45
Request for Proposal Explosive Cargo Load Unload Apron Mihail Kogalniҫeanu Air Base, Romania Contract Number: W912GB-17-D-0001 FY 2019 Corrected Final RFP Submittal 28 December 2018 Revised 20 May 2019 WSP USA 277 Bendix Road Suite 300 Virginia Beach, VA 23452

Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

Request for Proposal

Explosive Cargo Load Unload Apron

Mihail Kogalniҫeanu Air Base, Romania

Contract Number:

W912GB-17-D-0001

FY 2019

Corrected Final RFP Submittal

28 December 2018 Revised 20 May 2019

WSP USA

277 Bendix Road

Suite 300

Virginia Beach, VA 23452

Page 2: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

i  

Section 01 10 10 Statement of Work

Table of Contents 1.0  Project Information ........................................................................................................................... 1 

2.0  Project Description ............................................................................................................................ 1 

2.1.  General .......................................................................................................................................... 1 

2.2.  Project Site .................................................................................................................................... 2 

2.3.  Explosive Cargo Load Unload Apron ............................................................................................. 2 

2.4.  Parking Apron ................................................................................................................................ 3 

2.5.  Demolition and Debris Removal ................................................................................................... 3 

3.0  Permits and Approvals ...................................................................................................................... 3 

3.1.  Urbanism Certificate ..................................................................................................................... 3 

3.2.  Building Permit .............................................................................................................................. 3 

3.3.  Demolition Permit ......................................................................................................................... 4 

3.4.  Tree Removal and Endangered Species Permits ........................................................................... 4 

  Tree Removal Permit ............................................................................................................ 4 

  Endangered Species Permit .................................................................................................. 4 

3.5.  Work Plan and Construction Traffic Circulation Approval ............................................................ 5 

3.6.  DDESB Certification ....................................................................................................................... 5 

4.0  Project Requirements ....................................................................................................................... 5 

4.1.  Design Criteria ............................................................................................................................... 5 

4.2.  Explosive Cargo Apron, Parking Apron, and Taxiway Design ........................................................ 7 

  Design Life ............................................................................................................................. 7 

  Layout and Geometry ........................................................................................................... 7 

  Geometric Conflicts ............................................................................................................... 8 

  Tie‐Down and Grounding Requirements .............................................................................. 8 

  Airfield Pavements ................................................................................................................ 9 

  Pavement Markings ............................................................................................................ 13 

4.3.  Jet Blast Deflection ...................................................................................................................... 13 

4.4.  Access Roads ............................................................................................................................... 13 

4.5.  Stormwater and Drainage ........................................................................................................... 14 

  Background and Existing Conditions ................................................................................... 14 

  Hydrologic Criteria .............................................................................................................. 14 

  Spread ................................................................................................................................. 14 

Page 3: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

ii  

  Drainage System ................................................................................................................. 15 

  Runway Clear Zone Requirements ...................................................................................... 15 

  Oil/Water Separation .......................................................................................................... 15 

  Stormwater Low Impact Development (LID)/Volume Reduction ....................................... 15 

  Stormwater Base Bid ........................................................................................................... 16 

  Optional Bid Item 4 ‐Alternative Stormwater Management Area ...................................... 16 

4.6.  Earthwork .................................................................................................................................... 16 

  General Requirements ........................................................................................................ 16 

  Topsoil ................................................................................................................................. 16 

  Existing Fill ........................................................................................................................... 17 

  Trenching and Excavation for Appurtenances .................................................................... 17 

  Slopes .................................................................................................................................. 17 

  Excavation Support Systems ............................................................................................... 17 

  Subgrade ............................................................................................................................. 18 

  Existing Utilities ................................................................................................................... 18 

4.7.  Erosion, Sedimentation, and Dust Control ................................................................................. 18 

  Erosion and Sediment Control ............................................................................................ 18 

  Dust Control ........................................................................................................................ 19 

4.8.  Fire Protection ............................................................................................................................ 19 

  Background and Existing Water Systems ............................................................................ 19 

  Base Bid Water Supply ........................................................................................................ 19 

  Optional Bid Item 2 – Alternate Water Supply ................................................................... 19 

  Optional Bid Item 3 – Alternate Water Supply ................................................................... 19 

  Fire Protection Requirements ............................................................................................. 20 

4.9.  Electrical and Telecommunications ............................................................................................ 22 

  Base Bid Power Sources ...................................................................................................... 22 

  Optional Bid Item 1 – Alternative Power Source (Fire Protection and Floodlighting) ........ 23 

  Electrical Systems ................................................................................................................ 23 

  Airfield Ground Lighting and Signage .................................................................................. 23 

  Floodlighting ....................................................................................................................... 24 

  Lightning Protection and Grounding ................................................................................... 24 

  Power Supply ...................................................................................................................... 25 

  Communications ................................................................................................................. 25 

Page 4: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

iii  

  Cable and Conduit Routing ................................................................................................. 26 

4.10.  Perimeter Fence Reconstruction ............................................................................................ 26 

4.11.  Landscaping ............................................................................................................................. 26 

4.12.  Construction Duration ............................................................................................................ 26 

5.0  Construction Specification Requirements ...................................................................................... 26 

6.0  Environmental Requirements ......................................................................................................... 27 

6.1.  Hazardous Materials ................................................................................................................... 27 

  Soils ..................................................................................................................................... 27 

  Groundwater ....................................................................................................................... 27 

  Building Materials ............................................................................................................... 28 

  Threatened and Endangered Species ................................................................................. 28 

6.2.  Unexploded Ordinance (UXO) ..................................................................................................... 28 

7.0  D‐B Contractor’s Design and Submittal Requirements ................................................................... 28 

7.1.  General ........................................................................................................................................ 28 

7.2.  35% Concept Design.................................................................................................................... 29 

7.3.  65% Interim Design ..................................................................................................................... 29 

7.4.  95% Final Design ......................................................................................................................... 29 

7.5.  100% Corrected Final Design ...................................................................................................... 29 

7.6.  As‐Built Documentation .............................................................................................................. 30 

7.7.  Survey .......................................................................................................................................... 30 

7.8.  Geotechnical Investigation, Data and Report ............................................................................. 30 

  D‐B Contractor’s Geotechnical Engineer ............................................................................ 30 

  D‐B Contractor’s Geotechnical Report ................................................................................ 31 

7.9.  Recommended Drawings to be Developed by the D‐B Contractor ............................................ 31 

8.0  Design‐Build Quality Control ........................................................................................................... 34 

8.1.  Contractor Quality Control Plan (CQC) ....................................................................................... 34 

  CQC Contents ...................................................................................................................... 34 

8.2.  Design Quality Control Plan (DQC) .............................................................................................. 35 

  DQC Contents ...................................................................................................................... 35 

8.3.  Testing ......................................................................................................................................... 36 

  Testing Requirements ......................................................................................................... 36 

9.0  Construction Phasing Requirements ............................................................................................... 36 

9.1.  General ........................................................................................................................................ 36 

Page 5: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

iv  

9.2.  Haul Roads .................................................................................................................................. 36 

9.3.  Airfield Pavement Closures ......................................................................................................... 37 

9.4.  Airfield Construction ................................................................................................................... 37 

9.5.  D‐B Contractor Laydown Area and Concrete Batch Plant .......................................................... 37 

10.0  MKAB Requirements ....................................................................................................................... 38 

10.1.  General .................................................................................................................................... 38 

10.2.  Romanian Public Holidays ....................................................................................................... 38 

10.3.  U.S. Federal Holidays .............................................................................................................. 38 

10.4.  Night and Weekend Restrictions ............................................................................................ 39 

10.5.  Base Access Procedures .......................................................................................................... 39 

10.6.  Construction Site Restrictions ................................................................................................. 39 

10.7.  Flightline and/or Immediate Vicinity of Construction Site Requirements .............................. 40 

 

Appendices

Appendix A – RFP Drawings

Appendix B – Project UFGS Specification List and Division 00 and 01 Specifications

Appendix C – Bid Schedule

Appendix D – Form DD 1354

Appendix E – Geotechnical Report

Appendix F – Environmental Assessment Report

Appendix G – Fire Hydrant Flow Test Report

Page 6: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

1  

Section 01 10 10 Statement of Work

1.0 Project Information

Contract Number To Be Determined (TBD)

Task Order Number TBD

Work Order Number TBD

Project Title Explosive Cargo Load Unload Apron, Mihail Kogălniceanu AB, RO

Project Sponsor U.S. Army in Europe (USAREUR)

Location Mihail Kogălniceanu Air Base, Romania

Lat/Long 44°21’43.43” N, 28°28’14.79” E

Government Engineer U.S. ARMY COPRS OF ENGINEERS, EUROPE DISTRICT

Project Manager Tarek Eljizi, CENAU Tel: (+49)611-9744-2422

Email: [email protected]

2.0 Project Description 

2.1. General The project consists of a new explosive cargo load unload apron, a new parking apron, two new ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and construction efforts must be executed in accordance with the Host Nation agreements for European Deterrence Initiatives (EDI) to include construction and environmental permits. The existing taxiway oriented parallel to the existing runway is known as parallel Taxiway F. The existing taxiway with temporary arm/disarm pad connecting Taxiway F to the existing runway is known as Taxiway E. The new taxiway located parallel to and south of Taxiway E connecting to Taxiway F must be known as Taxiway G. The new ladder taxiway connecting the existing runway to the new explosive cargo load unload apron and Taxiway F must be known as Taxiway H. A conceptual design accompanies this Statement of Work (SOW) as Appendix A of this document. The conceptual drawings provided in Appendix A of this RFP are notional only. The D-B Contractor must develop and complete the entire design. The D-B Contractor must be the Designer of Record (DOR).The project must be designed in accordance with the design criteria outlined in this Statement of Work and the conceptual drawings provided in Appendix A. As the DOR, the D-B Contractor must collect data and revise the conceptual design as needed to provide a fully functional layout in compliance with all applicable regulations and design standards and in consideration of all valid constraints and impacts. In addition, since this project includes a fire protection system, a Qualified Fire Protection Engineer (QFPE) must be included as part of the D-B Contractor’s design team. The D-B Contractor must be responsible for the professional quality, technical accuracy, and the coordination of all designs, drawings, specifications, and other non‐construction services furnished by the D-B Contractor. The D-B Contractor must, without additional compensation, correct or revise any errors or deficiency in its designs, drawings, specifications, and other non‐

Page 7: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

2  

construction services and perform any necessary rework or modifications, including any damage to real or personal property, resulting from the design error or omission. The D-B Contractor’s point of contact throughout the project must be the USACE Contracting Officer’s Representative (COR).

2.2. Project Site The site for this facility is in the northwest corner of the airfield section of MKAB and is located immediately adjacent to Mihail Kogălniceanu International Airport as shared by the U.S. Army and Romanian Ministry of Defense (MOD). The combined facility is located approximately 25 km northwest of the city of Constanta. MKAB is positioned at 44°21’43.43” N longitude and 28°28’14.79” E latitude and has an elevation of 108 meters (353 feet) above sea level. The runway is owned and operated by the Romanian Government civilian air authority and the taxiways located west of the runway are owned and operated by the Romanian MOD in conjunction with the Romanian Government civilian air authority. The area where the facilities will be constructed covers approximately 19.2 hectares (47.5 acres). Most of this area was previously developed to serve previous iterations of MKAB operated by the Romanian military. Several earthen berms, concrete bunkers, buildings, concrete and gravel roads and platforms, and debris piles cover much of the site. At the time this RFP was prepared, the site is bounded by the MKAB perimeter fence to the north, the airport runway to the east, existing buildings and airfield infrastructure to the south, and railroad tracks to the west. Multiple future projects are adjacent to this project and are anticipated to be in design and/or under construction at the time this RFP is issued. A Railhead Facility will be located to the west, a Fuel Storage Facility will be located southwest, a C-17 parking apron will be located south, and a U.S. Army Ready Building will be located southwest of the parking apron portion of this project. These adjacent projects are collectively referred to as MK-1 and are anticipated to provide opportunities for the D-B Contractor to make utility connections. In addition, a future 2 MW power station will be located west of the future MK-1 Railhead Facility. This RFP assumes these projects will provide utility connections, which are included as Base Bid items. The D-B Contractor must coordinate and work with any contractors in the area.

2.3. Explosive Cargo Load Unload Apron The explosive cargo load unload apron must accommodate a single C-17 aircraft and will allow the aircraft to taxi in and taxi out under its own power. Aircraft will access the apron from proposed ladder Taxiway H. Aircraft will taxi out from this apron eastward along Taxiway H to parallel Taxiway F, turn south onto Taxiway F and turn onto the proposed parking apron or head further south to Taxiway G.

The center of the curved portion of the explosive cargo load unload apron must be an adequate distance away from the edge of the runway to ensure take-off and landing is not impacted by the presence of explosive cargo on this apron. Mooring points will be provided to accommodate a single C-17, a single UH-60, and single CH-47 rotary wing aircraft using the apron at different times.

The explosive cargo load unload apron must be constructed of Portland Cement Concrete (PCC) pavement with a drainage layer. Paved and unpaved shoulders must be provided along the access taxiway and around the perimeter of the pad to protect adjacent areas from jet blast, help mitigate foreign object damage (FOD), permit equipment storage, and to facilitate drainage. Paved shoulders must be constructed of Hot Mix Asphalt (HMA) pavement. An Oil Water

Page 8: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

3  

Separator (OWS) must be provided to minimize adverse environmental impacts in case of an inadvertent spill of petroleum, oil, or lubricants (POL) or other liquids from the aircraft.

