Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Page 1 of 49
REPUBLIC OF TRINIDAD AND TOBAGO
IN THE HIGH COURT OF JUSTICE
Claim No. CV 2017-00129
BETWEEN
COLIN LUCAS
Claimant
AND
PORT AUTHORITY OF TRINIDAD AND TOBAGO
Defendant
Before the Honourable Madame Justice Margaret Y Mohammed
Date of Delivery 29 May 2020
Appearances:
Mr Douglas Mendes SC and Mr Michael Quamina instructed by Ms Gabrielle Gellineau Attorneys at
law for the Claimant
Mr Russell Martineau SC and Ms Amirah Rahaman instructed by Mr Joel Roper Attorney at law for
the Defendant
JUDGMENT
INTRODUCTION
1. In early March 2013 the Claimant found himself in a predicament. He was advised to cease
reporting to work at the Defendant’s office as he was no longer employed by the Defendant.
The Claimant complied with this directive but he felt aggrieved as he was under the
impression that he had a contract of employment to work with the Defendant as the CEO of
the Port of Port of Spain (“ CEO of PPOS”) commencing 1 March 2013 (“the 2013 Contract”).
He instituted this action claiming that he was summarily dismissed. The Claimant seeks
against the Defendant damages for breach of the 2013 Contract and the sum of
Page 2 of 49
$1,200,000.00 which represented his base salary of $50,000.00 per month plus allowances
in the sum of $252,000.00 representing allowances of $10,500.00 per month totaling the
sum of $1,452,000.00 for the period 1 March, 2013 to 28 February 2015. He also seeks
gratuity of 25% of his gross salary for the period 1 March 2013 to 28 February 2015; interest
and costs.
2. Fortunately, in this matter several of the facts and contemporaneous documents are not in
dispute between the parties. It is therefore prudent at this stage to set out the undisputed
facts and address the disputed matters where I set out each party’s respective case.
THE UNDISPUTED FACTS AND CONTEMPORANEOUS DOCUMENTS
3. The Defendant is a statutory body1 which manages and co-ordinates the operations of the
Port of Port of Spain. During the period 1977 to 1999 the Claimant was employed by the
Defendant in various positions ranging from Acting Internal Auditor to General Manager. In
March 2011 the Claimant returned to work with the Defendant when by contract dated 22
April 2011 ("the 2011 Contract"), he was engaged by the Defendant as CEO of PPOS from 1
March 2011 and General Manager of the Defendant (“GM of the Defendant”) from 21 March
2011 for a two-year period.
4. In the 2011 Contract it was agreed that the Claimant would be paid “an interim basic salary”
of $50,000.00 per month and certain interim allowances, until such time as the Defendant
sought and obtained the requisite approval from the Office of the Chief Personnel Officer
(“CPO").
5. The Claimant’s employment under the 2011 Contract was for a term of two years expiring
on 28 February 2013 and he was entitled to the following additional benefits:
i) vacation leave of 25 working days per annum;
1 Port Authority Act Chapter 51:01
Page 3 of 49
ii) sick leave of 14 days with full pay every 12 months;
iii) the use of a vehicle or in lieu a monthly travelling allowance of $5,000.00;
iv) a telephone allowance of $500.00 per month;
v) a housing allowance of $3,000.00 per month;
vi) an entertainment allowance of $1,500.00 per month;
vii) an overseas passage allowance of $500.00 per month;
viii) a gratuity of 20% earned over the period of engagement;
ix) membership in the Defendant’s Group Life and Health plans.
6. The approval of the Claimant’s salary and other allowances as set out in the 2011 Contract
was obtained from the CPO on the 26 August 2013, months after the 2011 Contract came to
an end on 28 February 2013.
7. Clause 15 of the 2011 Contract provided that three months prior to the expiry of the term
of employment, the Claimant was to give notice of his desire “to remain in (the Defendant’s)
employment”, whereupon the Defendant was to “decide whether it will offer him further
employment”, such “re-engagement” to be “on such terms and for such period as may be
mutually agreed.”
8. In compliance with Clause 15 of the 2011 Contract, the Claimant notified the Chairman of
the Board of the Defendant, Mr Joseph Toney, (“Mr Toney”) by memorandum dated 1
December 2012 of his “desire to remain in the Authority’s employ”.
9. On 11 January 2013 (“the January 2013 meeting”), the Claimant met with Mr Toney who
offered him employment with the Defendant as the CEO of PPOS. The Claimant accepted the
offer.
10. By letter dated 18 January 2013, the Claimant wrote to the Chairman of the Defendant
indicating that he has accepted the Defendant’s offer with respect to the position of CEO of
Page 4 of 49
PPOS and he provided information on his salary under the 2011 Contract. Mr Toney
acknowledged the said letter by email dated 22 January 2013.
11. By memorandum dated 16 January 2013, the Executive Manager Human Resources Ms
Lyrine Lewis (“Ms Lewis”) wrote to the Defendant’s Secretary Ms Erva Bruno (“Ms Bruno”)
indicating that the 2011 Contract would expire on 28 February 2013 and that the Claimant
would have an excess of 13 vacation days left once the 2011 Contract ended. Ms Lewis
recommended that the Claimant be paid for the 13 vacation days, and requested guidance
on how to proceed. The memorandum was passed to Mr Toney who noted “Not Granted-
Mr Lucas to have these 13 days roll over in future employment.”
12. By memorandum dated 21 January 2013, Ms Bruno wrote to Ms Lewis indicating that the
Mr Toney has indicated that the 13 vacation days are to be rolled over into the Claimant’s
next contract term commencing 1 March 2013.
13. By letter dated 24 January 2013, Mr Toney informed the Minister of Works and Transport
(“the Minister”) that the Claimant had proceeded on annual vacation leave from 22 January
2013 to 28 February 2013 and that during his absence his duties would be performed by Ms
Sharon Mark (“Ms Mark”) and Ms Trudy Gill.
14. By memorandum dated 21 February 2013, Ms Mark, the Acting General Manager informed
Mr Toney of the results of an exercise carried out to determine the remuneration package
for the CEO of PPOS. The recommended salary was between $40,000.00 – $45,000.00 “plus
allowances within official guidelines”.
15. By letter dated 24 February 2013, Mr Toney proposed to the Acting Permanent Secretary,
Ministry of Transport (“the Permanent Secretary”), a salary of $40,000.00 to $45,000.00 for
the CEO of PPOS, plus allowances.
Page 5 of 49
16. On 27 February 2013 (“the February 2013 meeting”) the Claimant was invited to a meeting
with Mr Toney, Ms Mark and Mr Dorant Jack (“Mr Jack”) a Commissioner of the Board of the
Defendant. Mr Toney instructed the Claimant to immediately embark on the 13 vacation
days leave from 1 March 2013.
17. By memorandum dated 28 February 2013 to Ms Bruno, the Defendant’s Secretary Mr. Toney
cancelled the previous direction that the 13 vacation days be rolled over into the Claimant’s
“next contract term”, and instead he directed that the Claimant be paid the unutilised
vacation leave.
18. On the evening of 1 March 2013, the Claimant received a letter from Ms Bruno indicating
that he would be compensated for the 13 vacation days and that this decision superseded
Mr Toney’s earlier directive to have the said vacation days rolled over.
19. The Claimant reported to work on 4 March, 2013. By letter of even date he wrote to Mr
Toney drawing his attention to the letter of Ms Bruno dated 1 March 2013. On 5 March 2013,
Mr Toney had a telephone conversation with the Claimant.
20. By letter of 5 March 2013, Ms Pamela Ford (“Ms Ford”), the Senior Legal Officer of the
Defendant, wrote to the Claimant requesting from him particulars of the 2013 Contract,
including the terms and conditions and with whom it was negotiated and agreed upon. The
Claimant provided Ms Ford the information by letter dated 7 March 2013.
21. Ms. Ford responded by letter dated 11 March 2013. She indicated that discussions were held
between Mr Toney and the Claimant whereby the Defendant was willing to offer the
Claimant employment subject to remuneration and other terms to be agreed after receiving
the requisite approvals. She indicated that Mr Toney was under the impression that the offer
of employment was yet to be negotiated as the terms and conditions would be different
from the 2011 Contract and that it would require the approval of the Board of the Defendant
Page 6 of 49
and the CPO. The letter also contained a cheque in the sum of $24,197.15 which represented
payment for the Claimant’s 13 days vacation leave.
22. The Claimant acknowledged Ms Ford’s letter in his letter dated 12 March 2013. He stated
that while he disagreed with the Defendant’s contention that the 2013 Contract did not exist,
he would refrain from continuing to report for work.
23. By letter dated 26 August 20132 the Permanent Secretary wrote Mr Toney indicating that
the CPO approved the remuneration package for the two posts held by the Claimant in the
2011 Contract and for the post of CEO of PPOS for a period of three years with effect from
the 1 March 2013.
24. A pre-action protocol letter dated 5 May 2014 was sent by the Claimant to the Defendant
calling upon the Defendant to pay the Claimant damages in the sum of $1,440,000.00 for
breach of the 2013 Contract.
25. The Defendant responded by letter dated 15 April 2015 denying liability on the basis that
there was no valid 2013 Contract and there was no intention to enter into a contract as:
there was no properly constituted Board of the Defendant; Mr Toney had no authority to
enter into the 2013 Contract; and no remuneration was agreed.
THE CLAIMANT’S CASE
26. The Claimant pleaded that at the January 2013 meeting, Mr Toney on behalf of the Board of
the Defendant offered him a further term of employment in the position of CEO of PPOS on
the same terms and conditions as the 2011 Contract, save for the term concerning
remuneration, which the Claimant accepted. The Claimant also pleaded that Mr Toney
indicated that he would like to adjust the remuneration only because the Claimant would no
longer hold the position of CEO and GM of the Defendant but solely that of CEO of PPOS3.
2 Exhibit “C.L.10” of the Claimant’s witness statement. 3 Paragraphs 23 and 24 of the Statement of Case and paragraph 6 of the Reply
Page 7 of 49
27. The Claimant asserted that at the February 2013 meeting he was informed by Mr Toney that
the 2013 Contract was to be put before a soon to be installed Board of the Defendant as it
related to the issue of remuneration only.
28. The Claimant reported for work on 4 March 2013 with the expectation that his remuneration
would be settled once the new Board of the Defendant was appointed but he was wrongly
terminated on the 11 March 2013.
THE DEFENCE
29. The Defendant denied that it entered into the 2013 Contract and that it is liable for any loss
and/or damage suffered as alleged by the Claimant.
