are installed at the key bus

    locations and the information regarding which relays are to be tripped is sent to these relays

    from a main control centre. Thus the required load is shed from appropriate buses. Many of

    these schemes are referred to as special protection or wide area schemes. The two

    categories mentioned above are widely used as under voltage load shedding relays. These

    relays require logic and have to perform efficiently and accurately. Also, these relays must

    avoid false operation. Thus to satisfy the above requirements digital relays are being used for

    under voltage load shedding.

    Single Phase UVLS Logic measures voltages on every phase. This scheme distinguishes

    between voltage collapse and fault induced low voltages. The voltage collapse is a balanced

    phenomenon, hence results in a reduction of voltage on all the three phases. Except for a three

    phase fault all the other faults are unbalanced. The relays trips when it identifies a voltage

    collapse and blocks the relay for a fault induced low voltage. Unbalanced faults usually

    induce negative sequence voltages which are detected and used for blocking the relay.

    Positive sequence UVLS logic checks the positive sequence voltage with the set point value.

    Since the voltage collapse is balanced for all the three phases, the positive sequence voltage is

    equal to the three phase voltages. In case of a fault condition, the negative sequence voltage is

    utilized to block the relay.

    A load shedding scheme against long term voltage instability is proposed by Van Cutsem et al

    [11]. It uses distributed controllers which are delegated a transmission voltage and a group of

    loads to be controlled. Each controller acts in a closed loop, shedding loads that vary in

    magnitude based on the evolution of its monitored voltage. Each controller acts on a set of

  • 7/27/2019 Research Proposal for high voltage network

    10/27

  • 7/27/2019 Research Proposal for high voltage network

    11/27

    11

    Another method [14] triggers the under frequency relays based on a dynamically changing

    intelligent load shedding scheme. The main components of this scheme are the knowledge

    base, disturbance list and the ILS computation engine.

    Fig. 1 Block Diagram of the ILS scheme

    The generalized structure of the ILS scheme is shown in figure 1. The knowledge base is the

    most important block. It is connected to the computation engine which sends trip signals to

    relays. The network models can be accessed by the knowledge base while monitoring the

    system. The knowledge base is trained and its output consists of system dynamic scenarios

    and frequency responses during disturbances. This trained knowledge base also monitors the

    system continuously for all operating conditions. The disturbance list consists of pre-specified

    system disturbances. Based on the inputs for the system and the continuous system updates,

    the knowledge base notifies the ILS engine to update its load shedding list. Thus it ensures

    that the load shed is always minimum and optimum.

    Wee-Jen Lee [15] discuss about another intelligent load shedding based on microcomputers.

    The unique feature about this scheme is the built in frequency setting and the time delay

    setting. The frequency setting in the relay counters system re collapse situation. (Consider a

    generator loss which triggers a load shedding step. This causes the frequency of the system to

    recover. During this recovery period if another generator trips it results in a system re

    collapse). Typical frequency relays will not trip until the second generator loss causes

    sufficient frequency decay. The ILS system automatically adjusts the frequency settings such

    that load is shed immediately without delay.

    The time delay settings cause the load scheme to initiate during situations when a disturbance

    causes the frequency to drop and hold at a value less than the rated. The number of load

    shedding steps can be increased without a limit. The advantage of having large number of

  • 7/27/2019 Research Proposal for high voltage network

    12/27

    12

    load shedding steps is that it prevents large amount of transients. It also prevents over

    shedding.

    Denis Lee Hau Aik, [16] suggests a method using the System Frequency Response SFR and

    the Under Frequency Load Shedding UFLS together to get a closed form expression of the

    system frequency such that the UFLS effect can be included in it. On doing this, the system

    and UFLS performance indicators can be calculated. Thus these indicators can be used

    efficiently in any further optimization techniques of SFRUFLS model. One such method

    has been discussed using the regression tree by Chang et al [17]. The regression tree is

    utilized to interpolate between recorded data to give an estimate of the frequency decline after

    a generator outage. It is a non parametric method which can select the system parameters and

    their relations which are most relevant to the load imbalance (due to generator outage) and the

    frequency decline. The case considered here is only a generator outage but this method can be

    applied to other forms of disturbances as well.

