89
Request for Proposal Chiller Procurement Package for Bellevue Public School District Logan Fontenelle Middle School 701 Kayleen Drive, South Bellevue Nebraska RFP Issue Date: December 20, 2013 Mandatory Pre-Bid Meeting Date: January 3, 2014 Proposal Due Date: January 10, 2014 Delivery Date: March 12, 2014 Completion Date: April 15, 2014 Owners Representative: James McMillion Director of Facilities and Maintenance Bellevue Public Schools 1600 Highway 370 Bellevue, NE 68005 (402) 293-4011 Prepared By: Ricky D. Hiatt P.E.,CEM, LEED AP BD+C RDH Engineering, Inc. 13504 Stevens Street Omaha, NE 68137 402-333-9009 RDH #116-13-01 December 2013

Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

  • Upload
    dinhnhu

  • View
    234

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Request for Proposal

Chiller Procurement Package for

Bellevue Public School District 

Logan Fontenelle Middle School 701 Kayleen Drive, South

Bellevue Nebraska

 

 RFP Issue Date: December 20, 2013

Mandatory Pre-Bid Meeting Date: January 3, 2014

Proposal Due Date: January 10, 2014

Delivery Date: March 12, 2014

Completion Date: April 15, 2014

Owners Representative:

James McMillion

Director of Facilities and Maintenance

Bellevue Public Schools

1600 Highway 370

Bellevue, NE 68005

(402) 293-4011

Prepared By:

Ricky D. Hiatt P.E.,CEM, LEED AP BD+C

RDH Engineering, Inc.

13504 Stevens Street

Omaha, NE 68137

402-333-9009

RDH #116-13-01

December 2013

Page 2: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

toc - 1 RDH Engineering, Inc.

Division ..... Section Title .................................................................................... ............................................ Pages DIVISION 0 – BIDDING REQUIREMENTS 00100 ........ INVITATION TO BIDDERS ............................................................ ............................................ 2 00200 ........ INSTRUCTION TO BIDDERS ........................................................ ............................................ 5 00300 ........ PROPOSAL FORM ........................................................................ ............................................ 5 00700 ........ GENERAL CONDITIONS ............................................................... ............................................ 37 DIVISION 1 - GENERAL REQUIREMENTS 01100 ........ SUMMARY ..................................................................................... ............................................ 3 01230 ........ ALTERNATES ................................................................................ ............................................ 1 01250 ........ CONTRACT MODIFICATION PROCEDURES .............................. ............................................ 2 01290 ........ PAYMENT PROCEDURES ............................................................ ............................................ 2 01330 ........ SUBMITTAL PROCEDURES ......................................................... ............................................ 7 01600 ........ PRODUCT REQUIREMENTS ........................................................ ............................................ 4 01820 ........ OPERATION AND MAINTENANCE DATA .................................... ............................................ 8 DIVISION 23 – HEATING VENTILATING AND AIR CONDITIONING 15626 ........ AIR COOLED SCREW CHILLERS ................................................ ............................................ 14 ATTACHMENTS MECHANICAL SCHEDULE ............................................................................... ............................................ 1

Page 3: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00100 - 1

SECTION 00100 - INVITATION TO BIDDERS 1.0 INVITATION

A. Bellevue Public School District invites Bids for the Logan Fontenelle – Air Cooled Chiller Bid package – Procurement of an air cooled chiller for Logan Fontenelle school located in Bellevue, Nebraska.

2.0 PROJECT NAME: Logan Fontenelle – Air Cooled Chiller Replacement Project 3.0 COMPLETION

A. Bidder shall indicate proposed delivery date on the Proposal Form. 4.0 QUALIFICATION REQUIREMENTS

A. Bidder shall submit or have, on file, a current Contractor’s Qualification Statement to submit a Bid for this Project. See Section 00200 - Instructions to Bidders for requirements.

5.0 PRE-BID MEETING

A. All Bidders are required to attend and other interested parties are invited to attend a mandatory Pre-Bid meeting for distribution of information and tour of Project Site.

1. TIME: 10:00 AM, January 3, 2014 Local Time.

2. PLACE: Logan Fontenelle

701 Kayleen Drive, South Bellevue, Nebraska Note: Report at front desk Office 6.0 BID RECEIVING AND OPENING: Sealed Bid Proposals as follows:

A. RECEIVING TIME: 2:00 PM January 10, 2014 Local Time.

B. RECEIVING PLACE: Business Department, by one of following methods:

1. Hand-Carry Delivery: Bellevue Public Schools – Welcome Center Attn: Business Department

1600 Highway 370 Bellevue, Nebraska

2. Mailing Address: Bellevue Public Schools – Welcome Center Attn: Business Department

1600 Highway 370 Bellevue, Nebraska 68005

C. OPENING TIME: Opening shall be 10 minutes after “receiving time”, stated above.

1. OPENING PLACE: Bellevue Public Schools – Welcome Center 1600 Highway 370 Bellevue, Nebraska 68005

Page 4: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00100 - 2

D. Bids are valid only if deposited at designated location prior to receiving time. Bids deposited after receiving time will be returned unopened.

E. Valid Bids will be publicly opened and read aloud.

F. All Bidders and interested parties are invited to attend. A Bidder’s List of the Bids shall be

available for attendees. 7.0 EXAMINATION OF BID DOCUMENTS: Bidding Documents may be examined at:

A. Office of: Engineer RDH Engineering, Inc. 13504 Stevens Street, Suite D Omaha, NE 68137 ATTN: Ricky Hiatt (402) 333-9009 Fax: (402) 991-5383 [email protected]

B. Bellevue Public Schools – Web site www.bellevuepublicschools.org

C. Plan Rooms: Omaha Builders Exchange 4255 South 94th Street

Omaha, NE 68127

Phone: 402.593.6908

FAX: 402.593.6912

[email protected]

Page 5: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00100 - 3

8.0 OBTAINING BID DOCUMENTS

A. Bid Documents may be obtained from the Owner’s website, Plan Room or the office of the Engineer.

9.0 BID SECURITY (Not Applicable) 10.0 BOND (Not Applicable) 11.0 REJECTION OF BIDS

A. Owner reserves right to waive any informality or irregularity, in any Bid. Owner further reserves right to reject any or all Bids and to re-advertise for Bids.

B. Owner shall reject Bid of any Bidder who fails to attend Pre-Bid Meeting.

C. Owner reserves the right to reject Bid of any Bidder who fails to submit qualification documentation

for approval or fails to qualify. 12.0 EQUAL OPPORTUNITY IN PROCUREMENT AND CONTRACTS

A. Bellevue Public Schools recognizes the importance of a strong culturally diverse business community and the positive impact that successful businesses have upon the people of the State of Nebraska. Bellevue Public Schools assumes a leadership role in actions that will provide business opportunities for all businesses in the State of Nebraska.

B. Accordingly, Bellevue Public Schools reaffirms its policy of providing equal opportunity to small

business enterprises and to minority, disadvantaged and women owned business enterprises in all aspects of the District’s procurement and contracting activities. This includes procurement of or contracts for operational supplies and equipment, construction projects and materials, service contracts and lease agreements. It is also the District’s policy that any person or business seeking the opportunity to do business with the District shall not be discriminated against on the basis of race, color, religion, sex, national or ethnic origin, age, disability, marital status, or veteran status. Bellevue Public Schools conducts its procurement and contracting activities in a manner designed to prevent unlawful discrimination. District policies are consistent with applicable state and federal laws and regulations prohibiting unlawful discrimination.

END OF SECTION 00100

Page 6: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00200 - 1

SECTION 00200 - INSTRUCTIONS TO BIDDERS 1.0 DEFINITIONS

A. DISTRICT definitions set forth in latest edition of AIA Document A201 – General Conditions of the Contract for Construction, are applicable to these Instructions to Bidders.

B. Bidding Documents: Includes the following;

1. Invitation to Bidders.

2. Instructions to Bidders.

3. Proposal Form.

4. Proposed Contract Documents (Project Manual and Project Drawings).

5. Addenda (issued prior to receipt of Bids).

C. Bidder: Is a person or entity who submits a Bid.

2.0 BIDDER'S REPRESENTATIONS

A. Bidder, by making a Bid, represents that:

1. Bidder has read and understands Bidding Documents and Bid is made in accordance therewith.

2. Bidder has attended Pre-Bid meeting.

3. Bidder has visited the site, and has become familiar with local conditions under

which the Work is to be performed within the requirements of Bidding Documents.

4. Bid is based upon labor, materials, products, systems and equipment required by Bidding Documents without exception.

3.0 EXAMINATION OF BIDDING DOCUMENTS

A. Each Bidder shall examine and study Bidding Documents carefully, examine site and local conditions and shall make written request to Engineer for interpretation or correction of any ambiguity, error or inconsistency discovered. Request must be received at least 7 calendar days before Bid date.

B. Any instruction, change, interpretation or correction shall be set forth by Addenda. No

Bidder shall rely upon response made in any other manner.

4.0 SUBSTITUTIONS

A. Where Bidding Documents refer to any items, materials, products and equipment by means of one or more manufacturer's trade name, catalog reference or similar means of identification of manufacturer, such reference establishes standard of required quality, appearance, dimension or function.

B. Requests for proposed substitution shall be made in writing to Engineer.

1. Submit Request to be received by Engineer no later than 4 calendar days prior to

date of receipt of Bids.

Page 7: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00200 - 2

2. Request shall include name of material, product or equipment to be substituted and a complete description of proposed substitution including drawings, performance and test data and other information required or necessary for a complete evaluation.

3. Bidder shall assume and bear all responsibility for coordinating and performing

related changes in the Work necessitated by such substitution and has included such costs in the Bid.

4. Burden of proof of merit of proposed substitution is upon Bidder.

C. All approved substitutions shall be set forth by Addenda. No Bidder shall rely upon

approvals made in any other manner.

D. No substitutions will be considered after award of Contract, unless otherwise approved by Owner.

5.0 ADDENDA

A. Addenda: Written or graphic instruments issued by Engineer prior to execution of Contract, which modify or interpret Bidding Documents by additions, deletions, clarifications or corrections. Addenda shall be binding and become part of Contract Documents.

B. Prior to receipt of Bids, Addenda will be issued to all recorded by Engineer as having

received a complete set of Bidding Documents. Copies of Addenda will be available wherever Bidding Documents are on file for inspection.

C. Bidder is responsible to verify with Engineer that Bidder has received all addenda. Failure to

receive such addenda shall not relieve Bidder from any obligation under his Bid as submitted. Bidder shall acknowledge receipt on Proposal Form.

D. Addenda issued after receipt of Bids will be delivered to selected Bidder.

6.0 PREPARATION OF BIDS

A. Bids shall be submitted on Proposal Form included in Bid Documents.

B. All blanks on Proposal Form shall be filled in and executed with non-erasable ink product.

1. Any alteration or erasure shall be initialed by the signer of Bid.

2. Sums shall be written in both numbers and words. In case of discrepancy, amount expressed in words shall govern.

C. State the legal name of Bidder and nature of legal form of Bidder. Bid shall be signed by

person or persons legally authorized to bind Bidder to a contract. Bid submitted by a corporation shall also give the state of incorporation and have corporate seal affixed. Bid submitted by an agent shall have a current power of attorney attached certifying agent’s authority to bind Bidder.

7.0 BID SECURITY (Not Applicable) 8.0 SUBMISSION OF BIDS

A. Submit Proposal Form provided and with Bid Security, Electronic format of ”Chiller Bid Data Submittal Information” and any other required documents enclosed in special colored envelope provided, at time of required Pre-Bid Meeting, then sealed and identified with:

Project Title

Page 8: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00200 - 3

Name of Bidder

1. Bids sent by mail: Seal Bid Documents in special envelope as described above, then place in a separate mailing envelope and addressed as indicated in Invitation to Bidders. On the face of mailing envelope add notation: “SEALED BID ENCLOSED”. Allow at least 2 days for United States Postal Service delivery.

B. Bidder is responsible for method and timely delivery to location designated for receiving of Bids.

C. A Bid is invalid if it has not been deposited at designated location prior to time and date for

receipt of Bids indicated in Invitation to Bidders, or prior to any extension thereof issued to Bidders.

1. Bid is invalid if transmitted by automated electronic methods.

D. Unless otherwise provided, no Bidder shall modify, withdraw, or cancel his Bid or any part

thereof for 60 days after time designated for receipt of Bid.

E. Engineer will not answer questions regarding Bidding Documents within 24 hours prior to Bid opening.

9.0 RECEIPT OF BIDS

A. Bids shall be received as indicated in Invitation to Bidders. 10.0 OPENING OF BIDS

A. Bids will be opened publicly and read aloud at location indicated in Invitation to Bidders, directly following the specified closing time for receipt of Bids.

11.0 REJECTION OF BIDS

A. Bidder acknowledges right of Owner to reject any or all Bids, to waive any informalities or irregularities in Bids received and to re-advertise for Bid.

B. Bidder recognizes right of Owner to reject a Bid if Bidder failed to:

1. Submit data required by Bidding Documents.

2. Complete in any way the Proposal Form.

3. Attend the Pre-Bid meeting. 12.0 AWARD OF CONTRACT

A. Intent of Owner is to award a Contract to low responsible Bidder. In determining low responsible Bidder, consideration will be given to following factors associated with the Bidder:

1. Ability, capacity and skill to comply with Specifications and perform the Work

required by the Contract. 2. Performance data, and alternates will be performed to determine the best performing

equipment at the best cost for the Owner. 3. Character, integrity, reputation, judgment, experience and efficiency. 4. Ability to perform the Contract within time specified. 5. Quality of performance of previous Contracts. 6. Previous and existing compliance with laws relating to the Contract.

Page 9: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00200 - 4

7. Price bid for the Work.

B. Owner reserves right to reject Bid of apparent low Bidder, if in the good faith exercise of reasonable discretion, Owner determines that any sub-contractor designated by such Bidder is not qualified for this Project. Bidder shall submit sub-contractor qualifications to Owner within 5 days of bid opening.

C. Owner reserves the right to:

1. Waive informalities or irregularities, in all circumstances to analyze Bids in detail,

and to award contract, which in the good faith exercise of reasonable discretion of the Owner believes to be in its best interest.

2. Accept Alternates in any order or combination, unless otherwise specified. 3. Determine low responsible Bidder on basis of Lump Sum Bid and Alternates

accepted.

D. If a Bidder offers or submits a “voluntary alternate”, it shall be received as information only and not as a basis for determination of low Bidder.

13.0 SUBMISSION OF POST-BID INFORMATION

A. Upon notification by Owner, apparent low responsible Bidder shall submit within 5 days:

1. Statement of costs for each major item or work included in Bid. 2. Designation of the Work to be performed by Bidder with his own forces. 3. List of names of subcontractors, other persons, organizations, or entities (include

those who furnish materials or equipment fabricated to a special design) proposed for such portions of the Work designated in Bidding Documents or names of subcontractors proposed for principal portions of the Work.

a. Bidder shall establish to the satisfaction of Engineer and Owner, reliability and

responsibility of persons or entities proposed to furnish and perform the Work described in Bidding Documents.

b. Prior to final determination of low responsible Bidder, Owner will notify apparent low Bidder in writing if, Owner has reasonable or substantial objection to and refuses to accept any person or firm on list. If Owner has objection, Bidder may withdraw Bid or submit a substitute with adjustment in cost to cover any difference. Owner shall accept adjusted Bid price or disqualify Bidder. In either condition, Bid Security shall not be forfeited.

B. Subcontractors, other persons, organizations, or entities proposed by Bidder and accepted

by Owner must be used on the Work for which they were proposed and accepted, and shall not be changed except with written approval of Owner.

14.0 OWNER'S PROTECTIVE BOND (Not Applicable)

15.0 INSURANCE (Not Applicable) 16.0 SALES AND USE TAX

A. Owner shall furnish Contractor with a Purchasing Agent Appointment and Exempt Sale Certificate Form for items incorporated into the Work and considered by State of Nebraska to be exempt from Sales Tax. Contractor is responsible to monitor valid dates and notify Owner if an extension is necessary.

B. This Appointment and Exempt Sale Certificate does not apply to:

1. Purchase of materials to be used but not incorporated into the Contract work,

Page 10: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00200 - 5

including but not limited to form lumber, scaffolding, etc. 2. Purchase or rental of machinery, equipment or tools owned or leased by Contractor

and used in performing the Work. 17.0 PERMITS, FEES AND LICENSING (Not Applicable)

18.0 MODIFICATIONS OR WITHDRAWAL

A. Bidder may modify or withdraw his Bid at any time prior to bid receiving deadline by notice to Owner at place designated for receipt of Bids.

1. Notice shall be in writing and signed by authorized agent as indicated in original

Proposal Form. 2. Notice of modification or withdrawal of Bid is invalid if transmitted by automated

electronic methods. 19.0 START OF CONSTRUCTION

A. Work shall not begin until contractor has received written Notice to Proceed.

END OF SECTION 00200

Page 11: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00300 - 1

SECTION 00300 - PROPOSAL FORM

TO: Bellevue Public School District Attn: Business Department 1600 Highway 370 Bellevue, Nebraska BID PROPOSAL FOR: Logan Fontenelle – Air Cooled Chiller Replacement Project This Bid is offered and submitted by___________________________________________, hereinafter referred to as Bidder. Bidder proposes to enter into a Single Contract, including all Work as indicated on Drawings and Project Manual prepared by RDH Engineering and dated December 2013. Bidder hereby makes the following representations: 1. Bidder has received Bidding Documents on the above named project. 2. Bidder has received Addenda Numbers ____ through ____, and has included their provisions in this Bid. 3. Bidder has examined Bidding Documents, attended Pre-Bid meeting, visited the Project site, and is

otherwise familiar with local conditions affecting the construction of the Project. Bidder agrees to furnish all labor, materials, tools, equipment, services, transportation, supervision, and miscellaneous expenses required to complete the Work indicated on Bidding Documents within time set forth, for the sum of: Air Cooled Chiller Procurement BASE BID: Provide one (1) nominal 380-ton, motor-driven air cooled chiller, See Specification Section 15626 for approved vendors list and Chiller Schedule for Basis of Design, for the lump sum bid price of: LUMP SUM BID: $ DOLLARS (amount shown in both numbers and words. In case of discrepancy, words shall govern.) ALTERNATES Alternates: Lump Sum Bid may be increased or decreased by acceptance of Alternate proposals as listed below. For a full and complete description of Alternates see Section 01230 – Alternates.

Page 12: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00300 - 2

ALTERNATE # 1: Provide a 5-year compressor parts warranty, ADD from the Lump Sum Bid the sum of: $ DOLLARS (amount shown in both numbers and words. In case of discrepancy, words shall govern.)

ALTERNATE # 2: Provide factory mounted disconnect if required for submitted chiller. If this alternate is accepted, ADD from the Lump Sum Bid the sum of: $ DOLLARS (amount shown in both numbers and words. In case of discrepancy, words shall govern.) ALTERNATE # 3: Provide condenser coil louvers for hail protection. If this alternate is accepted, ADD from the Lump Sum Bid the sum of: $ DOLLARS

amount shown in both numbers and words. In case of discrepancy, words shall govern.) VOLUNTARY ALTERNATE: Provide an optimized vendor selected air cooled chiller at 380 tons. Lump Sum Bid: $ DOLLARS (amount shown in both numbers and words. In case of discrepancy, words shall govern.)

Page 13: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00300 - 3

In submitting this Bid, Bidder agrees: To hold this Bid open for 120 days following Bid date; To enter into and execute "Standard Form Construction Agreement" based upon this Bid, if this Bid is accepted by Owner; To perform all Work required by Contract Documents; Anticipated chiller delivery date March 12, 2014 To substantially complete the work, including start-up services, no later than April 15, 2014. To comply with Nebraska Fair Employment Practice Act, understanding that breach of this provision shall be regarded as a material breach of Contract; That this Bid amount has been arrived at without collusion with other eligible Bidders and without effort to prevent Bellevue Public Schools from receiving lowest possible competitive Bid. Dated this day of 20 . Signed: Title Printed name of signature of Above : Bid of: A Corporation organized and existing under laws of the State of : A Partnership doing business as: An Individual doing business as: Address of Bidder: Telephone Number of Bidder: Fax Number of Bidder: E-Mail of Bidder:

Page 14: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00300 - 4

BPS-Chiller Installation- Chiller Bid Data Submital InformationBASE BID

1.0 GENERAL1.1 Manufacturer1.2 Rated net full load capacity, tons1.3 Input Power1.4 Refrigerant Type1.5 Unit shall be selected with 33% Propylene glycol (Y/N)1.6 Unit voltage/Phase1.7 MCA1.8 MOP1.9 IPLV

2.0 COMPRESSOR2.1 Type (Screw,Scroll)2.2 Part load performance (attach performance curves/tables)

(Indicate 100%, 75%, 50%, and 25% loads at full flows with ambient air conditions at 95°F)

2.3 Number of compressors2.4 RLA2.5 Inrush current

3.0 EVAPORATOR3.1 Chilled water flow, gpm3.2 Number of evaporator passes3.3 Number of evaporator tubes3.4 Evaporator tube O.D., inches3.5 Internal tube surface area, sq. ft. 3.6 Tube water velocity, min/design/max - fps3.7 Pressure loss thru evaporator at design flow, ft. hd.3.8 Minimum chilled water flow at design temperatures, gpm3.9 Entering Fluid Temperature °F

Leaving Fluid Temperature °F

4.0 CONDENSER4.1 Number of Fans4.2 Fan motor HP4.3 Fan speed4.4 Low ambient control4.5 Unit Airflow4.6 Ambient Air Temperature4.7 Fan diameter

BASE BID5.0 INTEGRATED PART LOAD VALUES (IPLV)5.1 100% rated capacity, KW/Ton5.2 90% rated capacity, KW/Ton5.3 80% rated capacity, KW/Ton5.4 70% rated capacity, KW/Ton5.5 60% rated capacity, KW/Ton5.6 50% rated capacity, KW/Ton

6.0 MOTOR6.1 Type6.2 Manufacturer/Model6.3 Speed, RPM6.4 Horsepower6.5 Starting kVA6.6 Rated amperage6.7 Nameplate efficiency %6.8 Nameplate power factor6.9 Power factor correction capacitors, kVAR7.0 maximum number of starts per hour7.1 Part load efficiency/power factor curve

Page 15: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00300 - 5

7.0 STARTER7.1 Type7.2 Manufacturer/Model7.3 Protection package type7.4 Protection package manufacturer/Model7.5 Integral or separate protection package7.6 Total auxiliary power required at full load, kW

8.0 GENERAL8.1 Total refrigerant, lbs8.2 Number of components shipped8.3 Size of largest component, length x width x height, ft8.4 Assembled overall size, length x width x height, ft8.5 Operating weight, lbs8.6 Recommended tube removal length, ft8.7 Maximum operating loads at each base point, lbs

9.0 SOUNDPredicted sound power levels at full load when measured in accordance

with ARI Standard 575, db re:0.002 microbar with acoustical sound reducing wrap installed, +/- 5 db

9.1 Octave band center frequency 639.2 Octave band center frequency 1259.3 Octave band center frequency 2509.4 Octave band center frequency 5009.5 Octave band center frequency 10009.6 Octave band center frequency 20009.7 Octave band center frequency 40009.8 Octave band center frequency 80009.9 Representative A weighted sound power level, dBA

10.0 DELIVERY10.1 Delivery date after receipt of notice of contract award

Page 16: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00300 - 6

MULTIPLE CONTRACTS 

E‐VERIFY AGREEMENT 

 

This Agreement is made this ____day of ______________________by and between Sarpy County School 

District No. 001 a/k/a/ Bellevue Public Schools (hereinafter referred to as "BPS") and 

____________________________(hereinafter referred to as "Contractor''). 

BPS and Contractor hereby incorporate the following into each and every other agreement, whether oral or 

written, whether by work order, purchase order or otherwise, entered into between BPS and Contractor during 

any period during the term of this Agreement as if the following was part of each and every other agreement. 

NEW EMPLOYEE WORK ELIGIBILITY STATUS 

The Contractor is required and hereby agrees to use a federal immigration verification system to determine the 

work eligibility status of new employees physically performing services within the State of Nebraska.   A federal 

immigration verification system means the electronic verification of the work authorization program authorized 

by the Illegal Immigration Reform and Immigrant Responsibility Act of 1996,8 U.S.C. 1324a, known as the E‐Verify 

Program, or an equivalent federal program designated by the United States Department of Homeland Security or 

other federal agency authorized to verify the work eligibility status of newly hired employee. 

If the Contractor is an individual or sole proprietorship, the following applies: 

1. The Contract must complete the United States Citizenship Attestation Form, available on the Department of 

Administrative Services website at www.das.state.ne.us 

2. If the Contractor indicates on such attestation form that he or she is a qualified alien, the Contract agrees to 

provide the US Citizenship and Immigration Services documentation required to verify the Contractor's 

lawful presence in the United States using the Systematic Alien Verification for Entitlements (SAVE) 

Program. 

3. The Contractor understands and agrees that lawful presence in the United States I required by the Contractor may be disqualified or the contract terminated if such lawful presence cannot be verified as 

required by Neb. Rev. Stat. §4‐108.   

