Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
THE REPUBLIC OF UGANDA
REPORT OF THE AUDITOR GENERAL
ON THE FINANCIAL STATEMENTS OF THE MINISTRY OF GENDER,
LABOUR AND SOCIAL DEVELOPMENT FOR THE YEAR
ENDED 30TH JUNE, 2016
OFFICE OF THE AUDITOR GENERAL
UGANDA
i
TABLE OF CONTENTS
PAGE
LIST OF ACRONYMS .......................................................................................................... i
REPORT OF THE AUDITOR GENERAL ........................................................................... 1
ON THE FINANCIAL STATEMENTS OF THE MINISTRY OF GENDER, LABOUR AND
SOCIAL DEVELOPMENT FOR THE YEAR ENDED 30TH JUNE 2016 ............................ 1
DETAILED REPORT OF THE AUDITOR GENERAL ON THE FINANCIAL
STATEMENTS .................................................................................................................... 4
1.0 INTRODUCTION ..................................................................................................... 4
2.0 BACKGROUND INFORMATION ............................................................................. 4
3.0 ENTITY FINANCING ............................................................................................... 5
4.0 OBJECTIVES OF THE MINISTRY .......................................................................... 5
5.0 AUDIT OBJECTIVES ............................................................................................... 6
6.0 PROCEDURES PERFORMED .................................................................................. 6
7.0 AUDIT FINDINGS ................................................................................................... 7
Funds not accounted for ....................................................................................... 8
8.0 Detailed Audit Findings ......................................................................................... 8
8.2 Youth Livelihood programme ............................................................................... 9
8.3 Payroll and Pensions Audit ................................................................................. 12
8.4 Funds not accounted for ..................................................................................... 13
8.5 Non-payment of Workman’s compensation within the stipulated time ....... 13
8.6 Staff management ............................................................................................... 14
8.7 Un-renewed workplace registration certificates .............................................. 16
8.8 Non-implementation of provisions under the Occupational Safety and
Health (OSH) Act 9, 2006 ................................................................................... 17
8.9 Review of implementation of Previous Year’s Recommendations ................ 17
i
LIST OF ACRONYMS
ESP Expanded Social Protection Programme
ILO International Labour Organisation
MoFPED Ministry of Finance, Planning and Economic Development
MoUs Memoranda of Understanding
MOGLSD Ministry of Gender, Labour and social Development
NTR Non-Tax Revenue
OSH Occupational Safety and Health
PFMA Public Finance Management Act
PS/ST Permanent Secretary/Secretary to the Treasury
SDIP Social Development Investment Plan
SDS Social Development Sector
UGX Uganda Shillings
ULC Uganda Land Commission
UPDF Uganda Peoples Defence Force
USA Uganda Scouts Association
YLP Youth Livelihood Programme
1
REPORT OF THE AUDITOR GENERAL
ON THE FINANCIAL STATEMENTS OF THE MINISTRY OF GENDER, LABOUR
AND SOCIAL DEVELOPMENT FOR THE YEAR ENDED 30TH JUNE, 2016
THE RT. HON. SPEAKER OF PARLIAMENT
I have audited the financial statements of the Ministry of Gender, Labour and Social
Development (MoGLSD) for the year ended 30th June, 2016. These financial statements
comprise of the Statement of Financial Position, the Statement of Financial Performance,
and Cash flow Statement together with other accompanying statements, notes and
accounting policies.
Management Responsibility for the Financial Statements
Under Article 164 of the Constitution of the Republic of Uganda, 1995 (as amended) and
Section 45 of the Public Finance Management Act (PFMA), 2015, the Accounting Officer
is accountable to Parliament for the funds and resources of the Ministry of Gender,
Labour and Social Development. The Accounting Officer is also responsible for the
preparation of financial statements in accordance with the requirements of the PFMA,
2015, and the Financial Reporting Guide, 2008, and for such internal control as
management determines is necessary to enable the preparation of financial statements
that are free from material misstatement whether due to fraud or error.
