RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 1 o f 56
Request for Proposal for
Implementation of ERP and Web-based ERP- like Solutions
Volume I – System Integration Services and
Solution Scope
Indian Institute of Technology Bombay
Disclaimer: This document contains confidential information on Indian Institute of Technology
Bombay (IITB) which is provided for the sole purpose of permitting the bidder to make
a proposal. In consideration of receipt of this document, the bidder agrees to maintain
such information confidential and to not reproduce or otherwise disclose this
information to any person outside the group directly responsible for evaluation of its
contents, except that there is no obligation to maintain the confidentiality of any
information which was known to the bidder prior to receipt of such information from
IITB or becomes publicly known through no fault of bidder, from IITB or is received
without obligation of confidentiality from a third party owing no obligation of
confidentiality to IITB.
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 2 o f 56
This page has been left blank intentionally.
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 3 o f 56
Table of Contents
1. Introduction..............................................................................................................5
1.1 Purpose of this Document .....................................................................................5
1.2 Request for Proposal (RFP) Structure ...................................................................5
2. IITB Organization Structure and Functions ...............................................................6
2.1 Organization Structure ..........................................................................................6
2.2 Functional Structure ..............................................................................................7
3. Enterprise Resource Planning (ERP solution) ........................................................ 10
3.1 Objectives and Benefits ....................................................................................... 10
3.2 Strategic Considerations ..................................................................................... 10
3.3 Implementation Methodology .............................................................................. 11
4. Scope of Work ....................................................................................................... 13
4.1 General Scope .................................................................................................... 13
4.2 Functional Scope ................................................................................................ 13
4.3 Geographical Location ........................................................................................ 25
4.4 No of users ......................................................................................................... 25
4.5 Technical Scope ................................................................................................. 25
4.6 Scope of Services for Bidder ............................................................................... 27
5. Project Management.............................................................................................. 46
5.1 Proposed Project Plan ......................................................................................... 48
5.2 Project Deliverables ............................................................................................ 49
5.3 Governance Structure and Project team Requirements ....................................... 51
ANNEXURE I: BROAD FUNCTIONAL REQUIREMENT SPECIFICATION (SEPARATE
DOCUMENTS) ........................................................................................................... 54
ANNEXURE II: SCRIPTS FOR DEMONSTRATION BY BIDDER (SEPERATE
DOCUMENT) ............................................................................................................. 55
ANNEXURE III: INDICATIVE EXPECTATIONS AND PROCESS GAPS (SEPERATE
DOCUMENT) ............................................................................................................. 56
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 4 o f 56
This page has been left blank intentionally.
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 5 o f 56
1. Introduction IIT Bombay, set up by an Act of Parliament, was established in 1958, at Powai, a northern
suburb of Mumbai. Today, the Institute is recognized as one of the centers of academic
excellence in the country. Over the years, there has been dynamic progress at IIT Bombay in
all academic and research activities, and a parallel improvement in facilities and infrastructure,
to keep it on par with the best institutions in the world. Institutes in positions of excellence grow
with time. The ideas and ideals, on which such institutes are built, evolve and change with
national aspirations, national perspectives, and trends worldwide. IIT Bombay, too, is one such
institution.
1.1 Purpose of this Document
The objective of this document is to solicit proposals from the prospective bidders for
providing implementation services to implement the ERP. Abbreviation ‘ERP’ includes ERP
as well as web based ERP like products in the sequel.
1.2 Request for Proposal (RFP) Structure
Contents of this RFP have been documented as a set of two volumes explained below. Volume I: System Integration Services and Solution Scope
Volume I of RFP intends to highlight all the details with respect to functional and
technical requirements of the ERP solution along with the necessary scope of work
for implementing the solution that IITB deems necessary to share with the potential
bidders.
Volume II: Bidding Terms and Conditions
Volume II of RFP intends to mention all the information that may be required by the
potential bidders to understand the evaluation criteria, commercial terms, bid
process details, etc. to thereby participate in the bid process for implementation of
ERP and Web based ERP-like solutions at IITB.
This document is Volume I.
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 6 o f 56
2. IITB Organization Structure and Functions
2.1 Organization Structure
IIT Bombay is an autonomous institute, under aegis of Ministry of Human Resource
Development (MHRD), Government of India.
At the institutional level, IIT Bombay is governed by a Board of Governors with a
Chairman nominated by the Visitor (the President of India), the Director as a member and
the Registrar as secretary. Besides this, there are four persons having specialized
knowledge or practical experience in respect of education, engineering or science
nominated by the Council. Two professors are nominated by the Senate. Additionally,
one technologist or industrialist of repute is nominated by the Government of each of the
States of Maharashtra, Goa, and Dadra and Nagar Haveli.
For all academic matters, the Senate (Comprises all the professors of the institute and a
few nominated Members) is the authority having control and responsibility for the
maintenance of standards of instruction, education and examinations and all other allied
academic matters. The Senate is mainly constituted of all the professors of the Institute
and the Director is the Chairman.
*Detailed mapping of the organization will be provided during implementation phase.
High Level Organization Structure*
Council of IITs
Board of Governors
• Finance Committee • Senate • Building and Works Committee • Director
• Deputy Directors • Deans and Associate Deans
• Registrar, Deputy Registrars, Assistant Registrars • Librarian • HOD
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 7 o f 56
The key people in the execution of the Institute's activities are the Director and Deputy
Directors who are assisted by Dean (R&D), Dean (IPS), Dean (SA), Dean (AP), Dean
(ACR), Dean (IR), Dean (AA), Dean (FA) and the Heads of the Departments, Centers,
School and IDPs.
2.2 Functional Structure
Administration and Operation
Two Deputy Directors (Academic and Infrastructural Affairs, and Finance and External
Affairs) and eight Deans (Infrastructure Planning and Support, Research and
Development, Academic Programmes, Students Affairs, Alumni and Corporate Relations,
Faculty Affairs, Administrative Affairs and International Relations) assist the Director in his
executive roles.
The Registrar and senior officials in specific areas (Academic Affairs, Estate
Management, Materials Management, Finance and Accounts, Administration, Personnel
Training and Development, Placement, Publications and Public Relations, etc.) perform
administrative functions.
The Institute Advisory Council is a non-statutory body comprising eminent personalities
from business, industry and academia, which reviews and makes suggestions on long-
term policies and short-term goals.
Academic Office
The Academic Office of the Institute exists to facilitate, initiate and co-ordinate the
academic work of the Institute, particularly the teaching and assessment of students. It
acts as the repository of grades and academic records of all students, both past and
present. It provides administrative support to the Senate, which is the highest academic
body of the Institute.
The Head of the Academic Office is the Dean of Academic Programmes, who is a senior
professor of the Institute. The Dean is helped by a permanent administrative set-up
headed by a Deputy Registrar (Academic). Academic Office closely interacts with the
Dean of Student Affairs (DoSA), who looks after all non-academic issues of students.
The DoSA, as the ex-officio President of the Student Gymkhana, coordinates various
co-curricular activities of students.
Academics
IIT Bombay offers a wide variety of courses of study in engineering, pure sciences,
design, management and humanities with a primary focus on engineering. The institute
is a member of "Links to Asia by Organizing Traineeship and Student Exchange"
(LAOTSE), an international network of leading universities
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 8 o f 56
in Europe and Asia exchanging students and senior scholars.
The Institute conducts educational programmes leading to the degree of Bachelor of
Technology (BTech), Dual Degree (BTech and MTech in 5 years), Master of Science
(MSc), Master of Technology (MTech), Master of Design (MDes), Master of
Management (MMgmt), Master of Philosophy (MPhil) and Doctor of Philosophy (PhD).
Departments, centers, and schools
IIT Bombay has departments, multi-disciplinary centers, and schools of excellence.
List of departments in IIT Bombay are
Aerospace Engineering
Biosciences and Bioengineering
Chemical Engineering
Chemistry
Civil Engineering
Computer Science and Engineering
Earth Sciences
Electrical Engineering
Energy Science and Engineering
Humanities and Social Science
Industrial Design Centre
Mathematics
Mechanical Engineering
Metallurgical Engineering and Materials Science
Physics
Following multi-disciplinary centers are located in IIT Bombay.
Industrial Design Center (IDC)
Centre for Research in Nano-Technology and Sciences (CRNTS)
Centre for Aerospace Systems Design and Engineering (CASDE)
Centre for Distant Engineering Education Programme (C-DEEP)
Centre for Environmental Science and Engineering (CESE)
Centre of Studies in Resources Engineering (CSRE).