2.4. Parking Apron 

The parking apron must accommodate three (3) C-17 aircraft simultaneously and allow aircraft to taxi in and taxi out under their own power. Aircraft will access the parking apron from parallel Taxiway F. Aircraft will taxi out to parallel Taxiway F heading south and turn onto Taxiway G to gain access to the runway. The section of existing Taxiways E and F intersected by Taxiway G will be reconstructed to support loads imparted by C-17 aircraft.

The parking apron must be constructed of Portland Cement Concrete (PCC) pavement with a drainage layer. Paved and unpaved shoulders must be provided along the access taxiway and around the perimeter of the pad to protect adjacent areas from jet blast, help mitigate foreign object damage (FOD), permit equipment storage, and to facilitate drainage. Paved shoulders must be constructed of Hot Mix Asphalt (HMA) pavement. An Oil Water Separator (OWS) must be provided to minimize adverse environmental impacts in case of an inadvertent spill of petroleum, oil, or lubricants (POL) other liquids from the aircraft.

Tie-downs in the parking apron must be provided to allow simultaneous mooring of three (3) C-17 aircraft and simultaneous mooring of three (3) CH-47 rotary wing aircraft and the maximum number of UH-60 aircraft as feasible. Location of moorings must assume fixed wing and rotary wing aircraft will be occupying the parking apron at different times.

2.5. Demolition and Debris Removal Earthen berms, bunkers, buildings, and debris piles that lie within the project footprint and within required clear zones must be removed and hauled off site in compliance with Romanian Government rules and regulations as part of the scope of work for this project. Note that demolition must not commence prior to issuance of an Urbanism Certificate and Demolition Permit by the Romanian Government (See Section 3.0 Permits and Approvals).

3.0 Permits and Approvals It is the D-B Contractor’s responsibility to verify all permitting procedures and requirements and obtain required permits and approvals prior to starting construction. Basic Information regarding Romanian Government approvals and permits follows. 3.1. Urbanism Certificate

This Certificate will be obtained by the U.S. government and is required for delisting buildings from Romanian Government records prior to demolition and construction. The Urbanism Certificate will include all Building Permit and Demolition Permit requirements that the D-B Contractor will need to fulfill. At the time RFP was prepared, U.S. Army Europe had begun the application process with the Host Nation (HN) authority to obtain the Urbanism Certificate. The requirements of the Building Permit and Demolition Permit will be provided by the COR when they become available. The D-B Contractor is alerted to the fact that the Urbanism Certificate does not give the right to execute the construction work.  

3.2. Building Permit The D-B Contractor is responsible for obtaining a Building Permit from the HN government. The requirements of the Building Permit are provided in the Urbanism Certificate (see Section 3.1). Construction works are only allowed on the basis of a building permit in accordance with Romanian Governing Law No. 50/1991. To obtain the building permit, the D-B Contractor must apply to the appropriate City Hall responsible for the land on which the facility is proposed to be

Page 9: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

4  

built. The D-B Contractor is typically required to provide the following documentation in support of the application:

Urbanism Certificate; Proof of the property title of the land and/or existing buildings or an extract from the

updated cadastral plan and an extract from the updated land register information on the application date in the case in which the law does not provide otherwise;

Necessary legal approvals and agreements established by the Urbanism Certificate; The technical project/basis of design for authorizing the execution of construction works;

Proof of payment of legal fees.  

The Building Permit documentation typically requires professional design and/or endorsement by architects and engineers with diplomas recognized by the Romanian Government. Documentation includes:

Written description of the project that includes: o technical narratives, o supporting data and calculations, o cost estimate, and o all supporting information including but not limited to items such as geotechnical

studies and proof of authorization for utility connections Project drawings, including general layout plans and project specific layout plans.

Romanian Government requirements are typically provided after application is made to the reviewing authority. The Building Permit includes all areas to be utilized by D-B Contractor, including off-site areas.

3.3. Demolition Permit The D-B Contractor is responsible for obtaining a Demolition Permit from the HN government. The requirements of the Demolition Permit are provided in the Urbanism Certificate (see Section 3.1). The D-B Contractor must adhere to the requirements of the Demolition Permit, which will be provided by the COR when they become available. The D-B Contractor must coordinate permitting through the COR.

3.4. Tree Removal and Endangered Species Permits

Tree Removal Permit The D-B Contractor is responsible for obtaining the Tree Removal Permit from the HN government. The legal framework and procedural steps needed for obtaining official authorization for harvesting vegetation are provided in the Task 2.5 of the Phase II Environmental Site Assessment (Task 2.5), found in Appendix F. Per section 3.2 of Task 2.5., the Romanian MOD begins the process for the HN Government to determine the tree removal permit requirements and the D-B Contractor and their licensed harvesting company must obtain the permit. The D-B Contractor’s permit requirements will be provided by the COR when they become available.

Endangered Species Permit The D-B Contractor is responsible for obtaining the Endangered Species Permit from the HN government. A Threatened and Endangered Species (TES) Survey was conducted under contract by U.S. Army Corps of Engineers, Europe District as Task 2.6 of the Phase II Environmental Site Assessment (Task 2.6). Flora, Fauna, and Natural Habitats were assessed in the TES, which is located in Appendix F of this RFP. According to the TES, seven (7) avian breeding species are protected under the European Union Birds Directive - Natura 2000 (2009/147/EC) and ten (10) avian breeding species are protected under Romanian Ordinance 57/2007/Law 4/2011. The

Page 10: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

5  

Romanian MOD typically begins the process for the HN Government to determine permit requirements and the D-B Contractor typically obtains the permit. The D-B Contractor’s permit requirements will be provided by the COR when they become available. The D-B Contractor must coordinate any endangered species permitting through the COR and Romanian MOD.

3.5. Work Plan and Construction Traffic Circulation Approval The D-B- Contractor must prepare and submit to the Romanian civilian air authority through the COR a phased work plan including temporary construction and airport traffic circulation on all roads and work areas within 150 meters (492 feet) of the runway. Emergency procedures are also included in this submittal. The D-B Contractor must assume a minimum duration of six (6) to nine (9) months to obtain approval after submitting the application. The D-B Contractor must adhere to the approved plan throughout construction. This approval must be in place prior to obtaining a Building Permit.

3.6. DDESB Certification The D-B Contractor’s 100% design requires certification by the Department of Defense Explosives Safety Board (DDESB) before construction can commence. The D-B Contractor must anticipate a DDESB review period of 180 calendar days maximum after the 100% design submittal is accepted by the U.S. Government.

4.0 Project Requirements 4.1. Design Criteria

The facility must be compatible with applicable United States (U.S.) Department of Defense (DoD), Unified Facilities Criteria (UFC), US Air Force, US Army, NATO, and Host Nation (HN) design criteria, as well as all laws and acts. All relevant Host Nation (Romanian) and U.S. laws and building regulations and the applicable technical regulations, guidelines, standards, manufacturer specifications, etc. apply, whereby the Host Nation Building laws have priority. It is the DOR’s responsibility to demonstrate that the Host Nation standard is equal to cited U.S. Standards or specifications being superseded. The D-B Contractor’s design criteria sources must include, but not be limited to the following:

UFC 3-201-01 Civil Engineering UFC 3-210-10, Low Impact Development UFC 3-230-01, Water Storage, Distribution, and Transmission UFC 3-230-06a, Subsurface Drainage UFC 3-250-01 Pavement Design for Roads and Parking UFC 3-260-01, Airfield and Heliport Planning and Design UFC 3-260-02, Pavement Design for Airfields UFC 3-260-04, Airfield and Heliport Marking UFC 3-260-17 O&M Manual: Standard Practice for Dust Control on Roads, Airfields, Base

Camps, and Adjacent Areas UFC 3-301-01 Structural Engineering UFC 3-501-01 Electrical Engineering UFC 3-510-01 Foreign Voltages and Frequencies Guide UFC 3-530-01 Interior and Exterior Lighting Systems and Controls UFC 3-535-01 Visual Air Navigation Facilities, Including Change 1, 7 March 2018 UFC 3-535-02 Design Drawings for Visual Air Navigation Facilities, 21 May 2018 UFC 3-540-01 Engine-Driven Generator Systems for Backup Power Applications, with Change 1 UFC 3-550-01 Exterior Electrical Power Distribution UFC 3-575-01 Lightning and Static Electricity Protection Systems

Page 11: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

6  

UFC 3-600-01, Fire Protection Engineering for Facilities UFC 4-021-02 Electronic Security Systems

UFC 4-832-01N, Design: Industrial and Oily Wastewater Control/MIL-HDBK-1005/16, Wastewater Treatment System Design Augmenting Handbook 

Section 438 of the U.S. Energy and Security Act

NATO Bi-SC DIR-85 NATO Approved Criteria and Standards for Airfields (most current edition)  STANAG 3158, Day Marking of Airfield Runways and Taxiways STANAG 3316, Airfield Lighting AASTP-1 Manual of NATO Safety Principles for The Storage of Military Ammunition and

Explosives NFPA-1, Fire Code NFPA 10, Standard for Portable Fire Extinguishers NFPA 20, Standard for the Installation of Stationary Fire Pumps for Fire Protection NFPA 22, Standard for Water Tanks NFPA 24, Standard for the Installation of Private Fire Service Mains and Their Appurtenances NFPA 291, Recommended Practice for Fire Flow Testing and Marking of Hydrants NFPA 72, National Fire Alarm Signaling Code NFPA 780 Standard for the Installation of Lightning Protection Systems NFPA 1963, Standard for Fire Hose Connections (unless superseded by local requirements) Airforce AFM 88-9/Army TM 5-811-3, Electrical Design Lightning and Static Electricity Protection AC 150/5320-5 Surface Drainage Design AFI 32-1065-USAFE, Grounding Systems AFMAN 91-201 Explosive Safety Standards Army Pamphlet 385-64: Ammunition and Exploding Safety Standards AWWA M31, Distribution System Requirements for Fire Protection DOD Standard 6055.09-M DoD Ammunition and Explosives Safety Standards, Series of Manuals DoD Standard 6055.9 ETL 07-3: Jet Engine Thrust Standoff Requirements for Airfield Asphalt Edge Pavements IEC 60364 Electrical Installations for Buildings Illuminating Engineering Society, Technical Memorandum TM-15-11 Luminaire Classification

System for Outdoor Luminaires Mil-Hdbk 419, Grounding, Bonding and Shielding NAVAIR 51-50AAA-2, General Requirements for Shore Based Airfield Marking and Lighting C 169/1988 Normative for Execution of Excavation Works for Foundations of Civil and Industrial

Buildings; CR 0/2012 Design Code: Basis of structural design; NE 012-1/2007 Normative for Production and Execution of Concrete, Reinforced Concrete and

Post-Tensioned Concrete. Part 1: Concrete Production; NE 012-2/2010 Normative for Production and Execution of Concrete, Reinforced Concrete and

Post-Tensioned Concrete. Part 2: Execution of Concrete Works; Sr En 206-1/2002 Concrete. Part 1: Specification, Performance, Production and Conformity; ST 016/1997 Technical Specification. Criteria and Methods for Determining Constructions

Settlement by Measurements; St 009/2011 Technical Specification Related to Steel Products Used as Reinforcement:

Requirements and Performance Criteria; STAS 10493/1976 Terrestrial Measurements. Marking and Signaling of Points for Monitoring of

Settlements and Displacements of Constructions and Grounds; STAS 2745/1990 Foundation Soils. Monitoring of Settlements Using Topographical Methods; NP 112/2004 Normative for design of shallow foundations;

Page 12: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

7  

NP 113/2004 Normative for design, execution and monitoring of retaining walls;

NP 124/2010 Normative for geotechnical design of retaining systems;  NP 125/2010 Normative for foundation design on soils sensitive to wetting; P 100-1/2013: Seismic design code;

P 130/1999 Normative for Monitoring Construction Behavior in Time; 

P118/2-2013 Fire Safety Regulations for Construction 

4.2. Explosive Cargo Apron, Parking Apron, and Taxiway Design  Design Life

The airfield pavement systems must be designed to a minimum life of 20 years in accordance with UFC 3-260-02, Chapter 2.