Auditor’s Responsibility
My responsibility as required by Article 163 of the Constitution of the Republic of
Uganda, 1995 (as amended) and Sections 13 and 19 of the National Audit Act, 2008 is
to express an opinion on the financial statements based on my audit. I conducted my
audit in accordance with the International Standards on Auditing. Those standards
require that I comply with ethical requirements and plan and perform the audit to obtain
reasonable assurance about whether the financial statements are free from material
misstatement.
An audit involves performing audit procedures to obtain audit evidence about the
amounts and disclosures in the financial statements as well as evidence supporting
compliance with relevant laws and regulations. The procedures selected depend on the
2
Auditor’s judgment, including the assessment of risks of material misstatement of the
financial statements whether due to fraud or error. In making those risk assessments,
the Auditor considers internal controls relevant to the entity’s preparation and fair
presentation of financial statements in order to design audit procedures that are
appropriate in the circumstances, but not for purpose of expressing an opinion on the
effectiveness of the entity’s internal control. An audit also includes evaluating the
appropriateness of accounting policies used and the reasonableness of accounting
estimates made by management, as well as evaluating the overall presentation of the
financial statements.
I believe that the audit evidence I have obtained is sufficient and appropriate to provide
a basis for my opinion.
Part “A” of this report sets out my Opinion on the financial statements. Part “B” which
forms an integral part of this report presents in detail all the significant audit findings
made during the audit which have been brought to the attention of management.
PART "A"
Opinion
In my opinion, the financial statements of the Ministry of Gender, Labour and Social
Development present fairly in all material respects the financial position as at 30th June,
2016 and the financial performance and cash flows for the year then ended in
accordance with Section 51(1) of the PFMA, 2015 and the Financial Reporting Guide,
2008.
Emphasis of Matter
Without qualifying my opinion, I draw your attention to the following matter that is
disclosed in the financial statements under note 24;
Inadequate budget provision for Payables
Although the payables increased from UGX.3,726,312,583 in the previous financial
year 2014/15, to UGX.4,624,339,098, (2015/16) owing to the additions during the
year under review, the Ministry’s approved budget for Payables was only
3
UGX.1,004,045,000 for 2016/17 which is not sufficient to cover all payments for the
outstanding payables.
Other Matters
In addition to the matter raised above, I consider it necessary to communicate the
following matters other than those presented or disclosed in the financial statements;
Lack of accounting Framework for Youth Livelihood Program Funds (YLP)
By June 2016, the YLP had been implemented for three years. However, the
program lacked a detailed accounting framework resulting into inconsistent
accountability for the funds by the implementing entities.
Recoverability of Youth Livelihood Program Funds
By the end of the financial year 2015/16, the disbursements to the youth groups had
accumulated to UGX.58,438,923,900 to 8,213, projects. However, audit noted that
only UGX.5,501,217,366 had been repaid out of the UGX.14.2 billion that was due for
repayment by the beneficiaries.
John F.S. Muwanga
AUDITOR GENERAL
15th December, 2016
4
PART “B”
DETAILED REPORT OF THE AUDITOR GENERAL ON THE FINANCIAL STATEMENTS
OF THE MINISTRY OF GENDER, LABOUR AND SOCIAL DEVELOPMENT FOR THE
FINANCIAL YEAR ENDED 30TH JUNE 2016
This section outlines the detailed audit findings, management responses, if any, and
recommendations in respect thereof.
1.0 INTRODUCTION
Article 163(3) of the Constitution of the Republic of Uganda, 1995 (as amended)
requires me to audit and report on the public accounts of Uganda and all public
offices including the courts, the central and local government administrations,
universities, and public institutions of the like nature and any public corporation or
other bodies or organizations established by an Act of Parliament. Accordingly, I
carried out the audit of the Ministry to enable me report to Parliament.
2.0 BACKGROUND INFORMATION
The Ministry of Gender Labour and Social Development commonly called the
Ministry of Gender is a Government Ministry with the responsibility of promotion of
employment and productivity, positive cultural values, rights of vulnerable groups
and gender responsive development. The Ministry has one of its major tasks as to
ensure that all Ugandans enjoy better standards of living, especially the
disadvantaged and vulnerable groups.
The Ministry came into being by a constitutional requirement of the 1995
Constitution, Chapters 4 and 16 which mandates government to: “empower
communities to harness their potential through skills development, Labour
productivity and cultural growth.” The constitution advocates for protection and
promotion of fundamental rights of the poor and other vulnerable groups as well as
institutions of traditional or cultural leaders.
