153
Republic of the Philippines Autonomous Region in Muslim Mindanao DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS ARMM Complex, Cotabato City BONGAO, TAWI-TAWI BONGAO, TAWI-TAWI BIOSONG, LDS TALIPAO, SULU TUBURAN, BASILAN PARANG, SULU LUUK, SULU EMIL K. SADAIN, CESO II Regional Secretary 11 TH EXPANDED CABINET MEETING Waterfront Hotel,Davao City, December 21-22, 2013 Hon. MUJIV S. HATAMAN ARMM Regional Governor H.E. BENIGNO S. AQUINO, III President of the Philippines SULTAN KUDARAT, MAG. PERSPECTIVE OF NEW ORG BUILDING

Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

Embed Size (px)

Citation preview

Page 1: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

Republic of the Philippines

Autonomous Region in Muslim Mindanao

D E P A R T M E N T O F P U B L I C W O R K S A N D H I G H W A Y S ARMM Complex, Cotabato City

BONGAO, TAWI-TAWI

BONGAO, TAWI-TAWI BIOSONG, LDS TALIPAO, SULU TUBURAN, BASILAN

PARANG, SULU LUUK, SULU

E M I L K . S A D A I N , C E S O I I

R e g i o n a l S e c r e t a r y

1 1T H

E X P A N D E D C A B I N E T M E E T I N G

W a t e r f r o n t H o t e l , D a v a o C i t y , D e c e m b e r 2 1 - 2 2 , 2 0 1 3

Hon. MUJIV S. HATAMAN ARMM Regional Governor

H.E. BENIGNO S. AQUINO, III President of the Philippines

SULTAN KUDARAT, MAG.

PERSPECTIVE OF NEW ORG BUILDING

Page 2: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

I. MANDATE

Page 3: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

MANDATE DPWH-ARMM as the infra arm implement infrastructure programs and projects within the region.

LEGAL BASES

RA 6734. The Organic Act for the Autonomous Region in Muslim Mindanao was approved by then President Corazon C. Aquino last August 1, 1989 and ratified through a plebiscite last November 19, 1989 by the constituents of the region. RA 9054. An act to strengthen and expand the organic act for the Autonomous Region in Muslim Mindanao, amending for the purpose Republic Act No. 6734, entitled “An act providing for the Autonomous Region in Muslim Mindanao” as amended. Executive Order No. 426. Issued by President Corazon C. Aquino on October 12,1990 devolved the Department of Public Works and Highways to the Autonomous Region in Muslim Mindanao. Muslim Mindanao Autonomy Act (MMA). An act providing for a Regional Public Works Act for ARMM Infra 2012/2013.

VISION

An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure facilities and services in the ARMM government through sustainable developmental programs toward upliftment of socio- economic well being of its constituents by the end of 2015.

MISSION To carry out the implementation of infrastructure programs and projects within the ARMM.

CORE VALUES Public Service, Integrity, Professionalism, Excellence and Team Work.

KEY RESULT AREAS Road Network and Other Public Infrastructure Facilities.

Page 4: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

II. EXECUTIVE SUMMARY

Page 5: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

1. INITIATED AMENDMENT/ REVISION OF 2012 PUBLIC

WORKS ACT

No more Lump sum funding

No more regravelling

No more MOA on Major Infra

Page 6: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

2. 2012, 2013 & 2014 INFRA PROGRAMS AND TARGETS IMPLEMENTED/FOR IMPLEMENTATION.

CY 2012 costing P1 Billion involved construction/rehab of 37.872 kms national and local roads; construction/rehab of 9 sea ports; and construction of 5 bridges, 5 water supply projects and 2 other structures.

CY 2013 costing P1.5 Billion involved construction/rehab of 85.521 kms national and local roads; construction/rehab of 7 sea ports; and construction of 3 bridges, 2 drainage structures, 11 water supply projects and 6 other structures.

CY 2014 costing P5.025 Billion consist of rehab/ construction of 431 kms of national and local roads; construction/rehab of 13 bridges; construction/expansion of 17 sea ports and 30 water supply projects; and construction of 12 drainage structures.

Page 7: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

3. GENERATED SAVINGS FROM PRUDENT FISCAL MANAGEMENT

P190.797 M as of November 30, 2013.

DBM lauded DPWH-ARMM for the prudent used of its 2012 budget.

Page 8: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

4. ENSURED CLEAN AND HONEST COMPETITIVE PUBLIC BIDDING WITH SAVINGS GENERATED

I. EQUIPMENTS AND VEHICLES (All Budget derived from savings)

CONTRACT UNITS /

PROJECTS ABC

AMOUNT OF CONTRACT

CONTRACTOR / SUPPLIER

DATE OF CONTRACT

SIGNING

VARIANCE / SAVINGS

1) 1st Tranche 23 P47,700,000.00 P43,868,000.00 P3,832,000.00

a. Lot I - Supply and Delivery of Heavy Equipments

8 P38,100,000.00 P34,290,000.00 Tiger Motor Sales, Cebu City

Oct. 11, 2012

P3,810,000.00

b. Lot II - Supply and Delivery of Motor Vehicles

6 P6,500,000.00 P6,500,000.00 Toyota & Ford, Davao City

c. Lot III - Supply and Delivery of Survey Instruments

9 P3,100,000.00 P3,078,000.00 N.R. Estaquio, Davao City

Dec. 21, 2012

P22,000.00

2) 2nd Tranche 13 P23,094,000.00 P22,307,000.00 P786,577.00

a. Lot I - Supply and Delivery of Heavy Equipments

5

P9,594,000.00

P8,809,343.00

United Asia Automotive Group, Inc. (UAAGI)

Mar. 26, 2013 P784,657.00

b. Lot II - Supply and Delivery of Motor Vehicles

8 P13,500,000.00 P13,498,080.00 United Asia Automotive Group, Inc. (UAAGI)

Mar. 26, 2013 P1,920.00

3) 3rd Tranche 11 P27,419,000.00 P26,918,500.00 P500,500.00

a. Lot I - Supply and Delivery of Various Types of Heavy Equipment

9 P24,715,000.00 P24,215,000.00 D'Limitless Vehicles Oct. 4, 2013 P500,000.00

b. Lot II - Supply and Delivery of Motor Vehicles

2 P2,704,000.00 P2,703,500.00 MTL Gensan Motors, Inc.

Nov. 19, 2013 P500.00

4) 4th Tranche 11 P54,236,000.00 (Request for reallignment of MOOE Savings to Equipment Outlay, currently under process by the Department of Budget and Management)

SUB TOTAL 58 P152,449,000.00 P93,093,923.00 P5,119,077.00

Page 9: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

CONTRACT UNITS / PROJECTS

ABC AMOUNT OF CONTRACT

CONTRACTOR / SUPPLIER

DATE OF CONTRACT

SIGNING

VARIANCE / SAVINGS

1. Contract Package 1: 2 P23,317,970.27 P23,262,482.37 FIAT Const. Jan. 10, 2013 P55,487.90

a) Construction of Ganassi-Tubod Road, Madamba Section, Lanao del Sur II

b) Construction of Masiu Ganassi Road, Bayang section, Lanao del Sur

2. Contract Package 2: 2 P33,465,014.23 P33,299,355.81 MUST Ent. & Const. Feb. 12, 2013 P165,658.42

a) Reblocking along Cotabato - Lanao / Davao Road (Macaguiling to Dalumangcob Section) with exeptions, Sultan Kudarat, Maguindanao

b) Reblocking along Marbel –Ala Valley Road (Bitu to Dulungan Section), Datu Ondin Sinsuat, Maguindanao

3. Contract Package 3: 1 P11,154,984.93 P9,467.593.98 BAMEC Developer March 14, 2013 P1,687,391.92

a) Concrete Pavement Widening of Marbel - Ala - Cotabato Road (Poblacion Shariff Aguak Section), Maguindanao

4. Contract Package 4A: DESIGN AND BUILD 1 P22,310,000.00 P22,309,999.98 Basilan C & J Const. March 14, 2013 P0.02

a) Road Upgrading (Gravel to Paved) Concrete Pavement, Lamitan - Tuburan Road, Km. 26+690 to Km. 37+690, (Net Length = 1.00 Km.)

5. Contract Package 4B: DESIGN AND BUILD 1 P56,671,000.00 P54,970,870.00 BSP & Co./ March 14, 2013 P1,700,130.00

a) Road Concreting of Sumisip Junction to Proposed Buli - Buli Port, (Length=3.063 km.)

M. Abubakar Const.

II. CIVIL WORKS

4. ENSURED CLEAN AND HONEST COMPETITIVE PUBLIC BIDDING WITH SAVINGS GENERATED

Page 10: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

CONTRACT UNITS / PROJECTS

ABC AMOUNT OF CONTRACT

CONTRACTOR / SUPPLIER

DATE OF CONTRACT

SIGNING

VARIANCE / SAVINGS

6. Contract Package 4C: DESIGN AND BUILT 3 P91,181,000.00 P91,160,211.60 ESR Const. & Supply March 14, 2013 P20,788.40

a) Construction of Bacung Bridge, Sumisip, Basilan, Km. 67+986

b) Construction of Limbo Candiis Bridge, Sumisip, Basilan, Km. 76+950

c) Construction of Giong Bridge, Sumisip, Basilan, Km. 70+950

7. Repair of National Road along 1 P15,531,432.27 P15,378,752.00 BAMEC Developer July 10, 2013 P152,680.37

a) Lanao Road (Parang - Malabang Section), Brgy. Bayanga, Matanog, Maguindanao

8. Contract Package 4G: DESIGN AND BUILT 2 P63,050,000.00 P63,021,744.18 Roge Basilan C&J JV Nov. 19, 2013 P28,255.82

a) Construction of Road from Lamitan Proper - Brgy.Kulay Bato - Brgy.Bulanting - Brggy.Bato-Bato - Brgy. Semmut Phase I, Akbar, Basilan (1.250 Km.)

b) Construction of 2.5 Km. Sironggon – Buton Road, Muhammad Ajul, Basilan

9. Contract Package 1: 2 P38,703,000.00 P38,590,894.30 FFJJ Const. Nov. 25, 2013 P112,015.70

a) Concrete Reblocking along Marbel-Ala-Cotabato Road (Margues-Bitu-Dulangan Sections), KM.1836+000 to Km.1841+000 w/ exceptions, Datu Odin Sinsuat, Maguindanao

b) Concrete Reblocking along Cotabato-Lanao/Davao Road (Sultan Kudarat, Maguindanao Section ) w/ exception Sultan Kudarat, Maguindanao

II. CIVIL WORKS

4. ENSURED CLEAN AND HONEST COMPETITIVE PUBLIC BIDDING WITH SAVINGS GENERATED

Page 11: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

CONTRACT UNITS / PROJECTS

ABC AMOUNT OF CONTRACT

CONTRACTOR / SUPPLIER

DATE OF CONTRACT

SIGNING

VARIANCE / SAVINGS

10. Contract Package 2: 1 P62,105,220.00 P62,036,982.70 FFJJ Construction Nov. 25, 2013 P68,236.30

a) Construction/Concreting of Paglas - Columbio Provincial Road, Sta. 0+000 to Sta. 4+322, Paglas - Columbio Provincial Road, Maguindanao

11. Contract Package 3: 1 P58,200,000.00 P57,961,110.30 FFJJ Construction Nov. 25, 2013 P238,889.70

a) Construction/Concreting of Maslabeng Provincial Road, Sta. 0+000 to Sta. 3+740, Buluan, Maguindanao

12. Contract Package 4D: DESIGN AND BUILD 2 P87,300,000.00 P87,279,966.64 ESR Const. & Supply Nov. 25, 2013 P20,033.36

a) Construction of Road from Bato - Bato Port Al-barka - Kaili Ginanta - Magkawa (Phase I), Al-barka, Basilan (4.0 Km. Concreting and 6.0 Km. Road Opening), Basilan

b) Construction of Bato-Bato Port, Al-Barka, Basilan

13. Contract Package 4E: DESIGN AND BUILD 2 P53,482,000.00 P53,399,838.47 ASAP Gen. Trading Nov. 25, 2013 P82,161.53

a) Construction of Water System, Level III, Sumisip, Basilan

b) Concreting of 1 Km. Circumferential Road from Bitayan – Basak , Phase II, Sumusip, Basilan

Construction and Maintenance

14. Contract Package 4F: DESIGN AND BUILD 2 P9,700,000.00 P9,669,394.44 RAIN Construction Nov. 25, 2013 P30,605.56

a) Construction of Tinusa Port, Sumisip, Basilan

b) Construction of Sullo Port, Tabuan Lasa, Basilan

and APPLE Const Joint Venture

II. CIVIL WORKS

4. ENSURED CLEAN AND HONEST COMPETITIVE PUBLIC BIDDING WITH SAVINGS GENERATED

Page 12: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

CONTRACT UNITS / PROJECTS

ABC AMOUNT OF CONTRACT

CONTRACTOR / SUPPLIER

DATE OF CONTRACT

SIGNING

VARIANCE / SAVINGS

15. Contract Package 4I: DESIGN AND BUILD 3 P14,550,000.00 P14,536,460.97 RAIN Construction Nov. 25, 2013 P13,539.03

a) Construction of Steel Bridge Sub-structure, Buli-Buli - Tekos Coastal Road, Sumisip, Basilan

b) Construction of Steel Bridge Sub-structure, Basak – Babag Bato Coastal Road, Sumisip, Basilan

c) Construction of Steel Bridge Sub-structure, Brgy. Road, Sumisip, Basilan

and APPLE Const Joint Venture

16. Contract Package 4J: DESIGN AND BUILD 2 P38,800,000.00 P38,732,950.26 ASAP Gen. Trading Nov. 25, 2013 P67,194.74

a) Concreting of 1.20 Km. Circumferential Road from Bitayan - Basak, Sumisip, Basilan

b) Construction of Buli – Buli Port, Sumisip, Basilan

Construction and Maintenance

SUB TOTAL 28 P679,521,621.80 P675,078,698.03 P4,442,923.77

CONTRACT UNITS / PROJECTS

ABC AMOUNT OF CONTRACT

CONTRACTOR / SUPPLIER

DATE OF CONTRACT

SIGNING

VARIANCE / SAVINGS

1. Contract Package 5A: 4 P13,500,000.00 P13,498,080.00 Woodfields March 26, 2013 P1,920.00

Consultancy Services for the Conduct of Feasibility Studies and Detailed Eng'g Designs of High Impact Infrastructure Projects

a) Sumisip Water System Project and Drainage Improvement

b) Rehabilitation and Expansion of Jolo Water Supply Project under Public Private Partnership Program

Consultants Inc.

II. CIVIL WORKS

III. CONSULTANCY

4. ENSURED CLEAN AND HONEST COMPETITIVE PUBLIC BIDDING WITH SAVINGS GENERATED

Page 13: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

CONTRACT UNITS / PROJECTS

ABC AMOUNT OF CONTRACT

CONTRACTOR / SUPPLIER

DATE OF CONTRACT

SIGNING

VARIANCE / SAVINGS

1. Contract Package 5A: (Cont.) c) Jolo National Road and Drainage

Improvement Project

d) Development of Lamitan-Sumisip Trancentral Road

2. Consulting Services for the Development of Expanded ARMM Roads Mapping and Management System (e-ARMM)

1 P2,500,000.00 P2,498,000.00 Woodfields Consultants Inc.

Oct. 4, 2013 P2,000.00

3. For Bidding Process Conducting Feasibility Study Inclusive of Detailed Design and Program of Works

a) Expansion of Lamitan City Water System, Basilan

b) Sagay-Sagay Water System serving the Municipality of Talipao, Panamao, Omar, Panglima Estin and Kalingalan Caluang, all of Sulu Province

c) Expansion of Datu Odin Sinsuat Water System serving Mun. of DOS, Kabuntalan and nearby Municipality, all of Maguindanao

d) Urban Planning of Buli-Buli, Sumisip, Basilan

4 P9,700,000.00

SUB TOTAL 9 P25,700,000.00 P15,996,080.00 P3,920.00

GRAND TOTAL P857,670,621.80 P784,168,701.03 P9,565,920.77

CONSULTANCY

4. ENSURED CLEAN AND HONEST COMPETITIVE PUBLIC BIDDING WITH SAVINGS GENERATED

(Bidding in progress)

Page 14: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

5. ACQUIRED EQUIPMENT AND VEHICLES WITH FUNDING FROM SAVINGS.

PROCURED 22 UNITS HEAVY EQUIPMENT, 16 UNITS MONITORING VEHICLES AND 9 UNITS SURVEY INSTRUMENTS. ABOUT 11 MORE NEW HEAVY EQUIPMENT BEING PIPELINED FOR PROCUREMENT IN JANUARY 2014.