Layout and Geometry 

4.2.2.1. Horizontal Geometry The D-B Contractor must design and construct an access taxiway (Taxiway H) and a semicircular explosive load unload apron that accommodates parking for one C-17 aircraft. Locate the pad so that no part of the pad or the parked aircraft penetrates the approach/departure surfaces or the 7:1 transitional surface. The facility must be designed for aircraft to taxi in and out under their own power. Tie-down/mooring points/eyes are required for one C-17, one UH-60, and one CH-47 aircraft. Grounding points are required per the requirements of UFC 3-260-01, Appendix B, Section 11, Static Grounding Tie-down. Additionally, the D-B Contractor must construct a new access taxiway and new aircraft parking apron, located south of the explosive cargo apron. The new access taxiway (Taxiway G) will be constructed parallel to and south of Taxiway E. The runway to taxiway centerline curves must be constructed to a single 45.72 m (150 ft) radius to meet UFC 3-260-01 taxiway centerline criteria. The taxiway to taxiway centerline radii curves must be constructed to a 38.1 m (125 ft) radius to meet UFC 3-260-01 criteria. A minimum 45.72 m (150 ft) clearance from taxiway centerline to fixed or mobile obstacles must be provided. A minimum 38.1 m (125 ft) clearance from apron boundary markings to fixed or mobile objects must be provided. A taxiway connection between Taxiway H and Taxiway F must be provided. Due to the limited area allowable, the edge radius on the west side of this intersection is 25m (82 ft) to hold the north-south project limits. The pavement must be configured to maintain the required 38.1m (125 ft) centerline radius at this intersection. All taxiways and taxilanes must have a width of 22.5 m (74 ft) per NATO geometric design criteria. The new facility must be located so that no part of the aprons or parked aircraft penetrates the approach/departure surfaces or the 7:1 transitional surface. Explosives site planning is required and the facility must be sited in accordance with DoD Standard 6055.9. Separation from electromagnetic radiation is required to prevent ignition of electro-explosive devices (EED). The primary explosives site development criteria are defined as follows:

Page 13: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

8  

• 13,608 kg (30,000 lb.) Class HD 1.1 • Quantity Distance (QD) arc of 380 m (1,250 ft) radius per Department of the Army Pamphlet 385-64: Ammunition and Explosives Safety Standards, dated 24 May 2011 (DA PAM 385-64).

• Inhabited Building Distance (IBD) arc of 380 m (1,250 ft) radius per Table 8-7 of DA PAM 385-64.

4.2.2.2. Vertical Geometry

Longitudinal slopes for the new taxiways must be governed by the existing pavement to remain. Longitudinal slopes of Taxiway G must be governed by the existing pavement to remain on Taxiway E and the tie point on the runway. All longitudinal slopes and profiles must be developed to maximize the existing grade conditions and provide for smooth transitions for taxiing aircraft. The longitudinal grade of taxiways and shoulders must not exceed 3.0% and taxiway transverse grades must be between 1% and 1.5% per UFC 3-260-01. The transverse grade of paved and unpaved parking apron shoulders must be between 2% and 4%. Parking apron surface grades must be a maximum of 1% in accordance with Romanian criteria.

Geometric Conflicts The conceptual layout provided in this RFP is the result of mixing Army, UFC and NATO criteria to avoid conflicts with surrounding features with respect to QD/IBD circles and clear distances and to keep the project within the Primary Facilities quantity limits defined in the DD 1391 programming document. The D-B Contractor must anticipate utilizing both NATO and UFC criteria in their design to keep within established physical and programming limits. Preliminary design of the future adjacent railhead project shows that this project will require design coordination with the future railhead facility. At the 95% design submittal stage, the future railhead project extended approximately one meter into the parking apron taxilane clear zone. A section of jet blast fence is provided on the conceptual drawings to protect the future railhead facility from jet blast. Refer to Section 4.3 for more information.

Tie-Down and Grounding Requirements The parking apron must accommodate long-term parking for two C-17 aircraft and short-term parking for one C-17 located on the peripheral taxilane. Tie-down/mooring points/eyes are required on the parking apron for three (3) C-17, three (3) CH-47, and the maximum number of UH-60 aircraft as feasible. Grounding points are required per the requirements of UFC 3-260-01, Appendix B, Section 11 - Static Grounding Tie-down. On the explosive cargo apron, the D-B Contractor must provide tie-downs/moorings for a single C-17, a single UH-60, and single CH-47 rotary wing aircraft using the apron at different times. Grounding points are required per the requirements of UFC 3-260-01, Appendix B, Section 11 - Static Grounding Tie-down.

Page 14: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

9  

Airfield Pavements The design of the airfield pavement must be in accordance with UFC 3-260-01 Airfield and Heliport Planning and Design and UFC 3-260-02 Pavement Design for Airfields using the US Air Force requirements. This project is in a region where frost design is required; therefore, the base courses must utilize non-frost susceptible materials and a subdrain system must be provided. The taxiways and aprons must be surfaced with Portland Cement Concrete (PCC). The pavement sections developed in the following paragraphs are to be considered minimum requirement sections. The Design Build Contractor’s designer is the designer of record. As such, the D-B Contractor is responsible for the ultimate design and thickness of the pavement layers for this project. PCASE software may be utilized, per UFC 3-260-02. This software is available for download at http://www.pcase.com. In no case, unless authorized by USACE, must the constructed airfield pavement section be less than what is specified in this RFP. UFGS Specification Section 01 33 16.00 and Section 7.0 of this RFP provides geotechnical investigation and reporting requirements to be used in pavement design. The D-B Contractor's geometric layout and pavement design of any new, temporary or altered aircraft circulation and parking area must generally consider the types of vehicles expected to use the areas, the proposed amount of traffic, the design speed and any other types of stress applied to the surfaces.

4.2.5.1. Geotechnical Information A geotechnical investigation was conducted in July 2018 and the data from that investigation can be found in Appendix E.

4.2.5.2. Subgrade Properties The geotechnical investigation revealed that the subgrade soils are variable in texture and cross-section profile, with soils primarily consisting of a Clayey Silt (CL) soil. The CBR values varied from 4.99 to 6.64, determined using a modified proctor. A maximum CBR value of 5 must be utilized for flexible pavement sections (shoulders) on existing soil. For rigid pavement design, a maximum Modulus of Subgrade Reaction (k) value of 21 kPa/mm (77 pci) must be utilized for existing soil, per the geotechnical investigation results. Based on the geotechnical data, a frost classification of F3/F4 must be utilized in the design, based on PCASE and UFC 3-260-02 Pavement Design for Airfields.

4.2.5.3. Concrete Strength The design flexural strength of the concrete must be at least 4.48 MPa (650 psi) at 90 days. No reduction in thickness must be allowed for design strengths above 4.48 MPa (650 psi).

4.2.5.4. Design Traffic The selected design traffic for this apron is US Air Force medium load traffic without the B-52 or F-15E aircraft. The U.S. Air Force traffic pattern was prescribed during the May 2018 Design Charrette because the facility design is based on C-17 aircraft, a U.S. Air Force Strategic Transport Aircraft. Specifically, the traffic must be:

C-17 100,000 passes at 265,352 kg (585,000 pounds)

Page 15: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

10  

For the explosive cargo load unload apron and the parking apron, UFC

3-260-02 assigns a Type B Traffic Area designation.

For the access taxiways, UFC 3-260-02 assigns a Type A traffic area designation.

Shoulder design must be based on the PCASE standard parameters.

The number of passes was prescribed by the USACE project programming documents. Over the 20-year design life, this translates into approximately 13 aircraft passes per day.

4.2.5.5. Thickness Design

The thickness design for the minimum pavement section was calculated using the Pavement-Transportation Computer Assisted Structural Engineering (PCASE) software version 2.09.05. The frost depth in the project vicinity is 85 cm (33.5 inches) per Romanian Standard STAS 6054-77. Printouts of the PCASE runs are shown in Figure 3-1 and Figure 3-2, below. The thickness for the explosive cargo load unload and parking aprons for Type A traffic area is 354 mm (13.93 inches) unreinforced PCC, on 113 mm (4.44 inches) drainage layer, on 390 mm (15.35 inches) of aggregate base course layer on compacted subgrade.   

Figure 3-1: PCASE Output – PCC Taxiways and Aprons

Page 16: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

11  

Figure 3-2: PCASE Output – HMA Shoulders The PCASE design for the Type A traffic area resulted in a PCC section that is approximately 8 mm (0.31 inch) thicker than the Type B traffic area. Therefore, the thicker taxiway requirement (Type A traffic) must be extended to the entire footprint of the project as the minimum design. See Figure 3-1. Figure 3-2 shows the PCASE data for the shoulder area. The thickness for the shoulder pavement, as seen in Figure 3-2 and given by PCASE, is 102 mm (4 inches) hot-mix asphalt (HMA), on 152 mm (5.98 inches) of aggregate base course on 102 mm (4.02 inches) drainage layer on geotextile fabric on compacted subgrade. However, since the site can be subjected to approximately 85 cm (33.5 inches) of frost (per Romanian Standard STAS 6054-77), the shoulder pavement thickness design must be modified as follows to prevent frost heave of the HMA pavement: The surface must be 102 mm (4 inches) HMA, on 252 mm (9.92 inches) of aggregate base course equal to the thickness of PCC access apron. The thickness of the drainage layer both for the PCC and HMA must be 113 mm (4.45 inches), the depth of the geotextile layer must match the top of the base course under the PCC apron, and an additional 383 mm (15.08 inches) layer of aggregate bring the section below the depth of frost penetration and match the PCC pavement section depth. The substantial subgrade uniformity under the two paving features will prevent heaving of the shoulder pavement. Minimum pavement sections for this facility must be as follows:

Page 17: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

12  

Pavement Thickness Design

Rigid Pavement – Taxiways and Aprons

Flexible Pavements – Paved Shoulders

354 mm Portland Cement Concrete 102 mm HMA Surface Course

113 mm Drainage Layer 252 mm Aggregate Base Course

390 mm Aggregate Base Course 113 mm Drainage Layer

383 mm Aggregate Base Course

Geotextile Geotextile

Compacted Subgrade Compacted Subgrade

4.2.5.6. Aggregate Drainage Layer

The D-B Contractor must develop UFGS specifications for drainage layers with rapid draining material and/or an open graded material stabilized with cement or bituminous material. Materials properties must follow UFC 3-260-02 Pavement Design for Airfields and UFC 3-230-06A subsurface drainage.

4.2.5.7. Subdrain Design A subdrain system must be included as part of the design to collect infiltrated surface water. This infiltrated surface water is likely to enter the pavement from the surface through cracks or joints in the pavement, through pores in the pavement, and through shoulders and adjacent areas. The system must consist of a minimum of 150 mm (6 inch) diameter Perforated Polyvinyl Chloride (PPVC) pipe, flushing and observation risers (cleanouts) at required spacing, manholes, discharge laterals, filter fabric, and trench backfill. The subdrain system must be located below frost line to the extent practicable. The system must be designed to maintain positive flow, and in accordance with UFC 3-230-06A Subsurface Drainage.

4.2.5.8. Unpaved Shoulders Per Section 5-11.1.2 of UFC 3-260-01, unpaved shoulder areas must be designed based on the maximum number of wheels and the maximum gross weight of the design aircraft on the unpaved shoulder. In no case, must the design be less than computed stress conditions created by a wheel load of 22,667 kg (50,000 lb) at a contact pressure of 1,724 kPa (250 psi).

4.2.5.9. Paved Jet Blast Protection Area In accordance with Appendix B8-1.3 and Appendix B7-3 of UFC 3-260-01 and ETL 07-3: Jet Engine Thrust Standoff Requirements for Airfield Asphalt Edge Pavements referenced therein, the area along the west edge of the parking apron between the edge of paved shoulder and the jet blast deflection berm must be paved with a minimum 51 mm (2 inches) thick layer of asphalt. This paved jet blast protection area must be designed to match the strength requirements of the unpaved shoulders.

Page 18: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

13  

4.2.5.10. Rigid Joint Pavement All airfield pavement joints must be designed in accordance with UFC 3-260-02 Pavement Design for Airfields.

Pavement Markings Aircraft surface movement and parking aprons must be marked in accordance with UFC 3-260-04 Airfield and Heliport Marking. Included are centerline stripes, nose wheel guidelines, edge markings, and runway hold position markings. The centerlines of all taxiways, taxilanes on aprons, as well as parking positions and pads will be marked with a single continuous 152-millimeter (6-inch)-wide retro-reflective yellow stripe with glass beads, highlighted by marking a black, non-reflectorized 152-millimeter (6-inch) border. In accordance with Section 7-2 of UFC 3-260-04, thermoplastic markings must not be used. All markings must be made with waterborne paint. The D-B must include this information in UFGS Specification 32 17 23 Pavement Markings based on this information.

4.3. Jet Blast Deflection Jet blast deflection must be provided on the west edge of the parking apron to protect the adjacent railhead project. Section 7 and Section 8 of UFC 3-260-01 Appendix B provide jet blast requirements and jet blast deflector criteria. A 10-meter (32.8 feet) wide (minimum) earthen berm is provided aft of C-17 parking areas shown on the conceptual drawings. The D-B must provide appropriate cover treatment to eliminate the effects of jet blast erosion. At the time this RFP was written, preliminary layout of the future railhead project showed a portion of the railhead loading area extending into the limits of the jet blast deflection berm by approximately one meter. Based on this potential conflict, a section of jet blast fence or similar barrier must be provided to protect the future railhead facility from the effect of jet blast aft of the parking apron while maintaining the aviation clear zone around the peripheral taxiway of the parking apron. The berm and blast fence are shown on the conceptual drawings in this RFP. Any jet blast fence or similar type of barrier will require drawings and supporting design calculations for all components including but not limited to the fence, connections, and foundation. The D-B Contractor must coordinate with the adjacent projects through the COR, as the constructed location of the future railhead facility may differ from the layout used in this RFP.