The Agreements shall remain in full force and effect until either BPS or Contractor terminate said Agreement or in 

ten (10) years, whichever occurs first. 

Date: _____________,  20___. 

Sarpy County School District   

No. 001, a/k/a/  Bellevue Public Schools   _______________________Contractor 

 

By:_____________________________  By:______________________________   

Name: James McMillion  Name:___________________________ 

Title: Director of Facilities & Maintenance   Title:______________________ ______   

END OF SECTION 00300

Page 17: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 1

SECTION 00700 - GENERAL CONDITIONS 1.0 THESE GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION APPLY TO ALL

PHASES AND PARTS OF THE WORK. THE GENERAL CONDITIONS ARE THE AIA A201 (1997 15th Edition) GENERAL CONDITIONS.

ARTICLE 1 GENERAL PROVISIONS 1.1 BASIC DEFINITIONS 1.1.1 THE CONTRACT DOCUMENTS The Contract Documents consist of those documents set forth in this chiller procurement package. A

Modification is (1) a written amendment to the Contract signed by both parties, (2) a Change Order, (3) a Construction Change Directive, or (4) a written order for a minor change in the Work. Unless specifically enumerated in the Agreement, the Contract Documents do not include other documents such as bidding requirements (advertisement or invitation to bid, Instructions to Bidders, the Contractor's bid or portions of Addenda relating to bidding requirements).

1.1.2 THE CONTRACT The Contract Documents form the Contract for Construction. The Contract represents the entire and

integrated agreement between the parties hereto and supersedes prior negotiations, representations or agreements, either written or oral. The Contract may be amended or modified only by a Modification. The Contract Documents shall not be construed to create a contractual relationship of any kind (1) between the Engineer and Contractor or any Subcontractor, (2) between the Owner and a Subcontractor or Sub-subcontractor, (3) between the Owner and Engineer or (4) between any persons or entities other than the Owner and Contractor. The Engineer shall, however, be entitled to performance and enforcement of obligations under the Contract intended to facilitate performance of the Engineer's duties.

1.1.3 THE WORK The term "Work" means the construction and services required by the Contract Documents, whether

completed or partially completed, and includes all other labor, materials, equipment and services provided or to be provided by the Contractor to fulfill the Contractor's obligations. The Work may constitute the whole or a part of the Project.

1.1.4 THE PROJECT The Project is the total construction of which the Work performed under the Contract Documents may be

the whole or a part and which may include construction by the Owner or by separate contractors. 1.1.5 THE DRAWINGS The Drawings are the graphic and pictorial portions of the Contract Documents showing the design,

location and dimensions of the Work, generally including plans, elevations, sections, details, schedules and diagrams.

1.1.6 THE SPECIFICATIONS The Specifications are that portion of the Contract Documents consisting of the written requirements for

materials, equipment, systems, standards and workmanship for the Work, and performance of related services.

1.1.7 THE PROJECT MANUAL The Project Manual is a volume assembled for the Work which may include the bidding requirements, and

Conditions of the Contract and Specifications.

Page 18: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 2

1.2 CORRELATION AND INTENT OF THE CONTRACT DOCUMENTS 1.2.1 The intent of the Contract Documents is to include all items necessary for the proper execution and

completion of the Work by the Contractor. The Contract Documents are complementary, and what is required by one shall be as binding as if required by all; performance by the Contractor shall be required only to the extent consistent with the Contract Documents and reasonably inferable from them as being necessary to produce the indicated results. .1 In the event of inconsistencies or discrepancies among Contract Documents, interpretations will be

based on following priorities: a. The Agreement. b. Addenda, those of later date having precedence over earlier date. c. The General Conditions of the Contract for Construction. d. Division 1 (General Requirements) of the Specifications (other than the General Conditions). e. Drawings and Divisions 2-16 of the Specifications.

.2 In case of an inconsistency or discrepancy between Drawings and Divisions 2-16 of the Specifications or within either Document, not clarified by addenda, Contractor is deemed to provide the better quality or the greater quantity of the Work.

.3 Repeated features throughout must be constructed alike, although drawn in detail only once and, similarly, all detail and ornament must be continued throughout all moldings, bands, etc., and all indications of material, etc., shall apply to all similar features throughout.

.4 For Work specified to be done "as directed," Contractor must obtain written direction from Owner's Representative before undertaking such work.

1.2.2 Organization of the Specifications into divisions, sections and articles, and arrangement of Drawings, shall

not control the Contractor in dividing the Work among Subcontractors or in establishing the extent of Work to be performed by any trade. Contractor is solely responsible for coordination of bidding and scope of Work of subcontractors and shall assume full responsibility for complete coordination of subcontractors. Owner and/or Engineer will not act as arbiter as to which trade or subcontractor is to furnish and install various items indicated or required to perform construction.

1.2.3 REFERENCES

.1 All laws, ordinances, rules, regulations and orders of any public authority, all standard specifications, manuals and codes, and all manufacturer's specifications, directions, recommendations and publications referred to for the performance of the Work or for the establishment of construction, materials or equipment standards, whether or not specifically made a part of or incorporated by reference in the Contract Documents, shall be and include the latest revisions or editions thereof in effect on the date of the Contract Specifications, or as to Change Orders, on the date of the Change Order.

.2 All references to the "Manufacturer's Specifications," "Manufacturer's Directions" or "Manufacturer's Recommendations' shall refer to the referenced manufacturer's published specifications or manuals. These publications hereby are made a part of and incorporated by this reference in the Contract Specifications as though repeated therein in full, and all manufactured articles, materials and equipment shall be applied, installed, connected, erected, used, cleaned and conditioned accordingly, unless specified to the contrary.

.3 No provision or term of any referenced standard specification, manual, or code, or manufacturer's specification, direction, recommendation or publication, whether or not specifically made a part of or incorporated by reference in the Contract Documents, shall be effective to change the duties and responsibilities of the Owner or Engineer, or any of their consultants, agents, or employees from those set forth in the Contract Documents or Owner-Engineer Agreement, nor shall such provision or term be effective to assign to Engineer or any of Engineer's consultants, agents, or employees, any duty, responsibility, or authority to supervise, direct, or control the furnishing or performance of the Work or any duty, responsibility, or authority to undertake any duty or responsibility contrary to the provisions of the Contract Documents or Owner-Engineer Agreement.

Page 19: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 3

1.2.4 Wherever an article, device or piece of equipment is referred to in the singular, such reference shall apply to as many such articles as are shown on the Contract Documents or are required to complete the installation.

1.3 CAPITALIZATION 1.3.1 Terms capitalized in these General Conditions include those which are (1) specifically defined, (2) the titles of numbered articles or (3) the titles of other documents published by the American Institute of Architects. 1.4 INTERPRETATION 1.4.1 In the interest of brevity the Contract Documents frequently omit modifying words such as "all" and "any" and articles such as "the" and "an," but the fact that a modifier or an article is absent from one statement and appears in another is not intended to affect the interpretation of either statement. 1.4.2 Unless otherwise stated in the Contract Documents, words which have well-known technical or construction industry meanings are used in the Contract Documents in accordance with such recognized meanings.

.1 In the interest of conciseness, references to specification sections and details are preceded by the word "see". Any such references are to be interpreted to include applicable form of the phrase "and comply with,"

.2 In the interest of conciseness, certain sentences, statements, and clauses omit any form of the verb "shall," normally expressed in verb phrase with verbs such as "furnish", "install", "provide", "perform", "construct", "erect", "comply", "apply", "submit", etc. Any such sentences, statements, and clauses shall be interpreted to include the applicable form of the phrase “the Contractor shall," and requirements described therein shall be interpreted as mandatory elements of the Contract.

1.5 EXECUTION OF CONTRACT DOCUMENTS 1.5.1 The Contract Documents shall be signed by the Owner and Contractor. 1.5.2 Execution of the Contract by the Contractor is a representation that the Contractor has visited the site, become generally familiar with local conditions under which the Work is to be performed and correlated personal observations with requirements of the Contract Documents. 1.6 OWNERSHIP AND USE OF DRAWINGS, SPECIFICATIONS AND OTHER INSTRUMENTS OF SERVICE 1.6.1 The Drawings, Specifications and other documents, including those in electronic form, prepared by the

Engineer and the Engineer's consultants are Instruments of Service through which the Work to be executed by the Contractor is described. The Contractor may retain one record set. Neither the Contractor nor any Subcontractor, Sub-subcontractor or material or equipment supplier shall own or claim a copyright in the Drawings, Specifications and other documents prepared by the Engineer or the Engineer's consultants, and unless otherwise indicated the Engineer and the Engineer's consultants shall be deemed the authors of them and will retain all common law, statutory and other reserved rights, in addition to the copyrights. All copies of Instruments of Service, except the Contractor's record set, shall be returned or suitably accounted for the Engineer, on request, upon completion of the Work. The Drawings, Specifications and other documents prepared by the Engineer and the Engineer's consultants, and copies thereof furnished to the Contractor, are for use solely with respect to this Project. They are not to be used by the Contractor or any Subcontractor, Sub-subcontractor or material or equipment supplier on other projects or for additions to this Project outside the scope of the Work without the specific written consent of the Owner, Engineer and the Engineer's consultants. The Contractor, Subcontractors, Sub-subcontractors and material or equipment suppliers are authorized to use and reproduce applicable portions of the Drawings, Specifications and other documents prepared by the Engineer and the Engineer's consultants

Page 20: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 4

appropriate to and for use in the execution of their Work under the Contract Documents. All copies made under this authorization shall bear the statutory copyright notice, if any, shown on the Drawings, Specifications and other documents prepared by the Engineer and the Engineer's consultants. Submittal or distribution to meet official regulatory requirements or for other purposes in connection with this Project is not to be construed as publication in derogation of the Engineer's or Engineer's consultants' copyrights or other reserved rights.

ARTICLE 2 – OWNER 2.1 GENERAL 2.1.1 The Owner is the person or entity identified as such in the Agreement and is referred to throughout the

Contract Documents as if singular in number. The term "Owner" means the Owner or the designated Owner's Representative. The Districts Owner’s Representative will be designated at the start of the Project.

2.1.2 Owner as referred to in these documents is: Bellevue Public School District. 2.2 INFORMATION AND SERVICES REQUIRED OF THE OWNER

2.2.1 Any other provision of the Contract Documents to the contrary notwithstanding, it is expressly understood and agreed that the legal obligation of the Owner to pay the Contract Sum or any part thereof shall be contingent upon the availability of funds appropriated by the Legislature of the State of Nebraska as provided by law, or the availability of other funds of the Owner specifically approved by formal action of the school district for the purpose of payment of the Contract Sum or any part thereof.

2.2.2 Except for permits and fees, including those required under Section 3.7.1, which are the responsibility of the Contractor under the Contract Documents, the Owner shall secure and pay for necessary approvals, easements, assessments and charges required for construction, use or occupancy of permanent structures or for permanent changes in existing facilities.

2.2.3 The Owner shall furnish surveys describing physical characteristics, legal limitations and utility locations for

the site of the Project, and a legal description of the site. Information will be furnished only to extent it is readily available to or can reasonably be determined by Owner

2.2.4 Information or services required of the Owner by the Contract Documents shall be furnished by the Owner

with reasonable promptness. Any other information or services relevant to the Contractor's performance of the Work under the Owner's control shall be furnished by the Owner after receipt from the Contractor of a written request for such information or services.

2.2.5 Contractor will be furnished free of charge up to 10 copies of Contract Documents, including documents

reissued because of changes or revisions. Additional copies may be purchased at cost of reproduction, postage and handling.

2.3 OWNER'S RIGHT TO STOP THE WORK 2.3.1 If the Contractor fails to correct Work which is not in accordance with the requirements of the Contract

Documents as required by Section 12.2 or persistently fails to carry out Work in accordance with the Contract Documents, the Owner may issue a written order to the Contractor to stop the Work, or any portion thereof, until the cause for such order has been eliminated; however, the right of the Owner to stop the Work shall not give rise to a duty on the part of the Owner to exercise this right for the benefit of the Contractor or any other person or entity.

2.3.2 Owner may declare Contract or in default for any one or more of following conditions or reasons:

Page 21: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 5

.1 Failure to complete the Work within Contract period or any extension thereof.

.2 Failure or refusal to comply with order of Engineer or Owner's authorized representative within reasonable time.

.3 Failure or refusal to remove rejected materials.

.4 Failure or refusal to perform anew any defective or unacceptable work.

.5 Bankruptcy or insolvency, or making of any assignment for benefits of creditors.

.6 Failure to provide qualified superintendent, competent workmen or subcontractors to carry on the Work in an acceptable manner.

.7 Failure to execute the Work according to agreed schedule of completion.

.8 Disregard or violation of any provisions of Contract Documents. 2.4 OWNER'S RIGHT TO CARRY OUT THE WORK 2.4.1 If the Contractor defaults or neglects to carry out the Work in accordance with the Contract Documents and

fails within a seven-day period after receipt of written notice from the Owner to commence and continue correction of such default or neglect with diligence and promptness, the Owner may, without prejudice to other remedies the Owner may have, correct such deficiencies. In such case an appropriate Change Order shall be issued deducting from payments then or thereafter due the Contractor the reasonable cost of correcting such deficiencies, including Owner's expenses and compensation for the Engineer's additional services made necessary by such default, neglect or failure. If payments then or thereafter due the Contractor are not sufficient to cover such amounts, the Contractor shall pay the difference to the Owner.

2.4.2 Neither Owner nor its officers, agents, or employees are in any way liable or accountable to

Contractor or its Surety for the method by which completion of said Work, or any portion thereof, is accomplished or for price paid therefor. Contractor and Surety are responsible for all costs for completion of the Work including cost in excess of original Contract price. Contractor will be paid any amount saved if cost of completion is less than original Contract price. Owner does not forfeit the right to recover damages from Contractor or Surety for failure to complete the Contract by taking over the Work or by declaring Contract or Contractor in default. Maintenance of the Work remains Contractor's and Surety's responsibility as provided for in Owners Protective Bond and Guarantee of Contractor.

ARTICLE 3 – CONTRACTOR 3.1 GENERAL 3.1.1 The Contractor is the person or entity identified as such in the Agreement and is referred to throughout the

Contract Documents as if singular in number. The term "Contractor" means the Contractor or the Contractor's authorized representative.

3.1.2 The Contractor shall perform the Work in accordance with the Contract Documents. 3.1.3 The Contractor shall not be relieved of obligations to perform the Work in accordance with the Contract

Documents either by activities or duties of the Engineer or Owner in the Engineer's or Owner’s administration of the Contract, or by tests, inspections or approvals required or performed by persons other than the Contractor.

3.2 REVIEW OF CONTRACT DOCUMENTS AND FIELD CONDITIONS BY CONTRACTOR 3.2.1 Since the Contract Documents are complementary, before starting each portion of the Work, the Contractor

shall carefully study and compare the various Drawings and other Contract Documents relative to that portion of the Work, as well as the information furnished by the Owner pursuant to Section 2.2.3, shall take field measurements of any existing conditions related to that portion of the Work and shall observe any conditions at the site affecting it. The Contractor is responsible for recognizing such errors, inconsistencies or omissions and requesting clarification thereof and is responsible for

Page 22: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 6

consequences of failing to conduct a careful examination of the site as described herein. Any errors, inconsistencies or omissions discovered by the Contractor shall be reported promptly to the Engineer and Owner as a request for information in such form as the Engineer or Owner may require.

3.2.2 Any design errors or omissions noted by the Contractor during this review shall be reported promptly to the

Engineer and Owner, but it is recognized that the Contractor's review is made in the Contractor's capacity as a contractor and not as a licensed design professional unless otherwise specifically provided in the Contract Documents. The Contractor shall not proceed with the Work affected by a reported error, omission or inconsistency without receiving clarification or instruction from the Owner. The Contractor is not required to ascertain that the Contract Documents are in accordance with applicable laws, statutes, ordinances, building codes, and rules and regulations, but any nonconformity discovered by or made known to the Contractor shall be reported promptly to the Owner and Engineer.

3.2.3 If the Contractor believes that additional cost or time is involved because of clarifications or instructions

issued by the Engineer in response to the Contractor's notices or requests for information pursuant to Sections 3.2.1 and 3.2.2, the Contractor shall make Claims as provided in Sections 4.3.6 and 4.3.7. If the Contractor fails to perform the obligations of Sections 3.2.1 and 3.2.2, the Contractor shall pay such costs and damages to the Owner as would have been avoided if the Contractor had performed such obligations. The Contractor shall not be liable to the Owner or Engineer for damages resulting from errors, inconsistencies or omissions in the Contract Documents or for differences between field measurements or conditions and the Contract Documents unless the Contractor recognized such error, inconsistency, omission or difference and knowingly failed to report it to the Owner and Engineer.

3.2.4 By entering into the Agreement with Owner, Contractor acknowledges that the Contractor has examined all

the Contract Documents and other documents pertaining to the Work, examined the character of the site and any existing structures, and is well acquainted with the nature of the Work and with all other matters which can in any way affect the Work.

3.3 SUPERVISION AND CONSTRUCTION PROCEDURES 3.3.1 The Contractor shall supervise and direct the Work, using the Contractor's best skill and attention. The

Contractor shall be solely responsible for and have control over construction means, methods, techniques, sequences and procedures and for coordinating all portions of the Work under the Contract, unless the Contract Documents give other specific instructions concerning these matters. If the Contract Documents give specific instructions concerning construction means, methods, techniques, sequences or procedures, the Contractor shall evaluate the jobsite safety thereof and, except as stated below, shall be fully and solely responsible for the jobsite safety of such means, methods, techniques, sequences or procedures. If the Contractor determines that such means, methods, techniques, sequences or procedures may not be safe, the Contractor shall give timely written notice to the Owner and Engineer and shall not proceed with that portion of the Work without further written instructions from the Engineer. If the Contractor is then instructed to proceed with the required means, methods, techniques, sequences or procedures without acceptance of changes proposed by the Contractor, the Owner shall be solely responsible for any resulting loss or damage.

3.3.2 The Contractor shall be responsible to the Owner for acts and omissions of the Contractor's employees, Subcontractors and their agents and employees, and other persons or entities performing portions of the Work for or on behalf of the Contractor or any of its Subcontractors. 3.3.3 The Contractor shall be responsible for inspection of portions of Work already performed to determine that such portions are in proper condition to receive subsequent Work. 3.3.4 For equipment furnished by Owner and/or by Others and to be installed by Contractor, the Contractor shall

use manufacturer’s current detail drawings, as approved and provided by Owner, to establish roughing-in dimensions, size of and location of service. In case of conflict, the equipment detail drawings and dimensions shall be used, except where aesthetic or structural considerations make an adjustment necessary.

Page 23: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 7

3.4 LABOR AND MATERIALS 3.4.1 Unless otherwise provided in the Contract Documents, the Contractor shall provide and pay for labor,

materials, equipment, tools, construction equipment and machinery, transportation, and other facilities and services necessary for proper execution and completion of the Work, whether temporary or permanent and whether or not incorporated or to be incorporated in the Work. The Contractor shall coordinate and discuss its utility needs with the Owner. The Contractor shall verify the location of the nearest utilities services and use those services most efficient to the completion of the Work. See General Requirements for additional provisions regarding any Owner-furnished utilities.

3.4.2 The Contractor may make substitutions only with the consent of the Owner, after evaluation by the Engineer and in accordance with a Change Order. 3.4.2.1 It is the intent of the drawings and specifications to secure competition consistent with the level of quality and performance desired by the Owner and set out in these documents. 3.4.2.2 When the drawings and/or specifications refer to any item, article, material, method, fabrication, assembly or

construction by means of one or more manufacturer's trade name, catalog reference or similar means of identification or manufacturer, the Contractor shall furnish one of the makes so identified without substitution unless other make or makes have been approved by addendum to the contract documents prior to the receipt of bids. Requests for the approval of items of equal quality should be made in writing to the Engineer ten days prior to the date of the receipt of bids so that a list of acceptable equal quality items can be made known to all bidders by an addendum. If substitutions for named items, articles, materials, methods, fabrications, assembly or construction are approved, the Contractor assumes all responsibility for coordination and performing the related changes in the Work necessitated by such substitutions and shall include in its bid all costs involved therein.

3.4.3 Discipline and Order. The Contractor shall enforce strict discipline and good order among the Contractor's

employees and other persons carrying out the Contract. The Contractor shall not permit employment of unfit persons or persons not skilled in tasks assigned to them.

3.4.4 Bellevue Public School District Policy Prohibiting Sexual Harassment. 3.4.4.1 Federal law Nebraska prohibits sexual harassment. Sexual harassment includes; unwelcome sexual

advance toward a district employee or student, request for a sexual favor, and other verbal or physical conduct of a sexual nature that is so pervasive as to create a hostile or offensive working environment for district employees or a hostile or offensive academic environment for students.

3.4.4.2Contractor, subcontractors or suppliers working under Contract for this Project are required to

exercise control over their employees so as to prohibit acts of sexual harassment. Employer of any person whom the school district, in its reasonable judgment, determines has committed an act of sexual harassment agrees as a term and condition of this Contract to remove such person from the Project site and to take such other action necessary to cause sexual harassment to cease.

3.4.5 Contractor’s Drug Free Work Place Policy. Contractor certifies that as a condition of the Agreement

that neither Contractor nor any employee of Contractor shall engage in unlawful manufacture, distribution, dispensing, possession, or use of a controlled substance including alcohol or alcoholic beverages, in conducting any activity covered by this Agreement. The school district reserve the right to request and receive a copy of the Contractor’s drug Free Work Place Policy. Contractor further agrees to insert a provision similar to this statement in all subcontracts for services required under this Contract.

3.4.6 Use of Tobacco Products. The use of tobacco products in facilities is prohibited.

Page 24: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 8

3.4.7 Employees Under Work Release. The Contractor shall give written notice to the Owner’s Representative

of any employee on the project site that is on the Department of Correctional Services Work Release Program. This notice shall be given prior to that employee starting on the project site.

3.5 WARRANTY 3.5.1 The Contractor warrants to the Owner that materials and equipment furnished under the Contract will be of

good quality and new unless otherwise required or permitted by the Contract Documents, that the Work will be free from defects not inherent in the quality required or permitted, and that the Work will conform to the requirements of the Contract Documents. Work not conforming to these requirements, including substitutions not properly approved and authorized, shall be considered defective. The Contractor's warranty excludes remedy for damage or defect caused by abuse, modifications not executed by the Contractor, improper or insufficient maintenance, improper operation, or normal wear and tear and normal usage. If required by the Engineer or Owner, the Contractor shall furnish satisfactory evidence as to the kind and quality of materials and equipment. Warranties and guarantees of equipment suppliers will be assigned directly to the Owner at the end of the general warranty periods concluding one year from the date of Substantial Completion.

3.6 TAXES 3.6.1 Sales and use taxes on tangible personal property to be incorporated into the project are to be excluded

under the following procedure: The Owner will appoint the Contractor as a Purchasing Agent for the Owner. Such appointment will authorize the Contractor and his subcontractors to issue Exempt Sales Certificates to the vendors when purchasing tangible personal property to be incorporated into the project.

3.6.2 Owner shall furnish Contractor with a Purchasing Agent Appointment and Exempt Sale Certificate Form for

items incorporated into the Work considered by State of Nebraska to be exempt from Sales Tax. Contractor is responsible to monitor valid dates and notify Owner if an extension is necessary. (Ref. Neb. Rev. Stat. § 77-2704.15). This Appointment and Exempt Sales Certificate does not apply to: 1. Purchase of materials to be used but not incorporated into the Contract work, including but not limited

to form lumber, scaffolding, etc. 2. Purchase or rental of machinery, equipment or tools owned or leased by Contractor and used in

performing the work. 3.7 PERMITS, FEES AND NOTICES 3.7.1 Unless otherwise provided in the Contract Documents, the Contractor shall secure and pay for the building

permit and other permits and governmental fees, licenses and inspections necessary for proper execution and completion of the Work which are customarily secured after execution of the Contract and which are legally required when bids are received or negotiations concluded. Whereas, the Owner is an agency of the State of Nebraska, certain fees, licenses and permits may not be required. Therefore, the Contractor should coordinate securing any permits or licenses with the Owner prior to obtaining such. For additional requirements, see General Requirements.

3.7.2 The Contractor shall comply with and give notices required by laws, ordinances, rules, regulations and

lawful orders of public authorities applicable to performance of the Work. 3.7.3 It is not the Contractor's responsibility to ascertain that the Contract Documents are in accordance with

applicable laws, statutes, ordinances, building codes, and rules and regulations. However, if the Contractor observes that portions of the Contract Documents are at variance therewith, the Contractor shall promptly notify the Engineer and Owner in writing, and necessary changes shall be accomplished by appropriate Modification.

Page 25: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 9

3.7.4 If the Contractor performs Work knowing it to be contrary to laws, statutes, ordinances, building codes, and rules and regulations without such notice to the Engineer and Owner, the Contractor shall assume appropriate responsibility for such Work and shall bear the costs attributable to correction.

