Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
NOT PROTECTIVELY MARKED Paper 3
CCF Project Dossier Page 1 of 29 22 April 2015
Report to: SERVICE TRANSFORMATION COMMITTEE
Report No: C/STC/09-15
Date: 23 APRIL 2015
Report By: DCO CLARK
Subject: SERVICE TRANSFORMATION PROJECT DOSSIER SCRUTINY
1 PURPOSE
1.1 The purpose of this report is to provide the Service Transformation
Committee (STC) with an update on the eight project dossiers that were
planned to come forward to the STC at the April meeting.
2 RECOMMENDATIONS
2.1 The STC is asked to consider the project dossiers (appendix A) with a focus
on the following areas:
The two dossiers that will be presented at the meeting.
The three dossiers that will be made available for the STC to consider
that will be presented by the Programme Manager.
The three dossiers that have been delayed and their progress to date.
3 KEY POINTS
3.1 Two project dossiers will be presented by their project managers due to
their importance in ensuring the Programme delivers the benefits of
reform:
SA2.1.6 Specialist Resources Phase 2, Implementation. The
presentation will focus on the implementation methodology of
engaging the Service Delivery Areas, training and financial
implications.
SA 2.2.1.2 Command and Control Futures, as requested by the
NOT PROTECTIVELY MARKED Paper 3
CCF Project Dossier Page 2 of 29 22 April 2015
STC at their March meeting the presentation will focus the delivery
of the Edinburgh and Dundee control rooms. The presentation will
include a revised timeline for delivery along with the financial and
staffing implications.
3.2 There are three projects coming forward to the STC that will be set out by
the programme manager:
SA 2.2.1.3 Vehicle and Equipment Workshops
SA 2.2.1.4 National Headquarters
SA 2.2.1.7 Property Disposal
3.3 These three projects form part of the Strategic Intent for asset
management. The STC should note that this will leave one project still to
come forward from that workstream, SA 2.2.1.1 Training Accommodation
for Cambuslang. This allocation of funding for this project from the capital
plan approved by the Fire Board in April does not commence until 2017
after the Programme is anticipated to close and therefore the dossier for
this project is not planned to come forward to the STC.
3.4 There are three projects that were originally planned to come forward to
this meeting for the STC to consider have been delayed until the 11th June:
SA 2.1.8 Watch Duty System for Scotland has been delayed due to
further scoping work to be completed and the new project manager
being appointed only last week.
SA2.1.14 Out of Hospital Cardiac Arrest has been delayed as
further scoping work is required to align with the national strategy
that will be released in May by the Scottish Government.
SA 2.2.1.5 Office Accommodation has been delayed due to the
project manager being delayed due to work capacity issues.
4 FINANCIAL IMPLICATIONS
4.1 The financial implications for each project are set out in the project dossier
directly identified with this report.
5 EMPOYEE IMPLICATIONS
5.1 There are no employee implications directly identified with this report.
NOT PROTECTIVELY MARKED Paper 3
CCF Project Dossier Page 3 of 29 22 April 2015
Prepared by Frank Clayton Service Transformation Programme Manager 15 April 2015
Appendix A
Service Transformation Programme
Projects Dossier
Project Name: SA 2.1.6 Specialist Resources – Implementation Phase
Date: 31/3/2015
Parent Programme: Operational Service Delivery
Author: GM David Coulter
Project Manager AM John Dickie
Executive Lead ACO Goodhew
Project Start Date 1/4/2015
Project Finish Date 31/3/2018
Version 0.1
Revision History
Revision Date Summary of Changes Approval Date
0.1 Draft.
NOT PROTECTIVELY MARKED Paper 3
CCF Project Dossier Page 4 of 29 22 April 2015
Objectives
To implement the outcomes of the Review of Specialist Resources, as approved by
the Fire Board at the meeting of 27 January 2015. By ensuring that our specialist
resources are strategically located in such a manner to provide the most efficient and
resilient service delivery model for such limited assets, this will also assist the SFRS
to realise the key aims of reform:
Safeguard & improve local services, by reducing unnecessary duplication and
maintaining frontline outcomes.
Strengthen the connection with communities
Provide equal access to specialist resources
Scope The strategic positioning of specialist resources has been mandated following
approval of the Board. This project’s scope is to identify and implement all of the
report’s recommendations and objectives; including all appliance deployments,
redeployments and removals from service where appropriate.
Exclusions As previously outlined within the final report from Phase 1, this project is limited to
resources on the Scottish mainland. In addition, crewing arrangements for these
appliances are outwith the scope of this project.