4.4. Access Roads Three access roads, A, B, and C, must be provided for this project. Roads A and B will connect the explosive cargo load/unload apron to the future MK-1 fuel storage facility and existing local access road, respectively. Road C is not part of the Base Bid for this project and is included as Optional Bid Item 5 to be designed and constructed only if project funds are available. Access roads must be designed in accordance with UFC 3-201-01 Civil Engineering, UFC 3-250-01 Pavement Design for Roads and Parking Areas, and UFC 3-260-01 Airfield and Heliport Planning and Design. All access roads must be conventional flexible pavement designed for a 25-year design life based on anticipated vehicles and loadings described in accordance with UFC 3-250-01 (note this design life differs from that required for airfield pavements). Per UFC 3-260-01 and NFPA-1, all access roads must have a minimum unobstructed width of 6.1 meters (20 feet) to accommodate fire and rescue vehicles. The minimum Design Vehicle is a P-23 Crash Truck (Fire Truck) with a gross weight of 350 kN (77,880 lb), per Figure E-22 of UFC 3-250-01.

Page 19: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

14  

Per Table 2-1 of UFC 3-201-01, the minimum longitudinal grade and minimum transverse grade of each access road must be 0.3% and 2.0%, respectively. Per Section 3-5 of UFC 3-250-01, design using PCASE is required for the design of all roads required in the project scope as well as additional aggregate to reduce frost penetration into the subgrade. The minimum thickness of the access road pavement section is 300 mm (12 inches), including surface course, aggregate base, and aggregate subbase. The minimum thickness of the surface course is 50 mm (2 inches). Provide a minimum thickness of 100 mm (4 inches) of aggregate base course and 150 mm (6 inches) of graded crushed aggregate for access road subbase.

4.5. Stormwater and Drainage

The D-B Contractor must design and construct any required drainage facilities to maintain existing drainage patterns and systems in accordance with Host Nation Government regulations, unless otherwise specified. Stormwater drainage such as overland sheet flow, open channels or piping must be designed in a manner that conveys stormwater away from any existing or planned structure and pavement and does not collect on or seep into the ground adjacent to or beneath any structure. Capture of storm water from exterior surfaces can be achieved by installation of inlets, gutters, swales or other adequate collecting systems. The D-B Contractor must design and construct infield grading and storm drainage features to prevent surface storage of water as required by the Host Nation to avoid Bird Air Strike Hazard (BASH) issues.

Background and Existing Conditions The existing runway is oriented north-south with existing gutters located at intervals along the edge of the concrete shoulder. Adjacent to the west of the gutters are stormwater manholes and stormwater pipes that convey runoff southward to the runway closed conveyance system’s discharge point, a canal located approximately 700 meters (0.43 miles) from the southern end of the runway that ultimately discharges to a tributary of the Black Sea. Hydrologic Criteria Hydrologic criteria must follow UFC 3-201-01 or local regulations, whichever is more stringent. Taxiways and aprons must use the minimum required by the local governing authority for airfields and heliports or a minimum 5-year storm frequency per UFC 3-201-01, whichever is more stringent. Intensity-Duration-Frequency data must be based on Romanian standards or sources, such as STAS 9470-1973. Spread Surface drainage systems must be designed in accordance with UFC 3-201-01. Per Section 3-1.2.1 of UFC 3-201-01, the maximum spread for airfields must not include runways, taxiways and heliport pavements or paved shoulders using a 5-year storm frequency. Per Section 3-1.3.1 of UFC 3-201-01, the maximum spread from airfield pavement must not encroach on the center 50 percent, along the centerline, of runways, taxiways, or apron surfaces using a 10-year storm frequency. Per Section 3-1.3.2 of UFC 3-201-01, the maximum spread for aprons is a depth of 100 mm (4 inches) using a 5-year storm frequency and the maximum ponding depth is 100 mm (4 inches) around apron inlets. Per Section 3-1.3 of UFC 3-201-01, the maximum spread for roads is ½ driving lane. The access roads must be considered local roads; therefore, a 5-year storm frequency must be used.

Page 20: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

15  

Drainage System Stormwater conveyance systems must be designed in accordance with UFC 3-201-01. Per Section 3-1.2.1 of UFC 3-201-01, the taxiways and aprons use the minimum required by the local governing authority for airfields or a minimum 5-year storm frequency. Per Section 3-1.2 of UFC 3-201-01, drainage systems serving the access roads must use a minimum 10-year storm frequency or the minimum required by the Romanian governing authority, whichever is more stringent.

A conceptual drainage design is shown on plan sheets CG101 through CG104. The D-B Contractor must design and specify all systems to meet or exceed UFC, Host Nation requirements and the most current editions of the International Building Code and International Plumbing Code. New drainage system infrastructure on the facility must be aircraft load rated. The D-B Contractor, as the DOR, must develop their own drainage system design, subject to approval by Romanian regulatory authorities, the civilian air authority and USACE during the design phase. The D-B Contractor must coordinate stormwater design and permitting through the COR. The conceptual drainage design assumes Polyethylene (PE) Pipe. Reinforced Concrete (RCP), Polypropylene (PP) Pipe, and Polyvinyl Chloride (PVC) Pipe are acceptable alternatives. Watertight joints must be provided. Corrugated metal drainage structures must not be used. Pipe connections to concrete manholes and inlets must be made with flexible, watertight connectors. Specification Section 33 40 00 Storm Drainage Systems must be developed by the D-B Contractor based on this information. To meet Romanian requirements related to hydrocarbon discharge as well as jet blast protection requirements, the shoulders on the downslope side of the aprons and ditches that receive runoff from the aprons must be asphalt-lined to prevent the seepage of pollutants into the soil. Refer to Section 4.2.3.10 Paved Jet Blast Protection Area of the RFP for additional information.

Runway Clear Zone Requirements Per Romanian Government requirements, an open ponded drainage system in the area between Taxiways E, F, G, and H adjacent to the runway is prohibited.

Oil/Water Separation Stormwater runoff generated by the parking apron and the explosive cargo apron must pass through an oil/water separator device prior to discharge. Oil/water separator devices must be designed or selected in accordance with Romanian Government regulatory requirements and standards, including HG 352/2005 and NTPA 001/2005.

Stormwater Low Impact Development (LID)/Volume Reduction Stormwater volume reduction goals must be compliant with Section 438 of the Energy Independence and Security Act (EISA) as required by UFC 3-210-10 Low Impact Development and/or by Romanian Government requirements, whichever are more stringent. The D-B Contractor must provide documentation of the project’s compliance with EISA Section 438 for all design submittals. UFC 3-210-10 requires retention of stormwater runoff from the 95th percentile storm using all known, available, and reasonable methods described in Section 3-3 Design Options for LID Features in UFC 3-210-10, including engineered natural treatment, engineered subsurface treatment, and non-potable rainwater harvesting, to the maximum extent

Page 21: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

16  

technically feasible (METF) unless otherwise directed. The Romanian Government civilian environmental authority has stated that stormwater infiltration is not allowed on the project site due to the presence of aircraft and the risk of aviation fuel spills contaminating the groundwater. As such, non-LID stormwater management options, including but not limited to sand filters, mechanical devices, and detention pipe systems must also be considered. Stormwater management practices that utilize standing or ponded water are prohibited in the area between Taxiways E, F, G, and H and the runway. Stormwater Base Bid Stormwater runoff generated by the project is to be conveyed to the future stormwater drainage system serving the MK-1 Railhead, Fuel Storage Facility, and Ready Building. The future stormwater management pond that receives discharge from this drainage system must be enlarged by the D-B Contractor under the base bid scope of work to accommodate the required runoff volume generated by the proposed facilities, estimated to be a minimum of 8,300 cubic meters (6.9 acre feet).

Optional Bid Item 4 -Alternative Stormwater Management Area If the future pond serving the future MK-1 drainage system is not available to receive proposed stormwater runoff, the D-B must connect all proposed stormwater drainage systems to a proposed stormwater management practice to be located in the northwest corner of the project, within the MKAB property boundaries, that is compliant with BASH requirements. Acceptable practices include but are not limited to a sand filter basin.

4.6. Earthwork General Requirements A limited subsurface exploration was conducted in May 2018 to support conceptual design. Physical soil character is indicated in the boring logs and test data in this RFP. The typical soil profile in the project area consists of topsoil, fill consisting of sand and building debris, and clayey silt (loess) soil. The D-B Contractor must dispose of soil excavated from the site in accordance with all HN laws and regulations a minimum distance of 1 km (0.62 mile) from the MOD property limits. The D-B Contractor is hereby notified that no borrow pit exists within the MOD property limits.  Satisfactory materials comprise any materials classified by ASTM D2487 (similar to European Standard EN ISO 14688-1) as GW, GP, GM, GP-GM, GW-GM, GC, GP-GC, GM-GC, SW, SP, and CL. Materials which do not comply with the requirements for satisfactory materials are unsatisfactory. Unsatisfactory materials also include man-made fills; trash; refuse; backfills from previous construction; and material classified as Satisfactory which contains root and other organic matter or frozen material. The D-B Contractor must develop UFGS earthwork specifications based on the Government-provided geotechnical report and their own more detailed geotechnical study described in Section 7.0 of the RFP.    Topsoil Material suitable for topsoil obtained from offsite areas and excavations is defined as: natural, friable soil representative of productive, well-drained soils in the area, free of subsoil, stumps, rocks larger than 25 mm (1 inch) diameter, brush, weeds, toxic substances, and other material detrimental to plant growth. Topsoil will be separately

Page 22: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

17  

excavated, stored, and used for surface finish in preparation for seeding, sodding, or other planting, only where topsoil is superior for grass and plant growth as compared with the remainder of the excavated material. The D-B Contractor must keep topsoil separate from other excavated materials, brush, litter, objectionable weeds, roots, stones larger than 50 mm (2 inches) in diameter, and other materials that would interfere with planting and maintenance operations.    Existing Fill Based on the government-provided geotechnical report, the existing fill appears to have been placed without acceptable compaction or quality control and contains debris and possibly other deleterious materials. Where present, the debris appears to have created voids within the fill. Utilities and underground structures are also likely present underneath the fill.   Based on the government-provided geotechnical report, the D-B Contractor must, at a minimum, remove all the existing fill beneath and extending at least 3 meters horizontally beyond the edge of any planned pavement, utility, or other structure. Fill must be removed to expose natural subgrade and confirm removal of rubble, existing foundations, utilities, underground structures, and other deleterious materials.   There are various buildings and structures in the construction area as well as buried and stockpiled concrete and other debris. The debris and demolition materials may be disposed of at an acceptable off-site landfill. Disposing of these materials by burial in areas within the MK site is prohibited. Such material must be stored above-ground on site pending disposal.   The D-B Contractor must consider utilizing segregated recycled concrete, brick, and mortar materials for select fill, pipe bedding, frost-resistant fill, sub-base, or general structural fill and must develop UFGS specifications for these materials with appropriate Quality Control criteria in accordance with UFC 3-260-02 and the limits in the applicable UFGS sections.    Trenching and Excavation for Appurtenances The D-B Contractor must follow the trench excavation requirements of appropriate UFGS specifications. Rock, where encountered, must be excavated to a depth of at least 150 mm (6 inches) below the bottom of the pipe. Excavate pipe trenches as recommended by the manufacturer of the pipe to be installed. Shore trench walls more than 1.5 meters (5 feet) high, cut back to a stable slope, or provide with equivalent means of protection for employees who may be exposed to moving ground or cave in.  

Provide excavation for manholes, catch-basins, inlets, or similar structures sufficient to leave at least 300 mm (12 inches) clear between the outer structure surfaces and the face of the excavation or support members. 

Slopes Slope excavation and protection must follow the standard requirements of UFGS Specifications 31 00 00 Earthwork for all work on thesite and in borrow areas. The D-B Contractor must provide erosion and sediment control measures for temporary and permanent slope stabilization. 

Excavation Support Systems The Contractor will have the responsibility for designing the trench shoring and sheeting system or obtaining a suitable trench box on all trench excavations over 1.5 meters (5 feet) deep or where it is known that in-situ soils lack the stability to hold near vertical faces. Where sufficient room is available and all UFGS conditions are met, the Contractor may

Page 23: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

18  

slope back trench walls rather than having to use a shoring system. The D-B Contractor must develop a shoring and sheeting plan which will accomplish the following: 

Prevent undermining of pavements, foundations, and slopes 

Prevent slippage or movement in banks or slopes adjacent to the excavation 

Comply with all employee health and safety requirements 

Subgrade The D-B Contractor must develop a specification for proof rolling in the appropriate UFGS specifications. Compaction requirements beneath all airfield pavements must follow UFC 3-260-02. Compaction requirements beneath roads must follow UFC 3-250-01. Soil data in the geotechnical report included as Appendix E yielded a Liquid Limit ranging from 31.6 to 38.6 and a Plasticity Index ranging from 15.5 to 23.4.    Existing Utilities The Contractor must physically verify the location and elevation of the existing utilities indicated prior to starting construction. The Contractor must scan the construction site with electromagnetic and sonic equipment and mark the surface of the ground where existing underground utilities are discovered. Excavation made with power-driven equipment is not permitted within 600 mm (2 feet) of known utility or subsurface construction. For work immediately adjacent to or for excavations exposing a utility or other buried obstruction, excavate by hand. The D-B Contractor must relocate, improve, or protect any existing utilities that are impacted by construction of the project in accordance with all applicable standards.  

4.7. Erosion, Sedimentation, and Dust Control Due to the prevalence of silty soils in the geotechnical data, erosion, sediment, and dust control may require a significant level of effort.  