3.8 ALLOWANCES 3.8.1 The Contractor shall include in the Contract Sum all allowances stated in the Contract Documents. Items

covered by allowances shall be supplied for such amounts and by such persons or entities as the Owner may direct, but the Contractor shall not be required to employ persons or entities to whom the Contractor has reasonable objection.

3.8.2 Unless otherwise provided in the Contract Documents:

.1 allowances shall cover the cost to the Contractor of materials and equipment delivered at the site and all required taxes, less applicable trade discounts;

.2 Contractor's costs for unloading and handling at the site, labor, installation costs, overhead, profit and other expenses contemplated for stated allowance amounts shall be included in the Contract Sum but not in the allowances;

.3 whenever costs are more than or less than allowances, the Contract Sum shall be adjusted accordingly by Change Order. The amount of the Change Order shall reflect (1) the difference between actual costs and the allowances under Section 3.8.2.1 and (2) changes in Contractor's costs under Section 3.8.2.2.

3.8.3 Materials and equipment under an allowance shall be selected by the Owner in sufficient time to avoid

delay in the Work. 3.9 SUPERINTENDENT 3.9.1 The Contractor shall employ a competent superintendent and necessary assistants who shall be in

attendance at the Project site during performance of the Work. The superintendent shall represent the Contractor, and communications given to the superintendent shall be as binding as if given to the Contractor. Important communications shall be confirmed in writing. Other communications shall be similarly confirmed on written request in each case.

3.10 CONTRACTOR'S CONSTRUCTION SCHEDULES 3.10.1 The Contractor, promptly after being awarded the Contract, shall prepare and submit for the Owner's and

Engineer's information a Contractor's construction schedule for the Work. The schedule shall not exceed time limits current under the Contract Documents, shall be revised at appropriate intervals as required by the conditions of the Work and Project, shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work.

3.10.2 The Contractor shall prepare and keep current, for the Owner’s and Engineer's approval, a schedule of

submittals which is coordinated with the Contractor's construction schedule and allows the Engineer reasonable time to review submittals.

3.10.3 The Contractor shall perform the Work in general accordance with the most recent schedules submitted to

the Owner. 3.10.4 Project Schedule: See General Requirements.

Page 26: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 10

3.11 DOCUMENTS AND SAMPLES AT THE SITE 3.11.1 The Contractor shall maintain at the site for the Owner one record copy of the Drawings, Specifications,

Addenda, Change Orders and other Modifications, in good order and marked currently to record field changes and selections made during construction, and one record copy of approved Shop Drawings, Product Data, Samples and similar required submittals. These shall be available to the Engineer and Owner and shall be delivered to the Engineer for submittal to the Owner upon completion of the Work.

3.12 SHOP DRAWINGS, PRODUCT DATA AND SAMPLES 3.12.1 Shop Drawings are drawings, diagrams, schedules and other data specially prepared for the Work by the

Contractor or a Subcontractor, Sub-subcontractor, manufacturer, supplier or distributor to illustrate some portion of the Work.

3.12.2 Product Data are illustrations, standard schedules, performance charts, instructions, brochures, diagrams

and other information furnished by the Contractor to illustrate materials or equipment for some portion of the Work.

3.12.3 Samples are physical examples which illustrate materials, equipment or workmanship and establish

standards by which the Work will be judged. 3.12.4 Shop Drawings, Product Data, Samples and similar submittals are not Contract Documents. The purpose

of their submittal is to demonstrate for those portions of the Work for which submittals are required by the Contract Documents the way by which the Contractor proposes to conform to the information given and the design concept expressed in the Contract Documents. Review by the Engineer is subject to the limitations of Section 4.2.7. Informational submittals upon which the Engineer is not expected to take responsive action may be so identified in the Contract Documents. Submittals which are not required by the Contract Documents may be returned by the Engineer without action.

3.12.5 The Contractor shall review for compliance with the Contract Documents, approve and submit to the

Engineer Shop Drawings, Product Data, Samples and similar submittals required by the Contract Documents with reasonable promptness and in such sequence as to cause no delay in the Work or in the activities of the Owner or of separate contractors. Submittals which are not marked as reviewed for compliance with the Contract Documents and approved by the Contractor may be returned by the Engineer without action.

3.12.6 By approving and submitting Shop Drawings, Product Data, Samples and similar submittals, the Contractor

represents that the Contractor has determined and verified materials, field measurements and field construction criteria related thereto, or will do so, and has checked and coordinated the information contained within such submittals with the requirements of the Work and of the Contract Documents.

3.12.7 The Contractor shall perform no portion of the Work for which the Contract Documents require submittal

and review of Shop Drawings, Product Data, Samples or similar submittals until the respective submittal has been approved by the Engineer.

3.12.8 The Work shall be in accordance with approved submittals except that the Contractor shall not be relieved

of responsibility for deviations from requirements of the Contract Documents by the Engineer's approval of Shop Drawings, Product Data, Samples or similar submittals unless the Contractor has specifically informed the Engineer in writing of such deviation at the time of submittal and (1) the Engineer has given with consent of the Owner written approval to the specific deviation as a minor change in the Work, or (2) a Change Order or Construction Change Directive has been issued authorizing the deviation. The Contractor shall not be relieved of responsibility for errors or omissions in Shop Drawings, Product Data, Samples or similar submittals by the Engineer's approval thereof.

Page 27: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 11

3.12.9 The Contractor shall direct specific attention, in writing or on resubmitted Shop Drawings, Product Data, Samples or similar submittals, to revisions other than those requested by the Engineer on previous submittals. In the absence of such written notice the Engineer's approval of a resubmission shall not apply to such revisions.

3.12.10 The Contractor shall not be required to provide professional services which constitute the practice of

architecture or engineering unless such services are specifically required by the Contract Documents for a portion of the Work or unless the Contractor needs to provide such services in order to carry out the Contractor's responsibilities for construction means, methods, techniques, sequences and procedures. The Contractor shall not be required to provide professional services in violation of applicable law. If professional design services or certifications by a design professional related to systems, materials or equipment are specifically required of the Contractor by the Contract Documents, the Owner and the Engineer will specify all performance and design criteria that such services must satisfy. The Contractor shall cause such services or certifications to be provided by a properly licensed design professional, whose signature and seal shall appear on all drawings, calculations, specifications, certifications, Shop Drawings and other submittals prepared by such professional. Shop Drawings and other submittals related to the Work designed or certified by such professional, if prepared by others, shall bear such professional's written approval when submitted to the Engineer. The Owner and the Engineer shall be entitled to rely upon the adequacy, accuracy and completeness of the services, certifications or approvals performed by such design professionals, provided the Owner and Engineer have specified to the Contractor all performance and design criteria that such services must satisfy. Pursuant to this Section 3.12.10, the Engineer will review, approve or take other appropriate action on submittals only for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents. The Contractor shall not be responsible for the adequacy of the performance or design criteria required by the Contract Documents.

3.13 USE OF SITE 3.13.1 The Contractor shall confine operations at the site to areas permitted by law, ordinances, permits and the

Contract Documents and shall not unreasonably encumber the site with materials or equipment. 3.13.2 Contractor shall provide adequate protection throughout the course of the Work, for all trees and

shrubs on the site indicated in Contract Documents not to be removed. Contractor shall be responsible for damage to any such trees or shrubs during the period of construction and shall replace or repair, any trees or shrubs damaged by Contractor, its subcontractors or employees, with plantings acceptable to Owner at no cost to Owner. Damaged sod areas shall be replaced with top grade sod of a type acceptable to Owner. All landscape repairs shall carry one-year full guarantee.

3.13.3 Contractor shall enforce Owner's Instructions regarding smoking, noise, signs, advertisements, and

fires.

3.13.4 Contractor shall keep the site of construction reasonably free from weeds during the course of construction. Contractor shall cut all weeds on the site so as to discourage further germination.

3.13.5 All utilities, curbs, drives, pavements, streets, buildings, railings, guardrails, improvements, mechanical and electrical equipment, etc., which are damaged or cut during construction and are to be used after construction shall be repaired such that the quality of repaired item equals or exceeds its condition prior to construction.

3.13.6 Continued occupancy of existing facilities: See General Requirements. 3.14 CUTTING AND PATCHING 3.14.1 The Contractor shall be responsible for cutting, fitting or patching required to complete the Work or to make

its parts fit together properly.

Page 28: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 12

3.14.2 The Contractor shall not damage or endanger a portion of the Work or fully or partially completed construction of the Owner or separate contractors by cutting, patching or otherwise altering such construction, or by excavation. The Contractor shall not cut or otherwise alter such construction by the Owner or a separate contractor except with written consent of the Owner and of such separate contractor; such consent shall not be unreasonably withheld. The Contractor shall not unreasonably withhold from the Owner or a separate contractor the Contractor's consent to cutting or otherwise altering the Work.

3.15 CLEANING UP 3.15.1 The Contractor shall keep the premises and surrounding area free from accumulation of waste materials or

rubbish caused by operations under the Contract. At completion of the Work, the Contractor shall remove from and about the Project waste materials, rubbish, the Contractor's tools, construction equipment, machinery and surplus materials.

3.15.2 If the Contractor fails to clean up as provided in the Contract Documents, the Owner may do so and the

cost thereof shall be charged to the Contractor. 3.16 ACCESS TO WORK 3.16.1 The Contractor shall provide the Owner and Engineer access to the Work in preparation and progress

wherever located. 3.17 ROYALTIES, PATENTS AND COPYRIGHTS 3.17.1 The Contractor shall pay all royalties and license fees. The Contractor shall defend suits or claims for

infringement of copyrights and patent rights and shall hold the Owner and Engineer harmless from loss on account thereof, but shall not be responsible for such defense or loss when a particular design, process or product of a particular manufacturer or manufacturers is required by the Contract Documents or where the copyright violations are contained in Drawings, Specifications or other documents prepared by the Owner or Engineer. However, if the Contractor has reason to believe that the required design, process or product is an infringement of a copyright or a patent, the Contractor shall be responsible for such loss unless such information is promptly furnished to the Engineer.

3.18 INDEMNIFICATION 3.18.1 To the fullest extent permitted by law and to the extent claims, damages, losses or expenses are not

covered by Project Management Protective Liability insurance purchased by the Contractor in accordance with Section 11.3, the Contractor shall indemnify and hold harmless the Owner, Engineer, Engineer's consultants, and agents and employees of any of them from and against claims, damages, losses and expenses, including but not limited to attorneys' fees, arising out of or resulting from performance of the Work, provided that such claim, damage, loss or expense is attributable to bodily injury, sickness, disease or death, or to injury to or destruction of tangible property (other than the Work itself), but only to the extent caused by the negligent acts or omissions of the Contractor, a Subcontractor, anyone directly or indirectly employed by them or anyone for whose acts they may be liable, regardless of whether or not such claim, damage, loss or expense is caused in part by a party indemnified hereunder. Such obligation shall not be construed to negate, abridge, or reduce other rights or obligations of indemnity which would otherwise exist as to a party or person described in this Section 3.18.

3.18.2 In claims against any person or entity indemnified under this Section 3.18 by an employee of the

Contractor, a Subcontractor, anyone directly or indirectly employed by them or anyone for whose acts they may be liable, the indemnification obligation under Section 3.18.1 shall not be limited by a limitation on amount or type of damages, compensation or benefits payable by or for the Contractor or a Subcontractor under workers' compensation acts, disability benefit acts or other employee benefit acts.

Page 29: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 13

3.18.3 Contractor agrees to indemnify and hold Owner, Engineer, Engineer's Consultants and agents and employees of any of them harmless from any and all loss or damages arising out of labor disputes between organized local labor units, whether or not of the same trade or craft, or other labor concerns of any kind that may occur during performance of the Contract, to the fullest extent permitted by law.

ARTICLE 4 - ADMINISTRATION OF THE CONTRACT 4.1 ENGINEER 4.1.1 The Engineer is the person lawfully licensed to practice Engineering or an entity lawfully practicing

Engineering identified as such in the Agreement and is referred to throughout the Contract Documents as if singular in number. The term "Engineer" means the Engineer or the Engineer's authorized representative. Engineer, Engineer, Engineer/Engineer or Engineer/Engineer hereinafter called the Engineer as indicated in Bidding Requirement. Each of these terms means the Engineer or an affiliate as otherwise provided in Contract Documents, or duly authorized representatives, such representatives acting severally within the scope of particular duties entrusted to them, unless otherwise provided in Contract Documents. When Contractor is required to contact, notify or otherwise interact with the Engineer, contact the Owner's Representative first. Request instructions from Owner's Representative as to whether the Engineer should also be contacted.

4.1.2 Duties, responsibilities and limitations of authority of the Engineer as set forth in the Contract Documents

shall not be restricted, modified or extended without written consent of the Owner and Engineer. Consent shall not be unreasonably withheld.

4.1.3 If the employment of the Engineer is terminated, the Owner shall employ a new Engineer. 4.1.4 Engineer shall not be liable to Contractor for any claim, cause of action arising out of Engineer's

responsibilities under Contract, either personally or as an official of Owner, it being understood that in such matters Engineer acts as agent and representative of Owner.

4.2 ENGINEER'S ADMINISTRATION OF THE CONTRACT 4.2.1 Owner will provide administration of the Contract as described in Contract Documents during construction

and until final payment is due. Owner will advise and consult with Engineer. 4.2.2 A registered Engineer and/or registered engineer representing the Engineer shall make not less than one

visit to the project site each month during progress of construction, or as directed by Owner, with the Owner's Representative at a time mutually agreed upon between the Owner’s Representative and the Engineer. On the basis of on-site observations, the Engineer shall endeavor to guard the Owner against defects and deficiencies in the Work and shall assist the Owner in obtaining faithful performance of Contract Documents by the Contractor.

4.2.3 The Engineer will not be responsible for the Contractor's failure to perform the Work in accordance with the

requirements of the Contract Documents. The Engineer will not have control over or charge of and will not be responsible for acts or omissions of the Contractor, Subcontractors, or their agents or employees, or any other persons or entities performing portions of the Work.

4.2.4 Communications Facilitating Contract Administration. Except as otherwise provided in the Contract

Documents or when direct communications have been specially authorized, the Contractor shall endeavor to communicate with Owner about matters arising out of or relating to the Contract. Communications by and with the Engineer's consultants shall be through the Engineer. Communications by and with Subcontractors and material suppliers shall be through the Contractor. Communications by and with separate contractors shall be through the Owner.

Page 30: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 14

4.2.5 The Engineer shall not determine amounts owing to the Contractor and shall not issue Certificates for Payment.

4.2.6 The Engineer shall advise the Owner in matters relating to rejection of Work that does not conform

to the Contract Documents. Whenever the Engineer considers it necessary or advisable to ensure proper implementation of the intent of the Contract Documents, the Engineer will advise the Owner to require additional or special inspection or testing of the Work in accordance with the provisions of the Contract Documents whether or not such Work is fabricated, installed or completed.

4.2.7 The Engineer and the Owner will concurrently review and approve or take other appropriate action upon

the Contractor's submittals such as Shop Drawings, Product Data and Samples, but only for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents. Approval or other appropriate action will be taken with such reasonable promptness as to cause no delay in the Work or in the activities of the Owner, Contractor or separate contractors, while allowing sufficient time to permit adequate review. Review of such submittals is not conducted for the purpose of determining the accuracy and completeness of other details such as dimensions and quantities, or for substantiating instructions for installation or performance of equipment or systems, all of which remain the responsibility of the Contractor as required by the Contract Documents. Review of the Contractor's submittals shall not relieve the Contractor of the obligations under Sections 3.3, 3.5 and 3.12. Review shall not constitute approval of safety precautions or, unless otherwise specifically stated by the Engineer and the Owner, of any construction means, methods, techniques, sequences or procedures. Approval of a specific item shall not indicate approval of an assembly of which the item is a component.

4.2.8 With the consent of the Owner, the Engineer shall prepare data for Change Orders and Construction

Change Directives as required by the Owner. The Engineer shall receive a copy of all executed Change Orders and Construction Change Directives.

4.2.9 The Engineer shall assist the Owner in determining the dates of Substantial Completion and Final Completion.

The Engineer will receive and review for completeness written warranties and related documents required by the Contract and assembled by the Contractor. After review of the required documents, the Engineer will forward them to Owner for Owner’s review and records. The Engineer will assist the Owner in preparation of a Certificate of Substantial Completion upon compliance with the requirements of the Contract Documents. The Engineer shall assist the Owner and Contractor in the preparation of a "punch list" to be attached to the Certificate of Substantial Completion.

4.2.11 The Engineer will interpret matters concerning performance under and requirements of, the Contract

Documents on written request of the Owner . The Engineer's response to such requests will be made in writing within any time limits agreed upon or otherwise with reasonable promptness. If no agreement is made concerning the time within which interpretations required of the Engineer shall be furnished in compliance with this Section 4.2, then delay shall not be recognized on account of failure by the Engineer to furnish such interpretations until 15 days after written request is made for them.

4.2.12 Interpretations of the Engineer will be consistent with the intent of and reasonably inferable from the

Contract Documents and will be in writing or in the form of drawings. 4.2.13 The Engineer's interpretations on matters relating to aesthetic effect will be final if consistent with the intent

expressed in the Contract Documents. 4.2.14 Engineer shall advise and consult with the Owner during the Construction Administration Phase.

Engineer shall have authority to act on behalf of the Owner only to the extent provided in the Contract Documents, unless otherwise modified by Owner in writing.

4.3 CLAIMS AND DISPUTES

Page 31: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 15

4.3.1 Definition. A Claim is a demand or assertion by one of the parties seeking, as a matter of right, adjustment or interpretation of Contract terms, payment of money, extension of time or other relief with respect to the terms of the Contract. The term "Claim" also includes other disputes and matters in question between the Owner and Contractor arising out of or relating to the Contract. Claims must be initiated by written notice. The responsibility to substantiate Claims shall rest with the party making the Claim.

4.3.2 Time Limits on Claims. Claims by either party must be initiated within 21 days after occurrence of the event

giving rise to such Claim or within 21 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be initiated by written notice to the Engineer and the other party.

4.3.3 Continuing Contract Performance. Pending final resolution of a Claim except as otherwise agreed in writing

or as provided in Section 9.7.1 and Article 14, the Contractor shall proceed diligently with performance of the Contract and the Owner shall continue to make payments in accordance with the Contract Documents.

4.3.4 Claims for Concealed or Unknown Conditions. If conditions are encountered at the site which are (1)

subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, then notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than 21 days after first observance of the conditions. If requested by the Owner, the Engineer will promptly investigate such conditions and advise Owner as to whether they differ materially and cause an increase or decrease in the Contractor's cost of, or time required for, performance of any part of the Work. If the Owner determines that the conditions at the site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Owner shall so notify the Contractor in writing, stating the reasons. Claims in opposition to such determination must be made within 21 days after the Owner has given notice of the decision. If the conditions encountered are materially different, the Contract Sum and Contract Time shall be equitably adjusted, but if the Owner and Contractor cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment shall be subject to further proceedings pursuant to Section 4.5.

4.3.5 Claims for Additional Cost. If the Contractor wishes to make Claim for an increase in the Contract Sum,

written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.6.

4.3.6 If the Contractor believes additional cost is involved for reasons including but not limited to (1) a written

interpretation from the Engineer, (2) an order by the Owner to stop the Work where the Contractor was not at fault, (3) an order for a change in the Work issued by the Engineer or Owner, (4) failure of payment by the Owner, (5) termination of the Contract by the Owner, (6) Owner's suspension or (7) other reasonable grounds, Claim shall be filed in accordance with this Section 4.3.

4.3.6.1 Any claims for additional cost will be allowed only if the labor, materials, and equipment and the work related

thereto have been ordered in writing by the Owner. Claims for such additional cost must be approved by the Owner before payment is made.

4.3.7 Claims for Additional Time 4.3.7.1 If the Contractor wishes to make Claim for an increase in the Contract Time, written notice as provided

herein shall be given. The Contractor's Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay only one Claim is necessary.

4.3.7.2 If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented

by data substantiating that weather conditions were abnormal for the period of time, could not have been reasonably anticipated and had an adverse effect on the scheduled construction.

Page 32: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 16

4.3.7.3 Time extensions for unusually severe weather. The procedure for determination of time extensions for unusually severe weather shall be as set forth in this Article 4.3.7.3. The following listing defines monthly anticipated adverse weather for the Contract period.

Contractor’s schedule must reflect these anticipated adverse weather delays in all weather dependent activities.

MONTHLY ANTICIPATED ADVERSE WEATHER CALENDAR DAYS

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC (08) (05) (03) (04) (06) (04) (05) (05) (03) (02) (03) (06)

The schedule above will constitute the base line for monthly, or a portion thereof, weather time evaluations. Upon acknowledgement of Notice to Proceed and continuing throughout the Contract, on a monthly basis, actual adverse weather days will be recorded on a calendar day basis (including weekends and holidays) and compared to the monthly anticipated adverse weather schedule, above. The term “actual adverse weather days” shall include days impacted by adverse weather. The number of actual adverse weather days shall be calculated chronologically from the first to the last day in each month. Once the number of actual adverse weather days anticipated in schedule above has been exceeded, Owner will examine all actual adverse weather days to determine whether Contractor is entitled to a time extension. These actual adverse weather days must prevent 50 percent or more of Contractor’s workday, delay Work critical to timely completion of the Project, and be documented in Contractor Quality Control reports. Owner will convert any delays meeting these requirements to calendar days and issue a Change Order to Contractor.

4.3.8 Injury or Damage to Person or Property. If either party to the Contract suffers injury or damage to person

or property because of an act or omission of the other party, or of others for whose acts such party is legally responsible, written notice of such injury or damage, whether or not insured, shall be given to the other party within a reasonable time not exceeding 21 days after discovery. The notice shall provide sufficient detail to enable the other party to investigate the matter.

4.3.9 If unit prices are stated in the Contract Documents or subsequently agreed upon, and if quantities originally

contemplated are materially changed in a Change Order or Construction Change Directive or as a result of other changes in the Work or variations from quantities that are included in the Contract Documents as estimated quantities for unit priced work, so that application of such unit prices to estimated quantities of Work stated in the Contract Documents will cause substantial inequity to the Owner or Contractor, the applicable unit prices shall be equitably adjusted. A material change in the estimated quantities stated in the Contract Documents shall be deemed to have occurred only when the unit priced work item quantity is increased in excess of 125 percent or decreased below 75 percent of the original quantity stated in the Contract for such unit priced work item. This § 4.3.9 shall apply only to unit priced work items where estimated quantities are stated in the Contract Documents.

4.3.10 Claims for Consequential Damages. The Contractor hereby waives all claims against the Owner for all

consequential damages arising out of or relating to this Contract. This waiver includes, but is not limited to, damages incurred by the Contractor for principal office expenses including the compensation of personnel stationed there, for losses of financing, business and reputation, and for loss of profit. This waiver is applicable without limitation to all consequential damages due to Owner’s termination in accordance with Article 14.

4.4 RESERVED 4.5 MEDIATION 4.5.1 Any Claim arising out of or related to the Contract shall be subject to mediation prior to the institution of

legal or equitable proceedings by either party. The parties shall endeavor to resolve their Claims by

Page 33: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 17

mediation the procedures for which shall be mutually agreed upon by the parties. Request for mediation shall be provided by written notice to the other party. The request may be made concurrently with the institution of legal or equitable proceedings but, in such event, mediation shall proceed in advance of legal or equitable proceedings which shall be stayed pending mediation for a period of 60 days from the date of receipt of the request by the other party, unless stayed for a longer period by agreement of the parties or court order. In the event the parties cannot agree upon a mediator and on the procedures and timing for medication within 60 days of a party’s receipt of a request for mediation, such failure shall not preclude either party from instituting legal or equitable proceedings.

ARTICLE 5 - SUBCONTRACTORS 5.1 DEFINITIONS 5.1.1 A Subcontractor is a person or entity who has a direct contract with the Contractor to perform a portion of

the Work at the site. The term "Subcontractor" is referred to throughout the Contract Documents as if singular in number and means a Subcontractor or an authorized representative of the Subcontractor. The term "Subcontractor" does not include a separate contractor or subcontractors of a separate contractor.

5.1.2 A Sub-subcontractor is a person or entity who has a direct or indirect contract with a Subcontractor to

perform a portion of the Work at the site. The term "Sub-subcontractor" is referred to throughout the Contract Documents as if singular in number and means a Sub-subcontractor or an authorized representative of the Sub-subcontractor.

5.1.3 Subcontractors, sub-subcontractors and material suppliers are not to contact Engineer or Owner directly.

All requests for information should be directed to the Contractor. 5.2 AWARD OF SUBCONTRACTS AND OTHER CONTRACTS FOR PORTIONS OF THE WORK 5.2.1 Unless otherwise stated in the Contract Documents or the bidding requirements, the Contractor, as soon

as practicable after award of the Contract, shall furnish in writing to the Owner and the Engineer the names of persons or entities (including those who are to furnish materials or equipment fabricated to a special design) proposed for each principal portion of the Work. The Owner will promptly reply to the Contractor in writing stating whether or not the Owner, after due investigation, has reasonable objection to any such proposed person or entity. Failure of the Owner to reply promptly shall constitute notice of no reasonable objection.