Requirements The project will be project managed from within the current Response and Resilience
structure, with Project Support provided by a WM currently seconded to Command
and Control Futures (50% time commitment to this project).
Cross functional resources will be required from:
Service Delivery- 1 GM from West and East, 3 from North; operating within their existing workloads.
Fleet – Fleet Manager involved on project team
Property – Property Manager represented on project team
Workforce planning – representative on project team
Training – heavy commitment of training instructors scheduled within business as usual.
NOT PROTECTIVELY MARKED Paper 3
CCF Project Dossier Page 5 of 29 22 April 2015
Budget requirements
Resource Year 1 Year 2 Year 3 Training
Water £420,000 £220,000 £200,000 All training for these specialist resources can be delivered in-house, therefore are considered as business as usual for budget. Caveats: 1 capacity issues where increased activity is proposed. 2 accommodation costs 3 additional instructor training (USAR/Water) to bring into line with declaration of UK standard, estimated at £50k. Full detail will be included in the local plans.
Height £2m £2m £1.5
Line - £120,000 £110,000
HRV £300,000 - -
USAR £80,000
Marine Firefighting
- - -
Hazmats Subject to future SLT paper (May 2015), following review
Total £2,720m £2,420m £1,810m
Outputs
3 detailed project plans, to support the draft high level plan attached as appendix A
Full implementation to time and cost Milestones
1 The creation of a cross functional project team, with representatives from
Response and Resilience, Training and Employee Development, Service Delivery in
all 3 areas, Fleet, Property and others as required
Identification of team members by 31 March 2015
Team meeting schedule and initial meeting by 30 April 2015
2 The creation of 3 detailed, local project plans to support the high-level plan
attached to this outline document
Complete by 30 June 2015
3 Creation of a communications and engagement strategy, with ongoing local
engagement with staff representatives and external partners
Communications plan by 31 May 2015
Engage on local project plans June/July 2015
4 Agree target figures for training requirements
SLT paper April 2015
Commence training April 2015
4 Final delivery
March 2018
NOT PROTECTIVELY MARKED Paper 3
CCF Project Dossier Page 6 of 29 22 April 2015
Dependencies
Training and Employee Department resources and capacity
Fleet resources
Property department resources
Consultation and Engagement
A full engagement exercise was undertaken in delivering the Specials Review.
Ongoing engagement with internal and external stakeholders will commence as per
the local delivery plans, as per milestone 3 above.
Risks
There is a risk of cross functional capacity and priorities affecting the timeline for delivery
Benefits
a more efficient service delivery model, using standardised procedures and equipment, deployed from strategically positioned stations
more equal access to fire and rescue services for the communities of Scotland
reduced burden on stations, ensuring competency is maintained; thus improving firefighter and community safety
Performance Measures
Delivery of project milestones to time and cost
Disbenefits
capital costs
NOT PROTECTIVELY MARKED Paper 3
CCF Project Dossier Page 7 of 29 22 April 2015
Service Transformation Programme
Projects Dossier
Project Name: SA2.2.1.2 Control Rooms Integration
Date: 23 April 2015
Parent Programme: Strategic Intent
Author: GM David Coulter
Project Manager AM Tony Hughes
Executive Lead ACO Goodhew
Project Start Date Jan 2014
Project Finish Date Sept 2017
Version 0.3
Revision History
Revision Date Summary of Changes Approval Date
0.1 Draft. Based on original Business Case
and current SI planning
0.2 Draft following amendment
0.3 Draft following amendment
NOT PROTECTIVELY MARKED Paper 3
CCF Project Dossier Page 8 of 29 22 April 2015
Objectives
The creation of a single SFRS on 1st April 2013 brought a unique opportunity to
review all areas of service delivery with the goal of realising the expected benefits of
reform and ensuring a first class fire and rescue service for Scotland.
The inherited situation of eight control rooms serving Scotland but having an
extremely limited ability to interoperate and to identify and mobilise the most
appropriate resources; coupled with ageing operating systems, an ongoing reduction
in activity levels and tight financial climate, lacked the required levels of efficiency
and effectiveness.
The Command and Control Futures (CCF) programme will deliver to the SFRS a
modern, resilient and scalable command and control communications system and
supporting structure that meets the priorities of the organisation in terms of improving
firefighter and community safety; and improving the equity of access to resources for
all the communities of Scotland.
Scope
Within the scope of this project are 2 key outcomes, both of which have a series of
dependent workstreams to achieve; and are critically underpinned by an absolute
requirement to maintain day-to-day control room functionality. The twin outcomes
are:
The staged rationalisation of the existing control room portfolio to its agreed end state structure, including liaison with other key departments such as for technical (ICT) and property enabling and adaptations work
The procurement, delivery and installation of a standardised, resilient command and control technical platform.
