19
Space Applications Center | Indian Space Research Organization | Govt. of India REQUEST FOR PROPOSAL Payload Integration and testing Fixture Space Applications Center, Ahmedabad 380015 Document No: CS3-00-TEL-PIF-001-RF1-R0

REQUEST FOR PROPOSAL · 2018. 4. 27. · Obtain completion certificate for release of payment. 9. Maintaining the installation up to stipulated period of warranty. ... .As regards

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

  • Space Applications Center | Indian Space Research Organization | Govt. of India

    REQUEST

    FOR

    PROPOSAL

    Payload Integration

    and testing Fixture

    Space Applications Center,

    Ahmedabad 380015

    Document No:

    CS3-00-TEL-PIF-001-RF1-R0

  • Space Applications Center | Indian Space Research Organization | Govt. of India

    This page is intentionally left blank

  • Space Applications Center | Indian Space Research Organization | Govt. of India

    CONTENTS

    1. INTRODUCTION ...............................................................................................................................1

    2. SCOPE OF WORK .............................................................................................................................6

    3. RESPONSE TO THE RFP .................................................................................................................7

    4. SPECIFICATION ...............................................................................................................................8

    6. PERFORMANCE AND FUNCTIONALITY TEST ..................................................................... 10

    7. CONTAINERS FOR DISPATCH .................................................................................................. 10

    8. INSTALLATION AND COMMISSIONING ................................................................................ 10

    9. WARRANTY .................................................................................................................................... 10

    10. DELIVERABLES ......................................................................................................................... 10

    11. DELIVERY SCHEDULE ............................................................................................................ 11

    Annexure 1 ................................................................................................................................................ 12

  • Space Applications Center | Indian Space Research Organization | Govt. of India

    This page is intentionally left blank

  • Space Applications Center | Indian Space Research Organization | Govt. of India

    Page | 1

    1. INTRODUCTION

    Space Applications Center is interested in developing a payload integration and test fixture for the

    alignment and testing of state of art electro-optic payloads in axis horizontal and axis vertical

    configuration. This fixture would comprise of structure with automation for maneuvering of payload

    during various stage of integration and testing. These items will also expose to vacuum during

    development of payload.

    PAYLOAD INTEGRATION FIXTURE

    Payload is of cylindrical shape having three lugs. Overall dimensions and C.G of payload is shown in

    Figure-1. Total mass of the payload is 700 Kg. Payload integration fixture is required to integrate it in

    axis vertical condition and to test in axis horizontal condition. Configuration of payload with integration

    fixture is shown in figure-2 (in Axis Horizontal condition). Axis definition is also shown in figure-2

    Figure-2 Payload with Payload integration fixture (Only Schematic and not for fabrication)

    Figure-1 CG of EOM and Overall size of Payload

    2850 mm

    Dia

    14

    40

    mm

    1000mm

    (TBD)

    C.G.

    Pitch (X)

    Roll (Y)

    Yaw (Z)

  • Space Applications Center | Indian Space Research Organization | Govt. of India

    Page | 2

    Tentative configuration of payload integration fixture is shown in figure-2 to 6; vendor may suggest his

    configuration at the time of submitting quote. CAD model of configuration shown in fig-2 to 6 can

    be provided to vendor upon request, (this is not for fabrication purpose).

    +1.5° -1.5°

    P/L mounting plane

    Figure-3 Top view: Payload with Payload integration fixture

    (Only Schematic and not for fabrication)

    P/L CG

    plane

  • Space Applications Center | Indian Space Research Organization | Govt. of India

    Page | 3

    Ø 1750 mm(TBD)

    30

    00

    mm

    max

    (TB

    D)

    ((((

    99

    (ten

    4400mm max (TBD)

    Figure-4 Front view: Payload with Payload integration fixture

    (Only Schematic and not for fabrication)

    4700mm (TBD)

    Figure-5 Front view: Payload with Payload integration fixture

    (Only Schematic and not for fabrication)

  • Space Applications Center | Indian Space Research Organization | Govt. of India

    Page | 4

    Figure-6 Sectional view: Payload mounting interface with Payload integration fixture

    (Only Schematic and not for fabrication)

  • Space Applications Center | Indian Space Research Organization | Govt. of India

    Page | 5

    Figure-7 Payload to Payload integration fixture mounting interface

    PCD DIA.

