Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Space Applications Center | Indian Space Research Organization | Govt. of India
REQUEST
FOR
PROPOSAL
Payload Integration
and testing Fixture
Space Applications Center,
Ahmedabad 380015
Document No:
CS3-00-TEL-PIF-001-RF1-R0
Space Applications Center | Indian Space Research Organization | Govt. of India
This page is intentionally left blank
Space Applications Center | Indian Space Research Organization | Govt. of India
CONTENTS
1. INTRODUCTION ...............................................................................................................................1
2. SCOPE OF WORK .............................................................................................................................6
3. RESPONSE TO THE RFP .................................................................................................................7
4. SPECIFICATION ...............................................................................................................................8
6. PERFORMANCE AND FUNCTIONALITY TEST ..................................................................... 10
7. CONTAINERS FOR DISPATCH .................................................................................................. 10
8. INSTALLATION AND COMMISSIONING ................................................................................ 10
9. WARRANTY .................................................................................................................................... 10
10. DELIVERABLES ......................................................................................................................... 10
11. DELIVERY SCHEDULE ............................................................................................................ 11
Annexure 1 ................................................................................................................................................ 12
Space Applications Center | Indian Space Research Organization | Govt. of India
This page is intentionally left blank
Space Applications Center | Indian Space Research Organization | Govt. of India
Page | 1
1. INTRODUCTION
Space Applications Center is interested in developing a payload integration and test fixture for the
alignment and testing of state of art electro-optic payloads in axis horizontal and axis vertical
configuration. This fixture would comprise of structure with automation for maneuvering of payload
during various stage of integration and testing. These items will also expose to vacuum during
development of payload.
PAYLOAD INTEGRATION FIXTURE
Payload is of cylindrical shape having three lugs. Overall dimensions and C.G of payload is shown in
Figure-1. Total mass of the payload is 700 Kg. Payload integration fixture is required to integrate it in
axis vertical condition and to test in axis horizontal condition. Configuration of payload with integration
fixture is shown in figure-2 (in Axis Horizontal condition). Axis definition is also shown in figure-2
Figure-2 Payload with Payload integration fixture (Only Schematic and not for fabrication)
Figure-1 CG of EOM and Overall size of Payload
2850 mm
Dia
14
40
mm
1000mm
(TBD)
C.G.
Pitch (X)
Roll (Y)
Yaw (Z)
Space Applications Center | Indian Space Research Organization | Govt. of India
Page | 2
Tentative configuration of payload integration fixture is shown in figure-2 to 6; vendor may suggest his
configuration at the time of submitting quote. CAD model of configuration shown in fig-2 to 6 can
be provided to vendor upon request, (this is not for fabrication purpose).
+1.5° -1.5°
P/L mounting plane
Figure-3 Top view: Payload with Payload integration fixture
(Only Schematic and not for fabrication)
P/L CG
plane
Space Applications Center | Indian Space Research Organization | Govt. of India
Page | 3
Ø 1750 mm(TBD)
30
00
mm
max
(TB
D)
((((
99
(ten
4400mm max (TBD)
Figure-4 Front view: Payload with Payload integration fixture
(Only Schematic and not for fabrication)
4700mm (TBD)
Figure-5 Front view: Payload with Payload integration fixture
(Only Schematic and not for fabrication)
Space Applications Center | Indian Space Research Organization | Govt. of India
Page | 4
Figure-6 Sectional view: Payload mounting interface with Payload integration fixture
(Only Schematic and not for fabrication)
Space Applications Center | Indian Space Research Organization | Govt. of India
Page | 5
Figure-7 Payload to Payload integration fixture mounting interface
PCD DIA.
1300(TBD)
Space Applications Center | Indian Space Research Organization | Govt. of India
Page | 6
2. SCOPE OF WORK
The outline of scope of work to be carried out by the vendor is as under:
1. Review of the requirements and specifications of proposed payload integration fixture with
automation.
2. Propose design and implementation plan including details of hardware design, interface
methodology for mounting payload in form of PDR (preliminary design review) followed by
CDR (Critical design review), this will be reviewed by SAC/ISRO for clearing it for further
action. Vendor shall incorporate the suggestions given by SAC/ISRO during these review.
3. Procurement of the raw material, Z-stages, linear actuators, Jack, control systems, power
supply, display, switches, harness & its routing, any other accessory or tooling will be in scope
of vendor.