Exclusions
A number of functions and systems, while acknowledged to be key dependencies
and mission critical elements within a control room, fall outwith the scope of this
project. These are:
NOT PROTECTIVELY MARKED Paper 3
CCF Project Dossier Page 9 of 29 22 April 2015
Any Management Information System (MIS)
The supporting Geographical Information system (GIS)
Provision of any supporting broadband or interconnecting systems, which falls within the ICT strategy as Senior Suppliers to the CCF
Human Resource / Voluntary Severance, Early Retirement activities to achieve the agreed end-state staffing structure.
Requirements
Command and Control (Computer Aided Despatch - CAD)
Automatic resource availability management
ICCS (Integrated Computerised Communications System)
Uniform service and support provision
Capital investment: £7.5m plus £3.15m property upgrades. Outputs
3 regionally based control rooms
1 standardised, distributed Command and Control operating platform with accompanying standardised operating policies and procedures. (Partnership with Northern Ireland Fire and Rescue Service to share a single procurement exercise resulting in 2 separate contracts being issued).
2 Disaster Recovery Centres to ensure resilience and business continuity
Rationalised property, infrastructure and resource base
Centralised and standardised data capture and storage Milestones
Establish fully resourced project team by April 2014
Merger of Dumfries and Johnstone control rooms by Nov 2014
Issue procurement PQQ by end Feb 2015
Communications/engagement plan delivered by June 2015
Issue procurement ITT for new software platform by July 2015
Decant Tollcross control to temporary standby to allow property upgrade by 8/6/15
Re-occupy Tollcross control by end Oct 2015
Award system contract by 18/12/15
Close Maddiston and Thornton controls by 31 Dec 2015
User acceptance testing of new system commences Oct 2016
Upgrade Edinburgh control to new CCF system by end Dec 2016
Close Inverness and Aberdeen control rooms, merge with legacy Dundee control by end Dec 2016
Property upgrade North control room by end Mar 2017- (Blackness Road, Dundee remains the selected and Board approved location; however colleagues in Asset Management are currently also reviewing 2 additional sites in Dundee, in the interests of securing best value.)
Upgrade West Control to new system by end March 2017
Upgrade North Control to new system by end Jun 2017
NOT PROTECTIVELY MARKED Paper 3
CCF Project Dossier Page 10 of 29 22 April 2015
Project closure end Sept 2017
Dependencies
ICT resource and strategy
Property department resources
Airwave contract amendments
3rd party priorities (Capita and Northgate as suppliers of existing control systems)
Northern Ireland FRS requirements
GIS/Gazetteer project requirements and delivery of functionality
OI system requirements
National Callsigns delivery schedule and costs
ESMCP/SFCP projects for Firelink replacement
Incident Recording System
Consultation and Engagement
An engagement exercise will be undertaken from January 2015 to project closure,
including a formal plan created in May 2015. This will include the following
stakeholders:
Internal stakeholders External stakeholders
Fire Board Scottish Government
Strategic Leadership Team Airwave
Strategic Intent Board ESMCP/SFCP
CCF Board
Representative Bodies
Consultation will be conducted as required, for example with the Fire Board if any
substantial change to the business case is proposed.
Risks
There is a risk of insufficient staff resources being available, particularly if staff are required to return to Control to maintain business as usual
There is a risk of cross-functional resource limitations affecting timelines, for example ICT capacity, property upgrade decisions and capacity
There is a risk that engagement with NIFRS will complicate and delay the procurement process
NOT PROTECTIVELY MARKED Paper 3
CCF Project Dossier Page 11 of 29 22 April 2015
There is a risk that the final solution suppliers may not be able to meet the SI programme deadlines for CCF deliverables
There is a risk that final costs outweigh estimates
Benefits
A single Command and Control platform for the Scottish Fire and Rescue service will
provide:
A more consistent approach to the mobilisation of resources, which removes all historical boundaries and achieves a high degree of interoperability and resilience. Whilst difficult to measure accurately, comparison between response times and legacy ‘cross-border’ activity will indicate efficiency. Improved ‘call-handling’ and ‘call-challenging’ will also be measured
Standardised policies, procedures, practices and data gathering/storage
Centralised staff training and development
A fit for purpose mobilising system for the next 10 years with the option for a contract extension of a further 5 years
Consistency of access to national and strategic resources across all communities.