The Ministry is comprised of the Social Development Sector (SDS) that promotes
issues of social protection, gender equality, equity, human rights, culture, decent
5
work conditions and empowerment for different groups such as women, children,
the unemployed youth, internally displaced persons, the older persons and persons
with disabilities. The Ministry is the lead agency for this sector and is charged with
the development and implementation of the Social Development Investment Plan
(SDIP) with the mandate to empower communities to harness their potential
through cultural growth, skills development and Labour productivity for sustainable
and gender responsive development.
The Ministry’s Vision is to ensure a better standard of living, equity and social
cohesion while its Mission is Promotion of gender equality, social protection and
transformation of communities.
The Ministry is located at Plot 2, Simbamanyo House, George Street, Kampala.
3.0 ENTITY FINANCING
The Ministry of Gender Labour and Social development was financed by Grants from
Central Government to the tune of UGX.62,898,710,946 and generated Non-Tax
Revenue (NTR) of 1,178,187,000.
4.0 OBJECTIVES OF THE MINISTRY
The objectives of the Ministry are to:-
Empower communities to appreciate access, participate in, manage and
demand accountability in public and community based initiatives.
Protect vulnerable persons from deprivation and livelihood risks.
Create an enabling environment for increasing employment opportunities and
productivity for improved livelihoods and social security for all, especially the
poor and vulnerable.
Ensure that issues of inequality and exclusion in access to services across all
sectors and at all levels are addressed; and
Improve performance of Social Development Institutions to coordinate and
implement the Social Development Investment Plan (SDIP) at various levels.
6
5.0 AUDIT OBJECTIVES
The audit was carried out in accordance with International Standards on Auditing
and accordingly included a review of the accounting records and agreed procedures
as was considered necessary. In conducting my reviews, special attention was paid
to establish:-
1) Whether the financial statements have been prepared in accordance with
consistently applied accounting Policies and fairly present the revenues and
expenditures for the period and of the financial position as at the end of the
period.
2) Whether all funds were utilized with due attention to economy and efficiency
and only for the purposes for which the funds were provided.
3) Whether goods and services financed have been procured in accordance with
the Government of Uganda Procurement regulations.
4) Whether management put in place sufficient internal controls and the internal
controls operated as intended throughout the year.
5) Whether the management was in compliance with the Government of Uganda
financial regulations.
6) Whether all necessary supporting documents, records and accounts have been
kept in respect of all activities, and are in agreement with the financial
statements presented.
6.0 PROCEDURES PERFORMED
The following audit procedures were undertaken:-
a. Revenue
Obtained schedules of all revenues collected and reconciled the amounts to
the cashbooks and bank statements.
b. Expenditure
The payment vouchers were examined for proper authorization, eligibility and
budgetary provision, accountability and support documentation.
7
c. Internal Control system
Reviewed the internal control system and its operations to establish whether
sound controls were applied throughout the period audited.
d. Procurement
Reviewed the procurement of goods and services by the Ministry during the
period under review and reconciled with the approved procurement plan.
e. Fixed Assets Management
Reviewed the use and management of the Ministry’s assets during the period
audited.
f. Financial Statements
Examined on a test basis, evidence supporting the amounts and disclosures
in the financial statements; assessed the accounting principles used and
significant estimates made by management; as well as evaluating the overall
financial statement presentation.
7.0 AUDIT FINDINGS
7.1. Categorization of Findings
The following system of profiling of the audit findings has been adopted to better
prioritise the implementation of audit recommendations:-
o Category Description 1 High Significance Has a significant / material impact, has a high likelihood
of reoccurrence, and in the opinion of the Auditor General, it requires urgent remedial action. It is a matter of high risk or high stakeholder interest.
2 Moderate Significance Has a moderate impact, has a likelihood of reoccurrence, and in the opinion of the Auditor General, it requires remedial action. It is a matter of medium risk or moderate stakeholder interest.
3 Low Significance Has a low impact, has a remote likelihood of reoccurrence, and in the opinion of the Auditor General, may not require much attention, though its remediation may add value to the entity. It is a matter of low risk or low stakeholder interest.
