Reporting on 2009-2011 2-Year Milestones:. Recommendations MB Meeting – Dec. 8, 2010. Context CBP Executive Council Agreed Action re: State 2-Yr. Milestones. June 2010 – The Executive Council stated that The 2011 Bay Barometer will be revised to provide - PowerPoint PPT Presentation
Citation preview
Reporting on 2009-2011 2-Year Milestones:
Recommendations
MB Meeting – Dec. 8, 2010
Context
CBP Executive Council Agreed Action re: State 2-Yr. Milestones
June 2010 – The Executive Council stated that The 2011 Bay Barometer will be revised to provide a vehicle for reporting on each partner’s progress on
implementing their milestone actions and achieving the accelerated nutrient and sediment reductions committed to in May 2009.
Nov. 2010 – The PSC accepted the MB’s recommendation that milestone tracking not be included in Bay Barometer
… … vehicle for reporting on each vehicle for reporting on each partner’s progresspartner’s progress on implementing their milestone actions and achieving the accelerated nutrient and sediment reductions committed to in May 2009.
http://archive.chesapeakebay.net/pressrelease/EC_2009_allmilestones.pdf
… the partnership will use short-term goals to increase restoration work, called milestones. Every two years, the six states and D.C. will meet milestones for implementing measures to reduce pollution from nitrogen and phosphorous, with the first milestone on December 31, 2011.
Visualizing milestone periods
State 2-Yr Milestones timeframe*
May 2009 Dec 31, 2011
May 2011 - EC Mtg
Report on M’stones 5/09-12/10
Jan. 1, 2012
TMDL-related Milestones – 1st tracking period
Dec. 31, 2013
TMDL-related Milestone development period (WIPs, etc.)
•Actually 2.5 yr period; question on how ea. state will report – 2yrs or 3 yrs? WQGIT will work on reaching consensus on timeframe
May 2012 - EC Mtg
“Final” Report on State M’stones?? –Time period 5/09 – 12/11
For MB Discussion & Decision• HOW to report on milestone progress…
– Recommendation• Create a printed, concise “Summary” document (4 pp max.)
– Describes the concept of milestones (both State and coming TMDL) – Contains simple top-level statement of ea. state’s progress to date– Contains some graphs or charts that reflect top-level statements– Text & info for this document to be generated from data from states for 2010 progress run– Audience: Media, EC guests, general public– Answers the basic question: How is each state doing so far?– Date Complete: EC Meeting (May)
• ChesapeakeStat will show detailed tracking of states’ progress – Tracking info supported by BayTAS and same data as above.
– Audience: Educated media, Bay stakeholders (watershed groups, state agencies), educated public
– Date Complete: EC Meeting (May)
• WHAT to report on re: milestone progress…– For discussion!– Suggestion….keep it simple!
• Report on Nitrogen – Percentage reduction?• Report on Phosphorus – Percentage reduction?