    A Kalman filtering-based technique by A.A. Girgis et al [18] estimates frequency and its rate

    of change which is beneficial for load shedding. The noisy voltage measurements are used to

    estimate the frequency and its rate of change. A three-state extended Kalman filter in series

    with a linear Kalman filter is used in a two stage load shedding algorithm. The output of the

    three stage Kalman filter acts as the input to the linear Kalman filter. It is the second filter

    which identifies linear components of the frequency and its rate of change. The amount of

    load to be shed is calculated using the linear component of the estimated frequency deviation.

    Another method uses Kalman filtering [19] to estimate the frequency and its rate of change

    from voltage waveforms. The buses are ranked based on their rate of change of voltage

    (dV/dt) values. The disturbance magnitude is calculated from the swing equation. The rate of

    change of frequency required for this equation is calculated using the Kalman filter. Once the

    total amount of load to be shed is estimated then the load to be shed from each bus is

    determined based on the PV analyses.

    An optimization technique for load shedding [20] with distributed generation was developed.

    This technique converts differential equation into algebraic ones using the discretization

    method. Two cases are considered here; one with the distributed generation switched on to the

    system as a static model and the other case without the distributed generation on the grid.Both cases resulted in successful shedding of appropriate quantity of load.

  • 7/27/2019 Research Proposal for high voltage network

    13/27

    13

    Li Zhang suggests a method [21] which designs under frequency relays using both the

    frequency and the rate of change of frequency (df/dt). The scheme has been designed for a 50

    Hz Northeast China power system. Traditional schemes required only the frequency decay

    information. Here the rate of change of frequency is used as auxiliary information. The plots

    for the rate of change of frequency are oscillatory in nature. Hence a new scheme is devised in

    this paper which considers the integration of the rate of change of frequency (df/dt) to indicate

    the frequency drop. By integrating one is effectively measuring the area between two

    frequencies, fi-1 and fi. The schemes is made up of five load shedding steps for a 50 Hz system.

    These steps are from 50 to 49.2 Hz, 49.2 to 49 Hz, 49 to 48.8Hz, 48.8 to 48.6 Hz, 48.6 to 48.4

    Hz. The amount of load to be shed in each step is decided by integrating the df/dt value in

    each step. The simulation results when compared with the old scheme with just the frequency

    decay show a definite improvement in system frequency due to the inclusion of rate of change

    of frequency (df/dt) in the new scheme.

    The main idea in the paper proposed by Xiong et al [22] is the inclusion of on line load

    frequency regulation factors. Loads with smaller frequency regulation factors are shed first,

    followed by the ones with larger frequency regulation factors. The active power and load

    frequency relation is established in the form of the following equation.

    Where, fN is the nominal frequency. PLN is the rated active power and ai (i=1,2n) is the

    percentage of the total load associated with the i-th term of the frequency. The per unit form

    of the above equation is differentiated to get the change in load power as frequency changes

    (dPL/df) which is theKL factor or regulation factor. The higher order terms are neglected.

    Thus it is preferable to shed load for smaller regulation factors. Hence the loads are

    distinguished based on their individual regulation factors and accordingly load shedding

    schedules are planned based on their respective K factors.

  • 7/27/2019 Research Proposal for high voltage network

    14/27

  • 7/27/2019 Research Proposal for high voltage network

    15/27

    15

    where is the disturbance magnitude in per unit. Now another variable is defined. If

    a disturbance occurring at the weakest generator is less than this value then absolute

    frequency of that generator is within the permitted limits. For a situation where the

    disturbance magnitude, is less than no load shedding is required. The maximum

    load shedding magnitude is equal to the difference between the disturbance magnitude and

    Pthr - Pthr. The load to be shed is distributed inversely proportional to the generator

    inertia to make the load shedding most effective. The equation (4) represents this distribution.