8
7.2 Summary of Findings
No Title of Finding Significance
8.1 Inadequate budget provisions for payables High
8.2 Youth Livelihood Programme High
8.3.1 Missing pension files High
8.4 Funds not accounted for Moderate
8.5 Non-payment of Workman’s compensation within the stipulated
time
Moderate
8.6 Staff Management Moderate
8.7 Un-renewed workplace registration certificates Moderate
8.8 Non-implementation of provisions under the OSH Act 9, 2006
8.9 Review of implementation of previous year’s recommendations
8.0 Detailed Audit Findings
8.1 Inadequate budget provision for Payables
The payables increased from UGX.3,726,312,583 in the previous financial year
2014/15 to UGX.4,624,339,098, in 2015/16 owing to the additions during the year
under review. However, the Ministry’s approved budget for domestic arrears
was only UGX.1,004,045,000 for 2016/17which is not sufficient to cover payments
for all domestic arrears for the previous years. Following the PS/ST’s directive vide
circular referenced BPD 86/298/02 dated 10th June, 2016 requiring all accounting
Officers to prioritise payment of domestic arrears in the 1st Quarter of 2016/17,
settlement of huge domestic arrears balances will affect implementation of
activities planned for 2016/17.
The Accounting Officer explained that MoGLSD endeavoured to forecast budgetary
expectations but was constrained by the inconsistencies in quarterly budget
releases, which were not commensurate to the competing actual demands coupled
with the ceiling that was insufficient to cover the entire mandatory and priority
expenditure in a given financial year.
9
He added that the bulk of the domestic arrears were composed of Workman’s
compensation of which the Ministry of Finance, Planning and Economic
Development (MoFPED) had approved one (1) billion per annum over the last two
(2) Financial Years - to reduce the obligation.
I advised the Accounting Officer to liaise with the MoFPED and ensure that enough
funds are budgeted for to settle the outstanding liabilities.
8.2 Youth Livelihood programme
8.2.1 Lack of accounting framework
By 30th June 2016, the Youth Livelihood Programme (YLP) had been implemented
for three years. However, there was no proper accounting framework and/or
detailed guidelines for accountability. Consequently the implementing entities under
the programme accounted for funds differently, which is not only recipe for
improper accounting for programme funds but also impedes comparability of
accounting reports across the implementing entities.
Although the Permanent Secretary/Secretary to the Treasury (PS/ST) in letter dated
5th May 2016 had requested the PS - MoGLSD to work with the Accountant General
to develop detailed guidelines, by the time of audit, no guidelines had been
developed.
The Accounting Officer in response stated that some actions had been undertaken,
including developing simplified guidelines/formats which were shared with the
Accountant General for use by the YLP beneficiary groups at the community level. In
addition, the Accountant General had constituted a Technical Working Committee
for formulation of Accounting and Reporting Guidelines for all Government of
Uganda Revolving Funds and the MoGLSD nominated members to the committee
that was expected to work under the leadership of the Accountant General.
I advised the Accounting Officer to continue the engagement with the Accountant
General so as to expedite the process of developing guidelines to streamline the
programme’s accounting processes.
10
8.2.2 Recoverability of program funds
Phase I of the YLP programme started in the financial year 2013/2014 with a total
accumulated disbursement of UGX.58,438,923,900 to 8,213 projects by end of
2015/16 financial year. A review of the overall status of the program revealed the
following;
(i) Low rate of recovery
The overall repayment as at 28th October, 2016 stood at UGX.5,501,217,366 (39%)
of the UGX 14.2 billion that was due for repayment by the beneficiaries.
(ii) Non traceable group projects
During inspection, audit also noted that some projects/business managed by some
of the youth groups could not be traced on the ground. This was because some of
the projects were either non-existent, had been disbanded or members had
formed different projects thus presenting challenges of enforcing recoverability.
Consequently UGX.527,308,994 which had been released to these specific groups
may not be recoverable.
(iii) Non compliance with recovery schedules
In addition non-compliance with recovery schedules was noted in the districts of
Kanungu, Gulu and Koboko. A comparison of disbursement date, with first date of
recovery and due date to completion recovery showed that some projects in the
three districts had not paid instalments totalling UGX.290,873,435, as per the
agreed terms.