30. The Defendant’s position was that at the January 2013 meeting Mr Toney offered the
Claimant the single position of CEO of PPOS subject to the remuneration and other terms to
be agreed and approved by the Board of the Defendant. Mr Toney did not offer and the
Claimant did not accept a further term of employment in the position of CEO of PPOS on
the same terms and conditions of the 2011 Contract as the latter was for two jobs while Mr
Toney’s offer was for only one job which was the CEO of PPOS.
31. The Defendant asserted that there was no discussion at the January 2013 meeting of any
term or duration of the proposed 2013 Contract and no terms and conditions were finalised
or agreed upon. Its position was that, the discussions were preliminary and subject to
contract. Mr Toney made it clear to the Claimant that he needed to discuss the matter with
the Board of the Defendant in order to obtain the requisite approvals before any contract
could be made. As such the Defendant asserted that there was no intention to create legal
relations and there were no certainty of terms for the 2013 Contract for the following
reasons
Page 8 of 49
(a) At the time, there was no Board of Commissioners of the Defendant to approve the
2013 Contract;
(b) Mr Toney did not have authority to enter into the 2013 Contract;
(c) There was no approval from the CPO of the 2013 Contract;
(d) The proper hiring procedures were not followed.
32. The Defendant also asserted that, at the February 2013 meeting, Mr Toney did not inform
the Claimant that a new Board of the Defendant was soon to be installed and that he wished
to have their input on the sole question of remuneration or that he was awaiting the
appointment of a new Board of the Defendant to finalise only the remuneration package.
The Defendant’s position was that Mr Toney indicated at the February 2013 meeting that
the Board of the Defendant’s approval was required for all terms and conditions of the 2013
Contract.
33. The Defendant contended that by letter dated 1 July 2013 it paid to the Claimant, the sum
of $9,306.58, which represented the payment for five additional days worked during his
vacation period. By letter dated 16 September 2013, the Defendant paid the Claimant the
sum of $90,000.00 which represented the gratuity for the 2011 Contract.
THE ISSUES
34. In order for the Claimant to succeed with his claim the following issues must be determined
in his favour:
(a) Did Mr Toney and the Claimant enter into the 2013 Contract at the January 2013
meeting?
(b) Was Mr Toney’s conduct after the January 2013 meeting indicative that there
was an intention to create legal relations at the January 2013 meeting?
(c) If the 2013 Contract is valid, is it enforceable?
Page 9 of 49
(d) What measure of damages is the Claimant entitled to if he proves he was
wrongfully terminated?
35. There were different versions of the January 2013 meeting and the events which took place
after. In resolving the disputes of facts in this matter, the Court has to satisfy itself which
version of events is more probable in light of the evidence. To do so, the Court is obliged to
check the impression of the evidence of the witnesses on it against the: (1)
contemporaneous documents; (2) the pleaded case; and (3) the inherent probability or
improbability of the rival contentions, (Horace Reid v Dowling Charles and Percival Bain4
cited by Rajnauth–Lee J (as she then was) in Mc Claren v Daniel Dickey5).
36. The Court is also guided by the Court of Appeal judgment in The Attorney General of
Trinidad and Tobago v Anino Garcia6 where it stated that any deviation by a party from his
pleaded case immediately calls his credibility into question.
THE WITNESSES
37. At the trial the Claimant gave evidence on his behalf and he called Ms Lewis as his witness.
The Defendant’s witnesses were Mr Toney, Mr Jack, and Ms Marcia Charles- Elbourne (Ms
Elbourne”) Acting Deputy General Manager of the Defendant at the time of the trial.
DID MR TONEY AND THE CLAIMANT ENTER INTO THE 2013 CONTRACT AT THE JANUARY
2013 MEETING?
38. It was submitted on behalf of the Claimant that at the January 2013 there was a fully
functioning Board of the Defendant. Mr Toney on behalf of the Defendant agreed to employ
the Claimant as the CEO of PPOS for a period of three years on the same terms as the 2011
4 Privy Council Appeal No. 36 of 1897 5 CV 2006-01661 6 Civ. App. No. 86 of 2011 at paragraph 31
Page 10 of 49
Contract but with regard to remuneration, on terms to be determined by the CPO which was
the agreed mechanism.
39. Senior Counsel for the Defendant argued that at the January 2013 meeting there was no
concluded 2013 Contract, as the Claimant and Mr Toney, did not agree on the remuneration
(which included salary, allowances and gratuity) for the post of CEO of PPOS which Mr Toney
said had to be adjusted from that in the 2011 Contract. The parties also did not agree to any
duration of the 2013 Contract.
40. The fundamental difference between the parties on the January 2013 meeting was that the
Claimant was of the opinion that he entered into a valid 2013 Contract while the Defendant’s
position was that at best it was an agreement to agree on the post of CEO of PPOS.
Relevant principles of law
41. It was common ground by the parties that an agreement to agree is not a valid contract.
42. The United Kingdom Supreme Court in Wells v Devani7 reiterated the words of Lord Clarke
in RTS Flexible Systems Ltd v Molkerei Alois Müller GmbH8where he explained the relevant
principles required for the formation of a valid binding contract as :
“The general principles are not in doubt. Whether there is a binding contract
between the parties and, if so, upon what terms depends upon what they have
agreed. It depends not upon their subjective state of mind, but upon a consideration
of what was communicated between them by words or conduct, and whether that
leads objectively to a conclusion that they intended to create legal relations and had
agreed upon all the terms which they regarded or the law requires as essential for
the formation of legally binding relations. Even if certain terms of economic or other
significance have not been finalised, an objective appraisal of their words and
7 [2019] UKSC 4, para 17 8 [2010] UKSC 14; [2010] 1 WLR 753, para 45
Page 11 of 49
conduct may lead to the conclusion that they did not intend agreement of such terms
to be a precondition of a concluded and legally binding agreement.” (Emphasis
added)
43. The general rule is that certainty and completeness of the terms of the agreement are
essential in order to enforce a contract. The authors of The Law of Contract at paragraph
2.157 stated:
“If an agreement is to be enforced as a contract the parties to it must have reached
agreement on all its essential terms which must be expressed with sufficient clarity
to permit enforcement. If the terms of an agreement are incomplete, unclear,
ambiguous or uncertain it will often be assumed that the parties did not intend their
agreement to be legally binding, or that they have not yet reached a final agreement;
and since an acceptance must agree to all the terms of the offer, it follows that the
offer must contain all the terms of the contract, so that a statement which contains
terms which are unclear or ambiguous is unlikely to be regarded as an offer. Similarly,
a statement which indicates that important issues remain to be agreed is unlikely to
be construed as an offer.”
44. At paragraph 2.158 it was stated that:
“A failure to agree on all the essential terms of a bargain is generally fatal to a finding
that there is a contract. It follows that in order to be regarded as an offer a statement
must contain all the essential terms of the proposed contract. As a minimum,
therefore, an offer will normally contain a statement of the offeror's proposed
undertaking and the price (consideration) demanded in return for that undertaking.
However, agreement on price will not be sufficient if there is an indication that other
terms remain to be agreed. Similarly, a proposal which indicates a price will not be
construed as an offer if there is any other explicit or implicit indication that the
Page 12 of 49
person making the proposal does not intend to assume a legal obligation if the
proposal is accepted.”
45. Senior Counsel for the Claimant relied on the principles of law in the cases of Brown v
Gould9, Cudgen Rutile (no 2) Pty Ltd v Chalk10, Anderson and ors v London Fire and
Emergency Planning Authority11,Premier Telecom Communications Group Ltd and anor. v
Webb12, Hughes v Pendragon Sabre Ltd13 and Green Deal Marketing Southern Ltd v
Economy Energy Trading Ltd and ors14. The cases concerned allegations of incompleteness
of a contract where there were outstanding terms.
46. The Defendant did not take issue with the principles of law enunciated in the aforesaid cases.
However, Senior Counsel for the Defendant submitted that when the said principles are
applied to the facts in the instant case the Court ought to find that the Claimant’s case is
without merit.
47. It is appropriate to address the principles of law in the cases referred to by Senior Counsel
for the Claimant at this juncture. I will deal with them in the order of chronology of the dates
of the decision.
48. In Brown, the issue before the Court concerned the validity of a renewal of a lease where
there was a clause in it providing for an option to renew "at a rent to be fixed having regard
to the market value of the premises at the time of exercising this option taking into account
to the advantage of the tenant any increased value of such premises attributable to
structural improvements made by the tenant during the currency of this present lease."
9 (1972) 1 Ch 53 10 (1975) AC 520 11 (2013) EWCA Civ 321 12 (2014) EWCA Civ 994 13 (2017) 1 All ER (Comm) 173 14 (2019) 2 All ER (Comm) 191
Page 13 of 49
49. Megarry J identified three possible types of option. The first was where the option simply
said "at a rent to be agreed". In such a case, he said, "no formula for quantifying the rent is
laid down, and prima facie the option will ... be void as being a mere contract to make a
contract, or, perhaps more properly, as being an agreement to make a contract, or a contract
dependent upon the making of an agreement." The second and third types of option he
identified were those "expressed to be exercisable at a price to be determined according to
some stated formula, without any effective machinery being in terms provided for the
working out of that formula", and those which provide "both a formula and the machinery,
as, for example, arbitration." Megarry J found that the option fell within the second category
and therefore he held that it was not void for uncertainty. In arriving at that position Megarry
J reiterated the principle that "the proper approach ... is that the court is reluctant to hold
void for uncertainty any provision that was intended to have legal effect." It is to be noted
that in Brown there was a formula for fixing the rent.
50. Cudgen Rutile was a decision of the Privy Council on an appeal emanating from Australia.
The Appellants were given the right to or an authority to prospect and mine for minerals
over the certain lands which included Crown lands by the Minister of Mines which was
renewable for a further period of one year from 1 July 1966. On their application for renewal,
the appellants were granted two authorities to prospect, one by the Governor in Council
under section 46 (1) (b) of the Mining Acts in respect of so much of the area as consisted of
reserves and the other by the Minister under section 23A (1) in respect of so much of the
area as consisted of Crown land and private land. The two authorities were for terms of four
years from July 1, 1966, and granted the appellants the right to prospect the land subject to
the authority for all minerals other than coal, mineral oil and petroleum and the right to the
grant of mining leases over any part of the subject lands. The appellants carried out extensive
prospecting operations incurring considerable expense and discovered large mineral
deposits. On 2 February, 1970, they applied for three special mineral leases in respect of the
minerals so discovered in lands within the subject areas, but not including any private land.
Page 14 of 49
The applications were heard by the Mining Warden who recommended that the leases
should be granted, but the Government refused to grant any.