Erosion and Sediment Control The D-B Contractor must provide measures for erosion and sediment control for all aspects of the project, including but not limited to work limits, material storage and equipment laydown areas, field office areas, and haul roads. The D-B Contractor must include such measures in the project phasing plan drawings, keyed to the sequence of construction. Erosion and sediment control measures must be implemented in accordance with Romanian laws and regulations. Per UFC 3-201-01, if no erosion and sediment control requirements exist, an erosion and sediment control plan must be provided in accordance with the requirements of U.S. Environmental Protection Agency’s (EPA) Construction General Permit. Vegetation must be preserved to the maximum extent practicable.  

The D-B Contractor must prevent erosion by all practicable means, including but not limited to mulching, compost blankets, geotextiles, and temporary slope drains. Slope stabilization methods must include chemical stabilization, sodding, seeding, or such combination of these methods necessary for effective erosion control. Use of hay bales is prohibited. Seeding must utilize native species of grasses in compliance with Romanian standards.  

The D-B Contractor must implement sediment control practices to divert flows from exposed soils, temporarily store flows, or otherwise limit runoff and the discharge of pollutants from exposed areas of the site. Sediment control practices must be implemented prior to soil disturbance and prior to creating areas with concentrated flow, during the construction process to minimize erosion and sediment laden runoff. Devices including but not limited to silt fence, temporary diversion dikes, sediment traps, and storm drain inlet protection must be considered. Location and details of installation and construction must

Page 24: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

19  

be indicated on the drawings. Erosion controls must be low-profile and well-secured due to the proximity of construction activities to airfield operations.

Construction operations for dewatering must maintain compliance with Romanian laws and regulations, including water quality standards and anti-degradation provisions. The D-B Contractor must not discharge excavation water to the sanitary sewer, storm drains, or to surface waters without prior specific authorization in writing from the COR. Discharge of hazardous substances will not be permitted under any circumstances.

Dust Control The D-B Contractor must keep dust down always, including during nonworking periods. Acceptable methods of dust control include sprinkling or treating, with dust suppressants, the soil at the site, haul roads, and other areas disturbed by operations. Dry power brooming will not be permitted. Instead, use vacuuming, wet mopping, wet sweeping, or wet power brooming. Only wet cutting will be permitted for cutting concrete blocks, concrete, and bituminous concrete.   Dust particles from construction activities, and processing and preparation of materials must be controlled always, including weekends, holidays, and hours when work is not in progress. The D-B Contractor must maintain excavations, stockpiles, haul roads, permanent and temporary access roads, plant sites, spoil areas, borrow areas, and other work areas within or outside the project boundaries free from particulates that would cause a hazard or a nuisance to aviation activities. The D-B Contractor must implement dust control measures in accordance with UFC 3-260-17 Standard Practice for Dust Control on Roads, Airfields, Base Camps, and Adjacent Areas. The D-B Contractor must provide sufficient, competent equipment available to accomplish dust and particulate control and must perform particulate control as the work proceeds and whenever a particulate nuisance or hazard occurs. Comply with Romanian laws and regulations.  

4.8. Fire Protection Background and Existing Water Systems There is limited water supply distribution infrastructure in the project vicinity. The nearest known existing viable water system connection point is located approximately 1,000 m (3,281 ft) southwest of the project area, serving the U.S. Marines’ section of MKAB. Flow test data collected May 2018 are provided in Appendix G. Base Bid Water Supply The water supply connection point for the Base Bid is the water supply system serving the wash rack at the future Railhead Facility at the adjacent MK-1 project. The D-B Contractor must coordinate this connection through COR.

Optional Bid Item 2 – Alternate Water Supply If the Base Bid water source is not available, the D-B Contractor must connect to a hydrant at the existing water supply system serving the military installation located west of the airport discussed in Section 4.8.1. The D-B Contractor must coordinate this connection through the COR.

Optional Bid Item 3 – Alternate Water Supply If the Base Bid and Optional Bid Item 2 water sources are not available, the D-B Contractor must connect to the future water supply serving the future Ready Building at the adjacent MK-1 project. The D-B Contractor must coordinate this connection through the COR.

Page 25: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

20  

The Base Bid and Optional Bid Item water connections are shown on Sheets CG-102 and CG-103 of the conceptual drawings in this RFP. All investigations must be coordinated through the COR.

Fire Protection Requirements 4.8.5.1. General Fire Protection Requirements

Fire protection water service must be provided adjacent to the explosive cargo load unload apron, as required by Section 6-12.6.1 of UFC 3-260-01, and must be designed and constructed in accordance with all applicable UFC, NFPA, NATO and Romanian Standards. Fire protection work must include connecting to existing water supply, providing a new fire hydrant loop to accommodate new fire hydrants necessary to meet required fire flow and providing a complete and operable water distribution system for proposed airfield modifications. The D-B Contractor must coordinate any power connections with the Installation, the civilian airport, and with adjacent projects that may have spare capacity through the COR. The primary design references for fire pump installations are NFPA 20 Installation of Centrifugal Fire Pumps, and UFC 3-600-01 Design: Fire Protection Engineering for Facilities. Per Section 9-5.1.2 of UFC 3-600-01, fire pumps must be in a detached, noncombustible pump house or located in a fire-rated room in accordance with NFPA 20 with direct access from the exterior. The pump house must be protected by automatic sprinklers. The pump house must be located outside all aviation clear zones. Unless otherwise directed by the COR, the D-B Contractor must provide a back-up generator for the fire protection pump that must be critically silenced so that 71db are not exceeded 1 meter (3.3 feet) away and no hearing protection is required. Any generator larger than 300KVA will require a permit from the Romanian Government. The generator must be designed to provide full firefighting pressure in 2 to 3 seconds. The D-B Contractor must provide audible and visual alarms as required by NFPA 20 on the controller. Provide remote supervision as required by NFPA 20, in accordance with NFPA 72 under Section 26.6 Communications Methods for Supervising Station Alarm Systems using Digital Alarm Communicator Transmitter (DACT) for remote transmission to a remote constantly attended location to be determined by the COR. Power for alarms must not be supplied from the same circuit supplying power to the pump or from an emergency circuit. Design and construction must be coordinated with USACE, base personnel including the base fire chief, Romanian authorities, the local fire department, and IMCOM-Europe Fire Protection Specialist. The D-B Contractor will coordinate design and construction with required authorities through the COR. The D-B Contractor must develop UFGS specifications 21 13 00.00 40 Fire-Suppression Sprinkler Systems, 21 30 00 Fire Pumps, 21 40 00 Water Tanks for Private Fire Protection, and 33 11 00 Water Utility Distribution Piping to include

Page 26: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

21  

the information in this RFP and in accordance with all appropriate standards and codes. The system must meet minimum requirements of United States (U.S.) Department of Defense (DoD), U.S. Army, NATO, airport, and Romanian Government codes and design standards. The D-B Contractor must review all other referenced criteria and where conflicts exist, the most stringent must apply. The design must also comply with Unified Facilities Criteria (UFC) and be in accordance with the documents described in Section 4.1 Design Criteria.

4.8.5.2. Water Distribution and Storage System

The project requires evaluating existing water supply infrastructure through design analysis and tests for potential adequate water supplies. Water flow tests must be conducted in accordance with NFPA 291 and must be video-recorded. The D-B Contractor must coordinate all investigations through the COR. Flow test data collected in May 2018 are provided in Appendix G. Per Romanian State Standard STAS 6054-77 “Teren Fundare – Adancime de Inghet – Zonarea Teritoriului Romaniei”, the maximum freezing depth is 80 centimeters (2.62 ft) below grade near MKAB. A new underground water distribution system must be provided, adding fire hydrants in accordance with the design requirements. The fire flow must be calculated and the minimum fire flow of 3,785 L/min (1,000 gpm) must be provided per Section 9-2 of UFC 3-600-01. Pipe must be sized to provide the fire flow with a maximum head loss of 206.8 kPa (30 psi). The DB Contractor must refer to UFC 3-230-03, Chapter 3 entitled “System Sources and Flows” for additional fire flow requirements. Vaults installed within the project area must be designed for airport loading conditions. Water distribution mains, service mains and service laterals must be designed in accordance with AWWA M31, Distribution System Requirements for Fire Protection; NFPA 24 Standard for the installation of Private Service Mains and Their Appurtenances, latest edition; UFC 3-600-01, and UFC 3-230-01, and NATO and Romanian codes. Per NATO Bi-SC 85-5, Item 30A, firefighting pressurization requirements take precedence over those for the provision of domestic water. Pressurization for firefighting must not be affected adversely by typical demands for domestic consumption in any segment of the water distribution system. Provisions for backflow prevention and regular line flushing must be provided. The D-B Contractor must determine if corrosion protection is required both internally and externally (e.g., such as pipes in contact with corrosive soils) for all components of the water system. New firefighting water storage tanks and water pumps must comply with UFC 3-600-01, and UFC 3-230-01, NFPA 20, NFPA 22, and Romanian codes. Per NATO Bi-SC 85-5, Item 30A, fire booster pumps are required as a separate element. Components must adhere to all taxiway and apron clear zone requirements. Above-ground firefighting water storage must be located outside the IBD (380 m/1,250 ft) stated in Section 4.1.2.1. Per Table 8-5 of DA PAM 385-64, underground water storage tanks must be located greater than 30 m (100 ft) from the centroid of the explosive cargo apron.

Page 27: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

22  

The D-B Contractor must provide 100% of the required fire flow by an underground storage tank with a minimum volume of 545 cubic meters (147,000 gallons).

4.8.5.3. Hydrants and Extinguishers Fire hydrant design and location must follow UFC 3-600-01 and all standards referenced therein. Dry barrel or traffic-type hydrants must be used due to the possibility of freezing. Fire hydrant design must adhere to all height restrictions if located adjacent to airfield pavement. Fire hydrants must be sited in accordance with UFC 3-600-01 and must be installed adjacent to paved shoulders. Section 9-3.5.8.4.f of UFC 3-600-01 requires hydrants to be spaced at 91m (300 feet) maximum intervals along one side of the apron. Per Section 9-3.5.8.1 of this UFC, a sufficient number of hydrants must be provided so that the fire flow can be met without taking more than 4,740 L/min (1,250 gpm) from any single hydrant. The tops of the fire hydrants must not be installed more than 610 mm (24 inches) above the level of the adjacent airfield pavement but in no case, must the tops of the fire hydrants be installed higher than 760 mm (30 inches) above the airfield pavement. Per Army Regulation 420-1, Section 25-33.b.(4), the D-B Contractor must provide one 57-kg (125-pound) Class BC wheeled, dry chemical or equivalent fire extinguisher for each parked C-17 aircraft (3 extinguishers total).

4.8.5.4. Metering At a minimum, flow meters for the fire protection system must be provided for purposes of accepting and testing of fire protection systems, in accordance with UFC 3-600-01 and NFPA 20. The D-B Contractor must verify if metering of the general water supply is required by some other base or HN requirement.

4.8.5.5. Qualified Fire Protection Engineer (QFPE) In accordance with UFC 3-600-01 Section 9-6.3, all design documents must be prepared by or under the supervision of the design/build contractors Qualified Fire Protection Engineer (QFPE). The QFPE must be an individual who is a U.S. registered professional engineer (P.E.) who has passed the fire protection engineering written examination administered by the National Council of Examiners for Engineering and Surveying (NCEES) and has experience designing all facets of fire protection and life safety systems for at least three projects with the same type of facility and system(s) as utilized in this project, including responsibility for fire suppression, hydraulic analysis, life safety (including fire protection, life safety, and building code analysis) and fire alarm and mass notification systems.

4.9. Electrical and Telecommunications Base Bid Power Sources Substation PT14, located north of the existing runway, has been identified as the Base Bid power source for the proposed airfield lighting and signage, which must be under the control of the civilian air traffic control tower. PT14 is owned by the airport and operated and monitored from the civilian airport control tower (see Section 4.9.3). The D-B

Page 28: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

23  

Contractor must coordinate through the COR for this power source and ensure that the new total load with the loads added by this project do not exceed 80% of the full rating of the substation. Connection to PT14 requires approval by both the Romanian Government civilian airport as well as the central airport, and air authority. Per written communication from the Technical Director dated 10 January 2019, PT14 can accommodate the proposed airfield lighting and signage and connection to PT14 requires system upgrades such as replacement of seven (7) IDMAN regulators and replacement and/or upgrade of remote-control systems. Any equipment upgrades required by the Romanian Government must be confirmed and coordinated through the COR. The future 2 MW substation located southwest of the future MK-1 Railhead Facility has been identified as the Base Bid power source for the fire protection system and floodlighting, which does not require control by the civilian air traffic control tower. The D-B Contractor must coordinate through the COR for this power source and calculate that the new total load with the loads added by this project do not exceed 80% of the full rating of the substation. Optional Bid Item 1 – Alternative Power Source (Fire Protection and Floodlighting) If the future 2 MW substation is not available, the D-B Contractor must provide power from the existing transformer located along the service road east of the U.S. Marines Barracks. The D-B Contractor must coordinate through the COR for this power source and calculate that the new total load with the loads added by this project do not exceed 80% of the full rating of the substation. Electrical Systems The work must include the airfield ground lighting, apron flood lighting, power supplies, lightning protection, grounding, site electrical/communication connections to existing sources, generator systems, power distribution, connection to existing airfield lighting control system, and all related infrastructure to provide complete and operable systems. Systems must be provided per these criteria, attached drawings EA-101 through EA-104, and the standards and codes referenced in Section 4.1.3. Where conflicts exist, the most stringent must govern. Design and construction must be coordinated through the USACE with all stakeholders, including but not limited to the airport operators, military entities, host nation, and adjacent projects. These criteria are based on certain standards as indicated herein, but the D-B Contractor must review the criteria listed in Section 4.1.3 and provide the most stringent systems per the latest approved editions. The D-B Contractor must develop a design compliance report and submit for review to demonstrate compliance with all applicable standards. Airfield Ground Lighting and Signage The scope of the airfield ground lighting (AGL) and signage includes new taxiway and apron edge lighting, modifications to existing runway edge lights at new intersections, new elevated runway guard lights, and new mandatory runway hold signs. The primary criteria for AGL and Signage must be UFC 3-535-01. Drawings EA-101 through EA-104 show approximate locations and quantities of AGL and signs to delineate the general scope of work. The D-B Contractor must verify with criteria and provide the required quantities required per criteria. The estimated load of the AGL is approximately 12 kW.