    1300(TBD)

  • Space Applications Center | Indian Space Research Organization | Govt. of India

    Page | 6

    2. SCOPE OF WORK

    The outline of scope of work to be carried out by the vendor is as under:

    1. Review of the requirements and specifications of proposed payload integration fixture with

    automation.

    2. Propose design and implementation plan including details of hardware design, interface

    methodology for mounting payload in form of PDR (preliminary design review) followed by

    CDR (Critical design review), this will be reviewed by SAC/ISRO for clearing it for further

    action. Vendor shall incorporate the suggestions given by SAC/ISRO during these review.

    3. Procurement of the raw material, Z-stages, linear actuators, Jack, control systems, power

    supply, display, switches, harness & its routing, any other accessory or tooling will be in scope

    of vendor.

    4. Fabrication and assembly of the payload integration fixture including automation elements.

    5. Demonstrate performance to meet the specifications at vendor's premises for pre-dispatch

    clearance.

    6. Packing in a suitable container and shipment to SAC/ISRO.

    7. Installation and commissioning at SAC/ISRO.

    8. Obtain completion certificate for release of payment.

    9. Maintaining the installation up to stipulated period of warranty.

    10. Supplier shall ensure that all instruments operating on electrical power meet the requirements of electrical safety regulation.

    11. Whole fixture should have electrical grounding to earth conductively; all electrical instrumentations should have standard 3 pin power interface with its body connected to Earth.

    12. Appropriate protection mechanism and scheme shall build to prevent over-current, over-voltage, over-heating, etc. Provide scheme for safety measures to be implemented.

    13. Electrical Cable Wire type should be Teflon / Kapton and vacuum qualified. 14. Operating and troubleshooting manuals, sketches, drawings, and electric circuit and interface

    diagrams should be provided in a separate document.

    15. Fabrication and delivery of payload mounting ring is in the scope of vendor (refer fig-6 for payload mounting ring).

    16. The vendor should submit all design calculations for the structural, motion and drive elements. 17. The vendor shall have selected the brought out components from reliable and proven sources

    with COC, to ensure its quality and reliability.

    18. The fabrication materials should have test reports, with COC. 19. The vendor should demonstrate their Quality Management System for design and well as

    fabrication during PDR.

    20. The vendor should perform the Failure Mode Effect Analysis for the fixture design, and work out payload safety measures in case of fixture failures.

  • Space Applications Center | Indian Space Research Organization | Govt. of India

    Page | 7

    3. RESPONSE TO THE RFP

    Vendors should provide a detailed offer in response to the request for proposal for the proposed

    automation. The offer should contain the following information:

    4.1 Vendor should quote in two parts (one is technical bid + un-priced commercial bid and second

    is commercial bid with price).As regards to detail instruction on two part bid requirement,

    please refer separate instructions attached with this tender.

    4.2 Un-priced commercial bid should be attached with the technical bid.

    4.3 All the literature should be in English Language only.

    4.4 Compliance statement to all the specifications of each item as per this RFP. Offers without

    compliance sheet may not be considered during tendering process. Sample compliance table is

    shown in table-1

    4.5 Introduction by the vendor including technical capabilities relevant to proposed development. Vendor may add clientele details where similar installations are made.

    4.6 Work plan for fabrication of the proposed items. 4.7 Previous automation and fabrication carried out of a similar nature. 4.8 Delivery schedule.

  • Space Applications Center | Indian Space Research Organization | Govt. of India

    Page | 8

    4. SPECIFICATION

    Technical specification for optical payload integration fixture:

    1) Size of the fixture:

    4700 mm length (max) X 4400 mm width (max) X 3000 mm height (max).