TOTAL COST IS P150 MILLION.

Page 15: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

6. DEVELOPED POLICY & INSTITUTIONAL REFORMS AND CAPACITY BUILDING/ENHANCEMENT

ADOPTED DPWH-ARMM REFORM AGENDA 2012 AND BEYOND

CONSTRUCTION OF NEW BUILDING FOR NEWLY DEVOLVED BASILAN DISTRICT ENGINEERING OFFICE

CONSTRUCTION OF NEW BUILDING FOR LANAO DEL SUR 2ND DISTRICT ENGINEERING OFFICE

NEW LANAO SUR 2ND DEO

NEW BASILAN SATELLITE DEO

LAUNCHING OF DPWH-ARMM REFORM AGENDA 2012 AND BEYOND

Page 16: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

6. DEVELOPED POLICY & INSTITUTIONAL REFORMS AND CAPACITY BUILDING/ENHANCEMENT

CONSTRUCTION OF MANAGEMENT INFORMATION

SYSTEM BUILDING AND DPWH-ARMM STAFF HOUSE.

RENOVATION/EXPANSION OF DPWH-ARMM BUILDINGS, DEOs AND AEOs.

MAIN BUILDING OPERATIONS BUILDING

STAFF HOUSE

MIS BUILDING

Page 17: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

6. DEVELOPED POLICY & INSTITUTIONAL REFORMS AND CAPACITY BUILDING/ENHANCEMENT

CREATION OF NEW PLANTILLA FOR BASILAN DISTRICT ENGINEERING OFFICE, MAGUINDANAO 1ST DISTRICT ENGINEERING OFFICE AND LANAO DEL SUR 2ND DISTRICT ENGINEERING OFFICE.

CONDUCTED TRAININGS ON PROCUREMENT,

CONTRACT MANAGEMENT, MATERIALS QUALITY CONTROL, RoCon SURVEY, VALUES FORMATION AND INTEGRITY DEVELOPMENT. ALSO PIPELINED IN 2014 ARE DISTRICT ENGINEERS TRAINING COURSE, PROJECT ENGINEERS TRAINING COURSE, TRAINING ON PROJECT CONSTRUCTION MANAGEMENT AND FLOOD CONTROL MITIGATION.

Page 18: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

III. THE REPORT

Page 19: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

3.1 DETAILED TECHNICAL REPORT

Page 20: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

DISTRICT ENGINEERING OFFICE

APPROPRIATION IN MILLION PESOS

(1)

% OF ACTUAL ACCOMPLISHMENT

BY DEO

(2)

EQUIVALENT WEIGHTED % BY DEO

PROGRAM (3)

ACCOMPLISHMENT (4)=(2X3)/100

1. BASILAN DEO* 345.471 26.50 35.11 9.39

2. SULU 1ST DEO 123.810 90.47 12.58 11.38

3. SULU 2ND DEO 84.00 63.39 8.54 5.41

4. TAWI-TAWI DEO 155.995 71.09 15.85 11.27

5. MAGUINDANAO 1ST DEO 70.500 77.90 7.18 5.59

6. MAGUINDANAO 2ND DEO 67.550 73.18 6.69 4.89

7. LANAO DEL SUR 1ST DEO 75.634 86.50 7.69 6.63

8. LANAO DEL SUR 2ND DEO 62.040 59.62 6.37 3.79

TOTAL 985.00 100.00 58.34

SUMMARY STATUS OF 2012 REGULAR INFRA

As of December 16, 2013

BASILAN DEO

SULU-I DEO SULU-II DEO

TAWI-TAWI DEO

MAG. I DEO

MAG. II DEO

LANAO-I DEO LANAO-II DEO

*NEWLY DEVOLVED DEO TO ARMM/DPWH-ARMM

P345.471M (35.11%)

P62.040M (6.37%)

P75.634M (7.69%)

P67.55M (6.69%)

P70.50M (7.18%)

P155.995M (15.85%)

P84M (8.54%)

P123.81M (12.58%)

CAPITAL OUTLAY: P1 Billion (less P15 M PDES)

Page 21: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

SUMMARY MODE OF 2012 IMPLEMENTATION

As of December 16, 2013

MODE OF IMPLEMENTATION

NO. OF PROJ.

(1)

APPROPRIATION BY MODE

IN MILLION PESOS

(2)

PHYSICAL % ACCOM. /MODE

(3)

EQUIVALENT WEIGHTED % OF ACCOM./MODE

(4)

TOTAL WEIGHTED % OF

ACCOM./MODE (5)=(3X4)/100

By Administration 28 430.86 71.25 43.74 31.17

By MOA 16 270.43 65.31 27.455 17.93

By Contract 12 283.71 32.08 28.80 9.24

TOTAL 56 985.00 100.00 58.34

MODE OF IMPLEMENTATION

ADMIN MOA CONTRACT

APPROPRIATION BY MODE

P430.86 M (43.74%)

P283.71 M (28.80%) P270.43 M

(27.455%)

16 PROJ. 12 PROJ. 28 PROJ.

CAPITAL OUTLAY: P1 Billion (less P15 M PDES)

Page 22: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

SUMMARY STATUS OF 2013 REGULAR INFRA

As of December 16, 2013

BASILAN DEO

SULU-I DEO

SULU-II DEO

TAWI-TAWI DEO

MAG. I DEO

MAG. II DEO

LANAO-I DEO LANAO-II DEO

DISTRICT ENGINEERING OFFICE

APPROPRIATION IN MILLION PESOS

(1)

% OF ACTUAL ACCOMPLISHMENT

BY DEO

(2)

EQUIVALENT WEIGHTED % BY DEO

PROGRAM (3)

ACCOMPLISHMENT (4)=(2X3)/100

1. BASILAN DEO* 398.637 3.75 26.57 1.00

2. SULU 1ST DEO 364.118 20.65 24.27 5.01

3. SULU 2ND DEO 88.00 15.95 5.87 0.94

4. TAWI-TAWI DEO 169.00 62.25 11.27 7.01

5. MAGUINDANAO 1ST DEO 99.90 16.22 6.66 1.08

6. MAGUINDANAO 2ND DEO 191.526 27.78 12.77 3.55

7. LANAO DEL SUR 1ST DEO 115.00 54.11 7.67 4.15

8. LANAO DEL SUR 2ND DEO 74.00 50.40 4.93 2.48

TOTAL 1,500.181 100.00 25.22

*NEWLY DEVOLVED DEO TO ARMM/DPWH-ARMM

P74 M (4.93%)

P115 M (7.67%)

P191.526M (12.77%)

P99.9M (6.66%)

P169M (11.27%)

P88M (5.87%)

P364.118M (24.27%)

P398.637M (26.57%)

CAPITAL OUTLAY: P1,510.181 Million (less P10 M PDES)

Page 23: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

MODE OF IMPLEMENTATION

NO. OF PROJ.

(1)

APPROPRIATION BY MODE

IN MILLION PESOS

(2)

PHYSICAL % ACCOM. /MODE

(3)

EQUIVALENT WEIGHTED % OF ACCOM./MODE

(4)

TOTAL WEIGHTED % OF

ACCOM./MODE (5)=(3X4)/100

By Administration 56 830.32 28.45 54.68 15.56

By MOA 35 280.80 51.62 18.718 9.66

By Contract 15 399.06 0 26.60 0

TOTAL 106 1,500.181 100.00 25.22

SUMMARY MODE OF 2013 IMPLEMENTATION

As of December 16, 2013

MODE OF IMPLEMENTATION

ADMIN MOA CONTRACT

APPROPRIATION BY MODE

P830.32M (54.68%)

P399.06 M (26.60%)

P280.80 M (18.718%)

35 PROJ. 15 PROJ. 56 PROJ.

CAPITAL OUTLAY: P1,510.181 Million (less P10 M PDES)

Page 24: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

SUMMARY STATUS OF 2014 REGULAR INFRA/OPAPP

As of December 16, 2013

BASILAN DEO

SULU-I DEO

SULU-II DEO

TAWI-TAWI DEO

MAG. I DEO

MAG. II DEO LANAO-I DEO

LANAO-II DEO

DISTRICT ENGINEERING OFFICE

APPROPRIATION IN MILLION PESOS

% OF ACTUAL ACCOMPLISHMENT

BY DEO

(2)

EQUIVALENT WEIGHTED % BY DEO

REGULAR OPAPP TOTAL

(1) PROGRAM

(3) ACCOMPLISHMENT

(4)=(2X3)/100

1. BASILAN DEO* 902.80 655.00 1,557.80 31.10 2. SULU 1ST DEO 606.60 502.60 1,109.20 22.15 3. SULU 2ND DEO 189.20 50.00 239.20 4.78 4. TAWI-TAWI DEO 347.60 121.40 469.00 9.36 5. MAGUINDANAO 1ST DEO 364.80 260.83 625.63 12.49 6. MAGUINDANAO 2ND DEO 174.80 270.00 444.80 8.89 7. LANAO DEL SUR 1ST DEO 251.80 63.00 314.80 6.28 8. LANAO DEL SUR 2ND DEO 118.40 129.57 247.97 4.95 TOTAL 2,956.000 2,052.40 5,008.40 100.00 *NEWLY DEVOLVED DEO TO ARMM/DPWH-ARMM

P247.97M (4.95%)

P314.80 M (6.28%)

P444.80M (8.89%)

P625.63M (12.49%)

P469.00M (9.36%)

P239.20M (4.78%)

P1,109.20M (22.15%)

P1,557.80 M (31.10%)

CAPITAL OUTLAY: 5.0234 Billion (less P15 M PDES)

Page 25: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

MODE OF IMPLEMENTATION

NO. OF PROJ.

(1)

APPROPRIATION BY MODE

IN MILLION PESOS

(2)

PHYSICAL % ACCOM. /MODE

(3)

EQUIVALENT WEIGHTED % OF ACCOM./MODE

(4)

TOTAL WEIGHTED % OF

ACCOM./MODE (5)=(3X4)/100

By Administration 167 3,505.88 70

By MOA 24 500.84 10

By Contract 48 1,001.68 20

TOTAL 239 5,008.40 100.00

SUMMARY MODE OF 2014 IMPLEMENTATION

As of December 16, 2013

MODE OF IMPLEMENTATION

ADMIN MOA CONTRACT

APPROPRIATION BY MODE

P3,505.88M (70%)

P1,001.68 M (20%)

P500.84 M (10%)

24 PROJ. 48 PROJ. 167 PROJ.

CAPITAL OUTLAY: 5.0234 Billion (less P15 M PDES)

Page 26: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

MODE OF IMPLEMENTATION

NO. OF PROJ.

APPRO./MODE IN MILLION PESOS

EQUIVALENT WEIGHTED %

OF ACC./MODE

PHYSICAL % ACC. /MODE

TOTAL WEIGHTED %

OF ACC./MODE

By Administration 1 32.00 9.26 22.68 2.10

By MOA 4 99.80 28.888 53.08 15.33

By Contract 7 213.671 61.85 14.65 9.062

TOTAL 12 345.471 100.00 26.50

2012 ACCOMPLISHMENT AND MODE OF IMPLEMENTATION BY DISTRICT

As of December 16, 2013

BASILAN DISTRICT ENGINEERING OFFICE

MODE OF IMPLEMENTATION

NO. OF PROJ.

APPRO./MODE IN MILLION PESOS

EQUIVALENT WEIGHTED %

OF ACC./MODE

PHYSICAL % ACC. /MODE

TOTAL WEIGHTED %

OF ACC./MODE

By Administration 8 132.50 33.24 11.28 3.75 By MOA 1 31.00 7.776 0 0 By Contract 11 235.137 58.99 0 0 TOTAL 20 398.637 100.00 3.75

2013 ACCOMPLISHMENT AND MODE OF IMPLEMENTATION BY DISTRICT

As of December 16, 2013

BASILAN DISTRICT ENGINEERING OFFICE

Page 27: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

Lamitan Port

Basilan National

Park Asphalting Work by

AFP

Concreting of Lamitan-Tuburan Road Sta. 36+690 – Sta 37+690 Length : 1.00 Km. Project Cost : P 23.00 M

TABUAN LASA

HJI. MUHTAMAD

Concreting of Al-Barka Road Sta. 36+690 – Sta 37+690 Length : 1.88 Km. Project Cost : P 34.80 M

Construction of Bacung Bridge Sumisip Sta. 67+986 Length : 34.60 l.m.

Project Cost : P 29.00 M

Construction of Limbo-Candiis Bridge Sta. 76+950 Length : 39.62 l.m.

Project Cost : P 34.00 M

Construction of Giong Bridge Sumisip Sta. 70+953 Length : 34.60 l.m.

Project Cost : P 31.00 M

Construction of Buli-Buli Port Project Cost : P 20.00 M

Expansion of Lamitan Port Project Cost : P 40.00 M

Concreting of Road from Sumisip Junction Natl Road to

Buli-Buli Port Length : 3.063 km

Project Cost : P 56.671 M

Concreting of Isabela-Lantawan Rd Length : 1.081 km

Project Cost : P 20.00 M

Concreting of Limook-Balobo-Bulingan-Look Road Length : 0.270 km Project Cost : P 5.00 M

Concreting of Bitayan-Basak Circumferential Rd Length : 1.20 km

Project Cost : P 20.00 M

Construction of Km 18-Lantawan Proper-Baungis-Tairan-Pangasaan, Lantawan

Length : 2.00 km Project Cost : P32.00 M

LOCATION MAP CY-2012 REGULAR INFRA

BASILAN DISTRICT ENGINEERING OFFICE

Page 28: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

LOCATION MAP CY-2013 REGULAR INFRA

BASILAN DISTRICT ENGINEERING OFFICE

Lamitan Port

Basilan National

Park Asphalting Work by

AFP

Concreting of Lamitan-Tuburan Road Sta 37+690 – Sta 43+780 w/exceptions Length : 5.543Km. Project Cost : P 127.50 M

TABUAN LASA

HJI. MUHTAMAD

Concreting of Al-Barka Road Length : 3.00 Km. Project Cost : P 30.00 M

Construction of Brgy Matikang-Atong-Atong Road, Lantawan Length : 1.00 km Project Cost : P 10.00 M

Concreting of Tipo-Tipo –Bato-Bato Road, Al Barka Length : 1.00 km Project Cost : P 10.00 M

Construction of Water System, Level III Sumisip Project Cost : P 40.00 M

Concreting of Bohi-Ibu-Cabobo-Bohe-Bessey Road, Lamitan Length : 1.000 km Project Cost : P 10.00 M

Concreting of Lamitan City-Balas Road Length : 1.00 km Project Cost : P 18.50 M

Construction of Road from Lamitan Proper-Brgy. Kulay Bato-Brgy. Buianting-Brgy. Bato

Bato-Brgy. Semmul Phase 1 Akbar Length : 1.250 Km.

Project Cost : P20.00 M

Construction of Manaul Box Culvert Sumisip

Project Cost : P 4.00 M

Concreting of Circumferential Road from Bitayan-Basak Phase II Sumisip

Length : 1.00 Km. Project Cost : 15.137 M

Construction of Prov’l Road, Sayugan Lamitan-Bulanting Lamitan City

Length : 2.00 Km. Project Cost : P31.00 M

Concreting of Magkawa-Ginanta Albarka

Length : 1.00 Km. Project Cost : P10.00 M

Construction of Bato-Bato Port Albarka

Project Cost : P10.00 M

Construction of Road from Bato-Bato Port Albarka-Kaili-Ginanta-Magkawa

Albarka Phase 1 Length : 10.00 Km.