Centre for Technology Alternatives for Rural Areas (CTARA)
Centre for Formal Design and Verification of Software (CFDVS)
Sophisticated Analytical Instrument Facility (SAIF)
National Centre for Photovoltaic Research and Education (NCPRE)
Center for Urban Science and Engineering (CUSE)
In addition. IIT Bombay has following school.
Shailesh J Mehta School of Management (SJMSOM)
Further, IIT Bombay offers following inter-disciplinary programs.
Educational Technology
Industrial Engineering and Operations Research (IEOR)
Systems and Control Engineering
Climate Studies
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 9 o f 56
Development Activities
The Industrial Research and Consultancy Centre (IRCC) is responsible for fostering the
overall R&D growth of the institute by facilitating interactions with external agencies and
promoting and managing interactions between the institute and industries.
The institute undertakes R&D projects in various areas of specialization. They can
be broadly categorized as
Sponsored R&D Projects
Consultancy Projects
Sponsored Student Projects
Faculty members from IIT Bombay undertake industry sponsored research and
consultancy projects that are made available through the institute. These are funded by
various national agencies like the Department of Science and Technology, Department
of Electronics, Department of Space, Aeronautical Development Agency, Department of
Atomic Energy, and Oil & Natural Gas Commission (ONGC). The office of the Dean
(R&D) provides necessary liaison with industry and sponsoring agencies. The office
helps industry to identify faculty expertise and institutional facilities, and assists faculty in
identifying industry problems.
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 10 o f 56
3. Enterprise Resource Planning (ERP solution)
The complex institute environment at IITB necessitates standardized process flows, online
reporting, project monitoring and status updates, project planning and execution,
maintaining student life cycle, finance and accounting management, funds management
etc which IITB would like to implement as part of their ERP to meet their requirements.
Abbreviation ‘ERP’ includes ERP as well as web-based ERP-like products in the sequel.
3.1 Objectives and Benefits
IITB has decided to implement combinat ion of the best-in-breed ERP solution which suits all the Institute needs. IITB envisages the following benefits from implementing ERP across its functions / areas.
Common integrated system platform across different functions and processes
of IITB
Process standardization across the institute to bring-in unified approach
Monitor research activities and funds utilization
Monitoring and governance of the procurement processes
Mapping of assets and their life cycles
Analysis of budget and actual data
An ERP Solution to provide scalability options to accommodate the expected
growth plan
Data integrity across various IITB functions like departments, centers,
administrative units, finance and accounts, etc.
Facilitate paperless working and provide decision support mechanism
Automate management controls and approvals to reduce cycle time
Seamless integration of student information across the institute
Real time reporting on the performance of the individual operating departments
and a streamlined Management Information System
3.2 Strategic Considerations The strategic considerations for ERP solution at IITB are
Future expansion – The ERP solution will be used for automating all the functions
of IITB and is required to meet future expansions in terms of programmes,
departments, centers, scale of student intake capacity, etc.
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 11 o f 56
Integration – To protect the current investments in the stand-alone IT applications, IITB
intends to integrate them with the ERP solution. To ensure this, one of the key elements
of the solution strategy is to ensure having solution with open standards for integration of
different third party / legacy / in-house developed applications / solutions.
Proven Solution – Processes of IITB are moderately unique in the areas of finance,
human resource, payroll, project management, academics, etc. as compared to
general institute practices, but similar in some areas to the ones in public sector /
government sectors in India. Keeping this uniqueness and maturity of the processes in
mind, IITB will use ERP solutions which have been used implemented successfully in
the leading universities / education institutes / colleges around the world.
3.3 Implementation Methodology
The methodology to be deployed by the bidder to implement the ERP solution will
have different work elements and activities. All these activities and work elements
should coherently focus on achieving following key results.
i. Quality of the solution deployed
ii. User satisfaction while deploying and usage
iii. Successful implementation in terms of completeness and timely
accomplishment of the outcome
While there are different techniques and tools available as a part of the methodology,
followings are expected to be part of the implementation methodology to be adopted by
the bidder.
i. Workshops with different stake holders for capturing business
requirements, creating awareness of best practices, communicating the
changes, building consensus on process design, for signing off the
deliverables etc. These need to be organized at different intervals and in
different places throughout the duration of the project as demanded by
the context.
ii. Stakeholder consultations other than workshops, with those
stakeholders who will be identified by IITB, for the purpose of critical
inputs, review, suggestions, process description, etc.
iii. Review sessions with different stakeholders for signing off the
deliverables, walking through the deliverables for facilitating quick
understanding, etc.
iv. Reviews with experts from the ERP solution OEM.
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 12 o f 56
v. Internal review mechanisms of bidder for ensuring the quality of the
solution and the deliverables.
vi. Adoption of the review comments - effective mechanisms to adopt the
changes suggested.
vii. Documentation of proceedings – recording the developments,
discussions, deliverables, using standard methodology and native tools
available with the ERP solution.
viii. Work standards / practices for documentation, configuration, testing,
data migration, etc.
ix. Training different stakeholders on a continuous basis.
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 13 o f 56
4. Scope of Work Following are the key requirements across business processes at IITB. For details on each functions / area of IITB refer „ANNEXURE I: BROAD FUNCTIONAL REQUIREMENT SPECIFICATION (SEPARATE DOCUMENT)’.
4.1 General Scope
Following are the general features required in ERP application.
Web-based application hosted in the campus network
Secure web-based access (e.g., https instead of http)
Access with single sign-on
Supporting bio-metric, internet banking, and smart card inputs
Capability for continuous improvement and up-gradation
Configurability through web-interface and client interface
Provision for decision support mechanism
Facilitate paperless working
Workflow based process approval and archival mechanism
Digital signatures for selected high level functionaries
Comprehensive data and application security features
Adequate security provisions for preventing tampering of the software as well as
data
Archival of information and data
Provision to define and view rules and regulations of the Institute as per
applicable GOI / IITB norms
Provision for role based access rights
Provision of interactive validations of data entries
Provision for data item based access rights
Provision for reports generation as per requirements
Provision of Linguistic support (Hindi) wherever applicable
4.2 Functional Scope
IITB has decided to go in for a phased approach to implement the ERP solution
across the functional areas listed below.
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 14 o f 56
4.2.1 Indicative Business Coverage Scope
Sr.
No. Functional Area
Brief Description of Sub Modules / Sub
Functions
Required
in ERP ** Integration requirements
Annexure I –
FRS Reference
1 Finance and
Accounts
General
Accounts Receivable, Accounts
Payable, Student Fees and Billing,
Asset Accounting, Cash / Bank
Management, Funds Grants
Management, General Ledger,
Budgeting and Planning, Student
Accounts, etc.
Salary Unit
Drawing salary including allowances,
bonuses, etc. of employees of all
categories –regular, contract
,temporary / various advances and
settlements / reimbursement of
various allowances / retirements and
final payments/issue of annual Form
16 / Form 16A / calculation of Lien
contribution / payments to external
guests / examiners, etc. / pay fixation
and arrear payments
Retirement Benefits Unit
Pension
Payment of retirement benefits i.e.
gratuity, pension, family pension,
commuted value of pension / pension
revision and payment of arrears due
to revision in pay / monthly pension
disbursement of approx.. 1900
pensioners and family pensioners /
income tax calculation and issue of
Form 16 / preparing budget for
pensionary benefits
GPF / CPF
GPF, CPF subscriptions, advances,
withdrawals and payments.
Yes To be handled as part
of core ERP solution
IITB_FRS_
Accounts.xlsx
IITB_FRS_Inte
rnal Audit.xlsx
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 15 o f 56
NPS
Registration of employees / transfer
of NPS subscription to Specified
Financial Institutions subscribers
account / final payment of
accumulated fund through NSDL
Bank reconciliation / preparation of
final accounts / investment funds in
banks / budget preparation
Student Accounts Unit
Scholarship payments, contingency
payments for research scholars /
student fee collection/refund of fees /
student TA-DA advances and
settlements, NCC and student
gymkhana related expenditure /
independent student activities with
sponsored funding, etc.
Stores Accounts Unit
Local purchase through purchase
order / imports; payment through
telegraphic transfer and through
letter of credit, etc.
Hostel Accounts
Payment of Salary and pension
subsidy, uniform subsidy, medical
allowance / retirement benefits to
mess employees, purchases and
other expenditure / maintaining cash
book / investments, etc.
Works Accounts Unit
Payment for construction work bills /
maintenance and repair bills / power
supply and electrical maintenance
works / interior renovation /
decoration / design works / public
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 16 o f 56
health works, etc.