    2) Rotation of Axis: Pitch(X)

    Rotation: ± 1.5 degree about pitch axis (automation).

    Resolution: ≤ 1 arc second

    Speed: 10Arc second/second (Typical)

    3) Rotation of Axis: Roll axis(Y)

    Rotation: -2 to +90 Degree rotation of payload about roll axis form axis vertical to axis Horizontal,

    Jack-A shall have capability to rotate payload about roll axis. (Refer fig 5 for details of angles), It shall

    have sufficient range to clear all appendages of fixture while rotating -2 to + 90 degree. Axis of rotation

    shall be from C.G, also there shall be provision to adjust axis of rotation to pass it from C.G.

    Resolution and Range: 1 arc second over -1.5 to +1.5-degree range, refer fig-3. And 0.5 Degree

    over -2 to + 90 degree range.

    Speed: 10Arc second/second (Typical) over -1.5 to +1.5 degree range, 20degree/minute (typical)

    over -2 to + 90 degree range

    These rotations shall be motorized. Noiseless and smooth rotation and jerk free start and stop are to be

    ensured.

    4) Rotation of Axis: - Yaw (Z)

    Resolution and range: 1 arc second over -1.5 to +1.5 degree range, refer fig-3. And 0.5 Degree

    over 0 to 360-degree range

    Speed: 10Arc second/second (Typical) over -1.5 to +1.5-degree range, 20 degree/minute

    (typical) over -0 to 360-degree range

    This rotation shall be motorised. It shall have suitable ball/guide bearings along with ratchet

    arrangement for locking at 0°, 90, 180°, 270° angle. Noiseless and smooth rotation and jerk free start

    and stop are to be ensured.

    5) Orthogonality among all three axis ≤ 1 Degree

    6) Load capacity of the fixture ≥ 750 kgs.

    7) Total mass of the payload integration fixture (without payload) ≈ 1000 kgs.

    8) Control panel and display: Control panel shall be provided for electrical supply to the system and

    display unit of not smaller than 9 inch (typical) touch screen for operating functionality of the system.

  • Space Applications Center | Indian Space Research Organization | Govt. of India

    Page | 9

    Display unit shall show absolute current positions (w.r.t home reference position). It shall be able to

    control all stage and actuator independently.

    9) Encoders: Suitable encoders shall be used for feedback of actual position of tilt in three axes (i.e.

    Pitch, Roll and Yaw).

    10) Locking arrangement: All rotational axis shall have locking arrangement to lock before testing

    of the payload after final position is achieved.

    11) Material of construction: Base frame structure shall be made from stainless steel (preferably SS

    304/316)/ aluminum alloy, it shall be non-corrosive.

    12) Fixture mounting foot print: Vendor shall propose fixture mounting foot print to SAC, which

    will be reviewed by SAC for clearing it for fabrication.

    13) Footprint for payload mounting: Footprint for payload mounting on to fixture is shown in figure-

    6. Flatness required on payload to fixture mounting interface shall be better than 50 microns.

    Appropriate spherical ball joint spacer shall be provided to accommodate flatness error.

    14) Cutout: Fixture shall have 1135 mm (typical) inside hole on payload foot print area for various

    payload element integration\testing, while mounted of payload fixture, refer figure-4.

    15) Lifting brackets: Fixture shall have provision to lift (preferably four point lifting brackets) for

    easy handling of the fixture.

    16) Limit switch: Fixture shall have limit switches for rotational axis Pitch and Roll axis.

    17) Fixture rigidity: No noticeable deformation (change in flatness of payload mounting interface shall

    be < 100micron with payload mass) should be observed when a load (payload mass) is applied on

    platform. To be demonstrated using a 750 kg load on the payload mounting interface of fixture.

    18) Lubrication: sealed non-grease lubricants for the moving subassemblies, shall not degas in vacuum

    environment (1E-6 mbar).