Project Cost : P80.00 M

Construction of Tinusa Port Sumisip

Project Cost : P5.00 M

Construction of Sullo Port Tubuan Lasa

Project Cost : P5.00 M

Construction of Sirongon-Buton Prov’l Road

Muhammad Ajul Length : 20.250

Km. Project Cost :

P45.00 M Construction of 3 units Modular Steel Bridge Sub-Structure Bulibuli-Tekos

Coastal Road, Basak Babag Bato Coastal Road and Limbo Candiis-

Manggal Sumisip Project Cost : P15.00 M/P5.00 M each

Concreting of Bulibuli-Lower Manaul Tikes Brgy. Road Sumisip

Length : 3.50 Km. Project Cost : P35.00 M

Concreting of Basak-Babagbato Brgy. Road Sumisip Length : 1.50 Km.

Project Cost : P15.00 M

Page 29: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

LOCATION MAP CY-2014 REGULAR INFRA

BASILAN DISTRICT ENGINEERING OFFICE

Concreting of .345 km ARMM Learning Center Road, Inner Lagasan, Lamitan City

Concrete Road Widening of 4.982 km unpaved shoulder, Isabela – Lamitan Road

Construction of 3.5 km road from Kulay Bato, Lamitan – Bulanting-U. Batobato, Akbar

Concreting of 4.5 km Natl Road –Marang-Tong Sengal , Tikes Road, Sumisip

Construction /Expansion of Lamitan Water District, Lamitan City

Construction/Expansion of Sumisip Seaport

Concreting of 3.0 km Parangbasak-Bohe baka-Bohe Lebbeng Road, Tipo-Tipo

Construction of 2.9 km Bohe Bohe Mambung-Kalut Road, Tuburan

Concreting of 5 km Mohammad Adjul –Akbar Road

Construction of 3.53 km Road from Magkawa to Kaili, Al barka

Construction of 1 km Road from Natl Highway-Tungbato, Unkaya Pukan

Concreting of Maluso Port to Maluso Fish Port

Concreting of 3.125 km lantawan Proper Baungis-Tairan-Pangasaan, Lantawan

Construction/Expansion of Maluso Water District

Concreting of Limook-Balobo-Bulingan Road, Lamitan City , Phase I and II

Construction of Drainage Structure, Bulibuli, Sumisip

Construction of Single Barrel Box Culvert, Basak, Sumisip

Construction of1.0 km Road from Natl Highway-Tumahubong, Sumisip

Construction of Seaport, Brgyu. Bana, Tipo-Tipo

Construction of Water Supply Project for Ungkaya Pukan-Tipo-Tipo

Municipalities

Concreting of of 2.88km Lantawan Proper baungis-Tairan-

Pangasaan Provl Road

Construction of Seawall along Atong Atong-Matikang Road, Lantawan

Construction of Road from basak-Sahaya-Bohe Bato, Sumisip

Concreting of of Parang-Basak Lamita0Bohelebbeng Road

Concreting of of Badja-Bohelebbeng-Banah Road

Concreting of of Natl Higway-Lower Cabengbeng Road

Concreting of of Lagayas-Pipil Road

Concreting of Natl Highway-Bohesuyak-Tongbato-Amaluy Road

TOTAL COST P902.80 M

Page 30: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

BASILAN PROVINCE

Name of Project : Concreting of Brgy. Matikang-Atong Atong Road, Lantawan

Mode of Implementation : By Administration

Implementing Agency : Basilan District Engineering Office

Project Cost : Php 10,000,000.00

Length : 1.00 Km

Physical Accomplishment : 25.377% as of Nov. 28, 2013

Page 31: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

BASILAN PROVINCE

Name of Project : Construction of 2.00 km Provincial Road from Basilan Circumferential Road Km 18 – Lantawan Proper-Baungis-Tairan-Pangasaan, Lantawan

Mode of Implementation : By Administration

Implementing Agency : Basilan District Engineering Office

Project Cost : Php 32,000,000.00

Length : 2.00 Km

Physical Accomplishment : 22.68% as of Nov. 28, 2013

Page 32: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

BASILAN PROVINCE

Name of Project : Construction of Manaul Box Culvert, Sumisip

Mode of Implementation : By Administration

Implementing Agency : Basilan District Engineering Office

Project Cost : Php 4,000,000.00

Length : 1-Unit

Physical Accomplishment : 28.853% as of Nov. 28, 2013

Page 33: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

BASILAN PROVINCE

Name of Project : Concreting of Lamitan City-Balas Road, Lamitan City

Mode of Implementation : By Administration

Implementing Agency : Basilan District Engineering Office

Project Cost : Php 18,500,000.00

Length : 1.00 Km

Physical Accomplishment : 33.56% as of Nov. 28, 2013

Page 34: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

BASILAN PROVINCE

Name of Project : Concreting of Bohe-Ibu-Cabobo-Bohe-Bessey Road, Lamitan

Mode of Implementation : By Administration

Implementing Agency : Basilan District Engineering Office

Project Cost : Php 10,000,000.00

Length : 1.00 Km

Physical Accomplishment : 35.30% as of Nov. 28, 2013

Page 35: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

BASILAN PROVINCE

Name of Project : Concreting of Road from Sumisip Junction National Road to Buli Buli Port, Sumisip

Mode of Implementation : By Contract

Implementing Agency : Basilan District Engineering Office

Contractor : BSP & Company/MACE Inc. (Joint Venture)

Project Cost : Php 56,671, 000.00

Length : 3.063 Km

Physical Accomplishment : 13.60% as of Nov. 28, 2013

Page 36: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

BASILAN PROVINCE

Name of Project : Improvement/Concrete Paving of Isabela- Lantawan Road, Balatanay-Manggas Section, Lantawan Municipality, Basilan

Mode of Implementation : By MOA

Implementing Agency : Provincial Government of Basilan

Project Cost : Php 20.000, 000.00

Length : 1.081 Km

Physical Accomplishment : 78.19% as of Nov. 28, 2013

Page 37: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

BASILAN PROVINCE

Name of Project : Concreting of Al-barka Road (Tipo-Tipo Proper- Limbo Kassah-Magkawa-Kuhon Lenno) Tipo- Tipo Municipality, Basilan

Mode of Implementation : By MOA

Implementing Agency : L.G.U. of Tipo-Tipo Municipality

Project Cost : Php 34,800, 000.00

Length : 1.880 Km

Physical Accomplishment : 54.72% as of Nov. 28, 2013

Page 38: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

BASILAN PROVINCE

Name of Project : Road Upgrading (Gravel to Concrete Pavement) Lamitan-Tuburan Road, (Km 36+690—Km 37+690)

Mode of Implementation : By Contract

Implementing Agency : Basilan District Engineering Office

Contractor : Basilan C&J Construction

Project Cost : Php 34,800, 000.00

Length : 1.880 Km

Physical Accomplishment : 41.55% as of Nov. 28, 2013

Page 39: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

BASILAN PROVINCE

Name of Project : Concreting of Limook-Balobo-Bulingan- Look Road, Lamitan City

Mode of Implementation : By MOA

Implementing Agency : L.G.U. of Lamitan City

Project Cost : Php 5,000, 000.00

Length : 0.270 Km

Physical Accomplishment : 45.99% as of Nov. 28, 2013

Page 40: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

BASILAN PROVINCE

Name of Project : Expansion of Lamitan Port Lamitan City

Mode of Implementation : By MOA

Implementing Agency : City Government of Lamitan

Project Cost : Php 39,600,000.00

Length : 1-Unit

Physical Accomplishment : 39.99% as of Nov. 28, 2013

Page 41: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

MODE OF IMPLEMENTATION

NO. OF PROJ.

APPRO./MODE IN MILLION PESOS

EQUIVALENT WEIGHTED %

OF ACC./MODE

PHYSICAL % ACC. /MODE

TOTAL WEIGHTED %

OF ACC./MODE

By Administration 7 88.81 71.73 100.00 71.73

By MOA 2 35.00 28.269 66.29 18.74

By Contract 0 0 0 0 0

TOTAL 9 123.81 100.00 90.47

2012 ACCOMPLISHMENT AND MODE OF IMPLEMENTATION BY DISTRICT

As of December 16, 2013

SULU 1ST DISTRICT ENGINEERING OFFICE

MODE OF IMPLEMENTATION

NO. OF PROJ.

APPRO./MODE IN MILLION PESOS

EQUIVALENT WEIGHTED %

OF ACC./MODE

PHYSICAL % ACC. /MODE

TOTAL WEIGHTED %

OF ACC./MODE

By Administration 10 306.32 84.13 12.29 10.34 By MOA 5 57.80 15.874 64.95 10.31 By Contract 0 0 0 0 0 TOTAL 15 364.118 100.00 20.65

2013 ACCOMPLISHMENT AND MODE OF IMPLEMENTATION BY DISTRICT

As of December 16, 2013

SULU 1ST DISTRICT ENGINEERING OFFICE

Page 42: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

42

Road Upgrading of Jolo-Indanan-Parang-Silangkan Road

Sta. 28+970– Sta 30+540 Length : 1.75 Km.

Project Cost : P 40.21 M

Road Upgrading of Jolo Port-Bud Daho-Romandier Road

Sta. 9+000– Sta 17+200 w/ exceptions Length : 2.0304 Km.

Project Cost : P 46.70 M

Const of Deep Well Brgy. Lupah Abo, Parang Project Cost : P 0.400 M Const of Deep Well

Brgy. Samak, Talipao Project Cost : P 0.400 M

Const of Spring Development

Brgy. Tagbak, Indanan Project Cost : P 0.300 M

Const of Deep Well Brgy. Pangdanaon, Patikul Project Cost : P 0.400 M

Const of Deep Well Brgy. D. Jambangan, Maimbung

Project Cost : P 0.400 M

Construction of Tuyang Seaport Talipao, Municipality

Project Cost : 15.00 M

Construction of Prov. Road, Brgy. Laum Maimbung-Brgy.

Kulasi-Parang Rd Phase 1 Length : 1.2 km

Project Cost : 20.00 M

LOCATION MAP CY-2012 REGULAR INFRA

SULU 1ST DISTRICT ENGINEERING OFFICE

Page 43: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

Const./Repair of Panglima Tahil Port Project Cost : P 10.00 M

Road Upgrading of Jolo-Indanan-Parang-Silangkan Road Km 26+030 – km 28+455 w/ exemptions Length : 0.870 Km. Project Cost : P 20.00 M

LOCATION MAP CY-2013 REGULAR INFRA

SULU 1ST DISTRICT ENGINEERING OFFICE

Const of Tumantangis-Jolo Level III Water System Project Cost : P 30.00 M

Repair and Dredging Works of Jolo Drainage

System Length : 0.8 Km.

Project Cost : P10.00 m Concreting of Municipal Road, Maimbung Project Cost : P 10.00 M

Road Upgrading of Jolo-Indanan-Parang-Silangkan Road Km 26+030– km 28+455 w/ exceptions Length : 1.47 Km. Project Cost : P 33.80 M

Construction of Road from brgy. Laum Maimbung Junction Brgy.

Kulasi Phase II Parang Road Length : 1.30 km.

Project Cost : p22.80 M

Construction of Mapallam-Bangalan

Bridge Indanan Length : 10 m

Project Cost : P10.00M

43

Construction of Suwa-Suwa Single Box Culvert Patikul

Project Cost : P3.80 M

Jolo-Cadre-Capitol Road Km 0+510 – km 1+740 Length = 1.23 km Project Cost : P 40.150 M

Const of Anuling Box Culvert, Patikul Project Cost : P 4.00 M

Road Upgrading of Jolo Port-Bud Daho-Romandier Road Km 0+630 – km 2+000 Length : 1.37 Km. Project Cost : P 44.70 M

Concreting of Tuyang Road, Talipao Project Cost : P 10.00 M

Concreting of Kannaway-Tumangas Road Phase 1 Parang

Length : 1.00 Km. Project Cost : P20.00 M

Road Upgrading of Jolo-Indanan-Parang-Silangkan Road Km 0+650 – km 5+514

Length : 4.864 Km. Project Cost : P 123.668 M

Page 44: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

LOCATION MAP CY-2014 REGULAR INFRA

SULU 1ST DISTRICT ENGINEERING OFFICE

Rehabilitation/Reconstruction/Upgrading of 1.626 km Damaged

National Road – Junction Timbangan-Romandier Road

Construction of Maimbung Seaport

Concreting of 20 km Sulu Curcumferential Road

Upgrading of Parang – Maimbung Road

Construction of Sagay Sagay Water Supply System, Phase I (Talipao-Patikul-Jolo Mun.

Upgrading/Rehabilitation of Busbus Gandasuli Road, Jolo

Upgrading of 0.5 km Buntod Road, Talipao

Concreting of Jolo Pantao Road

Upgrading of Sapah Bunuan-Kabungkol Road

Rehabilitation of Pagsalipangan-Maimbung Road

Construction of Tumantangis –Lasuwag Spring Development,

Indanan

Rehab/Improvement of Tulay Open Canal, Jolo

Upgrading of Jolo-Silangkan Road

Rehabilitation of of Kasalamatan Road, Jolo

Upgrading of Pangdanon-Taong Road

Rehabilitation of Kahatian Road, Indanan

Construction /Improvement of Lagasan Dakulah Road, Parang

Rehabilitation of Barrio Militar Road, Jolo

Rehabilitation of Bunbun Road, Patikul

Concreting of Tuyang Road, Talipao

Rehabilitation of Asturias Road, Jolo

Concreting of Langtad-Kan Islam Road, Indanan

TOTAL COST P606.60 M

Page 45: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

SULU PROVINCE

Name of Project : Road Upgrading (gravel to paved) Jolo Port-Bud Daho Romandier Road Km. 9+000—Km. 17+200 with exceptions

Mode of Implementation : By Administration

Implementing Agency : Sulu 1st DEO

Project Cost : Php 46,700,000.00

Length : 2.0304 Km

Physical Accomplishment : 100% as of Nov. 28, 2013

Page 46: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

Name of Project : Road Upgrading (gravel to paved) Jolo-Indanan-Parang-Silangkan Road Km. 28+970—Km. 30+540

Mode of Implementation : By Administration

Implementing Agency : Sulu 1st DEO

Project Cost : Php 40,210,000.00

Length : 1.75 Km

Physical Accomplishment : 100% as of Nov. 28, 2013

SULU PROVINCE

Page 47: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

Name of Project : Construction of Tuyang Seaport Talipao, Sulu

Mode of Implementation : By MOA

Implementing Agency : L.G.U. of Talipao Municipality

Project Cost : Php 14,850,000.00

Length : 1-Unit

Physical Accomplishment : 85% as of Nov. 28, 2013

SULU PROVINCE

Page 48: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

Name of Project : Construction of Tuyang Road Talipao, Sulu

Mode of Implementation : By MOA

Implementing Agency : Sulu 1st DEO

Project Cost : Php 10,000,000.00

Length : 1.000 Km

Physical Accomplishment : 100% as of Nov. 28, 2013

SULU PROVINCE

Page 49: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

Name of Project : Concreting of Kannaway-Tumangas Road Parang, Sulu

Mode of Implementation : By Administration

Implementing Agency : Sulu 1st DEO

Project Cost : Php 19,800,000.00

Length : 1.000 Km

Physical Accomplishment : 60% as of Nov. 28, 2013

SULU PROVINCE

Page 50: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

Name of Project : Construction of Deep Well Barangay D. Jambangan, Maimbung

Mode of Implementation : By Administration

Implementing Agency : Sulu 1st DEO

Project Cost : Php 400,000.00

Length : 1-Unit

Physical Accomplishment : 100% as of Nov. 28, 2013

SULU PROVINCE

Page 51: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

Name of Project : Construction of Deep Well Barangay Lupah Abo, Parang

Mode of Implementation : By Administration

Implementing Agency : Sulu 1st DEO

Project Cost : Php 400,000.00

Length : 1-Unit

Physical Accomplishment : 100% as of Nov. 28, 2013

SULU PROVINCE

Page 52: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

Name of Project : Construction of Deep Well Barangay Pangdanon, Patikul

Mode of Implementation : By Administration

Implementing Agency : Sulu 1st DEO

Project Cost : Php 400,000.00

Length : 1-Unit

Physical Accomplishment : 100% as of Nov. 28, 2013

SULU PROVINCE

Page 53: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

MODE OF IMPLEMENTATION

NO. OF PROJ.