4. Fabrication and assembly of the payload integration fixture including automation elements.
5. Demonstrate performance to meet the specifications at vendor's premises for pre-dispatch
clearance.
6. Packing in a suitable container and shipment to SAC/ISRO.
7. Installation and commissioning at SAC/ISRO.
8. Obtain completion certificate for release of payment.
9. Maintaining the installation up to stipulated period of warranty.
10. Supplier shall ensure that all instruments operating on electrical power meet the requirements of electrical safety regulation.
11. Whole fixture should have electrical grounding to earth conductively; all electrical instrumentations should have standard 3 pin power interface with its body connected to Earth.
12. Appropriate protection mechanism and scheme shall build to prevent over-current, over-voltage, over-heating, etc. Provide scheme for safety measures to be implemented.
13. Electrical Cable Wire type should be Teflon / Kapton and vacuum qualified. 14. Operating and troubleshooting manuals, sketches, drawings, and electric circuit and interface
diagrams should be provided in a separate document.
15. Fabrication and delivery of payload mounting ring is in the scope of vendor (refer fig-6 for payload mounting ring).
16. The vendor should submit all design calculations for the structural, motion and drive elements. 17. The vendor shall have selected the brought out components from reliable and proven sources
with COC, to ensure its quality and reliability.
18. The fabrication materials should have test reports, with COC. 19. The vendor should demonstrate their Quality Management System for design and well as
fabrication during PDR.
20. The vendor should perform the Failure Mode Effect Analysis for the fixture design, and work out payload safety measures in case of fixture failures.
Space Applications Center | Indian Space Research Organization | Govt. of India
Page | 7
3. RESPONSE TO THE RFP
Vendors should provide a detailed offer in response to the request for proposal for the proposed
automation. The offer should contain the following information:
4.1 Vendor should quote in two parts (one is technical bid + un-priced commercial bid and second
is commercial bid with price).As regards to detail instruction on two part bid requirement,
please refer separate instructions attached with this tender.
4.2 Un-priced commercial bid should be attached with the technical bid.
4.3 All the literature should be in English Language only.
4.4 Compliance statement to all the specifications of each item as per this RFP. Offers without
compliance sheet may not be considered during tendering process. Sample compliance table is
shown in table-1
4.5 Introduction by the vendor including technical capabilities relevant to proposed development. Vendor may add clientele details where similar installations are made.
4.6 Work plan for fabrication of the proposed items. 4.7 Previous automation and fabrication carried out of a similar nature. 4.8 Delivery schedule.
Space Applications Center | Indian Space Research Organization | Govt. of India
Page | 8
4. SPECIFICATION
Technical specification for optical payload integration fixture:
1) Size of the fixture:
4700 mm length (max) X 4400 mm width (max) X 3000 mm height (max).
2) Rotation of Axis: Pitch(X)
Rotation: ± 1.5 degree about pitch axis (automation).
Resolution: ≤ 1 arc second
Speed: 10Arc second/second (Typical)
3) Rotation of Axis: Roll axis(Y)
Rotation: -2 to +90 Degree rotation of payload about roll axis form axis vertical to axis Horizontal,
Jack-A shall have capability to rotate payload about roll axis. (Refer fig 5 for details of angles), It shall
have sufficient range to clear all appendages of fixture while rotating -2 to + 90 degree. Axis of rotation
shall be from C.G, also there shall be provision to adjust axis of rotation to pass it from C.G.
Resolution and Range: 1 arc second over -1.5 to +1.5-degree range, refer fig-3. And 0.5 Degree
over -2 to + 90 degree range.
Speed: 10Arc second/second (Typical) over -1.5 to +1.5 degree range, 20degree/minute (typical)
over -2 to + 90 degree range
These rotations shall be motorized. Noiseless and smooth rotation and jerk free start and stop are to be
ensured.
4) Rotation of Axis: - Yaw (Z)
Resolution and range: 1 arc second over -1.5 to +1.5 degree range, refer fig-3. And 0.5 Degree
over 0 to 360-degree range
Speed: 10Arc second/second (Typical) over -1.5 to +1.5-degree range, 20 degree/minute
(typical) over -0 to 360-degree range
This rotation shall be motorised. It shall have suitable ball/guide bearings along with ratchet
arrangement for locking at 0°, 90, 180°, 270° angle. Noiseless and smooth rotation and jerk free start
and stop are to be ensured.