    Based on this equation the layers of the load shedding scheme are designed. Both the steps

    shed one third of the remaining load. These are in steps. They are presented in a table 1 with

    the first step being at 59.3 Hz.

    TABLE 1: SCADA Based Load Shedding Formula

    An adaptive load shedding scheme which includes a self healing strategy is presented by

    Vittal et al [26]. The proposed scheme is tested on a 179 bus 20 generator test system. This

    self healing strategy comes into play when the system vulnerability is detected. The system

    then divides into self sustaining islands. After this islanding, load shedding based on the rate

  • 7/27/2019 Research Proposal for high voltage network

    16/27

    16

    of change of frequency is applied to the system. Due to this division, it becomes easier to

    restore load. A Reinforcement Learning scheme is discussed in the paper.

    The first is the controlled islanding which is done using the two-time scale method. It deals

    with the structural characteristics of the power systems and determines the interactions of the

    generators and their strong or weak coupling. The Dynamic Reduction Program 5.0

    (DYNRED) is the software in which simulations are run to implement this technique.

    Through this software coherent group of generators can be obtained on the power system.

    Islanding causes two types of islands to be formed, the generation rich islands and the load

    rich islands. The load rich islands may have a further decline of frequency. This may result in

    the generator protection to trip the generators thus further declining the islands frequency.Thus a two layer load shedding strategy is employed for the load rich island. The first layer is

    based on the frequency decline approach. The second layer considers the rate of change of

    frequency. Due to the longer time delays and lower frequency thresholds for a frequency

    based scheme inadvertent load shedding is avoided. When the system disturbance is large and

    exceeds the signal threshold, the second layer comes into play. It sends a signal to discontinue

    the first layer of operation and continues with the load shedding based on rate of change of

    frequency. This layer will shed more load at the initial steps to prevent cascading effects. The

    magnitude of the disturbance is found based on the formula

    If we sum up all the equations for i=1 to n then the final equation obtained is

    Where, m0 is defined as df/dtwhich is the average rate of frequency decline.

    Rearranging the above equation we get a new equation which relatesPL to m0 .

  • 7/27/2019 Research Proposal for high voltage network

    17/27

    17

    SinceHi is constant, the magnitude ofm0 can be directly proportional to the rate of frequency

    decline. Hence the rate of change of frequency df/dt ) can be a measure of the disturbance.

    Once the disturbance threshold value, PL , for the second layer of load shedding is decided,the m0 value is calculated. The mi at each bus is calculated and compared with m0 . Ifmi m0

    then the second layer is activated, otherwise the conventional load shedding scheme is used.

    This new shedding scheme increases the stability of the system by shedding fewer loads as

    compared to the conventional scheme.

    Application of Neural Network in load shedding and some Predictable functioning of load

    shedding methods has been proposed [28 -30][32]. In this method the identification of the

    variables like inputs and outputs is an important step for a successful application of this

    technique. Sometimes a pre-processing stage is needed to choose the most significant

    variables to be used as inputs of a NN. Some of the meaningful variables that have been used

    as inputs of the NN

    Active real power generation Active load generation Amount of active load being shed Percentage of exponential type loads being shed Damping factor Power factor

    These variables provide the NN with valuable information, such that it can make the required

    assessment with respect to how much the generation load disproportion has been corrected

    and the influence each load type has on the resulting frequency response.

    2.3 Under voltage under frequency Load Shedding

    A load shedding scheme that incorporates, the frequency and the bus voltages, for deciding

    the instant, the amount and the location of the load to be shed is proposed [27]. The scheme

    developed consists of a stepwise approach. This has been represented in the form of an

    algorithm.

