Report on Mill Vibration

Embed Size (px)

Citation preview

  • 8/12/2019 Report on Mill Vibration

    1/7

    PROJECT : RAYALASEEMA UNIT 3

    PROBLEM : REPORT ON MILL VIBRATIONS

    The bowl mills A and B of Unit 3 Rayalseema Thermal Power Plant had

    already run for more than 500 hrs of when it developed vibrations in

    the grinding zone. The vibration used to appear for 5 seconds at

    every 15 seconds interval and the mill current oscillated from no load

    current to full load (40 56Amps).

    So both the mills were stopped for inspection. The following internal

    checks were done:

    1.Ring roll setting was readjusted as per recommendations.2.Spring Compression was verified.3.Mill vane wheel vertical clearance, Scrapper and skirt clearance

    were checked.

    4.Bull ring segments were checked for looseness and found normal.5.Classifiers were checked and found normal

    Since no abnormity was observed the mills were taken back into

    service but the vibrations did not subside. Coal flow and Air flows

    were varied to observe the change in performance. While reduction

    of airflow reduced the period of vibration, increase in airflow

    increased the duration. Coal flow variation did not yield any change.

    Also it was observed that the raw coal fed had a large percentage of

  • 8/12/2019 Report on Mill Vibration

    2/7

    fines (approx 40 %). So it was suspected that the fines may have

    increased the recirculation inside and led to inconsistent bed

    formation. To overcome this problem, site increased the ring roll gap

    by one flat more than recommended by design. This was done to

    increase the bed height and facilitate bed formation. In addition, in

    mill B, the journal trunnion were shifted from position no. 1 to 2.

    During the next start up of these mills, the behavior was as indicated

    below:

    1.Mill current was hunting during the period of bed formation.Vibration appeared at the same time. The whole process took

    about 15 minutes.

    2.Once the bed was formed, the current stabilized and vibrationdisappeared.

    3.Subsequently even when the coal flow was varied, there were novibrations and current was steady.

    4.The increased bed height increased the grinding power. Afterthe adjustment mill A & B currents increased by 4 amps and

    are kept in regular service.

  • 8/12/2019 Report on Mill Vibration

    3/7

    MIL 3A PERFORMANCE

    Before adjustment:

  • 8/12/2019 Report on Mill Vibration

    4/7

    MIL 3A PERFORMANCE IMPROVEMENT

    After adjustment:

  • 8/12/2019 Report on Mill Vibration

    5/7

    MILL 3B PERFORMANCE

    Before adjustment:

  • 8/12/2019 Report on Mill Vibration

    6/7

    MILL 3B PERFORMANCE IMPROVEMENTAfter adjustment:

  • 8/12/2019 Report on Mill Vibration

    7/7