Security deposits, earnest money
deposits, material advances,
mobilization advances, etc. / monthly
remittances of income tax, work
contract tax, professional tax etc./
issue of Form No. 16A for income tax
and Form 402 for Work Contract Tax,
etc.
Final Accounts unit
Preparation of final account
statements as per uniform format
issued by MHRD.
Generate receipts and payments
report
Reconcile cash book ,bank and cash
balance as on 31st March every year
Incorporate from sundry creditor
registers of each unit of account
section towards provision as on 31st
March
Create Sundry Debtors register
Create Journal Entry register
Consolidate various statements of
accounts
Provide depreciation
Preparation of budget and revised
estimates
Remittances and Deposits
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 17 o f 56
LIC salary saving scheme, group
saving linked insurance, professional
tax payments, post office recurring
deposit payment, postal life
insurance payment, GIS retired
members remittance calculation,
remittance of TDS collected from
employees, quarterly e-filling of TDS,
etc.
HBA / Staff Welfare Fund
Advances and settlement against
HBA and Staff Welfare Fund, etc.
Post-Retirement Medical Scheme
(PRMS)
Commencement of PRMS
subscription / maintenance of PRMS
broadsheet / reimbursement for
treatment / statement of accounts /
investments.
GATE,JEE,JAM,GMAT
Maintaining All India Entrance
Examination Income and Expenditure
Imprests Account, Advances ,
Direct Purchases
Cash Imprests: Settlement and
recoupment / general advance and
settlement of advances –For direct
purchases without PO / direct
purchase: Payment to party –(Rate
contract vendors and other party
payments) / Inter departmental
transfers, etc.
2 Human
Resource
Management
and Payroll
Employee Service Book, Faculty
Affairs, Leave Travel Concession,
Payroll, Recruitment, Staff Training,
etc.
Yes To be handled as part
of core ERP solution
IITB_FRS_Hu
man
Resources.xls
x
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 18 o f 56
IITB_FRS_Fun
ds,Recruitmen
t,Leaves,Trave
l.xlsx
IITB_FRS_TA
DA Medical
and other
advances.xlsx
IITB_FRS_IRC
C.xlsx
3 Purchasing
and Inventory
Management
Material code creation, requisition,
purchase order, goods receipt,
issues, returns, scrap sales, end-to-
end E-procurement, etc.
Yes To be handled as part
of core ERP solution
IITB_FRS_Est
ate and
MMD.xlsx
4 Project
Management –
Research and
Development
(R&D)
and
Project
Management –
New
Construction*
Manage project payables, project
receivables, fund allocations, project
proposals, project code creation,
receipt of grants and funds,
honorarium advances and
settlements, investments, budgets,
project monitoring and tracking,
project profitability, financial
statements, etc.
Yes To be handled as part
of core ERP solution
IITB_FRS_IRC
C.xlsx
*Please note –
The FRS for
New
Construction is
not available
at this stage.
5 Estate
Management –
Town Planning
Maintain dimensions and coordinates
of available spaces, bookings and
room / quarter allocations, generate
various notices, recovery of
damages, record warranty details of
fixtures and fittings, rent roll recovery
(electricity, water, license charges),
quarter allocation, etc.
Yes To be handled as part
of core ERP solution
IITB_FRS_IPS
Estate
EMD.xlsx
IITB_FRS_IRC
C.xlsx
6 Asset
Maintenance
Material planning, manpower
planning, resources and tools
planning, preventive maintenance
schedules, generate maintenance
Yes To be handled as part
of core ERP solution
IITB_FRS_IPS
Estate
EMD.xlsx
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 19 o f 56
work orders, integration of estimates
with Schedule of Rates,
Measurement Book, etc.
7 Right to
Information
(RTI)
Generation of RTI application, Online
payment of RTI application fees,
assignment of applications to
concerned units / sections /
departments, etc., generate appeal
orders, document management, etc.
Yes Finance and Accounts
integration for RTI fees
Integration of IITB
portal along with
Document
Management Solution
(DMS) and other core
ERP areas
IITB_FRS_RTI
.xlsx
8 Legal / Board
of Governance
Secretariat
Repository of legal documents,
tracking of legal enquiry, recording
orders against the enquiry, etc
Yes Document
Management System
(DMS) integration with
other core ERP areas
IITB_FRS_Ad
ministration
Legal.xlsx
9 Academics
and Student
Life Cycle
Course administration, timetable
management, admissions,
registrations, scholarships,
examinations, course evaluation,
convocation, etc.
Yes To be handled as part
of core ERP solution
IITB_FRS_Aca
demics.xlsx
IITB_FRS_Trai
ning and
Placements.xl
sx
IITB_FRS_Gy
mkhana.xlsx
10 Alumni
Management
and Corporate
Relations
Maintaining alumni and corporate
directory, recording biographic data,
tracking alumni academic /
employment history, fund raising,
donations, scholarships, etc.
Yes To be handled as part
of core ERP solution
IITB_FRS_Alu
mni
Management.x
lsx
11 Campus
School
Student fees, School
administration, timetable
management, examination
management, etc.
Yes To be handled as part
of core ERP solution
IITB_FRS_Ca
mpus
School.xlsx
12 Administration
–
Advertisement
Services
Generate advertisement requisitions,
advertisement quotations, approval
of requisitions, generation of
purchase order, etc.
Yes To be handled as part
of core ERP solution
IITB_FRS_Ad
ministration
Miscellaneous.
xlsx
13 Administration
– Uniform *
Generate requirements based on
uniform policy, monitor distribution of
uniforms, track performance of
Yes To be handled as part
of core ERP solution
and / or 3rd
party
solution as
IITB_FRS_Ad
ministration
Miscellaneous.
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 20 o f 56
uniform service provider, etc. recommended by the
bidder
xlsx
14 Administration
– Postal *
Track and monitor all information
pertaining to inward and outward
dispatches, barcode for dispatch
tracking, etc.
Yes To be handled as part
of core ERP solution
and / or 3rd
party
solution as
recommended by the
bidder
IITB_FRS_Ad
ministration
Miscellaneous.
xlsx
15 Administration
- Vehicle Fleet
Management *
Generation of vehicle requisition,
approval for vehicle requisition, ability
to schedule vehicle and drivers ,
approval of vehicles by vehicle
department, track and reconcile
distribution of fuel cards, track
performance of vehicle service
provider, etc.
Yes To be handled as part
of core ERP solution
and/or 3rd
party
solution as
recommended by the
bidder
IITB_FRS_Ad
ministration
Miscellaneous.
xlsx
16 Hostel
Management *
Hostel facility information, room
allocation and availability
management, attendance and visitor
records, expense calculation, mess
bill calculation, collection of fees /
fines, etc.
Yes To be handled as part
of core ERP solution
and / or 3rd
party
solution as
recommended by the
bidder
IITB_FRS_Ho
stel
Management.x
lsx
17 Security
Management*
Maintain database for all residents
including non-entitled dependents,
casual laborers, domestic help,
hostel workers, etc.
Covers ID card generation, allocating
names to every room under
academic area, monitoring and
tracking of room keys issue and
return, etc.
Campus security covering online
visitor intimation requests, generation
of visitor / contract passes,
generation of scanned images, bar
code scanner for recording in and out
time, etc.
Asset security around generation of
gate passes for asset movement, etc.
Yes To be handled as part
of core ERP solution
and / or 3rd
party
solution as
recommended by the
bidder
IITB_FRS_Sec
urity.xlsx
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 21 o f 56
* Functional area which needs to be part of the ERP solution (preferably should be part of core ERP
solution or could also be addressed by 3rd party solution in integration with ERP – this has to be
provided by bidder.)
** ERP includes Core ERP; Web based ERP like solution in sequel, and any 3rd party solutions.
“N/A – Not Applicable”
18 Public Health
Office (PHO)*
Complaints handling, scheduled
maintenance monitoring and
tracking, feedback management,
status management, etc.
Yes To be handled as part
of core ERP solution
and / or 3rd
party
solution as
recommended by the
bidder
IITB_FRS_Pu
blic Health
Office.xlsx
19 Guest House
Management
Guest house facility information,
room allocation and availability
management, visitor records,
expense calculation, collection of
fees, etc.
No Finance and Accounts,
Procurement and
Inventory related
activities ,etc. will be
required as part of
integration needs
N/A
20 Central Library Book acquisition, classification of
various library medias, pamphlet
processing, queries, circulation and
reference except serial control,
bound volumes and housekeeping,
etc.
No Students fees, library
fees / penalties finance
integration,
procurement and
inventory related
integration, monitoring
and tracking issue and
return of books and
journals on student
portal, alerts/reminders
on deadline dates,
availability of
requested books, etc.