Improve operational efficiency by reducing cost baseline. As displayed in the tables below, this can be measured against annual cost efficiencies of £2.34m through a staffing establishment reduced by 61 posts and a circa £400k annual reduction in ongoing system maintenance costs. Benchmarking against legacy and UK-wide ‘cost per incident’ should also show improvement.
Staff costs Firefighter Crew Manager
Watch Manager
Station Manager
Group Manager
Total
Baseline (legacy authorised)
122 46 50 9 3 230
End state 101 32 26 6 4 169
+/- -21 -14 -24 -3 +1 -61
Annual Saving (£’000s)
726
536
991
144
(57)
2340
System Costs Capital Resource
Baseline (legacy authorised)
Not identified, minimum 2 systems at end-of-life.
Aggregated annual maintenance fees for 8 control rooms
995
End state As per agreed Capital programme
10,500 Early estimate but subject to
ongoing tender exercise 600
+/- n/a 395
Saving (£’000s)
n/a
395
NOT PROTECTIVELY MARKED Paper 3
CCF Project Dossier Page 12 of 29 22 April 2015
Performance Measures
Timely delivery of project milestones to time, cost and quality
Adherence to project governance obligations
Transition of migrated operational services without interruption to live service
Realisation of cashable efficiencies
Improved ‘cost per incident’ and ‘call-handling’ (SFRS KPI)
Disbenefits
Staff displacement and redeployment
Perceived loss of ‘local knowledge’ although this is non-quantifiable and will be offset by improved technology and larger shift groups
Additional training
Paper 3
Strategic Intent Programme
Projects Dossier
Project Name: SA2.2.1.3 Vehicle and Equipment Workshops
Date: 24/11/2014
Parent Programme: Strategic Intent
Author: B Mallon
Project Manager B Mallon
Executive Lead Sarah O’Donnell
Project Start Date June 2014
Project Finish Date December 2020
Version 01
Revision History
Revision Date Summary of Changes Approval Date
Objectives
NOT PROTECTIVELY MARKED Paper 3
2
With the amalgamation of the 8 Scottish Fire and Rescue Services in one single Scottish
Fire and Rescue Service, it has been identified that the legacy provisions with regards to
asset management were adequate for the planned asset management functions of the
former eight services. As a single Scottish Service there is a business requirement to
structure the facilities that we operate in relation to asset management functions in the best
way to deliver our service effectively, and to minimise the cost of doing so. There is an
opportunity to combine the vehicle and equipment workshops with other asset support
functions (such as Stores, Communications, Property and PPE Management) into a network
of Asset Resource Centres across Scotland. This process would enable the development of
centres of expertise with a “One Stop” approach to all asset support functions. This is
anticipated to deliver managerial efficiencies, while also minimising the number of facilities
required with the associated property related savings.
There is a regulatory and legislative requirement to ensure that common standards,
processes and legal compliance are achieved across the Service for the maintenance and
inspection of all assets belonging to SFRS.
Due to the age and condition of legacy Workshop/Stores set up in the three services delivery
area’s there is a need to provide an ARC as described above in each of the service delivery
areas, as soon as is practicable to allow realisation of strategic intent aims and objectives.
Scope
There are four specific work Stages of the project which will produce strategically positioned
asset resources centres (ARC) and they are:
1. The current work shop facility at Newbridge Industrial Estate Edinburgh has been upgraded under a separate non Prince2 stand-alone project with an investment of circa £500K. To ensure quality controls and objectives have been obtained and confirmed, then this site will have to be included within the project scope to ensure all goals have been met before overall project can be closed out.
2. The current work shop facility at Seafield Road Inverness has been upgraded under a separate non Prince2 stand-alone project with an investment of circa £360K. To ensure quality controls and objectives have been obtained and confirmed, then this site will have to be included within the project scope to ensure all goals have been met before overall project can be closed out.
3. Hub Co has completed a scoping report for a facility to be located in the North East (A90 Aberdeen-Dundee corridor) and this is being used to assess the next stages of the project. As
NOT PROTECTIVELY MARKED Paper 3
3
this is at an early stage work by Hub Co so far predominately relates to selecting a suitable site. Additionally an outline high level specification for the ARC is being produced and discussed by all relevant stakeholders. In conjunction with the above a scoping exercise to locate and evaluate any turnkey options of suitable sites within the A90 corridor will be completed and a final decision on the preferred option will be presented to the SLT and board for approval and instigation.
4. It is envisaged that the model for the North East Arc will be replicated either partially or wholly for the West Arc. At the same time a lessons learned approach from the North East Arc will be employed to ensure maximum efficiency.
Exclusions
Any immediate change in current contractual obligations.