(iv) Lack of repayment/recovery schedule
In the districts of Isingiro, Ntungamo, Kisoro and Kabarole no copies of
repayment/recovery schedules were availed. It was not clear how funds were to be
recovered from the beneficiary groups. Consequently audit could not determine
the amounts due for recovery and how much had actually been recovered in the
four districts.
The above gaps in the implementation of the program are likely to affect
achievement of the program’s intended objectives.
11
The Accounting Officer explained that there was evidence of improved recovery
from the youth groups and that on average, the Ministry was recovering over
UGX.100 million per week.
He also stated the Ministry had taken measures to sensitize the beneficiaries and
the general public on the Programme and mobilize the beneficiaries for
repayment through stakeholder engagements in various fora
I advised the Accounting Officer to;
Hasten recover of funds from the youth groups as per the agreed terms and
schedules with a view of ensuring sustainability of the revolving fund and
thus the attainment of programme objectives.
Consider partnering other government institutions such as MTAC that are
mandated to incubate businesses and train stakeholders.
Improve on monitoring and supervision and where possible invoke sanctions
on youth groups that are defaulting on repayment.
8.2.3 Lack of memoranda of understanding/financing agreements
Paragraph 4.1(iii) of the programme guidelines requires MoGLSD to sign
Memoranda of Understanding (MoUs) with implementing District Local
Governments (DLGs). In the same vein the districts are required to sign financing
agreements with youth groups that have been approved for funding.
It was however noted that in Ntungamo and Isingiro Districts, some projects which
had received funding of UGX.673,689,519, never signed financing agreements,
contrary to the MOU requirements. Consequently there was a challenge of
enforceability of responsibilities and obligations. This has a bearing on both the
youths’ commitment to their projects and the funds recoverability.
In response, the Accounting Officer explained that he had taken up the matter
with the Accounting Officers of the two Districts, given that the training of groups
and the signing of financing agreements between the local governments and the
beneficiary groups were pre-conditions for disbursement of funds by the District to
the individual youth groups’ accounts.
12
I await the outcome of management’s actions on the Accounting Officers of the
two Districts. I also advised him to extend the same to all other districts as similar
challenges may be pertaining there.
8.2.4 Non-compliance with youth interest group composition requirements
It was noted that some youth groups had less than 30% female members, which is
a requirement in paragraph 4.2 of the YLP document, 2013. This was attributed to
inadequate guidance by the technical committees and this may disadvantage the
female youths in as far as development is concerned.
The Accounting Officer explained that overall, 45% of the 107,970 beneficiaries of
YLP were female, surpassing the minimum requirement of 30%, however arising
from errors of omission, a few projects 98 (1.2%) had fallen short of having at least
30% female members.
Management undertook to pay more attention at the review stage to ensure that
gender composition requirements are adhered to at the individual projects level.
I advised the Accounting Officer to ensure that all youth groups comply with the
gender composition requirement, before funding is accessed.
8.3 Payroll and Pensions Audit
8.3.1 Missing pensioner files
A sample of 15 pensioners out of 170 with payments totalling UGX.167,092,542
were randomly selected for verification tests and it was noted that only two had
personal files with original documents while the rest had uncertified photocopies of
documents such as appointment letters, confirmation and computation forms. This
was contrary to paragraph P-d (5) of the Standing Orders, 2010 that requires a
public officer’s personal records to be complete and up to date at any given time,
opened and maintained at the Ministry of Public Service and the Ministry
Department or Local Government where the officer is working.
Audit could neither confirm the authenticity of pension payments effected on
photocopied documents nor rule out payment of non-existing pensioners.
13
Management in its response explained that the Ministry was an amalgamation of
previously different ministries, which had metamorphosed overtime, consequently
leading to transit of documents including personal files. By the time of
decentralisation of salaries and pensions, most of the pensioners were already on
the payment system, thus any lapse in payment of emoluments would lead to
anxiety. As a stop gap measure the Ministry had to utilise photocopies of the
relevant documents.