Page 29: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

24  

New lighting and signage systems and fixtures must be compatible with the existing and must utilize the same types, sizes, and heights as already in use on the airfield to the extent practicable. The same models and manufacturers must be provided as existing unless the existing no longer meets criteria or is no longer available. New lights and signs must utilize Light-Emitting Diode (LED) technology, per Romanian civilian air authority requirements. All AGL lights must be installed on concrete encased FAA Type L-868 basecans whether elevated or in-pavement per UFC 3-535-01 Section 5-1.5.1. New basecans and conduit system must connect and drain to the new pavement subdrain system. Floodlighting Provide pole-mounted flood lighting to illuminate apron areas indicated on the Drawing EA-103, in accordance with the requirements of UFC 3-535-01. Luminaires must have BUG rating per IES TM-15-11, Appendix A with G<2 and be full cut off with U=0 to prevent light above the horizontal plane of the fixture. The luminaires must not utilize LED technology, per request by the Romanian MOD. The mounting height of the floodlights must be at least two times the height of the pilot’s eyes above pavement based on the C-17 design aircraft. Location and heights of the poles must be such that inconvenience to ground personnel due to glare is kept to a minimum. The floodlights must be located and aimed to minimize shadows and to avoid direct glare onto air traffic control tower cab windows and landing and departing aircraft. The estimated load of the apron floodlighting is approximately 16 kW. The floodlighting must provide a minimum illumination of 21.53 lux on pavement with uniformity ratio (average to minimum) of 4:1 or better. Final design must determine the appropriate pole height and quantity of poles/fixtures to provide the required illumination. The D-B Contractor must provide photometric calculations to demonstrate compliance with lighting criteria. As potential Value Engineering options, the D-B Contractor must evaluate if reducing the number of floodlights from the four floodlights shown on the conceptual drawings to the 2 westernmost lights (located northwest and southwest of the apron) would comply with the lighting criteria. The design of the flood lighting, including location and height of poles must coordinate with and not interfere with the existing ILS equipment, air traffic control tower and airport operations. Floodlighting must comply with regulations that restrict light sources or technologies that interfere with night vision technologies. Poles must meet relevant obstacle clearance requirements. Evaluate, in coordination with USACE and the Romanian Government, whether pole-top obstruction lights are required and provide per UFC 3-535-01. The D-B Contractor must provide poles and design foundations based on actual geotechnical soils report and to withstand local wind conditions: steady and with appropriate gust factor. Lightning Protection and Grounding Provide lightning protection, grounding and surge protection for all facilities in the project as required by the following: UFC 4-021-02, UFC 3-575-01, UFC 3-260-01, IEC 62305-1, IEC 62305-2, IEC 62305-3, IEC 62305-4, DOD Standard 6055.09-M Volume 2, AFI 32-1065-USAFE, AFM 88-9 Ch3/TM 5-811-3, AFM 91-201, and Romanian Government requirements. The D-B Contractor must coordinate with USACE through the COR to determine locations of handling and storage of ammunition and explosives. Provide grounding receptacles and/or grounded mooring connections for explosive cargo and parking apron discussed in Section 4.2.2.

Page 30: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

25  

The AGL system must be protected by a Safety Grounding System and a Counterpoise Lightning Protection System as described in UFC 3-535-01 and NFPA 780 unless directed otherwise. Power Supply

4.9.7.1. AGL and Signage The power for the new AGL and Signs must be constant current series circuits supplied from 6.6A output constant current regulators (CCR). The D-B Contractor must provide new CCRs in a new electrical vault or building along with interface to the existing airport lighting control system (ALCS) so that new AGL and signs are controlled from the same system as the existing AGL system. The D-B Contractor must update the existing ALCS control panel to reflect the new taxiway/apron layout and circuit paths. Primary criteria for this section must be UFC 3-535-01.

4.9.7.2. Apron Flood Lighting The power for the flood lights can come from new power distribution equipment and transformer located in the same new vault/building that houses the new CCRs or from the fire protection pump system. Control of the flood lights must be independent of the Romanian Government civilian airport operations. Backup power is not required for apron floodlighting, per UFC 3-260-01 and UFC 3-535-01.

4.9.7.3. Fire Protection Pump Power The D-B Contractor must provide normal and emergency backup power to the new fire pump. Backup power must be provided by stand-by generator with all fueling systems and storage to supply pump run-time per code in accordance with UFC 3-230-01 and air base and Romanian Government requirements. The generator system must provide full firefighting pressure within 3 seconds and must have noise rating not greater than 71dB at 1 meter (3.3 feet) so that hearing protection is not required. A generator larger than 300kVA will require a permit from the Romanian Government.

4.9.7.4. Electric Vault/Building The D-B Contractor must provide a new vault to house electrical distribution equipment, panels, transformers, CCRs, and control equipment required for the work. The D-B Contractor must provide interior lighting and power for convenience receptacles, HVAC and any other items in addition to an exterior luminaire above doors. Power to the vault must be provided with underground conduit and cable run to an existing power source.

Communications The D-B Contractor must provide two non-secure communications conduits 125mm (4.92 inches) in diameter from the civilian airport connection point to the new Electrical Vault/Building with polypropylene pull strings. Conduit material must be selected in accordance with UFC 3-550-01. The D-B Contractor must connect to and extend telephone land line from the civilian airport to the new vault using one of the conduits. The DB-Contractor must leave the second conduit for a spare, with polypropylene pull string left in place. The DB-Contractor must coordinate all communications location, connections and conduit installation through the COR.

Page 31: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

26  

Cable and Conduit Routing

The D-B Contractor may install cable by direct-burial when not under taxiway, roadway, rail, or beneath ditches, as is customary in the HN, unless otherwise directed. Cable must be suitable for underground installation. Per Section 3-11.3 of UFC 3-550-01, direct buried wiring methods must comply with Institute of Electrical and Electronics Engineers standard C2 (IEEE C2) or Romanian standards, whichever are more stringent. Cable must be installed in concrete encased duct when run under new airfield or roadway pavement, railroad tracks or ditches. Concrete encasement must extend 2m (6.6 feet) beyond pavement in areas without paved shoulders and 2 m (6.6 feet) beyond paved shoulders. Per UFC 3-535-01, duct under pavement must have a minimum of 75 millimeters (3 inches) concrete encasement all around. Wire and conduits must be installed below frost depth of 80 cm (31.5 inches). Manholes and handholes must meet the requirements of UFC 3-535-01, Section 12-1.4. At a minimum, manholes and handholes, including lids, must be designed for airport loads.

4.10. Perimeter Fence Reconstruction Relocation or replacement of sections of the perimeter fence may be required to access the construction site and to comply with aviation clear zone requirements. Perimeter fence replacement and relocation must comply with Host Nation Government requirements and UFC 4-022-03 Security Fences and Gates and must be coordinated through the COR.

4.11. Landscaping All disturbed areas must be seeded with native grasses. Planting must be completed in the appropriate season, using appropriate soil amendments to ensure vigorous growth. Erosion control measures must not be removed until all disturbed areas achieve 90% vegetative cover.

4.12. Construction Duration The anticipated period of performance including design and construction based on the work described in this RFP is described in the Price Schedule found in Appendix C of this RFP. Work may commence only after a NTP is issued by the COR.

5.0 Construction Specification Requirements The DB-Contractor must produce and provide construction specifications to USACE with the following minimum as part of the design-build package:

1. Signature Sheet with the architect or engineer firm’s seal 2. Table of Contents 3. Bid Schedule 4. ENG Form 4288 Submittal Register 5. All Division 02 through Division 48 Unified Facilities Guide (UFGS) technical

specifications applicable to this project, developed by the D-B Contractor in accordance with the work described in this RFP. UFGS specifications must be formatted using the latest edition of SpecsIntact software. The D-B Contractor must edit sections tailored to the work described in this RFP and submit to USACE through the COR during design. Where conflicts exist between specifications and criteria, the most stringent must apply. If work is required that is not covered by a listed section, the D-B Contractor must select the appropriate sections from the UFGS. A tentative list of the UFGS technical specifications to be developed by the D-B Contractor is provided in Appendix B. It is the D-B Contractor’s responsibility to develop appropriate specifications using the most

Page 32: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

27  

current release date of each UFGS specification. The UFGS specifications and all changes and revisions can be found at https://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs.

6. Form DD-1354 – Transfer and Acceptance of DoD Real Property, provided as Appendix D.

The U.S. Government provides all completed, final Division 00 and Division 01 UFGS Specifications, which are included in Appendix B of this RFP. The D-B Contractor is prohibited from making any changes to the Division 00 and Division 01 Specifications and must utilize them as is.

6.0 Environmental Requirements 6.1. Hazardous Materials

A Phase II Environmental Site Assessment (ESA) of the project area was contracted by USACE. The primary objectives of the ESA were to conduct environmental soil borings, install temporary monitoring wells, perform associated sampling of soil and groundwater, and conduct laboratory analyses on the collected samples. The ESA is included in Appendix F of this RFP. Based on the ESA, there is a possibility of hazardous materials still being present from previous use of the site, or that materials to be removed may contain hazardous materials. If hazardous materials are unexpectedly or otherwise found to exist, the D-B Contractor must immediately notify the COR, cease work in the area, and secure the site. The D-B Contractor must take precautions to protect the site from surface runoff and precipitation, and prevent leaching of any hazardous material in the surrounding area. The Romanian Government is responsible for all issues related to hazardous materials on the property and the D-B Contractor must coordinate through the COR.

Soils Soil analysis is the ESA did not reveal any Aromatic Hydrocarbons (AHC, including BTEX), chlorinated hydrocarbons (CHC), pesticides/herbicides, perfluoro octane sulfonate + perfluorooctanoic acid (PFOS + PFOA) or chlordane. PCB were detected in one sample at a concentration below the U.S. EPA MCL of 0.5 mg/kg. Single detects of TPH and/or PAH indicate that confined and isolated spot contamination may be present, especially within the fill material in the northern part of the site.

In soil, arsenic was consistently detected at levels slightly exceeding the U.S. EPA Carcinogenic SL of 3 mg/kg for industrial soil. The elevated arsenic concentrations are regarded as being of geogenic origin. For all other metals (lead, cadmium, total chromium, chromium VI, copper, nickel, mercury, and zinc), no concentrations exceeding the applied environmental trigger values were noted.

Groundwater Groundwater within the ESA investigation was only encountered within the shallow aquifer formed by sandy silts to silty sands. Due to the presence of siltier layers above, the groundwater is mainly confined and was encountered during the June 2018 sampling event at depths between 8.84 meters (29 feet) and 14.10 meters (46.25 feet) below ground surface (bgs). The ESA investigation confirmed the presence of elevated concentrations of various heavy metals exceeding environmental triggers in groundwater, but not in soil.

Page 33: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

28  

Building Materials The ESA investigation included the buildings to be demolished within the project area. Asbestos and lead were detected in some building component samples such as roofing and paint. The findings are in the ESA, which is included in Appendix F of this RFP. All demolition and debris handling, removal, transport, and disposal must be conducted in accordance with the Demolition Permit and all with all Romanian Government laws and Regulations.

Threatened and Endangered Species The ESA included an Endangered and Threatened Species Survey. Per Section 7 of the report, none of the plant species identified are subject to protection under Directive 92/43/EEC and the Romanian Law No 57/2011. Also per Section 7, multiple bird species protected under the Romanian Ordinance 57/2007 / Law No. 49/2011 and Romanian Ordinance 57/2007 / Law No. 49/2011 will be permanently impacted. As discussed in Section 3.0 of this RFP, the D-B Contractor must coordinate any permitting requirements through the COR. The Endangered and Threatened Species Survey is included in Appendix F.

6.2. Unexploded Ordinance (UXO) The Host Nation is responsible for verifying that the site is free of UXO. There is no prior knowledge of Unexploded Ordnance (UXO) material at the project sites described in this RFP. UXO scans conducted during the ESA and included in the ESA report included in this RFP did not detect UXO. If UXO material is unexpectedly or otherwise found to exist on the project site, the Contractor must immediately notify the COR. Once notified of UXO material, the COR must notify the appropriate authority which must then engage required measures for UXO clearance and unblock the concerned area for further construction work after clearance.