Requirements
Prince2 Project Management skills to complete the project and a confirmed budget allocation
of £860K committed for works at Newbridge and Inverness. A further investment of circa
£3.6M is envisaged for further works at the North East Arc.
Early indications are that a similar amount of £3.6M will be allocated for the West ARC
pending realisation of funds from the disposal project.
Outputs
The project will deliver a Vehicle and Equipment Workshop culminating in an Asset
Resource Centre (ARC) based in the North Service Delivery Area (NSDA), North East
Service Delivery Area (NESDA), East Service Delivery Area (ESDA) and West Service
Delivery Area (WSDA).
These centres will be a modern fit for purpose facility for all functions related to the Asset
Management Directorate activity in their respective SDA.
Four strategically located asset resource centres (ARC) accommodating Fleet, Equipment
and ICT workshops at Newbridge, Inverness and 2 centres one being in West (Greater
Glasgow/Lanarkshire area with motorway access) and the other being in the North East
(A90 Aberdeen-Dundee corridor) TBC
NOT PROTECTIVELY MARKED Paper 3
4
Milestones
The project will consist of 10 main stages (subject to funding and decisions being agreed)
Stage 1 Project start up – this will consist of the development of key areas in order that the project can commence It is anticipated that this stage will operate between 10/06/2014 to 18/11/2014
Stage 2 Initiating and planning the project – this will consist of identification of key areas of work required to deliver the project as required within the project brief. It is anticipated that this stage will operate between 10/06/2014 to 18/11/2014
Stage 3 Delivery Option Appraisal - This stage will appraise all options open to SFRS on how best to deliver a fit for purpose Asset Resource Centre (ARC) that meets the needs of the organisation. It is anticipated that this stage will have timelines which have still to be confirmed.
Stage 4 Completion of upgrades at Newbridge, it is anticipated that this stage will be completed on the 11/04/2014.
Stage 5 Completion of upgrades at Inverness, it is anticipated that this stage will be completed on the 11/04/2014.
Stage 6 Approval of location of North East ARC, it is anticipated that this will be confirmed by end of December 2014.
Stage 7 Commencement of North East ARC indicative date of June 2015.
Stage 8 Approval of location of West ARC indicative date of September 2016.
Stage 9 Commencement of West ARC indicative date of April 2018.
Stage 10 Project Closure – this stage will see the review and monitoring of all project objectives and deliverables with final hand over recommendations report to the Project Executive. Indicative date of December 2020.
NOT PROTECTIVELY MARKED Paper 3
5
Dependencies
The completion of the ARC will result in the release of other properties, producing a financial
realisation of funds from property rationalisation.
Consultation and Engagement
Meetings will be undertaken with representatives for the Property, Legal and Finance section at all stages of the project to ensure correct governance is obtained.
Risks
With the exception of a capital funding to complete the project, there are no other
dependencies with other Strategic Intent projects.
Benefits
Suitable modern facilities to enable routine and unplanned servicing, maintenance and repair of the SFRS fleet and equipment portfolio consisting of some 1500 vehicles and 650,000 items of operational equipment.
Access to road networks to maximise the number of assets to be reached within 60 minutes, currently estimated at 80% of Fleet vehicles.
Staff TUPE’d over from Fife to Tayside and Lothian and Borders, commensurate with the redistribution of legacy fleet vehicles from Fife Council.
Enabling the development of centres of expertise in line with the Institute of Road Traffic Engineering Council (IRTEC) best practice manual for all aspects of asset support, which would be scalable and in line with current and future service requirements.
Improved front line support with a facility for all asset related enquiries and support. This will reduce financial operating costs, provide enhanced performance from a pool of varied skilled technicians and will reduce any duplication of working practices across SFRS.
Will assist with the release of capital receipts through disposal of decommissioned assets on completion of ARC which will be carried out under the disposal project.
NOT PROTECTIVELY MARKED Paper 3
6
Opportunities to generate income from activities for third parties, i.e partnership working on a shared services basis with Scottish Police and Scottish Ambulance Services, based on the scalability of the ARC.
Performance Measures
Closure of Maddiston workshops with vehicles transferred to Newbridge to allow maintenance and repair work to be completed.
Transferral of all further Fife fleet of 60 vehicles to Newbridge from Tayside during the development of Newbridge.
Staff restructuring realising revenue savings in excess of £160K year on year.
Reduction in property cost of approximately £15K year on year.
Recruitment of skilled staff into existing unfilled posts.
Disbenefits
Early indications have identified the relocation of staff from one workshop to another may
pose problems, however, it is envisaged that these can be addressed as and when they
arise.