APPRO./MODE IN MILLION PESOS

EQUIVALENT WEIGHTED %

OF ACC./MODE

PHYSICAL % ACC. /MODE

TOTAL WEIGHTED %

OF ACC./MODE

By Administration 3 67.00 79.76 74.98 59.81

By MOA 2 17.00 20.238 17.74 3.59

By Contract 0 0 0 0 0

TOTAL 5 84.00 100.00 63.39

2012 ACCOMPLISHMENT AND MODE OF IMPLEMENTATION BY DISTRICT

As of December 16, 2013

SULU 2ND DISTRICT ENGINEERING OFFICE

MODE OF IMPLEMENTATION

NO. OF PROJ.

APPRO./MODE IN MILLION PESOS

EQUIVALENT WEIGHTED %

OF ACC./MODE

PHYSICAL % ACC. /MODE

TOTAL WEIGHTED %

OF ACC./MODE

By Administration 2 68.00 77.27 18.44 14.25 By MOA 3 20.00 22.727 7.50 1.70 By Contract 0 0 0 0 0 TOTAL 5 88.00 100.00 15.95

2013 ACCOMPLISHMENT AND MODE OF IMPLEMENTATION BY DISTRICT

As of December 16, 2013

SULU 2ND DISTRICT ENGINEERING OFFICE

Page 54: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

54

Concreting (Rehab) of Romandier-Camp Andres Tandu Bato Road

Sta. 26+000– Sta 55+000 w/ exceptions Length : 1.550 Km.

Project Cost : P 35.65 M

Concreting of Seit Tayungan-Camp Andres Road

Sta. 36+000– Sta 45+000 w/ exceptions Length : 0.580 Km.

Project Cost : P 13.35 M

Construction of Sapah Malaum Bridge along Seit Tayungan-Camp

Andres National Road Sta. 39+150 – Sta 39+170

Length : 20 m Project Cost : 18.00 M

Improvement of Siasi Port and access Road Project Cost : 10.00 M

Rehabilitation of Subasuba Port and

Access Road Project Cost : 7.00 M

LOCATION MAP CY-2012 REGULAR INFRA

SULU 2ND DISTRICT ENGINEERING OFFICE

Page 55: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

LOCATION MAP CY-2013 REGULAR INFRA

SULU 2ND DISTRICT ENGINEERING OFFICE

55

Concreting of Seit Tayungan-Camp Andres Road Sta. 36+000– Sta 45+000 w/ exceptions Length : 2.522 Km. Project Cost : P 58.00 M

Concreting of Brgy. Andalan-Saimbangon Road, Pata Length = 0.650 Project Cost : P 6.50 M

Concreting of Brgy. Kipot-Saimbangon Road, Pata Length = 0.350 Project Cost : P 3.50 M

Concreting of Duhul-Duhul Road, Siasi Length = 1.00 Project Cost : P 10.00 M

Concreting of Minapan Road, Siasi Length = 1.00 Project Cost : P 10.00 M

Page 56: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

Rehabilitation of/Upgrading of 1 km Siet Tayungan-Camp Andres Road

Upgrading of 0.75 km Camp Andres – Sucuban Road, Luuk

Construction of Water Supply project level II System Phase I

Expansion of Sagay Sagay Water Supply System Phase II

Construction of Pata Seaport

Construction of Tapul Seaport

Construction of Lugus Seaport

Construction of Omar Seaport

Concreting of Siasi Tausan Road

Construction of Lahing Lahing Camp Andres Provincial Road

Construction of Pang karungdong-Kalingalan Caluang Road

Construction of Water Supply Project, Bangingi

Construction of Water Supply Project, Tapul

Construction of Water Supply Project, Lugus

Construction of Water Supply Project, Siasi

Construction of Water Supply Project, Pata

Construction of Water Supply Project, Pandami

Construction of Panamao Seaport

LOCATION MAP CY-2014 REGULAR INFRA

SULU 2ND DISTRICT ENGINEERING OFFICE

TOTAL COST P189.20 M

Page 57: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

Name of Project : Concreting of Seit-Tayungan-Camp Andres Road

Mode of Implementation : By Administration

Implementing Agency : Sulu 2nd DEO

Project Cost : Php 13,216,500.00

Length : 0.580 Km

Physical Accomplishment : 92.66% as of Nov. 28, 2013

SULU PROVINCE

Page 58: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

Name of Project : Concreting of Romandier Camp Andres- Tandu Bato Road

Mode of Implementation : By Administration

Implementing Agency : Sulu 2nd DEO

Project Cost : Php 35,293,500.00

Length : 1.55 Km

Physical Accomplishment : 100% as of Nov. 28, 2013

SULU PROVINCE

Page 59: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

Name of Project : Concreting of Duhol-Duhol Road Siasi, Sulu

Mode of Implementation : By Administration

Implementing Agency : Sulu 2nd DEO

Project Cost : Php 9,900,000.00

Length : 1.000 Km

Physical Accomplishment : 30.15% as of Nov. 28, 2013

SULU PROVINCE

Page 60: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

MODE OF IMPLEMENTATION

NO. OF PROJ.

APPRO./MODE IN MILLION PESOS

EQUIVALENT WEIGHTED %

OF ACC./MODE

PHYSICAL % ACC. /MODE

TOTAL WEIGHTED %

OF ACC./MODE

By Administration 6 155.995 100.00 71.09 71.09

By MOA 0 0 0 0 0

By Contract 0 0 0 0 0

TOTAL 6 155.995 100.00 71.09

2012 ACCOMPLISHMENT AND MODE OF IMPLEMENTATION BY DISTRICT

As of December 16, 2013

TAWI-TAWI DISTRICT ENGINEERING OFFICE

MODE OF IMPLEMENTATION

NO. OF PROJ.

APPRO./MODE IN MILLION PESOS

EQUIVALENT WEIGHTED %

OF ACC./MODE

PHYSICAL % ACC. /MODE

TOTAL WEIGHTED %

OF ACC./MODE

By Administration 11 166.00 98.22 63.37 62.25 By MOA 2 3.00 1.775 0 0 By Contract 0 0 0 0 0 TOTAL 13 169.00 100.00 62.25

2013 ACCOMPLISHMENT AND MODE OF IMPLEMENTATION BY DISTRICT

As of December 16, 2013

TAWI-TAWI DISTRICT ENGINEERING OFFICE

Page 61: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

61

Road Upgrading of Sanga-Sanga – Lapid-Lapid Road Sta. 004+578.216– Sta 22+325 w/ exceptions

Length : 1.478 Km. Project Cost : P 33.995 M

Construction of Water Supply Panglima Sugala

Project Cost : P 70.00 M

Concreting of Circumferential Causeway and Docking Port Phase 1

Length : 315 m Project Cost : P37.00 M

Shore Protection Works along National Road approach to Sanga-Sanga Bridge

Length : 400 m Project Cost : 8.50 M

Repair/Rehabilitation of Simunul Port

Project Cost : 5.00M

Construction of Community Water Brake

Tangngah Project Cost : 1.50 M

LOCATION MAP CY-2012 REGULAR INFRA

TAWI-TAWI DISTRICT ENGINEERING OFFICE

Page 62: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

62

Road Upgrading of Sanga-Sanga – Lapid-Lapid Road Km 06+551.216– km 9+166.216 w/ exceptions Length : 1.695 Km. Project Cost : P 39.00 M

Concreting of Tubig-Indangan Port Road, Simunul Length = 0.50 Project Cost : P 5.00 M

Construction of Pierhead, Tabawan, South Ubian Project Cost : P2.00 M

Concreting of MSU Campus Access Road, MSU Bongao Length = 0.500 Project Cost : P 5.00 M

Concreting of Likud Tabawan, Likud Dampong to Putat Road South Ubian

Length : 0.50 Km. Project Cost : P5.00 M

Concreting of Malassa Road Bongao

Length : 0.20 Km. Project Cost : P2.00 M

Concreting of Sapa Sapa Pokkoan to Likud

Sicubong Road, Sapa Sapa

Length : 0.10 Km. Project Cost : P1.00 M

Concreting of Prov’l Road, Bato Bato, Panglima

Sugala-Kapatagan, Bongao Length : 5.00 Km.

Project Cost : P80.00 M

Construction of Sapa Sapa Port Road

Length : 0.25 Km. Project Cost : P5.00 M

Construction of Sibutu Municipal Road

Length : 0.25 Km. Project Cost : P 5.00 M

Concreting of Parangan to Balimbing Road, Panglima Sugala

Length : 1.00 Km. Project Cost : P10.00 M

LOCATION MAP CY-2013 REGULAR INFRA

TAWI-TAWI DISTRICT ENGINEERING OFFICE

Construction of Tandubas Municipal Road Length : 0.25 Km. Project Cost : P5.00 M

Construction of Mapun Municipal Road

Length : 0.25 Km. Project Cost : P5.00 M

Page 63: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

Concreting of Circumferential Causeway and Docking Port, Bongao

Concrete Paving of Tandubas-Ungus Matata national Road

Concrete Paving of Tampakan-Tongusong Road, Simunul

Concreting of LiLigayan-Tando Owak Road

Concrete paving of SangaSanga-Lapid-Lapid

Natl Road

Concreting of Sowangkagang-Nalil Road,

Bongao

Concreting of Patal-karungdong Road, Bongao

Concreting of Tanggah Road, Tandubas

Concreting of Tubig Indangan Road, Simunul

Concreting of Bato Bato –Tarawakan Natl Road, Panglima Sugala

Const of Ungus Matata_Buton Road, Tandubas

Construction ofTongsinah-Lagasan Road, Bongao

Concreting of Tongmaging-Larap Road, Sitangkai

Construction of Mantabuan Footbridge w/ Pierhead, Sapa Sapa

Construction of Palate Footbridge w/ Pierhead,

Sapa Sapa

Construction of Tandubato Footbridge w/ Pierhead, Bongao

Concreting of Boki-Tabulian Road, Mapun

Concreting of Bato Bato –Parangan Road, Panglima

Sugala

Construction of Seaport, Mapun

Construction of Mandulan Footbridge w/ Pierhead, Bongao

Const./Rehab of Sowangkagang Shore Protection, Bongao

LOCATION MAP CY-2014 REGULAR INFRA

TAWI-TAWI DISTRICT ENGINEERING OFFICE Concrete Paving of Lupa Pula-Um,us Mataha Road, Mapun

TOTAL COST P347.60 M

Page 64: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

TAWI-TAWI PROVINCE

Name of Project : Road Upgrading (Gravel to Paved) Sanga-Sanga - Lapid-Lapid Road Km. 13+789 – Km. 15+683 w/ exemptions

Mode of Implementation : By Administration

Implementing Agency : Tawi-Tawi District Engineering Office

Project Cost : Php 32,975,150.00

Length : 1.478 Km

Physical Accomplishment : 100% as of Nov. 28, 2013

Page 65: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

TAWI-TAWI PROVINCE

Name of Project : Concreting of Circumferential Causeway and Docking Port, Bongao-Phase I

Mode of Implementation : By Administration

Implementing Agency : Tawi-Tawi District Engineering Office

Project Cost : Php 35,890,000.00

Length : 1-Unit

Physical Accomplishment : 45% as of Nov. 25, 2013

Page 66: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

TAWI-TAWI PROVINCE

Name of Project : Road Upgrading (Gravel to Paved) Sanga-Sanga - Lapid-Lapid Road Km. 15+683-KM 20+140 w/ exemptions

Mode of Implementation : By Administration

Implementing Agency : Tawi-Tawi District Engineering Office

Project Cost : Php 67,900,000.00

Length : 3.043 Km.

Physical Accomplishment : 75% as of Nov. 25, 2013

Page 67: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

TAWI-TAWI PROVINCE

Name of Project : Road Upgrading (Gravel to Paved) Sanga-Sanga - Lapid-Lapid Road Km. 23+541 – Km. 25+241

Mode of Implementation : By Administration

Implementing Agency : Tawi-Tawi District Engineering Office

Project Cost : Php 37,830,000.00

Length : 1.695 Km.

Physical Accomplishment : 70% as of Nov. 25, 2013

Page 68: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

TAWI-TAWI PROVINCE

Name of Project : Concreting of Provincial Road, Bato-Bato, Panglima Sugala-Kapatagan,Bongao

Mode of Implementation : By Administration

Implementing Agency : Tawi-Tawi District Engineering Office

Project Cost : Php 77,600,000.00

Length : 5.00 Km.

Physical Accomplishment : 45% as of Nov. 28, 2013

Page 69: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

TAWI-TAWI PROVINCE

Name of Project : Construction of Sapa-Sapa Port Road Sapa-Sapa, Tawi-Tawi

Mode of Implementation : By Administration

Implementing Agency : Tawi-Tawi District Engineering Office

Project Cost : Php 4,850,000.00

Length : 0.250 Km.

Physical Accomplishment : 90% as of Nov. 28, 2013

Page 70: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

TAWI-TAWI PROVINCE

Name of Project : Construction of Sibutu Municipal Road Sibutu, Tawi-Tawi

Mode of Implementation : By Administration

Implementing Agency : Tawi-Tawi District Engineering Office

Project Cost : Php 4,850,000.00

Length : 0.250 Km.

Physical Accomplishment : 100% as of Nov. 28, 2013

Page 71: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

TAWI-TAWI PROVINCE

Name of Project : Construction of Tandubas Municipal Road Tandubas, Tawi-Tawi

Mode of Implementation : By Administration

Implementing Agency : Tawi-Tawi District Engineering Office

Project Cost : Php 4,850,000.00

Length : 0.250 Km.

Physical Accomplishment : 90% as of Nov. 28, 2013

Page 72: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

MODE OF IMPLEMENTATION

NO. OF PROJ.

APPRO./MODE EQUIVALENT WEIGHTED %

OF ACC./MODE

PHYSICAL % ACC. /MODE

TOTAL WEIGHTED %

OF ACC./MODE

By Administration 4 31.00 43.97 59.83 26.31

By MOA 1 5.00 7.092 100.00 7.092

By Contract 2 34.50 48.94 90.94 44.50

TOTAL 7 70.50 100.00 77.90

2012 ACCOMPLISHMENT AND MODE OF IMPLEMENTATION BY DISTRICT

As of December 16, 2013

MAGUINDANAO 1ST DISTRICT ENGINEERING OFFICE

MODE OF IMPLEMENTATION

NO. OF PROJ.

APPRO./MODE EQUIVALENT WEIGHTED %

OF ACC./MODE

PHYSICAL % ACC. /MODE

TOTAL WEIGHTED %

OF ACC./MODE

By Administration 5 50 50.05 21.00 10.51 By MOA 3 10 10.010 56.99 10.51 By Contract 2 39.90 39.94 0 0 TOTAL 10 99.90 100.00 16.22

2013 ACCOMPLISHMENT AND MODE OF IMPLEMENTATION BY DISTRICT

As of December 16, 2013

MAGUINDANAO 1ST DISTRICT ENGINEERING OFFICE

Page 73: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

73

Concreting of Poblacion Dalican Road Length : 0.333 Km.

Project Cost : P 5.00 M

Rehabilitation/Reconst./Upgrading of Damaged Paved Roads

Concrete Reblocking along Cotabato-Lanao Road

Sta. 1855– Sta 1865 w/ exceptions Length : 1.30 Km.

Project Cost : P 19.50 M

Rehabilitation/Reconst./Upgrading of Damaged Paved Roads

Concrete Reblocking alongMarbel-Ala- Cotabato-Road, Bitu-Dulangan Section

Sta. 1837+000– Sta 1839 w/ exceptions Length : 1.00 Km.

Project Cost : P 15.00 M

Concreting of Padang-Padang Adventure Park Road, Brgy

Moro Point, Parang Length : 0.333 Km.