N/A
21 Hospital
Management *
and
Pathology
Lab *
Issuing of counter slips to patients,
giving appointments of visiting
experts, registering for a pathology
test, entering test results and printing
reports, etc.
Yes
Finance and Accounts,
Procurement and
Inventory related
activities etc. will be
required as part of
integration needs
To be handled as part
of core ERP solution
and / or 3rd
party
solution as
recommended by the
bidder
IITB_FRS_Ho
spital
Management.x
lsx
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 22 o f 56
Note:
The integration needs mentioned for Non ERP areas are at a very high level and the bidder needs to showcase / share their experience of working with similar higher education institutes and recommend the best fit solution for IITB keeping in mind the ease of usability, solution fitment, integration needs, etc.
The bidder has to ensure system driven approach for Non ERP related areas considering the following aspects. Inventory management Procurement Asset management System driven approval Data exchange (inbound / outbound interface between legacy / 3rd party
application and ERP application) Master data management between legacy / 3rd party application and ERP
application Financial transactions in the legacy application to be integrated with ERP
application Facility to export data to standard office suites and generate reports The bidder will be responsible for mapping the functionality of the areas mentioned under core ERP in full as well as integrating the legacy applications (mentioned below).
4.2.2 Illustrative Phased Approach
The ERP solution deployment at IITB is envisaged in two waves (Wave I and
Wave II) as indicated in the section below.
IITB would like to first automate the core back bone processes and functions as
part of Wave I. The solution will then be extended to the student lifecycle
management as part of Wave II.
The integration, data exchange and interfacing needs between existing IITB
applications, legacy applications, 3rd party applications and the proposed ERP
system needs to be considered by the bidder as part of their proposed approach
and methodology for ERP enablement.
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 23 o f 56
Finance HR Mgmt Payroll
Indent Creation
PO Process
Inventory Mgmt.
Project Mgmt.
Estate Mgmt.
Asset Maintain.
R.T.I (DMS)
Legal (DMS)
Security Mgmt
PHO Fleet Mgmt
Hostel Mgmt.
Admin Uniform/
Postal
Pathology
Guest House
Central Library
Wave 1
To be covered as part of core ERP / web based ERP solution
Entire process flow to be preferably covered as part of ERP/web based ERP solution or through integrated 3
rd party applications
These applications will be continued and only the integration / interface needs to be built with ERP/ web based ERP solution
Student Lifecycle Mgmt.
Alumni Mgmt
R.T.I (DMS)
Legal (DMS)
Wave 2
Hospital Mgmt.
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 24 o f 56
Phased roll-out strategy is recommended for implementation of ERP / web-based ERP-like solution at IITB wherein there will be no co-existence of 3rd party
or legacy applications for areas where ERP / web-based ERP-like solution will be implemented.
All Finance / Inventory Management / Procurement related activities across multiple applications will be handled using the core ERP as part of Wave I.
Note - Above phased approach is illustrative and the bidder can propose their recommended phasing approach, methodology, functions / modules coverage for phased implementation as part of the RFP response (as per prior experience).
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 25 o f 56
4.3 Geographical Location
Geographic location is IITB campus in Mumbai, Maharashtra.
4.4 No of users
The tentative employee strength at IITB is around 3,000 employees (including
permanent, contract staff, etc.).
The approximate student strength at IITB to be considered as 10,000
students.
4.4.1 Access and Authorizations
Well defined authorization matrix based on roles and responsibilities to be
built into the system considering following features.
Single sign-on for all system components Support central authentication Ability to define multi-level authority, permissions and flexibility based
on segment / departments
4.5 Technical Scope
The Non Functional requirements for the ERP solution are listed below.
4.5.1. General Application/Solution Requirements
i. The solution should support the following network types.
a. LAN and WAN
b. Leased Lines
c. ADSL Lines
d. Satellite Networks
e. MPLS based Networks
f. VPNs
ii. The solution should provide context based help facilities and also on-
line help at functions, screen and field level that can be tailored to
suit IITB‟s requirement.
iii. The solution should have comprehensive online help facility to
access system specific technical / functional areas.
iv. In case an upgrade has impact on the system installed in the
following areas, the impact shall be borne by the bidder.
a. Configured parameters
b. Newly customized programs
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 26 o f 56
c. Modified standard program source
d. Modifications required for integration with ERP
v. Upgrades should not affect the current version adversely.
vi. The solution should support data conversion tools.
vii. The solution should support e-mail integration.
viii. The solution should support imaging and archiving.
ix. The solution should support the upload and download of multiple
types of documents into the Document Management System that
include office documents, image files and engineering drawings.
x. All functionalities like data entry screens, various reports, batch
processing, integration, etc. should use a common unified application
platform suite to provide ease of management to avoid compatibility
issues.
4.5.2 System Administration and Maintenance
Bidder is required to undertake followings.
i. Formulation of all policies and procedures related to system
administration, database management, applications, archives,
network management and security, back up, etc.
ii. Prepare requisite system landscape and procedures for smoothly
implementing the ERP system.
iii. Bidder shall assist the IITB team to perform all authorization-related
activities (activity group, authorizations, profiles, etc.) till the ERP
system stabilizes.
iv. Assist IITB to manage the legacy data interfaces, print spools, batch
Jobs, printer configuration, etc.
v. Prepare a detailed system administration manual, data administration
manual, operational manual and user manual, which shall be used by
IITB employees to run the ERP system. This shall also include how
the various parameters shall be monitored / tuned in a live system.
vi. Finalize the archival policies for all the functional areas. All
necessary configurations shall be done and tested.
vii. Prepare requisite system configuration for disaster recovery
management and Fail Over system plan.
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 27 o f 56
viii. Round the clock support for trouble shooting in functional and
technical area.
ix. Archiving - application should provide a data archival utility as a part
of standard offerings and facility to search the archived data to create
reports.
x. Audit Trails - Application should provide this facility to trace against
user ID or activity or field level.
xi. Facility to update historical data into the system e.g. Service Book ,
employee history.
4.6 Scope of Services for Bidder
The scope of services for the bidder is as follows.
I. Procurement and Supply of software product/s licenses and associated
software solution components
II. Procurement and supply of database and operating systems
III. Hardware / Infrastructure estimation and sizing and assistance in
procurement
IV. ERP Implementation Services till Go-Live
a. Project Preparation
b. Design / Blueprint
c. Configuration / Customization / Development
d. Testing
e. Data Migration
f. Training and Change Management
g. Documentation
h. Cutover and Go-Live
V. Post Go-Live Stabilization Support
VI. Operations and Maintenance Support
4.6.1 Procurement and Supply of ERP and Web-based ERP-like product/s
licenses and associated software solution components
IITB desires to implement ERP solution that will cater to various classes
of users like transactional, management users, Self Service Users. The
offered ERP product shall meet all requirements as specified in the RFP.
Bidder will provide IITB with options of slab wise license policy / unlimited
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 28 o f 56
license policy / any other policy based on product/s proposed against the
RFP. Bidder will also supply any other related software / Third party
applications / accessories required to make the offered ERP solution
complete.
Bidder will take responsibility of following.
i. Procure and Supply user licenses for transaction, technical and
system administration for the offered ERP product/s. The bidder
shall quote the license fees of the ERP solution including the Web
based ERP like products in sequel and the third party solutions as
applicable at IITB.
ii. Supply tools, accessories and documentation. Tools and
accessories shall be part of the offered solution.
iii. Product documentation to include hard copies and soft copies (sets
of two numbers) to be supplied along with ERP product licenses
and associated software solution and shall include but not limited to
the following.
i. Technical manuals.
ii. Installation guides.
iii. User manuals.
iv. System administrator manuals.
v. Toolkit guides and Troubleshooting guides.
All documents mentioned above or any other standard documentation for
the product will be included in the cost of the license.
Please note that all the licenses of ERP and associated third party software
would be in the name of “Indian Institute of Technology Bombay”.
4.6.2 Procurement and Supply of Database and Operating Systems
Bidder shall take responsibility of followings.
i. Procure and Supply database and operating system for the offered
ERP product/s and recommended hardware components
respectively. The bidder shall quote the cost for the database and
server operating systems as applicable at IITB.
ii. Tools and accessories shall be part of the offered database and
server operating system.
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 29 o f 56
iii. Product documentation to include hard copies and soft copies ( as
per RFP Volume II – Bidding Terms and Conditions) to be supplied
along with database and server operating system and shall include
but not limited to the following.
i. Technical manuals.
ii. Installation guides.
iii. User manuals.
iv. System administrator manuals.
v. Toolkit guides and Troubleshooting guides.