NOT PROTECTIVELY MARKED Paper 3
7
Projects Dossier
Project Name: SA2.2.1.6 National Headquarters
Date: December 2014
Parent Programme: Strategic Intent
Author: Claire Owens
Project Manager Claire Owens
Executive Lead Sarah O’Donnell
Project Start Date December 2014
Project Finish Date May 2017
Version Draft
Revision History
Revision Date Summary of Changes Approval Date
NOT PROTECTIVELY MARKED Paper 3
8
Objectives
On the creation of the SFRS there were 8 recognised headquarter buildings across
Scotland; one in each of the antecedent services. These are located in Hamilton, Dumfries,
Edinburgh, Maddiston, Thornton, Dundee, Aberdeen and Inverness. All of the buildings
currently contain staff working for either the service delivery area or in support of a
recognised headquarters function.
The Strategic Intent proposals considered by the board at its meeting in September 2013
and again in January 2014, identified the need for the SFRS to establish a headquarter that
would be fit for purpose and would form part of the infrastructure that would support an
effective single fire & rescue service. This will benefit the service by creating a focal point for
the organisation that will bring key staff together to develop strategy and ensure its effective
implementation. It will provide the service with a visible presence within Scotland and,
through visibility, help influence cultural change.
This proposal was agreed by the board with additional direction that the location of the
headquarters should fall within the triangular area bounded by the locations of Glasgow,
Perth and Edinburgh. This decision is aligned to the criteria established by Scottish
Government whereby it I recognised that as a significant national body the SFRS should
demonstrate its commitment to serving the whole of Scotland by maintaining a significant
national footprint across the country.
Scope
The establishment of a new principle office building (headquarters) for the Scottish Fire and Rescue Service that is reflective of a decentralised organisation.
Exclusions
HR activities Requirements
A site options appraisal and full business case must be prepared in line with the specific criteria set out by the Scottish Government (Appendix 1), in line with HMT Green Book.
Principal office to be designed to accommodate 120 staff with the potential to accommodate 200 staff in the future.
The budget will be determined on completion of the site appraisals and full business case followed by the decision of the board on the successful option.
Project to be managed in-house by SFRS employees Outputs
Full site options appraisal exercise
Production of a fully developed business case in line with HMT Green Book
Delivery of operationally ready Principal office building (headquarters)
NOT PROTECTIVELY MARKED Paper 3
9
Milestones
Completion of options appraisal exercise for the location of the new National HQ by mid February 2015.
Finalised full business case and site options developed 18th March 2015. Failure to complete this exercise could delay board decision on the location of the National HQ.
Board decision on the location of the new National HQ 27th March 2015. Failure to reach a decision at the board meeting will delay delivery of the project.
Design / Tender initiation of the site specific response to business case following board decision on HQ location Q 2 / 3 2015 ( dependent on project sign off and procurement route)
Development of tender works for completion May 2017 Dependencies
This project has no product dependencies
Consultation and Engagement
Section 15 of Schedule 1A of the Police and Fire Reform (Scotland) Act 2012 refers to the location of the principal office premises of the SFRS. It states that:
Any determination by SFRS as to the location of the principal office premises of its
members or its Chief Officer is subject to the approval of the Scottish Ministers.
Meetings will be undertaken with the appoint client liaison officer and representatives from Property, COMMs, HR, Legal and Finance Section and Representative Bodies
Consultation with Local Authorities on land availability, value and Section 75 requirements 20th and 23rd February.
Consultation with SI Board, SLT & SFRS Board will take place in the form of meetings and / or workshops on 25th February, 10th & 12th March 2015 (to be confirmed)
Finalised full business case and site options appraisal report 18th March for consideration by the board on 27th March 2015
Approval to proceed will be sought from the executive lead at each Gateway Review stage.
Risks
Early Identified risk includes:
Insufficient funding to provide a facility that meets the aspirational image and operational requirements of the service
NOT PROTECTIVELY MARKED Paper 3
10
Insufficient information being provided to the design team regarding the people to be accommodated within the new facility
High monitory value and publicity likely to be attracted by the development of the HQ facility means there is a greater risk of procurement challenge.
Staff displacement cost are in excess of estimated figures.
Relocation proposals will result in loss of key staff
Conflict between Board and SG on the preferred location of new facility.
Delays in decision making and approvals
Benefits
The establishment of a principal building (Headquarters) for SFRS serving all of Scotland that is a fit for purpose and forms part of the infrastructure that would support a single fire service.
The new HQ will create a focal point for the organisation and bring key staff together to develop strategy and its effective implementation whilst improving operational efficiency.