5.2.2 The Contractor shall not contract with a proposed person or entity to whom the Owner has made

reasonable and timely objection. The Contractor shall not be required to contract with anyone to whom the Contractor has made reasonable objection.

5.2.3 If the Owner has reasonable objection to a person or entity proposed by the Contractor, the Contractor

shall propose another to whom the Owner has no reasonable objection. If the proposed but rejected Subcontractor was reasonably capable of performing the Work, the Contract Sum and Contract Time shall be increased or decreased by the difference, if any, occasioned by such change, and an appropriate Change Order shall be issued before commencement of the substitute Subcontractor's Work. However, no increase in the Contract Sum or Contract Time shall be allowed for such change unless the Contractor has acted promptly and responsively in submitting names as required.

5.2.4 The Contractor shall not change a Subcontractor, person or entity previously selected if the Owner makes

reasonable objection to such substitute. 5.3 SUBCONTRACTUAL RELATIONS

Page 34: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 18

5.3.1 By appropriate agreement, written where legally required for validity, the Contractor shall require each Subcontractor, to the extent of the Work to be performed by the Subcontractor, to be bound to the Contractor by terms of the Contract Documents, and to assume toward the Contractor all the obligations and responsibilities, including the responsibility for safety of the Subcontractor's Work, which the Contractor, by these Documents, assumes toward the Owner. Each subcontract agreement shall preserve and protect the rights of the Owner under the Contract Documents with respect to the Work to be performed by the Subcontractor so that subcontracting thereof will not prejudice such rights. Where appropriate, the Contractor shall require each Subcontractor to enter into similar agreements with Sub-subcontractors. The Contractor shall make available to each proposed Subcontractor, prior to the execution of the subcontract agreement, copies of the Contract Documents to which the Subcontractor will be bound, and, upon written request of the Subcontractor, identify to the Subcontractor terms and conditions of the proposed subcontract agreement which may be at variance with the Contract Documents. Subcontractors will similarly make copies of applicable portions of such documents available to their respective proposed Sub-subcontractors.

5.4 CONTINGENT ASSIGNMENT OF SUBCONTRACTS 5.4.1 Each subcontract agreement for a portion of the Work is assigned by the Contractor to the Owner provided

that: .1 assignment is effective only after termination of the Contract by the Owner for cause pursuant to

Section 14.2 and only for those subcontract agreements which the Owner accepts by notifying the Subcontractor and Contractor in writing; and

.2 assignment is subject to the prior rights of the surety, if any, obligated under bond relating to the Contract.

5.4.2 Upon such assignment, if the Work has been suspended for more than 30 days, the Subcontractor's

compensation shall be equitably adjusted for increases in cost resulting from the suspension. ARTICLE 7 - CHANGES IN THE WORK 7.1 GENERAL 7.1.1 Changes in the Work may be accomplished after execution of the Contract, and without invalidating the

Contract, by Change Order, Construction Change Directive or order for a minor change in the Work, subject to the limitations stated in this Article 7 and elsewhere in the Contract Documents.

7.1.2 A Change Order shall be based upon agreement among the Owner and Contractor ; a Construction

Change Directive may or may not be agreed to by the Contractor; an order for a minor change in the Work may be issued by the Engineer with the consent of the Owner.

7.1.3 Changes in the Work shall be performed under applicable provisions of the Contract Documents, and the

Contractor shall proceed promptly, unless otherwise provided in the Change Order, Construction Change Directive or order for a minor change in the Work.

7.2 CHANGE ORDERS 7.2.1 A Change Order is a written instrument prepared by the Engineer and signed by the Owner and Contractor,

stating their agreement upon all of the following: .1 change in the Work; .2 the amount of the adjustment, if any, in the Contract Sum; and .3 the extent of the adjustment, if any, in the Contract Time.

7.2.2 Methods used in determining adjustments to the Contract Sum may include those listed in Section 7.3.3.

Page 35: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 19

7.3 CONSTRUCTION CHANGE DIRECTIVES 7.3.1 A Construction Change Directive is a written order prepared by the Engineer and signed by the Owner,

directing a change in the Work prior to agreement on adjustment, if any, in the Contract Sum or Contract Time, or both. The Owner may by Construction Change Directive, without invalidating the Contract, order changes in the Work within the general scope of the Contract consisting of additions, deletions or other revisions, the Contract Sum and Contract Time being adjusted accordingly.

7.3.2 A Construction Change Directive shall be used in the absence of total agreement on the terms of a Change

Order. 7.3.3 If the Construction Change Directive provides for an adjustment to the Contract Sum, the adjustment shall

be based on one of the following methods: .1 mutual acceptance of a lump sum properly itemized and supported by sufficient substantiating data to

permit evaluation; .2 unit prices stated in the Contract Documents or subsequently agreed upon; .3 cost to be determined in a manner agreed upon by the parties and a mutually acceptable fixed or

percentage fee; or .4 as provided in Section 7.3.6.

7.3.4 Upon receipt of a Construction Change Directive, the Contractor shall promptly proceed with the change in

the Work involved and advise the Engineer and Owner of the Contractor's agreement or disagreement with the method, if any, provided in the Construction Change Directive for determining the proposed adjustment in the Contract Sum or Contract Time.

7.3.5 A Construction Change Directive signed by the Contractor indicates the agreement of the Contractor

therewith, including adjustment in Contract Sum and Contract Time or the method for determining them. Such agreement shall be effective immediately and shall be recorded as a Change Order.

7.3.6 If the Contractor does not respond promptly or disagrees with the method for adjustment in the Contract

Sum, the method and the adjustment shall be determined by the Owner on the basis of reasonable expenditures and savings of those performing the Work attributable to the change, including, in case of an increase in the Contract Sum, an allowance for overhead and profit in accordance with the schedule of construction modification procedures identified in General Requirements. In such case, and also under Section 7.3.3.3, the Contractor shall keep and present, in such form as the Owner may prescribe, an itemized accounting together with appropriate supporting data. Unless otherwise provided in the Contract Documents, costs for the purposes of this Section 7.3.6 shall be limited to the following: .1 costs of labor, including social security, old age and unemployment insurance, fringe benefits required

by agreement or custom, and workers' compensation insurance; .2 costs of materials, supplies and equipment, including cost of transportation, whether incorporated or

consumed; .3 rental costs of machinery and equipment, exclusive of hand tools, whether rented from the Contractor

or others; .4 costs of premiums for all bonds and insurance, permit fees, and sales, use or similar taxes related to

the Work; and .5 additional costs of supervision and field office personnel directly attributable to the change.

7.3.7 The amount of credit to be allowed by the Contractor to the Owner for a deletion or change which results in

a net decrease in the Contract Sum shall be actual net cost as confirmed by the Owner. When both additions and credits covering related Work or substitutions are involved in a change, the allowance for overhead and profit shall be figured on the basis of net increase, if any, with respect to that change.

7.3.8 Pending final determination of the total cost of a Construction Change Directive to the Owner, amounts not

in dispute for such changes in the Work shall be included in Applications for Payment accompanied by a

Page 36: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 20

Change Order indicating the parties' agreement with part or all of such costs. For any portion of such cost that remains in dispute, the Owner will make an interim determination for purposes of monthly progress payment for those costs. That determination of cost shall adjust the Contract Sum on the same basis as a Change Order, subject to the right of either party to disagree and assert a claim in accordance with Article 4.

7.3.9 When the Owner and Contractor agree concerning the adjustments in the Contract Sum and Contract

Time, or otherwise reach agreement upon the adjustments, such agreement shall be effective immediately and shall be recorded by preparation and execution of an appropriate Change Order.

7.4 MINOR CHANGES IN THE WORK 7.4.1 The Engineer with the consent of the Owner and the Owner will have authority to order minor changes in

the Work not involving adjustment in the Contract Sum or extension of the Contract Time and not inconsistent with the intent of the Contract Documents. Such changes shall be effected by written order and shall be binding on the Owner and Contractor. The Contractor shall carry out such written orders promptly.

ARTICLE 8 - TIME 8.1 DEFINITIONS 8.1.1 Unless otherwise provided, Contract Time is the period of time, including authorized adjustments, allotted

in the Contract Documents for Substantial Completion of the Work. 8.1.2 The date of commencement of the Work is the date established in the Agreement. 8.1.2.1 Work or storage of materials or equipment on site shall not commence until the later of written notice to

proceed is issued, or upon execution of Contract. In no event shall construction commence until the Contract is executed. Following such execution it is essential that performance under the contract begin within ten days of Owner's Notice to Proceed.

8.1.3 The date of Substantial Completion is the date certified by the Engineer in accordance with Section 9.8. 8.1.4 The term "day" as used in the Contract Documents shall mean calendar day unless otherwise specifically

defined. 8.2 PROGRESS AND COMPLETION 8.2.1 Time limits stated in the Contract Documents are of the essence of the Contract. By executing the

Agreement the Contractor confirms that the Contract Time is a reasonable period for performing the Work. 8.2.2 The Contractor shall not knowingly, except by agreement or instruction of the Owner in writing, prematurely

commence operations on the site or elsewhere prior to the effective date of insurance required by Article 11 to be furnished by the Contractor and Owner. The date of commencement of the Work shall not be changed by the effective date of such insurance. Unless the date of commencement is established by the Contract Documents or a notice to proceed given by the Owner, the Contractor shall notify the Owner in writing not less than five days or other agreed period before commencing the Work to permit the timely filing of mortgages, mechanic's liens and other security interests.

8.2.3 The Contractor shall proceed expeditiously with adequate forces and shall achieve Substantial Completion

within the Contract Time.

Page 37: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 21

8.2.4 In the event Contractor shall fail to complete the Work by the completion date provided in the Contract, then Contractor shall be considered to be in breach of the Contract and will be liable to Owner for any and all damages suffered by Owner as a result of such breach of Contract.

8.3 DELAYS AND EXTENSIONS OF TIME 8.3.1 In the event that, at any time, Contractor’s commencement or performance of the Work is delayed or

interfered with by acts or neglect of the Owner or Engineer, or of any employee of either, or of a separate contractor employed by the Owner, or by changes ordered in the Work, or by labor disputes, fire, unusual delay in deliveries, unavoidable casualties or other causes beyond the Contractor’s control, or by other causes which the Owner determines may justify delay, then the Contract Time shall be extended by Change Order for such reasonable time as the Owner may determine, but Contractor shall not be entitled to any increase in the Contract Price or to damages or additional compensation as a consequence of such delay or interference. No allowance for an extension of time for any cause whatsoever shall be claimed by, or granted to, Contractor unless Contractor shall have made written request within the time periods and in the manner set forth in the Contract Documents.

8.3.2 Claims relating to time shall be made in accordance with applicable provisions of Section 4.3. 8.3.3 This Section 8.3 does not preclude recovery of damages for delay by Owner under any provision of the

Contract Documents. ARTICLE 9 - PAYMENTS AND COMPLETION 9.1 CONTRACT SUM 9.1.1 The Contract Sum is stated in the Agreement and, including authorized adjustments, is the total amount

payable by the Owner to the Contractor for performance of the Work under the Contract Documents. 9.2 SCHEDULE OF VALUES 9.2.1 Before the first Application for Payment, the Contractor shall submit to the Owner a schedule of values

allocated to various portions of the Work, prepared in such form and supported by such data to substantiate its accuracy as the Owner may require. This schedule, unless objected to by the Owner, shall be used as a basis for reviewing the Contractor's Applications for Payment.

9.2.2 Schedule of Values: See General Requirements. 9.3 APPLICATIONS FOR PAYMENT 9.3.1 Applications for Payment: See General Requirements. 9.3.2 Unless otherwise provided in the Contract Documents, payments shall be made on account of materials

and equipment delivered and suitably stored at the site for subsequent incorporation in the Work. If approved in advance by the Owner, payment may similarly be made for materials and equipment suitably stored off the site at a location agreed upon in writing. Payment for materials and equipment stored on or off the site shall be conditioned upon compliance by the Contractor with procedures satisfactory to the Owner to establish the Owner's title to such materials and equipment or otherwise protect the Owner's interest, and shall include the costs of applicable insurance, storage and transportation to the site for such materials and equipment stored off the site.

9.3.2.1 The Owner may approve progress in an amount equal to 95% of all work and materials under the following

conditions:

Page 38: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 22

The Contractor shall obtain the approval of the Owner’s Representative before making any arrangements to obtain an Application for Payment for materials stored off the site. Materials must be suitable for storage and must be properly packaged as necessary.

The Contractor shall furnish and maintain a suitable storage site and proper storage conditions, which must be approved in advance by the Owner’s Representative. Storage Conditions: Material covered by the Request for Application for Partial Payment must be stored above grade, and must be properly protected at all times against weather, heat, cold, moisture, vandalism or theft and other hazards as the material may require. All protection must be provided by the Contractor, at his own expense, and must be maintained throughout the storage period. It must be stored so that it can be readily inspected, measured, and counted, at all times, by the Owners' representatives.

9.3.3 The Contractor warrants that title to all Work covered by an Application for Payment will pass to the Owner no later than the time of payment. The Contractor further warrants that upon submittal of an Application for Payment all Work for which payments have been previously issued and payments received from the Owner shall, to the best of the Contractor's knowledge, information and belief, be free and clear of liens, claims, security interests or encumbrances in favor of the Contractor, Subcontractors, material suppliers, or other persons or entities making a claim by reason of having provided labor, materials and equipment relating to the Work.

9.4 RESERVED 9.5 DECISIONS TO WITHHOLD PAYMENT 9.5.1 The Owner may withhold payment in whole or in part, if in its sole discretion exercised in good faith based on

observations at the site and on the data comprising the Application for Payment, the Work has not progressed to the point indicated, or the Work is not in conformance with the Contract Documents (subject to an evaluation of the Work for conformance with the Contract Documents upon Substantial Completion, to the results of any subsequent tests required or performed under the Contract Documents, to minor deviations from the Contract Documents correctable prior to completion), or the Contractor is otherwise not entitled to payment in the amount specified. If the Owner decides to withhold payment on all or part of the amount of the Application, it will notify the Contractor within seven days of receipt of the Application. If the Owner and Contractor cannot agree on a revised amount, the Owner will pay the amount not in dispute, in accord with the Contract Documents. The Owner may also withhold payment because of subsequently discovered evidence or subsequent observations, to such extent as may be necessary, in the opinion of the Owner, to protect the Owner from loss because of: .1 defective Work not remedied; .2 third party claims filed or reasonable evidence indicating probable filing of such claims unless security

acceptable to the Owner is provided by the Contractor; .3 failure of the Contractor to make payments properly to Subcontractors or for labor, materials or

equipment; .4 reasonable evidence that the Work cannot be completed for the unpaid balance of the Contract Sum; .5 damage to the Owner or another contractor; .6 reasonable evidence that the Work will not be completed within the Contract Time, and that the unpaid

balance would not be adequate to cover actual or liquidated damages for the anticipated delay; or .7 persistent failure to carry out the Work in accordance with the Contract Documents.

9.5.2 When the above reasons for withholding payment are removed, payment will be made within a reasonable

time for amounts previously withheld. 9.6 PROGRESS PAYMENTS

Page 39: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 23

9.6.1 After the Contractor submits an Application for Payment, the Owner shall make payment in the manner and within the time provided in the Contract Documents.

9.6.2 The Contractor shall promptly pay each Subcontractor, upon receipt of payment from the Owner, out of the

amount paid to the Contractor on account of such Subcontractor's portion of the Work, the amount to which said Subcontractor is entitled, pursuant to the terms of its Subcontract, and, unless conflicting with Subcontract terms, reflecting percentages actually retained from payments to the Contractor on account of such Subcontractor's portion of the Work. The Contractor shall, by appropriate agreement with each Subcontractor, require each Subcontractor to make payments to Sub-subcontractors in a similar manner.

9.6.3 The Owner will, on request, furnish to a Subcontractor, if practicable, information regarding percentages of

completion or amounts applied for by the Contractor and action taken thereon by the Owner on account of portions of the Work done by such Subcontractor.

9.6.4 Neither the Owner nor Engineer shall have an obligation to pay or to see to the payment of money to a

Subcontractor except as may otherwise be required by law. 9.6.5 Payment to material suppliers shall be treated in a manner similar to that provided in Sections 9.6.2, 9.6.3

and 9.6.4. 9.6.6 An Application for Payment, a progress payment, or partial or entire use or occupancy of the Project by the

Owner shall not constitute acceptance of Work not in accordance with the Contract Documents. 9.6.7 Unless the Contractor provides the Owner with a payment bond in the full penal sum of the Contract Sum,

payments received by the Contractor for Work properly performed by Subcontractors and suppliers shall be held by the Contractor for those Subcontractors or suppliers who performed Work or furnished materials, or both, under contract with the Contractor for which payment was made by the Owner. Nothing contained herein shall require money to be placed in a separate account and not commingled with money of the Contractor, shall create any fiduciary liability or tort liability on the part of the Contractor for breach of trust or shall entitle any person or entity to an award of punitive damages against the Contractor for breach of the requirements of this provision.

9.7 FAILURE OF PAYMENT 9.7.1 If the Owner does not pay the sum requested in any Application for Payment within 45 days after receipt of

such Application, less any amount withheld in accordance with subparagraph 9.5.1, then the Contractor may, upon seven days written notice to the Owner, stop the Work until payment of the amount owing has been received. The Contract Sum shall be increased by the amount of the Contractor's reasonable cost of shut-down, delay and start-up, which shall be effected by appropriate Change Order in accordance with Paragraph 4.3.5 and 4.3.6, unless modified by the Contract as provided in Article 7.

9.8 SUBSTANTIAL COMPLETION 9.8.1 Substantial Completion is the stage in the progress of the Work when the Work or designated portion

thereof is sufficiently complete in accordance with the Contract Documents so that the Owner can occupy or utilize the Work for its intended use and a temporary occupancy permit has been issued by the appropriate public authorities in accordance with all applicable laws and regulations. Upon prior notice to the Contractor, the Owner may occupy the Work, or portions thereof, for the purpose of performing its preparatory tasks to make the Work suitable for its intended use. Such preparatory tasks to be performed by Owner include, but are not limited to, installation of temperature controls, installation of moveable equipment, and performance of custodial work.

9.8.2 When the Contractor considers that the Work, or a portion thereof which the Owner agrees to accept

separately, is substantially complete, the Contractor shall prepare and submit to the Engineer and Owner a

Page 40: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 24

comprehensive list of items to be completed or corrected prior to final payment. Failure to include an item on such list does not alter the responsibility of the Contractor to complete all Work in accordance with the Contract Documents.

9.8.3 Upon receipt of the Contractor's list, the Engineer and Owner will make an inspection to determine whether

the Work or designated portion thereof is substantially complete. If the inspection discloses any item, whether or not included on the Contractor's list, which is not sufficiently complete in accordance with the Contract Documents so that the Owner can occupy or utilize the Work or designated portion thereof for its intended use, the Contractor shall, before issuance of the Certificate of Substantial Completion, complete or correct such item upon notification by the Owner. In such case, the Contractor shall then submit a request for another inspection by the Engineer and Owner to determine Substantial Completion.

9.8.4 When the Work or designated portion thereof is substantially complete, the Engineer will prepare a

Certificate of Substantial Completion which shall establish the date of Substantial Completion, shall establish responsibilities of the Owner and Contractor for security, maintenance, heat, utilities, damage to the Work and insurance, and shall fix the time within which the Contractor shall finish all items on the list accompanying the Certificate. Warranties required by the Contract Documents shall commence on the date of Substantial Completion of the Work or designated portion thereof unless otherwise provided in the Certificate of Substantial Completion.

9.8.5 The Certificate of Substantial Completion shall be submitted to the Owner and Contractor for their written

acceptance of responsibilities assigned to them in such Certificate. Upon such acceptance and consent of surety, if any, the Owner shall make payment of retainage applying to such Work or designated portion thereof. Such payment shall be adjusted for Work that is incomplete or not in accordance with the requirements of the Contract Documents.

9.9 PARTIAL OCCUPANCY OR USE 9.9.1 The Owner may occupy or use any completed or partially completed portion of the Work at any stage when

such portion is designated by separate agreement with the Contractor, provided such occupancy or use is consented to by the insurer as required under Section 11.4.1.5 and authorized by public authorities having jurisdiction over the Work. Such partial occupancy or use may commence whether or not the portion is substantially complete, provided the Owner and Contractor have accepted in writing the responsibilities assigned to each of them for payments, retainage, if any, security, maintenance, heat, utilities, damage to the Work and insurance, and have agreed in writing concerning the period for correction of the Work and commencement of warranties required by the Contract Documents. When the Contractor considers a portion substantially complete, the Contractor shall prepare and submit a list to the Engineer and Owner as provided under Section 9.8.2. Consent of the Contractor to partial occupancy or use shall not be unreasonably withheld. The stage of the progress of the Work shall be determined by written agreement between the Owner and Contractor. Upon prior notice to Contractor, Owner may occupy portions of the Work for the purpose of performing its preparatory tasks to make the Work suitable for its intended use. Such preparatory tasks to be performed by Owner include, but are not limited to, installation of temperature controls, installation of moveable equipment, and performance of custodial work.

9.9.2 Immediately prior to such partial occupancy or use, the Owner, Contractor and Engineer shall jointly

inspect the area to be occupied or portion of the Work to be used in order to determine and record the condition of the Work.

9.9.3 Unless otherwise agreed upon, partial occupancy or use of a portion or portions of the Work shall not

constitute acceptance of Work not complying with the requirements of the Contract Documents. 9.10 FINAL COMPLETION AND FINAL PAYMENT 9.10.1 Project Closeout: See General Requirements for Project closeout requirements.

Page 41: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 25

9.10.1.1 Upon completion of the items contained on the Contractor’s list described in § 6.9.8 and of any items

identified by Owner or Engineer as described in § 9.8.3, Contractor shall request that a final inspection be made by Owner and Engineer to determine final completion.

9.10.1.2 Upon receipt of written notice that the Work is ready for final inspection and acceptance and upon

Owner’s receipt of a final Application for Payment, the Owner and Engineer will promptly make such inspection and, when the Owner and Engineer find the Work acceptable under the Contract Documents and the Contract fully performed, the Engineer will promptly issue a final Certificate of Completion stating that to the best of the Engineer’s knowledge, information and belief, and on the basis of the Engineer’s on-site visits and inspections, the Work has been completed in accordance with terms and conditions of the Contract Documents. The Engineer’s final Certificate of Completion will constitute a further representation that conditions listed in Subparagraph 9.10.2 as precedent to the Contractor’s being entitled to final payment have been fulfilled.

9.10.2 Neither final payment nor any remaining retained percentage shall become due until the Contractor

submits to the Owner a final Application for Payment and either provides to Owner or satisfies all the following requirements: (1) an affidavit or other evidence satisfactory to Engineer and Owner that payrolls, bills for materials and equipment, and other indebtedness connected with the Work (less amounts withheld by Owner) have been paid or otherwise satisfied, (2) a certificate evidencing that insurance required by the Contract Documents to remain in force after final payment is currently in effect and will not be canceled or allowed to expire until at least 30 days' prior written notice has been given to the Owner, (3) a written statement that the Contractor knows of no substantial reason that the insurance will not be renewable to cover the period required by the Contract Documents, (4) consent of surety, if any, to final payment (5), if required by the Owner, other data establishing payment or satisfaction of obligations, such as receipts, releases and waivers of liens, claims, security interests or encumbrances arising out of the Contract, to the extent and in such form as may be designated by the Owner, and (6) issuance by the Engineer of a final Certificate of Completion. If a Subcontractor refuses to furnish a release or waiver required by the Owner, the Contractor may furnish a bond satisfactory to the Owner to indemnify the Owner against such lien. If such lien remains unsatisfied after payments are made, the Contractor shall refund to the Owner all money that the Owner may be compelled to pay in discharging such lien, including all costs and reasonable attorneys' fees.

9.10.2.1 Before final payment can be made, Department of Labor Division of Employment Form No. 16.

Certificate of Contribution Status must be received from the State of Nebraska Department of Labor certifying that Contractor and each of its subcontractors have paid all contributions and interest due to and including the calendar quarter immediately preceding date of substantial completion.

9.10.2.2 Contributions Under Nebraska Employment Security Law. The Contractor and all Subcontractors

engaged to perform any part of the Work shall make payment to the Unemployment Compensation Fund of the State of Nebraska of all contributions and interest due under the provisions of the Employment Security Law, Neb. Rev. Stat. 48-601 et seq. (Reissue 1988), as amended, on wages paid to individuals employed in the performance of the Contract; and before final payment shall be made of the final 3 percent of this Contract, the Contractor shall secure and file with the Owner, and cause any Subcontractor to secure and file with the Owner, written clearance from the Commissioner of the Department of Labor of the State of Nebraska, certifying that all payments then due of contributions or interest which may have arisen under this Contract have been made by the Contractor or any Subcontractor to the Unemployment Compensation Fund.