    The first step of the load shedding procedure is the measurement and calculation of the rate of

    change of frequency. Depending on the relay, the frequency measurements or the rate of

    change of frequency are recorded in the system. The total load mismatch between the

  • 7/27/2019 Research Proposal for high voltage network

    18/27

    18

    generated power and load power is determined. For a single machine, the swing equation [1]

    is given by

    where, f0is the nominal frequency of the system and Pdiffis the difference in the generatedpower and the load power. In the above equation is replaced by f since = 2f. Thus arelation between the frequency and the power mismatch is obtained. This relation establishes

    the estimated magnitude of the disturbance. The inertia constant in the above equation is the

    kinetic energy Wkover the system base MVA. The inertia constants of all the machines in thesystem are on the base MVA.

    In a large power system where there are many generators which maybe geographically far

    away from each other,

    Also, the equivalent mechanical and electrical powers are given as;

    Pm = individual mechanical shaft power of each machine for all the machines in the system

    Pe =

    individual electrical power of each machine for all the machines in the system

    Once the magnitude of the disturbance is determined using the above equivalent swing

    equation, the location and the amount of load to be shed from each bus has to decided. In

    order to do this, the buses are ranked according to the dV/dt values at the point of detection of

    frequency decline. The bus with the largest dV/dt is listed at the top of the list and then so on

    in the decreasing order.

    Once the order is decided, the next step is to decide the amount of load to be shed at each bus.

    This is decided based on the voltage sensitivity at each bus. Thus the bus with voltage

    sensitivity very close to the instability limit will have a maximum load shed based on the

    reciprocal of its sensitivity as a fraction of the sum of the reciprocals of all the load bus

    sensitivities.

  • 7/27/2019 Research Proposal for high voltage network

    19/27

    19

    The load shedding scheme has been tested on the IEEE 39 bus and IEEE 145 bus test systems.

    Three studies based on contingency were carried out with each contingency being considered

    at a time:

    Case study 1: Loss of a generator for the IEEE 39 bus system. Case study 2: Loss of a generator for the IEEE 145 bus system. Case study 3: Loss of a transmission line IEEE 39 bus system

    The scheme is simple and does not involve complicated calculations. It proved to be

    successful in restoring the frequency within its pre-defined limits. It has also improved the

    voltage profile at certain buses which had critically low voltage before load shedding was

    applied. However the algorithm did not address some aspects and therefore requires fine

    tuning.

    Economical considerations need to be considered before shedding the load since certain loads

    cannot be kept offline. The study and testing of the scheme in a multiple contingency scenario

    like loss of a generator along with a loss of transmission line need to be considered as this

    would create a critical situation.

    Thus the various conventional schemes, under frequency schemes and under voltage load

    shedding schemes have been discussed above. These give an insight about the technological

    advancement achieved in this area. The proposed study intends to investigate the applicability

    of harmony search algorithm as an optimization tool and how it can be applied to address the

    disadvantages faced by the conventional schemes present in the industry.

  • 7/27/2019 Research Proposal for high voltage network

    20/27

    20

    3 METHODOLOGY3.1 Metaheuristics algorithmMetaheuristic algorithms are higher-level heuristic algorithms. Here, meta-means higher-

    level or beyond, so metaheuristic means literally to find the solution using higher-level

    techniques, though certain trial-and-error processes are still used. Broadly speaking,

    metaheuristics are considered as higher-level techniques or strategies which intend to combine

    lower-level techniques and tactics for exploration and exploitation of the huge space for

    parameter search.

    There are two important components in modern metaheuristics, and they are: intensification

    and diversification. For an algorithm to be efficient and effective, it must be able to generate a

    diverse range of solutions including the potentially optimal solutions so as to explore the

    whole search space effectively, while it intensifies its search around the neibourhood of an

    optimal or nearly optimal solution. In order to do so, every part of the search space must be

    accessible though not necessarily visited during the search. Diversification is often in the form

    of randomization with a random component attached to a deterministic component in order to

    explore the search space effectively and efficiently, while intensification is the exploitation of

    past solutions so as to select the potentially good solutions via elitism or use of memory or

    both [33-35]. If the intensification is too strong, only a fraction of local space might be

    visited, and there is a risk of being trapped in a local optimum, as it is often the case for the

    gradient-based search such as the classic Newton-Raphson method. If the diversification is

    too strong, the algorithm will converge too slowly with solutions jumping around some

    potentially optimal solutions. In this study good balance of these two important components

    will be maintained.