5) Orthogonality among all three axis ≤ 1 Degree
6) Load capacity of the fixture ≥ 750 kgs.
7) Total mass of the payload integration fixture (without payload) ≈ 1000 kgs.
8) Control panel and display: Control panel shall be provided for electrical supply to the system and
display unit of not smaller than 9 inch (typical) touch screen for operating functionality of the system.
Space Applications Center | Indian Space Research Organization | Govt. of India
Page | 9
Display unit shall show absolute current positions (w.r.t home reference position). It shall be able to
control all stage and actuator independently.
9) Encoders: Suitable encoders shall be used for feedback of actual position of tilt in three axes (i.e.
Pitch, Roll and Yaw).
10) Locking arrangement: All rotational axis shall have locking arrangement to lock before testing
of the payload after final position is achieved.
11) Material of construction: Base frame structure shall be made from stainless steel (preferably SS
304/316)/ aluminum alloy, it shall be non-corrosive.
12) Fixture mounting foot print: Vendor shall propose fixture mounting foot print to SAC, which
will be reviewed by SAC for clearing it for fabrication.
13) Footprint for payload mounting: Footprint for payload mounting on to fixture is shown in figure-
6. Flatness required on payload to fixture mounting interface shall be better than 50 microns.
Appropriate spherical ball joint spacer shall be provided to accommodate flatness error.
14) Cutout: Fixture shall have 1135 mm (typical) inside hole on payload foot print area for various
payload element integration\testing, while mounted of payload fixture, refer figure-4.
15) Lifting brackets: Fixture shall have provision to lift (preferably four point lifting brackets) for
easy handling of the fixture.
16) Limit switch: Fixture shall have limit switches for rotational axis Pitch and Roll axis.
17) Fixture rigidity: No noticeable deformation (change in flatness of payload mounting interface shall
be < 100micron with payload mass) should be observed when a load (payload mass) is applied on
platform. To be demonstrated using a 750 kg load on the payload mounting interface of fixture.
18) Lubrication: sealed non-grease lubricants for the moving subassemblies, shall not degas in vacuum
environment (1E-6 mbar).
19) Clean room and Vacuum compatibility: Entire system shall comply with the requirements of a
clean room class 100,000 and vacuum level of 1E-6 mbar.
20) Aesthetics/Safety: The equipment shall have good aesthetic look. The equipment should be safe in
all aspects. Sharp corners, open electrical points, exposed moving parts will all be adequately taken
care of in design.
21) Temperature limit: Entire system shall comply with temperature limits for operating (22 ± 15°C)
and non-operating (-10°C to 50°C) conditions.
22) Cables with feed through connector: Necessary two sets of cables (power supply cable, data
cables, etc) shall have minimum 5m length with feed through connectors (preferably LEMO, plug
in type) for operating fixture from outside of thermos vacuum chamber (fixture inside thermos
vacuum chamber). Electrical Cable Wire type should be Teflon / Kapton and vacuum compatible.
23) Jack-B: Refer figure-5 for configuration of it. It shall have lifting range of ±50mm, with resolution
of ≤ 1mm. This lifting shall be motorized, with the option of operating it in pair of two or Four
together.
24) Load sensor: load sensors shall be placed at each support locations of payload integration fixture
(at four locations below ball joints). Measurement range of load shall be capable to take care of
payload weight +payload integration fixture weight.
Space Applications Center | Indian Space Research Organization | Govt. of India
Page | 10
25) GUI: GUI shall display all load sensor results, all z stages displacement\angle results, position of
jack-A and Jack B. There shall be provision to take all stage to home position, also when power is
off, all stage position shall retain to last commended position, and it shall start from last position
upon powering on. GUI shall have provision for both absolute and incremental commanding for
all stages and actuators.
26) Wireless remote: GUI mentioned above shall be loaded in mobile handheld wireless unit with
9inch (Typical) display.
27) Payload mounting ring: Suitable payload mounting ring shall be design and deliver by vendor
along with payload integration fixture. (Refer figure-6 for schematic and section view of payload
mounting ring).
5. DESIGN REVIEW: Before start of fabrication, vendor needs to present design to SAC team in form of PDR (preliminary design review) and (CDR) Critical design review, all suggestion made
by SAC needs to be incorporate in design. Written approval of SAC is required before start of
fabrication.