9.10.3 If, after Substantial Completion of the Work, final completion thereof is materially delayed through no fault

of the Contractor or by issuance of Change Orders affecting final completion, the Owner shall, upon application by the Contractor, and without terminating the Contract, make payment of the balance due for that portion of the Work fully completed and accepted. If the remaining balance for Work not fully completed or corrected is less than retainage stipulated in the Contract Documents, and if bonds have been furnished, the written consent of surety to payment of the balance due for that portion of the Work fully completed and accepted shall be submitted by the Contractor to the Owner. Such payment shall be

Page 42: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 26

made under terms and conditions governing final payment, except that it shall not constitute a waiver of claims.

9.10.4 The making of final payment shall constitute a waiver of claims by Owner except those arising from:

.1 liens, Claims, security interests or encumbrances arising out of the Contract and unsettled;

.2 failure of the Work to comply with the requirements of the Contract Documents or with applicable codes and standards in the industry;

.3 terms of special warranties required by the Contract Documents;

.4 all warranties provided for in the Contract Documents; and

.5 claims arising out of latent defects in the Work. 9.10.5 Acceptance of final payment by the Contractor, a Subcontractor or material supplier shall constitute a

waiver of claims by that payee except those previously made in writing and identified by that payee as unsettled at the time of final Application for Payment.

9.11 PAYMENT CONTINGENT UPON AVAILABILITY OF APPROPRIATED FUNDS OR FUNDS

APPROVED BY BOARD OF REGENTS. 9.11.1 Any other provisions of the Contract Documents to the contrary notwithstanding, it is expressly understood

and agreed that the legal obligation of the Owner to pay the Contract Sum of any part thereof shall be contingent upon the availability of funds appropriated by the Legislature of the State of Nebraska as provided by law, or the availability or other funds of the Owner specifically approved by formal action of the school board for the purpose of payment of the Contract Sum or any part thereof. The appropriation, availability of funds, and the specific approval by formal action of the Board of Regents shall be conditions precedent to Owner’s obligation to make any payment to Contractor for the Work.

ARTICLE 10 - PROTECTION OF PERSONS AND PROPERTY 10.1 SAFETY PRECAUTIONS AND PROGRAMS 10.1.1 The Contractor shall be responsible for initiating, maintaining and supervising all safety precautions and

programs in connection with the performance of the Contract. This requirement applies continuously 24 hours per day during construction of the Project.

10.2 SAFETY OF PERSONS AND PROPERTY 10.2.1 The Contractor shall take reasonable precautions for safety of, and shall provide reasonable protection to

prevent damage, injury or loss to: .1 employees on the Work and other persons who may be affected thereby; .2 the Work and materials and equipment to be incorporated therein, whether in storage on or off the

site, under care, custody or control of the Contractor or the Contractor's Subcontractors or Sub-subcontractors; and

.3 other property at the site or adjacent thereto, such as trees, shrubs, lawns, walks, pavements, roadways, structures and utilities not designated for removal, relocation or replacement in the course of construction.

10.2.2 The Contractor shall give notices and comply with applicable laws, ordinances, rules, regulations and

lawful orders of public authorities bearing on safety of persons or property or their protection from damage, injury or loss. More specifically, the Contractor shall give notice in writing at least 48 hours before breaking ground, to all persons, Public Utility Companies, Owners of the property having structures or improvements in proximity to site of the Work, Superintendents, inspectors, or those otherwise in charge of property, streets, water pipes, gas pipes, sewer pipes, telephone cables, electric cables, railroads or otherwise, who may be affected by Contractor's operation, in order that they may remove any obstruction for which they are responsible and have a representative on site to see that their property is properly protected. Such notice does not relieve the Contractor of responsibility for any damages, claims, and defense of all actions against

Page 43: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 27

the Owner and the Engineer resulting from performance of such work in connection with or arising out of the Contract.

10.2.3 The Contractor shall erect and maintain, as required by existing conditions and performance of the

Contract, reasonable safeguards for safety and protection, including posting danger signs and other warnings against hazards, promulgating safety regulations and notifying owners and users of adjacent sites and utilities.

10.2.4 The Contractor shall exercise the utmost care so as not to endanger life or property in the execution of the

Work. Contractor is fully responsible for any and all damages, claims and for the defense of all actions against Owner and Engineer resulting from the failure to exercise such care. Explosives shall not be employed in the prosecution of the Work.

10.2.5 The Contractor shall promptly remedy damage and loss (other than damage or loss insured under property

insurance required by the Contract Documents) to property referred to in Sections 10.2.1.2 and 10.2.1.3 caused in whole or in part by the Contractor, a Subcontractor, a Sub-subcontractor, or anyone directly or indirectly employed by any of them, or by anyone for whose acts they may be liable and for which the Contractor is responsible under Sections 10.2.1.2 and 10.2.1.3, except damage or loss attributable to acts or omissions of the Owner or Engineer or anyone directly or indirectly employed by either of them, or by anyone for whose acts either of them may be liable, and not attributable to the fault or negligence of the Contractor. The foregoing obligations of the Contractor are in addition to the Contractor's obligations under Section 3.18.

10.2.6 The Contractor shall designate a responsible member of the Contractor's organization at the site whose

duty shall be the prevention of accidents. This person shall be the Contractor's superintendent unless otherwise designated by the Contractor in writing to the Owner and Engineer.

10.2.7 The Contractor shall not load or permit any part of the construction or site to be loaded so as to endanger

its safety. 10.2.8 Duty of Engineer to conduct construction review of Contractor's performance does not include review

of adequacy of Contractor's safety measures in, on, or near construction site. 10.2.9 Utilities or other services, indicated to be abandoned, shall be maintained in service as required until

new facilities are provided, tested and ready for use. Contractor shall schedule work so that it does not necessitate long periods of shut-down of existing facilities and these shut-downs shall be coordinated with and at the convenience of Owner. See General Requirements for additional requirements.

10.2.10 All improvements on or about site and adjacent property which are not to be altered, removed or

otherwise changed shall be returned to conditions which existed prior to initiation of the Work. 10.3 HAZARDOUS MATERIALS 10.3.1 If reasonable precautions will be inadequate to prevent foreseeable bodily injury or death to persons

resulting from a material or substance, including but not limited to asbestos or polychlorinated biphenyl (PCB), encountered on the site by the Contractor, the Contractor shall, upon recognizing the condition, immediately stop Work in the affected area and report the condition to the Owner and Engineer in writing.

10.3.2 The Owner shall obtain the services of a licensed laboratory to verify the presence or absence of the

material or substance reported by the Contractor and, in the event such material or substance is found to be present, to verify that it has been rendered harmless. Unless otherwise required by the Contract Documents, the Owner shall furnish in writing to the Contractor and Engineer the names and qualifications of persons or entities who are to perform tests verifying the presence or absence of such material or

Page 44: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 28

substance or who are to perform the task of removal or safe containment of such material or substance. When the material or substance has been rendered harmless, Work in the affected area shall resume upon written agreement of the Owner and Contractor. The Contract Time shall be extended appropriately and the Contract Sum shall be increased in the amount of the Contractor's reasonable additional costs of shut-down, delay and start-up, which adjustments shall be accomplished as provided in Article 7.

10.3.3 To the fullest extent permitted by law, the Owner shall indemnify and hold harmless the Contractor, Engineer,

Engineer's consultants and agents and employees or any of them from and against claims, damages, losses and expenses arising out of or resulting from performance of the Work in the affected area if in fact the material is asbestos or polychlorinated biphenyl (PCB) and has not been rendered harmless, provided that such claim, damage, loss or expense is attributable to bodily injury, sickness, disease or death, or to injury to or destruction of tangible property (other than the Work itself) including loss of use resulting therefrom, but only to the extent caused by negligent acts or omissions of the Owner, anyone directly or indirectly employed by the Owner or anyone for whose acts the Owner may be liable except if such claim, damage, loss or expense is caused in part by a party indemnified hereunder. Such obligation shall not be construed to negate, abridge, or reduce other rights or obligations of indemnity which would otherwise exist as to a party or person described in this Subparagraph 10.3.3.

10.3.4 Fines, penalties and any other action ordered by Environmental Protection Agency or State

Department of Environment arising from performance of this Contract, are responsibility of Contractor and as such not recoverable from Owner in any fashion.

10.3.5 Hazardous waste, if any, that is generated from the work shall be properly disposed of at the end of the

work by the Contractor pursuant to applicable hazardous waste laws and regulations. The Contractor shall coordinate the disposal with the Owner’s Representative. The waste left on-site at the end of the work shall be properly disposed of by the University with all costs associated for the disposal deducted from outstanding play invoices and/or billed to the Contractor. The term ‘hazardous waste’ means hazardous waster as defined pursuant to the federal Resource Conservation and Recovery Act, as amended. The Contractor must furnish receipts (shipping manifests) from recognized official disposal sites for the disposal of hazardous waster - including, but not limited to asbestos, PCB ballasts, etc.

10.4 The Owner shall not be responsible under Section 10.3 for materials and substances brought to the site by

the Contractor unless such materials or substances were required by the Contract Documents. 10.5 If, without negligence on the part of the Contractor, the Contractor is held liable for the cost of remediation

of a hazardous material or substance solely by reason of performing Work as required by the Contract Documents, the Owner shall indemnify the Contractor for all cost and expense thereby incurred.

10.6 EMERGENCIES 10.6.1 In an emergency affecting safety of persons or property, the Contractor shall act, at the Contractor's

discretion, to prevent threatened damage, injury or loss. Additional compensation or extension of time claimed by the Contractor on account of an emergency shall be determined as provided in Section 4.3 and Article 7.

10.7 WATER PRECAUTIONS 10.7.1 Contractor shall keep all parts of site, including excavations, free from any accumulation of water,

no matter the source or cause. 10.7.2 The Contractor shall dispose of water and waste water in such manner as will not endanger public health and

safety or cause damage or expense to property. The Contractor shall comply with all laws, or administrative regulations, rules or local ordinances applicable to the disposal of water and waste water. If sewers and streets are allowed to be used for drainage or disposal of water during construction, they shall be maintained and left satisfactorily clean upon completion of Work.

Page 45: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 29

10.8 SIGNS 10.8.1 The Contractor shall not erect signs, billboards, or advertisements on or about premises, except as required

by Contract. The display of signs other than those required by law shall be limited to those required by Contract Documents and for safety.

10.8.2 Contractor shall furnish and maintain all signs as required for execution of the Work and as required

by law. 10.9 WEAPONS POLICY 10.9.1 Possession of dangerous weapons (concealed or unconcealed) on school property, on the work site, or in

personal vehicles when on school property shall be a violation of school policy. (A dangerous weapon shall include guns, knives, explosives, or any other device as determined by the district, which in the manner used or intended is capable of producing death or bodily injury. Violations of this policy shall make the offender subject to appropriate disciplinary action.

ARTICLE 11 - INSURANCE AND BONDS 11.1 CONTRACTOR'S LIABILITY INSURANCE 11.1.1 The Contractor shall purchase from and maintain in a company or companies lawfully authorized to do

business in the jurisdiction in which the Project is located such insurance as will protect the Contractor from claims set forth below which may arise out of or result from the Contractor's operations under the Contract and for which the Contractor may be legally liable, whether such operations be by the Contractor or by a Subcontractor or by anyone directly or indirectly employed by any of them, or by anyone for whose acts any of them may be liable: .1 claims under workers' compensation, disability benefit and other similar employee benefit acts which

are applicable to the Work to be performed; .2 claims for damages because of bodily injury, occupational sickness or disease, or death of the

Contractor's employees; .3 claims for damages because of bodily injury, sickness or disease, or death of any person other than

the Contractor's employees; .4 claims for damages insured by usual personal injury liability coverage; .5 claims for damages, other than to the Work itself, because of injury to or destruction of tangible

property, including loss of use resulting therefrom; .6 claims for damages because of bodily injury, death of a person or property damage arising out of

ownership, maintenance or use of a motor vehicle; .7 claims for bodily injury or property damage arising out of completed operations; .8 claims involving contractual liability insurance applicable to the Contractor's obligations under Section

3.18; and .9 Claims under employers' liability by members of the employees' family for loss of consortium or third

party action against the Contractor. 11.1.2 The insurance required by Section 11.1.1 shall be written for not less than limits of liability specified in the

Contract Documents or required by law, whichever coverage is greater. See § 11.1.5, below, for additional requirements. Coverages, whether written on an occurrence or claims-made basis, shall be maintained without interruption from date of commencement of the Work until date of final payment and termination of any coverage required to be maintained after final payment.

11.1.3 Certificates of insurance acceptable to the Owner shall be filed with the Owner prior to commencement of

the Work. These certificates and the insurance policies required by this Section 11.1 shall contain a provision that coverages afforded under the policies will not be canceled or allowed to expire until at least 30 days' prior written notice has been given to the Owner. If any of the foregoing insurance coverages are

Page 46: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 30

required to remain in force after final payment and are reasonably available, an additional certificate evidencing continuation of such coverage shall be submitted with the final Application for Payment as required by Section 9.10.2. Information concerning reduction of coverage on account of revised limits or claims paid under the General Aggregate, or both, shall be furnished by the Contractor with reasonable promptness in accordance with the Contractor's information and belief.

11.1.5 Insurance required shall be written for not less than limits of liability that are specified on Owner's Insurance Form. Contractor shall complete this form prior to commencing any work on the Project, and it shall become part of the Contract Documents.

11.2 OWNER'S LIABILITY INSURANCE 11.2.1 The Owner shall be responsible for purchasing and maintaining the Owner's usual liability insurance. 11.3 PROJECT MANAGEMENT PROTECTIVE LIABILITY INSURANCE 11.3.1 Optionally, the Owner may require the Contractor to purchase and maintain Project Management

Protective Liability insurance from the Contractor's usual sources as primary coverage for the Owner's, Contractor's and Engineer's vicarious liability for construction operations under the Contract. Unless otherwise required by the Contract Documents, the Owner shall reimburse the Contractor by increasing the Contract Sum to pay the cost of purchasing and maintaining such optional insurance coverage, and the Contractor shall not be responsible for purchasing any other liability insurance on behalf of the Owner. The minimum limits of liability purchased with such coverage shall be equal to the aggregate of the limits required for Contractor's Liability Insurance under Sections 11.1.1.2 through 11.1.1.5.

11.3.2 To the extent damages are covered by Project Management Protective Liability insurance, the Owner,

Contractor and Engineer waive all rights against each other for damages, except such rights as they may have to the proceeds of such insurance. The policy shall provide for such waivers of subrogation by endorsement or otherwise.

11.3.3 The Owner shall not require the Contractor to include the Owner, Engineer or other persons or entities as

additional insureds on the Contractor's Liability Insurance coverage under Section 11.1. 11.4 PROPERTY INSURANCE 11.4.1 Unless otherwise provided, the Owner shall purchase and maintain, in a company or companies lawfully

authorized to do business in the jurisdiction in which the Project is located, property insurance written on a builder's risk "all-risk" or equivalent policy form in the amount of the initial Contract Sum, plus value of subsequent Contract modifications and cost of materials supplied or installed by others, comprising total value for the entire Project at the site on a replacement cost basis without optional deductibles. Such property insurance shall be maintained, unless otherwise provided in the Contract Documents or otherwise agreed in writing by all persons and entities who are beneficiaries of such insurance, until final payment has been made as provided in Section 9.10 or until no person or entity other than the Owner has an insurable interest in the property required by this Section 11.4 to be covered, whichever is later. This insurance shall include interests of the Owner, the Contractor, Subcontractors and Sub-subcontractors in the Project.

11.4.1.2 The Contractor shall provide and maintain “All peril” installation floater insurance e for the materials,

supplies, machinery, fixtures and equipment that will become a part of the installation, fabrication or erection project as shown and described in the Contract. Coverage under the Contractor’s installation floater shall pay for direct physical loss to property while:

In transit; At the site of installation, fabrication or erection, as shown and described in the Contract; and

Page 47: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 31

In storage awaiting installation, fabrication or erection.

The Contractor’s Installation Floater Limits of Insurance must be sufficient to cover the value of the installation up to a maximum limit of $200,000. The Owner will assume responsibility for any loss in excess of $200,000 subject to a maximum limit of $750,000 on property while in transit or in storage awaiting installation, fabrication or erection. The Contractor will be solely responsible for any deductible carried under their Installation Floater and any portion of a claim exceeding $950,000 on materials, supplies, machinery, fixtures and equipment which will become a part of the installation, fabrication or erection project as shown and described in the Contract Documents while in transit or in storage awaiting installation, fabrication or erection. Evidence of installation floater insurance shall be reflected or stated on the Certificate of Insurance in footnote 9 by the Contractor and be on file with the University prior to start of Work.

11.4.1.3 If the Owner does not intend to purchase such property insurance required by the Contract and with all of

the coverages in the amount described above, the Owner shall so inform the Contractor in writing prior to commencement of the Work. The Contractor may then affect insurance which will protect the interests of the Contractor, Subcontractors and Sub-subcontractors in the Work, and by appropriate Change Order the cost thereof shall be charged to the Owner. If the Contractor is damaged by the failure or neglect of the Owner to purchase or maintain insurance as described above, without so notifying the Contractor in writing, then the Owner shall bear all reasonable costs properly attributable thereto.

11.4.1.4 If the property insurance requires deductibles, the Owner shall pay costs not covered because of such

deductibles. 11.4.1.5 This property insurance shall cover portions of the Work stored off the site, and also portions of the Work

in transit. 11.4.1.6 Partial occupancy or use in accordance with Section 9.9 shall not commence until the insurance company

or companies providing property insurance have consented to such partial occupancy or use by endorsement or otherwise. The Owner and the Contractor shall take reasonable steps to obtain consent of the insurance company or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use that would cause cancellation, lapse or reduction of insurance.

11.4.1.7 Notice of and Proof of Loss: The contractor shall notify the Owner's Representative at the earliest possible

time but no later than 60 minutes after an occurrence. The contractor shall file Proof of Loss with the Owner's Representative within a reasonable length of time, but no more than 30 days after the final amount of loss is known by the contractor.

11.4.2 Boiler and Machinery Insurance. The Owner shall purchase and maintain boiler and machinery insurance

required by the Contract Documents or by law, which shall specifically cover such insured objects during installation and until final acceptance by the Owner; this insurance shall include interests of the Owner, Contractor, Subcontractors and Sub-subcontractors in the Work, and the Owner and Contractor shall be named insureds.

11.4.3 Loss of Use Insurance. The Owner, at the Owner's option, may purchase and maintain such insurance as

will insure the Owner against loss of use of the Owner's property due to fire or other hazards, however caused.

11.4.4 If the Contractor requests in writing that insurance for risks other than those described herein or other

special causes of loss be included in the property insurance policy, the Owner shall, if possible, include such insurance, and the cost thereof shall be charged to the Contractor by appropriate Change Order.

Page 48: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 32

11.4.5 If during the Project construction period the Owner insures properties, real or personal or both, at or adjacent to the site by property insurance under policies separate from those insuring the Project, or if after final payment property insurance is to be provided on the completed Project through a policy or policies other than those insuring the Project during the construction period, the Owner shall waive all rights in accordance with the terms of Section 11.4.7 for damages caused by fire or other causes of loss covered by this separate property insurance. All separate policies shall provide this waiver of subrogation by endorsement or otherwise.

11.4.6 Each policy shall contain all generally applicable conditions, definitions, exclusions and endorsements

related to this Project. Each policy shall contain a provision that the policy will not be canceled or allowed to expire, and that its limits will not be reduced, until at least 30 days' prior written notice has been given to the Contractor.

11.4.6.1 Copies of Owner's insurance are on file at the University's Office of Risk Management and may be

reviewed or obtained by Contractor if requested. 11.4.7 Waivers of Subrogation. The Owner and Contractor waive all rights against (1) each other and any of their

subcontractors, sub-subcontractors, agents and employees, each of the other, and (2) the Engineer, Engineer's consultants, separate contractors described in Article 6, if any, and any of their subcontractors, sub-subcontractors, agents and employees, for damages caused by fire or other causes of loss to the extent covered by property insurance obtained pursuant to this Section 11.4 or other property insurance applicable to the Work, except such rights as they have to proceeds of such insurance held by the Owner as fiduciary. The Owner or Contractor, as appropriate, shall require of the Engineer, Engineer's consultants, separate contractors described in Article 6, if any, and the subcontractors, sub-subcontractors, agents and employees of any of them, by appropriate agreements, written where legally required for validity, similar waivers each in favor of other parties enumerated herein. The policies shall provide such waivers of subrogation by endorsement or otherwise. A waiver of subrogation shall be effective as to a person or entity even though that person or entity would otherwise have a duty of indemnification, contractual or otherwise, did not pay the insurance premium directly or indirectly, and whether or not the person or entity had an insurable interest in the property damaged.

11.4.8 A loss insured under Owner's property insurance shall be adjusted by the Owner as fiduciary and made

payable to the Owner as fiduciary for the insureds, as their interests may appear, subject to requirements of any applicable mortgagee clause and of Section 11.4.10. The Contractor shall pay Subcontractors their just shares of insurance proceeds received by the Contractor, and by appropriate agreements, written where legally required for validity, shall require Subcontractors to make payments to their Sub-subcontractors in similar manner.

11.4.9 If required in writing by a party in interest, the Owner as fiduciary shall, upon occurrence of an insured loss,

give bond for proper performance of the Owner's duties. The cost of required bonds shall be charged against proceeds received as fiduciary. The Owner shall deposit in a separate account proceeds so received, which the Owner shall distribute in accordance with such agreement as the parties in interest may reach, or in accordance with an arbitration award in which case the procedure shall be as provided in Section 4.6. If after such loss no other special agreement is made and unless the Owner terminates the Contract for convenience, replacement of damaged property shall be performed by the Contractor after notification of a Change in the Work in accordance with Article 7.

11.4.10 The Owner as fiduciary shall have power to adjust and settle a loss with insurers unless one of the parties

in interest shall object in writing within five days after occurrence of loss to the Owner's exercise of this power.

11.5 PERFORMANCE BOND AND PAYMENT BOND 11.5.1 Contractor, before commencing the Work, shall furnish a bond, in a sum not less than Contract Sum, with a

corporate surety company acceptable to Owner and authorized to do business in the State of Nebraska,

Page 49: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 33

conditioned for faithful completion of the Work and performance of Contract, and insuring payment of all laborers and mechanics for labor and payment of all material and equipment used or rented in performing the Contract.

11.5.1.1 Should the principal amount of the Owner's Protective Bond be modified as a result of a Change Order, the

Contractor shall provide to the Owner written confirmation from the Surety indicating that bond has been modified and to what extent it has been modified.

11.5.2 Upon the request of any person or entity appearing to be a potential beneficiary of bonds covering payment

of obligations arising under the Contract, the Contractor shall promptly furnish a copy of the bonds or shall permit a copy to be made.

ARTICLE 12 - UNCOVERING AND CORRECTION OF WORK 12.1 UNCOVERING OF WORK 12.1.1 If a portion of the Work is covered contrary to the Engineer's request or to requirements specifically

expressed in the Contract Documents, it must, if required in writing by the Engineer, be uncovered for the Engineer's examination and be replaced at the Contractor's expense without change in the Contract Time.

12.1.2 If a portion of the Work has been covered which the Engineer has not specifically requested to examine

prior to its being covered, the Engineer may request to see such Work and it shall be uncovered by the Contractor. If such Work is in accordance with the Contract Documents, costs of uncovering and replacement shall, by appropriate Change Order, be at the Owner's expense. If such Work is not in accordance with the Contract Documents, correction shall be at the Contractor's expense unless the condition was caused by the Owner or a separate contractor in which event the Owner shall be responsible for payment of such costs.

12.2 CORRECTION OF WORK 12.2.1 BEFORE OR AFTER SUBSTANTIAL COMPLETION 12.2.1.1 The Contractor shall promptly correct rejected Work or Work failing to conform to the requirements of the

Contract Documents, whether discovered before or after Substantial Completion and whether or not fabricated, installed or completed. Costs of correcting such rejected Work, including additional testing and inspections and compensation for the Engineer's services and expenses made necessary thereby, shall be at the Contractor's expense.

12.2.2 AFTER SUBSTANTIAL COMPLETION 12.2.2.1 In addition to the Contractor's obligations under Section 3.5, if, within one year after the date of

Substantial Completion of the Work or designated portion thereof or after the date for commencement of warranties established under Section 9.9.1, or by terms of an applicable special warranty required by the Contract Documents, any of the Work is found to be not in accordance with the requirements of the Contract Documents, the Contractor shall correct it promptly after receipt of written notice from the Owner to do so unless the Owner has previously given the Contractor a written acceptance of such condition. The Owner shall give such notice promptly after discovery of the condition. During the one-year period for correction of Work, if the Owner fails to notify the Contractor and give the Contractor an opportunity to make the correction, the Owner waives the rights to require correction by the Contractor and to make a claim for breach of warranty. If the Contractor fails to correct nonconforming Work within a reasonable time during that period after receipt of notice from the Owner or Engineer, the Owner may correct it in accordance with Section 2.4.

Page 50: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 34

12.2.2.2 The one-year period for correction of Work shall be extended with respect to portions of Work first performed after Substantial Completion by the period of time between Substantial Completion and the actual performance of the Work.

12.2.2.3 The one-year period for correction of Work shall not be extended by corrective Work performed by the

Contractor pursuant to this Section 12.2. 12.2.3 The Contractor shall remove from the site portions of the Work which are not in accordance with the

requirements of the Contract Documents and are neither corrected by the Contractor nor accepted by the Owner.