Project Cost : P 5.00 M

Concreting of Matanog Road Length : 1 km

Project Cost : 10.00 M

Concreting of Datu Talusan Road including retrofitting of

double barrel box Culvert, Sultan Kudarat

Project Cost : 13.00 M

LOCATION MAP CY-2012 REGULAR INFRA

MAGUINDANAO 1ST DISTRICT ENGINEERING OFFICE

Riprapping of Sarakan Bridge Matanog

Project Cost : 3.00 M

Page 74: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

74

Rehabilitation/Reconst./Upgrading of Damaged Paved Roads Concrete Reblocking alongMarbel-Ala- Cotabato-Road, Bitu-Dulangan Section Sta. 1837+000– Sta 1839 w/ exceptions Length : 1.327 Km. Project Cost : P 19.90 M

Construction of Water System Sitio Mereges, Darugao, Upi Project Cost : P 10.00 M

Concreting of Brgy Rempis-Poblacion Road, North Upi Length= 0.500 Project Cost : P 5.00 M

LOCATION MAP CY-2013 REGULAR INFRA

MAGUINDANAO 1ST DISTRICT ENGINEERING OFFICE

Concreting of Miramar-Poblacion Road Parang Length = 0.500 Project Cost : P 5.00 M

Construction of Matanog Buldon Drainage, Matanog Length = 2.00 Km. Project Cost : P 20.00 M

Concreting of Water System Access Rd, Macasandag, Parang Length = 0.300 Project Cost : P 3.00 M

Construction of Water System Level II Brgy Pinguiaman and Bugawas Datu Odin Sinsuat Project Cost : P 5.00 M

Concreting of Campo Uno Road Brgy. Pinantao, Parang Length : 0.20 Km. Project Cost : P2.00 M

Construction of Water System Kabuntalan Mother Project Cost : P 10.00 M

Rehabilitation/Reconst./Upgrading of Damaged Paved Roads Concrete Reblocking along Cotabato-Lanao Road Sultan Kudarat Section Length : 1.333 Km. Project Cost : P 20.00 M

Page 75: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

Reblocking of 1.34 km Awang-Upi –Lebak Road

Reblocking of Marbel-Ala Cotabato Road

Construction of Parang Water Supply Level III

Concreting of Pob. Natl Highway – Pob Old Market, Datu Odin Sinsuat

Rehab/Development of Polloc Port

Concreting of Pinaring-Ibotegen Road

Concreting of Highway Macabiso-Solon Road, Sultan Mastura

Concreting of Sitio Kawa Bugawas, Datu Odin Sinsuat

Concreting of Lagumbingan-Labio Road, Northern Kabuntalan

Concreting of Taviran-Ganta –Tuka Road

Concreting of Tinendana-Pob. Road, rempis, North Upi

Construction of Fish Landing, Montay, Northern Kabuntalan

Concreting of Highway-Bago Inged Road, Datu Odin Sinsuat

Construction of Water System, Bago Inged, Datu

Odin Sinsuat

Concreting of Padang-Padang Road, Parang

Construction of Parang-Barira Road

Construction of Water System, Gayunga, Kabuntalan

Construction of North Upi-Datu Blah Sinsuat Road

Concrete Drainage along Cotabato-Lanao Road

LOCATION MAP CY-2014 REGULAR INFRA

MAGUINDANAO 1ST DISTRICT ENGINEERING OFFICE Upgrading of Parang-Buldon Road

Construction of Fish Port, Water System and Concreting of Barangay Road, Sitio Kalutan,

Making, Parang

TOTAL COST P364.80 M

Page 76: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

MAGUINDANAO PROVINCE

Name of Project : Concreting of Padang Padang Adventure Park, Brgy. Moro Point, Parang, Maguindanao

Mode of Implementation : By Administration

Implementing Agency : Maguindanao 1st District Engineering Office

Project Cost : Php 4,950,000.00

Length : 0.333 Km

Physical Accomplishment : 100% as of Nov. 28, 2013

Page 77: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

MAGUINDANAO PROVINCE Name of Project : Concrete Reblocking Along Marbel-Ala Valley-

Cotabato Rd Bitu-Dulangan Section, DOS Mag. Km. 1837+000 – Km. 1839+000 w/exceptions.

Mode of Implementation : By Contract

Implementing Agency : Maguindanao 1st District Engineering Office

Contractor : MUST Construction

Project Cost : Php 14,467,102.79

Length : 1.00 Km

Physical Accomplishment : 79.71% as of Nov. 28, 2013

Page 78: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

MAGUINDANAO PROVINCE Name of Project : Concreting of Poblacion Dalican Rd., Datu

Odin Sinsuat, Maguindanao

Mode of Implementation : By MOA

Implementing Agency : L.G.U.

Project Cost : Php 4,950,000.00

Length : 0.333 Km

Physical Accomplishment : 100% as of Nov. 28, 2013

Page 79: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

MAGUINDANAO PROVINCE Name of Project : Concreting of Datu Talusan Road including

Retrofitting of Double-Barrel Box Culvert, Sultan Kudarat, Maguindanao

Mode of Implementation : By Administration

Implementing Agency : Maguindanao 1st District Engineering Office

Project Cost : Php 12,870,000.00

Length : 1-Unit

Physical Accomplishment : 72% as of Nov. 28, 2013

Page 80: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

MAGUINDANAO PROVINCE Name of Project : Riprapping of Sarakan Bridge Approaches,

Km. 1897+653, Matanog Maguindanao

Mode of Implementation : By Administration

Implementing Agency : Maguindanao 1st District Engineering Office

Project Cost : Php 2,970,000.00

Length : 1-Unit

Physical Accomplishment : 80% as of Nov. 28, 2013

Page 81: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

MAGUINDANAO PROVINCE Name of Project : Construction of Water System Sitio Mereges,

Brgy. Darugao, North Upi, Maguindanao

Mode of Implementation : By Administration

Implementing Agency : Maguindanao 1st District Engineering Office

Project Cost : Php 9,900,000.00

Length : 1-Unit

Physical Accomplishment : 10% as of Nov. 28, 2013

Page 82: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

MAGUINDANAO PROVINCE Name of Project : Construction of Water System at Mother

Kabuntalan, Maguindanao

Mode of Implementation : By Administration

Implementing Agency : Maguindanao 1st District Engineering Office

Project Cost : Php 9,900,000.00

Length : 1-Unit

Physical Accomplishment : 30% as of Nov. 28, 2013

Page 83: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

MAGUINDANAO PROVINCE Name of Project : Concreting of Water System Access Road,

Macasandag, Parang, Maguindanao

Mode of Implementation : By Administration

Implementing Agency : Maguindanao 1st District Engineering Office

Project Cost : Php 2,970,000.00

Length : 0.300 km

Physical Accomplishment : 86% as of Nov. 28, 2013

Page 84: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

MAGUINDANAO PROVINCE Name of Project : Concrete Reblocking Along Cotabato-Lanao/

Davao Road Km. 1858+000-Km. 1862+000 w/exceptions Sultan Kudarat, Maguindanao

Mode of Implementation : By Contract

Implementing Agency : Maguindanao 1st District Engineering Office

Contractor : MUST Construction

Project Cost : Php 18,832,253.02

Length : 1.300 km

Physical Accomplishment : 90.89% as of Nov. 28, 2013

Page 85: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

MAGUINDANAO PROVINCE Name of Project : Concreting of Brgy. Rempis-Poblacion Road,

North Upi, Maguindanao

Mode of Implementation : By Administration

Implementing Agency : Maguindanao 1st District Engineering Office

Project Cost : Php 4,950,000.00

Length : 0.500 Km

Physical Accomplishment : 50% as of Nov. 28, 2013

Page 86: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

MODE OF IMPLEMENTATION

NO. OF PROJ.

APPRO./MODE IN MILLION PESOS

EQUIVALENT WEIGHTED %

OF ACC./MODE

PHYSICAL % ACC. /MODE

TOTAL WEIGHTED %

OF ACC./MODE

By Administration 2 23.05 34.123 69.77 17.76

By MOA 3 33.00 48.853 66.23 32.35

By Contract 1 11.50 17.024 100.00 17.024

TOTAL 6 67.55 100.00 73.18

2012 ACCOMPLISHMENT AND MODE OF IMPLEMENTATION BY DISTRICT

As of December 16, 2013

MAGUINDANAO 2ND DISTRICT ENGINEERING OFFICE

MODE OF IMPLEMENTATION

NO. OF PROJ.

APPRO./MODE IN MILLION PESOS

EQUIVALENT WEIGHTED %

OF ACC./MODE

PHYSICAL % ACC. /MODE

TOTAL WEIGHTED %

OF ACC./MODE

By Administration 9 57.50 30.022 80.86 24.28 By MOA 2 10 5.221 67.08 3.50 By Contract 2 124.03 64.757 0 0 TOTAL 13 191.526 100.00 27.78

2013 ACCOMPLISHMENT AND MODE OF IMPLEMENTATION BY DISTRICT

As of December 16, 2013

MAGUINDANAO 2ND DISTRICT ENGINEERING OFFICE

Page 87: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

87

Concreting of Poblacion Buluan- Maslabing Road, Buluan

Length : 1.081 Km. Project Cost : P 20.00 M

Rehabilitation/Reconst./Upgrading of Damaged Paved Roads

Reblocking along Marbel-Ala- Cotabato Road DAS-DAM Section

Sta. 1781+000– Sta 1821+838 w/ exceptions Length : 0.67 Km.

Project Cost : P 10.05 M

Concreting Pandag Road Length : 13.00 Km.

Project Cost : 13.00 M

LOCATION MAP CY-2012 REGULAR INFRA

MAGUINDANAO 2ND DISTRICT ENGINEERING OFFICE

Rehabilitation/Reconst./Upgrading of Damaged Paved Roads

Concrete Pavement Widening of Marbel-Ala- Cotabato Road, Shariff Aguak Section

Sta. 1797+113– Sta 1799+113 w/ exceptions Length : 0.767 Km.

Project Cost : P 11.50 M

Concreting of Talitay Road Length : 1.30 Km.

Project Cost : 13.00 M

Page 88: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

88

Construction of Water System Datu Saudi Ampatuan Project Cost : P 10.00 M

Construction of Water System Banaba, Abdullah Sangki Project Cost : P 1.00 M

Construction of Water System Sitio Malibacao, Romongaob, South Upi Project Cost : P 1.00 M

Concreting of Poblacion-Municipal Cemetery Road Shariff Aguak, L= 0.200 Project Cost : P 2.00 M

Concreting of Pandag Road Section 2 Pandag Length : 0.500 km Project Cost : P 5.00 M

Concreting of Pandag Road Section 1 Pandag Length : 0.500 km Project Cost : P 5.00 M

Concreting of Paglas-Columbio Prov’l Road Length : 4.268 Km.

Project Cost : P64.026 M

Concreting of Maslabeng Provincial Road

Length : 4.00 Km. Project Cost : P60.00 M

LOCATION MAP CY-2013 REGULAR INFRA

MAGUINDANAO 2ND DISTRICT ENGINEERING OFFICE

Rehabilitation/Reconst./Upgrading of Damaged Paved Roads Concrete Pavement Widening of Marbel-Ala- Cotabato Road, Datu Saudi Ampatuan Section Km 1805+455 – Sta 1807+455 w/ exceptions Length : 1.00 Km. Project Cost : P 15.00 M

Rehabilitation/Reconst./Upgrading of Damaged Paved Roads Reblocking along Marbel-Ala- Cotabato Road DAS-DAM Section Sta. 1781+000– Sta 1821+838 w/ exceptions Length : 1.50 Km. Project Cost : P 22.50 M

Concreting of Matagabong Rd Ampatuan Length : 0.300 km Project Cost : P 3.00 M

Concreting of Sitio Binibedan Road, Ampatuan Length= 0.100 km Project Cost : P 1.00 M

Construction of Road Dike Paglat, L= 0.200 km Project Cost : P 2.00 M

Page 89: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

Rehabilitation of Dulawan Bridge along Midsayap-Dulawan-Makar Road, Datu

Piang Section

Concrete Widening along Kidapawan-Ala-Junction Road, Datu Paglas Section

Concrete Widening with line canal along Marbel-Ala-Cotabato Road

Concreting of Pandag Road

Concrete Slope Protection of Alip Section, Datu Paglas

Rehab./Improvement of Meta Bridge Datu Unsay

Concrete Pavement of Libutan Road

Construction of Water System, Brgy. Sapakan, Rajah Buayan

Construction of Water Supply Project, Guindulungan

Construction of Water Supply Project,Datu Anggal M

Construction of Water Supply Project,Shariff Aguak

Construction of Water Supply Project,Buluan

Construction of Water Supply Project,Pagalungan

LOCATION MAP CY-2014 REGULAR INFRA

MAGUINDANAO 2ND DISTRICT ENGINEERING OFFICE Construction of Water

Supply Project,Datu Piang

Concreting of Banaba –Paitan , Datu Abdullah SangkiRoad Upgrading and Concreting of Road Dike,

Brgy Buayan-Brgy Balong, Datu Piang

TOTAL COST P174.80 M

Page 90: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

MAGUINDANAO PROVINCE

Name of Project : Concrete Reblocking along Marbel-Ala- Cotabato Road Datu Abdullah Sangki-Datu Anggal Midtimbang Section

Mode of Implementation : By Administration

Implementing Agency : Maguindanao 2nd District Engineering Office

Project Cost : Php 22,500,000.00

Length : 1.500 Km

Physical Accomplishment : 75% as of Nov. 28, 2013

Page 91: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

MAGUINDANAO PROVINCE

Name of Project : Concrete Pavement Widening along Marbel- Ala-Cotabato Road, Datu Saudi Ampatuan, Maguindanao, Km. 1805 + 675 – Km. 1806 + 675

Mode of Implementation : By Administration

Implementing Agency : Maguindanao 2nd District Engineering Office

Project Cost : Php 15,000,000.00

Length : 1.000 Km

Physical Accomplishment : 70% as of Nov. 28, 2013

Page 92: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

MAGUINDANAO PROVINCE

Name of Project : Concreting of Matagabong Road Ampatuan, Maguindanao

Mode of Implementation : By Administration

Implementing Agency : Maguindanao 2nd District Engineering Office

Project Cost : Php 3,000,000.00

Length : 0.300 Km

Physical Accomplishment : 50% as of Nov. 28, 2013

Page 93: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

MAGUINDANAO PROVINCE

Name of Project : Concreting of Barangay Binibedan Road Ampatuan, Maguindanao

Mode of Implementation : By Administration

Implementing Agency : Maguindanao 2nd District Engineering Office

Project Cost : Php 1,000,000.00

Length : 0.100 Km

Physical Accomplishment : 85% as of Nov. 28, 2013

Page 94: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

MAGUINDANAO PROVINCE

Name of Project : Construction of Water System (Level II) @ Barangay Romangaob, Sitio Malibacao, Maguindanao

Mode of Implementation : By Administration

Implementing Agency : Maguindanao 2nd District Engineering Office

Project Cost : Php 1,000,000.00

Length : 1-Unit

Physical Accomplishment : 100% as of Nov. 28, 2013

Page 95: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

MAGUINDANAO PROVINCE

Name of Project : Construction of Water System (Level II) @ Brgy Banaba, Datu Abdullah Sangki, Maguindanao

Mode of Implementation : By Administration

Implementing Agency : Maguindanao 2nd District Engineering Office

Project Cost : Php 1,000,000.00

Length : 1-Unit

Physical Accomplishment : 70% as of Nov. 28, 2013

Page 96: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

MODE OF IMPLEMENTATION

NO. OF PROJ.

APPRO./MODE IN MILLION PESOS

EQUIVALENT WEIGHTED %

OF ACC./MODE

PHYSICAL % ACC. /MODE

TOTAL WEIGHTED %

OF ACC./MODE

By Administration 0 0 0 0 0

By MOA 3 75.634 100.00 86.5 86.50

By Contract 0 0 0 0 0

TOTAL 3 75.634 100.00 86.50

2012 ACCOMPLISHMENT AND MODE OF IMPLEMENTATION BY DISTRICT

As of December 16, 2013

LANAO 1ST DISTRICT ENGINEERING OFFICE

MODE OF IMPLEMENTATION

NO. OF PROJ.