    19) Clean room and Vacuum compatibility: Entire system shall comply with the requirements of a

    clean room class 100,000 and vacuum level of 1E-6 mbar.

    20) Aesthetics/Safety: The equipment shall have good aesthetic look. The equipment should be safe in

    all aspects. Sharp corners, open electrical points, exposed moving parts will all be adequately taken

    care of in design.

    21) Temperature limit: Entire system shall comply with temperature limits for operating (22 ± 15°C)

    and non-operating (-10°C to 50°C) conditions.

    22) Cables with feed through connector: Necessary two sets of cables (power supply cable, data

    cables, etc) shall have minimum 5m length with feed through connectors (preferably LEMO, plug

    in type) for operating fixture from outside of thermos vacuum chamber (fixture inside thermos

    vacuum chamber). Electrical Cable Wire type should be Teflon / Kapton and vacuum compatible.

    23) Jack-B: Refer figure-5 for configuration of it. It shall have lifting range of ±50mm, with resolution

    of ≤ 1mm. This lifting shall be motorized, with the option of operating it in pair of two or Four

    together.

    24) Load sensor: load sensors shall be placed at each support locations of payload integration fixture

    (at four locations below ball joints). Measurement range of load shall be capable to take care of

    payload weight +payload integration fixture weight.

  • Space Applications Center | Indian Space Research Organization | Govt. of India

    Page | 10

    25) GUI: GUI shall display all load sensor results, all z stages displacement\angle results, position of

    jack-A and Jack B. There shall be provision to take all stage to home position, also when power is

    off, all stage position shall retain to last commended position, and it shall start from last position

    upon powering on. GUI shall have provision for both absolute and incremental commanding for

    all stages and actuators.

    26) Wireless remote: GUI mentioned above shall be loaded in mobile handheld wireless unit with

    9inch (Typical) display.

    27) Payload mounting ring: Suitable payload mounting ring shall be design and deliver by vendor

    along with payload integration fixture. (Refer figure-6 for schematic and section view of payload

    mounting ring).

    5. DESIGN REVIEW: Before start of fabrication, vendor needs to present design to SAC team in form of PDR (preliminary design review) and (CDR) Critical design review, all suggestion made

    by SAC needs to be incorporate in design. Written approval of SAC is required before start of

    fabrication.

    6. PERFORMANCE AND FUNCTIONALITY TEST After fabrication and assembly at vendor's premises, payload integration fixture will undergo

    functionality tests. These tests will include noise during operation, smoothness of rotation, and rigidity

    of platform under dummy load. (Dummy load simulating mass and C.G of payload shall be arranged

    by vendor, refer fig-1 for payload C.G details) These tests will be carried out in the presence of

    SAC/ISRO appointed engineers at vendor's premises. If all the specifications are met, the hardware will

    be cleared for dispatch to ISRO.

    7. CONTAINERS FOR DISPATCH The container and packing of all the sub-systems shall be robust enough to survive the rigors of handling

    and transportation between the vendor’s premises and ISRO. The manufacturer shall provide handling

    and storage instructions for the deliverables.

    8. INSTALLATION AND COMMISSIONING

    The vendor shall be responsible for installation and commissioning of all the supplied items at SAC.

    Vendor shall arrange all tools, accessories and man power necessary for installation. Performance and

    acceptance tests shall be repeated as per section 5 and satisfactory performance of payload integration

    fixture shall be ensured by the vendor to SAC for issuing of completion certificate necessary for release

    of payment.

    9. WARRANTY All the systems supplied by the vendor shall have on-site warranty period of 3 years from date of

    installation. Included in the warranty will be provision for rectifying malfunctioning of sub systems,

    breakdown and regular maintenance as required. System performance shall be guaranteed during this

    period.

    10. DELIVERABLES

    Payload Integration fixture as per this RFP = 2 No.

  • Space Applications Center | Indian Space Research Organization | Govt. of India

    Page | 11

    Note - The vendor shall provide the details like specifications, model and make of all bought out

    items like motors, encoders, controllers etc.