51. The Appellants filed a claim seeking specific performance of the contract to grant them
leases or damages. The Respondent representing the Government of Queensland entered
demurrers on the grounds, inter alia, that the Appellants were not entitled to the grant of
any special mineral leases and that, if on a true construction of the authorities to prospect,
any provision purported to entitle the Appellants to the grant of a special mineral lease or
to oblige the Governor in Council to grant any such lease, the term was void as neither the
Mining Acts nor any other Act permitted the inclusion in an authority to prospect, a term
which would oblige the Governor in Council to grant a special mineral lease. The Full Court
allowed the demurrers.
52. On appeal to the Privy Council, the Board found that the demurrers were well founded on
the basis that the Crown in Commonwealth of Australia could not contract for the disposal
of any interest in Crown lands except in accordance with powers conferred by statute.
Accordingly, where a statute prescribed a mode of exercise of the statutory power it had to
be observed. It followed that the freedom of the Minister responsible for implementing the
statute could not be validly fettered by anticipatory action. The Minister, before granting a
mineral lease, whether in respect of reserves Crown land, had to make statutory decisions
and exercise statutory discretions, and any attempt to bind him in advance was beyond his
statutory powers, and no purported agreement could give rise to any contractual obligation
enforceable in the courts.
53. Although the Board arrived at the aforesaid position Lord Wilberforce stated the modern
approach to be adopted by the Court in determining the validity of a contract as :
"A further argument, against a conclusion that a valid and enforceable contract was
constituted by the authority to prospect of September 15, 1966, was put by counsel
for the respondent: this was that a number of essential terms, namely, the character
Page 15 of 49
of the lease, the areas to be included, and the term, were not fixed by the authority
to prospect but were left to be determined by the Minister. Where this situation
exists, it was said, there is no effective contract, or to use a phrase of Sir Frederick
Pollock, a contract which is illusory. Examples of the judicial use of this concept are
the judgment of Cussen J. in Beattie v. Fine [1925] V.L.R. 363, 369 and the judgment
of Windeyer J. in Placer Development Ltd. v. Commonwealth of Australia, 121 C.L.R.
353. Their Lordships consider that, in modern times, the courts are readier to find an
obligation which can be enforced, even though apparent certainty may be lacking as
regards some term such as the price, provided that some means or standard by which
that term can be fixed can be found (cf. Hillas & Co. Ltd. v. Arcos Ltd. (1932) 147 L.T.
503; Sweet & Maxwell Ltd. v. Universal News Services Ltd. [1964] 2 Q.B. 699 and
Godecke v. Kirwan (1973) 47 A.L.J.R. 543)." (Emphasis added)
54. Subsequently the English Court of Appeal in Anderson and Hughes adopted the aforesaid
approach espoused Lord Wilberforce in Cudgen Rutile.
55. In Anderson, the appellant employees (E) appealed against a decision that a collective pay
agreement with the respondent employer (L) enabled L to choose from two alternative pay
increases.
56. L had made the agreement with E's trade union for the years 2007 to 2009, and it was
incorporated into E's employment contracts. It provided for set pay increases for 2007 and
2008, and for 2009 it provided that pay would be increased by 2.5 % or by the NJC Local
Government Services settlement plus 1 per cent. In 2009 L took the view that it was not
obliged to implement an increase of 2.5%. E began proceedings claiming unlawful
deductions from wages.
57. The Court of Appeal found that a clause in a collective agreement that "pay will be increased
by 2.5% or by the NJC for Local Government Services settlement plus any uplift required to
ensure general pay increases for the period 2007-09 are 1% above the NJC settlements for
Page 16 of 49
the same period” was not "an agreement to agree or an agreement to negotiate" but was
"an agreement for a rate of pay to be determined in accordance with the agreed terms,
properly construed."
58. In arriving at this position, the principle of law which the Court of Appeal enunciated was
that it was necessary to consider what the agreement conveyed to a reasonable person
having all the background knowledge that would have reasonably been available to the
parties. The Court found in Anderson that there was a formula for the increased pay.
59. In Hughes, H had learnt that Porsche was to manufacture a limited edition of its 911 GT3 RS4
model. He emailed the dealer, stating that he would like to place an order for the new model.
A few days later, a sales executive advised H that he needed to visit the dealership premises
that day to pay an "expression of interest deposit" of £10,000 to increase his chances of
obtaining a vehicle. He did so and also signed a document headed "Vehicle Order Form"
which stated that he agreed to purchase the vehicle subject to the terms and conditions in
the form. The document stated: "This document contains the terms of a contract and
includes the Terms and Conditions attached". It also indicated that the seller was not obliged
to fulfil orders in the sequence in which they were placed. A few days after the customer
signed the order form, the sales executive emailed him, confirming that he had placed an
order and confirming that he would get the first vehicle which the dealer was allocated by
Porsche. The dealer subsequently received a vehicle, but supplied it to another customer.
60. The issue was whether in the circumstances of that case, there was a contract or an
agreement to agree. On appeal, the Court of Appeal applied the principle of law stated by
Lord Wilberforce in Cudgen Rutile and found that H had entered into a binding agreement
with the dealer, as the terms and conditions in the order form, had all the hallmarks of what
would be expected in an agreement to sell a vehicle. Notably in Hughes, although the
agreement was subject to terms and conditions, the Court of Appeal found that the express
statement at the foot of the form that the document contained the terms of the contract
which included the terms and conditions attached.
Page 17 of 49
61. In Premier Telecom the appellants (P and R) appealed against an order granting summary
judgment to the respondent company director (W). P was a successful private company, 60
per cent of whose shares were owned by R and 40 per cent by W. The success of its
operations depended heavily on personal relationships built up between R and senior
representatives of various companies with which it did business. R had no contract with P.
Everything depended on trust and good working relationships. W was a director of P and
employed by it until October 2011, when a dispute arose between him on the one hand and
P and R on the other. A compromise was reached whereby P and R were to buy out W's
shareholding, and they agreed to delegate the valuing of the shares to expert valuers (G). G
accepted the appointment on terms set out in a letter of engagement dated December 2012.
P and R took issue with G's valuation, which led to the commencement of an action in which
they sought to overturn G’s valuation. W issued an application for summary judgment on
the grounds that the claim had no real prospect of success.
62. P and R submitted that the parties had intended that the court should decide all questions
of law bearing on the valuation, with the result that the valuers' decision was not intended
to be binding on any of them. They argued that the valuation was flawed, as G should have
valued P by reference to the absence of a contract between R and P which was likely to have
reduced the amount a willing buyer would have agreed to pay for it.
63. On appeal, P and R’s application to overturn G’s valuation was dismissed. The Court of
Appeal took the position that the contract was valid as it provided a machinery for the
resolution of a disagreement by a third party expert. The rationale was that the scope of G's
mandate was defined by the letter of engagement, the terms of which were agreed between
the parties. It contained nothing that suggested that the parties intended the court should
exercise a close degree of control over the performance of their functions. The Court of
Appeal was of the opinion that parties who referred a matter to an expert for decision
usually did so in order to obtain a quick and relatively inexpensive decision of a binding
nature on a matter that called for informed judgment. They had to be taken to have
Page 18 of 49
recognised that mistakes might be made, both of fact and law, but they were prepared to
take that risk because they placed a high degree of confidence in their chosen expert.
64. The most recent case concerning allegations of incompleteness of a contract was Green Deal
Marketing Southern Ltd. The Claimant, (G) was an energy marketing company which
claimed damages at common law against the Defendants energy supply companies and their
respective directors for breach of contract and for compensation under a specific 1993
Regulation in the UK. The Defendants counterclaimed for loss of profits said to have resulted
from a breach of contract by G.
65. Between May 2015 and January 2017, G had been engaged by the Defendants to visit
households which took their gas and electricity from the larger energy suppliers to try to
persuade them to switch to the Defendants. Initially it did so under a written contract (the
Partnering Agreement). Its case was that, from June 2016, its relationship was governed by
a new written contract (the Heads of Terms Agreement). On 31 January 2017, the
Defendants summarily ended the relationship on the basis that G had failed to comply with
the agreed targets and that its field agents were guilty of large-scale misselling.
66. One of the issues before the Court was the validity of the contractual arrangement between
the parties. The Court found that even though parts of the Heads of Terms Agreement and
the Partnering Agreement had been left incomplete, they had been formally executed by
both parties at a meeting after lengthy negotiations. While not conclusive, that was strongly
suggestive of an intention that they should have legal effect with the Partnering Agreement
intended to govern only the initial three-month period
67. Kerser J stated the following:
"[97] A distinct ground on which an agreement may lack contractual effect is that
important points remain to be agreed and the agreement is insufficiently complete.
Incomplete agreement or vagueness in expression may itself be a reason for inferring
Page 19 of 49
that the parties did not intend to create legal relations; in such a case the agreement
will lack contractual effect for that reason. Even if the parties did intend to create
legal relations, however, their failure to agree important terms may frustrate their
intention because the agreement may be held void for uncertainty. The courts are
reluctant to reach this latter conclusion, particularly if the parties have acted upon
the agreement. In Pagnan Spa v Feed Products Ltd [1987] 2 Lloyd’s Rep 601, which
concerned the question whether a prolonged exchange of telexes had resulted in the
formation of a contract, Bingham J said at 611 (citations omitted):
“Where the parties have not reached agreement on terms which they
regard as essential to a binding agreement, it naturally follows that
there can be no binding agreement until they do agree on those terms
… But just as it is open to parties by their words and conduct to make
clear that they do not intend to be bound until certain terms are
agreed, even if those terms (objectively viewed) are of relatively
minor significance, the converse is also true. The parties may by their
words and conduct make it clear that they do intend to be bound,
even though there are other terms yet to be agreed, even terms which
may often or usually be agreed before a binding contract is made …
The parties are to be regarded as masters of their contractual fate. It
is their intentions which matter and to which the Court must strive to
give effect."
68. Senior Counsel for the Defendant referred the Court to the principle of law set out by
Mendonca JA in the local Court of Appeal decision in Barrow v the National Insurance Board
of Trinidad and Tobago15 to support his position that the Claimant cannot rely of the terms
15 Civ Appeal No 59 of 2001
Page 20 of 49
of remuneration under the 2011 Contract as the basis for his dismissal or alleged breach of
the 2013 Contract.
69. It was argued on behalf of the Claimant that the learning in Barrow is totally inapplicable to
the facts of the instant case as the Appellant in Barrow was unable to provide any evidence
whatsoever of a concluded contract either orally or by conduct.