7.0 D-B Contractor’s Design and Submittal Requirements 7.1. General

The D-B Contractor will be required to make formal design submittals at 35%, 65%, 95% and 100% design. All CADD must be prepared in accordance with the applicable provisions of the US Army Corps of Engineers, Europe District, including but not limited to the NAU Building Information Modeling (BIM) Guidelines, ERDC/ITL TR-12-1 A/E/C Graphics Standard (Release 2.0), and ERDC/ITL TR-12-6 A/E/C CAD Standard (Release 6.0).   Each Design Submittal must be submitted as a complete package with all disciplines included. Partial Design Submittals will not be allowed. The D-B Contractor must provide a design analysis with each submittal. Design must be performed in English as the language, as well as in metric system units. Each design submittal must be in Romanian and English language. The D-B Contractor must have all design submittals verified and stamped in accordance with Romanian Government standards.   Design submissions are required to be developed to a level that the U.S. Government can determine compliance with the Contract requirements and must be in accordance with USACE publication HNC-PR-ED-2000.10 document titled Engineering Guidance Design Manual, prepared by the USACE Engineering Support Center, Huntsville (most current edition).  

Page 34: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

29  

The U.S. Government review time for each submittal is 30 days. The D-B Contactor is required to utilize Dr. Checks/Projnet as the forum for design review comment issuance and resolution. Access to the Dr Checks/Projnet system must be coordinated through the COR.  The D-B Contractor must provide As-Built documentation at the completion of the project.  

 7.2. 35% Concept Design

The 35% Design Submittal must consist of the following: Design Narrative and calculations for all disciplines; Fire Protection Basis of Design that must include a narrative description of the

proposed fire hydrant distribution, fire pump, fire alarm, and sprinkler systems following UFC 3-600-01;

Fire Protection Code Compliance Summary Sheets; Life Safety Floor Plan(s); Preliminary Floor Plans showing the proposed fire pump, fire alarm, and sprinkler

systems; Water System Demand Analysis; Intended (outline) specifications list; Environmental permitting memoranda; Concept Drawings; cost estimate;

required information and data for each required permit.  

7.3. 65% Interim Design The 65% Design Submittal must consist of the following: 

Design Analysis and calculations for all disciplines developed to 65% completion;

Approximately 65% complete drawings including those addressing construction phasing;  

Detailed cost estimate developed to approximately 65% completion  

Redlined marked specifications;  

Annotated Concept review comments;  

Completed permit applications.  

7.4. 95% Final Design The 95% Design Submittal must consist of the following:

Design Analysis and calculations for all disciplines developed to 95% completion;

Approximately 95% complete drawings including those addressing project construction phasing.

Detailed 95% cost estimate; Final edited specifications; Annotated Interim review comments; All supporting documentation required for permit applications

7.5. 100% Corrected Final Design

The 100% Design Submittal must consist of the following: 

Page 35: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

30  

Design Analysis and calculations for all disciplines developed to 100% completion;

100% complete drawings, signed and sealed; Detailed 100% cost estimate; Final specifications; Annotated Final review comments; All supporting documentation required for permit applications The D-B Contractor must provide a draft Form DD-1354 with the 100% Design

Submittal. Five (5) copies of the Final Design stamped for Romanian Government

compliance.

7.6. As-Built Documentation As-built drawings must be in accordance with the as-built documentation and must document both new and remaining existing conditions at project completion. All system components must be shown. As-built documentation must be submitted to and accepted by the KO, ACO or the COR.  

7.7. Survey The survey provided in the RFP’s conceptual drawings was limited in scope and was intended for preliminary design only. It is the responsibility of the D-B Contractor to obtain and complete any surveys required to perform design and execute construction. The Coordinate Reference System of the survey provided in the RFP conceptual drawings is stereographic projection system of 1970 (Stereo 1970) as is required for permitted construction projects in Romania.   

7.8. Geotechnical Investigation, Data and Report The subsurface soil information included in this RFP is derived from an investigation that was limited in scope. As such, the subsurface soil information and data in this RFP is for the Contractor's information only, is not guaranteed to fully represent all subsurface conditions, and is intended for proposal preparation and preliminary design only.  The Contractor must perform, at their expense, such subsurface exploration, investigation, testing, and analysis as their Designer of Record deems necessary for the design and construction of the site improvements. All geotechnical investigation work performed by the D-B Contractor at the project location must be coordinated with the COR and must not interfere with normal base or civilian airport operations. At a minimum, geotechnical investigations must follow the requirements of UFC 3-260-02 Pavement Design for Airfields and UFC 3-220-01 Geotechnical Engineering.  The D-B Contractor must prepare and submit to the COR a written geotechnical report that includes the geotechnical data provided in this RFP and all additional field work performed by the DB-Contractor. The geotechnical work and report must also satisfy Romanian design and permitting requirements.   

D-B Contractor’s Geotechnical Engineer The D-B Contractor’s Geotechnical Engineer must be a Geotechnical Engineer registered in the jurisdiction the construction is performed and experienced with soil conditions in the region where the project site is located. The D-B Contractor’s Geotechnical Engineer must evaluate the RFP data, obtain and evaluate all additional data as required to support the design and construction, and prepare a Geotechnical Report.   

Page 36: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

31  

D-B Contractor’s Geotechnical Report The D-B Contractor’s Geotechnical Report must be based on the Government-provided subsurface investigation data provided in this RFP and all additional field and laboratory testing accomplished at the discretion of the DB-Contractor’s Geotechnical Engineer. In addition to all Romanian requirements, the D-B Contractor’s Geotechnical Report must include the following: 

a. The project site description, vicinity map and site map indicating the location of

borings and any other sampling locations. Provide 24-hour groundwater observations for at least 20% of the borings. Provide notes explaining any abbreviations or symbols used and describing any special site preparation requirements.

b. Results of all applicable field and laboratory testing. Address existing subsurface conditions, selection and design of the airfield pavements, roadways, foundations and/or floor slabs, all underground construction including utility installation and all other site-specific requirements such as soil stabilization and slope stability.

c. Engineering analysis, discussion and recommendations including but not limited to: i. Settlement analysis ii. Bearing Capacity analysis iii. Airfield pavement and construction considerations and installation procedures. iv. Site preparation, such as earthwork procedures and equipment, compaction

requirements, building slab preparation, soil sensitivity to weather and equipment, groundwater influence on construction, mitigation of expansive soils or liquefaction potential, and dewatering requirements.

v. Sheeting and shoring considerations vi. Pavement design recommendations, including recommended thicknesses and

materials. vii. Haul routes and stockpile locations during earthwork operations. viii. Supporting calculations and assumptions, with all parameters defined ix. The Geotechnical Report must be signed by a Geotechnical Engineer registered

in the jurisdiction the construction is performed.  

7.9. Recommended Drawings to be Developed by the D-B Contractor 7.9.1.1. Title Sheet 7.9.1.2. Project Title,

a. Location, Year, and b. Volume Number.

7.9.1.3. Index Sheet a. Listing of Sheet Names b. Assigned Sheet Numbers

7.9.1.4. Legend a. Civil b. Electrical c. Mechanical d. Architectural

7.9.1.5. Existing Conditions Plan(s) a. Site Features b. Existing Utilities Plan 

Show Existing Utility Locations Show Pavement Penetrations

7.9.1.6. Location/Site Plan a. Base Map with Project Title,

Page 37: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

32  

b. Base Map with Region (Vicinity) Map c. Project Location d. Contractor Access Routes e. Location of Installation and Facility Gates and Any Restrictions f. Borrow/Waste Areas g. Batch Plant Area h. Contractor's Staging and/or Storage Area i. Utility Hookup Locations j. General or Special Notes k. Concurrent Construction (Not in Contract (NIC)).

7.9.1.7. Phasing Plan and Details (Include Requirements of UFC 3-260-01, Sections 15.3 and 15.4.)

a. Location and Sequencing of Work Areas b. Scheduling for Each Phase of Project c. General Listing of Tasks to be Performed Under Each Phase d. Concurrent Construction That May Affect Each Phase e. Location and Type of Area Control (Security) Measures

Temporary Barricades and Fencing Temporary Lighting Temporary Pavement Markings (Closure Markings)

f. Traffic Circulation (Aircraft and Vehicular) g. Special Notes

Security Measures Contractor's Housekeeping Measures Controls on Contractor's Traffic

7.9.1.8. Horizontal and Vertical Controls a. Layout b. Bench Marks c. Control Stationing d. Horizontal Control (Coordinates)

7.9.1.9. Geometric Layout Plan a. Curve Data b. Control Stationing c. Geometric Layout

7.9.1.10. Boring Location Plan and Boring Log Data a. Boring Logs and summary of all test results and groundwater observations b. Locations of all borings 

7.9.1.11. Pavement Removal Plan a. Pavement Removal Limits (e.g., Dimensions, Stationing) b. Type and Thickness of Pavement Removed c. Utilities and Structures Affected by the Removal d. Special Notes Regarding Removals e. Location of Removal Sections

7.9.1.12. Removal Sections and Details Sections must be specific, not general or typical. Show several sections. Show new sections for changes in pavement type, thickness, or any other condition that has an impact on pavement construction. Sections must be complete both laterally and vertically for the entire pavement structure, including subgrade preparation. 

a. Removal Limits (Lateral Dimensions, Depth) b. Show Make-Up of the Existing Pavement

Page 38: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

33  

Pavement Type and Thickness Joint Type (e.g., Doweled, Tied, Contraction) Existing Reinforcing (if any)

c. Special Notes Equipment Type/Size Procedures

Housekeeping 

Other 7.9.1.13. Paving Plan

a. Thickness b. Type c. Location d. Location of Section Cuts e. Stationing f. Dimensions

7.9.1.14. Paving Sections Make the sections specific. Do not overuse "Typical Sections." Cut a section wherever there is a change from one pavement section to another in any direction and on all pavement edges. The same section may be referenced numerous places on the plan sheets, but each location must be marked and properly annotated. Only by including everything in the plans can the design be built as envisioned. 

a. Include the entire paving section from surface through subgrade. Thickness of Surface Prime Coat Requirements

Thickness of Bases and Subbases 

Thickness of Drainage Layer 

Depth and Type of Subgrade Preparation  Jointing Locations and Type

Surface Grades/Slope 

Subsurface Drainage/Subdrain Provisions 7.9.1.15. Plan and Profile Sheets

a. Plan 

Outline of Pavement 

Utilities 

Stationing 

Geometrics b. Profile 

Stationing Elevations (New and Existing) Vertical Curve Data Utility Depth and Location

7.9.1.16. Grading and Drainage Plans Contours (New and Existing) Surface and Subsurface Drainage System Layouts, Alignments,

Structure Locations, Types, and Sizes Ditch Alignment

7.9.1.17. Grading Sections a. Cut/Fill Requirements b. Topsoil Requirements

Page 39: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

34  

7.9.1.18. Pavement Surface Elevations a. Spot Elevation Plan (Joint Intersections or Grid Pattern) b. Spot Elevation Schedule

7.9.1.19. Pavement Jointing Plans a. Legend with Joint Types b. Joint Location

7.9.1.20. Reinforcing Details a. Dowels b. Reinforcement c. Tie Bars d. Complete Pavement Joint Details

7.9.1.21. Surface and Subsurface Drainage Systems a. Profiles b. Schedules c. Details

7.9.1.22. Pavement Marking a. Plan b. Details

7.9.1.23. Visual Navaids/Lighting a. Plan b. Schedule c. Details

7.9.1.24. Airfield Lighting Vault/Housing a. Plan showing locations of constant current regulators, airfield lighting, control

systems, backup power set b. Elevations showing regulators, generator set, switch gear panels and wireways c. Details and wiring diagrams

7.9.1.25. Apron Flood Lights a. Location plan of lights with aiming data b. Plan with point-by-point light intensities showing compliances with minimum light

intensity requirements c. Details and wiring diagrams

 8.0 Design-Build Quality Control

The D-B Contractor must demonstrate sound design and construction through development of a Contractor Quality Control Plan (CQC) and a Design Quality Control Plan (DQC), the details of which will be provided in the Division 01 project specifications. Note that the Division 01 Specifications take precedence over subsections 8.1, 8.2, and 8.3, which are provided for general information purposes. Note that the U.S. Government Division 00 and Division 01 UFGS Specifications are included in Appendix B of this RFP.   

8.1. Contractor Quality Control Plan (CQC) The CQC must cover all design and construction-operations, both onsite and offsite, including work by subcontractor’s designers of record, consultants, architect/engineers (AE), fabricators, suppliers and purchasing agents and must include the following:  

CQC Contents 8.1.1.1. A description of the quality control organization, including a chart showing lines of

authority and acknowledgment that the CQC staff will implement the three-phase

Page 40: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

35  

control system for all aspects of the work specified. Include a CQC System Manager that reports to the project superintendent.

8.1.1.2. A copy of the letter to the CQC System Manager signed by an authorized official of the firm which describes the responsibilities and delegates sufficient authorities to adequately perform the functions of the CQC System Manager, including authority to stop work which is not in compliance with the Contract. Letters of direction to all other various quality control representatives outlining duties, authorities, and responsibilities will be issued by the CQC System Manager. Furnish copies of these letters to the Contracting Officer.

8.1.1.3. Procedures for scheduling, reviewing, certifying, and managing submittals, including those of subcontractors, designers of record, consultants, architect engineers (AE), offsite fabricators, suppliers, and purchasing agents.