    11. DELIVERY SCHEDULE

    Order signing and acceptance T0

    Proposal and presentation at SAC -PDR T0 + 1 month

    Finalization of design (CDR) and clearance of fabrication

    T0 + 2 months

    Completion of fabrication T0 + 4 months

    Acceptance testing and dispatch at vendors premises T0 + 4.5 months

    Installation at SAC

    T0 + 5 months

    SAC have all rights for onsite inspection during development of fixture at vendor’s premises.

    Note: Only vendors, who are confident to complete design with meeting indent specification in

    first two attempt ( i.e. PDR and CDR) needs to submit quote. Vendor failing in completion of

    design in first two attempt ( i.e PDR and CDR) will be disqualified and SAC will have rights to

    cancel order.

  • Space Applications Center | Indian Space Research Organization | Govt. of India

    Page | 12

    Annexure 1

    Table-1 Compliance matrix

    (to be filled in by vendor)

    Sr

    No Parameter Specification

    Vendor’s

    compliance

    (to be filled in by

    vendor)

    Compliance

    (Yes/No)

    (to be filled in

    by vendor)

    1 Size of the

    fixture

    4700 mm length (max) X 4400

    mm width (max) X 3000 mm

    height (max)

    2 Rotation of Axis:

    - pitch (X)

    Rotation: ± 1.5 degree about

    pitch axis (automation).

    Resolution: ≤ 1 arc second

    Speed: 10Arc second/second

    (Typical)

    3

    Rotation of Axis:

    - Roll axis (Y)

    Rotation: -2 to +90 Degree

    rotation of payload about roll

    axis form axis vertical to axis

    Horizontal, Jack-A shall have

    capability to rotate payload

    about roll axis. (Refer fig 5 for

    details of angles), It shall have

    sufficient range to clear all

    appendages of fixture while

    rotating -2 to + 90 degree. Axis

    of rotation shall be from C.G,

    also there shall be provision to

    adjust axis of rotation to pass it

    from C.G.

    Resolution and Range: 1 arc

    second over -1.5 to +1.5-degree

    range, refer fig-3. And 0.5

    Degree over -2 to + 90 degree

    range.

    Speed: 10Arc second/second

    (Typical) over -1.5 to +1.5

    degree range, 20degree/minute

    (typical) over -2 to + 90 degree

    range

    These rotations shall be

    motorized. Noiseless and

    smooth rotation and jerk free

    start and stop are to be ensured.

    4 Rotation of Axis:

    - Yaw (Z)

    Resolution and range: 1 arc

    second over -1.5 to +1.5 degree

    range, refer fig-3. And 0.5

    Degree over 0 to 360-degree

    range

    Speed: 10Arc second/second

    (Typical) over -1.5 to +1.5-degree

  • Space Applications Center | Indian Space Research Organization | Govt. of India

    Page | 13

    range, 20 degree/minute (typical)

    over -0 to 360-degree range

    This rotation shall be motorised. It

    shall have suitable ball/guide

    bearings along with ratchet

    arrangement for locking at 0°, 90,

    180°, 270° angle. Noiseless and

    smooth rotation and jerk free start

    and stop are to be ensured.

    5

    Orthogonality

    among all three

    axis

    ≤ 1 Degree

    6 Load capacity of

    the fixture ≥ 750 kgs

    7

    Total mass of the

    payload

    integration

    fixture (without

    payload)

    ≈ 1000kgs.

    8 Control panel

    and display

    Control panel shall be provided for

    electrical supply to the system and

    display unit of not smaller than 9

    inch (typical) touch screen for

    operating functionality of the

    system. Display unit shall show

    absolute current positions (w.r.t

    home reference position). It shall be

    able to control all stage and actuator

    independently.

    9 Encoders

    Suitable encoders shall be used for

    feedback of actual position of tilt in

    three axes (i.e. Pitch, Roll and

    Yaw).