70. In Barrow, the Claimant’s case was that when the contract by which he was employed as
Chief Accountant came to an end, he was employed in the higher post of Comptroller
Finance and Accounts. He alleged that by extending his acting appointment from time to
time the Defendant in effect promoted him to the position of Comptroller. There was
evidence that after his continuous acting in the post the Claimant offered his services on
terms which approximated a draft contract. He was seeking to negotiate special terms but
there was no response from the Defendant. There was also evidence that the Human
Resources Comptroller of the Defendant, a Mr. Lopez, prepared a Report (“the Lopez
Report”) for the Board of the Defendant which recommended that the Board consider the
Claimant’s draft contract. There was no evidence that the Board of the Defendant
considered and acted on the recommendations contained in the Lopez Report. The Claimant
contended that he was the Comptroller under an implied contract, which contract was to be
implied from the conduct of the Board including things said.
71. On the issue of whether the Claimant was appointed to the substantive post, Mendonca JA
stated at paragraph 35:
“It is of course trite law that if there is to be a binding contract there must be
consensus ad idem; that is to say a sufficient correlation between the offer and
acceptance. A contract will not be concluded unless the parties have agreed to its
material terms. An offer may be made by conduct and may be accepted by conduct
unless there is a prescribed method of acceptance that excludes it, which is not the
case here. Whether the offer has been accepted by conduct requires an objective
Page 21 of 49
test to be adopted. The test has been explained in this way in Chitty on Contracts Vol.
1 (31st Ed.) at para 2-002:
“Under this test, once the parties have to all outward appearances agreed in the
same terms on the subject matter, they neither can, generally, rely on some
unexpressed qualification or reservation to show that he had not in fact agreed to
the terms to which he had appeared to agree. Such subjective reservations of one
party therefore do not prevent the formation of a contract.”
72. The Court of Appeal concluded in Barrow that is was not prepared to accept the Appellant’s
written evidence that he was told that he was appointed to the position. Mendonca JA stated
at paragraphs 49 and 50:
“In my judgment when all the evidence is considered it leads inexorably to the
conclusion that the Appellant was not appointed to the permanent and substantive
post of Comptroller
The Appellant in his statement of case also advances the position that his offer of
April 4th, 1996 was accepted. But there is no evidence that the Appellant’s
employment, after the offer was made, was continued on the terms as contained in
the draft contract that accompanied the letter of April 4th, and on which the
Appellant offered his services as Comptroller. Indeed, according to the Appellant’s
case the Board did not agree on “pension matters” and the Board was yet to discuss
the matter with him. There was therefore no consensus ad idem on material matters.
Further, the Lopez Report itself invited the Board to consider the offer. That does not
support the contention that the offer was accepted. There is no evidence that the
Board accepted Mr. Lopez’s recommendation. Indeed, the subsequent letters of the
Appellant indicate clearly that it did not and he was still seeking the Board’s response
as to his contractual position within the Board.”
Page 22 of 49
73. I take no issue with the principles of law set out by Mendonca JA in Barrow. In my opinion,
Barrow, like the cases referred to by the Claimant all turned on the facts in each case.
74. The witnesses who were at the January 2013 meeting were the Claimant and Mr Toney. The
background knowledge which they parties had at the time is relevant in order to determine
the plausibility of the different versions of the discussions which took place at the said
meeting. In considering the background knowledge the evidence of other persons who were
not present namely Ms Lewis, Mr Jack and Ms Elbourne is also relevant.
The Evidence
75. The Claimant stated in his witness statement that on the 1 March 2011 he was employed by
PPOS as its CEO and on 21 March 2011, he also assumed duties as the Defendant’s
CEO/General Manager. The 2011 Contract with the Defendant was dated 22 April 2011 and
it was for a term of two years16. According to the Claimant, his remuneration in the 2011
Contract was stated as pending the approval of the CPO and that when he began to work
with the Defendant his salary was not yet finalised by the CPO. He stated that his interim
compensation, pending CPO approval, went to the Board of the Defendant by way of Board
Paper17, which was signed on 15 April 2011 and the Board of the Defendant approved the
interim remuneration package for him on 28 April 2011.
76. The Interim nature of the 2011 Contract was explained by the Claimant at paragraph 2 (a) of
his witness statement which stated that:
“Until such times as the Authority would have sought and obtained the
requisite approvals for an appropriate salary for the person engaged (such
salary to be paid retroactively from the commencement of the contract) he
shall be paid an interim basic salary of Fifty Thousand Dollars ($50,000.00)
per month, Trinidad and Tobago currency. In addition the person engaged
16 Exhibit “C.L.1” of the Claimant’s witness statement 17 Exhibit “C.L.2” of the Claimant’s witness statement
Page 23 of 49
shall be entitled to receive those Allowances set out at clauses 5 through 9
below. These Allowances are similarly interim applications, subject to
retroactive adjustment pursuant to representations as cited earlier in this
Clause.”
77. In cross examination, the Claimant accepted that the 2011 Contract was an Interim Contract
which was approved by the Board of the Defendant after a Board Paper was presented to it.
The Claimant agreed that he did not sign any Interim Agreement for the 2013 Contract as he
did with the 2011 Contract and that there was no Board Paper submitted for the 2013
Contract to the Board of the Defendant for consideration as was done for the 2011 Contract.
78. At paragraph 7 of his witness statement, the Claimant stated that for years he was aware
that there are clear guidelines for the determination of salaries and allowances for persons
employed at executive management level by the Defendant. He explained that the first step
in the procedure for a post such as CEO of PPOS, required the Defendant to make a proposal
for the remuneration for the said position to the CPO. The CPO would submit the proposal
with the recommendations to the Ministerial Committee responsible for salaries in the
public service. The Ministerial Committee would meet, make a determination and
communicate its position through the CPO who would then give the Defendant approval for
the said remuneration package. The Claimant noted that the process could take months and
in some instances years. He stated that it was not unusual for the Defendant to employ
persons at the executive management level in contract positions before receiving the
approval from the CPO for the salaries. He stated that he was first employed as CEO of PPOS
on 1 March 2011 and his remuneration was not finalised at the commencement of his
employment as there was no approval from the CPO.
79. During cross examination, the Claimant stated that once the terms of a new contract are
approved by the CPO the remuneration is implemented by the Defendant. He accepted that
Page 24 of 49
nothing prevented an employee of the Defendant from exercising his or her option not to
accept the terms approved by the CPO.
80. The Claimant relied on the evidence of Ms Lewis to support his evidence that it was not
unusual for the Defendant to employ persons on contract at the executive management
level before the approval of the CPO was obtained.
81. Ms Lewis testified that she was last employed with the Defendant in the position of Executive
Manager, Human Resources and that she retired in 2013. She testified that it was not
unusual for a person to be working with the Defendant while remuneration was not
approved by the CPO. She stated that there were two persons who were employed before
approval for remuneration was received from the CPO namely Ms Avagale Rajkumar (“Ms
Rajkumar”), the Head of IT and Mr Ramjattan Singh (“Mr Singh”), Head of Marketing. She
stated that they both had Interim Contracts and eventually the Defendant obtained approval
from the CPO for the contracts for the said persons.
82. The Claimant’s version of the January 2013 meeting was set out at paragraphs 13 to 15 of
his witness statement. According to the Claimant, at the time of the January 2013 meeting,
the Defendant had a valid subsisting Board as there was a Board meeting on the 15 January
2013 and a Special Board Meeting on the 17 January 2013. The Claimant stated that at the
January 2013, meeting Mr Toney indicated, that he had discussed with the existing Board of
the Defendant, about offering him the post of CEO of PPOS and that the Board of the
Defendant decided to offer him the 2013 Contract. Mr Toney also indicated to the Claimant
that he would like to adjust the remuneration because the Claimant would no longer have
the responsibilities as the GM of the Defendant. The Claimant stated that he accepted the
position of CEO of PPOS on the same terms and conditions as the 2011 Contract save for the
quantum of the remuneration which they agreed had to be discussed further as Mr Toney
was under the impression that he was in receipt of two salaries under the 2011 Contract.
The Claimant stated that he offered to set out a written explanation for the remuneration
structure under the 2011 Contract. Mr Toney agreed and they both decided that the
Page 25 of 49
Claimant would write to Mr Toney on the quantum of the remuneration under the 2011
Contract.
83. During cross examination, the Claimant accepted that his case is that he entered into the
2013 Contract with the Defendant on the 11 January 2011 at the January 2013 meeting. He
agreed that the arrangements for the 2013 Contract were based on a discussion he had with
Mr Toney at the January 2013 meeting.
84. The Claimant also testified in cross examination that (i) at the time of the January 2013
meeting he knew that the term of the existing Board of the Defendant was due to expire
shortly; (ii) it was not reasonable for a Board of the Defendant, which was about to demit
office, to finalise a contract for an important office as CEO of PPOS; (iii) Mr Toney would not
have known at the January 2013 meeting that he would have accepted the position of CEO
of PPOS; (iv) Mr Toney indicated that the salary had to change for the post of CEO of PPOS
and that the gratuity, travelling allowances and vacation leave would be the same as in the
2011 Contract; (v) there were no discussions on the individual terms of the 2013 Contract;
(vi) the remuneration and duration of the 2013 Contract were not agreed at the January
2013 meeting; (vii) the discussions were not about the renewal of the 2011 Contract but
continued employment with the Defendant; and (viii) there was no agreement on how his
outstanding vacation leave was to be treated.
85. There were two letters which the Claimant wrote to Mr Toney after the January 2013
meeting in which he referred to the discussions which he had with Mr Toney at the said
meeting. The Claimant annexed the said letters to his witness statement and they also
formed part of the Agreed Bundle of documents. They were dated 18 January 201318 and 7
March 201319.
18 Exhibit “CL 4” 19 Exhibit “CL15”
Page 26 of 49
86. The letter dated 18 January 2013 was written by the Claimant to address the issue that the
salary of the CEO of PPOS ought not to be adjusted downwards. It stated in the penultimate
paragraph that there is nothing to prohibit the Defendant from revisiting this initiative
through appropriate channels applying the appropriate methodology.
87. In the Claimant’s letter dated 7 March 2013 the Claimant referred to the January 2013
meeting and at paragraph 3 he stated that “…we both acknowledged that the determination
of the new package would require in any event, Board consideration and ultimately, the
sanction of the Chief Personnel Officer, a process with which I indicated both my familiarity
and comfort.”
88. Mr Toney’s evidence on the January 2013 meeting was set out at paragraphs 7 to 11 of his
witness statement. He stated that he called the January 2013 meeting, between the
Claimant and himself to discuss the Claimant’s memorandum dated 1 December 2012. He
did so after the Board of the Defendant had met informally in the absence of the Port
Secretary and any other executive officers of the Defendant to discuss the said
memorandum. At the January 2013 meeting, he told the Claimant that his memorandum
dated 1 December 2012, was discussed by the members of the Board of the Defendant and
that he can offer him the single position of CEO of PPOS, but that his present salary would
be revised. He stated that the Claimant was very concerned about the remuneration and he
insisted that he should be paid the same basic salary as that set out in the 2011 Contract for
the position of CEO of PPOS as an interim measure. The Claimant promised to provide a
written justification for the retention of his salary under the 2011 Contract in the now
offered single position of CEO of PPOS.