APPRO./MODE IN MILLION PESOS

EQUIVALENT WEIGHTED %

OF ACC./MODE

PHYSICAL % ACC. /MODE

TOTAL WEIGHTED %

OF ACC./MODE

By Administration 8 30.00 26.09 11.79 3.077 By MOA 12 85.00 73.913 69.05 51.04 By Contract 0 0 0 0 0 TOTAL 20 115.00 100.00 54.11

2013 ACCOMPLISHMENT AND MODE OF IMPLEMENTATION BY DISTRICT

As of December 16, 2013

LANAO 1ST DISTRICT ENGINEERING OFFICE

Page 97: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

97

Road Upgrading Molundo-Wao Road (Bukidnon Bdry.-North Cotabato Brdy.)

Km 1619+790 – km 1621+890 Length : 2.158 Km. Project Cost : P 49.634 M

Construction of Dilausan-Polo Bridge Ditsaan Ramain Project Cost : P 13.00 M

Concreting of Dilabayan-Ririk Road Taraka Length : 1.250 Km

Project Cost : P 13.00 M

LOCATION MAP CY-2012 REGULAR INFRA

LANAO DEL SUR 1ST DISTRICT ENGINEERING OFFICE

Page 98: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

98

Concreting of Malungun-Buadiadingun Road, Taraka Length : 0.50 Km. Project Cost : P5.00 M

Concreting of Dilabayan-Ririk Road, Taraka Length : 0.50 Km. Project Cost : P5.00 M

Concreting of Buot-Milaya Catolongan Road, Wao Length : 1.250 Km. Project Cost : P20.00 M

Concreting of Port, Lumbac Madaya, Marawi City Project Cost : P5.00 M

Tourism Development for Plaza Cabili Banggolo, Marawi City Project Cost : P5.00 M

Concreting of Saguiran-Piagapo Prov’l Road Length : 0.625 Km. Project Cost : P10.00 M

Concreting of Buadi-Buntong Road

Length : 0.20 Km. Project Cost : P2.00 M

Concreting of Kalaw Road, Marantao

Length : 0.20 Km. Project Cost : P2.00 M

LOCATION MAP CY-2013 REGULAR INFRA

LANAO DEL SUR 1ST DISTRICT ENGINEERING OFFICE Construction of Water System Saguiaran Project Cost : P 2.00 M

Construction of Water System, Lumba Bayabao Project Cost : P 10.00 M

Concreting of Ditsaan Ramain Road

Length : 0.20 Km. Project Cost : P2.00 M

Concreting of Bubong Road

Length : 0.20 Km. Project Cost : P2.00 M

Concreting of Wao Road

Length : 0.20 Km. Project Cost :

P2.00 M

Concreting of Bumbaran Road

Length : 0.10 Km. Project Cost :

P1.00 M

Concreting of Maguing Road

Length : 0.10 Km. Project Cost : P1.00 M

Concreting of Ditsaan Ramain-Buapuso Buntong

Road Length : 0.75 Km.

Project Cost : P12.00 M

Page 99: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

99

Road Upgrading Marawi-Pantar Diversion Road Length : 1.00 Km. Project Cost : P 23.00 M

Rehabilitation of Rizal Park, Gomisa Ave., Marawi City Project Cost : P2.00 M Realigned to Road Concreting of Brgy Dialonga Cawayan Marantao, Lanao del Sur per approved RLA Resolution

Construction of Water System and Public Toilet Brgy. Tolali, Marawi City Project Cost : P2.00 M

Concreting of Malimono Road. Brgy. Malimono, Marawi City Length : 0.200 Km. Project Cost : P2.00 M

LOCATION MAP CY-2013 REGULAR INFRA

LANAO DEL SUR 1ST DISTRICT ENGINEERING OFFICE MARAWI CITY

Page 100: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

Rehab./Upgrading of Pugaan Bridge, Ditsaan Ramain

Rehab./Upgrading of Ramain Bridge, Ditsaan Ramain

Rehab./Reconst./Upgrading of Marawi-Maranatao Road

Concreting of Ditsaan Ramain-Buadi Puso Buntong Road

Concreting of 1.087 km Tagoloan Road

Concreting of Marawi-Cabasaran Diversion Road, Phase II

Upgrading of Saguiaran Water System

Concreting of Saguiaran-Radapan Road, Piagapo

Concreting of 0.50 km Poona Bayabao Road

Concreting of Bout – Milaya-Catotongan Circumferential Road, Wao

Buadi Ulok-Buisan Road, Masiu

Concreting of Tamparan Road

Repair & Completion of Ramain Water System, Ditsaan Ramain

Concreting of Dimayon-Pagalamatan Provincial Road, Taraka

Concreting of Biaba Damag-Amito Road. Marawi City

Concreting of Cadayonan-Kawit Road, Taraka

Concreting of Piagapo Road

LOCATION MAP CY-2014 REGULAR INFRA

LANAO DEL SUR 1ST DISTRICT ENGINEERING OFFICE

Rehabilitation of Pugaan Port

Rehabilitation of Sumndad-Buadi Sacayo Flod Control

TOTAL COST P251.80 M

Page 101: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

LANAO DEL SUR PROVINCE

Name of Project : Road Upgrading (Gravel to Paved), Mulondo-Wao Road, Bukidnon bdry-North Cotabato Bdry

Mode of Implementation : By MOA

Implementing Agency : L.G.U. Lanao del Sur

Project Cost : Php 48,144,980.00

Length : 1.92 Kms

Physical Accomplishment : 100% as of Nov. 28, 2013

Page 102: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

LANAO DEL SUR PROVINCE

Name of Project : ROAD UPGRADING (Gravel to Paved), PANTAR DIVERSION ROAD, Cabasaran, Marawi City

Mode of Implementation : By MOA

Implementing Agency : L.G.U. Lanao del Sur

Project Cost : Php 22,310,000.00

Length : 1.20 Kms

Physical Accomplishment : 65% as of Nov. 28, 2013

Page 103: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

MODE OF IMPLEMENTATION

NO. OF PROJ.

APPRO./MODE IN MILLION PESOS

EQUIVALENT WEIGHTED %

OF ACC./MODE

PHYSICAL % ACC. /MODE

TOTAL WEIGHTED %

OF ACC./MODE

By Administration 5 33.00 53.19 45.91 24.42

By MOA 1 5.00 8.059 100.00 8.059

By Contract 2 24.04 38.75 70.03 27.14

TOTAL 8 62.04 100.00 59.62

2012 ACCOMPLISHMENT AND MODE OF IMPLEMENTATION BY DISTRICT

As of December 16, 2013

LANAO 2ND DISTRICT ENGINEERING OFFICE

MODE OF IMPLEMENTATION

NO. OF PROJ.

APPRO./MODE IN MILLION PESOS

EQUIVALENT WEIGHTED %

OF ACC./MODE

PHYSICAL % ACC. /MODE

TOTAL WEIGHTED %

OF ACC./MODE

By Administration 1 10.00 13.51 25.00 3.38 By MOA 9 64.00 86.486 54.37 47.03 By Contract 0 0 0 0 0 TOTAL 10 74.00 100.00 50.40

2013 ACCOMPLISHMENT AND MODE OF IMPLEMENTATION BY DISTRICT

As of December 16, 2013

LANAO 2ND DISTRICT ENGINEERING OFFICE

Page 104: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

104

Concreting of Sultan Pandapatan-Parao Road

Bayang Length : 0.550 Km. Project Cost : P 5.50 M

Concreting of Tagoranao-Tangcal Road Tubaran

Length : .550 Km. Project Cost : P 5.50 M

Concreting of Highway-Dibarosan Bualan Road, Balindong

Length : .550 Km. Project Cost : P 5.50 M

Concreting of Lumbayanague-Butig Road

Length : .550 Km. Project Cost : P 5.50 M

Concreting of Taliogan-Ririk Road Ganassi

Length : .550 Km. Project Cost : P 5.50 M

Road Upgrading Const. of Masiu - Ganassi-Road Km 1616+000 – km 1624+000

Length : 0.497 Km. Project Cost : P 11.44 M

Rehabilitation/Reconstruction Repair of Cotabato-Lanao Road

Biosong, Picong Section Km 1616+000 – km 1624+000

Length : 0.500 Km. Project Cost : P 12.00 M

LOCATION MAP CY-2012 REGULAR INFRA

LANAO DEL SUR 2ND DISTRICT ENGINEERING OFFICE Road Upgrading

Const. of Ganassi-Tubod Road Km 1607+000 – km 1620+944

Length : 0.548 Km. Project Cost : P 12.60 M

Page 105: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

105

Concreting of Bayang-Marogong Road Length : 1.50 Km. Project Cost : P 24.00 M

Concreting of Road Curahab, Malabang Length = 0.25 km Project Cost : P 2.50 M

Concreting of Road Pantao-on, Calanogas Length = 0.35 km Project Cost : P 3.50 M

Concreting of Provincial Road Lumbatan-Macadar Road Length = 0.667 km Project Cost : P 10.00 M

Concreting of Lumbatan-Lumbaca Unayan Road Length : 1.25 Km. Project Cost : P 20.00 M

Concreting of Gadungan Road Gadungan, Madalum Length = 0.30 km Project Cost : P 3.00 M

LOCATION MAP CY-2013 REGULAR INFRA

LANAO DEL SUR 2ND DISTRICT ENGINEERING OFFICE Concreting of Road Gadungan, Madalum Length = 0.25 km Project Cost : P 2.50 M

Concreting of Road Liangan, Picong Length = 0.25 km Project Cost : P 2.50 M

Concreting of Road Balintad, Madamba Length = 0.25 km Project Cost : P 2.50 M

Page 106: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

Construction of of Concrete Line Canal along Cotabato-Lanao del Norte Road,

Balabagan Section

Construction of Barorao Bridge, Balabagan

Construction of Tubaran Water System

Construction of Taliogon Water System, Ganassi

Construction of Bacolod-Kalawi Water System

Concreting of Sultan Pandapatan-Parao Road, Bayang

Concreting of Lumbatan-Marogong Road

Concreting of Binidayan-Bayang-Tubaran Road

Rehab./Reconst.of Damaged Paved National Road along Cotabato-Lanao Norte Road, Itil,

Balabagan Section

Reblocking of Marawi-Malabang Road (Madalum-Madamba section

Concrete Widening of of Luayan-Taliogon Road, Ganassi

LOCATION MAP CY-2014 REGULAR INFRA

LANAO DEL SUR 2ND DISTRICT ENGINEERING OFFICE

TOTAL COST P118.40 M

Page 107: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

LANAO DEL SUR PROVINCE

Name of Project : Repair of Cotabato-Lanao Norte Road, Biosong, Picong Section, (Km.1957+900 – Km. 1958+400) a. Const. of two (2) Barrel box culvert b. Embankment (2m high) c. Concrete paving

Mode of Implementation : By Administration

Implementing Agency : Lanao del Sur 2nd District Engineering Office

Project Cost : Php 12,000,000.00

Length : 0.500 Km

Physical Accomplishment : 100% as of Nov. 28, 2013

Page 108: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

LANAO DEL SUR PROVINCE

Name of Project : Concreting of Taliogan-Ririk Road, Ganassi

Mode of Implementation : By MOA

Implementing Agency : L.G.U. Lanao del Sur

Project Cost : Php 5,000,000.00

Length : 0.500 Km

Physical Accomplishment : 100% as of Nov. 28, 2013

Page 109: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

LANAO DEL SUR PROVINCE

Name of Project : Concreting of Lumbatan-Lumbaca Unayan Road

Mode of Implementation : By MOA

Implementing Agency : L.G.U. Lanao del Sur

Project Cost : Php 5,000,000.00

Length : 0.500 Km

Physical Accomplishment : 55% as of Nov. 28, 2013

Page 110: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

3.2 DETAILED FINANCIAL REPORT

Page 111: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

YEAR ALLOTMENT NCA RELEASED OBLIGATED DISBURSED % UTILIZED

2011 PS 189,444,284.00 184,428,620.00 189,444,284.00 184,428,620.00 100.00% MOOE 232,480,000.00 218,246,380.00 232,480,000.00 218,246,380.00 100.00% CO 1,000,000,000.00 745,896,543.97 1,000,000,000.00 615,386,703.33 82.50% Total 1,421,924,284.00 1,148,571,543.97 1,421,924,284.00 1,018,061,703.33 88.64%

2012

PS 205,159,438.00 193,634,767.37 205,159,438.00 193,634,767.37 100.00% MOOE 176,712,360.00 151,168,788.28 176,712,360.00 151,168,788.28 100.00% CO 1,000,000,000.00 600,899,000.00 1,000,000,000.00 474,223,864.85 78.92% CO (Equipment) 96,629,640.00 91,453,550.15 96,629,640.00 64,503,942.63 70.53%

Total 1,478,501,438.00 1,037,156,105.80 1,478,501,438.00 883,531,363.13 85.19%

2013

PS 198,293,000.00 177,535,471.00 183,872,065.00 176,474,395.70 99.40%

MOOE 275,380,000.00 239,759,667.00 157,216,332.62 136,362,852.84 56.87%

CO 1,510,181,000.00 225,627,000.00 1,510,181,000.00 280,686,117.73 124.40%

Total 1,983,854,000.00 642,922,138.00 1,851,269,397.62 593,523,366.27 92.32%

FINANCIAL UTILIZATION OF REGULAR FUNDS FY 2011 – 2013 NOVEMBER 31, 2013

Note : Pursuant to Sec. 3.4.2 of NBC 545 re: Guidelines on the Release of Funds of FY 2013.

Page 112: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

BUDGET ALLOCATION TO DISTRICT/AREA OFFICES FY 2012 As of December 31, 2012

OFFICE PS MOOE CO

TOTAL

Basilan Engineering District - 4,984,235.00 345,471,000.00 350,455,235.00

Maguindanao Engineering District I - 11,073,285.51 70,500,000.00 81,573,285.51

Maguindanao Engineering District II 23,552,315.56 31,607,699.41 67,550,000.00 122,710,014.97

Lanao Sur Engineering District I 29,828,040.68 16,069,888.26 75,634,000.00 121,531,928.94

Lanao Sur Engineering District II - 19,329,189.18 62,040,000.00 81,369,189.18

Sulu Engineering District I 23,848,992.98 16,761,080.00 123,810,000.00 164,420,072.98

Sulu Engineering District II 15,117,630.58 12,732,500.00 84,000,000.00 111,850,130.58

Tawi-Tawi Engineering District 19,009,764.84 12,653,116.00 155,995,000.00 187,657,880.84

Maguindanao Area Equipment Services 9,838,158.18 5,575,013.09 15,413,171.27

Lanao Area Equipment Services 9,429,534.40 3,561,492.90 12,991,027.30

Sulu Area Equipment Services 10,084,466.10 6,040,007.39 16,124,473.49

Tawi-Tawi Area Equipment Services 2,855,614.02 3,811,919.40 6,667,533.42

PDES ARMM REGIONWIDE 15,000,000.00

GRAND TOTAL 143,564,517.34 144,199,426.14 1,000,000,000.00 1,272,763,943.48

Page 113: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

BUDGET ALLOCATION TO DISTRICT/AREA OFFICES FY 2013 As of November 31, 2013

OFFICE PS MOOE CO TOTAL

Basilan Engineering District 5,846,357.90 398,637,000.00 404,483,357.90

Maguindanao Engineering District I 9,031,053.61 99,900,000.00 108,931,053.61

Maguindanao Engineering District II 21,671,281.72 15,980,375.19 191,526,000.00 229,177,656.91

Lanao Sur Engineering District I 24,164,666.07 14,051,497.91 115,000,000.00 153,216,163.98

Lanao Sur Engineering District II - 17,259,050.84 74,000,000.00 91,259,050.84

Sulu Engineering District I 21,842,314.36 13,433,684.27 364,118,000.00 399,393,998.63

Sulu Engineering District II 14,775,291.12 10,526,052.66 88,000,000.00 113,301,343.78

Tawi-Tawi Engineering District 18,968,089.60 11,392,750.56 169,000,000.00 199,360,840.16

Maguindanao Area Equipment Services 9,348,223.32 5,419,839.67 14,768,062.99

Lanao Area Equipment Services 8,985,215.45 2,896,098.52 11,881,313.97

Sulu Area Equipment Services 9,542,788.98 4,970,724.09 14,513,513.07

Tawi-Tawi Area Equipment Services 2,784,471.84 3,515,093.27 6,299,565.11

PDES ARMM REGIONWIDE 10,000,000.00

GRAND TOTAL 132,082,342.46 114,322,578.49 1,510,181,000.00 1,746,585,920.95

Page 114: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

CY IMPLEMENTATION

TOTAL NO. OF

PROJECTS APPROPRIATION

DBM OBLIGATED DISBURSED

NCA Released Balance Request Amount % Amount %

Utilization (1) (2) (3) (4) (5) (6) = (5) / (1) (7) (8) = (7) / (2)

2010 (1st Tranche) 294 659,000,000.00 659,000,000.00 - - 659,000,000.00 100% 659,000,000.00 100%

2010 (2nd Tranche) 55 191,000,000.00 114,764,000.00 69,446,084.06 33,019,600.00 191,000,000.00 100% 116,071,557.44 101%

2011 426 1,000,000,000.00 745,896,543.97 219,951,269.11 125,649,700.00 1,000,000,000.00 100% 615,386,703.33 83%

2012 57 1,000,000,000.00 600,899,000.00 371,520,077.90 247,061,500.00 1,000,000,000.00 100% 474,223,864.85 79%

2013 107 1,510,181,000.00 225,627,000.00 1,284,554,000.00 854,228,400.00 1,510,181,000.00 100% 280,686,117.73 124%

TOTAL 939 4,360,181,000.00 2,346,186,543.97 1,945,471,431.07 1,259,959,200.00 4,360,181,000.00 100% 2,145,368,243.35 91.44%

DPWH-ARMM 2010-2013 INFRASTRUCTURE PROJECT ACCOMPLISHMENT As of December 15, 2013

Note: Column (2) excluding Tax Withheld (TRA) by DBM

11.82%

10.60%

15.70%

33.45%

6.05%

3.63%

7.27%

17.97%

5.08%

20.65%

46.44%

91.44%

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100% • The average disbursement ratio of the agency for the year is 21.79%.

