1
Report On Educational Visit
To
Flyover Bridge On Kalewadi Phata To Dehu-Alandi Road
Class- BE (CIVIL) Date :-18 Sept. 2016
2
The Department of Civil Engineering of Dr. D. Y. Patil School of Engineering
organized educational visit to Flyover Bridge on Kalewadi Phata to Dehu-Alandi Road,
Chinchwad, Dist.- Pune on 18th Sep. 2017 for B.E. Civil Engineering students to study
different aspects of Bridge Engineering. Visit was organized as per Pune University
guidelines and recommendations regarding syllabus of B.E Civil Engineering.
Visit was organized with the prior permission and guidance of honourable
Director of DYPSOE, Lohegaon. Dr. S. S. Sonavane & by the initiative and hard efforts
of head of Civil Engineering department Dr.A.R.Kolhe, & class teacher Prof. J. D.
Dalvi guided the students . Along with the staff members, students of B.E Civil takes
hard efforts and initiative under the continuous guidance of Prof. Amol Wagh, which
makes this visit a grand success.
Students left the DYPSOE Campus for visit on 18th Sept 2017 at 9.30 am.
Students carefully studied and observed the different Parts of Bridge such as piers,
bearing plate, abutment, bridge girder,etc.
3
Name : Bridge Visit
Location : Empire Estate Fly Over bridge, Near Ranka Jwellers, Chinchwad.
Date of Visit: 18th September 2017
Purpose of Visit: To Study about bridge and its components.
Guide Name: Mr. Pradip Gaikwad.
4
INTRODUCTION
The bridge project at empire estate under client name as PCMC. Type of contract
is C-1 type Lump Sum contract given to T & T Infra.Pvt.Ltd with total project cost Rs.
99.99 cr for completion period of 30 months .S.N.BHOBE & ASSOCIATES PVT. LTD
are consultants for these project.
The Flyover project is proposed on 45 m wide DP road for continuous
connectivity over natural barriers. The proposed flyover provides facility for crossing the
existing Pawana River , 18 m DP Road , Pimpri – Chinchwad Link road , Mumbai-Pune
Railway Line & Existing 61m wide Pune Mumbai Road etc.
Six Lane Flyover/Viaduct crossing the Pawana River, 18 M DP Road , Existing
Pimpri Chinchwad Link Road ,Central Railway Line of Mumbai Pune Rail , Existing
61m wide Pune Mumbai Road ( NH-4) and landing after NH4 on DP Road with
approaches and ramps.
This project includes:-
1) Bridge on Pawana River:-
The River Bridge consists of two separate individual carriageways
with overall width of 14.95 m each with central median. The individual
carriageway of River Bridge Portion consist Kerb, crash barrier and railing
between Ch 3+010 to Ch 3+130. The Approach with returns for River Bridge will
start From Ch 2+800 on Kalewadi Side and ends at Ch 3+010 of River bridge. The
Approach Portion consists of two separate individual carriageways with overall
width of 13.15 m each with central median. The individual carriageway of
approach Portion consist Kerb, crash barrier and railing between Ch 2+800 to Ch
3+010.
5
2) Continuous flyover/viaduct from Pawana River Bridge up to Rail Over
Bridge (ROB) crossing 18 m DP road & existing Pimpri Chinchwad Link
Road: -
The flyover/viaduct consists of two separate individual carriageway with
overall width of 13.45 m each with Kerb , Crash Barrier in between M V Lane &
Cycle track/pedestrian path & Noise Barriers mounted on crash barrier of outer
sides of individual carriageway in between Ch 3+130 to Ch 3+616. The portion
between two individual carriageways of flyover/Viaduct is varying between Ch
3+130 to Ch 3+568. This portion is varying to accommodate the space required
for proposed elevated bus stop.
6
3) ROB on Central Railway -Mumbai Pune Railway Line :-
The ROB consists of two separate individual carriageways with overall
width of 15.30 m each with central median. The individual carriageway of ROB
Portion consist Kerb, crash barrier and railing between Ch 3+616 to Ch 3+653.20.