89. According to Mr Toney, there was no discussion at the January 2013 meeting of any term of
any proposed 2013 Contract and no terms and/or conditions were agreed upon or finalised
or settled. The discussions were only preliminary as he had no authority from the Board of
the Defendant to enter into any contract of employment with the Claimant. Mr Toney also
Page 27 of 49
stated that the tenure of most members of the Board of the Defendant was about to expire
and the latter had never decided to offer the Claimant a new contract of employment.
90. In cross examination, Mr Toney agreed that there was an agreement between him acting on
behalf of the Board of the Defendant and the Claimant to employ him as CEO of PPOS with
the Defendant on terms and conditions to be approved by the CPO. He also stated that those
terms and conditions which were approved by the CPO and which were received by the
Defendant in August 2013 were never communicated to the Claimant. In re-examination Mr
Toney stated that the Claimant’s employment at a future date were subject to the terms and
conditions to be agreed between himself and the Defendant.
91. According to Mr Jack’s witness statement he retired as an Assistant Divisional Manager,
Marine Division of the Defendant and he was appointed a Commissioner of the Board of the
Defendant from 13 October 2011 to 12 October 2013. He stated that he knew the Claimant
since the latter was working at the Defendant while he was working there and that the
Claimant was the CEO of PPOS and GM of the Defendant when he became a member of the
Board of the Defendant.
92. Mr Jack stated in his witness statement, the Board of the Defendant gave Mr Toney the
authority, to meet with the Claimant and have preliminary discussions concerning the single
position of CEO of PPOS, subject to terms and conditions and the approval of the Board of
the Defendant. Mr Jack’s evidence in cross examination was that the Board of the Defendant
authorised Mr Toney to meet with the Claimant and offer him the post of CEO of PPOS and
that the Claimant was interested in the said post. He agreed that in January 2013 there was
a properly constituted Board of the Defendant.
93. The Defendant relied on the evidence of Mrs Elbourne to support its case that there was no
concluded 2013 Contract as the process established by the Defendant were not followed.
94. Mrs Elbourne stated in her witness statement that she was the Deputy General Manager
(Ag) of the Defendant and since October 2014 and her substantive position is Port Secretary.
Page 28 of 49
According to Mrs Elbourne’s witness statement, the Board of the Defendant and the Human
Resource Committee, guide management on matters of recruitment of persons in key
positions of executive and senior management at the Defendant. She stated that the
remuneration packages for the Defendant’s executive and senior management positions are
determined prior to the recruitment/selection/retention of the individual(s). She stated that
an Evaluation Team/Committee is established by the Defendant to review current salaries
and allowances which would encompass the remuneration package and make
recommendations to either (a) maintain current levels or (b) to increase the quantum of
remuneration packages.
95. Ms Elbourne explained that if option (b) is chosen, a job evaluation exercise is conducted
and upon completion it is submitted to the Human Resource Committee for its
consideration. The Human Resource Committee may ask for it to be reviewed and re-
submitted, or if there are no concerns, the Job Evaluation Exercise Report will be submitted
with the Human Resource Committee’s recommendations to the Board of the Defendant for
approval.
96. According to Mrs Elbourne, the Board of Defendant’s approval of the recommendation of
the Human Resource Committee is submitted as the proposed remuneration package to the
Permanent Secretary for review, and onward submission to the CPO for approval. The
deliberations of the CPO are sent to the Human Resource Advisory Committee, which
determines the approved guidelines for the said positions. The advice is sent to the
Permanent Secretary from the CPO, and then conveyed to the Office of the General
Manager/CEO of the Defendant, who in turn advises the Senior Human Resources
functionary in the Defendant and the Port Secretary, who then communicates same to the
Board of the Defendant. She explained that it is only on the completion of this process that
the recruitment process can be progressed. She stated that the Job Evaluation Exercise in
respect of the post of CEO of PPOS, was completed on 21 February 2013.
97. According to Mrs Elbourne, the Defendant was not in the practice of employing persons in
posts where the salaries have not yet been approved by the CPO. To the contrary, the
Page 29 of 49
process of recruitment is usually progressed upon the completion of the fixing of
remuneration packages with the relevant approval of the CPO and the Board of the
Defendant.
98. In cross examination Mrs Elbourne accepted that there were two occasions when the
Defendant deviated from its established practice for entering into contracts of employment
with senior executives at management level namely with Ms Rajkumar the Head of IT and
Mr Singh, Head of Marketing.
Analysis and Findings
99. At the time of the January 2013 meeting, the relevant objective facts which must be taken
into account in determining whether the 2013 Contract was entered into at the January 2013
meeting were: the Claimant was a very senior officer who worked with the Defendant from
2011 to 2013 in the position of CEO of PPOS and GM of the Defendant. The Claimant was
very knowledgeable on the detailed process which was employed by the Defendant before
it entered into any contractual arrangement with any person in executive management
position at the Defendant. The Claimant was aware of the importance of obtaining the
approval of the Board of the Defendant for any contract of employment of an officer
employed at senior management level with the Defendant, even if it was an interim contract.
The Claimant was also aware of the importance of the approval from the CPO of any terms
and conditions in for any contract of employment for an officer at senior management with
the Defendant. Further, the Claimant knew that any Board of the Defendant whose term
was due to come to an end would be hesitant in making a decision on contracting an officer
in a senior management position such as CEO of PPOS. The Claimant was also aware that
there was a standard procedure which was used by the Defendant before entering into any
contract of employment with any senior executive or management level staff at the
Defendant and that the two exceptions of Ms Rajkumar and Mr Singh had interim contracts.
Page 30 of 49
100. In my opinion, when the aforesaid objective facts are considered in the context of the
evidence, the assertion by the Claimant that at the January 2013 meeting he entered into
the 2013 Contract is without merit.
101. First, it was not the Claimant’s pleaded case that he and Mr Toney agreed at the January
2013 meeting that the CPO would determine the remuneration for the 2013 Contract. With
respect to the events of the January 2013 meeting, the Claimant pleaded at paragraph 8 of
the Statement of Case that Mr Toney indicated that he would like to adjust the terms of
remuneration. At paragraph 10 of the Statement of Case, the Claimant pleaded that Mr
Toney indicated that the Defendant would have to revisit the remuneration. Paragraph 15
of the Statement of Case stated that the Claimant was informed by Mr Toney that a new
Board of the Defendant was soon to be installed and that he wished to have their input on
the question of remuneration only. Therefore, there was no pleaded facts by the Claimant
in the Statement of Case about the CPO determining the terms of the 2013 Contract. Indeed,
the Claimant’s case was that the Board of the Defendant had to determine the question of
remuneration only which is substantially different from his submission that the CPO had to
determine the terms of the 2013 Contract.
102. Unlike the facts in the cases of Brown, Cudgen Rutile and Anderson, the Claimant did not
plead that at the January 2013 meeting he and Mr Toney agreed on any formula or a
mechanism for the approval of the remuneration for the 2013 Contract.
103. Second, it was also not the Claimant’s evidence in his witness statement that he and Mr
Toney agreed at the January 2013 meeting that the CPO was the agreed mechanism for
determining the remuneration for the 2013 Contract. The Claimant’s evidence at paragraphs
13 to 15 of his witness statement was that at the January 2013 meeting he accepted the
position of CEO of PPOS on the same terms and conditions as the 2011 Contract save and
except for the quantum of remuneration which they agreed to be discussed further as Mr
Toney was under the impression that he was in receipt of two salaries under the 2011
Contract. In my opinion this aspect of the Claimant’s evidence in chief undermined the
Page 31 of 49
credibility of his assertion that he and Mr Toney agreed that the mechanism to determine
the remuneration under the 2013 Contract was the CPO.
104. Third, the contemporaneous documents namely the Claimants letters dated 18 January 2013
and 7 March 2013 also did not support his assertion that at the January 2013 meeting he
and Mr Toney agreed that the remuneration in the 2013 Contract would be determined by
the CPO. In the letter dated 18 January 2013 the Claimant accepted that the Board of the
Defendant could revisit the terms of the remuneration for the position of CEO of PPOS. He
did not speak about the CPO determining the remuneration in the said letter. Further, in the
letter dated 7 March 2013 the Claimant recognised that any remuneration package for the
post of CEO of PPOS had to be considered and approved by the Board of the Defendant
before any approval by the CPO. In neither letter the Claimant referred to he and Mr Toney
agreeing at the January 2013 meeting that the mechanism to determine the remuneration
for the 2013 Contract was the CPO.
105. Fourth, Mr Toney’s evidence in cross examination that there was an agreement between
him acting on behalf of the Board of the Defendant and the Claimant to employ the latter as
the CEO of PPOS on terms to be determined by the Defendant’s internal process and
approved by the CPO, in my opinion also did not assist the Claimant in proving his case, as
this was not his case. In any event, Mr Toney’s evidence in re-examination was that the
Claimant’s employment at a future date with the Defendant was subject to terms and
conditions to be agreed between the Claimant and the Defendant.
106. Fifth, the Claimant’s admission in cross examination that the duration of the 2013 Contract
was not agreed at the January 2013 meeting, in my opinion undermined his case that only
the issue of remuneration was outstanding. This admission was also important as the
Claimant pleaded a claim for damages and breach of contract for a period from 1 March
2013 to 28 February 2015 when he knew all along that there was no agreement on the term
of the 2013 Contract.
Page 32 of 49
107. Sixth, even the Claimant’s evidence in cross examination on the terms of the 2013 Contract
which were discussed at the January 2013 meeting were inconsistent which further
undermined the credibility of his case. At one point the Claimant stated in cross examination
that Mr Toney indicated that the salary had to change for the post of CEO of PPOS and that
the gratuity, allowances and vacation leave would be the same as the 2011 Contract yet later
he stated that at the January 2011 meeting there were no discussions on the individual terms
of the 2013 Contract.
108. Seventh, the Claimant was not being truthful with the Court when he stated in his witness
statement that when Mr Toney offered him the post of CEO of PPOS at the January 2013
meeting, the Board of the Defendant had offered him the 2013 Contract which he accepted.