    10 Locking

    arrangement

    All rotational axis shall have

    locking arrangement to lock before

    testing of the payload after final

    position is achieved.

    11 Material of

    construction:

    Base frame structure shall be made

    from stainless steel (preferably SS

    304/316)/ aluminum alloy, it shall

    be non corrosive.

    12 Fixture mounting

    foot print

    Vendor shall propose fixture

    mounting foot print to SAC, which

    will be reviewed by SAC for

    clearing it for fabrication

    13

    Footprint for

    payload

    mounting

    Footprint for payload mounting on

    to fixture is shown in figure-6.

    Flatness required on payload to

    fixture mounting interface shall be

    better than 50 microns. Appropriate

    spherical ball joint spacer shall be

    provided to accommodate flatness

    error.

    14 Cut-out

    Fixture shall have 1135 mm

    (typical) inside hole on payload foot

    print area for various payload

    element integration\testing, while

  • Space Applications Center | Indian Space Research Organization | Govt. of India

    Page | 14

    mounted of payload fixture, refer

    figure-4.

    15 Lifting brackets

    Fixture shall have provision to lift

    (preferably four point lifting

    brackets) for easy handling of the

    fixture.

    16 Limit switch Fixture shall have limit switches for

    rotational axis Pitch and Roll axis.

    17 Fixture rigidity

    noticeable deformation (change in

    flatness of payload mounting

    interface shall be < 100micron with

    payload mass) should be observed

    when a load (payload mass) is

    applied on platform. To be

    demonstrated using a 750 kg load

    on the payload mounting interface

    of fixture.

    18 Lubrication

    sealed non-grease lubricants for the

    moving subassemblies, shall not

    degas in vacuum environment (1E-

    6 mbar).

    19

    Clean room and

    Vacuum

    compatibility

    Entire system shall comply with the

    requirements of a clean room class

    100,000 and vacuum level of 1E-6

    mbar.

    20 Aesthetics/Safety

    The equipment shall have good

    aesthetic look. The equipment

    should be safe in all aspects. Sharp

    corners, open electrical points,

    exposed moving parts will all be

    adequately taken care of in design.

    21 Temperature limit

    Entire system shall comply with

    temperature limits for operating (22

    ± 15°C) and non-operating (-10°C

    to 50°C) conditions.

    Cables with feed

    through connector

    Necessary two sets of cables (power

    supply cable, data cables, etc) shall

    have minimum 5m length with feed

    through connectors (preferably

    LEMO, plug in type) for operating

    fixture from outside of thermos

    vacuum chamber (fixture inside

    thermos vacuum chamber).

    Electrical Cable Wire type should

    be Teflon / Kapton and vacuum

    compatible.

    23 Jack-B

    Refer figure-5 for configuration of

    it. It shall have lifting range of

    ±50mm, with resolution of ≤ 1mm.

    This lifting shall be motorized, with

    the option of operating it in pair of

    two or Four together.

    24 Load sensor

    load sensors shall be placed at each

    support locations of payload

    integration fixture (at four locations

    below ball joints). Measurement

    range of load shall be capable to

    take care of payload weight

    +payload integration fixture weight.

  • Space Applications Center | Indian Space Research Organization | Govt. of India

    Page | 15

    25 GUI

    GUI shall display all load sensor

    results, all z stages

    displacement\angle results, position

    of jack-A and Jack B. There shall be

    provision to take all stage to home

    position, also when power is off, all

    stage position shall retain to last

    commended position, and it shall

    start from last position upon

    powering on. GUI shall have

    provision for both absolute and

    incremental commanding for all

    stages and actuators

    26 Wireless remote

    GUI mentioned above shall be

    loaded in mobile handheld wireless

    unit with 9inch (Typical) display.

    27 Payload mounting

    ring

    Suitable payload mounting ring

    shall be design and deliver by

    vendor along with payload

    integration fixture. (Refer figure-6

    for schematic and section view of

    payload mounting ring).