All documents mentioned above or any other standard documentation for
the database and operating system components will be included in the
respective costs.
Please note that all the licenses for database and operating systems (if
applicable) would be in the name of “Indian Institute of Technology
Bombay”.
4.6.3 Hardware / Infrastructure Estimation and Sizing / Installation
The bidder shall identify and provide “Bill of material (BOM)” for
hardware/infrastructure and sizing requirement with specifications
(excluding networking and printers). The bidder shall provide power
planning recommendations of envisaged solution. Bidder shall identify
server requirements and specifications based on IITB‟s requirement for
performance, optimized power usage and scalability. Bidder shall
conduct necessary site visits for IT / non-IT infrastructure requirements,
Data Center (DC) in 3-Tier architecture requirements and Disaster
Recovery (DR / BCP) with near site locations.
Data centre and IT infrastructure components should be hosted
exclusively at IITB Campus (In-house).
The bidder also needs to suggest on staggered requirements of
hardware / network components as per the implementation plan with
required procurement lead time.
Hardware installation for all the components mentioned above shall be
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 30 o f 56
carried out by the bidder.
4.6.4 ERP Implementation Services till Go-Live
4.6.4.1 Project Preparation
Detailed project charter including the detailed project plan, indicating all
activities with resources required, their roles and responsibilities and time
schedule of deliverables should be prepared at the start of the project
including coordination of project implementation plan, approved by the
IITB team.
The project charter should also contain brief project description,
approach and methodology, milestones, project organization, project
risks and mitigation plans, dependencies etc.
The project charter should include a detailed program for installing and
implementing the ERP solution covered under this RFP. The program
shall be in the form of a bar chart/master network identifying key phases
in various stages of the project.
The bidder shall form a project team comprising the following key
positions:
i. Project Manager
ii. Technical Lead
iii. Functional Consultant Leads
iv. Industry expert / Subject Matter Expert
The bidder shall not change any member of the Project Team during the
course of the project. However, in the unlikely event of a change being
required, the procedure for replacement of the personnel can be detailed
by bidder in their response.
4.6.4.2 Business Design
The bidder shall perform a current business study and prepare a
Business Blueprint („As-is‟, „To-be‟ and `Gaps‟) report with required
process definition and flow diagrams, process enhancements and gap-
fitment analysis to map all business requirements of IITB in the ERP
solution as per the functional scope. Indicative expectations and gaps
have been presented under Annexure III for illustration. The bidder is
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 31 o f 56
expected to conduct workshops, give detailed presentations on the
Blueprint, which will include the gap analysis, way forward to fill the gap
and specific recommendations for adoption of new improved business
processes by IITB.
IITB will constitute a project governance structure with adequate
representation from all the stakeholders to review the recommendations
of the bidder and accord necessary approval for the Business Design
report and the new improved business processes to be adopted.
Business Design Objective, approach and methodology should ensure
the following four steps.
Simplification and Standardization of Processes: Processes
of all IITB functions / areas (Department, Centers, Academics,
Finance, Administration, etc.) need to be studied and simplified
into logical steps at first. All processes need to be depicted into
simple flow diagrams with clear linkages. This will help in
reviewing some of the old manual practices in view of the
integrated system scenario of the future. Bidder also needs to
explore the standardization of processes across all IITB functions
/ areas.
Elimination of Redundant and Non Value Adding Processes:
After simplifying the processes, all processes are to be reviewed
to eliminate the redundant steps and practices. Non availability of
information across the IITB functions / areas results in repetitive
and redundant activities in a manual work environment.
Value Addition: After eliminating the redundant processes,
reengineering of processes need to be done keeping in view the
standard available processes / practices in the proposed
enterprise solution software. The primary objective of this step is
to enhance functional efficiency and process performance. This is
the most important phase which will have a strong bearing on the
overall performance of the final solution.
Automation: After finalizing the „To-Be‟ process map, automation
through standard enterprise software should be done.
Configuring the „To-Be‟ processes in the system should be able
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 32 o f 56
to address all the defined requirements.
4.6.4.3 Configuration / Customization / Development
The bidder shall be responsible for installation of ERP software,
database, tools, and any other component (together referred as ERP
solution) required for making the ERP solution successfully operational
as per the requirements in RFP. The system is to be a single-instance;
centralized installation servicing the entire organization.
Based on the approved business blueprint, the bidder will undertake the
system configuration and customization. IITB intends to implement
standard ERP application/s functionalities and the leading practices
available in the offered solution, as far as practically possible. Bidder is
required to undertake customization that may be needed in line with the
changed, improved or specific business processes requirement prepared
during Business Design phase of the ERP implementation. Bidder shall
conduct a study of the IITB‟s technical and functional requirements with
process owners and then make required system design modifications
and implement the changes in order to achieve the desired functionality.
However the same must be tested, accepted and approved by IITB.
Bidder shall not expect or propose any additional charges for developing
/ enhancing / customizing / modifying or similar changes in following
objects.
a. Use of ERP application/s provided customer / user exits /
programming interface to achieve specific process requirements /
expectations.
b. Configuration / personalization of field selection and screen
layouts.
c. Any changes done to the standard programs of ERP, ERP add
on modules or third party applications to meet IITB requirements.
d. Definition and assignment of user defined statuses for various
objects.
e. Definition of authorization controls and assignment.
f. Configuration and customization of workflows.
g. Seamless integration across all ERP modules, ERP add-on
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 33 o f 56
components, etc.
h. Seamless integration of any third party / legacy application with
ERP modules and ERP add-on modules or applications
suggested by bidder, etc.
i. Standard reports and variants change to standard reports /
information systems to define and enable user specific variants.
j. Change to ERP standard forms to incorporate standard texts and
IITB logo.
k. Conversion programs developed for migrating master data and
open transaction data / cut over data including historical data
from existing applications for „Go-Live‟.
l. Custom development of reports, forms & print layouts,
enhancements, etc.
4.6.4.4 Testing
The bidder shall provide details of tests being carried out during the
implementation (e.g. including conference room pilots, unit tests, system
integration tests, stress tests and final user acceptance test). Details of
the testing strategy and approach should be provided in the response.
The bidder is responsible to identify and inform IITB regarding testing
requirements and impacts. The successful bidder shall work in a manner
to satisfy all the testing requirements and adhere to the testing strategy
outlined. The bidder must ensure deployment of necessary resources
and tools during the testing phases. The bidder shall take remedial action
based on outcome of the tests.
The bidder shall create the test strategy document that defines the
requirements and goals of ERP configuration, determine the tools and
methods used to check that the system responds correctly, determine
how and when the test will be performed and recommend how the
approval process should occur. The test strategy document shall guide
the project team through the implementation to ensure that planning and
conducting testing activities in the various phases of ERP implementation
are proper. Various testing phases are as follows.
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 34 o f 56
Base Line Testing
The purpose of baseline testing activities is to plan and conduct testing to
validate the baseline configuration. Baseline testing shall ensure that
Baseline configuration is valid, and shall support the business processes
defined in the Business blueprint report.
Baseline testing shall include
a) Unit testing: Testing of transactions and functions within modules and
b) Scenario testing: Testing of all business processes and scenarios
Baseline scope testing shall be carried out in following steps.
a. Define baseline test cases:.
The bidder shall develop the baseline test plan with scenarios
and test data to be used for testing based on the test
templates.
For simple transactions, testing (unit testing) shall be done
straightforward during configuration and the results shall be
recorded.
For transactions that are complex involving multiple screens,
functions and variations, the bidder shall document the test
cases and the test cases shall be tested with a business
process procedure. The bidder shall also maintain the test
cases with test conditions and any variations of the standard
transactions/case procedures.
The bidder shall use the test scenario template entering every
single step (transaction) with input and output data to
document process flows.
b. Create Baseline test plan.
Bidder shall organize and follow up the unit and scenario
testing at the module level during Baseline scope testing.
Bidder shall assign timeframes and resources for testing.
c. Test Baseline.
The bidder shall use the Baseline test plan and the test cases
to test Baseline configuration.
The bidder shall update the status including date of
completion in the Baseline worksheet.
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 35 o f 56
Development Testing
After development and customization / configuration of the ERP solution,
the bidder shall conduct tests to demonstrate the readiness of the system
which meets all the requirement specifications (functional and Non-
functional) as brought out in this RFP. This shall be in accordance with the
procedures detailed in approved business blueprint report.