Performance Measures Delivery of project within established:
Project governance obligations
Project programme
Approved budget
Agreed quality
Delivery of a fit for purpose principal office (headquarters) that is reflective of the project
brief.
Disbenefits
Potential loss of key staff due to relocation of workplace
Possible increase travel cost due to relocation of work place
NOT PROTECTIVELY MARKED Paper 3
11
Appendix 1
SCOTTISH FIRE AND RESCUE SERVICE HEADQUARTERS – CRITERIA
1. Section 15 of Schedule 1A of the Police and Fire Reform (Scotland) Act 2012 refers to the location of the principal office premises of the SFRS. It states that:
Any determination by SFRS as to the location of the principal office premises of its
members or its Chief Officer is subject to the approval of the Scottish Ministers.
This note sets out the criteria Ministers will apply in determining whether or not to grant
their approval to the SFRS Headquarters location proposed by the SFRS Board. In
addition to this specific statutory requirement, there are a number of generic
requirements on all public bodies which need to be taken into account, which are listed
here for ease of reference.
2. Ministers require the SFRS to follow the guidance contained within the SG Asset Management Policy and the Scottish Public Finance Manual (SPFM) - particularly the guidance around the acquisition of property.
3. Ministers require the SFRS to comply with the duty of Best Value placed upon it as outlined in the Guidance for Accountable Officers.
4. Ministers require that appropriate use is made of existing Framework agreements to ensure that procurement of services, property, goods, including but not limited to, equipment and furnishings is undertaken in line with the expectations placed on public bodies. The Scottish Procurement & Commercial Directorate can provide further advice on these issues.
5. In terms of securing the proper use of public money, Ministers require the SFRS Board to approach the selection of an HQ location in the same manner as any other investment decision, with a clear assessment of costs and benefits carried out in line with HMT Green Book guidance.
6. There will be a presumption in favour of the choice representing best value for money for the Scottish Government as a whole, providing that this meets the requirements of the organisation, unless clear reasons for an alternative are agreed by Ministers.
7. In addition to compliance with the policies and criteria highlighted above, Ministers expect the SFRS Board to take account of the following specific criteria.
NOT PROTECTIVELY MARKED Paper 3
12
Service Transformation Programme
Projects Dossier
Project Name: SA2.2.1.7 Disposal of Property Assets
Date: 25th March 2015
Parent Programme: Strategic Intent
Author: Russell Munn
Project Manager Russell Munn
Executive Lead Alex Lane
Project Start Date June 2014
Project Finish Date September 2018
Version One
Revision History
Revision Date Summary of Changes Approval Date
NOT PROTECTIVELY MARKED Paper 3
13
Objectives
The objective of the disposal project is to return maximum capital receipts from the property assets as identified for sale through the Strategic Intent programme in order to fund the future property projects required to facilitate the delivery of services in the new national service.
Scope
The disposal programme with cover the following properties:
2 Garelton Court, Gullane (residential property)
Sold for £150,000 on the 12th February 2015 to East Lothian Council. Funds
received March 2015.
19 Garelton Court, Gullane (residential property)
Sold for £152,000 on the 12th February 2015 to East Lothian Council. Funds
received March 2015.
26 Muirfield Park, Gullane (residential property)
Sold for £337,750 on the 30th January 2015 to private buyer. Funds received March
2015.
30 Muirfield Park, Gullane (residential property)
On the market to be sold by early summer 2015. Funds to be received by August
2015.
Training Centre, Main Street, Gullane (national training centre)
On the market to be disposed of by March 2016. Funds to be received in financial
year 2015/2016.
Laurieston Place, Edinburgh (offices and museum)
To be disposed of by October 2016. Funds to be received in financial year
2016/2017.
NOT PROTECTIVELY MARKED Paper 3
14
North Anderson Drive, Aberdeen (offices, training & site)
To be disposed of by July 2017. Funds to be received in financial year 2017/2018.
Maddiston Complex, Falkirk (offices, workshops & site)
To be disposed of by October 2016. Funds to be received in financial year
2016/2017.
Thornton Complex, Fife (offices, workshops & site)
To be disposed of by October 2016. Funds to be received in financial year
2016/2017.
Cowcaddens Complex, Glasgow (workshops, training & site)
To be disposed of by September 2018. Funds to be received in financial year
2017/2018.
Mounthooley Control, Edinburgh (offices & car parking)
To be disposed of by July 2017. Funds to be received in financial year 2017/2018.
The project will deal with the marketing and ultimate disposal of the above
properties with initial marketing and planning consultations to ensure maximum
receipts are received by SFRS for the assets concerned in an acceptable timetable.