I advised the Accounting Officer to liaise with the Ministry of Public Service to access
certified copies of documents for each pensioner.
8.4 Funds not accounted for
The MoGLSD and the Uganda Scouts Association (USA) hosted the International
Scouts Centenary Jamboree from 18th-28th August 2015 at Kaazi National Campsite,
which brought together 163 member countries. The preparatory activities included
mobilization, coordination & monitoring, installation of a dedicated website,
construction of Kaazi Camping Site, welfare activities, printing medals and
certificates, security and entertainment.
It was noted that payments totalling UGX.54,672,250 for various activities lacked
the requisite accountabilities, contrary to the requirement to have all vouchers
accompanied by supporting documents.
In the absence of the requisite accountability documentation, audit could not
confirm whether the funds were utilized for the intended Jamboree activities.
The Accounting officer indicated that all the accountability was available however on
examination the stated amount remained outstanding.
I advised the Accounting Officer to ensure funds are accounted for or recovered
accordingly.
8.5 Non-payment of Workman’s compensation within the stipulated time
In the year under review, the Ministry had compensation claims totalling to
UGX.536,834,749, which was an addition to the outstanding balance of
14
UGX.3,162,461,669 reported in the financial year 2014/15, resulting in a total figure
of UGX.3,699,296,414. Of this amount, only UGX.654,019,838 was settled leaving a
balance of UGX.3,045,276,580.
Long outstanding compensation claims implies that the beneficiary persons were
denied their compensation and this, if not timely handled may result into litigations
and their attendant costs.
Management attributed the non-payment of outstanding claims to inadequate
funding, and added that MoFPED was supporting the Ministry to clear the claims by
providing UGX 1 billion effective FY 2014/15. MoFPED had also made a proposal that
new claims should be budgeted for and handled by responsible institutions where
the accidents occured, which MoGLSD was agreeable to.
I await the outcome of management’s actions undertaken in collaboration with other
government departments in ensuring the settlement of the outstanding claims.
8.6 Staff management
8.6.1 Un implemented provisions in the National Employment Policy
The ministry developed a National Employment Policy for Uganda, April 2011 to
guide all stakeholders on creation and enhancement of the quality and availability of
gainful employment opportunities. A review of the Policy however revealed;
(i) Failure to review the National employment Policy
Paragraph 10 of the National Employment Policy for Uganda, April 2011 provides
for its review after every five (5) years to take into account, the impact,
performance and emerging challenges. However, by the time of audit, the five
year period of the policy had elapsed and yet there was no evidence of the
review. In the circumstances emerging developments especially regarding
externalization of labour may not be adequately catered for. In response, the
Accounting officer explained that arrangements were being made to review the
policy through consultancy.
15
(ii) Lack of employment register and computerised employment permits
The Ministry was supposed to issue computerised employment permits in order
to keep track of persons eligible for employment in the country and to maintain
an employment register, in fulfilment of paragraph 7.2 that states that one of
the strategies on labour market information was the strengthening of the
ministry responsible for labour to play its role as the national and regional
depository for labour and employment management information.
I noted that computerised employment permits have not been issued which
makes it impractical for the ministry to account for the work force - both foreign
immigrants and citizens. This hinders proper planning for the workforce.
In response, the Accounting explained that the development of labour market
information and analysis system was on-going and once finalised it would take
care of the registers and permits.
(iii) Lack of Labour Officers at the districts
Paragraph 3.7 of the National Employment Policy, 2011 provide for the
decentralisation of key aspects of labour administration in accordance with the
decentralisation policy by recruiting labour officers at districts to carry out
inspection of workplaces, investigate contract breaches and arbitrate cases of
undesirable working conditions between the workers and employers besides
providing the relevant technical advice.
By the time of audit, only 45 out of the 112 districts had recruited labour
officers. Consequently, the rights of employees may not be protected as far as
working conditions, engagement and disengagement are concerned.
Management attributed the scenario to inadequate funding at the districts.
In response the Accounting Officer explained that the MoGLSD continued to
lliase withLocal Governments, Ministry of Public Service, MoFPED and the
Ministry of Local Government on the essential role of Labour officers at the
district level.