12.2.4 The Contractor shall bear the cost of correcting destroyed or damaged construction, whether completed or

partially completed, of the Owner or separate contractors caused by the Contractor's correction or removal of Work which is not in accordance with the requirements of the Contract Documents.

12.2.5 Nothing contained in this Section 12.2 shall be construed to establish a period of limitation with respect to

other obligations which the Contractor might have under the Contract Documents. Establishment of the one-year period for correction of Work as described in Section 12.2.2 relates only to the specific obligation of the Contractor to correct the Work, and has no relationship to the time within which the obligation to comply with the Contract Documents may be sought to be enforced, nor to the time within which proceedings may be commenced to establish the Contractor's liability with respect to the Contractor's obligations other than specifically to correct the Work.

12.3 ACCEPTANCE OF NONCONFORMING WORK 12.3.1 If the Owner prefers to accept Work which is not in accordance with the requirements of the Contract

Documents, the Owner may do so instead of requiring its removal and correction, in which case the Contract Sum will be reduced as appropriate and equitable. Such adjustment shall be effected whether or not final payment has been made.

ARTICLE 13 - MISCELLANEOUS PROVISIONS 13.1 GOVERNING LAW 13.1.1 The Contract shall be governed by the law of the place where the Project is located. 13.2 SUCCESSORS AND ASSIGNS 13.2.1 The Owner and Contractor respectively bind themselves, their partners, successors, assigns and legal

representatives to the other party hereto and to partners, successors, assigns and legal representatives of such other party in respect to covenants, agreements and obligations contained in the Contract Documents. Except as provided in Section 13.2.2, neither party to the Contract shall assign the Contract as a whole without written consent of the other. If either party attempts to make such an assignment without such consent, that party shall nevertheless remain legally responsible for all obligations under the Contract. Should the Contractor assign its right to receive all or any part of any sum due or to become due under this Contract, the assignment must provide that the rights of assignees in and to any sum due or to become due under the Contract shall be subordinate to any liens and claims for services rendered; for payment of all laborers and mechanics for labor performed; for payment for all materials and equipment furnished and for payment for all materials and equipment used or rented in performance of the Work and for payment of any liens, claims, or amounts due to any governmental agency or affiliate.

13.2.2 The Owner may, without consent of the Contractor, assign the Contract to an institutional lender providing

construction financing for the Project. In such event, the lender shall assume the Owner's rights and

Page 51: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 35

obligations under the Contract Documents. The Contractor shall execute all consents reasonably required to facilitate such assignment.

13.3 WRITTEN NOTICE 13.3.1 Written notice shall be deemed to have been duly served if delivered in person to the individual or a

member of the firm or entity or to an officer of the corporation for which it was intended, or if delivered at or sent by registered or certified mail to the last business address known to the party giving notice.

13.4 RIGHTS AND REMEDIES 13.4.1 Duties and obligations imposed by the Contract Documents and rights and remedies available thereunder

shall be in addition to and not a limitation of duties, obligations, rights and remedies otherwise imposed or available by law.

13.4.2 No action or failure to act by the Owner, Engineer or Contractor shall constitute a waiver of a right or duty

afforded them under the Contract, nor shall such action or failure to act constitute approval of or acquiescence in a breach thereunder, except as may be specifically agreed in writing.

13.5 TESTS AND INSPECTIONS 13.5.1 Tests, inspections and approvals of portions of the Work required by the Contract Documents or by laws,

ordinances, rules, regulations or orders of public authorities having jurisdiction shall be made at an appropriate time. Unless otherwise provided, the Contractor shall make arrangements for such tests, inspections and approvals with an independent testing laboratory or entity acceptable to the Owner, or with the appropriate public authority, and shall bear all related costs of tests, inspections and approvals. The Contractor shall give the Engineer and Owner timely notice of when and where tests and inspections are to be made so that the Engineer may be present for such procedures.

13.5.2 If the Engineer, Owner or public authorities having jurisdiction determine that portions of the Work require

additional testing, inspection or approval not included under Section 13.5.1, the Engineer will, upon written authorization from the Owner, instruct the Contractor to make arrangements for such additional testing, inspection or approval by an entity acceptable to the Owner, and the Contractor shall give timely notice to the Engineer of when and where tests and inspections are to be made so that the Engineer may be present for such procedures. Such costs, except as provided in Section 13.5.3, shall be at the Owner's expense.

13.5.3 If such procedures for testing, inspection or approval under Sections 13.5.1 and 13.5.2 reveal failure of the

portions of the Work to comply with requirements established by the Contract Documents, all costs made necessary by such failure including those of repeated procedures and compensation for the Engineer's services and expenses shall be at the Contractor's expense.

13.5.4 Required certificates of testing, inspection or approval shall, unless otherwise required by the Contract

Documents, be secured by the Contractor and promptly delivered to the Engineer. 13.5.5 If the Engineer is to observe tests, inspections or approvals required by the Contract Documents, the

Engineer will do so promptly and, where practicable, at the normal place of testing. 13.5.6 Tests or inspections conducted pursuant to the Contract Documents shall be made promptly to avoid

unreasonable delay in the Work. 13.6 INTEREST

Page 52: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 36

13.6.1 Payments due and unpaid under the Contract Documents shall bear interest from the date payment is due at such rate as the parties may agree upon in writing or, in the absence thereof, at the legal rate prevailing from time to time at the place where the Project is located.

13.7 COMMENCEMENT OF STATUTORY LIMITATION PERIOD 13.7.1 As between the Owner and Contractor:

.1 Before Substantial Completion. As to acts or failures to act occurring prior to the relevant date of Substantial Completion, any applicable statute of limitations shall commence to run and any alleged cause of action shall be deemed to have accrued in any and all events not later than such date of Substantial Completion;

.2 Between Substantial Completion and Final Completion. As to acts or failures to act occurring subsequent to the relevant date of Substantial Completion and prior to issuance of the final Certificate of Completion, any applicable statute of limitations shall commence to run and any alleged cause of action shall be deemed to have accrued in any and all events not later than the date of issuance of the final Certificate of Completion; and

.3 After Final Completion. As to acts or failures to act occurring after the relevant date of issuance of the final Certificate of Completion, any applicable statute of limitations shall commence to run and any alleged cause of action shall be deemed to have accrued in any and all events not later than the date of any act or failure to act by the Contractor pursuant to any Warranty provided under Section 3.5, the date of any correction of the Work or failure to correct the Work by the Contractor under Section 12.2, or the date of actual commission of any other act or failure to perform any duty or obligation by the Contractor or Owner, whichever occurs last.

ARTICLE 14 - TERMINATION OR SUSPENSION OF THE CONTRACT 14.1 TERMINATION BY THE CONTRACTOR 14.1.1 The Contractor may terminate the Contract if the Work is stopped for a period of 30 consecutive days

through no act or fault of the Contractor or a Subcontractor, Sub-subcontractor or their agents or employees or any other persons or entities performing portions of the Work under direct or indirect contract with the Contractor, for any of the following reasons: .1 issuance of an order of a court or other public authority having jurisdiction which requires all Work to

be stopped; .2 an act of government, such as a declaration of national emergency which requires all Work to be

stopped; or .3 because the Owner has not made payment on an Application for Payment within the time stated

within the Contract Documents.

14.1.2 The Contractor may terminate the Contract if, through no act or fault of the Contractor or a Subcontractor, Sub-subcontractor or their agents or employees or any other persons or entities performing portions of the Work under direct or indirect contract with the Contractor, repeated suspensions, delays or interruptions of the entire Work by the Owner as described in Section 14.3 constitute in the aggregate more than 100 percent of the total number of days scheduled for completion, or 120 days in any 365-day period, whichever is less.

14.1.3 If one of the reasons described in Section 14.1.1 or 14.1.2 exists, the Contractor may, upon seven days'

written notice to the Owner and Engineer, terminate the Contract and recover from the Owner payment as set forth and subject to the limitations in § 14.4.3.

14.1.4 If the Work is stopped for a period of 60 consecutive days through no act or fault of the Contractor or a

Subcontractor or their agents or employees or any other persons performing portions of the Work under contract with the Contractor because the Owner has persistently failed to fulfill the Owner's obligations under the Contract Documents with respect to matters important to the progress of the Work, the

Page 53: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 37

Contractor may, upon seven additional days' written notice to the Owner and the Engineer, terminate the Contract and recover from the Owner as provided in Section 14.1.3.

14.2 TERMINATION BY THE OWNER FOR CAUSE 14.2.1 The Owner may terminate the Contract if the Contractor:

.1 persistently or repeatedly refuses or fails to supply enough properly skilled workers or proper materials;

.2 fails to make payment to Subcontractors for materials or labor in accordance with the respective agreements between the Contractor and the Subcontractors;

.3 persistently disregards laws, ordinances, or rules, regulations or orders of a public authority having jurisdiction; or

.4 otherwise is guilty of substantial breach of a provision of the Contract Documents. 14.2.2 When any of the above reasons exist, the Owner may, without prejudice to any other rights or remedies of

the Owner and after giving the Contractor and the Contractor's surety, if any, seven days' written notice, terminate employment of the Contractor and may, subject to any prior rights of the surety: .1 take possession of the site and of all materials, equipment, tools, and construction equipment and

machinery thereon owned by the Contractor; .2 accept assignment of subcontracts pursuant to Section 5.4; and .3 finish the Work by whatever reasonable method the Owner may deem expedient. Upon request of the

Contractor, the Owner shall furnish to the Contractor a detailed accounting of the costs incurred by the Owner in finishing the Work.

14.2.3 When the Owner terminates the Contract for one of the reasons stated in Section 14.2.1, the Contractor

shall not be entitled to receive further payment until the Work is finished. 14.2.4 If the unpaid balance of the Contract Sum exceeds costs of finishing the Work, including compensation for

the Engineer's services and expenses made necessary thereby, and other damages incurred by the Owner and not expressly waived, such excess shall be paid to the Contractor. If such costs and damages exceed the unpaid balance, the Contractor shall pay the difference to the Owner. The amount to be paid to the Contractor or Owner, as the case may be, shall be determined by the Owner, upon application, and this obligation for payment shall survive termination of the Contract.

14.2.5 If Owner’s termination of the Contract is based upon a reason that is subsequently determined to not be a

default of this Contract, such termination shall instantaneously and automatically be deemed a termination for the convenience of Owner. In any such termination, the Owner shall be liable to Contractor only for accepted Work completed prior to the date of Owner’s sending notice to Contractor of such termination, and Contractor agrees that in such case Owner is not and shall not be liable for any loss of anticipated profits on labor and material not yet furnished on the Project or on any portion of the unperformed Work.

14.3 SUSPENSION BY THE OWNER FOR CONVENIENCE 14.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work in

whole or in part for such period of time as the Owner may determine. 14.3.2 The Contract Sum and Contract Time shall be adjusted for increases in the cost and time caused by

suspension, delay or interruption as described in Section 14.3.1. Adjustment of the Contract Sum shall include profit. No adjustment shall be made to the extent: .1 that performance is, was or would have been so suspended, delayed or interrupted by another cause

for which the Contractor is responsible; or .2 that an equitable adjustment is made or denied under another provision of the Contract.

Page 54: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 00700 - 38

14.3.3 In event Owner is unable to make any payment under Contract due to non-appropriation of funds by Legislature or non-availability of other funds of Owner approved by the Board of Regents for purpose of payment of Contract Sum or any part thereof, upon giving 7 days written notice to Contractor, terminate the Contract. Upon such termination Contractor shall be entitled to recover from Owner payment as set forth and subject to the limitations of § 14.4.3.

14.4 TERMINATION BY THE OWNER FOR CONVENIENCE 14.4.1 The Owner may, at any time, terminate the Contract for the Owner's convenience and without cause. 14.4.2 Upon receipt of written notice from the Owner of such termination for the Owner's convenience, the

Contractor shall: .1 cease operations as directed by the Owner in the notice; .2 take actions necessary, or that the Owner may direct, for the protection and preservation of the Work;

and .3 except for Work directed to be performed prior to the effective date of termination stated in the notice,

terminate all existing subcontracts and purchase orders and enter into no further subcontracts and purchase orders.

14.4.3 In case of such termination for Owner’s convenience, the Contractor shall be entitled to receive

payment for Work executed and costs incurred for terminating and demobilizing operating from the project site, but shall not be entitled to either overhead or profit on Work not executed.

15.1 NEBRASKA FAIR EMPLOYMENT PRACTICE ACT 15.1.1 Neither the Contractor nor any Subcontractor shall discriminate against any employee or applicant for

employment to be employed in the performance of the Contract, with respect to hire, tenure, terms, conditions, or privileges of employment, because of race, color, religion, sex or national origin, as prohibited by the Nebraska Fair Employment Practice Act. The Contractor hereby warrants and represents that it is in compliance with said Act. Any failure to so comply during the performance of this Contract shall be a material breach of the Contract. The Contractor shall receive from each Subcontractor warranties and representations similar in substance to those contained in this paragraph.

15.2 EQUAL OPPORTUNITY CLAUSE AND CERTIFICATION OF NON-SEGREGATED FACILITIES 15.2.1 The Contractor hereby represents that it is in compliance with Executive Order No. 11246 of September 24,

1965, and of the rules, regulations and relevant orders of the Secretary of Labor of the United State of America as set forth in the Attachment.

END OF SECTION 00700

Page 55: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 01100 - 1

SECTION 01100 - SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General Conditions and other Division 1 Specification Sections, apply to this Section.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work consists of but is not limited to: Procurement of an air cooled chiller including required field assembly, full start-up and testing and indicated warranty/service provisions.

B. Engineer Identification: The Contract Documents, dated December 2013 were

prepared for the Project by; RDH Engineering, Inc.

C. Owner's Project Coordinator: Bellevue Public Schools will be designate an Owner's Project Coordinator for purpose of this Contract.

1. Contractor shall cooperate with, continually advise, coordinate and

communicate with Owner's Project Coordinator regarding progress of the Work, scheduling, prior notices of special arrangements necessary to move materials and equipment over Owner's site or through buildings, to cause mechanical and electrical outages and to perform any other operations which will affect normal use of any of Owner's facilities.

2. Owner's Project Coordinator will cooperate with Contractor and convey

Contractor's reports, notices and other information to those having Owner’s interest or responsibility for this Contract.

1.3 CONTRACT

A. Project will be constructed under a single general construction contract. 1.4 FUTURE WORK

A. Not Applicable. 1.5 EXISTING CONDITIONS AND MEASUREMENTS

A General: Information pertaining to existing building has been obtained through original drawings, documents, investigations and photographs; this is indicated on the Drawings and in Project Manual.

1. Information has been gathered with reasonable care but is of a schematic

quality and is not warranted.

2. Verify all dimensions and existing conditions in the field prior to ordering materials or construction.

B Discrepancies: Be alert to any evidence or indication of existing conditions not

indicated on the Drawings. Measurements shall be verified from actual observation at site.

B. Responsibility: Contractor is responsible for all Work fitting in place in an approved,

satisfactory and workman like manner in every condition and case. If unexpected conditions are encountered, cease operations immediately to minimize damage and notify Owner.

Page 56: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 01100 - 2

1. Contractor shall bear costs of damage resulting from failure to exercise

reasonable care or continuing operations without notifying Owner. 1.6 SPECIFICATION FORMATS AND CONVENTIONS

A. Specification Format: Specifications are organized into Divisions and Sections using CSI/CSC’s “MasterFormat” numbering system.

1. Section Identification: Specifications use section numbers and titles to help

cross-referencing in the Contract Documents. Sections in the Project Manual are in numeric sequence; however, the sequence is incomplete. Consult the table of contents at the beginning of the Project Manual to determine numbers and names of sections in the Contract Documents.

B. Specification Content: Specifications use certain conventions for the style of

language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:

1. Abbreviated Language: Language used in the Specifications and other

Contract Documents is abbreviated. Words and meanings shall be interpreted as appropriate. Words implied, but not stated, shall be inferred as the sense requires. Singular words shall be interpreted as plural, and plural words shall be interpreted as singular where applicable as the context of the Contract Documents indicates.

2. Imperative mood and streamlined language are generally used in the

Specifications. Requirements expressed in the imperative mood are to be performed by Contractor. Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be fulfilled indirectly by Contractor or by others when so noted.

a. The words “shall,” “shall be,” or “shall comply with,” depending on the

context, are implied where a colon (:) is used within a sentence or phrase.

1.7 PRODUCTS ORDERED IN ADVANCE (Not Applicable) 1.8 OWNER-FURNISHED PRODUCTS (Not Applicable) 1.9 WORK SCHEDULE

A. Bids Received as stipulated in Section 0200 B. Owner selection of chiller/vendor and issue of letter of intent to purchase chiller

C. Submission of shop drawings

D. Anticipated arrival of chiller to Owner site March 12, 2014

E. Inspection of chiller prior to assignment of equipment to installing contractor

F. Coordination with installing contractor

G. Start-up and commissioning period: April 9, 2014

H. Units fully operational, testing and training complete: April 15, 2014

1.10 ASSIGNMENT OF EQUIPMENT

Page 57: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 01100 - 3

A. After bids have been evaluated the Owner will issue the successful bidder a letter of intent to purchase a chiller. During chiller production, the Owner will assign the chiller to the successful bidding Contractor for installation. The Contractor shall become responsible for receiving, installing and insuring the chiller in the exact manner as if the Contractor had been the original purchaser of the chiller. The chiller vendor/manufacturer, is responsible for the chiller until the Contractor assumes responsibility. The assignment of responsibility shall switch to the installation Contractor when the chiller is rigged and entire weight lifted from the transportation vehicle on the Owner site. A thorough inspection of the chiller shall be conducted by all parties prior to the rigging/lifting of the equipment.

PART 2 - PRODUCTS (Not applicable). PART 3 – EXECUTION (Not applicable). END OF SECTION 01100

Page 58: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 01230 - 1

SECTION 01230 - ALTERNATES PART 1 - GENERAL 1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General Conditions and other Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes administrative and procedural requirements governing Alternates. 1.3 DEFINITIONS

A. Alternate: An amount proposed by Bidder and stated on Bid Form for certain work defined in Bidding Requirements that may be added to or deducted from Base Bid amount. The Owner may decide to accept a corresponding change in either amount of construction to be completed, or in products, materials, equipment, systems, or installation methods described in Contract Documents.

1. Cost for each alternate is net addition to or deduction from Contract Sum to

incorporate Alternate into the Work. No other adjustments are made to Contract Sum.

1.4 PROCEDURES

A. Coordination: Modify or adjust affected adjacent Work as necessary to completely and fully integrate Work of the alternate into the Project.

1. Include as part of each alternate, miscellaneous devices, accessory objects, and

similar items incidental to or required for a complete installation whether or not mentioned as part of Alternate.

B. Notification: Immediately following award of Contract, notify each party involved, in writing,

of status of each alternate. Indicate if alternates have been accepted, rejected, or deferred for later consideration.

C. Execute accepted alternates under same conditions as other Work of this Contract.

D. Schedule: "Schedule of Alternates" is included at end of this Section. Specification Sections

referenced in Schedule contain requirements for materials necessary to achieve the Work described under each alternate.

PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION (Not Applicable)

END OF SECTION 01230

Page 59: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 01250 - 1

SECTION 01250 – CONTRACT MODIFICATION PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS

A. Drawings and general provisions of Contract, with General Conditions and other Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section specifies administrative and procedural requirements for handling and processing contract modifications.

B. Related Sections: Following contain requirements relating to this Section:

1. Section 01290 – Payment Procedures: Procedures for payment.

1.3 MINOR CHANGES IN THE WORK

A. Engineer will issue supplemental instructions authorizing minor changes in the Work, not involving adjustment to Contract Sum or Contract Time.

B. Form: AIA Form G710, Architect's Supplemental Instructions.

1.4 PROPOSAL REQUESTS

A. Owner-Initiated Proposal Requests: Engineer or Owner will issue detailed description of proposed changes in the Work that may require adjustment to Contract Sum or Contract Time. If necessary, description will include supplemental or revised Drawings and Specifications.

1. Proposal Requests are for information only. Do not consider them as instructions

either to stop work in progress or to execute proposed change.

2. Within 5 days after receipt of a proposal request, submit a quotation estimating cost adjustments necessary to execute change. Submit to Owner for review. Include following:

a. Itemized breakdown for labor and material identifying both additions and

deletions. b. Statement indicating effect proposed change in the Work will have on

Contract Time.

B. Contractor-Initiated Proposal Requests: If latent or unforeseen conditions require modifications to the Contract, Contractor may propose changes by submitting a request for a change to Owner. Include following:

1. Statement outlining reasons for change and effect of change on the Work. Provide a

complete description of proposed change. Indicate effect that proposed change will have on Contract Sum and Contract Time.

2. Itemized breakdown for labor and material identifying both additions and deletions.

3. Indicate applicable delivery charges, equipment rental, and amounts of trade

discounts.

4. Comply with requirements in Section 01600 – Product Requirements, if proposed change requires substitution of one product or system for a product or system specified.

Page 60: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 01250 - 2

C. Form: AIA Document G709, Proposal Request. 1.5 ALLOWANCES (Not Applicable) 1.6 SCHEDULE OF CHARGEABLE LABOR RATES (Not Applicable) 1.7 CONSTRUCTION CHANGE DIRECTIVE

A. Construction Change Directive: Contains a description of a change in the Work. It designates method to be followed to determine change in Contract Sum or Contract Time and authorizes Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.

1. When Owner and Contractor disagree on terms of a Proposal Request, then

Contractor may be instructed to proceed with a change so that a delay does not occur.

B. Construction Change Directive Form:

1. Engineer may use Construction Change Directive on RDH standard form.

2. Owner may use Construction Change Directive on RDH standard form.

C. Documentation: Maintain detailed records on a time and material basis of work required by

Construction Change Directive.

1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to Contract.

1.8 DOCUMENTATION OF PROPOSALS AND CLAIMS

A. Contractor shall support each proposal or directive submitted with an itemized quotation.

1. To facilitate checking, review and analysis of quotations by Owner and Enginer for extras, credits or changes, all proposals or claims shall be accompanied by a itemization of costs including labor, materials and Sub-contracts. Labor and materials shall be itemized as prescribed below and no other costs than those described will be paid by Owner. Where major cost items are Sub-contracts, they shall be itemized also.

2. If proposal includes a time extension, furnish itemization.

3. Submit claims within 5 days of receipt of Change Order Proposal or Construction

Change Directive authorizing work to proceed. Owner will reject claims submitted no later than 21 days.

1.9 CHANGE ORDER PROCEDURES

A. Upon Owner's receipt of documentation and approval of a Proposal Request, Owner will issue a Change Order for signatures on RDH Change Order Form. Contractor then Owner will sign and date the form to indicate agreement.

1.10 CORRELATION WITH SUBMITTALS (Not Applicable) PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION (Not Applicable) END OF SECTION 01250

Page 61: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 01290 - 1

SECTION 01290 – PAYMENT PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General Conditions and other Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section specifies administrative and procedural requirements governing Contractor's Applications for Payment.

B. Payment Schedule:

1. 80% paid upon delivery of chiller.

2. 10% paid upon completion of start-up and receipt of start-up reports. (Substantial

Completion)

3. 10% paid upon completion of training and receipt of approved O&M manuals.

4. Pay requests shall be submitted to the Engineer by the tenth (10th) day of the month which will be submitted to the Owner by the fifteenth (15th) day of the month. Payment to the Contractor will occur after the next School Board meeting, which is generally the first Monday of the month. If the first Monday of the month is a holiday, the School Board will meet on the second Monday.

1.3 APPLICATIONS FOR PAYMENT

A. Each Application shall be consistent with previous applications and payments as certified and paid for by Owner.

1. Initial Application for Payment, Application for Payment at time of Substantial

Completion, and final Application for Payment involve additional requirements.

B. Waivers of Mechanics Lien: With Final Application for Payment, submit waivers of lien from every entity who is lawfully entitled to file a lien arising out of performance of Contract.

1. Owner reserves right to designate which entities involved in the Work must submit

waivers.

2. Form: Submit waivers of lien on forms, and executed in a manner, acceptable to Owner.

C. Initial Application for Payment: Administrative actions and submittals, that must precede or

coincide with submittal of first Application for Payment, include following:

1. List of principal suppliers and fabricators.

2. Equipment delivery Schedule.

3. Submittal Schedule.

4. Copies of authorizations and licenses from governing authorities for performance of the Work.

Page 62: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 01290 - 2

D. Application for Payment at Substantial Completion: After issuance of Certificate of

Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete. Administrative actions and submittals that shall precede or coincide with this application include:

1. Warranties (guarantees) and maintenance agreements.

2. Test/adjust/balance records.

3. Maintenance instructions.

4. Startup performance reports.

5. Application for reduction of retainage and consent of surety.

E. Final Payment Application: Administrative actions and submittals that precede or coincide with submittal of final Application for Payment:

1. Evidence of completion of Project closeout requirements.

2. Completion of items specified for completion after Substantial Completion.

3. Transmittal of required Product records to Owner.

4. Proof that taxes, fees, and similar obligations were paid.

5. Compliance with Nebraska Employment Security Law. Submit completed form.

PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION (Not Applicable) END OF SECTION 01290

Page 63: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 01330 - 1

SECTION 01330 – SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 RELATED DOCUMENTS

A. Drawings and general provisions of Contract, including General Conditions and other Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section specifies administrative and procedural requirements for submittal of Administrative Information, Shop Drawings, Product Data, Samples, Operation & Maintenance Manuals, and other miscellaneous submittals.