• The financial performance is on the rise. We had the lowest in June at only 3.63%. But performance picked up by October and steadily rose to 46.44% in November and finally rest at 91.44% as of date.

Disbursement Ratio for the period covering January 1 to December 15, 2013

Page 115: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

Productive Use of Savings FY 2012 & FY 2013

Projects FY 2012 Allotment FY 2013 Allotment Total

1st Tranche procurement of Heavy Equipment ₱47,700,000.00 ₱47,700,000

2nd Tranche procurement of Heavy Equipment 22,318,480.00 22,318,480

3rd Tranche procurement of Heavy Equipment 26,611,160.00 26,611,160

4th Tranche Procurement* ₱54,236,000.00 54,236,000.00

Renovation of ORG Building 10,526,315.79 10,526,315.79 21,052,631.58

Building and Structures - Regional Office ₱3,347,957.21 3,347,957.21

Repair of Bayanga Road 15,531,432.37 15,531,432.37

Total ₱110,503,913.00 ₱80,293,748.16 ₱190,797,661.16

16%

18%

38%

15%

2%

11% 0%

1st Tranche procurement of Heavy Equipment2nd Tranche procurement of Heavy Equipment3rd Tranche procurement of Heavy Equipment4th Tranche ProcurementRenovation of ORG BuildingBuilding and Structures - Regional OfficeRepair of Bayanga Road

*REQUEST FOR REALIGNMENT OF FUND FROM MOOE SAVINGS TO EQUIPMENT OUTLAY IS UNDER PROCESS BY DBM.

Page 116: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

Expenditure 2012 2013 2014 2015 2016 2017

(Actual) (Current) (NEP) (Proposed) (Proposed) (Proposed)

PS 205,159 198,293 194,256 252,130 252,486 253,198

MOOE 176,712 275,380 317,289 387,603 419,332 451,061

CO

Equipment Outlay 96,630

Regular Infra

Basilan Engineering District 345,471 398,637 902,800

Mag. Eng'g. District I 70,500 99,900 364,800

Mag. Eng'g. District II 67,550 191,526 174,800

Lanao Sur Eng'g. District I 75,634 115,000 251,800

Lanao Sur Eng'g. District II 62,040 74,000 118,400

Sulu Eng'g. District I 123,810 364,118 606,600

Sulu Eng'g. District II 84,000 88,000 189,200

Tawi-Tawi Eng'g. District 155,995 169,000 347,600

ARMM Region 15,000 10,000 15,000

1,000,000 1,510,181 2,971,000 15,149,290 14,634,290 13,063,190 PAMANA

Basilan 655,000

Maguindanao 530,830

Lanao del Sur 192,570

Sulu 552,600

Tawi-Tawi 121,400

- - 2,052,400 - - -

GRAND TOTAL 1,478,501 1,983,854 5,534,945 15,789,023 15,306,108 13,767,449

DPWH-ARMM

Previous and Current Budget and Forward Agency Estimates CY 2012-2017

(In Thousand Pesos)

Page 117: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

PROGRAMS/

PROJECTS

2014

2015 2016 2017

ARMM INFRA BUDGET OPAPP Projects (Road to Peace)

No. of

Proj

Length

(km)

Amount

(in Million)

No. of

Proj

Length

(km)

Amount

(in Million) No. of Proj

Length

(km)

Amount

(in Million) No. of Proj

Length

(km)

Amount

(in Million) No. of Proj

Length

(km)

Amount

(in Million)

National Road

(Repair/Rehab/

Reblocking)

18 14.923 241.299 - - - - - - - - -

Local Roads 107 179.554 1,944.095 34 205.24 2,052.40

Provincial 147 434.75 8,695.00 147 434.75 8,695.00 147 356.195 7,123.90

Municipal/Brgy. - 464.08 5,568.96 - 464.08 5,568.96 - 464.08 5,568.96

Bridge 13 - 124.420 - - -

Ports 17 - 288.520 - - -- 10 - 515.00 - - -

Water Supply 30 - 264.075 - - - 370 brgys - 370.33 370 brgys - 370.33 370 brgys - 370.33

Drainage/Canal

Improvements 12 - 59.010 - - - - - - - - -

Other Structures 9 - 49.581 - - - - - - - - -

Total 206 226.044 2,971.00 34 205.24 2,052.40 898.83 15,149.29 898.83 14,634.29 820.275 13,063.10

Summary of DPWH-ARMM Priority Investment Programs/Projects

Page 118: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

DISTRICT

ARMM

NATIONAL ROADS

(Per DPWH-ARMM Records)

DPWH-ARMM

ARMM INFRA BUDGET

(Road Upgrading Only)

DPWH

(National)

2013

Regular Infra

DPWH (National)

Transition Investment Support

Program – ARMM

(TISP-ARMM)

STIMULUS FUND

(Road Upgrading Only)

Concrete (km)

Asphalt

(km)

Gravel

(km)

Total

(km)

Approved 2012 Approved 2013 1ST Tranche -

2011

Proposed 2nd

Tranche

Length

(km)

Amount

(million)

Length

(km)

Amount

(million)

Length

(km)

Amount

( million)

Length

(km)

Amount

(million)

Length

(km)

Amount

(million)

Basilan 125.237 0.667 28.013 153.922 1.000 23.000 - - 9.072 300.00 15.52 434.130 8.910 319.855

Sulu I 68.299 0.240 21.336 89.875 3.7804 86.9100 8.334 228.518 4.536 150.00 2.5725 93.680 8.523 323.874

Sulu II 38.680 - 6.220 44.900 1.5500 35.6500 - - 4.536 150.00 2.6962 99.360 - -

Tawi-Tawi 52.6391 - 62.460 115.099 4.978 103.9950 5.549 103.995 4.536 150.00 - - 15.556 653.352

Maguindanao I 137.337 - 7.262 144.599 - - - - 9.829 325.00 - - 5.12 117.760

Maguindanao II 117.830 9.446 10.400 137.676 - - - - 2.268 75.00 9.970 234.255 - -

Lanao del Sur I 116.331 - 29.604 145.935 2.1580 49.6340 - - 4.536 150.00 4.580 155.480 25.474 637.000

Lanao del Sur II 146.262 - 14.322 160.584 1.0450 24.0400 - - 3.024 100.00 2.4200 72.679 7.552 190.000

ARMM Total 802.615 10.353 179.617 992.590 14.5114 323.229 13.883 332.513 42.34 1,400.00 37.75 1089.584 71.135 2,241.841

Total Length of National Road & Investment for ARMM

Page 119: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

IV. SPECIAL CONCERNS

Page 120: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

1. GOVERNANCE/ADMINISTRATION 1.1 DPWH-ARMM REFORM AGENDA 2012 AND BEYOND

Page 121: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

1. GOVERNANCE/ADMINISTRATION 1.1 DPWH-ARMM REFORM AGENDA 2012 AND BEYOND

Page 122: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

1. GOVERNANCE/ADMINISTRATION 1.2 DPWH-ARMM MANCOM

CHAIRMAN – Regional Secretary EMIL K. SADAIN, CESO II

MEMBERS – Asst. Regional Secretary DON MUSTAPHA A. LOONG

– Asst. Regional Secretary NASRUDIN D. MAKABINTA

– Head Planning Division DANILO A. ONG

– Head Construction Division NAZER P. EBUS

– Head Maintenance Division BARLIE S. NAHUDAN

– Head Finance Division MANGODA SINDAB

– Head Admin Division TONY J. KAMLANI

– Head Equipment Division HECTOR CELIS

– Head Survey and Design Division MALDAMIN B. DECAMPONG

– Head MQCH Division YAHIYA A. ABDULCALIM

– District Engineers of the eight (8) DEOs

– Area Equipment Engineers of the four (4) AEOs

Page 123: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

CONDUCT OF DPWH-ARMM OUTBOUND MANCOM/STAFF MEETINGS (January 2012 – December 2013)

PARTICULARS LOCATION ATTENDANCE DATE

1. 1st Outbound Mancom/Staff Meeting

Tawi-Tawi DEO Bongao, Tawi-Tawi

Regional Secretary, Division Heads, District Engineers and Area Equipment Engineers

March 8-10, 2012

2. 2nd Outbound Mancom/Staff Meeting

Sulu 1st DEO Jolo, Sulu

Regional Secretary, Division Heads, District Engineers and Area Equipment Engineers

May 10-13, 2012

3. 3rd Outbound Mancom/Staff Meeting

MSU Campus Marawi City

Regional Secretary, Division Heads, District Engineers and Area Equipment Engineers

June 28-July 1, 2012

4. 4th Outbound Mancom/Staff Meeting

Al-nor Complex Cotabato City

Regional Secretary, Division Heads, District Engineers and Area Equipment Engineers

August 30, 2012

5. 5th Outbound Mancom/Staff Meeting

Sulu 1st DEO Jolo, Sulu

Regional Secretary, Division Heads, District Engineers and Area Equipment Engineers

September 24-25, 2012

6. 6th Outbound Mancom/Staff Meeting

Zamboanga City Regional Secretary, Division Heads, District Engineers and Area Equipment Engineers

December 21-22, 2012

7. 7th Outbound Mancom/Staff Meeting

Zamboanga City Regional Secretary, Division Heads, District Engineers and Area Equipment Engineers

February 21-23, 2013

8. 8th Outbound Mancom/Staff Meeting

Zamboanga City Regional Secretary, Division Heads, District Engineers and Area Equipment Engineers

March 22-23, 2013

9. 9th Outbound Mancom/Staff Meeting

Lamitan City, Basilan

Regional Secretary, Division Heads, District Engineers and Area Equipment Engineers

November 28-29, 2013

10.10th Outbound Mancom/Staff Meeting

Tawi-Tawi DEO Bongao, Tawi-Tawi

Regional Secretary, Division Heads, District Engineers and Area Equipment Engineers

December 16-17, 2013

Page 124: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

2. ARMM HELPS/Convergence Cluster

Priority Barangays for 2013

BASILAN 1. Concreting of Sayugan Lamitan-Bulanting Lamitan City Php 31.00 Million (2013 Infra Budget)

2. Construction of Sullo Port Tabuan Lasa Php 5.00 Million (2013 Infra Budget)

TAWI-TAWI 1. Concreting of Tubig Indangan Port Road Tubig Indangan, Simunul Php 5.000 Million (2013 Infra Budget)

2. Concreting of Tubig Indangan Road Tubig Indangan, Simunul Php 10.00 Million (2014 Infra Budget)

MAGUINDANAO 1. Const. of Water System Sitio Kalutan, Making, Parang Php 1.675 Million (2014 Infra Budget)

2. Const. of Fish Port Sitio Kalutan, Making, Parang Php 2.00 Million (2014 Infra Budget)

3. Concreting of 100 meters- Barangay Road Sitio Kalutan, Making, Parang Php 1.00 Million (2014 Infra Budget)

4. Road Opening/Concreting of10 km Laguitan-

Highway Road Datu Blah Sinsuat Php 100.00 Million (2014 Road to Peace Projects/OPAPP)

5. Road Concreting of 5 km Poblacion -Tubak Road Ampatuan Php 50.00 Million (2014 Road to Peace Projects/OPAPP

Page 125: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

2. ARMM HELPS/Convergence Cluster

Priority Barangays for 2013

LANAO DEL SUR 1. Concreting of Taliogon-Ririk Road Ganassi Php 5.000 Million (2012 Infra Budget) 2. Construction of Taliogon Water System Ganassi Php 6.26 Million (2014 Infra Budget) 3. Concreting Widening of Luayan-Taliogon Road Ganassi Php 5.000 Million (2014 Infra Budget)

SULU 1. Construction of Tuyang Seaport Talipao, Sulu Php 15.000 Million (2012 Infra Budget)

Page 126: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

3. DPWH-ARMM OPLAN LINIS BAYAN PROGRAM Generated summer job April-June 2013 for out of school youth and students on vacation

BASILAN DISTRICT ENGINEERING OFFICE

Page 127: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

SULU 1ST AND 2ND DISTRICT ENGINEERING OFFICES

3. DPWH-ARMM OPLAN LINIS BAYAN PROGRAM Generated summer job April-June 2013 for out of school youth and students on vacation

Page 128: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

SULU 1ST AND 2ND DISTRICT ENGINEERING OFFICES

3. DPWH-ARMM OPLAN LINIS BAYAN PROGRAM Generated summer job April-June 2013 for out of school youth and students on vacation

Page 129: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

SULU 1ST AND 2ND DISTRICT ENGINEERING OFFICES

3. DPWH-ARMM OPLAN LINIS BAYAN PROGRAM Generated summer job April-June 2013 for out of school youth and students on vacation

Page 130: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

SULU 1ST AND 2ND DISTRICT ENGINEERING OFFICES

3. DPWH-ARMM OPLAN LINIS BAYAN PROGRAM Generated summer job April-June 2013 for out of school youth and students on vacation

Page 131: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

TAWI-TAWI DISTRICT ENGINEERING OFFICE

3. DPWH-ARMM OPLAN LINIS BAYAN PROGRAM Generated summer job April-June 2013 for out of school youth and students on vacation

Page 132: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

TAWI-TAWI DISTRICT ENGINEERING OFFICE

3. DPWH-ARMM OPLAN LINIS BAYAN PROGRAM Generated summer job April-June 2013 for out of school youth and students on vacation

Page 133: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

MAGUINDANAO 1ST AND 2ND DISTRICT ENGINEERING OFFICES

3. DPWH-ARMM OPLAN LINIS BAYAN PROGRAM Generated summer job April-June 2013 for out of school youth and students on vacation

Page 134: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

MAGUINDANAO 1ST AND 2ND DISTRICT ENGINEERING OFFICES

3. DPWH-ARMM OPLAN LINIS BAYAN PROGRAM Generated summer job April-June 2013 for out of school youth and students on vacation

Page 135: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

LANAO DEL SUR 1ST AND 2ND DISTRICT ENGINEERING OFFICES

3. DPWH-ARMM OPLAN LINIS BAYAN PROGRAM Generated summer job April-June 2013 for out of school youth and students on vacation

Page 136: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

LANAO DEL SUR 1ST AND 2ND DISTRICT ENGINEERING OFFICES

3. DPWH-ARMM OPLAN LINIS BAYAN PROGRAM Generated summer job April-June 2013 for out of school youth and students on vacation

Page 137: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

Strategy Collaborative undertaking between DPWH-ARMM and DPWH -National

Actions

DPWH-ARMM will construct 30 kms national roads using regular budget.