Based on the Claimant’s background knowledge of the Defendant’s practice and procedures
for entering into a contract of employment with a person at senior management level, he
knew at the January 2013 meeting that the position of CEO of PPOS was new and that the
established process had not been followed. He was also aware that the 2011 Contract was a
written Interim Contract. Based on Ms Lewis evidence, although the established procedure
was not followed for Ms Rajkumar and Mr Singh, those persons had interim contracts and
therefore their circumstances were different from his for the 2013 Contract. In this regard,
the evidence of Ms Lewis and Ms Elbourne were consistent on the practice and procedures
followed by the Defendant in entering into contracts of employment with senior
management persons and their evidence did not assist the Claimant’s case. Unlike the cases
of Green Deal Marketing Southern Ltd and Hughes there was no documents which
contained the terms the Claimant asserted he and Mr Toney agreed to at the January 2013
meeting.
109. Eighth, the lack of the Claimant’s credibility was borne out by his admissions in cross
examination that at the time of the January 2013 meeting the term of the existing Board of
the Defendant was due to expire shortly and that it was not reasonable for a Board of the
Defendant which was soon to demit office to enter into any contract of employment for a
senior management position as CEO of PPOS.
Page 33 of 49
110. Ninth, based on the objective facts, the Defendant’s version is more probable which was
that when the Claimant met with Mr Toney at the January 2013 meeting the only offer from
Mr Toney which the Claimant accepted was the position of CEO of PPOS and there was no
agreement entered on that day for the 2013 Contract. At best, Mr Toney and the Claimant
were still in discussions on the terms and conditions for the said position as they both knew
that the position of CEO of PPOS was different from the position which the Claimant held
under the 2011 Contract. It was also not probable that Mr Toney on behalf of a Board
entered into the 2013 Contract with the Claimant since they both were well aware that the
Board of the Defendant was soon to demit office and such action was unreasonable.
WAS MR TONEY’S CONDUCT AFTER THE JANUARY 2013 MEETING INDICATIVE THAT THERE
WAS AN INTENTION TO CREATE LEGAL RELATIONS AT THE JANUARY 2013 MEETING?
111. It was submitted on behalf of the Claimant that Mr Toney’s conduct after the January 2013
meeting, and the correspondence which he wrote and which were written on his behalf
demonstrated that he intended at the January 2013 meeting, that the Claimant’s future
employment with the Defendant in the position of CEO of PPOS under the 2013 Contract
was supposed to commence on the 1 March 2013.
112. On the other hand, Senior Counsel for the Defendant argued that it was highly unlikely that
Mr Toney’s actions, subsequent to the January 2013 meeting, demonstrated that he entered
into the 2013 Contract at the said meeting. In particular it was submitted that none of the
correspondence which were issued by the Claimant and or Mr Toney or on his behalf
referred to the Claimant’s future employment with the Defendant was under the 2013
Contract as CEO of PPOS which was due to start on the 1 March 2013.
113. After the January 2013 meeting there were several correspondence which were written
concerning the Claimant’s status at the Defendant and there were also discussions which
Page 34 of 49
took place at the February 2013 meeting. I have already briefly referred to the
correspondence in the undisputed facts and each party’s respective case.
The Evidence
114. The Claimant stated in his witness statement that by letter dated 18 January 2013 he wrote
Mr Toney addressing the latter’s concerns about his remuneration package under the 2011
Contract. He stated that by email dated 22 January 2013, Mr Toney replied to him stating
“Thanks, I shall need to get advice on your note and get back to you.”
115. The Claimant continued in his witness statement that he was invited to the February 2013
meeting by Mr Toney. He attended and Ms Mark and Mr Jack were also present. The
Claimant stated that he was informed by Mr Toney that a new Board of the Defendant was
soon to be installed and that Mr Toney wished to have their input on the sole question of
the quantum of his remuneration for the post of CEO of PPOS. Mr Toney then instructed him
to embark on his 13 days vacation leave with effect from 1 March 2013. According to the
Claimant, Mr Toney also indicated that by the time this vacation was up the new Board of
the Defendant would be in place and the issue of the remuneration would be finalised. He
agreed to proceed on the said vacation leave as instructed.
116. The Claimant stated that on the evening of 1 March 2013 he received a letter from Ms Bruno
indicating that he would be compensated for his 13 vacation days leave instead of it being
rolled over into the new employment term. According to the Claimant, by letter dated 1
March 2013, he wrote to Mr Toney drawing his attention to Ms Bruno’s letter dated 1 March
2013. He indicated that it was not in accordance with Mr Toney’s previous instructions. He
said that he also indicated that he had begun working in accordance with the 2013 Contract
with the expectation that the issue of quantum of remuneration would be settled once the
new Board of the Defendant was appointed.
117. The Claimant continued in his witness statement that on 5 March 2013, Mr Toney called him
at his office phone at the Defendant, to enquire about his duties at the Defendant on the 26,
Page 35 of 49
27, 28, 29 and 31 January 2013. He said he informed Mr Toney that he was assisting the
Defendant’s Attorney at law with the Defendant’s response to an injunction brought by the
then Executive Manager, Finance, Ms Charmaine Lewis against the Defendant. During this
conversation, Mr Toney did not at any time indicate to the Claimant that the latter was not
working in accordance with the 2013 Contract. The Claimant also stated that by letter dated
5 March 2013 he wrote to Mr Toney confirming the conversation and setting out the duties
he had undertaken for the Defendant on the dates Mr Toney had requested.
118. According to the Claimant, on the morning of the 6 March 2013, he received a letter dated
5 March 2013, from Ms Ford who requested particulars of the 2013 Contract including the
terms and conditions and with whom it was negotiated. The Claimant stated he provided
the details by letter dated 7 March 2013. Ms Ford responded by letter dated 11 March 2013
terminating the 2013 Contract without notice. By letter dated 12 March 2013, the Claimant
acknowledged Ms Ford’s letter dated 11 March 2013 and noted that while he disagreed that
no 2013 Contract existed, he would refrain from reporting to work in accordance with the
Defendant’s wishes.
119. The Claimant was cross examined on a few of the correspondence. The Claimant testified
that the first and last paragraphs of the letter dated 18 January 2013 which he wrote to Mr
Toney, after the January 2013 meeting, on the explanation of his remuneration under the
2011 Contract, demonstrated that he had another contract with the Defendant which was
the 2013 Contract. He relied on the first paragraph which stated “Further to our discussions
last Thursday on the renewal of my contract but only with respect to the post of Chief
Executive Officer, PPOS (consistent with the initial intention when I was asked to return to
the Port in 2011), I wish, in accepting the Authority’s offer, to address your concerns/
questions with respect to the remuneration package attaching the post, both at present and
in the future.” He said that he also relied on the last paragraph which stated “I hope the
foregoing has adequately addressed your concerns, and I thank the Authority for the
opportunity to continue to serve for another contract term.”
Page 36 of 49
120. The Claimant accepted in cross examination that in the notation made by Mr Toney, at the
top of the memorandum dated 16 January 201320 from the Executive Manager Human
Resources of the Defendant, to the Port Secretary which stated “ Not granted. Mr Lucas to
have those 13 days roll over in future employment” Mr Toney did not state that the 2011
Contract was renewed but that he was referring to the Claimant’s future employment with
the Defendant.
121. The Claimant was referred to the letter dated 25 February 2013 sent by Mr Toney to the
Permanent Secretary which concerned the revised compensation packages for the positions
of: (1) CEO of PPOS and GM of the Defendant on contract; (2) the GM/ CEO of the Defendant
on contract and; (3) the CEO of PPOS on contract. The Claimant accepted in cross
examination that Mr Toney did not need the approval of the Board of the Defendant to send
the said letter and that the employment of the CEO of PPOS required the approval of the
Board of the Defendant.
122. The Claimant also accepted in cross examination that in the letter dated 26 August 2013
from the Permanent Secretary, the CPO’s approval for the 2011 Contract stated his name
but the approval for the remuneration package for position of CEO of PPOS for the period of
three years commencing 1 March 2013 did not state his name. The Claimant admitted in
cross examination that in most circumstances it was sensible to link the duration of the term
of a contract to the remuneration package.
123. Mr Toney stated in his witness statement that by letter dated 18 January 2013, the Claimant
wrote to him to address his concerns with respect to the remuneration package for the post
of CEO of PPOS. He also stated that after the January 2013 meeting, the term of office of the
members of the Board of the Defendant, save and except for his and Mr Jack’s came to an
end on 18 January 2013. According to Mr Toney, during the period 18 January 2013 to 13
October 2013 there was no quorum of the Board of the Defendant to transact the
20 Exhibit :C.L.6” of his witness statement
Page 37 of 49
Defendant’s business and no valid contract or any matter could have been entered into or
renewed by the Defendant.
124. Mr Toney also stated in his witness statement that he received an email from the Claimant
on 22 January 2013 with respect to the salary the Claimant was in receipt of under the 2011
Contract. He replied by email dated 22 January 2013, stating that “I shall get advice on your
note and get back to you.” Mr Toney stated that his response to the Claimant’s email dated
22 January 2013, was not an acknowledgement of the 2013 Contract as there was no
agreement on the remuneration and that no other terms or conditions were discussed or
settled at the January 2013 meeting.
125. According to Mr Toney, he wrote to the Minister on the 24 January 2013 informing him of
the Claimant’s approved annual vacation leave. He stated at that time the issue of the
remuneration to offer the Claimant for the position of CEO of PPOS was still undetermined.
126. Mr Toney continued in his witness statement that on 21 February 2013, Ms Mark wrote to
him concerning the proposed remuneration packages for CEOs of Companies under the
Defendant. On 25 February 2013, he wrote to the Permanent Secretary for clarification on
the revised compensation packages for the various executive positions within the
Defendant, including but not limited to the CEO of PPOS.
127. Mr Toney stated that he called the February 2013 meeting with the Claimant, Ms Mark, and
Mr Jack. At the said meeting, he indicated to the Claimant that he had received his advice on
the proposed remuneration for the post of CEO of PPOS as stated in the email dated 22
January 2013, and that the said advice would be considered by the Board of the Defendant,
when it was appointed because at that time there were insufficient members to make a
quorum. He also informed the Claimant that a new Board of the Defendant was soon to be
installed and he wished to have their input on the question of remuneration for the position
of CEO of PPOS. He said that he never advised the Claimant that the new Board’s input was
required on the question of remuneration “only”. He stated that he indicated to the Claimant
Page 38 of 49
that the new Board’s approval was required to approve any new contract and all its terms
and conditions.
128. Mr Toney explained that although the Port Secretary, Ms Bruno used the words “next
contract term” in her letter dated 1 March 2013 to the Claimant, he wrote at the top left-
hand corner of the memorandum dated 16 January 2013 the words in “future employment.”
According to Mr Toney, the letter dated 1 March 2013, issued by the Port Secretary, Ms
Bruno, pursuant to his instructions, but which did not include the instructions about a “next
contract term”, did not acknowledge the existence of the 2013 Contract and it did not
contain instructions to the Claimant to commence work in accordance with the 2013
Contract. Mr Toney stated that the letter dated 1 March 2013 ended the 2011 Contract. The
Claimant was paid and he accepted payment for his unused vacation leave.