Retaining Wall on one side of required length is to be constructed for retaining the
existing slope of the shunting track while excavating the foundation along the rail
line on Pune Mumbai within ROW
7
8
4) Continuous flyover/viaduct from Rail Over Bridge with Crossing of Existing
61 M wide Pune Mumbai Road (NH-4) with approach :-
The flyover/viaduct consists of two separate individual carriageways with
varying overall width as described below in between Ch 3+653.20 to Ch 4+393.
The flyover/viaduct consists of two separate individual carriageways with overall
width of 13.45 m each with central median. The individual carriageway of
flyover/viaduct Portion consist Kerb, Crash Barrier in between M V Lane & Cycle
track/pedestrian path & Noise Barriers mounted on crash barrier at outer sides
only of individual carriageway between Ch 3+653.20 to Ch 3+707.
5) Pedestrian Facilities such as Cycle cum pedestrian footpaths/ Track, &
Staircase :-
The raised Pedestrian Footpath with cycle track of 3.65 m wide is to be
provided on Pawana River Bridge and Rail Over Bridge in the individual
carriageway. The raised Pedestrian Footpath cum cycle track of 1.60 m wide is to
be provided on balance length of flyover/Viaduct portion in the individual
carriageway. Eight numbers of individual dog legged staircases of 3.00 m clear
width and landing at each corner is to be provided at Pawana River Bridge and
Rail Over Bridge.
9
These bridge is design for 80 kmph but allowance speed is 40 kmph . It is two-
way two-lane with clear carriageway of 9 m &11m for flyover. As per IRC gradient of 1
in 25 is limited and 1 in 30 is most preferable but for these bridge gradient provided is 1
in 28 .Water spot are provided with runner pipes as a drainage arrangement for bridge . It
also conisist of anti –crash barrier with height of 1200 mm and constructed as per IRC.
Defination:-
Bridge is a structure which covers a gap generally bridges carry a road,
walkways, pipelines or railway across a natural or artificial obstacle such as, a
river, water body (part of sea, canal) or another railway or another road /junction,
structure. Nowadays bridges are constructed to decongest traffic
10
Components of bridge:-
1. Foundation
Foundation constructed on dry land are called as land foundation .according to
geological condition of soil type of foundation used was pile foundation .
2. Sub-structure
a) Bearing:
The device which are provided over the support of the bridge to accommodate
the change in main girder.
11
Function of bearing is to absorb movements of girder , angular movement ,
longitudinal expansion or contraction , etc
Types :
a. Cement concrete pad
b. Expansion bearing
c. Knuckle bearing
d. Rocker and rolling bearing
e. Rubber bearing
f. Sliding bearing
g. Tar paper bearing
The Cement concrete bearing was used for construction .The load carrying
capacity of bearing is 2700 tonnes .
b) Approaches :The length of communication route affected by the layout and
design of the bridge , at both of its end are known as approach .
3. Super-structure
a) Piers
The intermediate support of a bridge superstructureare known as Piers .
Function of piers is to divide the total length of bridge into suitable spans
with minimum obstruction to the stream.
Types :-
a. Column bents
b. Cylindrical piers
c. Dumb-bell piers
d. Pile bent
12
e. Solid piers
f. Trestle bents.
The piers of bridge are single casted with some flower like grooves are made
for aesthetic purpose . The bridge is desigensuch maximum height of piers is
5.5m suitated in center and height decrease toward both end and Trestle bents
are used .
Dirt wall – These are used to take end wall load . These are made from individual
connected panels plus in shape.
CONCLUSION:-
We learn about various factor affect planning , designing , and execution of bridge
work . We also learn about Rail Over Bridge (ROB) crossing 18 m DP road. We also
learn about various documentation required for construction of bridge.
Prof. AMOL WAGH Prof. R.C.Katdare
(Subject teacher) (H.O.D)
Civil Dept. SOE