    Another important feature of modern metaheuristics is that an algorithm is either trajectory-

    based or population-based. It is difficult to decide which type of method is more efficient as

    both types work almost equally successfully under appropriate conditions. In this study the

    focus will be on population based algorithm.

    3.2 Harmony Search AlgorithmIn the HS algorithm, diversification is essentially controlled by the pitch adjustment and

    randomization -- here there are two subcomponents for diversification, which might be an

    important factor for the high efficiency of the HS method. The first subcomponent ofcomposing new music, or generating new solutions, via randomization would be at least at

  • 7/27/2019 Research Proposal for high voltage network

    21/27

    21

    the same level of efficiency as other algorithms by randomization. However, an additional

    subcomponent for HS diversification is the pitch adjustment characterized by rpa. Pitch

    adjusting is carried out by adjusting the pitch in the given bandwidth by a small random

    amount relative to the existing pitch or solution from the harmony memory. Essentially, pitch

    adjusting is a refinement process of local solutions. Both memory consideration and pitch

    adjusting ensure that the good local solutions are retained while the randomization and

    harmony memory considering will explore the global search space effectively. The subtlety of

    this is that it is a controlled diversification around the good solutions (good harmonics and

    pitches), and it almost acts like an intensification factor as well. The randomization explores

    the search space more efficiently and effectively; while the pitch adjustment ensures that the

    newly generated solutions are good enough, or not too far away from existing good solutions.

    The intensification is mainly represented in the HS algorithm by the harmony memory

    accepting rate raccept. A high harmony acceptance rate means the good solutions from the

    history/memory are more likely to be selected or inherited. This is equivalent to a certain

    degree of elitism. Obviously, if the acceptance rate is too low, the solutions will converge

    more slowly.

    Furthermore, the HS algorithm is a population-based metaheuristic, this means that multiple

    harmonics groups can be used in parallel. Proper parallelism usually leads to better

    implantation with higher efficiency. The good combination of parallelism with elitism as well

    as a fine balance of intensification and diversification is the key to the success of the HS

    algorithm, and in fact, to the success of any metaheuristic algorithms. These advantages make

    it very versatile to combine HS with other metaheuristic through hybridization .This research

    will focus on hybridization of Harmony search algorithm with Cuckoo search optimization.

    3.3 Cuckoo Search OptimizationCuckoos are brood parasites that lay their eggs in the nests of other birds (such as crows) who

    serve as hosts to hatch their eggs. To elucidate, let there be n parasites and equally many

    (although not necessarily) hosts. Each parasite individual would be represented by a point (x

    in m-dimensional space) and similarly each host individual would be represented by a point (y

    in m-dimensions). These points may be randomly generated and would lie in the domain of

    the function to be optimized. Each cuckoo would take a Lvy flight and if its post-flight

    fitness is better than its pre-flight fitness, it would randomly choose a host nest that has not as

    yet been invaded by another cuckoo and the quality of the host eggs are inferior to the cuckooegg. If this condition is not met, it would not lay any egg in the host nest. The egg of a

  • 7/27/2019 Research Proposal for high voltage network

    22/27

    22

    successful parasite may, however, be detected (with probability p) by the host and be

    destroyed. If not detected, however, it would be hatched in the host nest and eventually join

    the cuckoo population. Only the best n cuckoos, however, would enter into the next

    generation.