6. PERFORMANCE AND FUNCTIONALITY TEST After fabrication and assembly at vendor's premises, payload integration fixture will undergo
functionality tests. These tests will include noise during operation, smoothness of rotation, and rigidity
of platform under dummy load. (Dummy load simulating mass and C.G of payload shall be arranged
by vendor, refer fig-1 for payload C.G details) These tests will be carried out in the presence of
SAC/ISRO appointed engineers at vendor's premises. If all the specifications are met, the hardware will
be cleared for dispatch to ISRO.
7. CONTAINERS FOR DISPATCH The container and packing of all the sub-systems shall be robust enough to survive the rigors of handling
and transportation between the vendor’s premises and ISRO. The manufacturer shall provide handling
and storage instructions for the deliverables.
8. INSTALLATION AND COMMISSIONING
The vendor shall be responsible for installation and commissioning of all the supplied items at SAC.
Vendor shall arrange all tools, accessories and man power necessary for installation. Performance and
acceptance tests shall be repeated as per section 5 and satisfactory performance of payload integration
fixture shall be ensured by the vendor to SAC for issuing of completion certificate necessary for release
of payment.
9. WARRANTY All the systems supplied by the vendor shall have on-site warranty period of 3 years from date of
installation. Included in the warranty will be provision for rectifying malfunctioning of sub systems,
breakdown and regular maintenance as required. System performance shall be guaranteed during this
period.
10. DELIVERABLES
Payload Integration fixture as per this RFP = 2 No.
Space Applications Center | Indian Space Research Organization | Govt. of India
Page | 11
Note - The vendor shall provide the details like specifications, model and make of all bought out
items like motors, encoders, controllers etc.
11. DELIVERY SCHEDULE
Order signing and acceptance T0
Proposal and presentation at SAC -PDR T0 + 1 month
Finalization of design (CDR) and clearance of fabrication
T0 + 2 months
Completion of fabrication T0 + 4 months
Acceptance testing and dispatch at vendors premises T0 + 4.5 months
Installation at SAC
T0 + 5 months
SAC have all rights for onsite inspection during development of fixture at vendor’s premises.
Note: Only vendors, who are confident to complete design with meeting indent specification in
first two attempt ( i.e. PDR and CDR) needs to submit quote. Vendor failing in completion of
design in first two attempt ( i.e PDR and CDR) will be disqualified and SAC will have rights to
cancel order.
Space Applications Center | Indian Space Research Organization | Govt. of India
Page | 12
Annexure 1
Table-1 Compliance matrix
(to be filled in by vendor)
Sr
No Parameter Specification
Vendor’s
compliance
(to be filled in by
vendor)
Compliance
(Yes/No)
(to be filled in
by vendor)
1 Size of the
fixture
4700 mm length (max) X 4400
mm width (max) X 3000 mm
height (max)
2 Rotation of Axis:
- pitch (X)
Rotation: ± 1.5 degree about
pitch axis (automation).
Resolution: ≤ 1 arc second
Speed: 10Arc second/second
(Typical)
3
Rotation of Axis:
- Roll axis (Y)
Rotation: -2 to +90 Degree
rotation of payload about roll
axis form axis vertical to axis
Horizontal, Jack-A shall have
capability to rotate payload
about roll axis. (Refer fig 5 for
details of angles), It shall have
sufficient range to clear all
appendages of fixture while
rotating -2 to + 90 degree. Axis
of rotation shall be from C.G,
also there shall be provision to
adjust axis of rotation to pass it
from C.G.
Resolution and Range: 1 arc
second over -1.5 to +1.5-degree
range, refer fig-3. And 0.5
Degree over -2 to + 90 degree
range.
Speed: 10Arc second/second
(Typical) over -1.5 to +1.5
degree range, 20degree/minute
(typical) over -2 to + 90 degree
range
These rotations shall be
motorized. Noiseless and
smooth rotation and jerk free
start and stop are to be ensured.
4 Rotation of Axis:
- Yaw (Z)
Resolution and range: 1 arc
second over -1.5 to +1.5 degree
range, refer fig-3. And 0.5
Degree over 0 to 360-degree
range
Speed: 10Arc second/second
(Typical) over -1.5 to +1.5-degree
Space Applications Center | Indian Space Research Organization | Govt. of India
Page | 13
range, 20 degree/minute (typical)
over -0 to 360-degree range
This rotation shall be motorised. It
shall have suitable ball/guide
bearings along with ratchet
arrangement for locking at 0°, 90,
180°, 270° angle. Noiseless and
smooth rotation and jerk free start
and stop are to be ensured.