On the basis of these tests, a report would be submitted by the bidder for
review and approval by IITB. The test results and response times should
be demonstrated by the bidder during all the testing phases (system
preparation, integration and stress and load testing) at IITB location in an
environment / infrastructure as mutually agreed upon.
The development testing shall cover testing of
Unit testing of customer-specific development
Conversions
Enhancements (User-exits / programming interface and other code
enhancements)
Reports
Development should not only be tested by the developer but also by the
process owner to make sure that the test results (output data) are correct,
and reflect the business processes defined in the business blueprint
report. After unit testing is completed, all customer-specific developments,
programs and forms etc. shall be included in the Final Integration Test
Integration and System Testing
Purpose of the integration test is to execute the integrated components,
including simulation of live operations, and analyze the results that are
important for the functional verification of the production system.
Integration testing shall be accomplished through the execution of
predefined business flows, or scenarios, that emulate how the system
will run the processes of IITB. These business flows, using migrated data
from the existing systems, shall be performed in a multifaceted
computing environment comprising of ERP products, third-party
software, system interfaces and various hardware and software
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 36 o f 56
components. The integration tests shall build the necessary level of
confidence that the solution is complete and will perform the business
processes of IITB.
Integration testing shall focus on cross-functional integration points, as
well as end-to-end business processes. The final integration test plan
shall start with the testing of the cross-functional integration points (touch
points) and end with the end-to-end testing of critical business processes
identified within the business blueprint report.
Integration testing shall be done in two iterations.
The first iteration (Integration test) shall concentrate on testing all
important business processes inside the ERP system / Web-
based ERP-like solution applications / third party applications,
starting with touch point scenarios and ending with end-to-end-
scenarios. It will be done by bidder's functional consultants. Unit
testing shall be carried out for customer specific developments
like user-exits / programming interface and transactions.
Authorizations and user roles would also be tested in the
Integration Test.
System Testing, as a second iteration, shall focus on the most
important cross-enterprise scenarios with touch points to external
components, including testing of conversions, interfaces, reports,
and the necessary authorizations. It will be conducted by IITB
users with the assistance of core team.
Integration and system tests need to be an evolutionary process
that is driven from the previous testing efforts. The test cases and
scenarios that were used for baseline need to be reviewed
collectively by IITB and bidder and enhanced for the integrated
and system tests. These selected cases will be combined to
represent a business process flow such as a project management
cycle or a material acquisition cycle, etc. Problems encountered
during these activities shall also need to be tested under an
integrated environment.
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 37 o f 56
Load and Stress Testing
Once the system integration testing of the configured and customized
solution has been conducted successfully, load, scalability and stress
testing would be conducted prior to commissioning and Go-Live. The
bidder should use suitable simulation tools in accordance with the
agreed test procedures keeping in view IITB‟s projected future load of
transactional users as mutually agreed with IITB. After successful testing
and its approval by IITB, the solution would then be considered as ready
for Migration and Go-Live.
System Acceptance Testing
The bidder will develop acceptance test procedures for IITB approval.
The purpose of this acceptance is to ensure conformance to the required
process operations, response times, and integrity of the software after
installation, and to eliminate any operational bugs. Acceptance has to
commence before data migration activities take place.
This will include
Fine tuning of the software, ensuring all required related software
components are installed.
All the acceptance tests should be carried out before Go-Live at site.
At the satisfactory conclusion of these acceptance tests, the
implementation of the software shall be considered complete for
migration and Go-live.
4.6.4.5 Data Migration
Data migration will include identification of data migration requirements,
collection and migration of user data, master data, open transactions,
documents and data from the legacy systems.
The key requirements for data migration are as follows.
Identify and assess data to be migrated
Specify forms / formats / templates / tools for data inputs and
upload
Data migrated will be rationalized, transformed and reconciled
All the legacy data will need to be migrated as per the
following requirement / list
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 38 o f 56
Opening and closing balances
All open transactions and historical data available for 10 years
in third party / legacy applications till „Go-Live‟
Archival data which will include documents such as
transactions or any other relevant document required for
pattern or trend analysis or statutory / legal requirements, etc.
o All employee records
o All asset records since the date of capitalization
o Identification and development of the data upload /
download programs or deployment of specific data
migration tools
Additional Requirements for Data Migration
The bidder shall be responsible for extraction of data from the legacy
applications / spreadsheets, mapping of such extracted data and
uploading of data into the proposed ERP solutions including
consistency checks.
The bidder shall formulate the “Data Migration Strategy Document”
which will also include quality assurance mechanism. This will be
reviewed and signed–off by IITB prior to commencement of data
migration.
The bidder shall convey to IITB in advance all the mandatory data
fields required for functioning of the proposed solution and which are
not available in the legacy systems / spreadsheets that are required
to be obtained by IITB.
The bidder shall develop data entry programs / applications or deploy
any data migration tools that may be required for the purpose of data
migration in order to capture data available with / obtained from IITB
in non– electronic format.
The bidder shall generate appropriate control reports before and after
migration to ensure accuracy and completeness of the data.
IITB and the bidder shall mutually conduct the acceptance testing and
verify the completeness and accuracy of the data migrated from the
legacy systems to the proposed solution.
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 39 o f 56
4.6.4.6 Training and Change Management
The bidder is required to train all staff identified as ERP core users to
enable them to effectively operate and perform the relevant services
using the software. The training content will have to be relevant to the
target trainees depending upon the role played by them in IITB.
Training Approach
A training need assessment for IITB ERP core team members as
well as for end users shall be conducted by the bidder, as a
component of process improvement and change management.
Training needs should be continuously refined and frequently
reconfirmed with the end user community as the project
progresses.
Training would be in the form of hands-on training on the ERP
solution. The bidder shall have to identify specific functional
trainers to provide classroom based hands-on training to the
identified users. Bidder shall also provide detailed training
manuals in paper and electronic media formats for each
functional area of ERP solution.
Following kinds of training needs are to be provided by the
bidder.
a. Initial ERP Product Training: Initial training shall be
provided to the ERP core team members. The training should
provide a comprehensive coverage of the ERP solution and
its functionalities. The training shall also highlight the unique
requirement of the proposed ERP solution.
b. ERP Core Functional User Training: Core team user
training shall provide a detailed training to ERP core team
members, so as to enable them to handle future maintenance
of the system and address functional queries, if any.
c. ERP End user Training: Functional training shall be provided
to all ERP users. This training shall focus on user specific
requirements and address the daily working and reporting
requirements in the ERP solution. A refresher training of all
the functions needs to be provided to update the knowledge
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 40 o f 56
of ERP solution users. The refresher course needs to be user
specific.
d. Technical Training: This training shall be given to the
technical team responsible for carrying out technical activities
related to the ERP system programming, maintenance /
administration of database and operating system, backups,
etc.
Training Matrix
The bidder shall mutually discuss and finalize the training plan to
impart training to different users at IITB as per their roles and
responsibilities. The proposed training schedules, duration,
content of training, etc. will be based on the final sign-off from
IITB.
4.6.4.7 Documentation
The bidder will provide detailed final system documentation for the
reference of IITB. The bidder shall provide ongoing relevant product
information for reference purposes and facilitating self-education for IITB
personnel.
Two sets of product documentation to include hard copies and soft
copies to be supplied and shall include following (but not limited).
Configuration document consisting of system setting and
parameters for each functional module
Standard operational procedure (SOP) manuals
Documents related to data structures / tables
On-line help manual
Technical manuals
Installation guides
System administration manuals
Toolkit guides and troubleshooting guides
User manuals including system instructions and use cases,
how to run a program to perform specific task in the system
with sample reports, screen formats, etc.
Program flow and descriptions
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 41 o f 56
Any other documentation required for usage of implemented
solution
All documents mentioned above or any other standard documentation for
the product to be submitted to IITB as applicable throughout the lifecycle
of the project.
4.6.4.8 Cutover and Go-Live
The scope of cutover shall cover all the core processes. The cutover
strategy needs to detail the sequence of activities, schedule for the
activities / tasks, data conversion and the data migrations of the
necessary balances and open items before Go-Live.
The key requirements of cut over plan are as follows.
It should detail the data migration strategy mentioning the
nature and volume of backlog transactions and the specified
forms / formats / templates to capture the data.
It should detail the strategy of handling data elements and
open items used for planning cut over before Go-Live.
It should describe the various pre-requisites and assumptions
used for each of the data elements before uploading in the
live system.
It should detail the various institute decisions to be taken
collaboratively by IITB management and bidder for finalizing
the cut over strategy.
Once “Certificate of system acceptance” is provided to bidder
by IITB, it will consider Go-Live date of the ERP solution. IITB
shall provide the certificate based on the following acceptance
criteria.