    To implement this search scheme, Yang & Deb[37] formulated the following idealized rules:

    (a) Each cuckoo lays a single egg into a randomly chosen host nest from among n nests; (b)

    The nests with better quality eggs (implying better fitness value of the function concerned), if

    not detected, would be hatched to grow into the cuckoo chicks, who would join the next

    generation; (c) The number of available host nests is fixed. The host can detect the alien egg

    with a probability [0, 1] and, if detected, it will either abandon the nest and build a new nest

    elsewhere or destroy the egg; (d) When generating new solutions xi(t+1) from the old one xi

    (t),

    Levy flight is performed with parameter 1< < 3 and thus

    The Lvy flight is a type of random walk which has a power law step length distribution with

    a heavy tail.

  • 7/27/2019 Research Proposal for high voltage network

    23/27

    23

    4 THESIS DEVELOPMENT SCHEDULE

    YEAR 1 YEAR 2 YEAR 3

    ACTIVITY

    Jul-13

    Aug-13

    Sep-13

    Oct-13

    Nov-13

    Dec-13

    Jan-14

    Feb-14

    Mar-14

    Apr-14

    May-10

    Jun-14

    Jul-14

    Aug-14

    Sep-14

    Oct-14

    Nov-14

    Dec-14

    Jan-15

    Feb-15

    Mar-15

    Apr-15

    May-15

    Jun-15

    Jul-15

    Aug-15

    Sep-15

    Oct-15

    Nov-15

    Dec-15

    Jan-16

    Feb-16

    Mar-16

    Apr-16

    May-16

    Jun-16

    Proposal Editing and Presentation

    Literature Review:Harmony search algorithm study

    and coding

    Load shedding study using harmony

    search algorithm

    Paper Presentation

    Hybridization of harmony search

    ith Cuckoo search algorithm

    Load shedding study using the

    hybrid algorithm

    Paper Presentation

    Thesis Writing & Presentation

    Thesis Examination

    Thesis Corrections and editing

    Thesis Defence

  • 7/27/2019 Research Proposal for high voltage network

    24/27

    24

    5 BUDGET

    ITEM COST (KSH)

    1

    Stationery, Printing, Photocopying for

    entire research period 40,000

    2

    Computer Soft ware ( C++, Matlab and

    associated tool boxes) 80,000

    3 Computer Hardware: Printer, Laptop 80,000

    4 Access to journals: IEEE, Actpress 50,000

    5 Transport 50,000

    6 Books 40,000

    7 Conferences and Paper presentation 360,000

    8 Thesis printing and binding 20,000

    Total 720,000

  • 7/27/2019 Research Proposal for high voltage network

    25/27

    25

    6 REFERENCES[1] D. Craciun, S. Ichim, and Y. Besanger, A new soft load shedding: Power system stability

    with contribution from consumers,IEEE/PTC, pp. 1-6, June/July 2009.[2] D.Andersson, P.Elmersson, A.Junti, Z.Gajie, D.Karlsson, and L.Fabiano, Intelligent load

    shedding to counteract power system instability,IEEE/PES, pp. 570-574, 2004.

    [3] G. Shahgholian, M. E. Salary Effect of Load Shedding Strategy on Interconnected Power

    Systems Stability When a Blackout Occurs, International Journal of Computer and

    Electrical Engineering, Vol. 4, No. 2, pp 212-217, April 2012

    [4] B. Suneetha, S. Hemachandra, B. Gowri Prasad and A. Jayanth, Application of Neural

    Network in Load Shedding and Some Predictable Functioning of Load Shedding

    Methods, International Journal of Electronics, Communication & Instrumentation

    ngineering Research and Development (IJECIERD),Vol. 3, Issue 2, pp 45-50, Jun 2013

    [5] B. Isaias Lima Lopes, A.C. Zambroni de Sow, An Approach for UnderVoltage Load

    Shedding, IEEE Bologna PowerTech Conference.,2003

    [6] Dai Jianfeng, Zhou Shuangxi, Lu Zongxiang, A New Risk Indices Based Under Voltage