16
(iv) Lack of a revolving fund
In the recent past, the labour markets abroad have increasingly continued to
provide employment opportunities for Ugandans. Paragraph 7.8 of the National
Employment Policy for Uganda, April 2011, (under externalisation of labour),
provides for a strategy of establishing a revolving fund to facilitate Ugandans
seeking employment abroad.
However audit noted that the Ministry had not established the required
revolving fund. The Accounting Officer explained that the Revolving Fund as
envisaged by the National Employment Policy shall be taken care of under one
of the components of Promotion of green Jobs and fair Labour Markets .
I advised the Accounting Officer to ensure that;
The National Employment Policy is reviewed to reflect the emerging labour
conditions and challenges, so as to remain relevant to the labour force.
An employment register and computerised employment permits are put in
place to enable proper planning for the workforce.
Relevant stakeholders are engaged to ensure that labour officers are
recruited in all the districts to undertake the envisaged roles more effectively
in the districts.
The revolving fund is actualised, as had been envisaged by the National
Employment Policy.
8.7 Un-renewed workplace registration certificates
Analysis of Register for the registered workplaces revealed that 60 of themhad not
renewed their certificates, contrary to Section 41(3) of the Occupational Safety and
Health (OSH) Act 9, 2006 which requires all work places to possess certificates of
registration that are renewed every three years. This not only contravenes the legal
requirement but also deprives the Ministry of Non-tax revenue.
Management attributed this to inadequate personnel (numbers and skills) and
logistics which hampers enforcement. While International Labour Organisation (ILO)
standard requires inspector to worker ratio of 1:500, Uganda stood at 1:389,286 In
17
addition OSH services were never decentralised, but the Ministry had 26 staff to
cover all registration and inspection of over 500,000 workplaces in the country.
I advised the Accounting Officer to enforce compliance with the above provision and
put in place an appropriate mechanism to ensure that the renewals are effected.
The Ministry should consider automation of the process to address the limitation of
manpower.
8.8 Non-implementation of provisions under the Occupational Safety and
Health (OSH) Act 9, 2006
8.8.1 Lack of a Policy and board for Occupational Safety and Health
Review of the strategic plan 2011/12-2015/16 revealed that despite having the OSH
Act, the Ministry lacked a National Policy for Occupational Safety and Health. This
implies that there are no clear procedures and systems to follow in taking decisions
to achieve the intended objectives of Occupational Safety and Health law.
Additionally, whereas Section 10 of the OSH Act 9, 2006 requires establishment of a
board appointed by the Minister, I noted that the Minister had never constituted the
board. Absence of the board potentially leads to supervision challenges and lack of
strategic direction regarding occupational safety and health activities and the
implementation of the Act itself.
In response, the Accounting Officer explained that the development of the policy on
OSH was on-going and is expected to be approved by 31st December 2016.
Subsequently, the board shall be established.
I advised the Accounting Officer to hasten the process of having the policy approved
so as to guide the operationalization of the Act.
8.9 Review of implementation of Previous Year’s Recommendations
A review of the implementation of the previous year’s audit recommendations
revealed status of implementation, as shown in the following table;
18
No Observation Status of
Implementation
Management Response
1 Payables Partially
Addressed
Arrears are being settled as when
funding is received. Most of the
payables are due to Workman’s
compensation
2 Under-staffing Partially
addressed
Some positions have been filled
3 Accumulation of
labour disputes at the
Industrial Court
Not Addressed Ministry engaging Ministry of Public
Service and the Public Service
Commission to handle staffing gaps at
the Industrial Court
4 Status of reception
Centre, and remand
Homes
Partially
Addressed
Funding received and more expected
from MoFPED to improve all
institutions under the ministry
5 Payroll management
weaknesses
Partially
Addressed
Funds overpaid have been recovered
by underpaying pensions for the
concerned staff
6
Inadequate
monitoring of Youth
Interest Groups
(YIGs) projects under
the YLP.
Partially
Addressed
Monitoring has improved.
7 Non-recovery of
revolving funds
Partially
Addressed
More funds recovered.
8 Potential Loss of
funds
Not Addressed Funds not recovered.
I advised management to implement all the pending recommendations pointed out
in the previous audit report to enhance sound stewardship.