The bidder is required to undertake the following to review
“Go-Live” readiness.
Facilitate in setting up central help desk for any queries
Review the health and performance of the system till the
cutover of the system
Ensure resolution / documentation and closure of all open
issues raised during implementation
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 42 o f 56
Complete final configuration / integration, volume and stress
testing
Review switch over plan to production environment
i. Declaration of “Go Live” – the system will be declared “Go Live” when
the Go-Live tasks / activities are accomplished satisfactorily.
ii. The bidder shall provide user adoption support after implementation of
ERP solution. During the implementation period prior to “Go Live”, the
bidder would support IITB users in using the system.
Delay in Implementation and Associated Costs
Evaluation will be conducted for the reasons of delay in the project at
various stages of the project. In case of delay in project execution on
account of the bidder, the bidder will be subjected to appropriate penalty.
Penalty Calculations: The framework for penalties, as a result of not
meeting the implementation period is as follows.
The delay will be evaluated for each of the defined project stages.
If the overall delay is more than 2 months on account of
bidder, two (2) % of cost of implementation services will be
deducted.
If the overall delay is more than 6 months on account of the
bidder, five (5) % of cost of implementation services will be
deducted.
If the overall delay found more than 12 months on account of
the bidder, ten (10) % of cost of implementation services will
be deducted.
In addition to penalties stated above, IITB reserves right to
recover cost of investment for delay in implementation.
4.6.5 Post Go-Live Support
The bidder shall provide post Go-Live support, as part of the scope of the
project. The bidder shall continue deploying the technical and functional
consultants on-site after implementation and Go-Live till end of three years.
During the support period, the bidder shall help IITB users to correct any errors
encountered / committed while executing transactions, generating reports,
handholding for quarter closures or month closures. The bidder shall update
the user manuals and configuration manuals, if required.
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 43 o f 56
4.6.6 Operations and Maintenance Support
The bidder shall provide operations and maintenance support to IITB for a
period of four years post conclusion of Go-Live support.
Application Functional Support
The application functional support services contemplated herein shall be
provided for ERP solutions implemented by the bidder. The bidder shall render
on-site maintenance and support services to IITB including back-up and
restoring data services, periodic clean-up and archival.
The scope of the services is as below.
Enhancements and defect fixes. The bidder shall incorporate
technological changes, and provide enhancements as per the requests
made by IITB. The bidder shall also perform minor changes, bug fixes,
error resolutions and minor enhancements that are incidental to proper
and complete working of the application.
Routine functional changes. The bidder shall be responsible for user
and access management, creating new report formats, and configuration
of reports. The bidder shall provide user support in case of technical
difficulties in use of the software, answering procedural questions,
providing recovery and backup information, and any other requirement
that may be incidental/ancillary to the complete usage of the application.
The bidder shall perform user ID and group management services. The
bidder shall maintain access controls to protect and limit access to the
authorized end Users of the IITB.
The services shall include administrative support for user registration, creating
and maintaining user profiles, granting user access and authorization, providing
ongoing user password support, etc.
Following are the key service level requirements for the system, which need to
be ensured by the bidder during the operations and maintenance period.
Service Level Agreements
The response time (time within which the reported incident must be updated /
acknowledged by the support team post assignment) and resolution time (time
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 44 o f 56
within which the reported incident stands completely resolved and the erroneous
functionality becomes operational again) will be the basis for defining service
level agreements (SLA) for functional and technical support.
The performance of the support team shall be tracked on a monthly
basis for software only and on daily basis (8 Hours) for hardware as per
the SLA percentage detailed in the table above. In case of slip in SLA
percentage for any category of incidents, the bidder shall be subjected to
penalty as detailed below. In case of abysmally low performance of the
Priority Criteria Service Levels for Software
(In Business Hours)
Service Levels for Hardware (In Business Hours)
1 (High) Business
Showstopper
A critical function is not available
or very seriously impaired; the
impact on business in severe; a
large number of end users are
unable to perform their normal
work; and / or no readily available
alternative exists.
Response within
30 minutes
Restoration of
service / service
will be within 2
hours 95% of the
time
Response within
10 minutes
System downtime
for each reported
incident not to
exceed 5 % of
total available
hours
2 (Medium) A critical service is unavailable or
seriously impacted by a problem;
no realistic work around is
available and financial, customer-
related or safety related impacts
could occur.
Response with in
1 hour
Restoration of
service / service
will be within 8
hours
(One working day)
90% of the time
Response within
15 minutes
System downtime
for each reported
incident not to
exceed 10 % of
total available
hours
3 (Low) A non-critical service is
unavailable or impaired by a
problem. There is no direct
immediate impact on the business.
Work can continue with minor
disruptions or loss of efficiency.
Alternative ways of performing
normal work is available.
Response within 4
hours Restoration
of service / service
will be within 24
hours (Three
working days)
85% of the time
Response within
30 minutes
System downtime
for each reported
incident not to
exceed 15 % of
total available
hours
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 45 o f 56
support team in terms of meeting the defined SLAs, IITB at its own
discretion may consider termination of the support contract.
SLA Violations and Associated Penalties
A three-monthly performance evaluation will be conducted using the
three monthly reporting periods of that period.
Penalty Calculations: The framework for Penalties, as a result of not
meeting the Service Level Targets is as follows.
The performance will be measured for each of the defined service
level metric against the minimum / target service level
requirements and the violations will be calculated accordingly.
The number of violations in the reporting period for each level of
severity will be totaled and used for the calculation of penalties.
Penalties applicable for each of the high severity violations are
two (2) % of respective quarterly payments to the bidder.
Penalties applicable for each of the medium severity violations
are one (1)% of respective quarterly payments to the bidder.
Penalties applicable for each of the low severity violations is half
(0.5)% of respective quarterly payments to the bidder.
Penalties applicable for not meeting a high (H) critical
performance target in two consecutive quarter periods on same
criteria shall result in additional deduction of five (5) % of the
respective quarterly payment to the bidder. Penalty shall be
applicable separately for each such high critical activity.
Penalties applicable for not meeting a medium (M) critical
performance target in two consecutive quarter periods on same
criteria shall result in additional deduction of three (3) % of the
respective quarterly payment to the bidder. Penalty shall be
applicable separately for each such medium critical activity.
Penalties applicable for not meeting a low (L) critical performance
target in two consecutive quarter periods on same criteria shall
result in additional deduction of two (2) % of the respective
quarterly payment to the bidder. Penalty shall be applicable
separately for each such medium critical activity.
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 46 o f 56
5. Project Management
Other than the management of resources / deployment of experts and
management of timeline as explained in the next sections, the project
management will focus on work plan containing a detailed set of phases, work
packages, activities, and tasks preferably from the standard ERP solution
implementation roadmap.
Use of project management tool - The bidder will use the project management
tool to record the entire activities of the project including but not limited to:
i. The design documents with version control review comments
ii. The minutes of meetings
iii. System documentation
iv. Issue lists, resolutions
v. Training materials
vi. Management reporting
vii. Issue management
viii. Scope management
ix. Risk management
x. Work plan for ERP solution Implementation
The resource plan containing the resources assigned to the ERP solution
implementation should display the planned and actual number of workdays per
month, as well as the variance between the two.
The bidder has to propose an overall work plan to be created for the
implementation of the integrated ERP solution at IITB. A detailed work plan shall
be created for each milestone separately. Status reports shall be prepared on a
periodic basis to facilitate the timely implementation of the project. These shall
be discussed in weekly status meetings to ascertain the progress of the project
team.
Detailed work plans shall be created for all milestones based on a consistent
approach to implementing and tracking their progress against pre-determined
project milestones. The implementation shall follow a consistent approach,
inclusive of a comprehensive project management approach. Project status shall
be communicated on a weekly basis, based upon the standards suggested by
the bidder as Project management approach. The bidder is expected to present
in detail the approach to the following project management parameters but not
limited to:
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 47 o f 56
Road Map
The bidder shall provide complete road map for implementation of project by
component and module wise. The bidder may also suggest changes to the
schedule with justification wherever required. However, IITB shall reserve the
right to effect changes in the Project Plan submitted by the bidder.
Resource Plan
The resource plan will be prepared by the bidder based on the assessment of
the skills required during different phases of the project. The bidder is required
to staff the project so as to complete all the activities within the timelines
expected by IITB. Although the bidder is free to work out its own resource
loading and the skill deployment plan, IITB will use this to judge whether the
bidder is planning to staff the project to ensure timely completion of the project
or not. IITB will have the right to ask for changing the resource plan during the
project execution stage, if it finds that the project is either under staffed or over
staffed with inadequate skills (to ensure that inadequate skills are not substituted
by more people).