    Load Shedding Scheme.,Transmission and Distribution Conference and Exhibition: Asia

    and Pacific, 2005 pg 1-5

    [7] T. Amraee, B. Mozafari, A.M. Ranjbar, An Improved Model for Optimal Under Voltage

    Load Shedding: Particle Swarm Approach. Power India, New Delhi Conference, IEEE,

    2006

    [8] Shamir S. Ladhani, William Rosehart, Criteria for Load Control when Considering Static

    Stability Limits. Power Engineering Society General meeting, 2005, IEEE,vol 2 pg 1558 -

    1562

    [9] Naoto Yorino, E. E. El-Araby, Hiroshi Sasaki, Shigemi Harada, A New Formulation for

    FACTS Allocation for Security Enhancement Against Voltage Collapse.Power Systems,

    IEEE transactions, 2003, vol 18,issue 1,pg 3-10

    [10] Charles J. Mozina (Beckwith Electric Co., Inc.), Undervoltage Load Shedding., Power

    Systems Conference: Advanced Metering, Protection, Control, Communication, and

    Distributed Resources, 2007. Pg 39-54

    [11] Mark Adamiak, William Premerlani, Dr. Bogdan Kasztenny, Synchrophasors:

    Definition, Measurement, and Application.

    [12] [21] Vladimir V. Terzija, (2006) Adaptive Underfrequency Load Shedding Based on

  • 7/27/2019 Research Proposal for high voltage network

    26/27

    26

    the Magnitude of the Disturbance Estimation, IEEE TRANSACTIONS ON POWER

    SYSTEMS, VOL. 21, NO. 3.

    [13] Emmanuel J. Thalassinakis, Member, IEEE, and Evangelos N. Dialynas,(2004)

    A Monte-Carlo Simulation Method for Setting the Underfrequency Load Shedding Relays

    and Selecting the Spinning Reserve Policy in Autonomous Power Systems, IEEE

    TRANSACTIONS ON POWER SYSTEMS, 2004,VOL. 19,NO. 4.

    [14] Farrokh Shokooh, Shervin Shokooh, Jacques Tastet, Hugo Castro, Tanuj Khandelwal,

    Gary Donner, An Intelligent Load Shedding System Application in a Large Industrial

    Facility, Industry Applications Conference, 2005. Fourtieth IAS Annual Meeting.

    Conference Record of the 2005 (Volume:1 ) pg 417-425

    [15] Wen-Jen Lee, Microcomputers based intelligent load shedding. Power Delivery, IEEE

    Transactions on (Volume:4 , Issue: 4 ) 2002, pg 2018 - 2024

    [16] Denis Lee Hau Aik, Member, A General-Order System Frequency Response Model

    Incorporating Load Shedding: Analytic Modeling and Applications, IEEE

    TRANSACTIONS ON POWER SYSTEMS, 2006, VOL. 21,NO.2.

    [17] Rung-Fang Chang, Chan-Nan Lu, Tsun-Yu Hsiao, Prediction of Frequency Response

    After Generator Outage Using Regression Tree, IEEE TRANSACTIONS ON POWER

    SYSTEMS, 2005, VOL. 20, NO. 4.

    [18] Adly. A. Girgis, William Peterson, Adaptive estimation of frequency deviation and its

    rate of change for load shedding, Power Delivery, IEEE Transactions on (Volume:5 ,

    Issue: 2 ),2002

    [19] Adly.A.Girgis, Shruti Mathure, Dissertation on Load shedding using voltage,

    frequency and their rate of change.