5
Orthogonality
among all three
axis
≤ 1 Degree
6 Load capacity of
the fixture ≥ 750 kgs
7
Total mass of the
payload
integration
fixture (without
payload)
≈ 1000kgs.
8 Control panel
and display
Control panel shall be provided for
electrical supply to the system and
display unit of not smaller than 9
inch (typical) touch screen for
operating functionality of the
system. Display unit shall show
absolute current positions (w.r.t
home reference position). It shall be
able to control all stage and actuator
independently.
9 Encoders
Suitable encoders shall be used for
feedback of actual position of tilt in
three axes (i.e. Pitch, Roll and
Yaw).
10 Locking
arrangement
All rotational axis shall have
locking arrangement to lock before
testing of the payload after final
position is achieved.
11 Material of
construction:
Base frame structure shall be made
from stainless steel (preferably SS
304/316)/ aluminum alloy, it shall
be non corrosive.
12 Fixture mounting
foot print
Vendor shall propose fixture
mounting foot print to SAC, which
will be reviewed by SAC for
clearing it for fabrication
13
Footprint for
payload
mounting
Footprint for payload mounting on
to fixture is shown in figure-6.
Flatness required on payload to
fixture mounting interface shall be
better than 50 microns. Appropriate
spherical ball joint spacer shall be
provided to accommodate flatness
error.
14 Cut-out
Fixture shall have 1135 mm
(typical) inside hole on payload foot
print area for various payload
element integration\testing, while
Space Applications Center | Indian Space Research Organization | Govt. of India
Page | 14
mounted of payload fixture, refer
figure-4.
15 Lifting brackets
Fixture shall have provision to lift
(preferably four point lifting
brackets) for easy handling of the
fixture.
16 Limit switch Fixture shall have limit switches for
rotational axis Pitch and Roll axis.
17 Fixture rigidity
noticeable deformation (change in
flatness of payload mounting
interface shall be < 100micron with
payload mass) should be observed
when a load (payload mass) is
applied on platform. To be
demonstrated using a 750 kg load
on the payload mounting interface
of fixture.
18 Lubrication
sealed non-grease lubricants for the
moving subassemblies, shall not
degas in vacuum environment (1E-
6 mbar).
19
Clean room and
Vacuum
compatibility
Entire system shall comply with the
requirements of a clean room class
100,000 and vacuum level of 1E-6
mbar.
20 Aesthetics/Safety
The equipment shall have good
aesthetic look. The equipment
should be safe in all aspects. Sharp
corners, open electrical points,
exposed moving parts will all be
adequately taken care of in design.
21 Temperature limit
Entire system shall comply with
temperature limits for operating (22
± 15°C) and non-operating (-10°C
to 50°C) conditions.
Cables with feed
through connector
Necessary two sets of cables (power
supply cable, data cables, etc) shall
have minimum 5m length with feed
through connectors (preferably
LEMO, plug in type) for operating
fixture from outside of thermos
vacuum chamber (fixture inside
thermos vacuum chamber).
Electrical Cable Wire type should
be Teflon / Kapton and vacuum
compatible.
23 Jack-B
Refer figure-5 for configuration of
it. It shall have lifting range of
±50mm, with resolution of ≤ 1mm.
This lifting shall be motorized, with
the option of operating it in pair of
two or Four together.
24 Load sensor
load sensors shall be placed at each
support locations of payload
integration fixture (at four locations
below ball joints). Measurement
range of load shall be capable to
take care of payload weight
+payload integration fixture weight.
Space Applications Center | Indian Space Research Organization | Govt. of India
Page | 15
25 GUI
GUI shall display all load sensor
results, all z stages
displacement\angle results, position
of jack-A and Jack B. There shall be
provision to take all stage to home
position, also when power is off, all
stage position shall retain to last
commended position, and it shall
start from last position upon
powering on. GUI shall have
provision for both absolute and
incremental commanding for all
stages and actuators
26 Wireless remote
GUI mentioned above shall be
loaded in mobile handheld wireless
unit with 9inch (Typical) display.
27 Payload mounting
ring
Suitable payload mounting ring
shall be design and deliver by
vendor along with payload
integration fixture. (Refer figure-6
for schematic and section view of
payload mounting ring).