B. Related Sections include the following:

1. Section 01290 – Payment Procedures; for submitting Applications for Payment.

2. Section 01820 – Operation and Maintenance Data; for operation and maintenance manual requirements.

1.3 DEFINITIONS

A. Action Submittals: Written and graphic information that requires Engineer’s and Owner’s responsive action.

B. Informational Submittals: Written information that does not require Engineer’s and Owner’s

approval. Submittals may be rejected for not complying with requirements. 1.4 SUBMITTAL PROCEDURES

A. General: Unless otherwise approved by the Owner and Engineer, electronic copies of CAD Drawings of the Contract Drawings will not be provided for contractor’s use in preparing submittals.

B. Coordination: Coordinate preparation and processing of submittals with performance of

construction activities. Transmit each submittal to Owner sufficiently in advance of scheduled performance of related construction activities to avoid delay.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other

submittals, and related activities that require sequential activity.

a. Testing. b. Purchasing. c. Fabrication. d. Delivery.

C. Processing Time: Allow sufficient time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Engineer’s receipt of submittal.

1. Initial Review: Allow 14 days for initial review of each submittal. Allow additional time

if processing must be delayed to permit coordination with subsequent submittals. Engineer will notify Contractor when a submittal being processed must be delayed for coordination.

2. Allow 21 days for reprocessing each submittal.

3. No extension of Contract Time will be authorized because of Contractor's failure to

Page 64: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 01330 - 2

transmit submittals to Engineer sufficiently in advance of the Work to permit processing.

D. Identification: Place a permanent label or title block on each submittal for identification.

1. Indicate name of firm or entity that prepared each submittal on label or title block.

2. Provide “white space” of approximately 4 by 5 inches on label or beside title block to

record Contractor’s review and approval markings and action markings taken by Engineer and Owner.

3. Include the following information on label for processing and recording action taken:

a. Project name and Project number. b. Date. c. Name of Engineer. d. Name of Contractor. e. Name of subcontractor (if applicable). f. Name of supplier. g. Name of manufacturer. h. Number and title of Specification Section. i. Drawing number and detail references, as appropriate.

E. Deviations: Highlight, encircle, or otherwise identify deviations form the Contract Documents on submittals.

F. Transmittal: Package each submittal individually and appropriately for transmittal and

handling. Transmit each submittal with approved Transmittal Form. Submittals containing information about more than one item or one Specification Section will be returned without action. Submittals received from sources other than Contractor will be returned without action.

1. Record relevant information, requests for data, revisions other than those requested

by Engineer and Owner on previous submittals, and deviations from requirements of the Contract Documents, including minor variations and limitations. Include the same label information as the related submittal on Transmittal Form.

G. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers,

fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.

H. Use for Construction: Use only final submittals with marking indicating approved action taken

by Engineer and Owner in connection with construction. PART 2 - PRODUCTS 2.1 ACTION SUBMITTALS

A. General: Prepare and submit Action Submittals required by individual Specification Sections.

1. Number of Copies: Submit 5 copies of each submittal, unless copies are required for operation and maintenance manuals. Owner will retain 2 copies, Engineer will retain 1 copy; remainder will be returned.

B. Shop Drawings: Submit newly prepared Project-specific information, drawn to accurate

scale. Provide Shop Drawings as complete submittals, no partial sets. Highlight, encircle, or otherwise indicate deviations from Contract Documents.

1. Do not reproduce Contract Documents or copy standard information as basis of Shop

Page 65: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 01330 - 3

Drawings. Standard information prepared without specific reference to the Project is not considered Shop Drawings.

2. Shop Drawings include but are not limited to following; fabrication and installation

drawings, setting diagrams, schedules, patterns, design mix formulas, templates and similar drawings. Include following information, as applicable:

a. Dimensions. b. Identification of products and materials. c. Notation of coordination requirements. d. Notation of dimensions established by field measurement. e. Compliance with specified standards. f. Fabrication and installation drawings g. Rough-in and setting diagrams h. Wiring diagrams showing field-installed wiring, including power, signal, and

control wiring. i. Templates and patterns j. Design calculations.

3. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed

wiring.

4. Sheet Size: Except for templates, patterns and similar full-size Drawings, submit Shop Drawings on sheets at least 8-1/2" x 11" but no larger than size of Contract Drawings.

5. Submittal: Submit 1 correctable translucent reproducible print and 5 black-line prints

of each drawing to Engineer. At the same time submit 1 black-line print of each drawing to Owner for concurrent review. Owner's review print shall not be returned. Submit prints without folds; flat sheets, if size permits, or rolled in tubes.

a. Engineer will review and stamp drawings marked with action taken and

corrections or modifications required, then submit prints of each drawing to Owner.

b. Owner will review and stamp drawings marked with action taken and corrections or modifications required. Owner will retain 2 prints of each drawing, send 1 print of each drawing to Engineer, reproducible print and remainder of prints of drawing shall be returned to Contractor. One print shall be marked up and maintained by Contractor as a Project Record Drawing.

C. Product Data: Collect standard printed data and information into a single submittal for each

element of construction and type of product or equipment.

1. If data and information must be specially prepared because standard printed data or information is not suitable for use, submit as "Shop Drawings," not as Product Data.

a. Product Data includes but is not limited to; printed information such as

manufacturer's product specifications and installation instructions, catalog cuts, standard color charts, roughing-in diagrams and templates, standard wiring diagrams and performance curves.

2. Mark each copy of each submittal to show applicable choices and options. Where

printed Data includes information on several products, clearly mark copies to indicate applicable information only.

3. Include the following information, as applicable:

a. Manufacturer's written recommendations. b. Compliance with recognized trade association standards. c. Compliance with recognized testing agency standards.

Page 66: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 01330 - 4

d. Application of testing agency labels and seals. e. Notation of dimensions verified by field measurement. f. Notation of coordination requirements. g. Manufacturer’s product specifications. h. Manufacturer’s installation instructions. i. Manufacturer’s catalog cuts. j. Color charts. k. Wiring diagrams showing factory-installed wiring. l. Printed performance curves. m. Operational range diagrams. n. Standard product operating and maintenance manuals. o. Provide copy of manufacturer's Material Safety Data Sheet (MSDS).

4. Do not submit Product Data until compliance with requirements of Contract

Documents has been confirmed.

a. Product Data submitted with extra information not clearly marked out or deleted shall be returned.

2.2 INFORMATIONAL SUBMITTALS

A. General: Prepare and submit Informational Submittals required by other Specification Sections.

1. Number of Copies: Submit 3 copies of each submittal, unless otherwise indicated. No

copies will be returned.

2. Certificates and Certifications: Provide a notarized statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.

B. Product Certificates: Prepare written statements on manufacturer’s letterhead certifying that product complies with requirements.

C. Manufacturer Certificates: Prepare written statements on manufacturer’s letterhead certifying that manufacturer complies with requirements. Include evidence of manufacturing experience where required.

D. Material Certificates: Prepare written statements on manufacturer’s letterhead certifying that

material complies with requirements.

E. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency’s standard form, indicating and interpreting test results of material compliance with requirements.

F. Product Test Reports: Prepare written reports indicating current product produced by manufacturer complies with requirements. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.

G. Maintenance Data: Prepare written and graphic instructions and procedures for operation

and normal maintenance of products and equipment. Comply with requirements of Section 01820 - Operation and Maintenance Data.

H. Manufacturer’s Instructions: Prepare written or published information that documents

manufacturer’s recommendations, guidelines, and procedures for installing or operating a

Page 67: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 01330 - 5

product or equipment. Include name of product and name, address, and telephone number of manufacturer.

1. Include the following as applicable:

a. Preparation of substrates. b. Required substrate tolerances. c. Sequence of installation or erection. d. Required installation tolerances. e. Required adjustments. f. Recommendations for cleaning and protection.

I. Insurance Certificates and Bonds: Prepare written information indicating current status of

insurance or bonding coverage. Include name of entity covered by insurance or bond, limits of coverage, amounts of deductibles, if any, and term of coverage.

J. Material Safety Data Sheets: Submit information directly to Owner.

PART 3 - EXECUTION 3.1 CONTRACTOR’S REVIEW (Not Applicable) 3.2 ENGINEER'S AND OWNER'S ACTION

A. Action Submittals: Engineer and Owner will review each submittal, make marks to indicate corrections or modifications required, and return it. Engineer and Owner will stamp each submittal with a uniform, self-explanatory action stamp. Stamp will be appropriately marked, as follows, to indicate action taken:

1. Final Unrestricted Release: Submittal marked "Reviewed, No Exceptions Taken", that

part of the Work covered by submittal may proceed provided it complies with requirements of Contract Documents; final acceptance will depend upon that compliance.

2. Final-But-Restricted Release: Submittal marked "Reviewed, Exceptions Taken As

Noted", that part of the Work covered by submittal may proceed provided it complies with notations or corrections on submittal and requirements of Contract Documents; final acceptance will depend on that compliance.

3. Returned for Resubmittal: Submittal marked "Revise and Resubmit" or "Rejected", do

not proceed with that part of the Work covered by submittal, including purchasing, fabrication, delivery, or other activity. Revise or prepare a new submittal in accordance with notations; resubmit without delay. Repeat if necessary to obtain a different action mark.

a. Do not permit submittal marked "Revise and Resubmit" or "Rejected" to be

used at Project site, or elsewhere where Work is in progress.

B. Informational Submittals: Engineer and Owner will review each submittal and will not return it, or will reject and return if it does not comply with requirements. Engineer and Owner will forward each submittal as appropriate.

C. Submittals not required by the Contract documents will not be reviewed and may be

discarded. END OF SECTION 01330

Page 68: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 01600 - 1

SECTION 01600 – PRODUCT REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General Conditions and other Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes the following administrative and procedural requirements; selection of products for use in the Project; product delivery, storage, and handling, manufacturers’ standard warranties on products; special warranties; product substitutions; and comparable products.

B. Related Sections include the following:

1. Section 01230 - Alternates: for products selected under an alternate.

2. Section 01820 – Operation and Maintenance Data.

3. Specific requirements for warranties on products and installations specified to be

warranted. 1.3 DEFINITIONS

A. Products: Items purchased for incorporation into the Work, whether purchased for this Project or taken from previously purchased stock. The term "product" includes the terms: "material," "equipment," "system," and terms of similar intent.

1. Named Products: Items identified by manufacturer's product name, including make or

model number or other designation, shown or listed in current edition of manufacturer's published product literature, current as of date of Contract Documents.

2. New Products: Items that have not previously been incorporated into another project

or facility, except that products consisting of recycled-content materials are allowed, unless stated otherwise. Products salvaged or recycled from other projects are not considered new products.

3. Comparable Product: Product that is demonstrated and approved through submittal

process, or where indicated as a product substitution, to have the indicated qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics that equal or exceed those of specified product.

4. Foreign Products: As distinguished from "domestic products", are items substantially

manufactured (50 percent or more of value) outside United States and its possessions. Products produced or supplied by entities substantially owned (more than 50 percent) by persons who are not citizens of, nor living within, United States and its possessions are also considered to be foreign products.

1.4 SUBMITTALS (Not Applicable) 1.5 QUALITY ASSURANCE

A. Source Limitations: To fullest extent possible, provide products of same kind, from a single source.

Page 69: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 01600 - 2

1. When specified products are available only from sources that do not, or cannot, produce a quantity adequate to complete Project requirements in a timely manner, consult with Engineer and Owner to determine most important product qualities before proceeding. Qualities may include attributes, such as visual appearance, strength, durability or compatibility. When a determination has been made, select products from sources producing products that possess these qualities, to fullest extent possible.

B. Compatibility of Options: If Contractor is given option of selecting between two or more

products for use on Project, product selected shall be compatible with products previously selected, even if previously selected products were also options.

1. Each contractor is responsible for providing products and construction methods

compatible with products and construction methods of other contractors.

2. If a dispute arises between contractors over concurrently selectable but incompatible products, Engineer shall determine which products shall be used.

1.6 PRODUCT DELIVERY, STORAGE AND HANDLING

A. Deliver, store and handle products according to manufacturer's recommendations, using means and methods to prevent damage, deterioration, loss, and theft.

1. Schedule delivery to minimize storage at Project site and to prevent over-crowding of

construction spaces.

2. Coordinate delivery with installation time to ensure minimum holding time for items that are flammable, hazardous, easily damaged, or sensitive to deterioration, theft, and other losses.

3. Deliver products to Project site in an undamaged condition in manufacturer's original

sealed container or other packaging system, complete with labels and instructions for handling, storing, unpacking, protecting, and installing.

4. Inspect products upon delivery to ensure compliance with Contract Documents, and

ensure that products are undamaged and properly protected.

5. Store products to allow for inspection and measurement of quantity or counting of units.

6. Store materials in a manner that will not endanger Project structure.

7. Store products subject to damage by the elements, above ground, under cover in a

weather-tight enclosure, with ventilation adequate to prevent condensation.

8. Comply with product manufacturer’s written instructions for temperature, humidity, ventilation, and weather-protection requirements for storage.

9. Protect stored products from damage.

1.7 PRODUCT WARRANTIES

A. Warranties specified in other Sections shall be in addition to, and run concurrent with, other warranties required by the Contract Documents. Manufacturer’s disclaimers and limitations on product warranties do not relieve Contractor of obligations under requirements of the Contract Documents.

B. Special Warranties: Prepare a written document that contains appropriate terms and

identification, ready for execution. Submit a draft for approval by Owner, before final execution.

Page 70: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 01600 - 3

1. Manufacturer’s Standard Form: Modified to include Project-specific information and

properly executed.

2. Refer to Specification Sections for specific content requirements and particular requirements for submitting special warranties.

PART 2 - PRODUCTS 2.1 PRODUCT OPTIONS

A. General Product Requirements: Provide products that comply with Contract Documents, that are undamaged, and unless otherwise indicated, that are new at time of installation.

1. Provide products complete with all accessories, trim, finish, fasteners, safety guards,

and other items, devices, and details needed for a complete installation and for intended use and effect.

2. Standard Products: If available, and unless custom products or nonstandard options

are specified, provide standard products of types that have been produced and used successfully in similar situations on other projects.

3. Owner reserves the right to limit selection to products with warranties not in conflict

with requirements of the Contract Documents.

4. Where products are accompanied by the term “as selected,” Engineer will make selection.

5. Where products are accompanied by the term “match sample,” sample to be matched

is Owner’s.

B. Product Selection Procedures: Selection is governed by Contract Documents and governing regulations. Procedures governing product selection include following:

1. Product: Where Specification paragraphs or subparagraphs titled “Product” name a

single product and manufacturer, provide product indicated. No substitutions will be permitted.

2. Manufacturer/Source: Where Specification paragraphs or subparagraphs titled

“Manufacturer” or “Source” name a single manufacturers or sources, provide a product by the manufacturer or from the source named that complies with requirements.

3. Products: Where Specification paragraphs or subparagraphs titled “Products”

introduce a list of names of both products and manufacturers, provide one of the products listed that complies with requirements.

4. Manufacturers: Where Specification paragraphs or subparagraphs titled

“Manufacturers” introduce a list of manufacturers’ names, provide a product by one of the manufacturers listed that complies with requirements.

5. Available Products: Where Specification paragraphs or subparagraphs titled

“Available Products” introduce a list of names of both products and manufacturers, provide one of the products listed or another product that complies with requirements. No substitutions will be permitted.

6. Available Manufacturers: Where Specification paragraphs or subparagraphs titled

“Available Manufacturers” introduce a list of manufacturers’ names, provide a product by one of the manufacturers listed or another manufacturer that complies with

Page 71: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 01600 - 4

requirements.

7. Product Options: Where Specification paragraphs titled “Product Options” indicate that size, profiles, and dimensional requirements on Drawings are based on a specific product or system, provide either the specific product or system indicated or a comparable product or system by another manufacturer. Comply with provisions in “Product Substitutions” Article.

8. Basis-of-Design Products: Where Specification paragraphs or subparagraphs titled

“Basis-of-Design Product” are included and also introduce or refer to a list of manufacturers’ names, provide either the specified product or a comparable product by one of the other named manufacturers. Drawings and Specifications indicate sizes, profiles, dimensions, and other characteristics that are based on the product named. Comply with provisions in “Comparable Products” Article to obtain approval for use of an unnamed product.

PART 3 – EXECUTION (Not Applicable.) END OF SECTION 01600

Page 72: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 01820 - 1

SECTION 01820 - OPERATION AND MAINTENANCE DATA PART 1 - GENERAL 1.1 RELATED DOCUMENTS

A. Drawings and general provisions of Contract, including General conditions and other Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section specifies administrative and procedural requirements for preparing operation and maintenance manuals, including the following:

1. Preparation and submittal of operating and maintenance manuals for building

operating systems or equipment. 2. Instruction of Owner's operating personnel in operation and maintenance of building

systems and equipment.

B. Related Sections include the following:

1. Section 01330 - Submittal Procedures: for submitting copies of submittals for operation and maintenance manuals.

2. Divisions 2 through 16 Sections for specific operation and maintenance manual

requirements for products in those Sections.

1.3 DEFINITIONS

1. System: An organized collection of parts, equipment, or subsystems united by regular interaction.

2. Subsystem: A portion of a system with characteristics similar to a system.

1.4 QUALITY ASSURANCE

A. Maintenance Manual Preparation: Use personnel trained and experienced in operation and maintenance of equipment or system involved.

1. For written instructions, use personnel skilled in technical writing, as necessary for

communication of essential data. 2. For Drawings or diagrams, use draftsperson to prepare Drawings clearly in an

understandable format.

B. Instruction of Owner's Personnel: Use experienced instructors trained and experienced in operation and maintenance of equipment or system involved.

1.5 SUBMITTALS

A. Draft Submittal: Submit 3 draft copies of each manual at least 15 days before requesting inspection for Substantial Completion. Submit 1 copy to Engineer and 2 copies to Owner for review and comment. Include a complete index or table of contents of each manual.

Engineer will return 1 copy of draft with Engineer and Owner review comments and will mark whether general scope and content of manual are acceptable. This copy will be returned to Contractor within 15 days of receipt, other draft copies shall not be returned.

Page 73: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 01820 - 2

B. Final Submittal:

1. Before Final Inspection: Submit 1 copy of each manual in final form, to Owner, at

least 15 days before final inspection. Owner will return this copy with comments within 7 days after final inspection.

2. After Final Inspection: Make corrections or modify each manual to comply with

Owner’s comments. Submit three (3) hard copies of each corrected manual, with three (3) accompanying CDs of electronic files, to Owner, within 15 days of receipt of Owner’s comments.

1.6 COORDINATION

A. Where operation and maintenance documentation includes information on installations by more than one factory-authorized service representative, assemble and coordinate information furnished by representatives and prepare manuals.

PART 2 - PRODUCTS 2.1 OPERATION AND MAINTENANCE DOCUMENTATION DIRECTORY

A. Organization: Include a section in the directory for each of the following:

1. List of documents. 2. List of systems. 3. List of equipment. 4. Table of contents.

B. List of systems and Subsystems: List systems alphabetically. Include references to

operation and maintenance manuals that contain information about each system. C. List of Equipment: List equipment for each system, organized alphabetically by system. For

pieces of equipment not part of system, list alphabetically in separate list. D. Table of Contents: Include a table of contents for each emergency, operation, and

maintenance manual. E. Identification: In the documentation directory and in each operation and maintenance

manual, identify each system, subsystem, and piece of equipment with the same designation used in the Contract Documents.

2.2 MANUALS, GENERAL

A. Organization: Unless otherwise indicated, organize each manual into separate sections for each system and subsystem, and a separate section for each piece of equipment not part of a system.

1. Each manual shall contain following materials, in the order listed:

a. Title page. b. Table of contents c. Manual contents

B. Title Page: Provide in a transparent plastic envelope as first sheet of each manual.

1. Provide following information:

Page 74: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 01820 - 3

a. Subject matter covered by manual. b. Name and address of the Project. c. Date of submittal. d. Name, address, and telephone number of Contractor. e. Name and address of Engineer. f. Cross reference to related systems in other volumes of operating and

maintenance manuals.

C. Table of Contents: After Title Page, include a typewritten table of contents for each volume, arranged systematically according to Project Manual format. Include a list of each product included, identified by product name or other appropriate identifying symbol and indexed to content of the volume. 1. If more than one volume is used, provide a comprehensive table of contents for all

volumes in each binder of the set.

D. Manual Contents: Organize into sets of manageable size. Arrange contents alphabetically by system, subsystem, and equipment. Assemble instructions for subsystems, equipment, and components of one system into a single binder.

1. Binders: Heavy-duty, 3-inch thick, 3-ring vinyl covered, loose-leaf binder, sized to

hold 8-1/2-inch by 11-inch paper; with clear plastic sleeve on spine to hold label and a pocket on inside of each cover.

a. If two or more binders are necessary to accommodate data of a system,

correlate data in each binder into related groupings in by subsystem and related components in accordance with Project Manual Table of Contents. Cross-reference other binders if necessary to provide essential information for proper operation or maintenance of equipment or system.

b. Identify each binder on front and spine, with typed or printed title "OPERATION AND MAINTENANCE MANUAL," Project title or name, and subject matter of contents. Indicate volume number for multiple-volume sets.

2. Dividers: Heavy-paper dividers with celluloid covered tabs for each Section. Mark

each tab to indicate contents. Include typed list of products and major components of equipment included in section on each divider, cross-referenced to Specification Section number and title of Project Manual.

3. REQUIREMENTS BELOW ARE NORMAL. INSERT SPECIAL REQUIREMENTS,

SUCH AS SPECIAL PAPER OR PLASTIC LAMINATION OF IMPORTANT ITEMS FOR PERMANENT PRESERVATION, IF CIRCUMSTANCES WARRANT.Text Material: Use manufacturer's standard printed material, or if specially prepared data, typewritten, on 8-1/2-inch by 11-inch, 20 pound, white bond paper.

4. Drawings: Where used, provide reinforced binder tabs on punched edge of drawing

and bind in manual.

a. Fold-outs: If oversize drawings are necessary, fold drawing to same size as text pages and use as foldouts.

b. Over-sized Drawing: If drawings, are too large to be used as foldouts, fold and place drawings in pocket in rear cover of manual. At appropriate locations in manual, insert a typewritten page indicating drawing title, description of contents, and drawing location.

2.3 OPERATION MANUALS

A. Content: In addition to requirements in this Section, include operation data required in individual Specification Sections.

1. Include the following information:

Page 75: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 01820 - 4

a. System, subsystem, and equipment descriptions. b. Operating standards. c. Operating procedures. d. Operating logs. e. Wiring diagrams. f. Control diagrams. g. Piped system diagrams. h. Precautions against improper use. i. License requirements including inspection and renewal dates.

B. Descriptions:

1. Include the following:

a. Product name and model number. b. Manufacturer’s name. c. Equipment identification with serial number of each component. d. Equipment function. e. Operating characteristics. f. Limiting conditions. g. Performance curves. h. Engineering data and tests. i. Complete nomenclature and number of replacement parts.

C. Operating Procedures:

1. Include the following, as applicable.

a. Startup procedures. b. Equipment or system break-in procedures. c. routine and normal operating instructions. d. Regulation and control procedures. e. Instructions on stopping. f. Normal shutdown instructions. g. Seasonal and weekend operating instructions. h. Required sequences for electric or electronic systems. i. Special operating instructions and procedures.

D. Systems and Equipment Controls: describe the sequence of operation, and diagram controls

as installed. E. Piped Systems: Diagram piping as installed, and identify color-coding where required for

identification. F. Coordination Drawings: Provide Contractor's Coordination Drawings. Provide as-installed

color-coded piping diagrams, where required for identification. G. Valve Tags: Provide charts of valve tag numbers, with location and function of each valve. H. Circuit Directories: For electric and electronic systems, provide complete circuit directories of

panelboards.

1. Include the following:

a. Electric service. b. Controls. c. Communication.

2.4 EMERGENCY MANUALS

Page 76: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 01820 - 5

A. Content: Organize manual into a separate section for each of the following:

1. Type of emergency. 2. Emergency instructions. 3. Emergency procedures.

B. Type of Emergency:

1. Where applicable for each type of emergency indicated below, include instructions and procedures for each system, subsystem, piece of equipment, and component: a. Fire. b. Flood. c. Gas leak. d. Water leak. e. Power failure. f. Water outage. g. System, subsystem or equipment failure. h. Chemical release or spill.

C. Emergency Procedures:

1. Include the following, as applicable:

a. Instructions on stopping. b. Shutdown instructions for each type of emergency. c. Operating instructions for conditions outside normal operating limits. d. Required sequences for electric or electronic systems. e. Special operating instructions and procedures.