    [20] Adly.A.Girgis, Ding Xu, Optimal Load shedding strategies in power systems with

    distributed generation. Power Engineering Society Winter Meeting, 2001. IEEE Volume:2

    pg 788-793

    [21] Li Zhang, Jin Zhong, UFLS Design by using f and integrating df/dt., Power Systems

    Conference and Exposition, 2006. Pg 1840-1844

    [22] Xiaofu Xiong, Wenyuan Li, A New under frequency load shedding scheme considering

    load frequency characteristics. Power System Technology, 2006. PowerCon 2006. Pg 1-4

    [23] H. Seyedi, M. Sanaye-Pasand, M.R. Dadashzadeh, Design and Simulation of an adaptive

    Load Shedding Algorithm using a real network. Power India Conference, IEEE, 2006

    [24] Matthew A. Mitchell, J.A. Peas Lopes, J.N. Fidalgo James D. McCalley,

    http://ieeexplore.ieee.org/xpl/RecentIssue.jsp?punumber=61http://ieeexplore.ieee.org/xpl/RecentIssue.jsp?punumber=61http://ieeexplore.ieee.org/xpl/tocresult.jsp?isnumber=1488http://ieeexplore.ieee.org/xpl/tocresult.jsp?isnumber=1488http://ieeexplore.ieee.org/xpl/RecentIssue.jsp?punumber=61http://ieeexplore.ieee.org/xpl/RecentIssue.jsp?punumber=61
  • 7/27/2019 Research Proposal for high voltage network

    27/27

    Using a Neural Network to Predict the Dynamic Frequency Response of a Power System

    to an Under-Frequency Load Shedding Scenario. Power Engineering Society Summer

    Meeting, 2000. IEEE (Volume:1 ) pg 346 - 351

    [25] M. Parniani, A. Nasri, SCADA based under frequency load shedding integrated with rate

    of frequency decline. Power Engineering Society General Meeting, 2006. IEEE

    [26] Juhwan Jung, Chen-Ching Liu, Steven Tanimoto, Vijay Vittal, Adaptation in

    Load Shedding under vulnerable operating conditions. Power Systems, IEEE Transactions

    on (Volume:17 , Issue: 4 ) pg 1199-1205

    [28] B. Suneetha, S. Hemachandra, B. Gowri Prasad & A. Jayanth, Application Of Neural

    Network in Load Shedding and some Predictable Functioning of Load Shedding

    Methods, International Journal of Electronics, Communication & Instrumentation

    Engineering Research and Development (IJECIERD) Vol. 3, Issue 2, Jun 2013, pg 45-50

    [29] E. J. Thalassinakis, E. N. Dialynas, D. Agoris, Method Combining Ann's and Monte

    Carlo Simulation for the Selection of the Load Shedding Protection Strategies in

    Autonomous Power System, IEEE Trans. on PowerSystem, Vol. 21, No.4, pp. 1574-82,

    2006.

    [30] C. T. Hsu, M. S. Kang and C. S. Chen, Design of Adaptive Load Shedding by Artificial

    Neural Networks, IEE Generation, Transmission, Distribution, Vol. 152, No. 3, pp. 415-

    421, 2005.

    [31] T. Amraee, B. Mozafari, A. M. Ranjbar, An Improved Model for Optimal Under Voltage

    Load Shedding, Particle Swarm Approach, IEEE Power Conf. India, April 2006.

    [32] Gh. Isazadeh, R. Hooshmand and A. Khodabakhshian, Design Of An Adaptive Dynamic

    Load Shedding Algorithm Using Neural Network in the Steelmaking Cogeneration

    Facility, IJST, Transactions of Electrical Engineering, Vol. 36, No. E1, Pp 67-82,2012

    [33] Yang XS (2008) Nature-inspired Metaheuristic Algorithms. Luniver Press

    [34] Glover F and Laguna M (1997) Tabu Search. Kluwer Academic Publishers

    [36] Yang, X.S. & Deb, S. (2009) Cuckoo search via Lvy flights, Proc. World Congress on

    Nature & Biologically Inspired Computing (NaBIC 2009, India),IEEE Publications, 210

    214.

    http://ieeexplore.ieee.org/xpl/tocresult.jsp?isnumber=25389http://ieeexplore.ieee.org/xpl/tocresult.jsp?isnumber=25389