DPWH National will construct 38 kms national roads using regular budget.

DPWH National TISP I using special funds.

DPWH ARMM/National TISP II using special funds.

2013 30 kms

38 kms

38 kms

______ 106 kms

2014

73 kms _________

73 kms

Measure 919 kms (93% Paved)

992 kms (100% Paved)

Resource Requirements

P2.734 Billion (2013) P2.247 Billion (2014)

Support Agencies DBM, DPWH-National, ORG, NGOs.

A. Sector Outcome : 100% Paved National Roads by end of 2014 ARMM has 992 kms National Roads 813 kms paved (82%) and 179 kms unpaved (18%).

4. RAPID INFRASTRUCTURE DEVELOPMENT ASSISTANCE (RIDA) for ARMM

Page 138: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

Strategy Collaborative undertaking between DPWH-ARMM and the 5 Provincial Government Offices of ARMM

Actions

DPWH-ARMM and 5 Provincial Govt. Offices will construct provincial roads under following funds: Regular Budget

OPAPP PAMANA ARMM funds (Roads to Peace)

Special funds/ODA

2013

39.836 kms

________ 39.836 kms

2014

30.309 kms

78.55 kms

________ 108.859 kms

2015

100 kms

200 kms

925.695 kms 1225.695kms

Measure 317.606 kms (19.22% Paved)

426.465 kms (25.81% Paved)

1652.16 kms (100 %Paved)

Resource Requirements

P588.13 Million (2013) P1,959.462 Million (2014); P24,513.9 Million (2015)

Support Agencies OP intervention, DBM, ORG, 5 Provincial Gov’t. offices, possible ODA assistance, NGOs.

B. Sector Outcome : 100% Paved Provincial Roads by end of 2015

JICA Study 2008, ARMM has 1,652.16 kms Provincial Roads.

Only 277.77 kms paved (16.81%) and 1,374.39 kms unpaved (83.19%).

4. RAPID INFRASTRUCTURE DEVELOPMENT ASSISTANCE (RIDA) for ARMM

Page 139: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

Strategy Collaborative undertaking between DPWH-ARMM and the 116 LGUs of ARMM.

Actions DPWH-ARMM and selected technically capable LGUs will construct local roads under following funds: Regular Budget

OPAPP PAMANA ARMM funds (Roads to Peace)

Special funds/ODA

2013

42.14 kms

________ 42.14 kms

2014

118.93 kms

126.69 kms

245.62 kms

2015

100 kms

200 kms

1,092.24 kms

1,392.24 kms

Measure 462.14 kms (22% Paved)

707.76 kms (34% Paved)

2,100 kms (100 %Paved)

Resource Requirements

P425 Million (2013) P2,491.64 Million (2014); P13,922.40 Million (2015)

Support Agencies OP intervention, DBM, ORG, 116 LGUs, possible ODA assistance, NGOs.

C. Sector Outcome : 100% Paved Municipal Roads by end of 2015

DPWH-ARMM initial report, ARMM has 2,100 kms Municipal

Roads. Only 420 kms paved (20%) and 1,680 kms unpaved (80%)

4. RAPID INFRASTRUCTURE DEVELOPMENT ASSISTANCE (RIDA) for ARMM

Page 140: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

Strategy Provide water supply projects in all 1,497 barangays (Level I, II or III Water Supply); conduct inventory of potential water sources in the areas; and secure Geo-Resistivity mapping that identify sufficient ground water sources

Actions

DPWH-ARMM will construct

WS projects using Regular Funds

DPWH-ARMM will construct WS projects using special funds/ODA assistance

2013 108 brgys

______ 108 brgys

2014 278 brgys

________ 278 brgys

2015 500 brgys

611 brgys

_______ 1,111 brgys

Measure 1,106 brgys (44%)

1,384 brgys (55%)

2,495 brgys (100%)

Resource Requirements

P108 Million (2013) P278 Million (2014); P 1,111 Million (2015)

Support Agencies OP intervention, DBM, NWRB, ORG, possible ODA assistance, LWUA, NGOs.

D. Sector Outcome : WATER FOR ALL 2,495 BARANGAYS in the ARMM by end of 2015. JICA Study revealed, only 998 barangays (40%) are provided with safe water supply facilities. About 1,497 barangays (60%) are deriving water from open dug wells or surface water with no treatment.

4. RAPID INFRASTRUCTURE DEVELOPMENT ASSISTANCE (RIDA) for ARMM

Page 141: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

Strategy Rehabilitation of 23 Sea Ports and Expansion of the other 10 Sea Ports.

Actions

DPWH-ARMM will

rehabilitate/reconstruct 23 Sea Ports under regular budget.

DPWH-ARMM will expand the other 10 sea ports under regular budget.

2013 11 Ports

2 Ports

_______ 13 Ports

2014 7 Ports

3 Ports

________ 10 Ports

2015 5 Ports

5 Ports

_______ 10 Ports

Measure 13 Ports (39%)

23 Ports (70%)

33 Ports (100%)

Resource Requirements

P135 Million (2013) P155 Million (2014); P515 Million (2015)

Support Agencies DBM, ORG, LGUs, NGOs.

E. Sector Outcome : 100% Operational and Serviceable 33 Sea Ports in the ARMM by

end of 2015.

4. RAPID INFRASTRUCTURE DEVELOPMENT ASSISTANCE (RIDA) for ARMM

Page 142: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

Strategy Generated in-house savings to purchase 9 units of survey instruments and solicited support from JICA on 8 RoCon Survey instruments for the 8 DEOs.

Actions

DPWH-ARMM generated saving from MNRB funds and purchased 9 survey instruments for the Regional Office and the 8 DEOs.

Convinced JICA to support the RoCon Survey of National Roads in the ARMM; JICA donated 8 units of Rocon Survey instrument for the 8 DEOs.

Measure All 8 DEOs will complete their RoCon Survey 3rd Quarter of 2013

Resource Requirements

P2.40 Million

Support Agencies Lanao del Sur 1st DEO, Lanao del Sur 2nd DEO, Maguindanao 1st DEO, Maguindanao 2nd DEO, Basilan Satellite DEO, Sulu 1st DEO, Sulu 2nd DEO and Tawi-Tawi DEO

F. Outcome : 100% Road Condition (RoCon) Survey as Baseline Data for

National Road Maintenance budgeting before end of 2013.

4. RAPID INFRASTRUCTURE DEVELOPMENT ASSISTANCE (RIDA) for ARMM

Page 143: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

Strategy Implement the expanded-ARMM Road Mapping and Management (e-ARMM) Project, in order to: establish a database containing all roads in the ARMM inclusive

of their connectivity and conditions, and other public infrastructures within ARMM which are essential for use as monitoring tool and reference in future programming; and

create a network system (via internet) involving 8 DEOs as data providers and the ORG thru DPWH ARMM as data repository.

Actions

A portion of PDES fund has been reserved for e-ARMM Project.

8 DEOs of the DPWH-ARMM shall be tapped to collaborate with the provincial engineering offices and LGUs in their respective areas and jointly conduct surveys and data gathering.

Measure Completion of e-ARMM Project is in March 2014.

Resource Requirements

P2.50 Million

Support Agencies ORG, REO and the 8 DEOs of DPWH-ARMM, 5 Provincial Government Offices, 116 LGUs and NGOs.

G. Outcome : 100% Baseline Data Mapping on Roads (national, provincial and municipal) Connectivity by end of 2013. This will serve as reference in prioritizing road programs and budgeting.

4. RAPID INFRASTRUCTURE DEVELOPMENT ASSISTANCE (RIDA) for ARMM

Page 144: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

Strategy Initiated talk with DPWH ManCom in 2012. Accepted conditionalities prior to devolution.

Actions

DPWH-ARMM established the Basilan Satellite DEO in Lamitan City through EO 14, series of 2012 signed by RG Hataman.

Assigned Technical Personnel to run the office.

Constructed the building for Satellite Office in Feb 2013.

Allocated project funds for 2012, 2013 and MOOE/PS.

Measure Devolution will take effect on the 3rd Quarter 2013.

Resource Requirements

Will be provided Regular Budget

Support Agencies DPWH-ARMM, DPWH National, DBM and ORG

H. Outcome : Devolution of Basilan DEO from DPWH National to DPWH-ARMM before end of 2013.

4. RAPID INFRASTRUCTURE DEVELOPMENT ASSISTANCE (RIDA) for ARMM

Page 145: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

I. Outcome : Sufficient Acquisition of DPWH-ARMM Construction Equipment

Fleet for the 5 Area Equipment Service Offices by the end of 2013.

Strategy Generate savings to purchase additional equipment.

Action

Prudent fiscal

management on budget spending. additional 11 equipment/vehicles to be purchased.

2013 (First Half) 27 equipment/vehicles

9 survey instruments

________________ 27 equipment/vehicles

2013 (Second Half) 11 equipment/vehicles

___________________ 11 equipment/vehicles

Measure 27 units (73%)

38 units (100%)

Resource Requirements

P150 M (Budget from savings)

Support Agencies DBM, ORG and DPWH-ARMM

4. RAPID INFRASTRUCTURE DEVELOPMENT ASSISTANCE (RIDA) for ARMM

Page 146: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

V. PERSONNEL REPORT

Page 147: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

PERSONNEL SUMMARY

Regional Office

Basilan DEO

Lanao del Sur

Maguindanao Sulu Tawi-Tawi

Total

a. DEO I b. DEO II c. AES

a. DEO b. AES

a. DEO I b. DEO II c. AES

a. DEO b. AES

a. DEO b. AES

Regular 128 44 a. 81 b. 12 c. 37

a. 73 b. 41

a. 75 b. 45 c. 41

a. 59 b. 14 650

Casual None None a. None b. None c. None

a. None b. None

a. 10 b. None c. None

a. None b. None 10

Contractual None None a. None b. None c. None

a. None b. None

a. None b. None c. None

a. None b. None None

Contract of Service

None None a. None b. None c. None

a. None b. None

a. None b. None c. None

a. None b. None None

Job Order 79 20 a. 104 b. 33 c. 4

a. 98 b. 6

a. None b. 36 c. 5

a. None b. 4 389

Total 79 64 a. 185 b. 45 c. 41

a. 171 b. 47

a. 85 b. 81 c. 46

a. 59 b. 18 1,049

As of December 15, 2013

Page 148: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

STATUS OF APPOINTMENTS As of December 15, 2013

OFFICES Number of Personnel

Permanent Temporary Co-terminus

Regional Office 128 126 0 2

Maguindanao Engineering District 73 72 1 0

Lanao del Sur Engineering District 93 92 1 0

Sulu First Engineering District 75 74 1 0

Sulu Second Engineering District 45 41 4 0

Tawi-Tawi Engineering District 59 59 0 0

Basilan Engineering District 44 44 0 0

Maguindanao Area Equipment Services 41 41 0 0

Lanao del Sur Area Equipment Services 37 37 0 0

Sulu Area Area Equipment Services 41 41 0 0

Tawi-Tawi Area Equipment Services 14 14 0 0

TOTAL 650 641 7 2

Page 149: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

DPWH – ARMM CURRENT ORGANIZATIONAL CHART

OFFICE OF THE REGIONAL CABINET SECRETARY

OFFICE OF THE ASSISTANT REGIONAL SECRETARIES

PLANNING & PROGRAMMING

DIVISION

ADMINISTRATIVE DIVISION

SURVEY & DESIGN DIVISION

MAGUINDANAO AREA EQUIPMENT

SERVICES

MAGUINDANAO ENGINEERING.

DISTRICT OFFICE

LANAO DEL SUR ENGINEERING

DISTRICT OFFICE

SULU 1ST ENGINEERING

DISTRICT OFFICE

SULU 2ND ENGINEERING

DISTRICT OFFICE

TAWI-TAWI ENGINEERING

DISTRICT OFFICE

LANAO DEL SUR AREA EQUIPMENT

SERVICES

SULU AREA EQUIPMENT SERVICES

FINANCE AND MANAGEMENT

DIVISION

CONSTRUCTION DIVISION

MATERIAL QUALITY CONTROL & HYDROLOGY

DIVISION

MAINTENANCE DIVISION

EQUIPMENT DIVISION

SERVICES TECHNICAL

TAWI-TAWI AREA EQUIPMENT

SERVICES

Page 150: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

DPWH – ARMM 2014 MODIFIED ORGANIZATIONAL CHART

NEWLY CREATED OFFICES/PLANTILLA IN 2014 EXISTING OFFICES

MANAGEMENT INFORMATION SYSTEM

PLANNING & PROGRAMMING

DIVISION

ADMINISTRATIVE DIVISION

SURVEY & DESIGN DIVISION

MAGUINDANAO 1ST ENGINEERING

DISTRICT

MAGUINDANAO AREA EQUIPMENT SERVICES

TAWI-TAWI AREA

EQUIPMENT SERVICES

MAGUINDANAO 2ND ENGINEERING

DISTRICT

LANAO DEL SUR 1ST ENGINEERING

DISTRICT

LANAO DEL SUR 2ND ENGINEERING

DISTRICT

SULU 1ST ENGINEERING

DISTRICT

SULU 2ND ENGINEERING

DISTRICT

TAWI-TAWI ENGINEERING

DISTRICT

BASILAN ENGINEERING

DISTRICT

LANAO DEL SUR AREA EQUIPMENT SERVICES

SULU AREA EQUIPMENT SERVICES

BASILAN AREA EQUIPMENT

SERVICES

FINANCIAL & MANAGEMENT

DIVISION

CONSTRUCTION DIVISION

MATERIALS QUALITY CONTROL & HYDROLOGY

DIVISION

MAINTENANCE DIVISION

EQUIPMENT DIVISION

BUREAU OF SERVICES BUREAU O F OPERATIONS

OFFICE OF THE REGIONAL CABINET SECRETARY

OFFICE OF THE ASSISTANT REGIONAL SECRETARIES

Page 151: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

VI. CHALLENGES

Page 152: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

DPWH-ARMM TO SUSTAIN THE SIGNIFICANT GAINS OF REFORM ON ITS EXISTING PROGRAMS AND POLICIES UNDER THE HATAMAN ADMINISTRATION.

DPWH-ARMM TO ACCELERATE IMPLEMETATION OF ARMM

INFRASTRUCTURE AS EMBODIED UNDER THE “RAPID INFRASTRUCTURE DEVELOPMENT ASSISTANCE (RIDA) for ARMM” IN ORDER TO UPLIFT LIVING CONDITION OF LOCAL RESIDENTS AND ENSURE SOCIO-ECONOMIC DEVELOPMENT IN THE ARMM BEFORE THE BANGSAMORO TRANSITION IN 2015.

DPWH-ARMM TO ENHANCE COLLABORATIVE EFFORT WITH THE

PROVINCIAL AND LOCAL GOVERNMENT UNITS IN THE ARMM, AND SECURE TECHNICAL AND FINANCIAL ASSISTANCE FROM THE JICA IN THE SUSTAINABLE IMPLEMENTATION OF THE EXPANDED ARMM ROAD MAPPING AND MANAGEMENT (e-ARMM) SYSTEM.

Page 153: Republic of the Philippines Autonomous Region in Muslim ...€¦ · Muslim Mindanao Autonomy Act ... An effective and efficient DPWH-ARMM mandated to deliver basic infrastructure

Thank you…

“BIYAHENG DPWH-ARMM SA MATUWID NA DAAN TUNGO SA REPORMA AT KAUNLARAN.”