Management Reporting
A management reporting structure has to be proposed by the bidder and all
deliverables associated with the project shall be categorized and maintained in a
system environment (server) so that they are accessible to all the members of
the project team. The size, scope and strategic nature of the implementation
project, required executive level leadership and sponsorship, as well as an
organized and agreed-upon structure that supports the flow of information. This
structure shall assist in facilitating many of the process teams' daily activities as
well as project and sub-project level communications and knowledge co-
ordination activities.
Issue Management
An issue is a formally identified matter that may hinder progress on a project or
program and about which no agreement has yet been reached. Often it can be
difficult to determine which questions should be documented as issues and
which can be resolved directly without impeding the project flow. Those items
that require documentation, formal investigation and approval should be
managed as issues and this issue management methodology has to be
proposed by the bidder.
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 48 o f 56
Scope Management
Scope of the project will be managed through a formal scope change
management process. Project management is essential to ensure that changes
to the scope of the program do not adversely affect the program objectives.
Change management documentation of project scope and approval procedures
provide a visible decision-making process for the project and provide a clear
audit trail of scope changes and the corresponding cost benefit appraisal and
has to be proposed by the bidder in the Project Management Methodology.
Risk Management
An implementation project, like other projects, has some risks associated with it.
Identifying and managing the risks is very important to the critical success of the
project. During the detailed scoping exercise, the risks shall be identified and a
mechanism to identify and manage such risks shall be defined by the bidder.
Risk management is a continuous iterative process and shall be established
when the project begins and continuously performed until the project ends.
Risks shall be defined at the Project level. It will be the responsibility of IITB and
the bidder Project Management Team to address the project risks from
milestone-to-milestone and make sure the respective responsibilities are
managed.
5.1 Proposed Project Plan
The Time frame for wave wise Implementation is of 24 months with post go-live
support till the end of 3rd year. The bidder is expected to submit their project
plans and milestone as per the proposed time frame.
Sr.No Items M1 M2 M3 M4 M…
1 Procurement and supply of ERP Product
and other software
2 Hardware Procurement
3 Implementation Services
A Project Preparation
B Design / Blueprint document
C Configuration / Customization /
Development
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 49 o f 56
D Testing
E Data Migration
F Training
G Go-Live
4 Post Go-Live Stabilization
5 Operations and Maintenance Support
5.2 Project Deliverables The bidder shall submit a schedule for the below mentioned milestones and
deliverables (but not limited to) that would be delivered during the course of the
project plan. The proposed timeline of submission of the deliverable should also be
mentioned in „T+W‟ format wherein „T‟ shall specify the day of kick-off meeting and
„W‟ shall specify the number of weeks after the kick-off meeting when the deliverable
would be submitted. The bidder shall be bound with the proposed and finalized (after
discussion with IITB) project plan and timelines for submission of deliverables.
i. The table gives a set of high-level activities and corresponding deliverables
which will be in project scope.
ii. The bidder should use this list only as a guideline in terms of expected
deliverables. The bidder is required to furnish detailed information regarding
each deliverables of every step of activities proposed during and after the
implementation of the project.
Following are the list of key activities and deliverables (but not limited to) for the
project phases as a part of ERP implementation at IITB.
Activities Deliverables
1. Project preparation Project charter and Project plan
Initial Training on ERP and Modules functionality
2. Design / Blueprint
Detailed Project Plan for Design / Blueprint
As-Is report
To-Be report
GAP assessment report
Change management work shop for new process
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 50 o f 56
3. Hardware / Infrastructure
Estimation and sizing
Detail BOM with technical specifications and services
required with estimated expenditure. (IT infrastructure sizing
shall be certified by ERP OEM)
BCP / DR plan document, Backup strategy document,
Storage strategy document
Power Planning report
4. Configuration and
Customization Configuration documents for all process and modules
Customization-design, development and technical
documents
Customized Components:
o Reports
o Forms / Layouts
o Enhancements
o Workflow
o Interface
Roles and Authorization Matrix
5. Testing Testing Strategy document -Testing Plan, Test data and
results
Load testing report
System acceptance testing report
Baseline testing report
Development testing report
Integration testing report
Issue Log for all testing
6. Data Migration Data collection templates
Data migration strategy report
Data migration tools and conversions
7. Training and Change
Management
Training Plan with schedules and content
User Plan
Change management report
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 51 o f 56
Delivery of User Training as per the matrix
8. Cut-over and Go-live Cut-Over strategy and Go-live Plan
9. Post Go-live support Go-live support till the end of 3rd
year
10. Operation and
Maintenance support for four
Years
O&M support for Four (4) years
(After post Go- live support)
5.2.1 Deliverables Acceptance Criteria
The acceptance criteria shall be specified for all the project phases
proposed by the bidder. A list of standard deliverables (indicative)
for each phase is listed above. The formal acceptance of the phase
wise deliverables by IITB constitutes completion of the phase and
approval to launch the next phase. The bidder may invoice IITB for
payment for the completed phase as per agreed payment
milestones.
5.3 Governance Structure and Project team Requirements
5.3.1 IITB Project Team
IITB will constitute a project governance framework.
The bidder shall propose the governance structure which will be interacting
with the IITB along with the escalation matrix and time duration of the
response by the concerned personnel.
5.3.2 Bidder Project Team
The bidder shall propose a team that would be involved in the entire
project life cycle. The minimum expected experience, certifications and
other required details are mentioned below. IITB reserves rights to
interview and approve / reject the project team member(s) proposed for
implementation from time to time.
Project Manager Minimum twelve years of experience, including ERP Project Management
experience of minimum two Projects and implementation experience in
minimum three ERP implementation lifecycles which includes at least one
implementation experience in a University / Education Institute / College
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 52 o f 56
in India / worldwide.
Functional Integration Manager Minimum ten years of experience, including ERP Project Implementation
experience of minimum three Projects which includes at least one
implementation experience in a University / Education Institute / College
in India / worldwide. Should understand different modules of ERP and
effect of change in parameters in one module how the same will affect the
system. He / she should be in charge of all the integration issues during
implementation.
Change Management Lead Minimum ten years of professional experience including experience of
Conducting change management workshops, developing change
management strategy. The person should have led the change
management track in at least two ERP implementation lifecycles.
Functional Leads Minimum eight years of professional experience including Functional Lead
experience of minimum two ERP implementation projects, implementation
experience of minimum three ERP implementation lifecycles which includes
at least one India localization experience in the relevant modules. The
experience should also include minimum one ERP project implementation
in University / Education Institute / College in India / worldwide.
Functional Consultants Minimum three years of professional experience including two years of
experience in ERP implementation including minimum two ERP
implementation lifecycles which include at least one India localization
experience in the relevant modules. The experience should include a
minimum of one ERP project implementation in University / Education
Institute / College in India / worldwide.
Technical Leads
Minimum eight years of experience in the technical domain including
Technical Lead experience of minimum two ERP implementation projects,
implementation experience of minimum three ERP implementation cycle
experience.
Technical Consultants
Minimum three years of professional experience including two years of
experience in ERP technical domain including minimum two ERP
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 53 o f 56
implementation lifecycle experience on different modules, implementing
interfaces to legacy applications, report customization, system architecting
and Database management, etc.
Industry Subject Matter Expert (SME): Should have knowledge about University / Education Institute and
academics functions. ERP implementation experience will be preferred.
IT Infrastructure Lead Should have knowledge on server sizing, how to make specification of the
data-centre, planning for disaster recovery. He/ she should have experience
for at least two instance of developing specification of data centre including
LAN, WAN and storage system.
The proposed project team members should be on the payroll of the bidder
and should have been working with the bidder for more than six months.
The detailed resumes to be provided in the format mentioned in Volume-
II.ANNEXURE III Article 10. For Project manager, Leads and Industry SME
one plus one profile should be proposed. IITB has rights to reject, or change
any proposed bidder team member based on IITB evaluation during
contract finalization.
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 54 o f 56
ANNEXURE I: BROAD FUNCTIONAL REQUIREMENT SPECIFICATION (SEPARATE
DOCUMENTS)
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 55 o f 56
ANNEXURE II: SCRIPTS FOR DEMONSTRATION BY BIDDER
(SEPERATE DOCUMENT)
RFP: Volume I - System Integration Services and Solution Scope, IIT Bombay
P a g e | 56 o f 56
ANNEXURE III: INDICATIVE EXPECTATIONS AND PROCESS GAPS (SEPERATE DOCUMENT)