2.5 PRODUCT MAINTENANCE MANUAL

A. Content: Organize manual into a separate section for each product, material, and finish. Include source information, product information, maintenance procedures, repair parts and sources, and warranties and bonds, as described below.

B. Source Information: List each product included in manual, identified by product name and

arranged to match manual’s table of contents. For each product, list name, address, and telephone number or Installer or supplier and maintenance service agent, and cross-reference Specification Section number and title in Project Manual.

C. Product Information:

1. Include following, as applicable:

a. Product name and model number. b. Manufacturer's name. c. Material and chemical composition. d. Color, pattern, and texture. e. Reordering information for specially manufactured products.

D. Maintenance Procedures:

1. Include manufacturer’s written recommendations and the following:

a. Inspection procedures. b. Types of cleaning agents to be used and methods of cleaning. c. List of cleaning agents and methods of cleaning detrimental to product. d. Schedule for routine cleaning and maintenance.

Page 77: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 01820 - 6

e. Repair instructions.

E. Repair Materials and Sources: Include lists of materials and local sources of materials and related services.

F. Warranties and Bonds: Include copies of warranties and bonds and lists of circumstances

and conditions that would affect validity of warranties or bonds.

1. Include procedures to follow and required notifications for warranty claims. 2.6 SYSTEMS AND EQUIPMENT MAINTENANCE MANUAL

A. Content: For each system, subsystem, and piece of equipment not part of a system, include source information, manufacturers’ maintenance documentation, maintenance procedures, maintenance and service schedules, spare parts list and source information, maintenance service contracts, and warranty and bond information, as described below.

B. Source Information: List each system, subsystem, and piece of equipment included in the

manual, identified by product name and arranged to match manual’s table of contents. For each product, list name, address, and telephone number of Installer or supplier and maintenance service agent, and cross-reference Specification Section number and title in Project Manual.

C. Manufacturers’ Maintenance Documentation: Manufacturers’ maintenance documentation

including following information for each component part or piece of equipment:

1. Standard printed maintenance instructions and bulletins.

2. Drawings, diagrams and instructions required for maintenance, including disassembly and component removal, replacement, and assembly.

3. Identification and nomenclature of parts and components. 4. List of items recommended to be stocked as spare parts.

D. Maintenance Procedures:

1. Include the following information and items that detail essential maintenance

procedures:

a. Test and inspection instructions. b. Troubleshooting guide. c. Precautions against improper maintenance. d. Disassembly; component removal, repair and replacement; and reassembly

instructions. e. Aligning, adjusting and checking instructions. f. Demonstration and training videotape, if available.

E. Maintenance and Service Schedules: Include service and lubrication requirements, list of

required lubricants for equipment, and separate schedules for preventive and routine maintenance and service with standard time allotment.

1. Scheduled Maintenance and Service: Tabulate actions for daily, weekly, monthly,

quarterly, semiannual, and annual frequencies. 2. Maintenance and Service Record: Include manufacturers’ forms for recording

maintenance.

F. Spare Parts List and Source Information: Include lists of replacement and repair parts, with parts identified and cross-referenced to manufacturers’ maintenance documentation and local sources of maintenance materials and related services.

Page 78: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 01820 - 7

G. Maintenance Service Contracts: Include copies of maintenance agreements with name and

telephone number of service agent. H. Warranties and Bonds: Include copies of warranties and bonds and lists of circumstances

and conditions that would affect validity of warranties or bonds.

1. Include procedures to follow and required notifications for warranty claims. PART 3 - EXECUTION 3.1 MANUAL PREPARATION

A. Operation and maintenance Documentation Directory: Prepare a separate manual that provides an organized reference to emergency, operation, and maintenance manuals.

B. Emergency Manual: Assemble a complete set of emergency information indicating

procedures for use by emergency personnel and by Owner’s operating personnel for types of emergencies indicated.

C. Product Maintenance Manual: Assemble a complete set of maintenance data indicating care

and maintenance of each product, material, and finish incorporated into the Work. D. Operation and Maintenance Manuals: Assemble a complete set of operation and

maintenance data indicating operation and maintenance of each system, subsystem, and piece of equipment not part of a system.

1. Engage a factory-authorized service representative to assemble and prepare

information for each system, subsystem, and piece of equipment not part of a system.

2. Prepare a separate manual for each system and subsystem, in the form of an

instructional manual for use by Owner’s operating personnel.

E. Manufacturer's Data: Where manuals contain manufacturers’ standard printed data, include only sheets pertinent to product or component incorporated into the Work. Mark each sheet to identify each product or component incorporated into the Work. Where more than one item is included, identify each item using appropriate references from Contract Documents. Identify only data or items that are applicable to the Work and delete (clearly mark-out) references to information not applicable.

1. Supplementary Text: If manufacturer's standard printed data is not available and

where the information is necessary for proper operation and maintenance of equipment or systems, or it is necessary to provide additional information, prepare written text to provide information.

a. Organize in a consistent format with separate headings for different procedures

and in a logical sequence of instruction for operating or maintenance procedure.

F. Drawings: Provide specially prepared drawings to supplement manufacturer's printed data to illustrate the relationship of component parts of equipment or systems, or to illustrate control sequence and flow diagrams. Coordinate these drawings with information contained in record Drawings to ensure correct illustration of completed installation.

1. Do not use original Project Record Documents as part of operation and maintenance

manuals. 3.2 DEMONSTRATION AND TRAINING

A. Instruction: Instruct Owner's personnel in operation, adjustment, and maintenance of

Page 79: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 2013 Logan Fontenelle- Chiller Procurement

RDH Engineering, Inc. 01820 - 8

products, equipment, systems, and subsystems. Provide instruction at mutually agreed upon place and time before Final Inspection. Provide a minimum of 24 hours of training across three operating shifts of Owner’s operations personnel.

1. For equipment that requires seasonal operation, provide similar instruction during

other seasons. 2. Schedule training with Owner with not less than 14 days’ advance notice. 3. Coordinate instructor, including providing notification of dates, times, length of

instruction, and course content.

B. Program Structure: Develop an instruction program that includes individual training modules for each system and equipment not part of a system, as required by individual Specification Sections. For each training module, develop a learning objective and teaching outline.

1. Include instruction for the following:

a. System design and operational philosophy. b. Review of documentation. c. Operations. d. Adjustments. e. Troubleshooting. f. Emergency procedures. g. Maintenance. h. Repair.

END OF SECTION 01820

Page 80: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 13 Logan Fontenelle- Chiller Procurement

ROTARY-SCREW WATER CHILLERS 15626 - 1 RDH Engineering Project # 116-13-01

SECTION 15626 - ROTARY-SCREW WATER CHILLERS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes: 1. Packaged, air-cooled chillers.

1.2 SUBMITTALS

A. Product Data: For each type of product indicated. Include refrigerant, rated capacities, operating characteristics, furnished specialties, and accessories.

B. Shop Drawings: Include plans, elevations, sections, details, and attachments to other work.

C. Certificates: For certification required in "Quality Assurance" Article.

D. Startup service reports.

E. Operation and maintenance data.

F. Warranty.

1.3 QUALITY ASSURANCE

A. ARI Certification: Certify chiller according to ARI 550 and ARI 590 certification program(s).

B. ARI Rating: Rate chiller performance according to requirements in ARI 550/590.

C. ASHRAE/IESNA Compliance: Applicable requirements in ASHRAE/IESNA 90.1-2004

D. ASME Compliance: Fabricate and label chiller to comply with ASME Boiler and Pressure Vessel Code: Section VIII, Division 1, and include an ASME U-stamp and nameplate certifying compliance.

E. Comply with NFPA 70.

F. Comply with requirements of UL and UL Canada and include label by a qualified testing agency showing compliance.

1.4 WARRANTY

A. Special Warranty: Manufacturer's standard form in which manufacturer agrees to repair or replace components of chillers that fail in materials or workmanship within specified warranty period.

Page 81: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 13 Logan Fontenelle- Chiller Procurement

ROTARY-SCREW WATER CHILLERS 15626 - 2 RDH Engineering Project # 116-13-01

1. Extended warranties include, but are not limited to, the following:

a. Complete chiller including refrigerant and oil charge. b. Parts and labor. c. Loss of refrigerant charge for any reason.

2. Warranty Period: Five years from date of Substantial Completion.

PART 2 - PRODUCTS

2.1 PACKAGED, AIR-COOLED CHILLERS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

B. Basis-of-Design Product: Subject to compliance with requirements, provide product indicated on Drawings or comparable product by one of the following or Voluntary Alternate as specified.

1. Daikin 2. Dunham-Bush. 3. Trane; a division of American Standard. 4. YORK International Corporation. 5. SMARDT.

C. Description: Factory-assembled and run-tested chiller complete with base and frame, condenser casing, compressors, compressor motors and motor controllers, evaporator, condenser coils, condenser fans and motors, electrical power, controls, and accessories.

D. Fabricate base, frame, and attachment to chiller components strong enough to resist chiller movement during a seismic event when chiller base is anchored to field support structure.

E. Cabinet:

1. Base: Galvanized-steel base extending the perimeter of chiller. Secure frame, compressors, and evaporator to base to provide a single-piece unit.

2. Frame: Rigid galvanized-steel frame secured to base and designed to support cabinet, condenser, control panel, and other chiller components not directly supported by base.

3. Casing: Galvanized steel. 4. Finish: Coat base, frame, and casing with a corrosion-resistant coating capable of

withstanding a 500-hour salt-spray test according to ASTM B 117. 5. Sound-reduction package designed to reduce sound level without affecting performance

and consisting of the following: Sound package shall reduce rated noise by a minimum of 6 db.

a. Acoustic enclosure around compressors. Discharge lines. b. Reduced-speed fans with acoustic treatment.

Page 82: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 13 Logan Fontenelle- Chiller Procurement

ROTARY-SCREW WATER CHILLERS 15626 - 3 RDH Engineering Project # 116-13-01

6. Security Package: Provide removable louvered panels with fasteners for additional protection of compressors, evaporator, and condenser coils without inhibiting service access. Finish to match cabinet. Panels shall protect unit condenser coils from hail damage.

F. Compressors:

1. Description: Positive displacement, hermetically sealed. 2. Casing: Cast iron, precision machined for minimum clearance about periphery of rotors. 3. Rotors: Manufacturer's standard one- or two-rotor design. 4. Each compressor provided with suction and discharge shutoff valves, crankcase oil

heater, and suction strainer.

G. Service: Easily accessible for inspection and service.

H. Capacity Control: On-off compressor cycling and modulating slide-valve assembly or port unloaders combined with hot-gas bypass, if necessary, to achieve performance indicated.

1. Maintain stable operation throughout range of operation. Configure to achieve most energy-efficient operation possible.

2. Operating Range: From 100 to 20 percent of design capacity. 3. Condenser-Air Unloading Requirements over Operating Range: Drop-in entering

condenser-air temperature of 5 deg F drop for each 10 percent in capacity reduction. 4. For units equipped with a variable frequency controller, capacity control shall be both

"valveless" and "stepless," requiring no slide valve or capacity-control valve(s) to operate at reduced capacity.

I. Oil Lubrication System: Consisting of pump if required, filtration, heater, cooler, factory-wired power connection, and controls.

1. Provide lubrication to bearings, gears, and other rotating surfaces at all operating, startup, shutdown, and standby conditions including power failure.

2. Thermostatically controlled oil heater properly sized to remove refrigerant from oil. 3. Factory-installed and pressure-tested piping with isolation valves and accessories. 4. Oil compatible with refrigerant and chiller components. 5. Positive visual indication of oil level.

J. Vibration Control:

1. Vibration Balance: Balance chiller compressors and drive assemblies to provide a precision balance that is free of noticeable vibration over the entire operating range.

2. Isolation: Mount individual compressors on vibration isolators.

K. Compressor Motors:

1. Hermetically sealed and cooled by refrigerant suction gas. 2. High-torque, induction type with inherent thermal-overload protection on each phase.

L. Compressor Motor Controllers: 1. Star-Delta, Reduced-Voltage Controller: NEMA ICS 2, closed transition, or solid state.

Page 83: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 13 Logan Fontenelle- Chiller Procurement

ROTARY-SCREW WATER CHILLERS 15626 - 4 RDH Engineering Project # 116-13-01

2. Variable Frequency Controller:

a. Motor controller shall be factory mounted and wired on the chiller to provide a single-point, field-power termination to the chiller and its auxiliaries.

b. Description: NEMA ICS 2; listed and labeled as a complete unit and arranged to provide variable speed by adjusting output voltage and frequency.

c. Enclosure: Unit mounted, NEMA 250, Type 3R, with hinged full-front access door with lock and key.

d. Integral Disconnecting Means: Door-interlocked, NEMA AB 1, instantaneous-trip circuit breaker with lockable handle. Minimum withstand rating shall be as required by electrical power distribution system, but not less than [42,000] [65,000] [100,000] A.

e. Technology: Pulse width modulated (PWM) output suitable for constant or variable torque loads.

f. Motor current at start shall not exceed the rated load amperes, providing no electrical inrush.

M. Refrigerant Circuits:

1. Refrigerant Type: R-134a. Classified as Safety Group A1 according to ASHRAE 34. 2. Refrigerant Compatibility: Chiller parts exposed to refrigerants shall be fully compatible

with refrigerants, and pressure components shall be rated for refrigerant pressures. 3. Refrigerant Circuit: Each shall include an electronic-expansion valve, refrigerant

charging connections, a hot-gas muffler, compressor suction and discharge shutoff valves, a liquid-line shutoff valve, a replaceable-corefilter-dryer, a sight glass with moisture indicator, a liquid-line solenoid valve, and an insulated suction line.

4. Pressure Relief Device:

a. Comply with requirements in ASHRAE 15 and in applicable portions of ASME Boiler and Pressure Vessel Code: Section VIII, Division 1.

b. ASME-rated, spring-loaded pressure relief valve; single- or multiple-reseating type.

N. Evaporator:

1. Description: Shell-and-tube design.

2. Retain one or both of first two subparagraphs below. Indicate evaporator type on Drawings if Project requirements for multiple chillers differ. Evaporator types vary among chiller manufacturers and models. Retaining a specific type may exclude some listed manufacturers. Verify availability of type with manufacturer.

a. Flooded type with fluid flowing through tubes and refrigerant flowing around

tubes within the shell.

3. Code Compliance: Tested and stamped according to ASME Boiler and Pressure Vessel Code: Section VIII, Division 1.

4. Shell Material: Carbon steel. 5. Shell Heads: Removable carbon-steel heads located at each end of the tube bundle.

Page 84: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 13 Logan Fontenelle- Chiller Procurement

ROTARY-SCREW WATER CHILLERS 15626 - 5 RDH Engineering Project # 116-13-01

6. Fluid Nozzles: Terminated with mechanical-coupling flanged end connections for connection to field piping.

7. Tube Construction: Individually replaceable copper tubes with enhanced fin design, expanded into tube sheets.

8. Heater: Factory-installed and -wired electric heater with integral controls designed to protect the evaporator to minus 20 deg F.

O. Air-Cooled Condenser:

1. Plate-fin coil with integral subcooling on each circuit, rated at 450 psig.

a. Construct coil casing of galvanized or stainless steel. b. Construct coils of copper tubes mechanically bonded to aluminum fins. c. Hail Protection: Provide condenser coils with louvers, baffles, or hoods to protect

against hail damage.

2. Fans: Direct-drive propeller type with statically and dynamically balanced fan blades, arranged for vertical air discharge. Provide with VFD and associated controls.

3. Fan Motors: Totally enclosed nonventilating (TENV) or totally enclosed air over (TEAO) enclosure, with permanently lubricated bearings. Equip each motor with overload protection integral to either the motor or chiller controls.

4. Fan Guards: Steel safety guards with corrosion-resistant coating.

P. Electrical Power:

1. Factory-installed and -wired switches, motor controllers, transformers, and other electrical devices necessary shall provide a single-point, field-power connection to chiller.

2. House in a unit-mounted, NEMA 250, Type 3R enclosure with hinged access door with lock and key or padlock and key.

3. Wiring shall be numbered and color-coded to match wiring diagram. 4. Install factory wiring outside of an enclosure in a raceway. 5. Field-power interface shall be to wire lugs NEMA AB 1, instantaneous-trip circuit

breaker with lockable handle.

a. Disconnect means shall be interlocked with door operation. b. Minimum withstand rating shall be as required by electrical power distribution

system, but not less than 65,000 KVA.

6. Provide branch power circuit to each motor and to controls with one of the following disconnecting means:

a. NEMA KS 1, heavy-duty, fusible switch with rejection-type fuse clips rated for fuses. Select and size fuses to provide Type 2 protection according to IEC 60947-4-1.

b. NEMA AB 1, motor-circuit protector (circuit breaker) with field-adjustable, short-circuit-trip set point.

7. Provide each motor with overcurrent protection. 8. Overload relay sized according to UL 1995 or an integral component of chiller control

microprocessor.

Page 85: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 13 Logan Fontenelle- Chiller Procurement

ROTARY-SCREW WATER CHILLERS 15626 - 6 RDH Engineering Project # 116-13-01

9. Phase-Failure and Undervoltage Relays: Solid-state sensing with adjustable settings. 10. Provide power factor correction capacitors to correct power factor to 0.90 at full load. 11. Control Transformer: Unit-mounted transformer with primary and secondary fuses and

sized with enough capacity to operate electrical load plus spare capacity.

a. Power unit-mounted controls where indicated. b. Power unit-mounted, ground fault interrupt (GFI) duplex receptacle.

12. Control Relays: Auxiliary and adjustable time-delay relays. 13. For chiller electrical power supply, indicate the following:

a. Current and phase to phase for all three phases. b. Voltage, phase to phase, and phase to neutral for all three phases. c. Three-phase real power (kilowatts). d. Three-phase reactive power (kilovolt amperes reactive). e. Power factor. f. Running log of total power versus time (kilowatt-hours). g. Fault log, with time and date of each.

Q. Controls:

1. Standalone and microprocessor based. 2. Enclosure: Share enclosure with electrical power devices or provide a separate

enclosure for remote mounting in the field. 3. Operator Interface: Multiple-character digital or graphic display with dynamic update of

information and with keypad or touch-sensitive display located on front of control enclosure. In either imperial or metric units, display the following information:

a. Date and time. b. Operating or alarm status. c. Operating hours. d. Outdoor-air temperature if required for chilled-water reset. e. Temperature and pressure of operating set points. f. Entering and leaving temperatures of chilled water. g. Refrigerant pressures in evaporator and condenser. h. Saturation temperature in evaporator and condenser. i. No cooling load condition. j. Elapsed time meter (compressor run status). k. Pump status. l. Antirecycling timer status. m. Percent of maximum motor amperage. n. Current-limit set point. o. Number of compressor starts.

4. Control Functions:

a. Manual or automatic startup and shutdown time schedule.

Page 86: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 13 Logan Fontenelle- Chiller Procurement

ROTARY-SCREW WATER CHILLERS 15626 - 7 RDH Engineering Project # 116-13-01

b. Entering and leaving chilled-water temperatures, control set points, and motor load limits. Chilled-water leaving temperature shall be reset based on return-water temperature.

c. Current limit and demand limit. d. External chiller emergency stop. e. Antirecycling timer. f. Automatic lead-lag switching. g. Variable evaporator flow. h. Thermal storage.

5. Manually Reset Safety Controls: The following conditions shall shut down chiller and require manual reset:

a. Low evaporator pressure or high condenser pressure. b. Low chilled-water temperature. c. Refrigerant high pressure. d. High or low oil pressure. e. High oil temperature. f. Loss of chilled-water flow. g. Control device failure.

6. Trending: Capability to trend analog data of up to five parameters simultaneously over an adjustable period and frequency of polling.

7. Security Access: Provide electronic security access to controls through identification and password with at least three levels of access: view only; view and operate; and view, operate, and service.

8. Control Authority: At least four conditions: Off, local manual control at chiller, local automatic control at chiller, and automatic control through a remote source.

9. BAS Interface: Factory-installed hardware and software to enable the BAS to monitor, control, and display chiller status and alarms.

a. Hardwired Points:

1) Monitoring: On-off status, common trouble alarm electrical power demand (kilowatts).

2) Control: On-off operation, chilled-water, discharge temperature set-point adjustment.

b. ASHRAE 135 (BACnet) Industry-accepted, open-protocol communication interface with the BAS shall enable the BAS operator to remotely control and monitor the chiller from an operator workstation. Control features and monitoring points displayed locally at chiller control panel shall be available through the BAS.

R. Insulation:

1. Material: Closed-cell, flexible elastomeric, thermal insulation complying with ASTM C 534, Type I for tubular materials and Type II for sheet materials.

2. Thickness: 3/4 inch. 3. Factory-applied insulation over cold surfaces of chiller components.

Page 87: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 13 Logan Fontenelle- Chiller Procurement

ROTARY-SCREW WATER CHILLERS 15626 - 8 RDH Engineering Project # 116-13-01

a. Adhesive: As recommended by insulation manufacturer and applied to 100 percent of insulation contact surface. Seal seams and joints.

4. Apply protective coating to exposed surfaces of insulation to protect insulation from weather.

S. Accessories:

1. Factory-furnished, chilled-water flow switches for field installation. 2. Individual compressor suction and discharge pressure gages with shutoff valves for each

refrigerant circuit. 3. Factory-furnished neoprene or spring isolators for field installation.

T. Capacities and Characteristics: See attached Air Cooled Chiller schedule.

2.2 SOURCE QUALITY CONTROL

A. Perform functional tests of chillers before shipping.

B. Factory test and inspect evaporator and condenser according to ASME Boiler and Pressure Vessel Code: Section VIII, Division 1.

C. For chillers located indoors, rate sound power level according to ARI 575.

D. For chillers located outdoors, rate sound power level according to ARI 370.

PART 3 - EXECUTION

3.1 CHILLER INSTALLATION

A. Charge chiller with refrigerant and fill with oil if not factory installed.

B. Install separate devices furnished by manufacturer and not factory installed.

3.2 STARTUP SERVICE

A. Engage a factory-authorized service representative to perform startup service.

1. Complete installation and startup checks according to manufacturer's written instructions. 2. Verify that refrigerant charge is sufficient and chiller has been leak tested. 3. Verify that pumps are installed and functional. 4. Verify that thermometers and gages are installed. 5. Operate chiller for run-in period. 6. Check bearing lubrication and oil levels. 7. For chillers installed indoors, verify that refrigerant pressure relief device is vented

outdoors. 8. Verify proper motor rotation.

Page 88: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

Bellevue Public School District December 13 Logan Fontenelle- Chiller Procurement

ROTARY-SCREW WATER CHILLERS 15626 - 9 RDH Engineering Project # 116-13-01

9. Verify static deflection of vibration isolators, including deflection during chiller startup and shutdown.

10. Verify and record performance of fluid flow and low-temperature interlocks for evaporator and condenser.

11. Verify and record performance of chiller protection devices. 12. Test and adjust controls and safeties. Replace damaged or malfunctioning controls and

equipment.

B. Inspect field-assembled components, equipment installation, and piping and electrical connections for proper assembly, installation, and connection.

C. Prepare test and inspection startup reports.

END OF SECTION 15626

Page 89: Request for Proposal Chiller Procurement Package for · Request for Proposal Chiller Procurement Package for ... Director of Facilities and Maintenance Bellevue Public Schools 1600

CHILLER - AIR COOLED COMPRESSOR

CHILLED WATER DATA DATA CONDENSER DATA CONNECTED LOAD

MARK

NETCAP MBH GPM EWT F LWT F

MAXPD

FT H2OMINEER NO

COMPTYPE

REFTYPE

FANNO

FANHP

AMBTEMP

F V MOP RLA PH BASIS OF DESIGN WEIGHTMECHNOTES

(LBS)

ACC-1 4522.8 955.4 55 45 15 10.9 2 SCREW R-134A 24 1.4 95 460 800 726 3 DAIKIN AWS400CDP 26649 1-9

MECHANICAL NOTES:1. COMPRESSOR STARTER - VFD2. IPLV- 19.2 EER3. PROVIDE WITH DISCONNECT SWITCH4. SELECT CHILLER AT 33% PROPYLENE GLYCOL5. PROVIDE WITH LOW AMBIENT CONTROL TO 35°F6. PROVIDE WITH SOUND ATTENUATION PACKAGE7. UNIT DIMENSIONS: 496 IN LENGTH X 100 IN HEIGHT X 88 IN WIDTH8. PROVIDE WITH SINGLE POINT POWER CONNECTION WITH CIRCUIT BREAKERS9. PROVIDE WITH 1 YEAR PARTS AND LABOR WARRANTY

NOTE:

The existing chiller electrical service feeder is (3) sets, each consisting of 3 #400MCM (CU) & #3/0 (CU) Grd in 3”C., which limits the new chiller single point power connection to a maximum MCA of 1005A at 480V 3 Phase. The existing fusible disconnect switch which serves the existing chiller is 1200A/3P, 480V, fused at 1000A which limits the maximum fuse MOP to 1000A. All bids shall include equipment which complies with these limitations and shall be equipped with single point power connection lugs able to terminate the existing feeder conductors.

MSCHED CHILLER-AIR COOLED.xls12/20/2013 1:05 PM