8.1.1.4. Control, verification, and acceptance testing procedures for each specific test to include the test name, specification paragraph requiring test, feature of work to be tested, test frequency, and person responsible for each test. (Laboratory facilities approved by the Contracting Officer are required to be used.)

8.1.1.5. Procedures for tracking preparatory, initial, and follow-up control phases and control, verification, and acceptance tests including documentation.

8.1.1.6. Procedures for tracking design and construction deficiencies from identification through acceptable corrective action. Establish verification procedures that identified deficiencies have been corrected.

8.1.1.7. Reporting procedures, including proposed reporting formats. 8.1.1.8. A list of the definable features of work. A definable feature of work is a task

which is separate and distinct from other tasks, has separate control requirements, and is identified by different trades or disciplines, or it is work by the same trade in a different environment. Although each section of the specifications can generally be considered as a definable feature of work, there is frequently more than one definable feature under a particular section. This list will be agreed upon during the coordination meeting.

 

8.2. Design Quality Control Plan (DQC) DQC Contents

8.2.1.1. The D-B Contactor must submit and maintain a Design Quality Control (DQC) Plan as an effective quality control program which assures that all services required by this contract are performed and provided in a manner that meets professional architectural and engineering quality standards. As a minimum, all documents must be technically reviewed by competent, independent reviewers identified in the DQC Plan. The same element that produced the product may not perform the independent technical review (ITR). Correct errors and deficiencies in the design documents prior to submitting them to the Government.

8.2.1.2. Include the design schedule in the master project schedule, showing the sequence of events involved in carrying out the project design tasks within the specific Contract period. This must be at a detailed level of scheduling sufficient to identify all major design tasks, including those that control the flow of work. Include review and correction periods associated with each item. This must be a forward planning as well as a project monitoring tool. The schedule reflects calendar days and not dates for each activity. If the schedule is changed, submit a revised schedule reflecting the change within 7 calendar days. Include in the DQC Plan the discipline-specific checklists to be used during the design and quality control of each submittal. Submit at each design phase as part of the project documentation these completed discipline-specific checklists.

Page 41: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

36  

8.2.1.3. Implement the DQC Plan by a Design Quality Control Manager who has the responsibility of being cognizant of and assuring that all documents on the project have been coordinated. This individual must be a person who has verifiable engineering or architectural design experience and is a professional engineer or architect licensed and registered in accordance with the requirements of the country where the construction work is performed. Notify the Contracting Officer, in writing, of the name of the individual, and the name of an alternate person assigned to the position.

8.3. Testing

The D-B Contractor must perform specified or required tests to verify that control measures are adequate to provide a product which conforms to contract requirements. Upon request, the D-B Contractor must furnish to the Government duplicate samples of test specimens for possible testing by the Government. Testing includes operation and acceptance tests when specified. The D-B Contractor must procure the services of a Corps of Engineers approved testing laboratory or establish an approved testing laboratory at the project site. The D-B Contractor must perform the following activities and record and provide the following data:   Testing Requirements

8.3.1.1. Verify that testing procedures comply with contract requirements. 8.3.1.2. Verify that facilities and testing equipment are available and comply with testing

standards. 8.3.1.3. Check test instrument calibration data against certified standards. 8.3.1.4. Verify that recording forms and test identification control number system,

including all the test documentation requirements, have been prepared. 8.3.1.5. Record results of all tests taken, both passing and failing on the CQC report for

the date taken, specification paragraph reference, location where tests were taken, and the sequential control number identifying the test. Failure to submit timely test reports as stated results in nonpayment for related work performed and disapproval of the test facility for the Contract.

9.0 Construction Phasing Requirements

9.1. General The D-B Contractor must prioritize the safety of Air Base patrons and all Air Base and Contractor personnel throughout construction. The Contractor must comply with all applicable Air Base safety and security regulations, including but not limited to base access protocol. Military operations may unexpectedly require shutdown of the Contractor’s operations. The Host Nation and/or COR must provide a 24-hour notice prior to any shutdown, if possible. As discussed in Section 3.0, the D-B Contractor must submit to the Romanian civilian air authority and MOD a plan of works and temporary traffic management measures to be taken that affect the movement and flight of aircraft on the airfield together with the construction vehicles traffic management plan. This plan must include construction phasing that minimizes airfield pavement closure time.

9.2. Haul Roads The D-B Contractor must construct and maintain all haul roads as deemed necessary to perform the required construction operations. The D-B Contractor must maintain haul

Page 42: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

37  

roads in a dust-free condition always. All pavements, roadway, drives, and any other area used by the D-B Contractor as a haul road must be maintained and repaired in kind by the D-B Contractor to the satisfaction of the COR. The D-B Contractor and the COR must review the haul routes to be used during construction and agree to the preexisting condition prior to beginning any work. The D-B Contractor must video-record the haul routes prior to use to document existing condition. No additional compensation must be made to the D-B Contractor for repair of any damage caused by the D-B Contractor’s operations. This must include but not be limited to pavements, roadways, drives, and airfield pavement, both new and existing. The D-B Contractor must be responsible for coordinating all access from local roads with Romanian Government officials as well as any other appropriate agency responsible for the roadways. Any permits, signage, or lighting required for access by these agencies must be in place prior to initiating construction.

9.3. Airfield Pavement Closures The D-B Contractor must coordinate all airfield closures through the COR, with a minimum of 7 days’ notice. Construction activities within 30 meters (100 feet) from the edge of runway and 70 meters (225 feet) from the centerline of a taxiway require closure. The D-B Contractor must develop a phasing plan that minimizes closure time. This phasing plan must be a component of the temporary works plan described in Section 3.0. For construction work carried out on the flightline or in the immediate vicinity, the D-B Contractor and the project manager are required to undergo training in accordance with a Romanian government training program. Upon completion of the training, the D-B Contractor is required to instruct all his subcontractors.

9.4. Airfield Construction The D-B Contractor must keep taxiways, runways, and other airfield pavements clear of Foreign Object Debris (FOD) at all times. For airfield pavement work, provide and maintain a vacuum sweeper truck for removal of FOD. The D-B Contractor must thoroughly clean the entire airfield pavement surface impacted by their operations throughout construction and immediately before the pavement is opened to aircraft traffic. The D-B Contractor must remove debris from the construction site on a continuous basis to reduce potential FOD. D-B Contractor must also maintain control of trash and non-trash construction FOD (e.g., plastic wrap, cardboard, drink cups, spray cans, tools, etc.) and control FOD within vehicles, trailers, or closed trash containers. Open excavations and holes are prohibited within 150 meters (492 feet) of the runway when aircraft are active on the runway. The D-B Contractor must coordinate any work within 150 meters (492 feet) of the edge of runway with the COR.

9.5. D-B Contractor Laydown Area and Concrete Batch Plant The D-B Contractor must be responsible for coordinating the final laydown site and onsite concrete batch plant with base officials and the USACE COR. No separate payment shall be made to the D-B Contractor for preparing storage area to be used, including the removal of existing features and installation of required security measures. Additionally, the laydown site may not contain water, electricity, or telephone utilities. The D-B Contractor must plan for temporary utilities as required. The D-B Contractor shall bear all costs of temporary utilities from hookup through removal.

Page 43: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

38  

The D-B Contractor shall be responsible for providing all erosion control protection required for the laydown site, and must completely restore the site to its original condition and to the satisfaction of the COR upon completion of the project. Erosion controls must be low-profile and well-secured due to the proximity of construction activities to airfield operations.

10.0 MKAB Requirements 10.1. General

MKAB is operational 24 hours a day, 7 days a week. Office operating hours are: 8:00-18:30

The base-wide speed limit is 32km/h (20 mph); D-B Contractor must expect the construction site to be fenced and separated

from the airport during construction. When fences are removed to carry out work, security oversight will occur.

Smoking is only allowed in existing designated places and at the D-B Contractor’s provided designated place.

Use of alcohol by the D-B Contractor’s personnel is strictly prohibited on the site.

10.2. Romanian Public Holidays 1 January Anul nou - New Year's Day

2 January Anul nou - Day after New Year's Day

24 January

Unirea Principatelor Române/Mica Unire -Unification of the Romanian Principalities/Small Union

8 April Paştele - Orthodox Easter Sunday (Floating, not Fixed)

9 April Doua zi de Pasti - Orthodox Easter Monday (Floating, Not Fixed)

1 May - Ziua muncii - Labour Day

27 May Rusaliile - Orthodox Whit Sunday (Date Varies +/– 15 days)

28 May Doua zi de Rusaliile - Orthodox Whit Monday

1 June Ziua Copilului - Children's Day

15 August Adormirea Maicii Domnului/Sfânta Maria Mare - Dormition of the Theotokos

30 November Sfântul Andrei - St. Andrew's Day

1 December Ziua Națională/Marea Unire - National Day/Great Union

25 December Crăciunul - Christmas Day

26 December Crăciunul - Boxing Day

10.3. U.S. Federal Holidays

1 January New Year's Day

Page 44: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

39  

15 January Birthday of Martin Luther King, Jr. (Date Varies: occurs on the third Monday of January)

19 February Washington’s Birthday (Date Varies: occurs on the third Monday of February)

28 May Memorial Day (Date Varies: occurs on the last Monday of May)

4 July Independence Day

3 September Labor Day (Date Varies: occurs on the first Monday of September)

8 October Columbus Day (Date Varies: occurs on the second Monday of October)

11 November Veteran’s Day (Date Varies: occurs on the first Monday of November)

22 November Thanksgiving Day (Date Varies: occurs on the fourth Thursday of November)

25 December Christmas Day

10.4. Night and Weekend Restrictions

There are no night and weekend restrictions. However, the D-B Contractor is required to request and gain approval from the COR prior to working nay nights and weekends.

10.5. Base Access Procedures 1. The D-B Contractor’s personnel will fill out 4 types of forms:

Personnel Forms – various data Vehicle Forms – various data about vehicles Computer Forms – various data Phone and Camera Forms - various data

2. The above forms must be submitted for approval to the MOD through the COR to the security officer in charge of access. The MOD process time is a three (3) week minimum and a 60-day maximum. Approval is typically valid for 1 year.

3. A Passport or ID is required to gain entry to the base with vehicle identification. 4. Photos shall not be taken without registration with the appropriate form, per Item

1, above. The D-B Contractor risks incarceration if using phone or camera without proper registration.

5. All vehicles, including but not limited to trucks and excavators require vehicle registration forms per Item 1 above.

6. All contract employees, including subcontractor employees who are not in possession of the appropriate security clearance or access privileges, will need to be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas.

10.6. Construction Site Restrictions 1. The outer limit of the construction site must be delineated or clearly labeled by

the D-B Contractor. The labeling must use nonflammable materials. 2. The construction site must be marked with numbers (e.g., Hot Cargo Pad No 1,

etc.).

Page 45: Request for Proposal Government... · ladder taxiways, and a reconstructed and extended parallel taxiway on Mihail Kogălniceanu Air Base (MKAB) near Constanta, Romania. Design and

 

40  

3. The D-B Contractor must provide a listing of at least two 24-hour emergency contacts, including telephone numbers, should the project require immediate response for safety/security reasons during non-work hours. Additionally, the D-B Contractor must assign a person responsible during working hours. This information must be submitted to the Romanian MOD Representative.

4. The D-B Contractor must post point of contact telephone numbers at the construction site.

5. The construction site shall be maintained in a clean condition as previously described. This shall require continuous debris removal and particular attention must be paid to the storage of garbage. All flowing garbage must be stored in closed containers.

6. If material is stored outside of the D-B Contractor’s construction site, it must be coordinated with the MOD Romanian Security Officer Department representative through the COR. D-B Contractor materials stored outside of the construction site must be stored in a designated fenced area, which requires a permit from Romanian MOD.

7. The D-B Contractor must comply with U.S. Army occupational health and safety requirements for personal protective equipment (PPE) as required by USACE EM-385-1-1, Safety and Health Requirements Manual.

10.7. Flightline and/or Immediate Vicinity of Construction Site Requirements 1. Prior to beginning work, the D-B Contractor must submit to the Romanian

Government air authority through the COR, a work plan that includes traffic management measures to be taken during construction that will avoid conflict with the movement of aircraft. This approval is discussed in Section 3.0 of this Statement of Work. The D-B Contractor must expect strict enforcement of the approved plan.

2. If the D-B Contractor notices danger on the flightline, the air traffic controller must be contacted. Contact information must be obtained from the COR;

3. In case of fire, the D-B Contractor must call fire and rescue. Contact information must be obtained from the COR.

4. For construction work to be carried out on the flightline or in the immediate vicinity, the D-B Contractor’s personnel are required to undergo training in accordance with the training program prior to the performance of any work. Upon completion of the training, the D-B Contractor must instruct all their subcontractors with the same training.

5. Smoking in the flightline area or in the immediate vicinity is strictly prohibited. 6. The temporary obstacle height above the ground (soil, stacks of materials, etc.)

must not exceed 1 meter (3.3 feet). All temporary obstacles that exceed this height must be removed from the said zone prior to flights.

7. The D-B Contractor must maintain radio contact with the Air Base communications network, as appropriate, to contact the air traffic control throughout the duration of operations within the flightline and/or immediate vicinity.

8. For activities within 150 meters of the runway, the D-B Contractor must submit their work plan through the COR to the HN civilian air authority to facilitate publishing of the required Notice to Airmen (NOTAM).