129. Mr Toney stated that on 4 March 2013, the Claimant wrote to him with respect to “payment
in lieu of thirteen (13) days’ vacation leave.” It was only upon the receipt of that letter, he
realised that the Claimant was at the office of the Defendant and that he did not ask the
Claimant to report to work. On 5 March 2013, Mr Toney telephoned the Claimant to ask him
to submit details of the days he worked without compensation and Claimant replied by letter
dated 5 March 2013.
130. According to Mr Toney, by letter dated 7 March 2013, the Claimant acknowledged that “the
determinates of the new package would require in any event Board consideration and
alternatively, sanction of the Chief Personnel Officer, a process with which I indicated both
my familiarity and comfort.”21 Mr Toney stated that on the 7 March 2013 there was no
approval by the Board of the Defendant nor sanction of the CPO for the 2013 Contract for
the Claimant.
21 Paragraph 3 of Exhibit “J.T.15 of the witness statement of Mr Toney. Also Exhibit “C.L.15” of the witness statement of Mr Lucas
Page 39 of 49
131. In cross examination, Mr Toney accepted that on the 17 January 2013 when he wrote the
note “Not granted Mr Lucas to have those 13 days roll over in future employment’” on the
memorandum dated 16 January 2013, he meant that the Claimant would be employed with
the Defendant at a future date after the 17 January 2013. He stated that he received the
Claimant’s letter dated 18 January 2013 on the 22 January 2013 and he had seen it before
the February 2013 meeting. Mr Toney accepted that on the 24 January 2013 when he wrote
to the Minister with respect to the approval of the Claimant’s outstanding vacation leave, he
did not inform the Minister that the Claimant’s employment under the 2011 Contract would
cease by 28 February 2013. He stated that he informed the Minister that the Claimant was
not employed after 28 February 2013 in a letter dated 28 February 201322.
132. Mr Toney also stated in cross examination that at the time of the February 2013 meeting the
term of most of the members of the Board of the Defendant had expired. He accepted that
at the February 2013 meeting he had informed the Claimant to proceed on vacation leave
on the 1 March 2013 since the remuneration for the post of CEO of PPOS had to be
determined by the Board of the Defendant in the future. Mr Toney also accepted that on the
28 February 2013 he told the Port Secretary, Ms Bruno, that he cancelled his previous
decision with respect to the Claimant’s vacation leave and he instructed her to pay the
Claimant for his leave. Mr Toney explained that he changed his decision, as he realised
overnight, that he did not have the authority to contract with the Claimant to work with the
Defendant and if he had allowed the Claimant to proceed on vacation leave from the 1 March
2013, he would be contracting him to work at the Defendant. He accepted that in his last
conversation with the Claimant he did not tell him that he did not have any further contract
of employment with the Defendant.
133. Mr Jack stated in his witness statement that he was present at the February 2013 meeting
with the Claimant, Ms Mark, and Mr Toney. According to Mr Jack, at the said meeting the
Claimant indicated he wished to be paid for the 13 days vacation leave and he requested
22 Exhibit “J.T. 19” of Mr Toney’s supplemental witness statement
Page 40 of 49
payment of his gratuity owed to him for the 2011 Contract. Mr Jack stated that Mr Toney
never told the Claimant that he wished to have the input of the new Board of the Defendant
on remuneration “only” for the 2013 Contract. According to Mr Jack, Mr Toney told the
Claimant that the approval by the Board of the Defendant was required for all terms and
conditions of the 2013 Contract and there was no quorum of the Board at the time. Mr Jack
stated that Mr Toney indicated to the Claimant at the February 2013 meeting that nothing
could be done without a Board of the Defendant and he told the Claimant to proceed on his
vacation leave from 1 March 2013.
134. In cross examination, Mr Jack stated at the February 2013 meeting he was unsure if the
Board of the Defendant was properly constituted. He maintained that at the February 2013
meeting the Claimant stated that he wanted to be paid for his 13 days vacation leave and
that Mr Toney told the Claimant that once the Board of the Defendant was properly
constituted it would meet about the post of CEO of PPOS.
Analysis and Findings
135. It was submitted on behalf of the Claimant, that the following three contemporaneous
documents concerning the Claimant’s vacation leave, namely (a) the notation by Mr Toney
on the 16 January 2013 memorandum; (b) the memorandum dated 21 January 2013 from
Ms Bruno, the Port Secretary to the Human Resources Manager in the Defendant; and (c)
Mr Toney’s letter dated 24 January 2013 to the Minister, demonstrated that it was Mr
Toney’s intention from the January 2013 meeting that the 2013 Contract was due to start on
the 1 March 2013.
136. The notation made by Mr Toney on the memorandum dated 16 January 2013 stated “Not
granted Mr Lucas to have those 13 days roll over in future employment.” In my opinion, if
Mr Toney intended to enter into the 2013 Contract at the January meeting, it was more
probable that, he would have expressly stated so in his notation. Mr Toney’s notation of
“future employment” on the said memorandum was consistent with the Claimant’s evidence
in cross examination that Mr Toney was referring to his future employment with the
Page 41 of 49
Defendant and that the notation did not state that the 13 days were to rollover into the 2013
Contract or that it was supposed to start in the Claimant’s future employment which was
due to start on the 1 March 2013. It was also consistent with Mr Toney’s evidence in cross
examination that he was referring to the Claimant’s employment with the Defendant at a
future date after 1 March 2013.
137. The memorandum dated 21 January 2013 was written by the Port Secretary, Ms Bruno to
another officer employed by the Defendant and not the Claimant. It stated “The Chairman
has directed that those days (13 days) are to be rolled over into Mr. Lucas' next contract
term commencing March 1, 2013". This statement by Ms Bruno was inconsistent with Mr
Toney’s notation on the memorandum dated 16 January 2013 which stated “roll over in
future employment" as opposed to “next contract term commencing 1 March, 2013”. It was
also inconsistent with Mr Toney’s evidence in chief and cross examination. Mrs Bruno was
not called as a witness during the trial to explain the inconsistency between Mr Toney’s
expressed instructions and her memorandum. In the absence of Mrs Bruno’s evidence, it
would be purely speculative for me to assume that when she wrote this memorandum her
instructions were that there was a next contract term for the Claimant commencing 1 March
2013. As such I have attached little weight to the contents of this document concerning the
starting date of a next contract term for the Claimant.
138. I agree that the submission by Senior Counsel for the Claimant on the interpretation of Mr
Toney’s letter dated 24 January 2013 was probable. However it was equally probable that
Mr Toney was informing the Minister, that the Claimant, the CEO of PPOS and the GM of the
Defendant was proceeding on vacation leave and therefore away from office and that Ms
Mark and Ms Gill were performing the duties. In my opinion, it was material, that Mr Toney
did not state in the said letter that the Board of the Defendant and the Claimant had entered
into the 2013 Contract at the January 2013 meeting.
139. As stated previously, the Claimant wrote a memorandum to Mr Toney dated 18 January 2013
concerning the discussions at the January 2013 meeting. Senior Counsel for the Claimant
Page 42 of 49
argued that the failure by Mr Toney to respond, refuting the Claimant’s acceptance of the
Defendant’s offer to serve for another term as CEO of PPOS was indicative that Mr Toney
knew of the 2013 Contract after the January 2013 meeting.
140. It was not in dispute that in response to the Claimant’s letter dated 18 January 2013, Mr
Toney emailed the Claimant on the 22 January 2013 which stating that “Thanks I shall need
to get advice on your note and get back to you.”
141. In my opinion, there was nothing for Mr Toney to refute as the Claimant’s memorandum
dated 18 January failed to clearly indicate that the Claimant was speaking about a specific
contract, which was supposed to start on the 1 March 2013. The words used by the Claimant
in the first paragraph of the said letter were “Further to our discussions last Thursday on the
renewal of my contract, but only with respect to the post of Chief Executive Officer, PPOS”.
In any event, this was contradicted by the Claimant’s admission in cross examination that
that the discussion he had with Mr Toney at the January 2013 meeting was not about
renewal of the 2011 Contract but continued employment with the Defendant and there was
no agreement to continue the 2011 Contract.
142. The Claimant continued in the same paragraph of the said letter “I wish, in accepting the
Authority’s offer to address your concerns/ questions with respect to the remuneration
package attaching to the post, both at present and in the future”. In my opinion, if the 2013
Contract was entered into at the January 2013 meeting and the Claimant was due to start
on the 1 March 2013 as he asserted, he would have expressly indicated this in the said letter
and not refer to the remuneration package for the post of CEO of PPOS “in the future”. In
the last paragraph of the said letter, the Claimant stated “...I thank the Authority for the
opportunity to continue to serve for another contract term”. Again if the Claimant knew, as
he has asserted in this case, that the 2013 Contract was entered into at the January 2013
meeting, he would have expressly stated that his service for another contract term was to
start on the 1 March 2013. However, he failed to do so.
Page 43 of 49
143. In any event, the Claimant agreed in cross examination that Mr Toney’s email dated 22
January 2013 to him, never stated that he needed to get advice on remuneration only.
Therefore based on the Claimant’s own evidence, Mr Toney’s conduct up to the 22 January
2013 did not clearly demonstrate that the only issue outstanding in the 2013 Contract was
remuneration. Based on the said email, Mr Toney version was more probable, namely after
the January 2013 meeting the parties were still in discussion about the terms of the 2013
Contract.
144. The two correspondence which were written after the 24 January 2013 and before the
February 2013 meeting were the memorandum dated 21 February 2013 from Ms Mark to
Mr Toney, on the results of the exercise to determine the remuneration package for the CEO
of PPOS, and the letter dated 25 February 2013 from Mr Toney to the Permanent Secretary
with the proposal for the remuneration package for the post of CEO of PPOS.
145. Senior Counsel for the Claimant argued that the conjoint effect of the memorandum dated
21 February 2013 from Ms Mark to Mr Toney, Mr Toney’s letter dated 25 February 2013 to
the Permanent Secretary and Mr Toney’s evidence in cross examination were consistent
with the position that Mr Toney and the Claimant agreed at the January 2013 meeting that
the latter would be employed by the Defendant as the CEO of PPOS on terms to be
determined by the CPO.