Exclusions
The project will not identify the projects which the capital receipts from the disposals are directed to.
The project will not identify the areas within each of these properties where there are questions over the exact extent of the disposal such as at Laurieston Place and Cowcaddens.
NOT PROTECTIVELY MARKED Paper 3
15
The individual property values will not be shown due to commercial sensitivity. Requirements
The programme will be run in house with advice from external professional bodies in the areas of value, title, marketing and planning. The need for such advice will incur professional fees from various parties. These will be assessed as to whether such advice is essential or if it will add value in terms of ultimate capital receipts.
Outputs
Market Valuation reports have been instructed in order to ascertain the likely receipts from the disposals.
Title reports have been instructed for the initial subjects for sale, namely the residential properties in Gullane and the National Training Centre also in Gullane.
The next costs are likely to be for advice on marketing and planning in order that the correct assessments can be made as to whether to engage with local planning departments prior to sales and what timescales are appropriate to put the properties to the market.
Milestones
Dispose of Gullane Houses 1/03/2015
Dispose of Gullane Training Centre 1/03/2016
Dispose of Mounthooley Control 1/03/2016
Dispose of Maddiston Site 1/10/2016
Dispose of Thornton Site 1/10/2016
Dispose of Laurieston Place 1/10/2016
Dispose of North Anderson Drive 1/07/2017
Dispose of Cowcaddens 1/09/2018 Dependencies
In terms of producing the capital receipts projected through the Market Valuations this project is dependent on the outcome of decisions within other projects as to the realisation of the full potential.
The Heritage Project is looking in to the heritage aspect of the service and depending on the outcome of this the sale of Laurieston Place could be delayed depending on the outcome of decisions in this project or the capital receipts predicted for the property could be restricted to a greater or lesser extent depending on the decision to retain some of the elements of the existing building.
The sites to be disposed of are currently in use by various areas of the Service and so this project is heavily dependent on the provision of space at other locations being made available to accommodate the relevant personnel and equipment.
NOT PROTECTIVELY MARKED Paper 3
16
Consultation and Engagement
The full exercise covering the 6 identified properties will require consultation with several internal and external bodies including the Area personnel concerned, professional advisors, Local Authorities and Central Government.
At this stage it is not possible to timetable the numerous consultation that will be
required but these will be in line with the current milestones as set out as the
perceived disposal dates for each of the properties.
To date in terms of the disposal the Gullane Houses we have engaged with the
Scottish Government through the initial Trawl process, solicitors to determine the
Title, a Valuer to identify Market Value, East Lothian Council who are purchasing 2 of
the properties and a Marketing Agent for the remaining 2 houses.
We have engaged planning consultants, Barton Willmore to make representations to
East Lothian Council in order to maximise the potential for the site at Gullane through
the Local Plan process which will involve direct contact with planners, the community
and other professionals.
We have tendered to position of Marketing Agent for the former training college at
Gullane and have awarded this contract to Graham & Sibbald through their
Edinburgh offices.
Risks
Based on the basis that the success of the project will be to dispose of the properties identified to full market value in order to fund capital projects the various risks are as follows;
The full extent of sales will not proceed due to both internal and external factors such as the retention of elements of the identified sites or changes in the Service’s national requirements.
Local Authorities or communities identify the sites for community benefit. New legislation on this area is imminent but the potential effects of this are unclear at this stage.
The market will deteriorate over the timescale of the disposals and so the values stated to date will become unachievable.
NOT PROTECTIVELY MARKED Paper 3
17
Benefits
The project will raise capital receipts at a projected value of £14.8m to fund future property projects to replace these redundant premises with modern fit for purpose facilities within the strategic intent programme.
The disposal of these subjects will also remove the considerable revenue costs associated with these properties that are often functionally obsolete and run at a higher level of cost due to this redundancy and age. These are currently estimated at £4.7m sustainable annual revenue savings as per year (January 2014 Fire Board paper). Refreshment of this assessment is currently underway.
The change from these older obsolete properties to new better located premises with facilitate the purpose of the single national service and the principles behind this.
Performance Measures
The basic performance measures are time based in terms of realising the capital receipts in the financial year as required.
There will also be measures against the values as set out at the start of the project though as previously mentioned these may evolve given the timetable set.
The financial savings relating to the disposed property running and maintenance costs.
Disbenefits
The nature of property means that a sale of such requires initial costs in terms of legal and marketing advice and it will be the case that monies will be outgoing prior to receipts being realised therefore funds will require to be in place to meet these fees. Selling fees will vary according to the property being sold.
The properties may not achieve their projected value to meet the overall programme value of £14.8m