146. As I have stated previously, it was not the Claimant’s pleaded case that he entered into the
2013 Contract at the January 2013 meeting on terms to be agreed by the CPO.
147. The contents of the memorandum dated 21 February 2013 to Mr Toney were instructive. In
my opinion, it did not support the Claimant’s assertion that Mr Toney and the Claimant
agreed at the January 2013 meeting that the Claimant would be employed by the Defendant
as CEO of PPOS with effect from 1 March 2013 for the following reasons. The subject matter
of the said memorandum was “PROPOSED REMUNERATION PACKAGES FOR CEOS OF
COMPANIES UNDER PATT”. It was not the proposed remuneration package for “Mr Colin
Page 44 of 49
Lucas, CEO of PPOS”. The first line of the memorandum stated that its purpose was to
determine the remuneration package for the position of CEO of PPOS. It did not state that
its purpose was to determine a remuneration package for the Claimant for the 2013
Contract. Further, the memorandum explained the reasons it did not only consider the
remuneration package for CEO of PPOS and the methodology used in determining the
remuneration package for the positions of CEO of PPOS, and two other CEO positions
namely, CEO of TTIT and CEO of POSINCO.
148. In my opinion if Mr Toney had entered into the 2013 Contract with the Claimant at the
January 2013 meeting, it is more probable that his instructions to Ms Mark would have been
to only determine a remuneration package for the Claimant as opposed to the post of CEO
of PPOS. Further, it was also more probable that if there was a 2013 Contract for the
Claimant, which was supposed to commence on the 1 March 2013, Ms Mark who was the
Acting GM on the 21 February, 2013 would have stated in the said memorandum that the
report was for the remuneration of the Claimant in the post of CEO of PPOS with effect from
1 March 2013. In my opinion, this notable omission in the memorandum dated 21 February
2013, supported the Defendant’s version that there was no 2013 Contract with the Claimant
which was supposed to commence on 1 March 2013.
149. The letter from Mr Toney to the Permanent Secretary dated 25 February 2013 dealt with
two matters. It stated that the Board of the Defendant had approved an interim
compensation package on 14 April 2011 for the combined positions of CEO of PPOS/
GM/CEO PATT on a two year contractual basis subject to ratification by the CPO. It also
stated its recommendation of the position of GM/ CEO of PATT on contract and CEO of PPOS
on Contract. In my opinion, this correspondence did not assist the Claimant’s case that he
entered into the 2013 Contract with Mr Toney at the January 2013 meeting since it did not
expressly state that the Board of the Defendant had approved any 2013 Contract for any
person, including the Claimant. It also did not state that any interim contract commencing 1
March 2013 was approved for the Claimant.
Page 45 of 49
150. Therefore, at its highest, the actions by Mr Toney in seeking out information concerning the
remuneration for the post of CEO of PPOS, which Ms Mark sent to him in the memorandum
dated 21 February 2013 and his letter dated 25 February 2013 to the Permanent Secretary
were all consistent with the Defendant’s established practice of seeking the CPO’s approval
for a remuneration package for an executive management position at the Defendant such
as for the post of CEO of PPOS, before the latter entered into any contract with any person
for the position. Mr Toney’s actions were also consistent with the Defendant’s case that
there was no approval from the Board of the Defendant for the 2013 Contract for the
Claimant.
151. The February 2013 meeting took place on the 27 February 2013. There was common ground
that at the February 2013 meeting, Mr Toney advised the Claimant that a new Board of the
Defendant was to be installed and that the former instructed the latter to proceed on 13
days’ vacation leave from the 1 March 2013. The dispute was what the new Board of the
Defendant was supposed to discuss. In my opinion, Mr Toney’s version that the new Board
of the Defendant was to consider and approve a new contract for the Claimant (as opposed
to the Claimant’s version that it was supposed to only settle the issue of remuneration) was
more plausible for the following reasons. Both the Claimant and Mr Toney were aware that
a contract for a senior manager such as the CEO of PPOS had to be approved by the Board
of the Defendant; there was no such approval from the previous Board and there was no
written notation in any of the contemporaneous documents of such approval.
152. Further, Mr Toney admitted in cross examination that at the time of the February 2013
meeting, he was in receipt of the Claimant’s letter dated 18 January 2013. In my opinion, if
the Claimant had clearly asserted in the said letter to the Claimant that he was of the view
that he had a contract to work as the CEO of PPOS from the 1 March 2013, it was more
probable than not, that Mr Toney would have addressed this at the February 2013 meeting.
However, there was no such assertion by the Claimant.
Page 46 of 49
153. At the February 2013 meeting, Mr Toney had instructed the Claimant to immediately embark
on the 13 days unused vacation leave from the 1 March 2013 but on the following day, by
memorandum dated 28 February 2013 from Mr Toney to Ms Bruno, he cancelled his
instructions and instead directed the Claimant be paid his unutilised vacation leave.
154. Senior Counsel for the Claimant argued that Mr Toney’s actions to cancel his decision for the
Claimant to take leave from 1 March 2013 and his direction to roll-over the unused leave,
were indicative that he knew, at the January 2013 meeting, he had already entered into the
2013 Contract with the Claimant to employ him as CEO of PPOS with effect from 1 March
2013, on terms to be determined by the CPO.
155. Mr Toney explained in cross examination that overnight, after the February 2013 meeting,
he realised that if he had told the Claimant to start his vacation leave by the 1 March 2013
he would have been finalising a new contract of employment with the Claimant, an authority
which he did not.
156. I accept Mr Toney’s explanation for cancelling the Claimant’s vacation leave and instead
directing him to be paid was reasonable as he acted quickly after realising his error. In my
opinion, this singular act by Mr Toney of approving the Claimant’s vacation leave and then
cancelling it within 1 day thereafter cannot be examined in isolation but must be taken in
the context of the nature of the discussions at the January 2013 meeting, the knowledge by
both the Claimant and Mr Toney that shortly after the January 2013 meeting there was no
quorum of the Board of the Defendant to make decisions and the contents of
correspondence which were written thereafter by both parties.
157. Further, I have not attached any weight to the letter of Ms Bruno dated 1 March 2013, which
she sent to the Claimant and in which she stated that “ Please be further advised that item
(2) [ie approval for payment for the balance of Mr Lucas’ vacation leave amounting to
thirteen (13) days] be rolled over into Mr Lucas’ next contract term” as she was not called
Page 47 of 49
as a witness and Mr Toney’s instructions stated "future employment" which was different
from stating a commencement date of 1 March 2013.
158. It was not in dispute that in response to Ms Bruno’s letter of the 1 March 2013, the Claimant
wrote a letter of 4 March, 2013 to Mr Toney in connection with the latter’s change of
instructions for the Claimant to go on leave. In that letter, he asserted that he had entered
into the 2013 Contract at the January 2013 meeting. It was not in contention that Ms Ford
replied by letter dated 5 March 2013 requesting the basis for the Claimant’s assertion of the
2013 Contract.
159. The Claimant’s evidence was that he had a telephone conversation with Mr Toney on the 5
March 2013 and Mr Toney did not indicate to him that he was not working in accordance
with the 2013 Contract. Mr Toney’s version of that conversation was that he asked the
Claimant to submit details of the days he had worked without compensation and that the
Claimant replied by letter dated 5 March 2013. In the Claimant’s letter dated 5 March 2013,
he indicated the days he worked certain days between 26 and 31 January 2013 and the
nature of is work.
160. Notably, there was no assertion by the Claimant that in the conversation he had with Mr
Toney on the 5 March 2013, Mr Toney indicated that he was working in accordance with the
2013 Contract. Indeed, the nature of the conversation between Mr Toney and the Claimant
on the 5 March 2013 was consistent with Mr Toney’s position that the Claimant was to be
paid for his unused vacation leave. In my opinion, given the sequence of events from the
January meeting up until this discussion, it was not important for Mr Toney to raise in any
conversation with the Claimant anything about the 2013 Contract. Rather, it was more
important for the Claimant to do so as he was the one who took the position that he had
entered into the 2013 Contract at the January 2013 meeting.
161. Further, in the Claimant’s letter dated 7 March 2013, to Ms Ford, he still recognised that the
2013 Contract was not approved by the Board of the Defendant which was consistent with
Page 48 of 49
Mr Toney’s version of the February 2013 meeting. In the said letter, the Claimant stated,
“the determinates of the new package would require in any event Board consideration and
alternatively, sanction of the Chief Personnel Officer, a process with which I indicated both
my familiarity and comfort.”
162. The Permanent Secretary replied to Mr Toney’s letter dated 25 February 2013 by letter
dated 26 August 2013. The letter dated 26 August 2013 indicated that the CPO approved a
compensation package to be paid to the Claimant under the 2011 Contract for the period 1
March 2011 to 28 February 2013; the compensation package to be paid to the GM/CEO PATT
at basic monthly salary of $45,000 to $50,000 for the duration of 1 March 2013 to 29
February, 2016 and CEO of PPOS at a basic monthly salary of $40,000 to $45,000 for the
duration of 1 March 2013 to 29 February 2016.
163. In my opinion, this letter assisted the Defendant’s case as it was more probable that the
approval for the 2011 Contract stated the Claimant’s name as there was an Interim Contract
which was approved by the Board of the Defendant. However, by the said letter not
expressly stating that the approval of the CPO for the post of CEO of PPOS was for the
Claimant for the period 1 March 2013 to 29 February 2016, this was consistent with the
Defendant’s position that there was no 2013 Contract and there was no approval by the
Board of the Defendant of any Interim Contract.
164. Therefore, I am of the opinion for the reasons set out aforesaid, that based on the evidence
and the contemporaneous documents after the January 2013 meeting, Mr Toney’s actions,
after the said meeting were not indicative that he had entered into the 2013 Contract with
the Claimant at the said meeting.
IF THE 2013 CONTRACT IS VALID, IS IT ENFORCEABLE?
165. Having concluded that there was no 2013 Contract this issue does not arise for
determination.
Page 49 of 49
WHAT MEASURE OF DAMAGES IS THE CLAIMANT ENTITLED TO IF HE PROVES HE WAS
WRONGFULLY TERMINATED?
166. There is no need for me to address this issue in any significant detail as I have found that
there was no valid and subsisting 2013 Contract. In so finding the Claimant failed to prove
the breach of any alleged 2013 Contract, therefore there was no loss suffered. In any event,
the Claimant did not dispute that he was paid for the days he actually worked after the
expiration of the 2011 Contract23.
COSTS
167. I have no exceptional circumstances to deviate from the general rule that the successful
party is entitled to its costs. In terms of quantum, on the 10 April 2018 a cost budget was set
for the action in the sum of $519,630.00. There were no submissions made by the parties to
reduce the sum set in the said order. Therefore, I order that the Claimant is to pay the
Defendant its costs in the sum of $519,630.00.
ORDER
168. The Claimant’s action is dismissed.
169. The Claimant to pay the Defendant’s in the sum of $519,630.00 as set by the budgeted cost
order dated the 10 April 2018.
Margaret Y. Mohammed
Judge
23 Exhibit PO1 attached to the Amended Defence